Date post: | 05-Apr-2018 |
Category: |
Documents |
Upload: | romeotango |
View: | 216 times |
Download: | 0 times |
of 117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
1/117
Urban Mobility India Conference & Exhibition 2011(3rd to 6th December 2011)
Presenter - Anil Gupta
(President & Head Infrastructure)
Challenges faced by private parties in planningdesign and operation of rail / guided transit"
5th December 2011
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
2/117
Slide 2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
3/117
Slide 3
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
4/117
Slide 4
Roads & Sea Link
Metros
Cement
Airports
Power Sector
Distribution
Transmission
Trading
Generation
R InfraPresence
Infrastructure Sector
RInfra Overview
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
5/117
Slide 5
PAN India Presence
Maharashtra
Maharashtra: 15 projects1 Road, 2 Metros, 1 Sea Link,
5 Airports, 1 Real Estate,
1 Cement plant , 1 Generation,
2 Transmission & 1 Distribution
Goa : 1 project
Goa Power Generation Plant
Gujarat : 2 projects1 Road Project &
1 Transmission Project
Rajasthan : 1 project1 Road Project
Tamil Nadu: 6 projects6 Road Projects
Delhi: 3 projects1 Road Projects, 1 Metro & 1 Distribution
Andhra Pradesh & Orisaa: 3 projects1 Ultra Mega Transmission Project ,
1 Hyderabad Real Estate &
1 Samalkot Power Generation Plant
Madhya Pradesh, Uttar Pradesh &
Chattisgarh & Haryana,: 3 projects1 Ultra Mega Transmission Project
1 Road Project , 1 Cement Plant
Kerala : 1 project
BSES Kerala Power Generation Plant
Karnataka : 1 project
Wind Farm Generation Plant
Punjab & Himachal Pradesh
: 1 project1 Transmission Project
37 Projects I 17 States I 8 Sectors
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
6/117
Slide 6
Infrastructure
Businesses
Roads 11 ` 120 Bn
Metros 3 ` 160 Bn
Sealink 1`
46 Bn
Airports 5 ` 5 Bn
Total 22 380 Bn
Cement 2 ` 47 Bn
BusinessNo. of
projects
Project Cost
Bn
Infrastructure Portfolio
Largest private sector infrastructure developer on ownership basis
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
7/117
Slide
Details Delhi Metro Mumbai Line-1 Mumbai Line-2
Project Cost(Rs. Bn)
28.8 23.6 110.0
Debt: Grant:Equity
70:0:30 51:27:22 64:21:15
Length (km) 23 11 32
CoD Feb 2011 Q4FY12 Within 5 years
ConcessionPeriod*
30 years 35 years 35 years^
Shareholding
Ridershipin lacs
(on 1st yr Operation)
0.36 (Yr 2012) 7.0 (Yr 2012) 14.0 (Yr 2016)
7
Metro Rail Portfolio
* Including construction period ^ Could be extended for further 10 years
3 Projects I 66 kms I Project Cost - ~ 160 Bn
Expectedridership
over 21Lacs
[66 km]
Expectedridership
over 21Lacs
[66 km]
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
8/117
Slide 8
Project Delhi Airport Express
Project Cost Rs. 2,878 Crs
Length 23 km, largely underground.
Stations 6 nos, 5 underground and 1
elevated.
Concession Period 30 years(incl. Construction
period)
Travel time from New Delhi to Airport reduced
to 18 mins.
Project Cost Rs. 2,878 Crs
Length 23 km, largely underground.
Stations 6 nos, 5 underground and 1
elevated.
Concession Period 30 years(incl. Construction
period)
Travel time from New Delhi to Airport reduced
to 18 mins.
1st PPP Metro Project to be operational in India.
High Speed Metro , tops speed of 120kmph.
Connecting Airport, Dwarka Subcity, Dhaula Kuan,
Aero City to New Delhi/CP.
Provides check in facility within city at New Delhi &
Shivaji Stadium station, Dhaula Kuan (Passenger
only)
Have brought Delhi to league of selected cities
having such a facility.
1st PPP Metro Project to be operational in India.
High Speed Metro , tops speed of 120kmph.
Connecting Airport, Dwarka Subcity, Dhaula Kuan,
Aero City to New Delhi/CP.
Provides check in facility within city at New Delhi &
Shivaji Stadium station, Dhaula Kuan (Passenger
only)
Have brought Delhi to league of selected cities
having such a facility.
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
9/117
Slide
Metro Line - 1
9
Project Mumbai Metro One
Project Cost Rs. 2,356 Crs
Length 11.4 km (Elevated)
Stations 12 nos.
Grant (VGF) Rs. 650 Cr.
