Report of the Auditor
Grand Kru County AdministrationFY 2006/07-2007/08 John S. Morlu, II Auditor-General, R.L.
Report of the Auditor-General
County Administration 2007/08
General, R.L.
General
i Promoting Accountability, Transparency, Integrity and Fiscal Probity
Office of the Auditor-General Republic of Liberia
10 December 2010 TRANSMITTAL LETTER REPORT OF THE AUDITOR-GENERAL ON GRAND KRU COUNTY ADMINISTRATION FOR THE FINANCIAL YEARS 2006/2007 AND 2007/2008
1. I am pleased to issue this report, which is the second audit I have commissioned on the
accounts and related records of the Grand Kru County Administration including the County
Development Fund (CDF). The report covered the financial years 2006/ 2007 and 2007/2008.
2. A number of key findings conveyed in this report were formerly reported in my first forensic
audit report covering the CDF of Grand Kru County for the FY 2005/2006. Those findings were
not addressed and implemented by the Authorities of the County.
3. As indicated in the methodology segment of this report, all findings conveyed in the report were
formally communicated to the Authorities of Grand Kru County for their responses. The
reportable issues were submitted through Audit Observation Memoranda and a Draft
Management Letter, and where responses were provided they were evaluated and incorporated
verbatim in this report. Essentially, the Superintendent and other county officials were given the
maximum opportunity to respond to issues raised during the course of the audits.
4. For the period under audit, financial activities and the conduct of the affairs of Grand Kru
County were marred by irregularities and major control deficiencies that accrued losses to the
Government of Liberia and thus, timely resolution by the Legislature and the Executive are vital.
A total of US$340,272.11 of the US$366,666.67 CDF was expended on 15 projects during the
audit for 2006/2007 and 2007/2008, respectively.
5. In account #10210185022016, I noted other irregular withdrawals in the tune of US$18,640.00
paid in the name of PMC Treasurer Michael K. W. Tarweh. In furtherance of acquitting the
US$18,640.00, the Assistant Superintendent submitted documents indicating that the payments
were purportedly made to various universities.
6. As noted, a payment voucher submitted for the students at the Tubman National Institute of
Medical Arts (TNIMA) and Stella Maris Polytechnic indicated US$1,300.00 for 13 students, with 7
at TNIMA and 6 students at Stella Maris. But the attached listing indicated that 16 students
purportedly received money from TNIMA. There is no listing for Stella Maris Polytechnic. The
US$1,300.00 voucher and receipts were meant to acquit part of the undocumented payments in
the tune of US$18,640.00 paid in the name of PMC Treasurer Michael K.W. Tawreh. It is also
indicated on the listing of TNIMA that US$450.00 was provided to sixteen (16) students,
US$100.00 for union and travel fees and US$150.00 for expediter and facilitator fees. This gave
a combined total of US$700.00 as reflected on the payment voucher. But interestingly, the
purported receipt number 45599 purportedly issued by JFK Medical Center Tubman National
ii Promoting Accountability, Transparency, Integrity and Fiscal Probity
Institute of Medical Arts (TNIMA) and stamped by a TNMIA Business Manager’s office indicated
US$700.00. This means that TNMIA also received payment for union and travel fees, and
expediter and facilitator fees. The inconsistency on the unapproved Student Listing and
payment voucher denied assurance on the reliability of the document submitted.
7. I further examined the receipts submitted by Stella Maris Polytechnic. It was signed by a
Jefferson Nagbe. Independent confirmation with Stella Maris indicated that a Jefferson Nagbe is
not in the employ of the Stella Maris Polytechnic and the purported receipt issued bearing the
insignia of Stella Maris Polytechnic does not belong to the Polytechnic. This clearly showed that
Assistant Superintendent Wisseh manufactured the receipts and submitted them for audit
which was meant to acquit the US$600.00. This is a contravention of Section 12.31 of the
Penal Code, which forbids the altering, forging and submission of documents that is known to
be lacking in authenticity. Regulation N-3 of the PFM Regulation also prohibits the submission of
false documents to acquit expenditure in Government.
8. I did not accept PMC Chairman Wreh contention that, “That the Auditing team should
understanding that the community projects are not failed but delayed.” As indicated in
subsequent paragraphs some of the projects did not even start, although the money was paid
to the contractors.
9. One (1) of the four (4) companies contracted on CDF projects did not exist as a registered
entity in Liberia. This was established through a confirmation obtained from the Ministry of
Commerce and Industry. But the authorities of Grand Kru County signed two contracts that
indicated that the company was a legally established entity under the laws of Liberia.
