Denver Marriott South at Park MeadowsLone Tree, CO
October 17-18, 2018
Renewable Planning and Operations Conference
Instructed by:Theodore (Ted) Burhans, Director, Emerging Technology and and Innovations, Tucson Electric Power
Robert Mechler, Director, T&D Project Development and Regional General Manager, Black & Veatch Corp. David Penney, Sr. Principal Engineer, Texas Reliability Entity
Byron Woertz, Manager, System Adequacy Planning, Western Electricity Coordinating Council Anna Lundin, Sr. Project Manager, Environmental; Business Class Lead, HDR
Cody Sickler, Engineer II (Power System Planning), Tri-State Generation & Transmission Association Elizabeth Waldren, P.E., Renewable Energy Consultant, Black & Veatch Corp.
Rod Fisher, Principal Project Manager, Gateway Transmission, PacifiCorp Jeffrey Plew, Director of Development, NextEra Energy Resources
RMEL ~ 6855 S. Havana, Ste 430 ~ Centennial, CO 80112 ~ (303) 865-5544 ~ FAX: (303) 865-5548 ~ www.RMEL.org
WiFi InformationNetwork: Marriott_ConferencePassword: RMEL2018
Wednesday, October 17,
20188:00-8:15 a.m.Welcome and Introductions
8:15-9:00 a.m.Renewable Planning for Generation Theodore (Ted) Burhans, Director, Emerging Technology and Innovations, Tucson Electric PowerTucson Electric Power has had continual year-over-year growth of solar DG adoption since the late 2000s. In addi-tion, it is on track to achieve 30% of its energy needs from renewable resources by 2030. TEP will present on what some of the acute sys-tem impacts and integration challenges are from variable generation; as well as what it sees as the long-term issues from high solar and wind deployment.
9:00-9:45 a.m.The New Power Grid: Obligations in the ERA of ChangeRobert Mechler, Director, T&D Project Development and Regional GM, Black & VeatchThe presentation will cover a brief history of the electric power industry from its earliest beginnings into the past 40 years where new market drivers have started to change how we see the power grid, but not neces-sarily changed our focus on having a reliable system. The presentation will draw some conclusions from the 2018 Strategic Directions Re-port on Electric Power which Black & Veatch assembles annually from a national survey of the electric power industry.
9:45-10:00 a.m.Networking Break
10:00-10:45 a.m.Operational Considerations for Integration of RenewablesDavid Penney, Sr. Principal Engineer, Texas Reliability EntityInverter-based renewable generation has much dif-ferent performance charac-teristics than synchronous machines. Integrating re-newables in large quantities into the bulk power system requires an understanding of how these inverter-based machines can affect system performance, including frequency control, primary frequency response, system inertia, ramping, voltage ride-through, and system dynamic performance. This presentation will present a high level view of how these issues are being addressed in ERCOT.
10:45-11:30 a.m.Renewable Integration and Other Reliability Assessments 2016-2019Byron Woertz, Manager, System Adequacy Planning, WECCWECC developed a study program for 2016-2017 to evaluate potential future reli-ability risks associated with the changing resource mix, possible changes to loads and transmission topology. The presentation will review the results of the 2016-2017 Study Program as well as the reliability assessment ap-proach and themes currently being considered for the 2018-2019 Study Program.
11:30 a.m. - 12:00 p.m.Morning Recap and Discussion
12:00-1:00 p.m.Networking Lunch
1:00-1:45 p.m.Identifying and Addressing Environmental Constraints in the Federal Permitting ProcessAnna Lundin, Sr. Project Manager, Environmental Business Class Lead, HDRAddressing a federal nexus in siting and permitting of renewable energy projects can often create unan-ticipated project delays and expenses. This presentation reviews lessons learned on how to move a project through the federal review process more efficiently by identifying and resolving potential environmental constraints early in the plan-ning process, based on the federal permitting processes of four recent renewable en-ergy generation projects in the Rocky Mountain region. The potential constraints to be reviewed include early identification of environmen-tal issues ranging from eagle take, sage-grouse impacts, and potential air space violations; development of reasonable alternatives to satisfy requirements of the National Environmental Policy Act (NEPA); and, addressing emerging and evolving federal regulations and associated case law as early as possible in the environmental permitting process, including the recent establishment of Executive Order 13807 and Department of Interior Secretarial Order 3355, both aimed at stream-lining federal infrastructure decisions.
1:45-2:30 p.m. San Luis Valley: Non-Transmission AlternativesCody Sickler, Engineer II (Power System Planning), Tri-State Generation & Transmission AssociationThis presentation will give an overview of Tri-State’s evalu-ation of Non-Transmission Alternatives to mitigate reliability issues in the San
Luis Valley (located in south-central Colorado). Under heavy loading, a loss of the 230kV line serving the valley results in voltage collapse and load shedding. The identified solution is to build a second 230kV line into the valley, however this is high cost project (60+ miles) and there are several land rights issues. As an alternative to a second 230kV line, this study evaluated the use of energy storage (with a focus on battery storage) to serve the load in the valley follow-ing an outage of the existing 230kV source. This covers battery sizing using a sta-tistical analysis of daily load and solar generation curves as well as a cost analysis.
2:30-2:45 p.m.Networking Break
2:45-3:00 p.m.Attendee AnnouncementsAny registered attendee is invited to make a short announcement on their com-pany, new products, tech-nologies or informational updates. Announcements may include showing a prod-uct sample but not videos and power point slides. Please limit announcement to 5 minutes.
3:00-4:30 p.m.Roundtable Discussion
Thursday October 18,
20188:00 a.m. - 8:45 a.m.Benefits of Pairing BESS with RenewablesElizabeth Waldren, P.E., Renewable Energy Consultant, Black & VeatchThis presentation will begin with an introduction of energy storage technologies including a brief overview of the technical concept, benefit and challenges of batteries: lithium-ion, flow,
CONFERENCE AgENdA*Visit www.RMEL.org for the latest topic and
speaker information.
Thank You RMEL Transmission Committee
Thank You RMEL Generation CommitteeCHAIR
Curt BrownAssociate Vice President,
Retrofit and Plant Betterment, Power Genera-
tion ServicesBlack & Veatch Corp.
VICE CHAIRTom Wos
Regulatory Program Administrator
Tri-State Generation and Transmission Assn.
David ArandaNewman Plant Manager
El Paso Electric Company
Matt FergusonVP, Power & Energy Section
ManagerHDR, Inc.
Jeff KruseCPS Energy
Sr. Director - Coal Gen-eration Operations │ Power
Generation
Gary RuhlManager, Fuels & Technical
ServicesOmaha Public Power District
Ed Seal Arizona Public Service
Richard ThreetDirector, Power Generation
PNM Resources
Kellen WaltersRegional Sales DirectorMitsubishi Hitachi Power Systems Americas, Inc.
and zinc based electro-chemistries. An update will be provided on recently announced and installed renewable + storage projects in the US. The presentation will explore benefits of pairing renewable genera-tion with batteries in terms of land use, transmission interconnection, and grid services / use cases.
8:45-9:30 a.m.PacifiCorp’s Energy Vision 2020Rod Fisher, Principal Project Manager, Gateway Transmission, PacifiCorpPacifiCorp’s Energy Vision 2020 is a $3 billion invest-ment in 1150 MW of new wind in Wyoming, repower-ing approximately 900 MW (648 MW in Wyoming) of existing wind projects, and constructing 191 miles of new high voltage transmission lines in Wyoming. These investments stem from the Company’s 2017 Integrated Resource Plan as the least risk, least cost option to serve our 1.9 million custom-ers into the future. These projects are planned to be in-service before December 31, 2020 to qualify for 100% of the Production Tax Credits.
9:30-9:45 a.m.Networking Break
9:45-10:30 a.m.Battery Storage: The “Swiss Army Knife” of the GridJeffrey Plew, Director of Development, NextEra Energy ResourcesAs battery costs continue to decline and energy markets evolve, opportunities to apply energy storage on the T&D grid in an economic manner are becoming more prevalent. As a flexible resource, energy storage can provide a variety of different services to the grid. This session will includes an over-view of the concept of “Use-Case Stacking” and where future opportunities might arise as a result of FERC or-ders 841 and 845, as well as a review of several different battery storage projects in operation that demonstrate use case stacking in both traditional vertical utilities as well as those in ISO markets.
10:30-11:30 a.m.Roundtable Discussion
CHAIRAngela Piner
VPHDR, Inc.
VICE CHAIRAna Bustamante
Director, T&D EngineeringUNS Energy Corporation
Scott BayerManaging Engineer,
Substation Relay Engineering
Austin Energy
Jedd FischerSenior Project Manager Nebraska Public Power
District
Chad KinsleyElectric T&D Engineering
Manager Black Hills Corporation
Chris KochManager, Substation
EngineeringKansas City Power & Light
Keith NixVP, Technical Services and
System ReliabilityTexas New Mexico Power
Mike PfeisterManager of Scheduling &
Reliability ServicesSRP
Chris PinkTechnical Services and Bulk
Systems Planning Mgr. Tri-State Generation & Trans-
mission Association
John QuintanaTransmission Asset
Maintenance ManagerWestern Area Power
Administration
CHAIRBill Galloway
Colorado Springs UtilitiesStandards Managing
Engineer
VICE CHAIRJoshua Jones
PacifiCorpDirector, Distribution
Standards and Engineering Publications
Andy AlexanderKansas City Power & Light
Manager, T&D Central Design
Steve DuranSRP
Engineer
Thank You RMEL Distribution Committee
Brent GerlingKansas City Power & Light
Engineer IV – Central Design
Travis JohnsonXcel Energy
Electric Standards Manager
Danny McReynoldsAustin Energy
Power System Engineer Sr.