Concession Period 35 years(incl. Construction period)
Expected Traffic 7 Lakhs per day in the opening year
East West to East travel time to reduce from 90mins to 20 mins
Project Cost Rs. 2,356 Crs
Length 11.4 km (Elevated)
Stations 12 nos.
Grant (VGF) Rs. 650 Cr.
Concession Period 35 years(incl. Construction period)
Expected Traffic 7 Lakhs per day in the opening year
East West to East travel time to reduce from 90mins to 20 mins
Versova Andheri Ghatkopar Project
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
10/117
Slide
Metro Line - 2(Charkop-Bandra-Mankhurd Metro Project ) Project Cost Rs. 11,551 Crs
Length 33 km
Stations 28 nos.
GoI/GoM to provide Rs 2,298 Crs as Viability Gap Funding
(VGF)
Concession Period 35+10 yrs (incl.5 yrs Construction)
Expected Traffic 14 Lakhs per day in the opening year
To provide North - South Connectivity
Direct connectivity to all the Suburban Rail Lines -
Western, Central & Harbour
Reduces Travel time by 90 minutes
10
Project Metro Line - 2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
11/117
Slide 11
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
12/117
Slide 12
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Implementation/Operation Framework
Due Diligence Logistics
Type of structure
Intermodal Integration
Due Diligence
Logistics
Type of structure
Intermodal Integration
Depot Route finalization
Phase Commissioning
Depot
Route finalization
Phase Commissioning
Clearances pre -
construction
Right of Way
Safety issues
Public interface
Utilities
Clearances pre -
construction
Right of Way
Safety issues
Public interface
Utilities
RAMs requirements Operation hours
Training
Depot issues
Intermodal integration
Safety
RAMs requirements
Operation hours
Training
Depot issues
Intermodal integration
Safety
11 22 33 44
Challenges Challenges Challenges Challenges
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
13/117
Slide 13
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Implementation/Operation Framework
Due Diligence Logistics
Type of structure
Intermodal Integration
Due Diligence
Logistics
Type of structure
Intermodal Integration
11
Challenges
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
14/117
Slide
Due diligence by Concessioning Authority before awarding/ inviting ofbids. Few examples:
Delhi Airport Express
1) Original plan was with at-grade siding at Palam, this would have facilitated thematerial movement and access during construction
2) Long inter-station distances(7 km) without evacuation passage duringemergency.
Mumbai Metro-1
1) Depot Ownership was not with Concessioning authority
2) Final available depot land different from original DPR (shape & size)
Mumbai Metro-2
1) Both the depot lands falling in CRZ.areas
2) Part of the elevated viaduct infringing the Aircraft landing funnel
3) Railway approvals for crossing Railway tracks/ lands.
4) Lack of clarity on the Commercial Space utilisation.
5) Location of the DN Nagar station (MCGM Land) and Bandra Station (Relief
and Rehabilitation issues).
14
Due Diligence
Implementation / Operation Framework
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
15/117
Slide 15
Layout of Dwarka Depot(as planned earlier )
Delhi Airport Metro Express
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Depot land location changed by DMRC
Due to change in land in-fructuous works had to be done e.g.:
Geo-technical investigations
Depot Layout planning
Constraint leading to 3 trains in the line
Original Location
Changed
Location
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
16/117
Slide
Layout of Charkop car shed showingCRZ areas
16
Mumbai Metro Line 2
Total depot area 18.7 hectare
Challenges
82% (16.2 ha) falls under CRZ
No heavy maintenance allowed
Proposed construction on stilt
Leads to cost & time over run
Un-hygenic work environment
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
17/117
Slide 17
Layout of Mankhurd Depot showing CRZ areas
Mumbai Metro Line 2
Total depot area 24 hectare
Challenges
91% (21.8 ha) falls under CRZ
Zero maintenance allowed on CRZ-1
Depot on stilt as no alternate land
Leads to time & cost over run
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
18/117
Slide18
Infringement of aircraftfunnel near Juhu Station
Mumbai Metro Line 2
18
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
19/117
Slide 19
Mumbai Metro Line 2
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Viaduct
Infringement of aircraft funnelnear Juhu Station
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
20/117
Slide
Railway Clearances
Mumbai Metro Line1
Railway Clearances Andheri Steel Bridge
Long approval process & has implication on design and planning
Mumbai Metro Line 2
Railway Clearances Uncertainties at Kurla crossing
Ambiguity about the height of Metro track at Kurla.
It can be at 7 mtrs or 22 mtrs above ground level.
Implications:
On vertical profile upto 2 kms on either side
Additional cost impact
In-principle approval is still awaited on this matter.
