+ All Categories
Home > Documents > Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

Date post: 05-Apr-2018
Category:
Upload: romeotango
View: 216 times
Download: 0 times
Share this document with a friend

of 117

Transcript
  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    1/117

    Urban Mobility India Conference & Exhibition 2011(3rd to 6th December 2011)

    Presenter - Anil Gupta

    (President & Head Infrastructure)

    Challenges faced by private parties in planningdesign and operation of rail / guided transit"

    5th December 2011

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    2/117

    Slide 2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    3/117

    Slide 3

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    4/117

    Slide 4

    Roads & Sea Link

    Metros

    Cement

    Airports

    Power Sector

    Distribution

    Transmission

    Trading

    Generation

    R InfraPresence

    Infrastructure Sector

    RInfra Overview

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    5/117

    Slide 5

    PAN India Presence

    Maharashtra

    Maharashtra: 15 projects1 Road, 2 Metros, 1 Sea Link,

    5 Airports, 1 Real Estate,

    1 Cement plant , 1 Generation,

    2 Transmission & 1 Distribution

    Goa : 1 project

    Goa Power Generation Plant

    Gujarat : 2 projects1 Road Project &

    1 Transmission Project

    Rajasthan : 1 project1 Road Project

    Tamil Nadu: 6 projects6 Road Projects

    Delhi: 3 projects1 Road Projects, 1 Metro & 1 Distribution

    Andhra Pradesh & Orisaa: 3 projects1 Ultra Mega Transmission Project ,

    1 Hyderabad Real Estate &

    1 Samalkot Power Generation Plant

    Madhya Pradesh, Uttar Pradesh &

    Chattisgarh & Haryana,: 3 projects1 Ultra Mega Transmission Project

    1 Road Project , 1 Cement Plant

    Kerala : 1 project

    BSES Kerala Power Generation Plant

    Karnataka : 1 project

    Wind Farm Generation Plant

    Punjab & Himachal Pradesh

    : 1 project1 Transmission Project

    37 Projects I 17 States I 8 Sectors

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    6/117

    Slide 6

    Infrastructure

    Businesses

    Roads 11 ` 120 Bn

    Metros 3 ` 160 Bn

    Sealink 1`

    46 Bn

    Airports 5 ` 5 Bn

    Total 22 380 Bn

    Cement 2 ` 47 Bn

    BusinessNo. of

    projects

    Project Cost

    Bn

    Infrastructure Portfolio

    Largest private sector infrastructure developer on ownership basis

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    7/117

    Slide

    Details Delhi Metro Mumbai Line-1 Mumbai Line-2

    Project Cost(Rs. Bn)

    28.8 23.6 110.0

    Debt: Grant:Equity

    70:0:30 51:27:22 64:21:15

    Length (km) 23 11 32

    CoD Feb 2011 Q4FY12 Within 5 years

    ConcessionPeriod*

    30 years 35 years 35 years^

    Shareholding

    Ridershipin lacs

    (on 1st yr Operation)

    0.36 (Yr 2012) 7.0 (Yr 2012) 14.0 (Yr 2016)

    7

    Metro Rail Portfolio

    * Including construction period ^ Could be extended for further 10 years

    3 Projects I 66 kms I Project Cost - ~ 160 Bn

    Expectedridership

    over 21Lacs

    [66 km]

    Expectedridership

    over 21Lacs

    [66 km]

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    8/117

    Slide 8

    Project Delhi Airport Express

    Project Cost Rs. 2,878 Crs

    Length 23 km, largely underground.

    Stations 6 nos, 5 underground and 1

    elevated.

    Concession Period 30 years(incl. Construction

    period)

    Travel time from New Delhi to Airport reduced

    to 18 mins.

    Project Cost Rs. 2,878 Crs

    Length 23 km, largely underground.

    Stations 6 nos, 5 underground and 1

    elevated.

    Concession Period 30 years(incl. Construction

    period)

    Travel time from New Delhi to Airport reduced

    to 18 mins.

    1st PPP Metro Project to be operational in India.

    High Speed Metro , tops speed of 120kmph.

    Connecting Airport, Dwarka Subcity, Dhaula Kuan,

    Aero City to New Delhi/CP.

    Provides check in facility within city at New Delhi &

    Shivaji Stadium station, Dhaula Kuan (Passenger

    only)

    Have brought Delhi to league of selected cities

    having such a facility.

    1st PPP Metro Project to be operational in India.

    High Speed Metro , tops speed of 120kmph.

    Connecting Airport, Dwarka Subcity, Dhaula Kuan,

    Aero City to New Delhi/CP.

    Provides check in facility within city at New Delhi &

    Shivaji Stadium station, Dhaula Kuan (Passenger

    only)

    Have brought Delhi to league of selected cities

    having such a facility.

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    9/117

    Slide

    Metro Line - 1

    9

    Project Mumbai Metro One

    Project Cost Rs. 2,356 Crs

    Length 11.4 km (Elevated)

    Stations 12 nos.