Frank SandersonArizona Public Service
Manager, Metro Distribution Maintenance
RENEWABLE PLANNING AND OPERATIONS CONFERENCERenewable Integration: RMEL Member Best Practices, Case
Studies, Strategies and Experiences
Renewable Planning for Generation
Theodore (Ted) Burhans Director, Emerging Technology and Innovations
Tucson Electric Power
Tucson Electric PowerTED BURHANS
DIREC TOR, EMERGING TECHNOLOGY AND INNOVATIONRMEL , OC TOBER 17, 2018
Who & Why?
Tucson Electric Power• ~420,000 customer over
1,000 square miles• Vertically integrated• Balancing Authority for
TEP, UNSE, and others
Arizona Corporation Commission
Arizona Renewable Energy Standard• Annual renewable goals increase 1%
each year to 15% in 2025• 8% in 2018
• At least 30% of total from distributed generation
• One of the highest in the nation
TEP’s Commitment
• TEP plans to reach 30% by 2030
• Planned additions of 800-1000 MW over next 10 years
• 1,000 MW Winter / 2,500 MW Summer
TEP Utility-Scale Renewable Portfolio
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
2018 2019 2020 2021 2022 2023 2024 2025
GWh
Solar Wind
*Does not include DG
Diversifying TEP’s Resource Portfolio
36%
34%
30%
2014 2017 2023 2032
Energy MixCoal Natural Gas & Purch. Power Renewables & Energy Efficiency
20%
30%
16%
TEP and Renewables
• Roughly 350 MW Utility-Scale Wind and Solar
• Additional 355 MW over the next 2 ½ years
5
• 270 MW Residential and Commercial Distributed Generation (DG)– Additional ~70 MW in 2017
620 MW Total
Annual Installations
6
0
1,000
2,000
3,000
4,000
5,000
6,000
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Num
ber o
f Ins
talla
tions
Annual Residential Solar Installations
# of Installs In Progress
Installation Distribution
7
250
8
Acute Integration Issues
Solar Production
9
Operator Challenges From Intermittancy
10Causes NERC Area Control Error (Load Matching Generation) Havic
Renewable Energy Forecasting
11
Types of Forecasting• Advanced Numerical Modeling
• Prediction based on intense iterative modeling• Lots of computing power
• Satellite Imagery• Watching clouds and predicting cloud behavior (space down)
• Irradiance/Velocimetric Model• Watching clouds and predicting cloud behavior (ground up)
TEP Energy Storage Projects
• As of EOY 2016 TEP had ≈5% of the grid-scale energy storage capacity in U.S
• Provide frequency and voltage support for local distribution grid
1. NextEra Energy Resources• 10MW lithium nickel-manganese-cobalt
battery, 15 minute duration (2.5 MWh)• DeMoss-Petrie Substation
2. E.On Climate & Renewables• 10MW lithium Titanate oxide battery, 15
minute duration (2.5 MWh)• Combined with 2 MW Solar PV• U of A Science and Tech Park
Next Era’s Pima Energy Storage System (PESS)
E.On C&R’s Iron Horse Energy Storage System
EPRI – Resource Aggregation and Integration Network (Project RAIN)
• Purpose• The state of the industry with respect to Distributed Energy Resource (DER)
aggregation • The real-world capabilities of individual DER as well as groups• Potential for customer engagement in supporting the grid• Practical challenges of communication and coordination• Future strategies for applying DER management to TEP grid operations
• What is a DERMS?• Command translation among disparate protocols• Aggregates many resources into smaller set of control points• Reduces overall instructions group to a usable size• Optimizes commands fairly efficiently influence controlled devices
14
DERMS Architecture
15
About the Demonstration
Project Includes:• Commercial PV• Residential PV• Battery Storage• Grid-Interactive Water Heating• Smart Thermostats• Electric Vehicle Charging
About the Demonstration:• Field testing beginning Fall 2018• Results available Summer 2019
17
Grid-Scale Integration Issues
TEP’s Solar Coaster
-
200
400
600
800
1,000
1,200
1,400
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
Hour
30% Target
2030 Winter/Spring Day
Existing Solar (8% of 2030 Target)
15% of 2030 Target
Reduced Thermal Unit Minimums
Thermal Unit Ramp UpThermal Unit Ramp Down
No Peak Contribution
TEP Coal minimum(reduced with retirements)
Flexible Generation Resources
• Gila River Power Station• 2 Units Natural Gas Combined Cycle• Backstop for coal plant retirements• Low cost, efficient, fast-ramping resources• $300/kW purchase price
• Natural Gas Reciprocating Internal Combustion Engines (RICE)• Fast-ramping resource for renewable
integration (starts in 2 minutes, full load in 5 minutes)
• Low water consumption• ~56 million gallons to <1,000 gallons
• 200 MW online in 2019
Future…
• 100 MW Wind – COD mid-2020• NextEra Energy Resources• New Mexico wind• Existing Transmission Capacity
• 100 MW Solar + 30 MW Energy Storage – COD end of 2020• NextEra Energy Resources• Sub-$30 per MWh for solar energy• 4-hour duration storage
• Wind RFP• 150 MW New Mexico wind• ~47% capacity factor• Complements solar production
20
Future…
• Energy Storage Task Force• Identifying use cases for future storage up to ~70 MW• Solutions looking for problems• Batteries can do a lot of things, but only 1 or 2 really well
• Arizona Energy Modernization Plan• 80% Clean Resources by 2050• 3,000 MW of storage
• Batteries, pumped, compressed air, etc.• 2,000 pumped-storage hydro in development – Big Chino
• Biomass• 50,000 acres per year ~60 MW per year
• Electric Vehicles• Revamped Energy Efficiency
• NextGen Constitutional Ballot Initiative (Proposition 127)• 50% by 2030• 20% Distributed Generation carve-out
21
Operational Considerations for Integration of Renewables
David Penney Sr. Principal Engineer Texas Reliability Entity
David Penney, P.E., CISSPSenior Principal Engineer
Texas Reliability Entity, Inc.