Mumbai Metro
20
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
21/117
Slide
FOOT OVER BRIDGE
EXISTING RAILWAY TRACKS (CST-THANE LINE)
STEEL GIRDER BRIDGE FOR METRO CBM CORRIDOR (LINE-2)AT KURLA STATION YARD
MANKHURDBANDRA
7.0 M
Mumbai Metro Line 2 Original Plan
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
21
Metro Bridge Originally Planned
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
22/117
Slide
ExecutionExecution
PROPOSED ELEVATED
CORRIDOR (RAILWAY)
FOOT OVER BRIDGE
EXISTING RAILWAY TRACKS (CST-THANE LINE)
STEEL GIRDER BRIDGE FOR METRO AT KURLA STATIONMANKHURDBANDRA
7.0 M
3.0 M
22 M
Mumbai Metro Line 2 Revised Plan
PlanningPlanning DesignDesign OperationOperation
Metro Bridge proposed to be atheight of a 5 storey building
22
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
23/117
Slide
Problem of Commercial Development
CA allowed for commercial development above the platform level.
Present rules do not permit.
Development Control Rules (DCR) are under modification since last two years.
Creating Commercial Space above the stations is difficult, since Fire Laws require
separate escape stairs for persons above the platform. This causes huge
constraints on the footpath space.
Mumbai Metro Line 2
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
23
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
24/117
Slide
Station with Concourse and Platform
Mumbai Metro Line 2
24
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
.next
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
25/117
Slide
CommercialFloor
30m
4.0m
Carriagewayup
Carriagewaydown
4.5m
25m
25m
4.0m
4.0m
Implication of Commercial space
above Platform level
Additional floor above PF requires
extra staircases on the Pathway.
Mumbai Metro Line 2
25
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
More setback on already constrained
road
Challenges
Infringement with existing structures
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
26/117
Slide26
Locations where localIssues may affect alignment
Locations where localIssues may affect alignment
26
Infringement with Aircraft funnel path
Challenges
Infringement with EHV lines at 13 nos.locations
Infringement with monorail crossing and roadflyover
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Mumbai Metro Line 2
R&R issues at Kurla & BandraDepot on CRZ areas
Railways approval
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
27/117
Slide
Logistics plays major role in Construction methodology, costing &timelines.
Need for Govt. to identify & make available casting yards ahead of bidding.
This ensures level playing field during bidding but also smoothen theexecution greatly.
Metro -1 :
CA , had provision for 2 nos. casting yards against 1 no. made available.
This had implications on Cost & timelines of project (also, logistics & planning)
We faced logistic issues with U-girders due to RoW availability
Metro -2 : Based on learning from Line-1, moving to segmental approachmethodology.
However, Segmental methodology, requires Continuous stretch of RoW
Location & nos. of casting yards would decide the contracting strategy
27
Logistics
Implementation / Operation Framework
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
28/117
Slide
Sub Str 1 +Super Str 1,2,3Package
Sub Str 3Package
Contract ing St rategy : ( Based on 3 Cast ing Yards)
V 3Package
Pack age Sect ion
(F rom-T o )
Leng t h
( k m )
Sub Str - 1 Charkop to D N Nagar 9.30
Sub Str - 2 D N Nagar to Juhu 3.25
Sub Str - 3 Juhu to Bandra 6.37
V2 Package Bandra to Kurla 6.75
V3 Package Kurla to Mankhurd 7.44
1
2
3
Sub Str 2Package
V2 Package
28
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
V1Package
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
29/117
Slide
SS1Package
SS3Package
Contract ing St rategy : ( Based on 2 Cast ing Yards)
Pack age Sect ion(F rom-To )
Sub Structure 1 (SS1) Charkop to D N Nagar
Sub Structure 2(SS2) D N Nagarto Juhu
Sub Structure 3(SS3) Juhu to BandraSuper Structure I Charkop to Bandra
Sub Structure 4(SS4) Bandra to Kurla
Sub Structure 5(SS5) Kurla to Mankhurd
Super Structure II Bandra to MankhurdSS2 Package
Super
StructurePackage
SS4 & Super Structure IIPackage
SS5 & SuperStructure III Package 29
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
30/117
Slide 30
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Implementation / Operation Framework
Metro-1 : RoW Availability
Non availability of fronts as perplanning hampers the timelines and
thus the Cost of project
100% RoW still not available
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
31/117
Slide 31
Sr . Part icular RoW Required RoWAvailablePercentage(%)
1 Viaduct 33.71 km 17.3 km 51 %
2 Stat ions 28 stat ions 15 Stat ions 54 %
3 Depot2 depots(43 hectare) Nil 0 %
4Railway BridgesCrossings- Inprinciple approvals
4 crossings 1 crossing 25 %
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Implementation / Operation Framework
Metro-2 : RoW Availability (100% by Apr11)
Segmental approachrequires more continuous RoWto prevent idling of girder launching truss
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
32/117
Slide
Type of Structure
The success of the project is determined by the prompt & efficient
execution of civil engineering structure.