10. I informed the County Authorities that the contracts awarded to unregistered businesses could
provide no remedy for a breach. Regulatory laws, such as a business registration requirement,
are intended to protect the public against incompetence, frauds, etc. The Superintendent and
Assistant Superintendent did not exercise the minimum professional due care to ensure that at
the very least this company met the legal capacity requirement. This was a noted breach of
Section 32 (1f) of the PPC Act, 2005. Further the Grand Kru County Authorities violated Section
4.2 of Chapter 4 of the Business Law of Liberia. Section 4.2 of Chapter 4 states “No person shall
conduct or carry on a business unless he has registered such business with the Assistant
Minister, who shall perform his duties under this chapter subject to the direction and control of
the Minister of Commerce and Industry. Any person violating the provisions of this section shall
be subject to a fine not less than $10.00 and not more than $1,000.00 or imprisonment not less
than one month or more than one year or both”.
11. The contravention of the procurement law created an opportunity for the county authorities to
award contracts to companies, without much regard to determining the financial condition of
companies awarded contracts. Tax identification requirements were also not met. These basic
requirements are contained in Section 32 of the PPC Act, 2005. Furthermore, from the review of
financial documents and the Bank Statement, it was noted that all the contractors did not pay
service tax to the Liberian Government, causing the Government a loss in revenue.
12. For the period under audit, the Grand Kru County Authorities undertook thirteen (13)
construction projects and one (1) road rehabilitation project, and the purchase of equipment for
iii Promoting Accountability, Transparency, Integrity and Fiscal Probity
road rehabilitation and construction, again bringing the total projects to fifteen (15) projects.
Additionally, there was a scholarship program.
13. As noted in the report, the Grand Kru County Authorities made nearly 100 percent payments on
the fourteen (14) projects associated with construction of structures and road rehabilitation, but
as my physical inspection revealed these 14 projects are yet to be completed. It is indicated in
the report that Six (6) projects have not started, three (3) projects are at foundation Level, four
(4) projects were incomplete and one (1) project with only sticks planted in the ground. Of the
four (4) uncompleted projects, substantial works were done on the Barclayville Generator House
Project and the Barclayville City Hall Project.
14. The fourteen (14) construction and road rehabilitation projects were contracted to various
contractors and individuals for a total contract of US$147,317.00, representing forty (40)
percent of the total CDF of US$366,666.67. It is instructive to note that the County Authorities
without due regard to the terms as specified in the contracts which required three installment
payments, paid the purported contractors and individuals US$140,397.11, representing 95.30
percent of the total contract sum for the 14 projects. The amount of US$140,397.11 also
represented 38.29 percent of the CDF of US$366,666.67 for the periods 2006/2007 and
2007/2008.
15. All the contractors though paid by the county authorities, defaulted in the implementation of the
projects. Superintendent Sneh in attempting to exonerate herself from the wrong done to the
people of Grand Kru County stated:
“Therefore, it is the statutory responsibility of the PMC to provide that oversight. The PMT
elected by the community selects their contractor and presents same to the PMC. Once the
PMC, as the technical arm certifies the contractor, the Superintendent cannot reject. The
PMC again prepares the contract with all the payment terms stipulated and once the
contract is signed by all parties the Superintendent countersign same. The actual payments
are by the PMC even though the Superintendent approves the voucher. So when I asked
about the payment terms on the voucher, I am told by the PMC that due to the difficulty in
transporting the materials to Grand Kru County, the payment was ordered once, instead of
three installments. Therefore, I Rosalind Sneh cannot be held accountable for the PMC’
responsibility”.
16. I noted the Superintendent’s response and appreciate the explanation provided. But such
explanation was not substantive to cure the opportunity loss to the citizens of Grand Kru
County. Instead of responding to the substantive issues raised in the report, Superintendent
Sneh blamed the PMC and the PMT. The Superintendent in her response provided a material
justification why she and other Grand Kru officials should be held liable. She rightly indicted
herself by saying:
“Therefore, it is the statutory responsibility of the PMC to provide that oversight. The
PMT elected by the community selects their contractor and presents same to the
PMC. Once the PMC, as the technical arm certifies the contractor, the
Superintendent cannot reject. The PMC again prepares the contract with all the
payment terms stipulated and once the contract is signed by all parties the
Superintendent countersign same. “
iv Promoting Accountability, Transparency, Integrity and Fiscal Probity
“The PMC again prepares the contract with all the payment terms stipulated and
once the contract is signed by all parties the Superintendent countersign same. The
actual payments are by the PMC even though the Superintendent approves the
voucher. So when I asked about the payment terms on the voucher, I am
told by the PMC that due to the difficulty in transporting the materials to Grand Kru
County, the payment was ordered once, instead of three installments.”