Operational Considerations for Integration of Renewables
Meeting Title Date
2
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Agenda
● ERCOT Operational considerations for integration of renewable generation
Renewable generation growth in ERCOT Inertia Frequency Control and Frequency Response Ramping Voltage Ride Through Other Dynamic Issues
3
Introduction
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
● Separate electric interconnection located entirely within the state of Texas
● Operates as a single Balancing Authority and Reliability Coordinator area
● 25 million Texas customers● 90 percent of the state's electric load● Covers approximately 200,000 square miles● 46,500 miles of transmission lines● More than 600 generation units● All-time peak of 73,264 MW in July 2018● Energy-only market with diverse
membership
4
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Renewable Generation in ERCOT
As of Aug 1, 2018Wind - 21,190 MW
- 2,621 MW Coastal wind- 18,569 MW non-Coastal
Solar – 1,487 MW
Projected by 2020Wind – 28,457 MWSolar – 2,816 MWBased on signed IA’s with financial security posted
5
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Historical Renewable Generation Growth
6
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Historical Renewable Generation Growth
7
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
● ERCOT Operational considerations for integration of renewable generation
Renewable generation growth in ERCOT Inertia Frequency Control and Frequency Response Ramping Voltage Ride Through Other Dynamic Issues
Agenda
8
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Inertia Background
● System Inertia – tendency of the system to maintain 60hz during a disruption without any resource response
● Inertia of various system resources: Synchronous machines – mechanical motion, proper
speed Wind – mechanical motion, low and variable speed Solar – no mechanical motion
● In ERCOT, inertia can be correlated to load and wind gen: MW-Seconds or MW*s Inertia = function of synch machines & characteristics No. synch machines = function(load, wind gen)
9
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Inertia Background
● Power Converters allow wind generator speed and system frequency to be decoupled More efficient Most of modern wind turbines are Type 3 and 4
• Type 3 - Doubly Fed Induction Generator • Type 4 - Full Converter Generator
● Synthetic Inertia (other terms: emulated inertia, wind inertia …) Electronic Power Converters Almost instantaneous adjustment of electrical torque (a few cycles) Not natural inertial response – controlled vs uncontrolled If electronics lost, inertia is lost Actually a frequency response , Energy available is limited and
cannot be sustained, unless coupled with storage or load
10
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Inertia vs Renewable Generation %
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
0% 10% 20% 30% 40% 50% 60%
Renewable Generation as a % of Load vs Inertia (MW-sec) Critical Inertia level for ERCOT is approximately 100 GW-sec (noted by red dashed line)
Interpolating the slope of the regression line leads to the conclusion that ERCOT can manage 60-65% renewable penetration before the critical inertia level is reached
11
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Inertia vs Time of Year
Inertia (MW-Sec)360,000352,000344,000336,000328,000320,000312,000304,000296,000288,000280,000272,000264,000256,000248,000240,000232,000224,000216,000208,000200,000192,000184,000176,000168,000160,000152,000144,000136,000
Hour Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec0 1 8 2 1 3 6 .8 7 8 1 1 6 4 8 3 7 .4 2 1 1 6 6 0 0 3 .4 8 8 1 1 7 0 0 6 1 .9 1 7 2 1 8 7 4 3 1 .2 4 8 1 2 4 4 6 8 7 .1 8 0 7 2 7 6 8 2 9 .9 6 5 2 7 4 6 6 5 .0 8 1 4 2 2 2 4 7 3 .2 9 8 1 1 8 8 0 9 6 .9 2 4 2 1 7 1 9 9 3 .7 7 1 4 2 0 6 3 0 8 .7 5 8 5
1 1 8 1 1 7 8 .1 0 3 9 1 6 3 1 5 1 .2 4 0 3 1 6 3 8 9 1 .9 8 1 7 1 6 4 3 7 6 .0 5 1 2 1 8 3 2 7 7 .5 4 8 2 4 0 1 2 3 .9 6 0 4 2 7 1 9 9 3 .9 0 9 8 2 7 1 0 9 3 .4 8 0 4 2 1 9 0 1 8 .9 4 6 6 1 8 5 6 3 2 .1 2 3 9 1 7 0 5 5 3 .6 0 3 2 0 4 9 9 4 .5 7 2 3
2 1 8 2 0 7 1 .2 3 4 3 1 6 3 8 0 0 .4 9 0 4 1 6 3 9 3 4 .1 8 4 9 1 6 4 3 3 2 .9 7 4 7 1 8 3 2 5 2 .5 8 7 5 2 3 9 4 8 3 .3 4 7 6 2 7 1 5 3 1 .7 5 9 2 7 0 7 1 4 .5 9 5 6 2 1 8 8 0 0 .3 9 0 2 1 8 5 8 0 4 .5 9 0 4 1 7 0 6 6 1 .1 5 8 3 2 0 5 9 6 3 .4 1 6 6
3 1 8 4 4 3 1 .1 9 6 6 1 6 5 7 1 9 .8 4 6 1 1 6 6 0 4 2 .6 4 6 1 1 6 5 5 7 3 .0 3 6 1 1 8 3 9 9 0 .5 0 9 4 2 3 9 6 5 5 .4 6 0 4 2 7 1 3 2 7 .4 3 2 2 7 0 9 5 3 .0 1 4 9 2 1 8 9 5 6 .6 3 4 5 1 8 6 4 3 6 .7 9 4 8 1 7 2 1 9 6 .3 6 3 1 2 0 7 8 8 7 .2 3 5 5
4 1 9 0 5 5 7 .0 4 5 1 1 7 2 2 7 2 .5 6 4 5 1 7 1 9 4 7 .7 2 8 1 6 9 1 7 9 .5 3 4 1 1 8 6 6 0 2 .6 3 9 7 2 4 1 3 3 9 .2 8 0 7 2 7 1 5 6 3 .4 3 4 6 2 7 1 5 7 4 .0 8 7 2 2 1 0 0 7 .4 2 7 1 1 8 9 5 6 9 .1 9 2 1 1 7 6 0 6 1 .4 7 6 9 2 1 3 8 0 2 .0 9 8 3
5 2 0 1 0 1 9 .0 4 5 4 1 8 5 5 6 3 .0 2 9 6 1 8 2 4 9 4 .7 9 8 7 1 7 7 1 6 1 .7 6 6 9 1 9 5 0 6 9 .9 6 2 7 2 4 8 2 0 0 .7 5 4 7 2 7 3 7 1 8 .2 5 1 5 2 7 3 4 0 7 .2 7 7 7 2 2 5 6 5 4 .3 0 3 1 9 8 3 0 4 .7 8 9 5 1 8 6 5 2 5 .5 0 9 6 2 2 5 5 3 7 .5 8 9 4
6 2 0 5 7 4 1 .3 2 3 6 1 9 2 7 2 5 .2 5 2 3 1 8 9 3 6 2 .8 7 2 8 1 8 2 2 4 6 .2 4 0 5 2 0 3 9 5 2 .7 6 4 1 2 5 7 0 0 3 .3 7 6 2 7 8 4 8 5 .0 5 1 7 2 7 5 7 9 6 .1 7 1 4 2 2 9 8 9 3 .2 0 4 1 2 0 4 2 5 9 .8 7 5 9 1 9 3 1 3 2 .1 6 2 2 2 3 0 6 9 1 .0 8 6 9
7 2 0 7 3 1 6 .8 9 7 7 1 9 5 5 5 7 .9 8 6 5 1 9 3 3 4 1 .9 0 0 2 1 8 7 3 8 5 .9 0 8 4 2 1 0 5 0 9 .5 8 2 5 2 6 5 2 2 7 .7 6 4 8 2 8 5 2 6 3 .0 2 3 8 2 8 1 1 1 7 .1 3 2 8 2 3 6 3 6 9 .0 6 0 6 2 0 8 8 3 0 .3 6 3 1 1 9 7 3 1 7 .5 8 2 1 2 3 2 7 1 4 .6 3 1 9
8 2 0 8 8 2 5 .1 1 6 3 1 9 8 4 1 9 .1 4 4 2 1 9 7 5 1 2 .5 4 4 7 1 9 3 4 2 9 .7 1 7 9 2 1 8 5 3 4 .3 4 8 6 2 7 7 0 3 6 .7 3 6 8 2 9 5 5 7 1 .7 6 4 2 9 0 2 8 1 .7 6 1 9 2 4 7 2 0 9 .9 2 0 8 2 1 7 4 2 5 .2 6 2 1 2 0 1 4 7 7 .1 5 5 5 2 3 4 4 3 1 .4 8 1 3
9 2 1 0 1 6 9 .1 2 0 5 2 0 1 0 5 8 .0 5 0 5 2 0 1 3 1 6 .5 7 8 7 1 9 9 6 2 3 .7 2 5 9 2 2 7 2 0 8 .0 7 0 5 2 8 9 7 7 9 .6 4 3 7 3 0 9 0 1 6 .9 6 2 2 3 0 2 0 9 3 .1 6 9 3 2 6 0 9 8 2 .7 2 1 4 2 2 4 7 9 0 .2 8 8 6 2 0 6 0 3 2 .0 4 1 6 2 3 5 8 4 7 .5 6 8 7
10 2 1 0 5 6 3 .5 9 0 1 2 0 2 7 5 4 .6 2 7 2 2 0 6 3 0 8 .4 8 0 4 2 0 5 8 8 9 .5 2 2 4 2 3 6 3 8 6 .8 5 6 6 3 0 0 0 3 9 .5 6 4 6 3 2 1 6 3 2 .4 8 0 5 3 1 2 2 7 8 .1 4 2 3 2 7 7 2 9 9 .4 5 8 3 2 3 2 4 4 8 .5 6 8 4 2 1 0 3 5 6 .0 7 7 2 3 7 0 8 7 .1 3 7 4
11 2 0 9 6 1 8 .2 9 2 0 4 1 2 2 .1 9 3 1 2 0 9 2 6 0 .6 1 6 1 2 1 1 4 3 4 .9 2 2 9 2 4 4 4 3 5 .3 4 8 8 3 0 7 6 3 3 .6 1 4 6 3 3 1 2 2 8 .7 2 2 7 3 1 9 3 1 7 .7 4 5 8 2 8 7 1 6 3 .5 9 0 9 2 3 8 3 7 0 .9 2 1 3 6 0 2 .5 8 2 2 2 3 7 0 1 4 .9 5 0 1
12 2 0 9 1 9 3 .8 0 4 7 2 0 4 7 4 1 .1 7 7 1 2 1 1 2 9 2 .5 1 5 5 2 1 6 1 7 3 .7 0 5 5 2 4 9 3 5 4 .5 8 2 7 3 1 2 7 7 1 .4 8 7 7 3 3 8 1 9 0 .8 2 2 7 3 2 4 0 3 7 .1 3 0 4 2 9 3 7 6 4 .7 0 7 6 2 4 2 9 3 5 .4 1 9 6 2 1 6 1 5 3 .2 7 5 3 2 3 6 5 3 0 .9 2 3 8
13 2 0 9 4 8 2 .6 0 6 1 2 0 5 1 7 7 .7 2 6 1 2 1 3 0 8 4 .5 3 8 1 2 1 8 7 5 7 .3 7 4 9 2 5 2 1 0 6 .8 8 4 5 3 1 6 1 5 3 .4 5 5 5 3 4 2 3 9 3 .3 6 4 2 3 2 7 4 0 2 .1 1 6 2 9 7 2 7 7 .5 3 0 5 2 4 6 7 2 2 .1 7 8 3 2 1 7 8 8 8 .0 0 6 3 2 3 6 5 3 8 .0 3 9 4