Urban environment call for greater adoption of pre-cast
structures.
The logistics of the movement of precast material with restrictions
space can also determine the type of construction.
e.g Delhi with generally wide roads, while U girders could be considered as a
feasible option, for line 2 in Mumbai we have chosen the option of precast
segmental construction.
32
Implementation / Operation Framework
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
I l i O i F k
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
33/117
Slide 33
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
U- Girder handling
Implementation / Operation Framework
Narrow Right of Way constraints
Challenges
Hampering planned execution
Girder movement, during nighthours (4-5 hrs block)
Min. width of 7 mtr on straight road& larger on turns
Length 30 mtr (max.)
Width 5.7 mtr
I l t ti / O ti F k
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
34/117
Slide
Scheme being adopted for line 2 (segmental construction)
34
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Implementation / Operation Framework
Segment :
Width 3 mtr
Length 10 mtr
I l t ti / O ti F k
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
35/117
Slide 35
Implementation / Operation Framework
Typical section showing clearances required for a Viaduct
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
36/117
Intermodal Integration Delhi Airport Exp
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
37/117
Slide 37
Missing
linkbe
tween
Airport
line&DMRC
No IntermodalIntegration planned
Intermodal Integration Delhi Airport Exp
Limited & constrained Car Parks near station
Intermodal Integration with other modes missing
(DMRC, DTC buses etc)
Connectivity between Rajiv Chowk and Shivaji Stadium stn
Intermodal Integration Delhi Airport Exp
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
38/117
Slide 38
PROP
OSED
FOB
No Connectivity with NewDelhi Railway Station
Intermodal Integration Delhi Airport Exp
DAMEPL Proposed a Foot over Bridge for
passenger convenience, pending with Railway
Subway
Entry
New DelhiStation
Connectivity between Railway stn and New Delhi Station (Airport Exp)
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
39/117
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
40/117
Slide 40
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Standards in regard to securitydeployment and scale of equipment
StationsIn-TrainOther sensitive installations like depot &Receiving Stations
Standards in regard to luggage transfer and customs facilities etc.
Integration with othertransportation modes and civic
facilities
Other upcoming Metro linesRoads
AirportsCity CentersMono RailsPod Taxis,Bus stand,Railway Stations,Taxistands
Drainage
SewerageHinterland signage
Implementation / Operation Framework
Coordinating agency for facilitationand enforcement
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
41/117
Slide 41
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Statutory approvals(Fire, Height, PTCC, Frequency, Safety, Sub-systems etc) Lack of Clear procedures, documentation & Time
frame for stage approval
(Concept, Design, Final)
Lack of Clear National DesignStandards
Multiple standards
Execution Traffic Diversion
Civic facility DiversionConstruction safety standardsLong tunnels Temporary ventilation
Access
Emergency medical facility
Emergency communication
Implementation / Operation Framework
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
42/117
Slide 42
Implementation / Operation Framework
DesignDesign ExecutionExecutionPlanningPlanning OperationOperationDesignDesign
Depot
Route finalization
Phase Commissioning
Depot
Route finalization
Phase Commissioning
22
Challenges
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
43/117
Slide
Depot
43
Implementation / Operation Framework
Depot where the rakes are maintained and stabled is the heart of any Metro
System.
It requires a large area for carrying out the multifarious activities.
Unfortunately in Urban areas the land is at a premium, and the urge of the Govt.
is to limit the size to the minimum.
Both (Line 1 & 2) depots planning has been beset with difficulties & constraints.
Mumbai Line 1 Govt. carved out a chunk of land right in the middle of the depot land and
gave to a builder. This has resulted in a very constricted depot with very
sharp curves and constrained movement of rakes, men and materials.
Mumbai Line 2 Both the depots are embroiled in CRZ issues.
The conditions of no maintenance in CRZ zone can virtually sound the
death knell of the project unless a solution is found.
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
44/117
Mumbai Metro One
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
45/117
Slide 45
Design layout - D N Nagar Depot
Land given toprivatedeveloper
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
46/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
47/117
Mumbai Metro Line 2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
48/117
Slide
Layout of Charkop car shed showing
CRZ areas
48
Total depot area 18.7 hectare
Challenges
82% (16.2 ha) falls under CRZ
No heavy maintenance allowed
Proposed construction on stilt
Leads to cost & time over run
Un-hygenic work environment
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Mumbai Metro Line-2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
49/117
Slide 49
Mankhurd Depot
Challenges
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Embroiled in CRZ issues
Total depot area 24 hectare
91% (21.8 ha) falls under CRZ
Mumbai Metro Line 2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
50/117
Slide 50
Layout of Mankhurd Depot showing CRZ areas
Total depot area 24 hectare
Challenges
91% (21.8 ha) falls under CRZ
Zero maintenance allowed on CRZ-1
Depot on stilt as no alternate land
Leads to time & cost over run
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
51/117
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
52/117
Slide
While ideally the stations should be located at about every one Km.
or so on a typical metro system, but various constraints prevail:
Feasibility from consideration of track alignment as curves and
grades are to be avoided.