    Grant (VGF) Rs. 650 Cr.

    Concession Period 35 years(incl. Construction period)

    Expected Traffic 7 Lakhs per day in the opening year

    East West to East travel time to reduce from 90mins to 20 mins

    Project Cost Rs. 2,356 Crs

    Length 11.4 km (Elevated)

    Stations 12 nos.

    Grant (VGF) Rs. 650 Cr.

    Concession Period 35 years(incl. Construction period)

    Expected Traffic 7 Lakhs per day in the opening year

    East West to East travel time to reduce from 90mins to 20 mins

    Versova Andheri Ghatkopar Project

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    10/117

    Slide

    Metro Line - 2(Charkop-Bandra-Mankhurd Metro Project ) Project Cost Rs. 11,551 Crs

    Length 33 km

    Stations 28 nos.

    GoI/GoM to provide Rs 2,298 Crs as Viability Gap Funding

    (VGF)

    Concession Period 35+10 yrs (incl.5 yrs Construction)

    Expected Traffic 14 Lakhs per day in the opening year

    To provide North - South Connectivity

    Direct connectivity to all the Suburban Rail Lines -

    Western, Central & Harbour

    Reduces Travel time by 90 minutes

    10

    Project Metro Line - 2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    11/117

    Slide 11

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    12/117

    Slide 12

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Implementation/Operation Framework

    Due Diligence Logistics

    Type of structure

    Intermodal Integration

    Due Diligence

    Logistics

    Type of structure

    Intermodal Integration

    Depot Route finalization

    Phase Commissioning

    Depot

    Route finalization

    Phase Commissioning

    Clearances pre -

    construction

    Right of Way

    Safety issues

    Public interface

    Utilities

    Clearances pre -

    construction

    Right of Way

    Safety issues

    Public interface

    Utilities

    RAMs requirements Operation hours

    Training

    Depot issues

    Intermodal integration

    Safety

    RAMs requirements

    Operation hours

    Training

    Depot issues

    Intermodal integration

    Safety

    11 22 33 44

    Challenges Challenges Challenges Challenges

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    13/117

    Slide 13

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Implementation/Operation Framework

    Due Diligence Logistics

    Type of structure

    Intermodal Integration

    Due Diligence

    Logistics

    Type of structure

    Intermodal Integration

    11

    Challenges

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    14/117

    Slide

    Due diligence by Concessioning Authority before awarding/ inviting ofbids. Few examples:

    Delhi Airport Express

    1) Original plan was with at-grade siding at Palam, this would have facilitated thematerial movement and access during construction

    2) Long inter-station distances(7 km) without evacuation passage duringemergency.

    Mumbai Metro-1

    1) Depot Ownership was not with Concessioning authority

    2) Final available depot land different from original DPR (shape & size)

    Mumbai Metro-2

    1) Both the depot lands falling in CRZ.areas

    2) Part of the elevated viaduct infringing the Aircraft landing funnel

    3) Railway approvals for crossing Railway tracks/ lands.

    4) Lack of clarity on the Commercial Space utilisation.

    5) Location of the DN Nagar station (MCGM Land) and Bandra Station (Relief

    and Rehabilitation issues).

    14

    Due Diligence

    Implementation / Operation Framework

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    15/117

    Slide 15

    Layout of Dwarka Depot(as planned earlier )

    Delhi Airport Metro Express

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Depot land location changed by DMRC

    Due to change in land in-fructuous works had to be done e.g.:

    Geo-technical investigations

    Depot Layout planning

    Constraint leading to 3 trains in the line

    Original Location

    Changed

    Location

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    16/117

    Slide

    Layout of Charkop car shed showingCRZ areas

    16

    Mumbai Metro Line 2

    Total depot area 18.7 hectare

    Challenges

    82% (16.2 ha) falls under CRZ

    No heavy maintenance allowed

    Proposed construction on stilt

    Leads to cost & time over run

    Un-hygenic work environment

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    17/117

    Slide 17

    Layout of Mankhurd Depot showing CRZ areas

    Mumbai Metro Line 2

    Total depot area 24 hectare

    Challenges

    91% (21.8 ha) falls under CRZ

    Zero maintenance allowed on CRZ-1

    Depot on stilt as no alternate land

    Leads to time & cost over run

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    18/117

    Slide18

    Infringement of aircraftfunnel near Juhu Station

    Mumbai Metro Line 2

    18

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    19/117

    Slide 19

    Mumbai Metro Line 2

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Viaduct

    Infringement of aircraft funnelnear Juhu Station

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    20/117

    Slide

    Railway Clearances

    Mumbai Metro Line1

    Railway Clearances Andheri Steel Bridge

    Long approval process & has implication on design and planning

    Mumbai Metro Line 2

    Railway Clearances Uncertainties at Kurla crossing

    Ambiguity about the height of Metro track at Kurla.

    It can be at 7 mtrs or 22 mtrs above ground level.

    Implications:

    On vertical profile upto 2 kms on either side

    Additional cost impact

    In-principle approval is still awaited on this matter.