14 2 1 0 6 6 4 .8 7 7 8 2 0 6 2 9 7 .1 6 6 1 2 1 3 6 7 3 .3 0 5 9 2 2 0 6 1 1 .0 5 6 7 2 5 4 6 8 7 .1 1 2 6 3 1 8 2 8 6 .0 4 5 2 3 4 4 3 9 1 .1 3 1 8 3 2 9 8 0 4 .7 0 3 9 2 9 9 2 9 5 .8 7 0 1 2 4 8 8 5 6 .5 4 7 2 1 9 1 3 5 .4 4 7 2 3 7 5 2 7 .4 2 2 8
15 2 1 2 3 4 4 .8 4 5 9 2 0 6 9 6 2 .9 5 0 2 2 1 3 5 0 7 .0 1 5 4 2 2 2 1 8 3 .6 9 0 7 2 5 6 0 4 2 .7 9 1 5 3 1 9 4 7 4 .5 5 0 5 3 4 5 5 4 3 .5 7 2 6 3 3 0 9 0 5 .2 0 3 8 3 0 0 3 6 1 .2 8 5 6 2 4 9 6 5 8 .7 9 3 4 2 1 9 9 3 2 .3 0 4 1 2 3 9 4 1 5 .9 3 4 2
16 2 1 3 6 2 8 .6 0 2 2 0 7 1 7 4 .2 5 9 2 2 1 3 8 3 9 .5 8 5 8 2 2 2 6 6 6 .9 8 6 7 2 5 6 8 5 5 .7 4 8 7 3 1 9 5 0 7 .5 6 3 7 3 4 5 6 1 1 .4 4 5 8 3 3 1 1 4 7 .1 0 1 8 3 0 0 5 4 7 .5 3 2 2 2 5 0 1 6 7 .8 3 1 3 2 2 0 3 5 7 .8 6 9 2 4 0 6 6 1 .7 4 7 7
17 2 1 4 1 4 4 .3 6 7 5 2 0 7 5 4 3 .4 0 8 2 1 3 8 2 7 .8 6 2 1 2 2 2 4 1 1 .5 8 0 8 2 5 6 3 7 9 .5 3 9 3 1 8 3 7 9 .7 5 9 1 3 4 4 3 2 6 .4 9 2 2 3 3 0 0 2 5 .0 5 7 6 2 9 9 3 8 6 .9 5 6 2 2 4 9 9 8 4 .7 5 8 5 2 2 0 6 1 9 .1 7 0 1 2 4 1 3 8 9 .6 9 9 8
18 2 1 3 9 6 1 .4 8 3 4 2 0 7 5 6 2 .3 1 1 2 1 3 0 3 3 .3 1 1 2 2 1 6 1 2 .7 4 8 2 5 3 8 9 7 .4 0 9 2 3 1 4 8 0 1 .5 7 9 8 3 4 0 0 9 2 .1 2 8 5 3 2 6 7 0 1 .6 6 2 9 2 9 6 1 0 9 .3 1 6 7 2 4 7 9 5 1 .6 6 2 9 2 1 9 9 5 4 .6 9 9 4 2 4 1 9 4 3 .8 7 5
19 2 1 1 3 6 2 .9 8 4 2 2 0 4 9 1 9 .3 8 5 3 2 1 1 0 5 2 .8 2 3 2 2 1 9 1 1 3 .4 3 9 5 2 4 9 3 9 5 .9 3 7 1 3 0 9 1 9 6 .5 0 6 8 3 3 4 4 7 0 .9 1 8 3 3 2 2 6 8 8 .6 9 6 7 2 9 0 2 1 9 .1 6 9 6 2 4 4 0 1 7 .9 8 7 2 2 1 5 5 2 3 .0 8 3 2 2 4 0 2 4 8 .5 9 9 8
20 2 0 6 9 2 3 .4 6 4 3 1 9 8 6 8 2 .5 8 7 3 2 0 7 6 8 0 .6 1 5 3 2 1 7 7 5 1 .9 4 9 9 2 4 5 1 6 0 .6 1 7 8 3 0 2 1 9 3 .7 6 9 6 3 2 8 0 3 8 .8 7 2 2 3 1 8 0 2 9 .7 5 3 1 2 8 3 5 3 2 .0 4 0 3 2 3 7 0 2 1 .7 7 1 5 2 0 7 7 8 3 .2 3 7 4 2 3 6 9 2 4 .9 0 9 3
21 2 0 2 0 4 7 .2 1 4 1 9 2 1 7 7 .7 5 4 2 2 0 0 0 8 5 .3 3 0 9 2 1 1 2 6 9 .4 7 4 4 2 3 8 1 2 0 .3 2 2 1 2 9 3 1 3 4 .2 3 3 4 3 2 0 0 1 7 .4 3 3 2 3 0 9 8 8 1 .6 6 7 7 2 6 9 6 4 0 .4 6 8 4 2 2 6 5 2 9 .5 2 7 4 1 9 9 6 6 4 .4 5 9 2 2 3 2 3 8 3 .0 8 8 4
22 1 9 3 1 8 9 .1 7 2 7 1 8 0 2 2 2 .0 3 1 5 1 8 5 0 7 5 .0 6 6 8 1 9 6 4 6 6 .2 6 1 2 1 9 5 3 0 .3 8 6 7 2 7 6 2 9 5 .0 4 0 5 3 0 5 4 1 6 .9 3 0 2 2 9 5 6 4 0 .4 1 8 6 2 5 0 0 7 4 .0 1 8 2 2 1 1 8 5 4 .0 0 2 7 1 8 7 5 4 0 .8 3 3 7 2 2 4 4 8 4 .2 8 4 2
23 1 8 6 8 5 8 .6 2 3 2 1 7 0 7 6 9 .4 2 7 2 1 7 3 8 0 0 .7 8 2 8 1 8 3 5 7 6 .8 1 3 3 2 0 0 9 3 9 .2 5 6 7 2 5 7 7 7 7 .7 7 3 1 2 8 8 8 4 9 .8 1 0 4 2 8 2 0 6 2 .2 7 4 1 2 3 1 8 7 7 .1 2 5 1 1 9 7 6 2 5 .4 3 2 5 1 7 8 1 9 0 .7 9 4 5 2 1 6 6 2 1 .2 3 8 4
A heat map graph of 2017 inertia levels shows the weakest inertia time periods are HE 01, 02, 03, and 04 during the shoulder months of February, March, April, and November.
12
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Monitoring/Maintaining Critical Inertia (Day Ahead)
Hour Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Reserves1 2 9 2 0 3 2 0 0 3 1 5 0 3 1 5 0 2 9 5 7 2 5 6 5 2 5 0 7 2 5 0 7 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5 32002 2 9 2 0 3 2 0 0 3 1 5 0 3 1 5 0 2 9 5 7 2 5 6 5 2 5 0 7 2 5 0 7 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5
3 2 9 2 0 3 1 5 0 3 1 5 0 3 1 5 0 3 0 0 6 2 6 1 4 2 5 2 8 2 5 2 8 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5 31004 2 9 2 0 3 1 5 0 3 1 5 0 3 1 5 0 3 0 0 6 2 6 1 4 2 5 2 8 2 5 2 8 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5
5 2 9 2 0 3 1 5 0 3 1 5 0 3 1 5 0 3 0 0 6 2 6 1 4 2 5 2 8 2 5 2 8 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5
6 2 9 2 0 3 1 5 0 3 1 5 0 3 1 5 0 3 0 0 6 2 6 1 4 2 5 2 8 2 5 2 8 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5 30007 2 7 7 2 2 9 5 7 2 9 5 7 3 0 0 6 2 8 2 3 2 5 2 8 2 4 4 0 2 4 4 0 2 6 1 4 2 8 4 2 2 8 7 2 2 9 0 5
8 2 7 7 2 2 9 5 7 2 9 5 7 3 0 0 6 2 8 2 3 2 5 2 8 2 4 4 0 2 4 4 0 2 6 1 4 2 8 4 2 2 8 7 2 2 9 0 5 29009 2 7 7 2 2 9 5 7 2 9 5 7 3 0 0 6 2 8 2 3 2 5 2 8 2 4 4 0 2 4 4 0 2 6 1 4 2 8 4 2 2 8 7 2 2 9 0 5
10 2 7 7 2 2 9 5 7 2 9 5 7 3 0 0 6 2 8 2 3 2 5 2 8 2 4 4 0 2 4 4 0 2 6 1 4 2 8 4 2 2 8 7 2 2 9 0 5
11 2 7 7 2 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 0 5 2 3 0 0 2 3 7 3 2 4 4 0 2 6 6 5 2 8 4 2 2 8 4 2 280012 2 7 7 2 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 0 5 2 3 0 0 2 3 7 3 2 4 4 0 2 6 6 5 2 8 4 2 2 8 4 2
13 2 7 7 2 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 0 5 2 3 0 0 2 3 7 3 2 4 4 0 2 6 6 5 2 8 4 2 2 8 4 2 270014 2 7 7 2 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 0 5 2 3 0 0 2 3 7 3 2 4 4 0 2 6 6 5 2 8 4 2 2 8 4 2
15 2 7 7 2 2 9 5 7 2 9 1 7 2 8 6 6 2 5 9 5 2 3 7 3 2 3 0 0 2 3 4 2 2 4 0 5 2 6 1 4 2 8 4 2 2 8 4 2
16 2 7 7 2 2 9 5 7 2 9 1 7 2 8 6 6 2 5 9 5 2 3 7 3 2 3 0 0 2 3 4 2 2 4 0 5 2 6 1 4 2 8 4 2 2 8 4 2 260017 2 7 7 2 2 9 5 7 2 9 1 7 2 8 6 6 2 5 9 5 2 3 7 3 2 3 0 0 2 3 4 2 2 4 0 5 2 6 1 4 2 8 4 2 2 8 4 2
18 2 7 7 2 2 9 5 7 2 9 1 7 2 8 6 6 2 5 9 5 2 3 7 3 2 3 0 0 2 3 4 2 2 4 0 5 2 6 1 4 2 8 4 2 2 8 4 2 250019 2 8 1 6 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 4 1 2 3 4 2 2 4 0 5 2 4 6 6 2 7 4 7 2 8 4 2 2 8 4 2
20 2 8 1 6 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 4 1 2 3 4 2 2 4 0 5 2 4 6 6 2 7 4 7 2 8 4 2 2 8 4 2
21 2 8 1 6 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 4 1 2 3 4 2 2 4 0 5 2 4 6 6 2 7 4 7 2 8 4 2 2 8 4 2 240022 2 8 1 6 2 9 5 7 2 9 1 7 2 9 1 7 2 6 5 4 2 4 4 1 2 3 4 2 2 4 0 5 2 4 6 6 2 7 4 7 2 8 4 2 2 8 4 2
23 2 9 2 0 3 2 0 0 3 1 5 0 3 1 5 0 2 9 5 7 2 5 6 5 2 5 0 7 2 5 0 7 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5
24 2 9 2 0 3 2 0 0 3 1 5 0 3 1 5 0 2 9 5 7 2 5 6 5 2 5 0 7 2 5 0 7 2 6 6 5 2 9 0 5 2 9 8 5 2 9 8 5 2300
● Inertia levels forecasted in Day-Ahead studies● Additional frequency-responsive generation reserves are procured if low inertia
levels are forecasted
13
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Monitoring/Maintaining Critical Inertia (Real-Time)
● Critical Inertia level for ERCOT ~ 100 GW-sec● Visual alarms when inertia gets close to critical
120 GW-sec >= Inertia Normal 120 GW-sec > Inertia >= 110 GW-s Yellow 110 GW-sec > Inertia >= 100 GW-s Orange 100 GW-sec < Inertia Red
● Take Action when system inertia < 105 GW-sec Possible Actions:
• Deploy Non-Spinning Reserve from Offline Generation Resources♦ ~4000 MW-sec inertia increment
• Deploy Quick Start Resources♦ ~6000 MW-sec inertia increment
• Order generation on-line that can be turned on within one hour
14
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
● ERCOT Operational considerations for integration of renewable generation
Renewable generation growth in ERCOT Inertia Frequency Control and Frequency Response Ramping Voltage Ride Through Other Dynamic Issues
Agenda
15
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Frequency Control
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
59.9
59.9
0559
.91
59.9
1559
.92
59.9
2559
.93
59.9
3559
.94
59.9
4559
.95
59.9
5559
.96
59.9
6559
.97
59.9
7559
.98
59.9
8559
.99
59.9
95 6060
.005
60.0
160
.015
60.0
260
.025
60.0
360
.035
60.0
460
.045
60.0
560
.055
60.0
660
.065
60.0
760
.075
60.0
860
.085
60.0
960
.095
60.1
2011 2017ERCOT Frequency Profile
0.017 Hz deadband
• In 2011, required maximum governor dead-band was 0.034 Hz
• Regional standard BAL-001-TRE went into effect 4/2015 and required all resources to have active governor dead-bands of 0.017 Hz
• Wind resources with active governor control rarely provide frequency response for low frequencies, but respond very well during high frequency deviations