Space constraints as a station for an elevated alignment leaves
a complex footprint on the ground due to its piers, lift wells,
staircases and escalators.
52
Route Finalisation - Station Locations
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
53/117
Mumbai Metro-2 : Phased Commissioning
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
54/117
Slide
Phase 1
Phase 2
1
2
3
Phase 3
54
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
55/117
Slide 55
PlanningPlanning DesignDesign ExecutionExecution OperationOperationExecutionExecution
Clearances pre -
construction
Right of Way
Safety issues
Public interface
Utilities
Clearances pre -
construction
Right of Way
Safety issues
Public interface
Utilities
33
Challenges
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
56/117
Slide 56
A major issue that the private concessionaire has to contend
with is the approvals from a multifarious number of agencies/
bodies.
Approvals before project commencement Approvals for Project Commissioning
Clearances pre-construction
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
57/117
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
58/117
Slide
Broadly there are 2 types of approval required :
Approvals for Project Commissioning
CMRS (Commissioner for Metro Rail Safety)
Approval required for running the Metro Rail.
Buildings Permissions / Local Municipal
Authority For discharge of sewerage, stormwater and supply of drinking & fire fighting water to
the stations.
EIG (Electrical Inspector General)- Approvals are
required for all electrical systems installed for the
running of the Metro Rail.
Safety, Health & Environment Approvals
required for proper functioning of the infrastructure
at the stations for general public at large
IE (Independent Engineer) Approvals required
that all the construction and infrastructure is as per
best industries practices
MoR / RDSO Approvals required from Ministry
of Raliways and RDSO for proper functioning of the
infrastructure at the stations for general public at
large
Fire Final fire NOC is required for the operations
of the stations and via ducts from the Local FireAuthority.
Lift Inspector Approval required for
commissioning of the lifts and escalators to the
stations
Clearances pre-construction1/2
58
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
59/117
Slide
The Right of way can have a serious impact on the
planning of the type of structure and of the scheduling.
E.g . in the vicinity of Navrang Cinema on Mumbai Line 1 with
access to site only from one direction, we have been forced to
do sequential working one at a time at each pier and
superstructure as advance construction of substructure would
have left no space for the movement of cranes for the erection
of girders.
59
Right of Way (RoW)
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
60/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
61/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
62/117
P bli I f
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
63/117
Slide 63
Public Interface PlanningPlanning DesignDesign ExecutionExecution OperationOperation
To limit inconvenience to citizens
Challenges
To maintain flow of traffic, limit jams
Safety of local people and workers
Interference by NGOs/political parties
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
64/117
Slide 64
Lack of defined process and ownership of utility shifting
It is suggested that, Concessionaire is given an advance payment
to expedite the work through agencies.
In Line-2 , there are 11 locations where EHV lines are infringing
with our proposed alignment.
Relocating the towers, involves land acquisition and is a protracted
process
In Mumbai, shifting of Utilities can be undertaken only in fair season
(non monsoon), which puts pressure on the project timelines.
Utilities
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Need for :1)Dedicated corridor for shifting underground cables2)Need of GIS mapping of underground utility network.
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
65/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
66/117
Mumbai Metro One Complex Utilities
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
67/117
Slide 67
A typical section showing undergroundutilities:1.Live Sewer Lines2.Electricity Cables
Tata Power : 2 nos.
Reliance Energy: 6 nos.
3.Water Pipe lines4.Storm water drain5.Gas Pile line
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
Airport Express Metro- Tunnel Work
Pl i
D i
E ti
O ti
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
68/117
Slide 68
Concreting in long tunnels for track works
Challenges
Concrete Choking in pipe , leading to waste
Spent hours in clearing to restart the work
Distressing and Final Parameter Checking in Progress
PlanningPlanning DesignDesign ExecutionExecution OperationOperation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
69/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
70/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
71/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
72/117
B id L h 183
Mumbai Metro One - Andheri Steel Bridge
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
73/117
Slide 73
Bridge Length : 183 mtrs
No. of spans : 3 nos. Span length : 61 mtr. Height(rail level): 8 mts Weight (steel) : 1275 metric tonne
Artists impression
Mumbai Metro One -WEH Bridge
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
74/117
Slide
Positioned at a height of 22 metersfrom ground
Positioned at a height of 22 metersfrom ground
Crossing over busiest westernexpress highway
Crossing over busiest westernexpress highway
Highly skilled and precision jobHighly skilled and precision job
Contemporary Constructionmethodology
Contemporary Constructionmethodology
Cable Stay Bridge TechnologyChallenge
Cable Stay Bridge TechnologyChallenge
74
Existing Express way
Main road underExpress way
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
75/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
76/117
Restrictive RoW
Mumbai Metro One
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
77/117
Slide 77
Andheri Stn Area
RoW of 18 mtr against plan of 27 mtrs.
