REMEDIATION AND REUSE OF CONTAMINATED SEDIMENTS: A NEW PHYSICAL-CHEMICAL PROCESS TO THE POINT
2nd International Workshop: Mechanism and Modelling of Waste/Cement InteractionsLe Croisic, October 12-16, 2008 october 2008
G. Ferrari, A. Careghini, S. Dastoli, L.Bonomo,L.DePropris, M.Gabellini, S.Saponaro
VOLUME OF SEDIMENT TO BE REMEDIATED 6.000.000 m3
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
VOLUME OF SEDIMENT TO BE DREDGED 13.000.000 m3
Analytical results of most contaminated sediment selected for this work (600.000 m3)
Compound Concentration (mg/kg d.w.)
ISPRAintervention
values
D. Lgs. 152/06
column B
HazardousSubstances
limitsChromium (total) 91 150 800 1000
Copper 210 75 600 250 000
Nickel 22 63 500 10 000
Lead 51 80 1 000 5 000
Zinc 314 165 1 500 1 000
Arsenic 18 32 50 1 000
Cadmium 1 1 15 1 000
Mercury 200 1 5 500
PCB (total) 3 0,2 5 50
>C12 petroleum hydrocarbons 5 000 - 750 1 000
HCB 0,003 0,005 5 1 000
PAH (total) 5 4 100 1 000
PCDD/F 2,8· 10–4 0,3 · 10–4 1 · 10–4 1 · 10–2
TBT 0,003 0.07 - 2 500
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
THE OBJECTIVE OF THIS STUDY IS TO EVALUATE THE EFFICIENCY OF A NEW PHYSICAL-CHEMICAL PROCESS FOR THE TREATMENT OF LARGE VOLUME OF CONTAMINATED SEDIMENTS FROM AUGUSTA BAY
REUSE OF RESULTING S/S MATERIAL
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
Ordinary Solidification/Stabilization (S/S) processes aims at encapsulating wastes into a solid cement matrix (Solidification) and decreasing mobility and toxicity of inorganic contaminants (Stabilization)
Poor attention has been paid in the past to impart to S/S materials good mechanical properties in a form which could allow their reuse. The reason for this is that, in Italy, S/S process has been normally used to reduce leaching before landfill disposal.
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
first step: production of a cementitious granular material, based on principles of high performance concrete (HPC)
use of superplasticizers and hydrophobic additive to reduce W/C and to improve watertightness
Environmental aspectService life Mechanical properties
MAPEI HPSS SYSTEMHigh Performance Solidification/Stabilization2 STEPS
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process for the purpose
LOWER W/C AND HIGHER WATERTIGHTNESS MEANS
Lower leaching of contaminants
HIGHER ENVIRONMENTAL COMPATIBILITY
Lower permeability
HIGHER DURABILITY
Stronger bonds
HIGHER MECHANICAL STRENGTH
First step: granulation
Formulation:• Augusta harbour sediment (60%, dry basis) • Cement (CEM I, 52.5) (21%)• Additives: Mapeplast ECO 1-A e ECO 1-B (2 %)• Water (17%)
High shear mixer Rotating plate
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
W/C = 0.8
W/C+S = 0.2
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
0
5
10
15
20
25
30
35
40
<1 1 2 4 5,6 >8
RET
AIN
ED F
RA
CTI
ON
(%)
MESH SIZE (mm)
TYPICAL PARTICLE SIZE DISTRIBUTION OF GRANULAR MATERIAL FROM STEP 1
First step: granulation
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
INDUSTRIAL PLANT CAPACITY 4m3/h
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
Second step: thermal vacuum distillation (TDV) of the granular materialsfrom step 1. It is necessary when soil or sediments containorganic/volatile/semivolatile contaminants.
Low temperature distillation (max 250 °C) under high vacuum (≤20 mm Hg)
No degradation of cement matrixNo gas emissions because the process is operating in high vacuum conditionsNo dust problems because the process is operated on the granular materials
MAPEI HPSS SYSTEMHigh Performance Solidification/Stabilization2 STEPS
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
THERMAL VACUUM DISTILLATION EQUIPEMENTS
LAB SCALE (LEFT) – PILOT SCALE (RIGHT)
XRD after 24 hours XRD after 28 days
FISRST STEP - CEMENT HYDRATION
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
• no negative effect of sediment on set and hydration rate• portlandite consumption• monocarbonate formation
Fine quartz sand mortar
W/C = 0.8
ESEM images after 24 hours of hydration
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
Sediment based granular material
W/C = 0.8
FISRST STEP - CEMENT HYDRATION
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
ESEM images after 7 days of hydration
Fine quartz sand mortar
W/C = 0.8
Sediment based granular material
W/C = 0.8
FISRST STEP - CEMENT HYDRATION
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
ESEM images after 28 days of hydration
Fine quartz sand mortar
W/C = 0.8
Sediment based granular material
W/C = 0.8
FISRST STEP - CEMENT HYDRATION
SECOND STEP: THERMAL VACUUM DISTILLATION TVD
Evaluation of three different conditions
1. Temperature = 150 °C and tresidence = 16 hours;2. Temperature = 200 °C and tresidence = 6 hours;
development process parameters
3. Temperature = 250 °C and tresidence = 4 hours.
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
0
50
100
150
200
250
300
0 2 4 6 8 10 12
TIME (HOURS)
TEM
PER
ATU
RE
(°C
)
SELECTED CONDITIONS: 250 °C FOR 4 HOURS
250 °C, 4 hours
150 °C, 16 hours
Results of morphological analysis
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
SECOND STEP: THERMAL VACUUM DISTILLATION TVD
Results of chemical analysis (1/3)Mercury
0
50
100
150
200
250
300
Sediment Step one 150 °C x16 h
200 °C x6 h
250 °C x4 h
gravel 1 gravel 2
mg
/ kg
d.w
.
