+ All Categories
Home > Documents > Renewable Integration in the US - Regulatory … Regulatory Assistance Project 50 State Street,...

Renewable Integration in the US - Regulatory … Regulatory Assistance Project 50 State Street,...

Date post: 30-Mar-2019
Category:
Upload: lydung
View: 212 times
Download: 0 times
Share this document with a friend
52
The Regulatory Assistance Project 50 State Street, Suite 3 Montpelier, VT 05602 Phone: 802-223-8199 www.raponline.org Renewable Integration in the US Institute of Energy, Economics and Financial Analysis New York City Presented by Richard Sedano March 15, 2016
Transcript

The Regulatory Assistance Project 50 State Street, Suite 3Montpelier, VT 05602

Phone: 802-223-8199www.raponline.org

Renewable Integration in the US

Institute of Energy, Economics and Financial Analysis

New York City

Presented by Richard Sedano

March 15, 2016

Introducing RAP and Rich

• RAP is a non-profit organization providing technical and educational assistance to government officials on energy and environmental issues. RAP staff have extensive utility regulatory experience. RAP technical assistance to states is supported by US DOE, US EPA and foundations.

─ Richard Sedano directs RAP’s US Program. He was commissioner of the Vermont Department of Public Service from 1991-2001 and is an engineer.

2

VisionOne Path: An Integrated Grid

3

US Interconnections

Connections between interconnections are with DC lines that can be dispatched

4

Renewable Integration

• Technical analysis of Interconnections

5

Renewable Integration

• Technical analysis – green lights

• The question is no longer “is there a reliability threat from high penetration renewables?”

• The task is to maintain reliability while intensive renewables are deployed

─ Doable

─ Different

6

Question: where will RE come from?

• A few years ago: large scale Mid-continent wind dominant source

7

Where is the Biggest Wind?

8

Question: where will RE come from?

• A few years ago: large scale Mid-continent wind dominant source

• Emerging Deployment Rate Questions:

– Distribution deployment (especially solar PV)

– Offshore wind

– Storage

• Thermal (e.g. Grid Integrated Water Heaters, Ice)

• Electric (Battery, including Electric Vehicles)

9

Integration Challenges: Management, Policy alignment

• Wholesale/Transmission • Retail/Distribution

10

Wholesale/Transmission Topics

• RTO receptivity (regional transmission organization)

• Western Govs Association (WGA) measures

• Critical role of flexible resources and monetizing their value

• CREZ (competitive renewable energy zones)

• Siting (single state, multi-state)

– Utility owned facilities vs. independent transmission

• Interconnection

11

The Bulk Power System in Context

12

Bulk Power System• Transmits power from

generators at extra high voltage.

• The higher the voltage, the greater the amount of power transmitted

• Some capacity needs to be reserved in case something big fails

• Transformers step down the voltage for delivery to us.

13

RTOs/ISOs

ReliabilityMarketsPlanningCost Allocation

14

Regional Transmission Organizations

• Manage reliability

– Enough power -- adequacy

– Smooth operations -- stability

• Manage markets

– Energy

– Capacity

– Ancillary services

• Governance

15

Less revenue from energy Means

More revenue needed from capacity

& ancillary svc

Challenges to Institutions

• From Large Scale RE

– Congestion, low prices, curtailment risk

– Operating during low demand, high RE periods

– New Contingencies

– Forecasting resources not under operator control

• From small scale RE

– Control, forecasting variability, contingencies, replacing ancillary services

• New Transmission strengthens the system, but is costly, we would hope to avoid it

17

19

WGA Report: Nine Paths to Big RE

• Sub-hourly Dispatch and Scheduling

• Dynamic Transfers bet. Balancing Auth.

• Energy Imbalance Market

• Forecasting: Weather, Wind, Solar

• Geographic Diversity

• Reserves Management

• Demand Response

• Generation Dispatch

• Generation Flexibility

20

21

22

Tenth Western Initiative

• Expansion of California ISO

23

24

Gross/net demand comparison

25

Little demand for baseload, big demand for mid-merit, demand for peaking pretty much unchanged

Gross Demand Net Demand

After taking all wind and solar, this is the operator’s task

Flexible generation is just one piece of the puzzle

26

Source: IEA Energy Technology Perspectives 2014

Flexible generation is just one piece of the puzzle

27

Source: IEA Energy Technology Perspectives 2014

Principal Sources of Flexibility

• Customers

– Demand response

– Storage

• The Grid

– Load following capacity in thermal plants

– Storage

28

Demand Response

• Progress

• Much more to do

– Markets for flexibility (ramping, cycling)