Challenges
Heavy vehicular & pedestrian traffic owing toproximity to andheri station
RoW of 18 mtr leading to separate utility building
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
78/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
79/117
Constrained & Narrow RoW
Mumbai Metro One
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
80/117
Slide 80
Ghatkopar Station
Station overcongested area
..1/2
RoW of 18 mtr leading to separate utility building
Challenges
Heavy vehicular & pedestrian traffic owing toproximity to Ghatkopar station
Close proximity to adjoining structures
Utility Building
Constrained & Narrow RoW
Mumbai Metro One
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
81/117
Slide81
Densely crowded& narrow lane
81
Ghatkopar Station ..2/2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
82/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
83/117
Cons t r a ined RoW ow ing t o
Mumbai Metro One
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
84/117
Slide 84
Densely crowded routedense ly c row ded st ree t
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
85/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
86/117
Mumbai Metro 2
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
87/117
Slide 87
High Voltage & various other lines infringing the proposedalignment
HT
Tower
Mumbai Metro 2
High Voltage lines infringing
ith d li t
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
88/117
Slide 88
with proposed alignment7 locations showing EHV lines
infringing with proposedalignment between Bandra to
Mankhurd
7 locations showing EHV linesinfringing with proposed
alignment between Bandra toMankhurd
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
89/117
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
90/117
Slide 90
PlanningPlanning
DesignDesign
ExecutionExecution
OperationOperationOperationOperation
RAMs Requirements
Operation hours
Training
Depot issues
Security
Inter-modal integration
RAMs Requirements
Operation hours
Training
Depot issues
Security
Inter-modal integration
44
Challenges
OperationOperation
RAMs requirements
Operation hours
Training
Depot issues
Intermodal integration
Safety
RAMs requirements
Operation hours
Training
Depot issues
Intermodal integration
Safety
44
Challenges
Planning
Planning Design
Design Execution
Execution Operation
Operation
Delhi Airport Metro Express Operational Challenges
RAMS Requirement
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
91/117
Slide 91
RAMS Requirement
Stringent compliance norms for a Private Operator.
Provision for penalties in case of default , threat of
termination of Concession agreement for a Private Operator.
Delhi Airport Metro Express
System Availability 99.94%
Other Metros
Less stringent norms
No such punitive provisions for Government Metro Operators
..additional system capacity and redundancy
Planning
Planning Design
Design Execution
Execution Operation
OperationOperating Hours
Delhi Airport Metro Express
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
92/117
Slide
Concession Agreement Requirementsfor Operating Hours
Passenger Service Operating Hours:
CA requires 20 hours passenger services daily
Currently at 18 hours from 0530 hrs to 2330 hrs.CA : Concession Agreement
92
Very Short maintenance period(white hours
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
93/117
Slide 93
Training Train Operator Certification
Train OperatorCertifications
DMRC Delhi Airport
Interview Selection Interview One or more Selection Interview
Psychometric Test Written Psychometric test CADAT for low-speed
Computer Aided Drivers' AptitutudeTest (CADAT) for trains above 105
kmph by RDSO
Passing marks 60% 75%
Train Simulator 80 hrs 6 weeks
Train Handling OnTest Track
40 Kms 1 week (Minimum 90 Kms.)
Train Handling(revenue service)
4 weeks 4 weeks (Minimum 400 Kms.)
Mumbai Metro Line-1 No clarity on Train Operators
Certification as of nowMumbai Metro Line-2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
94/117
Planning
Planning Design
Design Execution
Execution Operation
Operation
Training
Delhi Airport Metro Express
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
95/117
Slide 95
No existing Running system in India
Majority of staff new
Very little time for acclimatization
Direct training to staff (No time to train the Trainers)
Section unavailable for training due to intensive testing
No Operator willing to take the risk
Continuously changing scenario
Large number of skill sets to be trained
Training
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
96/117
Airport Express Metro- Depot Work
Planning
Planning Design
Design Execution
Execution Operation
Operation
Ch ll
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
97/117
Slide 97
Single Line, Single Entry
Challenges
Steep ramp at entry & exit
No space to achieve isolation
Unsuitable shape of plot(Dwarka Depot )
Delhi Airport Metro Express
In sufficient
Planning
Planning Design
Design Execution
Execution Operation
Operation
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
98/117
Slide 98
Depot layout revised according to new land plan and submitted to DMRC
DMRC instructed to revise depot layout in order to integrate the function area with property area
Layout revised to avoid shunting neck, falling into ramp area. Shunting neck could have been adjusted withoutchanging the layout if DMRC had agreed to provide small additional land near to the ramp.