16
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Inertial Effect
Initial rate of change of frequency (RoCoF) prior to any resource response is solely a function of inertia
Source: Inertia Basic Concepts and Impacts on the ERCOT Grid, ERCOT Report, 2018
17
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Inertial Effect
Higher Inertia
Lower Inertia
Source: Inertia Basic Concepts and Impacts on the ERCOT Grid, ERCOT Report, 2018
18
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Modeled Inertia Effect on Frequency Response
Source: Frequency Response Study on ERCOT under High Photovoltaic Penetration Conditions, 2017, University of Tennessee-Knoxville
ERCOT frequency response after 1129MW generator trip
Metric Base case
20% 40% 60%
RoCoF (mHz/s) 100 110 140 200
Nadir (Hz) 59.67 59.62 59.44 59.26
Settling time (s) 15 20 23 25
Settling frequency (Hz)
59.77 59.71 59.55 59.43
Renewable Penetration
19
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Measured RoCoF vs Inertia During Unit Trips
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
0 50,000 100,000 150,000 200,000 250,000 300,000 350,000 400,000 450,000
Rate of Change of Frequency (RocoF) per GW vs Inertia (MW-s)
RoCo
F/GW
Inertia
Actual measured RoCoF vs Inertia during ERCOT large generator trips
20
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
● ERCOT Operational considerations for integration of renewable generation
Renewable generation growth in ERCOT Inertia Frequency Control and Frequency Response Ramping Voltage Ride Through Other Dynamic Issues
Agenda
21
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Wind vs Load
• Wind generation output typically moves in opposite direction from load (summer peak)• Balancing load & generation during morning/evening ramp periods becomes critical
22
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Ramping - Wind
-12,000
-9,000
-6,000
-3,000
0
3,000
6,000
9,000
12,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Wind Ramping Example: July 22, 2018
Net Load Ramp Load Net Load Wind
Wind/Ramp MWLoad MW • Net Load up-ramp exceeds 6,000 MW per hour during morning load ramp
• Net Load down-ramp exceeds 6,000 MW per hour during evening hours
• Synchronous generation must be able to respond to these up & down ramps
23
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Ramping - Solar
-1,000
-750
-500
-250
0
250
500
750
1,000
1,250
1,500
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Solar Ramping Example: April 15, 2018
Solar Ramp Load Net Load Solar
Load MW Solar/Ramp MW • Solar ramp more predictable than wind
• Ramp rate can approach 50% or more of total capacity in the hour
24
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Large Ramp Alert System
• ERCOT Large Ramp Alert System (LRAS) forecasting tool for wind ramping
• Estimates probability for different ramp rates in 15-minute, 1-hour, and 3-hour horizons
25
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
● ERCOT Operational considerations for integration of renewable generation
Renewable generation growth in ERCOT Inertia Frequency Control and Frequency Response Ramping Voltage Ride Through Other Dynamic Issues
Agenda
26
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Voltage Ride Through
6400
6750
7100
7450
7800
59.85
59.9
59.95
60
60.05
4:55
4:56
4:57
4:58
4:59
5:00
5:01
5:02
5:03
5:04
5:05
5:06
5:07
5:08
5:09
5:10
Wind MW Loss and Frequency
Frequency Total Wind
• A 345 kV line fault caused a single-phase low voltage excursion• Lost 343 MW of wind generation across seven wind plants• PMU data - voltage oscillated between 0.78 and 1.07 per-unit for <0.5
seconds
27
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Voltage Ride Through
2900
3050
3200
3350
3500
3650
3800
59.9
59.925
59.95
59.975
60
60.025
60.05
15:0
8
15:0
9
15:1
0
15:1
1
15:1
2
15:1
3
15:1
4
15:1
5
15:1
6
15:1
7
15:1
8
15:1
9
15:2
0
15:2
1
15:2
2
15:2
3
Wind MW Loss and Frequency
Frequency Total Wind
• A 138 kV line fault caused a low voltage excursion• Lost 404 MW of wind generation across six wind plants• Five wind plants were connected to the 345 kV transmission grid• PMU data from the 345 kV system - voltage oscillated between 0.84 and 1.09
per-unit for ~ 0.2 seconds
28
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Voltage Ride Through Issues Noted
• Failure of Uninterruptible Power Supplies Clean power for critical aux controls: blade pitch, nacelle yaw, and brake control Power for SCADA, metering, and other controls Battery failures Environment-related (humidity, temperature, vibration) circuit board failures
• Failed Crowbar Components• “Smart Crowbar” hardware – not functioning properly
Without: ride-through voltage excursions limited to +/-10% of nom voltage• Ride-through Tolerance - insufficient for the magnitude of the voltage disturbance
capabilities ranged from: • Less than 0.80 per-unit for 0.08 to 0.2 seconds • Between 0.80 and 0.90 per-unit for up to 60 seconds
• NERC Lesson Learned LL20170701: Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System
29
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
● ERCOT Operational considerations for integration of renewable generation
Renewable generation growth in ERCOT Inertia Frequency Control and Frequency Response Ramping Voltage Ride Through Dynamic Issues
Agenda
30
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Dynamic Effects – Sub Synchronous Resonance
Aug 24, 2017• Sub-Synchronous oscillations
started after WGRs became radially connected to series capacitors
• Oscillation frequency: ~ 25.6 Hz
Source: ERCOT, South Texas SSR, Report to Reliability Operations Subcommittee, May 2018
Sept 27, 2017• Sub-Synchronous oscillations
started after WGRs became radially connected to series capacitors
• Oscillation frequency: ~22.5 Hz
31
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Dynamic Effects Lessons Learned
• Interconnecting wind units at or near series capacitors requires detailed modeling and can pose reliability issues
• SSR/SSCI events were not easily observable Appeared to be a simple relay trip Requires high resolution measurements to detect PMUs are not suitable for detecting SSCI events
• Reproducing the disturbance requires detailed analysis Model adequacy and assumptions are critical
• Controller tuning is inherently difficult Wide variety of grid conditions and dispatch conditions May require controller re-design (not just a parameter change) Type III (DFIG) wind turbines - tend to be more vulnerable Rely more heavily on damping controllers
32
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Summary
• The impact of integrating large amounts of renewable generation into the grid is becoming better understood
• The effect of lower system inertia can be mitigated by: Studies to determine the critical inertia level Procedures to take action when inertia approaches the critical level
• Ramping issues can be mitigated by: Forecasting tools to predict ramping limitations Procedures to take action in advance of large system ramps
• Ride-through and dynamic issues can be understood by: Detailed modeling of inverters and controllers High resolution measurement devices Generation interconnection requirements
33
Questions?