• Ancillary Services

– Better planning to identify valuable times and locations

– Pricing to motivate customers

– Programs to connect services with customers and monetize benefits

– Technology to operationalize DR benefits

30

Eastern Wind Integration and Transmission

Study

20% wind with no offshore

32

Eastern Wind Integration and Transmission

Study

20% wind with

aggressive offshore

33

Eastern Wind Integration and Transmission

Study

30% wind with

aggressive offshore

34

Distribution/Retail Topics

• Distribution planning, platform, IDSO

─ IDSO: independent distribution system operator

• Different physical Upgrades needed

• Two-way/all-way operations

• Interconnection

• Teaching the Duck to Fly

37

The Distribution System in Context

38

Distribution System• Delivers power from

step down transformers• Collects power from

customers, feeds excess into the transmission system

• Interconnection assures safety in case of distribution outage

• Protection systems assure customer generation does not damage transformers

Typical Utility Distribution Planning

• Opaque process

– Prime Directives:

• Safety

• Do not drive rate increases

– Typical concerns:

• Address load growth

• Address end of life assets (replace before failure)

• Deferred maintenance is raising costs

• Now comes Lots of Distributed Generation

39

Fully under state PUC or local municipal/cooperative control

Updated Distribution Planning

• Integration Capacity

• Locational (nodal) values

• Forecasting Distributed Energy Resources

• Updated protection systems

– Especially to protect transformers at high DG, low demand times

• DG on both sides of the meter

• Demos, Deployment, Data

40

41PG&E’s Distribution Resources Plan (DRP) 19

Publishing Integration Capacity on PG&E RAM Map

PG&E analyzed all three

phase line sections for all

the 3,000+ distribution

circuits

• Results for approx.

102,000 line sections • Average of 34 line sections per

feeder

• Largest number of line sections for

one feeder was found to be 310

• Locational results

published by each DER

type

• Granular down to fuse

devices

• Initially colored by PV

Results • Line Section IC / Feeder IC

• Red, Amber, Green color

scheme with green being higher

capacities

An N-Way System

An N-Way

System

An N-Way System

An N-Way System

It’s Easy To Spot a Water Heater

43

44

Dramatic Impact on Net Load

Ten Ready Solutions to Accommodating Growing PV

• Teaching the Duck to Fly

– 2nd Edition emphasis on water

• Pumping

• Heating

• Ice

• Storage

46

47

48

Role of the Utility

• Delivery, yes

• A “Platform” provider

─ Enabling services, policy goals

• A distribution system operator (like an RTO?)

─ Should an independent entity, IDSO, do this?

• How does the utility of 2030 earn revenue and net income

─ Fewer energy/delivery sales, more services?

50

Perspective Question

• How should the integration challenge be framed?

─ How will new renewable sources fit into the existing grid?

─ New and more renewable sources are a given, so how will the grid adapt to them?

• Note that in the first, legacy assets and process are not assumed to change, while they are assumed to change in the second

51

Pivotal Question

• If PV takes off toward ubiquity…

─ Will we need that much more transmission?

52

Resources

• National Renewable Energy Lab

─ Renewable Energy Futures

─ Integration Studies, East and West

• Teaching the Duck to Fly

• Clean Energy Keeps the Lights On

• Designing DG Tariffs Well

• All the RTOs have deep websites

• EU Roadmap 2050

65

About RAP

The Regulatory Assistance Project (RAP) is a global, non-profit team of experts that focuses on the long-term economic and environmental sustainability of the power sector. RAP has deep expertise in regulatory and market policies that:

Promote economic efficiency Protect the environment Ensure system reliability Allocate system benefits fairly among all consumers

Learn more about RAP at www.raponline.org

[email protected]

Regional Relationships - ERCs

Regional Relationships - Interconnections

Connections between interconnections are with DC lines that can be dispatched

Regional Relationships – RTOs/ISOs

ReliabilityMarketsPlanningCost Allocation

Regional Relationships – Control Areas

AESO – Alberta Electric

System Operator

AZPS – Arizona Public

Service Company

AVA – Avista Corporation

BANC – Balancing

Authority of Northern CA

BPAT – Bonneville

Power Admin

Transmission

BCHA – British Columbia

Hydro Authority

CISO – California ISO

CFE – Comision Federal

de Electricidad

DEAA – Arlington Valley,

LLC

EPE – El Paso Electric

Company

GRMA – Gila River

Power , LP

GRIF – Griffith Energy,

LLC

IPCO – Idaho Power

Company

IID – Imperial Irrigation

District

LDWP – Los Angeles

Dept. of Water and

Power

GWA – NaturEner Power

Watch, LLC

NEVP – Nevada Power

Company

HGMA – New

Harquahala GenCo LLC

NWMT – NorthWestern

Company

PACE – PacifiCorp East

PACW – Pacificorp

West

PGE – Portland

General Electric

PSCO – Public Service

of Colorado

PNM – Public Service

of New Mexico

CHPD – Chelan County

PUD

DOPD – Douglas

County PUD

GCPD – Grant County

PUD

PSEI – Puget Sound

Energy

SRP – Salt River

Project

SCL – Seattle City Light

SPPC – Sierra Pacific

Power Company

TPWR – Tacoma Public

Utilities

TEPC – Tucson Electric

Power Co.

TIDC – Turlock

Irrigation District

WACM – Western

Colorado Missouri

Region

WALC – Western Lower

Colorado Region

WAUW –Western

Upper Great Plains

West

WWA – NaturEnur

Wind Watch, LLC


Recommended