Due to delay in finalization of layout, Depot works were put on hold for 2 months
DMRC Line 3 Viaduct
In sufficientwidth
Planning
Planning Design
Design Execution
Execution Operation
Operation
Intermodal Integration
Delhi Airport Metro Express
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
99/117
Slide 99
Intermodal Integration
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
100/117
Planning
Planning Design
Design Execution
Execution Operation
Operation
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
101/117
Slide 101
Risk Sharing
Revenue
Accidents
Projected Traffic V/s Actual
External causes
Sub-optimal use of resources due to
short route lengths
Major Accidents & Breakdowns
Major Repairs and Overhauls
Sensitive to major disruptions Migration of key officials
Interoperability in case of contiguous sections/extensions
Lack of uniform minimum Operation, Safety & Reliability standards
Resources alignment with Railways, DMRC forDisaster Management
Planning
Planning Design
Design Execution
Execution Operation
Operation
Ticketing (with DMRC);
Implementation / Operation Framework
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
102/117
Slide 102
ConnectivityTicketing (with DMRC);Last mile (bus, rickshaw etc);Car parking
Bedding in periodRemoval of repeat failures;
Closure of punch lists/open item lists;Transfer of knowledge, spares etc from suppliersQuality management from projects into operations.
Security Same as the Airports (more than the metro)
Awareness Marketing / advertisements etc local, national & international
Effective & EfficientOrganization
Support requirements including training: org should matchridership wherever possible, multi-skilling etc
Safety Primary Goal Transition from project safety to operational safety, closeworking with National Disaster Authority
Performance Tracking Aligned to CA, back to back with suppliers; emulateinternational best practices
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
103/117
Slide 103
Enabling Frameworks
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
104/117
Slide 104
Policy &
Regulatory
Policy &Regulatory
FinancialFinancialCommercial
Viability
CommercialViability
OthersOthers
Tramway Vs Metro act
Training standards
Certification body Tariff
Taxation
Levy of penalties
Testing & accreditation
Tramway Vs Metro act
Training standards
Certification body Tariff
Taxation
Levy of penalties
Testing & accreditation
Timely project
completion
VGF support Project Funding
Revenue realization
Timely project
completion
VGF support Project Funding
Revenue realization
Traffic (Forecast/ actual)
Tariffs
Non Fare box revenue Cost & Time over run
Traffic (Forecast/ actual)
Tariffs
Non Fare box revenue Cost & Time over run
Environment
Timely Clearance
Security (private/CISF) Public perception
Stakeholders
Environment
Timely Clearance
Security (private/CISF) Public perception
Stakeholders
11 22 33 44
Policy & Regulatory
Policy & Regulatory Financial
FinancialCommercial
Viability
CommercialViability
Others
Others
Enabling Frameworks
L k f l it i P li F k Metro Act V/s Tramway Act
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
105/117
Slide 105
Lack of clarity in Policy Frame-work Metro Act V/s Tramway ActApplicability for PPP Projects (Authority splitbetween Concessioning Authority andConcessionaire)
Concessionaire to be made party to any
amendments to Acts / Rules
Powers and Liabilities as per Metro Act Concessioning AuthorityConcessionaireThird Party / Contractor
Security Policy Framework missing e.gDelhi Airport Metro Express , the cost of CISF was not planned as CAhad provision for private Security by the concessionaire.
Policy for Metro Railway Security
Clarity on Cost
Training Standards Model guidelines DurationContentTests
Competency Certification standards Model guidelines for competencycertification.(Key Officials, TO, Shunting drivers, Controllers, points man etc)
Minimum Qualification
MedicalPsychologicalRefresher / Retraining
Policy & Regulatory
Policy & Regulatory Financial
FinancialCommercial
Viability
CommercialViability
Others
Others
Enabling Frameworks
Staff classification & Working Hour Classification of staff
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
106/117
Slide 106
Staff classification & Working Hourregulation Model Guidelines
Classification of staffHours of working and rest period
Alcohol and drug testing standard Breath test levels
Tariff uniformity Provision for Inflation linked tariff increasePower to commercial establishments in station
Taxation Project and construction equipmentElectricity dutyLocal taxesProperty taxesOctroi issues, local duties
Construction in vicinity of ROW
Model guidelinese.g Petrol storage tank
Administrator for alignment against unsafe construction(Especially over the Tunnels): Concessionaire orConcessioning Authority
Rules/Guidelines for Metro railway endorsement forconstruction in vicinity
Should be informed
upfront about taxexemptions
Policy & Regulatory
Policy & Regulatory Financial
FinancialCommercial
Viability
CommercialViability
Others
Others
Enabling Frameworks
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
107/117
Slide 107
Passengers amenities Model
Guidelines for Assistance byEmergency Services / Police etc.