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
34
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Appendix
35
0%
10%
20%
30%
40%
50%
60%
Jan-
08
Apr-
08
Jul-0
8
Oct
-08
Jan-
09
Apr-
09
Jul-0
9
Oct
-09
Jan-
10
Apr-
10
Jul-1
0
Oct
-10
Jan-
11
Apr-
11
Jul-1
1
Oct
-11
Jan-
12
Apr-
12
Jul-1
2
Oct
-12
Jan-
13
Apr-
13
Jul-1
3
Oct
-13
Jan-
14
Apr-
14
Jul-1
4
Oct
-14
Jan-
15
Apr-
15
Jul-1
5
Oct
-15
Jan-
16
Apr-
16
Jul-1
6
Oct
-16
Jan-
17
Apr-
17
Jul-1
7
Oct
-17
Jan-
18
Apr-
18
Jul-1
8
Fuel Type as % of Total Energy
Gas Coal Nuclear Renewable12 per. Mov. Avg. (Gas) 12 per. Mov. Avg. (Coal) 12 per. Mov. Avg. (Nuclear) 12 per. Mov. Avg. (Renewable)
Changes in Overall ERCOT Generation Mix
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Jan 2018: Retirement of 4400 MW of coal generation
36
Historical Inertia
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
450,000
ERCOT System Inertia
37
Critical Inertia Concept
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Source: Inertia Basic Concepts and Impacts on the ERCOT Grid, ERCOT Report, 2018
Currently, the Critical Inertia Level for ERCOT is approximately 94 GW-s (based on current operations and response characteristics of current resources)
• Simulation results have shown that below this level RoCoF is high enough that frequency would drop below 59.3 Hz for two nuclear units tripping
• Simulation results have also shown wide-area voltage oscillations at inertia below this level
38
Critical Inertia Concept
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Source: Inertia Basic Concepts and Impacts on the ERCOT Grid, ERCOT Report, 2018
39
Inertia from Synchronous Machines
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
• The amount of inertia present in a system depends on the number and size of on-line generators and motor loads synchronized to the system. It may be difficult to account for motor loads as this information typically is not available to the system operator; therefore, inertial response of motor load is usually lumped into load damping constant1.
• For any hour, synchronous inertial response (SIR) from generators (Msys) is calculated as follows:
sys=Σ ∗ VA
where I is the set of on-line synchronous generators or condensers; MVAi is MVA base of on-line synchronous generator or synchronous condenser I; and Hi is the inertia constant for an on-line generator or synchronous condenser i in a system (in seconds on machine MVA base, MVAi).
40
Inertia from Synchronous Machines
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
MVA base range Inertia Constant (H)
Inertial responsecontribution range
(H*MVA base)Nuclear 1410 – 1504 3.8 – 4.34 5344 – 6530
Coal 194 – 1120 2.9 – 4.5 863 – 3158
Combustion Turbine 7 – 235 1 – 12.5 22 – 1288
Gas-Steam 14 – 887 1 – 5.4 13 – 2216
Combined Cycle 25 – 1433 1.1 – 9 97 – 8765
Hydro 9 – 36 2 – 3 19 – 1133
Reciprocating Engine
10 - 70 1.1 – 2.1 13 – 97
Wind - 0 0
Solar PV - 0 0
Source: Inertia Basic Concepts and Impacts on the ERCOT Grid, ERCOT Report, 2018
41
Synthetic Inertia from Wind Generators
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Source: G.C. Tarnowski, P. C. Kajaer, P.E. Sorensen, J. Ostergaard Variable Speed Wind Turbines Capability for Temporary Over-Production, IEEE PES GM 2009
● As wind turbine extracts available power from wind, it is possible to generate a temporary active power overproduction. This temporary active power overproduction mainly depends on rotational speed variations, drive train inertia and wind speed conditions.
42
Synthetic Inertia from Wind Generators
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Source: Inertia Basic Concepts and Impacts on the ERCOT Grid, ERCOT Report, 2018
● Performance close to nominal wind speed is most demanding for the recovery phase
43
Synthetic Inertia from Battery Storage
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
0
8
16
24
32
59.85
59.9
59.95
60
60.05
13:0
5
13:0
6
13:0
7
13:0
8
13:0
9
13:1
0
13:1
1
13:1
2
13:1
3
13:1
4
13:1
5
13:1
6
13:1
7
13:1
8
13:1
9
13:2
0
30 MW Battery Response to 800 MW Unit Trip
Frequency MW
Battery storage units can quickly provide and sustain energy (synthetic inertia) to the grid following frequency disturbances
44
System Strength
RMEL Renewables Planning and Operations ConferenceOctober 17-18, 2018
Recorded unstable response for a wind plant connected to a weak transmission grid
• When a portion of the grid has low short-circuit currents relative to the power flow, it is referred to as an area of low system strength
• Synchronous generators produce large short-currents, typically 5-10 times rated load current
• Fault currents from inverter-based generators can be as low a 1-1.1 times rated load current
• Inverter-based generation controllers require sufficient system strength for reliable operation
• Controller tuning and coordination is necessary to dampen oscillations• Accurate modeling of controller settings is critical
Renewable Integration and Other Reliability Assessments 2016-2019
Byron Woertz Manager, System Adequacy Planning
Western Electricity Coordinating Council
Renewable Integration and Other Reliability Assessments—2016 to 2019
Byron Woertz, Manager—System Adequacy Planning
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Overview
• What is WECC?• 2016-2017 Study Program
– Study Program scope– Observations
• 2018-2019 Study Program– Study Program approach– Initial themes for consideration
2
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Who We Are
Not-for-Profit Organization• Assure reliable bulk power system in
the Western Interconnection
Regional Entity• Approved by FERC• Largest of seven
Authority delegated by NERC• Create, monitor and enforce reliability
standards
Unique Perspective• Both Region and Interconnection
3
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
WECC
What Does WECC Do?
Compliance
• Ensure compliance with NERC reliability standards
• Conduct audits every 1-3 years
Planning
• Reliability Assessments 0-20 years in the future
• Essential Reliability Services, Economics and Policy Impacts
• Event Analysis• Situational Awareness• Performance Analysis
4
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
2016-2017 Study Program
• Study Program Development• Long-Term Reliability Assessment (LTRA)• 2016 Study Cases• 2017 Study Cases• Preliminary Observations
5
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
2016 Study Program
2026 Common Case
• Most likely future in 2026
Sensitivity Cases
• High/Low Loads• High/Low
Hydro• High/Low Gas
Price• High/Low CO2
Price
Special Interest Cases
• Resource retirements
• Resource expansion
• Resource locations
• Probabilistic study
• Energy storage
6
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
2017 Study Program—Year 10 Cases
2026 Common Case
• Most likely future in 2026
Resource Cases
• High Wind• High Solar
Transmission Expansion Cases
• East-to-West• NE-to-SW• “Transmission
Backbone”
Special Interest Case
• Curtailment Prices
• Probabilistic Study
7
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
2017 Study Program—Year 20 Cases
2034 Reference Case
• Extension of 2026 Common Case
Scenario-Based Cases
• S2—Focus on Clean Energy
• S3—Focus on ST Consumer Costs
• S4—Focus on LT Societal Costs
• Energy-Water-Climate Change
Special Interest Cases
• High Distributed Energy Resources
• High Coal Retirements
8
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Observations—LTRA (2017)
Planning Reserve Margins
Based on Reference Margin Level (RML)
No WECC subregiondrops below the RML within the
assessment period
Demand
CA/MX: Relatively flat (0.27% growth)
Other subregions: 0.62% – 1.88%
growth
Generation
Based on 2015 flexibility study, WI appears to be able
to function with expected high
renewables
Retirement of generation is not currently a major
concern
Ongoing study of gas-electric interface
Transmission
Several entities have proposed new transmission
projects
It is not anticipated that transmission additions will be
needed to maintain reliability
9
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Cautionary Note—2016-2017 Study Program
10
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Results are based on modeling
Interpret results in view of modeling
assumptions
Consider limitations of
modeling approach
Transmission Utilization
Terminology
“Utilization” rather than
“Congestion”
Some Paths Designed for High
Utilization
Utilization Metrics
U75: % of hours flows are 75% or
more of path rating
U90: % of hours flows are 90% or
more of path rating
U99: % of hours flows are 99% or
more of path rating
“Most Heavily Utilized”
U75 > 50% OR
U90 > 20% OR
U99 > 5%
11
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Preliminary Observations—Year 10 Studies
Transmission
Across all studies, grid appears to be
adequate
Storage Cases
Additional storage facilitates additional
wind—with limitations
Pumped hydro storage can absorb wind
fluctuations
Incremental pumped hydro has minimal
transmission or resource mix
impacts—modeling issue?