    Mumbai Metro

    20

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    21/117

    Slide

    FOOT OVER BRIDGE

    EXISTING RAILWAY TRACKS (CST-THANE LINE)

    STEEL GIRDER BRIDGE FOR METRO CBM CORRIDOR (LINE-2)AT KURLA STATION YARD

    MANKHURDBANDRA

    7.0 M

    Mumbai Metro Line 2 Original Plan

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    21

    Metro Bridge Originally Planned

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    22/117

    Slide

    ExecutionExecution

    PROPOSED ELEVATED

    CORRIDOR (RAILWAY)

    FOOT OVER BRIDGE

    EXISTING RAILWAY TRACKS (CST-THANE LINE)

    STEEL GIRDER BRIDGE FOR METRO AT KURLA STATIONMANKHURDBANDRA

    7.0 M

    3.0 M

    22 M

    Mumbai Metro Line 2 Revised Plan

    PlanningPlanning DesignDesign OperationOperation

    Metro Bridge proposed to be atheight of a 5 storey building

    22

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    23/117

    Slide

    Problem of Commercial Development

    CA allowed for commercial development above the platform level.

    Present rules do not permit.

    Development Control Rules (DCR) are under modification since last two years.

    Creating Commercial Space above the stations is difficult, since Fire Laws require

    separate escape stairs for persons above the platform. This causes huge

    constraints on the footpath space.

    Mumbai Metro Line 2

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    23

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    24/117

    Slide

    Station with Concourse and Platform

    Mumbai Metro Line 2

    24

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    .next

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    25/117

    Slide

    CommercialFloor

    30m

    4.0m

    Carriagewayup

    Carriagewaydown

    4.5m

    25m

    25m

    4.0m

    4.0m

    Implication of Commercial space

    above Platform level

    Additional floor above PF requires

    extra staircases on the Pathway.

    Mumbai Metro Line 2

    25

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    More setback on already constrained

    road

    Challenges

    Infringement with existing structures

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    26/117

    Slide26

    Locations where localIssues may affect alignment

    Locations where localIssues may affect alignment

    26

    Infringement with Aircraft funnel path

    Challenges

    Infringement with EHV lines at 13 nos.locations

    Infringement with monorail crossing and roadflyover

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Mumbai Metro Line 2

    R&R issues at Kurla & BandraDepot on CRZ areas

    Railways approval

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    27/117

    Slide

    Logistics plays major role in Construction methodology, costing &timelines.

    Need for Govt. to identify & make available casting yards ahead of bidding.

    This ensures level playing field during bidding but also smoothen theexecution greatly.

    Metro -1 :

    CA , had provision for 2 nos. casting yards against 1 no. made available.

    This had implications on Cost & timelines of project (also, logistics & planning)

    We faced logistic issues with U-girders due to RoW availability

    Metro -2 : Based on learning from Line-1, moving to segmental approachmethodology.

    However, Segmental methodology, requires Continuous stretch of RoW

    Location & nos. of casting yards would decide the contracting strategy

    27

    Logistics

    Implementation / Operation Framework

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    28/117

    Slide

    Sub Str 1 +Super Str 1,2,3Package

    Sub Str 3Package

    Contract ing St rategy : ( Based on 3 Cast ing Yards)

    V 3Package

    Pack age Sect ion

    (F rom-T o )

    Leng t h

    ( k m )

    Sub Str - 1 Charkop to D N Nagar 9.30

    Sub Str - 2 D N Nagar to Juhu 3.25

    Sub Str - 3 Juhu to Bandra 6.37

    V2 Package Bandra to Kurla 6.75

    V3 Package Kurla to Mankhurd 7.44

    1

    2

    3

    Sub Str 2Package

    V2 Package

    28

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    V1Package

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    29/117

    Slide

    SS1Package

    SS3Package

    Contract ing St rategy : ( Based on 2 Cast ing Yards)

    Pack age Sect ion(F rom-To )

    Sub Structure 1 (SS1) Charkop to D N Nagar

    Sub Structure 2(SS2) D N Nagarto Juhu

    Sub Structure 3(SS3) Juhu to BandraSuper Structure I Charkop to Bandra

    Sub Structure 4(SS4) Bandra to Kurla

    Sub Structure 5(SS5) Kurla to Mankhurd

    Super Structure II Bandra to MankhurdSS2 Package

    Super

    StructurePackage

    SS4 & Super Structure IIPackage

    SS5 & SuperStructure III Package 29

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    30/117

    Slide 30

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Implementation / Operation Framework

    Metro-1 : RoW Availability

    Non availability of fronts as perplanning hampers the timelines and

    thus the Cost of project

    100% RoW still not available

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    31/117

    Slide 31

    Sr . Part icular RoW Required RoWAvailablePercentage(%)

    1 Viaduct 33.71 km 17.3 km 51 %

    2 Stat ions 28 stat ions 15 Stat ions 54 %

    3 Depot2 depots(43 hectare) Nil 0 %

    4Railway BridgesCrossings- Inprinciple approvals

    4 crossings 1 crossing 25 %

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Implementation / Operation Framework

    Metro-2 : RoW Availability (100% by Apr11)

    Segmental approachrequires more continuous RoWto prevent idling of girder launching truss

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    32/117

    Slide

    Type of Structure

    The success of the project is determined by the prompt & efficient

    execution of civil engineering structure.