Model Disaster Management PlanAssistance of state emergency services in case ofemergencies
Carriage of Luggage (Accompanied/Unaccompanied) Model rules /
guidelines
Size & shapeFire ArmsPetsLiability for lost, damaged or late transfer
Fare fixation Flexibility to fix fares and fare products
Levy of Penalties Missing penalties: Overstay, Defacing of MetroProperty
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
108/117
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
109/117
Policy & Regulatory
Policy & Regulatory Financial
FinancialCommercial
Viability
CommercialViability
Others
Others
Enabling Frameworks
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
110/117
Slide 110
Traffic Forecasted Vs Actual
Tariffs Provision for Inflation linked tariff revision
Non fare box revenue For improving project viability, non fare revenue is
stream is must for the bidder
e.g. Retail, Real Estate, Advertisement etc
Critical for success of a PPP project
Policy & Regulatory
Policy & Regulatory Financial
FinancialCommercial
Viability
CommercialViability
Others
Others
Enabling Frameworks
Environment
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
111/117
Slide 111
EnvironmentGovt. support for fast track approvalsRelaxation in norms & policies for special Infra Projects like Metros
Timely Clearances
Propose to have a single window clearance system to avoid delays
Security (CISF/ Private)e.g Delhi Airport Metro Express , the cost of CISF was not plannedas CA had provision for private Security by the concessionaire.
Public Perception
Stakeholders Support from NGOs, Local bodies, citizens must
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
112/117
Slide
Execution Challenges
112
Large number of interfaces with civil structures constructed by DMRC
Airport Express Metro - Challenges .1/2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
113/117
Slide 113
Large number of interfaces with civil structures constructed by DMRC.
Very long length for concreting in tunnels
leading to repeated choking of concrete.
requiring clearing tons of wasted concrete from inside tunnels.
Flooding of tunnels with tons of earth despite temporary flood protection measures.
Simultaneous working by all contractors in constricted space of tunnels & stations.
Handing over of civil strictures by DMRC in an unplanned and unpredictable
sequence making impossible to plan system's work in advance.
Last minute surprises due to major changes in civil structures.
Track occupancy and access management getting extremely critical in the final
Airport Express Metro - Challenges .2/2
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
114/117
Slide 114
Track occupancy and access management getting extremely critical in the final
stages of project commissioning.
Multiple variety of rail borne construction vehicles requiring elaborate manualprocedures to ensure operational safety in the transition to full operation phase.
Situation changing by hour requiring very close coordination.
New staff not accustomed to rail borne operation and the dangers of roll down. OTE (Over the track exhaust) ducts raising and alignment requiring high precision.
RHEDA track for all the 3 variety of tunnels and via duct with severe limitation on
loading.
RHEDA Tracks First time in the country, behavior not known
For speed >250 kmph;Train max. speed:120kmph
Check-In & Baggage Handling System Implemented 1st time in the country. Integration of two, a highly complex process
Labour Shortages/unavailability affecting planned activities
Mumbai Metro One - Challenges
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
115/117
Slide 115
Land availability for Casting Yard & Labour Camps in proximity.
Obtaining approvals from various agencies like Railways, Commissioner of
Railway Safety, Traffic Police, MCGM, PWI, MPCB etc.
Frequent and substantial changes in Project planning and timelines on
account of uncontrollable factors:
RoW delay Very constrained RoW
Constraints on account of traffic clearances
Complex network of underground utilities
Over ground structures/ encroachments on the RoW
Constraints in Traffic Diversions and barricading
Non availability of access/ delay in work due to other agencies
Conclusions
There is need for exercise of greater due dilligence by the concessioning authority
before inviting bids
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
116/117
Slide
before inviting bids.
There is need for quicker decision making/actions on the part of Govt. agencies to
facilitate the project. A single window clearance is required for all approvals. The Concessioning authority
should be empowered or a nodal committee formed to expedite approvals.
Cap on VGF (presently 40% of project cost) needs to be eased.
A minimum guaranteed fare revenue should be assured to the concessionaire. The
Govt. should also share some of the risk rather than the private player absorbing
everything.
Infrastructure project inputs should get some sort of relief from taxes/levies at least tothe same level that the Govt. executing them would have got.
7/31/2019 Reliane Infra Presentation on Infrastructure and Urban Mobility - Challenges Faced
117/117
Q&A