17. The Superintendent admitted to counter-signing the contracts, which means that she was
aware of the status of the contractors. She also authorized payments to the contractors and
cannot divorce herself from the legal and financial dealings on the projects. Superintendent
Sneh placed her legal reliance on the Budget Law 2007/2008. But she failed to also note that
there is no provision in the Budget law 2007/2008 that provides her the substantive authority
to attest to contracts or approve payment vouchers. The Budget Law only provides that the
Superintendent serves as the second A signatory to the CDF bank account, signing checks only
in the event that the Assistant Superintendent for Development is absent.
18. As noted in the observation, payments were to be made in three installments, but examination
of the Bank Statements and vouchers revealed that a total of US$140,397.11 against the total
contract cost of US$147,317.00 was paid on fourteen projects. This represents 95.30 percent
of the total contract sum for the projects. These payments were made without much regard to
the payment terms in the contracts, contracts that were attested by Superintendent Sneh.
Superintendent Sneh provided the following unsubstantiated excuse for her lack of oversight
on the projects:
“So when I asked about the payment terms on the voucher, I am told by the PMC
that due to the difficulty in transporting the materials to Grand Kru County, the
payment was ordered once, instead of three installments.”
19. By her own admission, Superintendent Sneh is indicating that she was aware that contract
payments terms were being violated. Instead of insisting on the payment terms to protect
public resources in the event of a default on the part of the contractor, she duly approved all
the payments. Superintendent Sneh did not produce a single document to support her
contention that she queried the violation of the payment terms.
20. A Fayiah Henneh, President and Supervisor of NAFAPD abandoned the projects and fled from
Grand Kru. NAFAPD, as confirmed by the Ministry of Commerce and Industry, is an illegal
establishment. Mr. Henneh did not perform on the contracts, though the Superintendent and
her officials made a total payment of US$18,994.44 on the two projects. County Builders
Construction Company also defaulted in the implementation of the Gbeatao Town Hall Project
and Nifao Clinic Project after receiving US$19,130.84. The Gbeatao Project is at foundation
level whereas the contractor has not commenced work on the Nifao Town Project. This has
denied the citizens of Grand Kru their timely benefit of development projects financed by the
Government of Liberia. The Superintendent and her officials did not provide any evidence of a
legal action taken to enforce performance by the contractors.
21. By not doing a simple background check on the NAFAPD, the Superintendent and her officials
violated Section 32 (1f) of the PPC Act, 2005 by knowingly awarding contract to an illegal
entity. A violation of the PPC Act, 2005 is punishable under Section 138 (1) of the PPC
v Promoting Accountability, Transparency, Integrity and Fiscal Probity
Act, 2005. They also violated Section 4.2 of the Business Law which states states “No person
shall conduct or carry on a business unless he has registered such business with the Assistant
Minister, who shall perform his duties under this chapter subject to the direction and control of
the Minister of Commerce and industry. Any person violating the provisions of this section shall
be subject to a fine not less than $10.00 and not more than $1,000.00 or imprisonment not
less than one month or more than one year or both”.
22. Superintendent Sneh provided the following non-material justification to explain her lack of
oversight:
“Therefore, it is the statutory responsibility of the PMC to provide that oversight.
The PMT elected by the community selects their contractor and presents same to
the PMC. Once the PMC, as the technical arm certifies the contractor, the
Superintendent cannot reject”.
23. By her assertions, Superintendent Sneh recognized the statutory responsibility of the PMC and
PMT to provide oversight but failed to recognize her own statutory responsibility. She is the
Superintendent of the County and a signatory to the CDF account. She counter-signed a
contract in which there is a clause that clearly indicated that NAFAPD is a company duly
registered and operating under the laws of Liberia. This was a material misinformation as it is
confirmed that NAFAPD does not exist as a legal company in Liberia.
24. By Superintendent’s Sneh failure to remedy material breaches in contract performance and her
lack of oversight, the Government of Liberia was exposed to fraudsters operating illegal
companies for the purpose of stealing funds from Government coffers through fraudulent
procurement schemes. Superintendent Sneh should accept full responsibility for the role she
played on the CDF, as she signed contracts and financial documents.
25. Superintendent Sneh’s reliance on the Budget Law 2007/2008 was baseless and unsupported
as the same Budget Law did not make provision for her to sign contracts and financial
documents. By affixing her signature to contracts and financial documents in contravention of
the Budget Law 2007/2008, she became active participant in the expending of CDF monies
to illegally operated contractors, and contractors that have not performed, although received
payments.