Gas
In high renewable cases, gas varies
counter to renewables
No consistency in impacts on
transmission flows
12
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Preliminary Observations—Year 20 Studies
Renewable Development
Increase in renewables requires
larger generation portfolio
Increased variability increases reserve and
flexibility requirements
CO2 Cost
At $58/ton, all coal present in 2026 is displaced in 2034
Gas resources maintained to meet
reliability needs
Water consumption and CO2 production decreased by over
50%
Energy and Capacity
2027 Common Case resources can satisfy
most energy goals
Additional resources needed for capacity
and seasonal variations in
moderate-to-high growth scenarios
Higher capacity needed for
scenarios with higher renewables
or constraints
13
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Year 20 Observations—Cont.
SolarPV preferred over CSP
DG carve-outs may be a factor
WindMost economic
renewable based on energy production
Significant additions in NM
Potential need for transmission
reinforcements may warrant further study
GasGas generation may not be economically
competitive for energy-only in 10-20
year horizon
Needed for flexibility and reliability goals
Potential need for market-based
incentives
14
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
From Past to Future
Tool-Based Approach
• What can we learn from PCM analyses?
• What can we learn from power flow analyses?
Risk-Based Approach
• What potential future reliability risks should we be thinking about?
• How can we study them?
15
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Drivers for Future Reliability Assessments
2018-2019 Study
Program
Priority Reliability
Issues
Board Near-Term Priorities
WECC Scenarios
16
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
WECC Near-Term Priorities
• Improve the representation of inverter-based resources in WECC’s base cases• Focus on data collection for utility-scale photovoltaic resources, battery
storage, and Distributed Energy Resources (DER)
Representation of Inverter-Based Resources
• Existing Path Ratings• Remedial Action Scheme effectiveness• Expansion of utility-scale storage devices• Protection system ratings• Resource adequacy (RA) and alternate RA methodologies• Interface between transmission and distribution with a focus on modeling
techniques• Essential Reliability Services unique to the Western Interconnection
Impacts of the Changing Resource Mix
17
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
WECC Near-Term Priorities
• Evaluate potential reliability risks and mitigating measures• Consider Regional Reliability Standards, resulting from the expansion of
Reliability Coordinators (RC) and/or market service providers
Expansion of RC and Market Service Providers
• Improve coordination by clarifying the roles, responsibilities, and relationships among WECC and• FERC-Jurisdictional Regional Planning Groups• International Planning Groups (non-FERC Jurisdictional Canadian entities)• Planning Coordinators• Transmission Planners• Other stakeholders involved in BPS planning
Clarify Roles in BPS Planning
18
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
WECC Scenarios19
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Scenario 1 Scenario 2
Scenario 3 Scenario 4
Reliability Assessment Structure
Key Reliability Question
Connection to NT Priorities
and Scenarios
Modeling Options
Data Needs
Expected Results
Resource Requirements
Potential Partners
20
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Potential Reliability Assessments Themes
Electric Vehicle Market Penetration
• Do high penetration levels (10%? 20%? 50%?) create reliability risks?
• How would these penetration levels affect transmission utilization?
Achieving GHG Reduction
• Are renewables the best option?
• What additional resources ca be used to enhance ERS with high renewable penetration levels?
• What CO2 price would be required to achieve GHG reduction targets?
Significant Increase in Demand
• What reliability risks could result from a significant increase in demand in the next 10-20 years?
• At what demand increase level could stability issues create a reliability risk?
21
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Potential Themes, cont.
Resilience
• What are the reliability impacts of a major disruption in 2020, 2028 and 2038?
• What natural events could cause a major disruption?
• What corresponding impacts on gas, water, communications or other systems could exacerbate electric system impacts?
Water Availability Impacts
• With projected increases in natural gas generation, will there be sufficient water to operate thermal resources?
Utility Business Models
• Will alternate utility business models create reliability risks?
• Could the development of “prosumagers” create reliability risks?
• What could be the impact of aggregated prosumagersbecoming virtual utilities?
22
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Potential Themes, cont.
WECC Scenarios
• What are the reliability impacts of each of the five WECC Scenarios?
Change in System Inertia
• What are the reliability impacts of retiring significant thermal resources?
• What are the impacts on frequency response?
• Could the system respond adequately with high solar/wind penetration an no synthetic inertia?
Gas-Electric Interface Issues
• What additional reliability risks might the Western Interconnection experience with high intermittent resource penetration?
• What additional strains could there be on the gas transmission system?
23
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Potential Themes, cont.
Resource Adequacy Under Contingency
• Will there be sufficient resource adequacy if generator outages in 2028 follow historic patterns observed in 2015-2017?
Reliability Impacts of the Most Likely Year 10 Future
• In the Year 10 “Base Case” (2028 Anchor Data Set), are there any reliability risks associated with path flows, resource adequacy, system stability or other parameters?
24
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
2018-2019 Study Program Timeline25
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
2018 2020
Today
Jan Apr Jul Oct 2019 Apr Jul Oct 2020
2018-2019 Study Program ApprovedSep 30
Jan 1 - Jun 29Create Study Program Protocol
Jul 1 - Sep 30Develop 2018-2019 Study Program
Oct 1 - Dec 31Complete and Report on Priority Reliability Assessments
Dec 1 - Feb 29Create Summary Report on 2018-2019 Study Program
Contact Information
Byron WoertzManager—System Adequacy
[email protected](801) 883-6841
26
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Identifying and Addressing Environmental Constraints in the
Federal Permitting Process
Anna Lundin Sr. Project Manager, Environmental Business
Class Lead HDR
© 2014 HDR, Inc., all rights reserved.
Anna Lundin
Identifying and Addressing Environmental Constraints in the Federal Permitting Process
Federal permitting and NEPA nexus in Renewable Energy Development
Constraints in U.S. Mtn West
Climate change as a constraint
Recommendations on how to address constraints
Federal NexusAgency (Department) Action Implementing Authority
EPA (Independent) NPDES Permit, compliance with NSPS and NAAQS standards, waste and substance management
Clean Water Act; Clean Air Act; Noise Control Act; Resource Conservation and Recovery Act; Solid Waste Disposal Act; Toxic Substance Control Act
ACHP, SHPO, THPO, NPS (DOI)
Archaeological, cultural impacts National Historic Preservation Act; Native American Graves Protection and Repatriation Act
USACE (DOD) Section 404 Permit for activities in jurisdictional waters or wetlands, Section 9 or 10 Permit
Clean Water Act; Rivers and Harbours Act
Forest Service (USDA) Activities on federal (Forest Service) land Federal Land Policy and Management Act
BLM (DOI) Activities on federal (BLM) land Federal Land Policy and Management ActUSFWS (DOI) Incidental Take Permit/Eagle Take Permit Endangered Species Act/ Bald and Golden Eagle Protection Act
Rural Development (USDA)
Loans, Loan Guarantees, Grants Rural Electrification Act
WAPA, SWPA etc. (DOE)
Interconnections to Power Administrations or Power Authorities; Permitting or Financial Assistance
Energy Policy Act of 2005 (Sections 216 & 1222); Transmission Infrastructure Program
FERC Hydrodam Licensing Federal Power Act
Evolving and Emerging Regulations
Agency with Jurisdiction Evolving Action Implementing Law
USDA, DOE Loans, Loan Guarantees, Grants Rural Electrification Act, Energy Policy Act, Agricultural Act
EPA Greenhouse Gas Rules Clean Air Act
USACE Section 404 Permit for activities in jurisdictional waters or wetlands Clean Water Act
Forest Service or BLM
Incentives or moratoriums for activities on Federal lands Federal Land Policy and Management Act
USFWS or NMFS Changes to listings of endangered or threatened species Endangered Species Act
USFWS Eagle Take Permit Bald and Golden Eagle Protection ActUSFWS Migratory Bird Take Permit Migratory Bird Treaty Act FERC Order 1000 Energy Policy Act
Increasing Regulatory “Rollbacks” & Uncertainties
Umbrella law triggered by:o Federal permito Federal lando Federal money (federal loan, loan guarantees
and grants) 95% CEs, <5% EAs, <1% EISs >50% of EISs
o Forest Serviceo BLMo USACEo Federal Highway Administration
Federal Nexus = NEPA
1. Reasonable alternatives
2. Impacts to federally protected avian species (sage-grouse, migratory birds, eagles)
3. Potential air space violations
4. Visual impacts
5. Tribal consultations
6. Regulatory “gray” areas
Identification of Constraints in Federal ROW Permitting
Reasonable Alternatives
Use Alternatives Screening Criteria such as specifying
that reasonable alternatives must:• Meet the purpose and need • Pose a clear choice for the decision maker • Be consistent with laws and regulations • Be technically feasible (that is, would use
commercially available technology) • Be implementable by the project proponent
Addressing Constraints
Protected species & air space violations
• Include airspace designations and biological data in siting reviews
• Early consultations with BMPs identified at the pre-construction (10-30% design) phase
Addressing Constraints
Visual Impacts
• Complete simulations » BLM VCR methodology by default» Variations if impacts to USACE, FHA,
NPS or FS properties
Addressing Constraints
Tribal Consultations
• NHPA, EO 13175 and Environmental Justice
• Early engagement and understand “meaningful opportunity” for consultations
Addressing Constraints
Regulatory “gray” areas: climate change
U.S. has no binding international agreements Domestically, the EPA regulates GHGs as pollutants under the CAA CEQ 2010, 2014, 2016 & 2017: Draft, Revised Draft, Final Guidance & Withdrawal EO 13783 Energy Independence and Economic Growth EO 13807 Discipline and Accountability in Environmental Review
Addressing Constraints
NEPA litigation is most common form of federal environmental litigation 711 lawsuits in U.S. involving climate change and various permits and planning documents
(also common in Australia)o Massachusetts v. EPAo Center for Biological Diversity v. National Highway Traffic Safety Administrationo Hapner v. Tidwello Montana Environmental Information Center v. BLMo WildEarth Guardians v. Jewello High Country Conservation Advocates, et al. v. U.S. Forest Serviceo Friends of the Earth and the Western Organization of Resource Councils v. BLM
Litigation
Shareholder proposals: average support for proposals on climate risk jumped from 7% in 2011 to 28% in 2016 Institutional Investors Activist boycotts and campaigns
Additional Incentive
Include climate change in specific aspects of federal permitting and planning documentation
Two broad categories of climate change considerations need to be addressed: o Effects of climate change on a projecto Effects of a project on climate change
How to Address Climate Change
1. Characterize the projected future affected environment due to climatic effects2. Design operations to account for changing environment Identify Sensitivities Incorporate Adaptability Design for Resiliency
Effects of Climate Change on a Project
Climate Change can produce chronic stressors and be responsible for acute shocks. Resiliency is a defense against all chronic stressors and acute shocks By assessing the risks associated with climate change as part of the due diligence on project design,
project liability is reduced by identifying and communicating the nature of those risks so that cost-efficient adaptive actions can be taken.