    Urban environment call for greater adoption of pre-cast

    structures.

    The logistics of the movement of precast material with restrictions

    space can also determine the type of construction.

    e.g Delhi with generally wide roads, while U girders could be considered as a

    feasible option, for line 2 in Mumbai we have chosen the option of precast

    segmental construction.

    32

    Implementation / Operation Framework

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    I l i O i F k

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    33/117

    Slide 33

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    U- Girder handling

    Implementation / Operation Framework

    Narrow Right of Way constraints

    Challenges

    Hampering planned execution

    Girder movement, during nighthours (4-5 hrs block)

    Min. width of 7 mtr on straight road& larger on turns

    Length 30 mtr (max.)

    Width 5.7 mtr

    I l t ti / O ti F k

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    34/117

    Slide

    Scheme being adopted for line 2 (segmental construction)

    34

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Implementation / Operation Framework

    Segment :

    Width 3 mtr

    Length 10 mtr

    I l t ti / O ti F k

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    35/117

    Slide 35

    Implementation / Operation Framework

    Typical section showing clearances required for a Viaduct

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    36/117

    Intermodal Integration Delhi Airport Exp

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    37/117

    Slide 37

    Missing

    linkbe

    tween

    Airport

    line&DMRC

    No IntermodalIntegration planned

    Intermodal Integration Delhi Airport Exp

    Limited & constrained Car Parks near station

    Intermodal Integration with other modes missing

    (DMRC, DTC buses etc)

    Connectivity between Rajiv Chowk and Shivaji Stadium stn

    Intermodal Integration Delhi Airport Exp

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    38/117

    Slide 38

    PROP

    OSED

    FOB

    No Connectivity with NewDelhi Railway Station

    Intermodal Integration Delhi Airport Exp

    DAMEPL Proposed a Foot over Bridge for

    passenger convenience, pending with Railway

    Subway

    Entry

    New DelhiStation

    Connectivity between Railway stn and New Delhi Station (Airport Exp)

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    39/117

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    40/117

    Slide 40

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Standards in regard to securitydeployment and scale of equipment

    StationsIn-TrainOther sensitive installations like depot &Receiving Stations

    Standards in regard to luggage transfer and customs facilities etc.

    Integration with othertransportation modes and civic

    facilities

    Other upcoming Metro linesRoads

    AirportsCity CentersMono RailsPod Taxis,Bus stand,Railway Stations,Taxistands

    Drainage

    SewerageHinterland signage

    Implementation / Operation Framework

    Coordinating agency for facilitationand enforcement

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    41/117

    Slide 41

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Statutory approvals(Fire, Height, PTCC, Frequency, Safety, Sub-systems etc) Lack of Clear procedures, documentation & Time

    frame for stage approval

    (Concept, Design, Final)

    Lack of Clear National DesignStandards

    Multiple standards

    Execution Traffic Diversion

    Civic facility DiversionConstruction safety standardsLong tunnels Temporary ventilation

    Access

    Emergency medical facility

    Emergency communication

    Implementation / Operation Framework

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    42/117

    Slide 42

    Implementation / Operation Framework

    DesignDesign ExecutionExecutionPlanningPlanning OperationOperationDesignDesign

    Depot

    Route finalization

    Phase Commissioning

    Depot

    Route finalization

    Phase Commissioning

    22

    Challenges

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    43/117

    Slide

    Depot

    43

    Implementation / Operation Framework

    Depot where the rakes are maintained and stabled is the heart of any Metro

    System.

    It requires a large area for carrying out the multifarious activities.

    Unfortunately in Urban areas the land is at a premium, and the urge of the Govt.

    is to limit the size to the minimum.

    Both (Line 1 & 2) depots planning has been beset with difficulties & constraints.

    Mumbai Line 1 Govt. carved out a chunk of land right in the middle of the depot land and

    gave to a builder. This has resulted in a very constricted depot with very

    sharp curves and constrained movement of rakes, men and materials.

    Mumbai Line 2 Both the depots are embroiled in CRZ issues.

    The conditions of no maintenance in CRZ zone can virtually sound the

    death knell of the project unless a solution is found.