C > 12 petroleum hydrocarbons
0
1000
2000
3000
4000
5000
6000
7000
Sediment Step one 150 °C x16 h
200 °C x6 h
250 °C x4 h
gravel 1 gravel 2m
g / k
g d.
w.
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
SECOND STEP: THERMAL VACUUM DISTILLATION TVD
Results of chemical analysis (2/3)
PAHs (total)
0
1
2
3
4
5
6
7
8
9
10
Sediment Step one 150 °C x 16 h 200 °C x 6 h 250 °C x 4 h
mg
/ kg
d.w
.
PCBs (total)
0
1
2
3
4
5
6
Sediment Step one 150 °C x 16 h 200 °C x 6 h 250 °C x 4 h
mg
/ kg
d.w
.
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
SECOND STEP: THERMAL VACUUM DISTILLATION TVD
PCDD/Fs ( WHO-TE index)
0
50
100
150
200
250
300
350
400
Sediment Step one 150 °C x 16 h 200 °C x 6 h 250 °C x 4 h
ng /
kg d
.w.
Results of chemical analysis (3/3)
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
SECOND STEP: THERMAL VACUUM DISTILLATION TVD
Results of leaching test (EN 12457-2)
Mercury
0
0.2
0.4
0.6
0.8
1
1.2
Step one 150 °C x 16h
200 °C x 6 h 250 °C x 4 h gravel 1 gravel 2
μg /
L
Lead
0
10
20
30
40
50
60
Step one 150 °C x 16h
200 °C x 6 h 250 °C x 4 h gravel 1 gravel 2
μg /
L
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
SECOND STEP: THERMAL VACUUM DISTILLATION TVD
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
Results of leaching test (EN 12457-2)
SECOND STEP: THERMAL VACUUM DISTILLATION TVD
Copper
0
50
100
150
200
250
Step 1 150 °C x 16h 200 °C x 6h 250 °C x 4h
μg/L
Nickel
0
10
20
30
40
50
60
Step 1 150 °C x 16h 200 °C x 6h 250 °C x 4h
μg/
L
• pH value too high (13) – conditioning step in water
• Chlorides
• Selenium
Identified problems:
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
BEFORE VTD
AFTER VTD (250 °CFOR 4 HOURS)
AFTER REHYDRATION
CONDITIONING STEP IN WATER FOR 7 DAYS
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
0
5
10
15
20
25
30
35
40
EFFUSIVEROCKS
LIMESTONE MIXEDAGGREGATE
SILTYLIMESTONE
BLAST FURNACESLAG
AC
V (%
)
TYPE OF AGGREGATE
MAPEI HPSS SYSTEM
CONCLUSIONS (1/2)
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
MAPEI HPSS TREATMENT WAS EFFECTIVE IN STABILIZING INORGANIC AND REMOVING VOC AND SVOC WHEN APPLIED TO MARINE SEDIMENT OF THE AUGUSTA HARBOUR (SICILY)
1.
HYDRATION RATE WAS NOT AFFECTED BY THE SEDIMENT, BUT CHEMICAL INTERACTION BETWEEN CEMENT AND SEDIMENT WERE EVIDENT (PORTLANDITE CONSUMPTION, MONOCARBONATE FORMATION AND MORPHOLOGICAL MODIFICATION OF THE HYDRATED MATRIX)
2.
THERMAL TREATMENT OF HYDRATED GRANULAR PRODUCTS HAD A POSITIVE EFFECT IN REDUCING THE LEACHING OF COPPER, NICKEL AND COBALT
3.
4. THERMAL TREATMENT OF HYDRATED GRANULAR PRODUCTS DECOMPOSED AFt AND AFm PHASES BUT REHYDRATION IN WATER PROMOTE THEIR REFORMATION
Remediation and Reuse of Contaminated Sediment: a new physical-chemical
process to the point
5.
CONCLUSIONS (2/2)
Pollutants mass balancea.
FUTURE DEVELOPMENTS
More complete tests for physical and mechanical properties and durability (total porosity, Los Angeles, Micro-Devall, alkali-silicareaction, freezing-thawing) will be performed
b.
pH dependent leaching tests and leaching column test c.
Speciation of mercuryd.
THERMAL TREATMENT OF HYDRATED GRANULAR PRODUCTS AT 250 °C DID NOT CAUSE THE DEGRADATION OF THE CEMENT MATRIX AND THE RESULTING PRODUCTS SHOWED GOOD MECHANICAL PROPERTIES FOR REUSE OPTION