Plan for Change
GHG emissions and changes in carbon sequestration and storage Connected actions (upstream and downstream) Quantify and evaluate GHG emissions from a project and its connected actions
Project Effects on Climate Change
Identify comprehensive constraints (underground, surface, air, tribal & NGO) during site analysis.
Characterize foreseeable changes due to climatic changes for the life of the project as part of the affected environment.
Evaluate sensitivities, adaptation and resiliency as part of project alternatives, design and planning.
Recommendations
Thank You andQuestions
San Luis Valley: Non-Transmission Alternatives
Cody Sickler Engineer II (Power System Planning)
Tri-State Generation & Transmission Association
1
2
Purpose
To comparatively consider Non-Transmission Alternatives to mitigate the reliability issues in the San Luis Valley.
Specifically, Tri-State has received stakeholder feedback that asks about using energy storage in the San Luis Valley as alternatives to transmission upgrades.
3
4
Flows can be >120MW
230kV
115kV65MW Capacity
San Luis Valley~140 – 150 MW peak load
San Luis Valley~140 – 150 MW peak load
5
Storage Technology Overview
Pumped Hydro Large size (100+ MW) and long
discharge time (16+ hours) ~$1-2M per MW (not counting
interconnection costs) Lack of suitable location in SLV Environmental concerns
Compressed Air Storage Similar performance/cost as
pumped hydro Requires underground caverns
http://www.usbr.gov/projects/Powerplant.jsp?fac_Name=Mount+Elbert+Powerplant
6
Storage Technology Overview
Flywheels Fast response time (<1ms) Large power density Low power (100kW per
flywheel) Short discharge time (<15min) High frictional losses for long
term storage Best for frequency/voltage
regulationhttp://beaconpower.com/hazle-township-pennsylvania/
7
Electro-Chemical Battery Technology Lead-acid
~$5-6M per MW <4hr discharge 90% Efficiency 2000 cycle life
Lithium-ion (Li-ion) ~$1-3M per MW ~4hr discharge 90% Efficiency 4000 cycle life Many vendors-fast growing
market Sodium Sulfur (NaS)
~$3-4M per MW 6-7hr discharge 75% Efficiency 4500 cycle life
DOE/EPRI 2013 Electricity Storage Handbook in Collaboration with NRECA
8
Industry Examples of Grid Scale NaSBattery Installations
34MW (NaS) – Rokkasho, Japan Largest single NaS
installation in the world Used for wind following
4MW (NaS) – Presidio, Texas Outage mitigation for radial
distribution system http://www.eei.org/about/meetings/meeting_documents/abe.pdf
9
65MW : Voltage collapse threshold for 230kV outage
10
65MW : Voltage collapse threshold for 230kV outage
11
Typical Daily Load Curves
Sum of the flows on Poncha-Sargent 115kV
and Poncha-SLV 230kV
Years 2014 and 2015
Average of Top 10% of heaviest loading
days from Summer months
12
13
Battery Sizing Example
6hr Outage Peak MW deficit
24hr Outage Greater of:
Peak MW deficit MW capacity to deliver
MWh energy deficit 48hr Outage
Greater of: Peak MW deficit MW capacity to deliver
2x MWh energy deficit less available charging energy
14
Battery Sizing Scenarios Provide mitigation for
approximately 99% of days in the year.
Summer 2016 Top 10% of summer days in
2014-15 Added assumption of new
50MW Hooper Solar Farm 24hr and 48hr outages
15
Battery Sizing Scenarios
Summer 2016 Light Solar Summer 2016 plus 1
standard deviation accounts for solar variation
6hr, 24hr, 48hr outages
16
Battery Sizing Scenarios
Summer 2020 Light Solar Summer 2016 Light Solar
plus load growth (shifted by 10MW so that peak matches 2011 peak)
6hr, 24hr, 48hr outage
17
Battery Configuration
18
Cost Estimates
Battery/Converter Module Costs DOE/NRECA Study with quotes from vendors Capital cost including installation, transportation, etc. Fixed O&M
Substation Costs Switchgear Step-up Transformers 230kV Buswork
19
Sizing and Cost Results (NaS)
20
Conclusion• High cost
• Short outage (6hr) mitigation: $197-229 Million
• Long outage (48hr) mitigation: $663-877 Million
• SLV battery storage would be largest system of its kind• May be scaling issues for large sizes
• Limited capacity for future growth
• Doesn’t fully mitigate need for load shedding• Relies partially on solar generation
• Analysis doesn’t include other transmission reliability
factors (VAR support, stability, etc.)
21
Questions?
PacifiCorp’s Energy Vision 2020
Rod Fisher Principal Project Manager, Gateway Transmission
PacifiCorp
Energy Vision 2020RMEL Presentation October 18, 2018
• Company Overview
• Energy Gateway / Transmission Update
• Energy Vision 2020• Overview
• Repowering
• New Wind
• New Transmission
• Questions
Agenda
PacifiCorp Overview
• Two divisions – Rocky Mountain Power and Pacific Power
• 5600 Employees
• 1.9 million electricity customers
• 141,000 square miles of service territory in six states
• 16,500 miles of transmission
• 10,887 MW owned generation capacity
• Generating capacity by fuel type• Coal 55%
• Natural Gas 25%
• Hydro 10%
• Wind, geothermal and other 10%
Energy Gateway Program Status
Energy Vision 2020 https://youtu.be/Ojb0h568nvc
Energy Vision 2020
• PacifiCorp announced April 4, 2017 $3.0 billion wind and transmission projects
• Repowering of 905 MW (648 MW in WY) of existing wind
• 1,150 MW of new wind
• 191-mile transmission project to connect new wind
• New Ekola bridge - $4.2 million
• All federal tax credits will offset costs to our customers
• Net result is a cost savings for PacifiCorp customers
Energy Vision 2020 in Wyoming
Energy Vision 2020 Wyoming Benefit
Repowering Overview• Repowering of 999 MW of existing wind facilities; 12 of
13 existing PacifiCorp projects.
• Regulatory proceedings complete with pre-approval in Utah, Idaho, and Wyoming; awaiting Wyoming commission written order.
• Turbine supply and installation negotiations nearly complete for all facilities.
• 2019 - 2020 in-service dates.
New Wind and Transmission Overview• 950 MW of new owned wind facilities; three projects
• TB Flats I & II – 500 MW
• Ekola Flats – 250 MW
• Cedar Springs – 200 MW
• An additional 200 MW of wind procured through PPA
• Cedar Springs – 200 MW
• 140-mile, 500 kV segment of Gateway West transmission
• 230 kV transmission network upgrades required for wind interconnection
• Regulatory proceedings complete; awaiting Wyoming commission written order
• Landowner negotiations proceeding across Wyoming.
• Final commercial negotiations for wind projects ongoing; transmission in bidding phase
• Strong state and local stakeholder support in Wyoming
• Construction start – April 2019
• 2020 in-service
Questions?