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    44/117

    Mumbai Metro One

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    45/117

    Slide 45

    Design layout - D N Nagar Depot

    Land given toprivatedeveloper

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    46/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    47/117

    Mumbai Metro Line 2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    48/117

    Slide

    Layout of Charkop car shed showing

    CRZ areas

    48

    Total depot area 18.7 hectare

    Challenges

    82% (16.2 ha) falls under CRZ

    No heavy maintenance allowed

    Proposed construction on stilt

    Leads to cost & time over run

    Un-hygenic work environment

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Mumbai Metro Line-2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    49/117

    Slide 49

    Mankhurd Depot

    Challenges

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Embroiled in CRZ issues

    Total depot area 24 hectare

    91% (21.8 ha) falls under CRZ

    Mumbai Metro Line 2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    50/117

    Slide 50

    Layout of Mankhurd Depot showing CRZ areas

    Total depot area 24 hectare

    Challenges

    91% (21.8 ha) falls under CRZ

    Zero maintenance allowed on CRZ-1

    Depot on stilt as no alternate land

    Leads to time & cost over run

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    51/117

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    52/117

    Slide

    While ideally the stations should be located at about every one Km.

    or so on a typical metro system, but various constraints prevail:

    Feasibility from consideration of track alignment as curves and

    grades are to be avoided.

    Space constraints as a station for an elevated alignment leaves

    a complex footprint on the ground due to its piers, lift wells,

    staircases and escalators.

    52

    Route Finalisation - Station Locations

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    53/117

    Mumbai Metro-2 : Phased Commissioning

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    54/117

    Slide

    Phase 1

    Phase 2

    1

    2

    3

    Phase 3

    54

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    55/117

    Slide 55

    PlanningPlanning DesignDesign ExecutionExecution OperationOperationExecutionExecution

    Clearances pre -

    construction

    Right of Way

    Safety issues

    Public interface

    Utilities

    Clearances pre -

    construction

    Right of Way

    Safety issues

    Public interface

    Utilities

    33

    Challenges

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    56/117

    Slide 56

    A major issue that the private concessionaire has to contend

    with is the approvals from a multifarious number of agencies/

    bodies.

    Approvals before project commencement Approvals for Project Commissioning

    Clearances pre-construction

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    57/117

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    58/117

    Slide

    Broadly there are 2 types of approval required :

    Approvals for Project Commissioning

    CMRS (Commissioner for Metro Rail Safety)

    Approval required for running the Metro Rail.

    Buildings Permissions / Local Municipal

    Authority For discharge of sewerage, stormwater and supply of drinking & fire fighting water to

    the stations.

    EIG (Electrical Inspector General)- Approvals are

    required for all electrical systems installed for the

    running of the Metro Rail.

    Safety, Health & Environment Approvals

    required for proper functioning of the infrastructure

    at the stations for general public at large

    IE (Independent Engineer) Approvals required

    that all the construction and infrastructure is as per

    best industries practices

    MoR / RDSO Approvals required from Ministry

    of Raliways and RDSO for proper functioning of the

    infrastructure at the stations for general public at

    large

    Fire Final fire NOC is required for the operations

    of the stations and via ducts from the Local FireAuthority.

    Lift Inspector Approval required for

    commissioning of the lifts and escalators to the

    stations

    Clearances pre-construction1/2

    58

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    59/117

    Slide

    The Right of way can have a serious impact on the

    planning of the type of structure and of the scheduling.

    E.g . in the vicinity of Navrang Cinema on Mumbai Line 1 with

    access to site only from one direction, we have been forced to

    do sequential working one at a time at each pier and

    superstructure as advance construction of substructure would

    have left no space for the movement of cranes for the erection

    of girders.

    59

    Right of Way (RoW)

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    60/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    61/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    62/117

    P bli I f

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    63/117

    Slide 63

    Public Interface PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    To limit inconvenience to citizens

    Challenges

    To maintain flow of traffic, limit jams

    Safety of local people and workers

    Interference by NGOs/political parties

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    64/117

    Slide 64

    Lack of defined process and ownership of utility shifting

    It is suggested that, Concessionaire is given an advance payment

    to expedite the work through agencies.

    In Line-2 , there are 11 locations where EHV lines are infringing

    with our proposed alignment.

    Relocating the towers, involves land acquisition and is a protracted

    process

    In Mumbai, shifting of Utilities can be undertaken only in fair season

    (non monsoon), which puts pressure on the project timelines.

    Utilities

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Need for :1)Dedicated corridor for shifting underground cables2)Need of GIS mapping of underground utility network.

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    65/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    66/117

    Mumbai Metro One Complex Utilities

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    67/117

    Slide 67

    A typical section showing undergroundutilities:1.Live Sewer Lines2.Electricity Cables

    Tata Power : 2 nos.

    Reliance Energy: 6 nos.

    3.Water Pipe lines4.Storm water drain5.Gas Pile line

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

    Airport Express Metro- Tunnel Work

    Pl i

    D i

    E ti

    O ti

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    68/117

    Slide 68

    Concreting in long tunnels for track works

    Challenges

    Concrete Choking in pipe , leading to waste

    Spent hours in clearing to restart the work

    Distressing and Final Parameter Checking in Progress

    PlanningPlanning DesignDesign ExecutionExecution OperationOperation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    69/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    70/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    71/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    72/117

    B id L h 183

    Mumbai Metro One - Andheri Steel Bridge

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    73/117

    Slide 73

    Bridge Length : 183 mtrs

    No. of spans : 3 nos. Span length : 61 mtr. Height(rail level): 8 mts Weight (steel) : 1275 metric tonne

    Artists impression

    Mumbai Metro One -WEH Bridge

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    74/117

    Slide

    Positioned at a height of 22 metersfrom ground

    Positioned at a height of 22 metersfrom ground

    Crossing over busiest westernexpress highway

    Crossing over busiest westernexpress highway

    Highly skilled and precision jobHighly skilled and precision job

    Contemporary Constructionmethodology

    Contemporary Constructionmethodology

    Cable Stay Bridge TechnologyChallenge

    Cable Stay Bridge TechnologyChallenge

    74

    Existing Express way

    Main road underExpress way

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    75/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    76/117

    Restrictive RoW

    Mumbai Metro One

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    77/117

    Slide 77

    Andheri Stn Area

    RoW of 18 mtr against plan of 27 mtrs.

    Challenges

    Heavy vehicular & pedestrian traffic owing toproximity to andheri station

    RoW of 18 mtr leading to separate utility building

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    78/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    79/117

    Constrained & Narrow RoW

    Mumbai Metro One

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    80/117

    Slide 80

    Ghatkopar Station

    Station overcongested area

    ..1/2

    RoW of 18 mtr leading to separate utility building

    Challenges

    Heavy vehicular & pedestrian traffic owing toproximity to Ghatkopar station

    Close proximity to adjoining structures

    Utility Building

    Constrained & Narrow RoW

    Mumbai Metro One

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    81/117

    Slide81

    Densely crowded& narrow lane

    81

    Ghatkopar Station ..2/2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    82/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    83/117

    Cons t r a ined RoW ow ing t o

    Mumbai Metro One

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    84/117

    Slide 84

    Densely crowded routedense ly c row ded st ree t

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    85/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    86/117

    Mumbai Metro 2

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    87/117

    Slide 87

    High Voltage & various other lines infringing the proposedalignment

    HT

    Tower

    Mumbai Metro 2

    High Voltage lines infringing

    ith d li t

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    88/117

    Slide 88

    with proposed alignment7 locations showing EHV lines

    infringing with proposedalignment between Bandra to

    Mankhurd

    7 locations showing EHV linesinfringing with proposed

    alignment between Bandra toMankhurd

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    89/117

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    90/117

    Slide 90

    PlanningPlanning

    DesignDesign

    ExecutionExecution

    OperationOperationOperationOperation

    RAMs Requirements

    Operation hours

    Training

    Depot issues

    Security

    Inter-modal integration

    RAMs Requirements

    Operation hours

    Training

    Depot issues

    Security

    Inter-modal integration

    44

    Challenges

    OperationOperation

    RAMs requirements

    Operation hours

    Training

    Depot issues

    Intermodal integration

    Safety

    RAMs requirements

    Operation hours

    Training

    Depot issues

    Intermodal integration

    Safety

    44

    Challenges

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

    Delhi Airport Metro Express Operational Challenges

    RAMS Requirement

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    91/117

    Slide 91

    RAMS Requirement

    Stringent compliance norms for a Private Operator.

    Provision for penalties in case of default , threat of

    termination of Concession agreement for a Private Operator.

    Delhi Airport Metro Express

    System Availability 99.94%

    Other Metros

    Less stringent norms

    No such punitive provisions for Government Metro Operators

    ..additional system capacity and redundancy

    Planning

    Planning Design

    Design Execution

    Execution Operation

    OperationOperating Hours

    Delhi Airport Metro Express

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    92/117

    Slide

    Concession Agreement Requirementsfor Operating Hours

    Passenger Service Operating Hours:

    CA requires 20 hours passenger services daily

    Currently at 18 hours from 0530 hrs to 2330 hrs.CA : Concession Agreement

    92

    Very Short maintenance period(white hours

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    93/117

    Slide 93

    Training Train Operator Certification

    Train OperatorCertifications

    DMRC Delhi Airport

    Interview Selection Interview One or more Selection Interview

    Psychometric Test Written Psychometric test CADAT for low-speed

    Computer Aided Drivers' AptitutudeTest (CADAT) for trains above 105

    kmph by RDSO

    Passing marks 60% 75%

    Train Simulator 80 hrs 6 weeks

    Train Handling OnTest Track

    40 Kms 1 week (Minimum 90 Kms.)

    Train Handling(revenue service)

    4 weeks 4 weeks (Minimum 400 Kms.)

    Mumbai Metro Line-1 No clarity on Train Operators

    Certification as of nowMumbai Metro Line-2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    94/117

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

    Training

    Delhi Airport Metro Express

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    95/117

    Slide 95

    No existing Running system in India

    Majority of staff new

    Very little time for acclimatization

    Direct training to staff (No time to train the Trainers)

    Section unavailable for training due to intensive testing

    No Operator willing to take the risk

    Continuously changing scenario

    Large number of skill sets to be trained

    Training

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    96/117

    Airport Express Metro- Depot Work

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

    Ch ll

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    97/117

    Slide 97

    Single Line, Single Entry

    Challenges

    Steep ramp at entry & exit

    No space to achieve isolation

    Unsuitable shape of plot(Dwarka Depot )

    Delhi Airport Metro Express

    In sufficient

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    98/117

    Slide 98

    Depot layout revised according to new land plan and submitted to DMRC

    DMRC instructed to revise depot layout in order to integrate the function area with property area

    Layout revised to avoid shunting neck, falling into ramp area. Shunting neck could have been adjusted withoutchanging the layout if DMRC had agreed to provide small additional land near to the ramp.

    Due to delay in finalization of layout, Depot works were put on hold for 2 months

    DMRC Line 3 Viaduct

    In sufficientwidth

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

    Intermodal Integration

    Delhi Airport Metro Express

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    99/117

    Slide 99

    Intermodal Integration

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    100/117

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    101/117

    Slide 101

    Risk Sharing

    Revenue

    Accidents

    Projected Traffic V/s Actual

    External causes

    Sub-optimal use of resources due to

    short route lengths

    Major Accidents & Breakdowns

    Major Repairs and Overhauls

    Sensitive to major disruptions Migration of key officials

    Interoperability in case of contiguous sections/extensions

    Lack of uniform minimum Operation, Safety & Reliability standards

    Resources alignment with Railways, DMRC forDisaster Management

    Planning

    Planning Design

    Design Execution

    Execution Operation

    Operation

    Ticketing (with DMRC);

    Implementation / Operation Framework

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    102/117

    Slide 102

    ConnectivityTicketing (with DMRC);Last mile (bus, rickshaw etc);Car parking

    Bedding in periodRemoval of repeat failures;

    Closure of punch lists/open item lists;Transfer of knowledge, spares etc from suppliersQuality management from projects into operations.

    Security Same as the Airports (more than the metro)

    Awareness Marketing / advertisements etc local, national & international

    Effective & EfficientOrganization

    Support requirements including training: org should matchridership wherever possible, multi-skilling etc

    Safety Primary Goal Transition from project safety to operational safety, closeworking with National Disaster Authority

    Performance Tracking Aligned to CA, back to back with suppliers; emulateinternational best practices

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    103/117

    Slide 103

    Enabling Frameworks

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    104/117

    Slide 104

    Policy &

    Regulatory

    Policy &Regulatory

    FinancialFinancialCommercial

    Viability

    CommercialViability

    OthersOthers

    Tramway Vs Metro act

    Training standards

    Certification body Tariff

    Taxation

    Levy of penalties

    Testing & accreditation

    Tramway Vs Metro act

    Training standards

    Certification body Tariff

    Taxation

    Levy of penalties

    Testing & accreditation

    Timely project

    completion

    VGF support Project Funding

    Revenue realization

    Timely project

    completion

    VGF support Project Funding

    Revenue realization

    Traffic (Forecast/ actual)

    Tariffs

    Non Fare box revenue Cost & Time over run

    Traffic (Forecast/ actual)

    Tariffs

    Non Fare box revenue Cost & Time over run

    Environment

    Timely Clearance

    Security (private/CISF) Public perception

    Stakeholders

    Environment

    Timely Clearance

    Security (private/CISF) Public perception

    Stakeholders

    11 22 33 44

    Policy & Regulatory

    Policy & Regulatory Financial

    FinancialCommercial

    Viability

    CommercialViability

    Others

    Others

    Enabling Frameworks

    L k f l it i P li F k Metro Act V/s Tramway Act

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    105/117

    Slide 105

    Lack of clarity in Policy Frame-work Metro Act V/s Tramway ActApplicability for PPP Projects (Authority splitbetween Concessioning Authority andConcessionaire)

    Concessionaire to be made party to any

    amendments to Acts / Rules

    Powers and Liabilities as per Metro Act Concessioning AuthorityConcessionaireThird Party / Contractor

    Security Policy Framework missing e.gDelhi Airport Metro Express , the cost of CISF was not planned as CAhad provision for private Security by the concessionaire.

    Policy for Metro Railway Security

    Clarity on Cost

    Training Standards Model guidelines DurationContentTests

    Competency Certification standards Model guidelines for competencycertification.(Key Officials, TO, Shunting drivers, Controllers, points man etc)

    Minimum Qualification

    MedicalPsychologicalRefresher / Retraining

    Policy & Regulatory

    Policy & Regulatory Financial

    FinancialCommercial

    Viability

    CommercialViability

    Others

    Others

    Enabling Frameworks

    Staff classification & Working Hour Classification of staff

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    106/117

    Slide 106

    Staff classification & Working Hourregulation Model Guidelines

    Classification of staffHours of working and rest period

    Alcohol and drug testing standard Breath test levels

    Tariff uniformity Provision for Inflation linked tariff increasePower to commercial establishments in station

    Taxation Project and construction equipmentElectricity dutyLocal taxesProperty taxesOctroi issues, local duties

    Construction in vicinity of ROW

    Model guidelinese.g Petrol storage tank

    Administrator for alignment against unsafe construction(Especially over the Tunnels): Concessionaire orConcessioning Authority

    Rules/Guidelines for Metro railway endorsement forconstruction in vicinity

    Should be informed

    upfront about taxexemptions

    Policy & Regulatory

    Policy & Regulatory Financial

    FinancialCommercial

    Viability

    CommercialViability

    Others

    Others

    Enabling Frameworks

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    107/117

    Slide 107

    Passengers amenities Model

    Guidelines for Assistance byEmergency Services / Police etc.

    Model Disaster Management PlanAssistance of state emergency services in case ofemergencies

    Carriage of Luggage (Accompanied/Unaccompanied) Model rules /

    guidelines

    Size & shapeFire ArmsPetsLiability for lost, damaged or late transfer

    Fare fixation Flexibility to fix fares and fare products

    Levy of Penalties Missing penalties: Overstay, Defacing of MetroProperty

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    108/117

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    109/117

    Policy & Regulatory

    Policy & Regulatory Financial

    FinancialCommercial

    Viability

    CommercialViability

    Others

    Others

    Enabling Frameworks

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    110/117

    Slide 110

    Traffic Forecasted Vs Actual

    Tariffs Provision for Inflation linked tariff revision

    Non fare box revenue For improving project viability, non fare revenue is

    stream is must for the bidder

    e.g. Retail, Real Estate, Advertisement etc

    Critical for success of a PPP project

    Policy & Regulatory

    Policy & Regulatory Financial

    FinancialCommercial

    Viability

    CommercialViability

    Others

    Others

    Enabling Frameworks

    Environment

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    111/117

    Slide 111

    EnvironmentGovt. support for fast track approvalsRelaxation in norms & policies for special Infra Projects like Metros

    Timely Clearances

    Propose to have a single window clearance system to avoid delays

    Security (CISF/ Private)e.g Delhi Airport Metro Express , the cost of CISF was not plannedas CA had provision for private Security by the concessionaire.

    Public Perception

    Stakeholders Support from NGOs, Local bodies, citizens must

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    112/117

    Slide

    Execution Challenges

    112

    Large number of interfaces with civil structures constructed by DMRC

    Airport Express Metro - Challenges .1/2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    113/117

    Slide 113

    Large number of interfaces with civil structures constructed by DMRC.

    Very long length for concreting in tunnels

    leading to repeated choking of concrete.

    requiring clearing tons of wasted concrete from inside tunnels.

    Flooding of tunnels with tons of earth despite temporary flood protection measures.

    Simultaneous working by all contractors in constricted space of tunnels & stations.

    Handing over of civil strictures by DMRC in an unplanned and unpredictable

    sequence making impossible to plan system's work in advance.

    Last minute surprises due to major changes in civil structures.

    Track occupancy and access management getting extremely critical in the final

    Airport Express Metro - Challenges .2/2

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    114/117

    Slide 114

    Track occupancy and access management getting extremely critical in the final

    stages of project commissioning.

    Multiple variety of rail borne construction vehicles requiring elaborate manualprocedures to ensure operational safety in the transition to full operation phase.

    Situation changing by hour requiring very close coordination.

    New staff not accustomed to rail borne operation and the dangers of roll down. OTE (Over the track exhaust) ducts raising and alignment requiring high precision.

    RHEDA track for all the 3 variety of tunnels and via duct with severe limitation on

    loading.

    RHEDA Tracks First time in the country, behavior not known

    For speed >250 kmph;Train max. speed:120kmph

    Check-In & Baggage Handling System Implemented 1st time in the country. Integration of two, a highly complex process

    Labour Shortages/unavailability affecting planned activities

    Mumbai Metro One - Challenges

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    115/117

    Slide 115

    Land availability for Casting Yard & Labour Camps in proximity.

    Obtaining approvals from various agencies like Railways, Commissioner of

    Railway Safety, Traffic Police, MCGM, PWI, MPCB etc.

    Frequent and substantial changes in Project planning and timelines on

    account of uncontrollable factors:

    RoW delay Very constrained RoW

    Constraints on account of traffic clearances

    Complex network of underground utilities

    Over ground structures/ encroachments on the RoW

    Constraints in Traffic Diversions and barricading

    Non availability of access/ delay in work due to other agencies

    Conclusions

    There is need for exercise of greater due dilligence by the concessioning authority

    before inviting bids

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    116/117

    Slide

    before inviting bids.

    There is need for quicker decision making/actions on the part of Govt. agencies to

    facilitate the project. A single window clearance is required for all approvals. The Concessioning authority

    should be empowered or a nodal committee formed to expedite approvals.

    Cap on VGF (presently 40% of project cost) needs to be eased.

    A minimum guaranteed fare revenue should be assured to the concessionaire. The

    Govt. should also share some of the risk rather than the private player absorbing

    everything.

    Infrastructure project inputs should get some sort of relief from taxes/levies at least tothe same level that the Govt. executing them would have got.

  • 7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced

    117/117

    Q&A


Recommended