26. Project Management Committee (PMC) Chairman Johnson T. Wreh’s, also blamed the lack
of performance on the bad roads when he contended, “Bad roads are major constraint in
implementing projects in Grand Kru County; yet commitment and seriousness are guiding
principle in our drive to successfully implement projects in the County."
27. Superintendent Sneh and PMC Chairman Wreh failed to note that the doctrine of impossibility,
impracticability, and frustration of purpose excuse performance only if a supervening
circumstance was not reasonably contemplated or foreseeable when the contract was made.
Unreasonable rain and deplorable road condition in April to November 2008 is not such a
circumstance in Liberia, much less Grand Kru. Bad road condition is an ordinary business risk in
Grand Kru. Bad road condition is no news in Liberia, much less a county that is deemed as the
“forgotten” County due to its bad road and poor infrastructure. Additionally, the purchase of
vi Promoting Accountability, Transparency, Integrity and Fiscal Probity
materials in Monrovia is a noted business practice in Liberia and therefore cannot be used as
an excuse to contravene provisions of contracts and agreements.
28. In the implementation of the CDF in Grand Kru County, conflict of interest was noted. Two
projects were awarded to the Grand Kru County Resident Engineer, Nyandeh Sieh. Nyandeh
Sieh received a total of US$13,550.00 for the construction of the Generator House Project
and the Kplio Road Rehabilitation Project. After receiving US$9,550.00, representing 95.5
percent of the contract sum of US$10,000.00, Nyandeh failed to implement the Kplio Road
Project.
29. Awarding contracts to a serving county official is an indication of conflict of interest. The
Grand Kru County Authorities and Nyandeh Sieh contravened Section 131 (1c) of the PPC
Act, 2005 and Article 90 (a) of the Constitution of Liberia. While the Superintendent does not
recognize that conflict of interest exist in the Generator House Project, she admitted to
conflict of interest in the Kplio Town Road Rehabilitation Project. In her response to the
observations on the Generator House Project she stated:
“The County Authority therefore used an employee, a general builder who was the County
Engineer. The person who held the post before tenure was Development Coordinator. This is
why it was on the EDP payroll. It was the very MIA, though its template that changed the
title to County Engineer. This is not conflict of interest.”
30. In her response to the Kplio Road Rehabilitation Project, Rosalind Sneh stated:
“When it was brought to our attention that our employee, Nyandeh Sieh signed a contract with
the PMC for the Kplio Road Rehabilitation Project, and entered into contract with the German
Agro Action (GAA), we immediately requested Mr. Nyandeh Sieh to resign his post with
government because this particular case is conflict of interest. Mr. Nyandeh Sieh complied and
resigned on March 6, 2009”.
31. The Superintendent was paradoxical in her response. The two issues are a glaring conflict of
interest and the Superintendent sanctioned this conflict of interest by attesting to the contracts
entered into with her own Engineer. The Superintendent is conflicted in her response.
32. In furtherance of conflict of interest in Grand Kru County, the Authorities knowingly engaged the
services of PMT Member Daniel Wiah for the Barfowin Town School Building Project, D. Wah
Hne/Representative Slopadoe for the Buah Guest House and Betu PMC Member Abacus K.
Nimene, for the Renovation of a School Building in Betu. Awarding projects to technicians who
should be checking contractors for compliance is glaring conflict of interest.
33. As noted the 14 projects, which include thirteen construction projects and one Road
Rehabilitation, undertaken in Grand Kru County are incomplete and notably as indicated in the
table supra, majority of the structures are either at foundation level or have not started at all.
The County Authorities failed to take remedial measures against defaulting contractors, except
in the case of Nyandeh Sieh where he resigned upon the request of the Superintendent but is
yet to pay the US$9,550.00 he received for the Kplio Road Rehabilitation Project for which he
did not rehabilitate.
vii Promoting Accountability, Transparency, Integrity and Fiscal Probity
34. For the period under review, citizens of Grand Kru County decided to purchase an earth moving
equipment, one dump truck, one new double cabin pick-up, one new motor bike, fuel oil and
lubricants. This was a major project in the County with a cost of US$199,875.00. The contract
was awarded to Monrovia Developer Management Corporation (MDMC). I checked with PPCC
and it was confirmed that Grand Kru did not obtain a No Objection as the Threshold Schedule of
the PPC Act, 2005 indicated that an amount above US$100,000.00 for goods should be
internationally competitively bided. This was not done and therefore led to a violation of the
Threshold provisions of the PPC Act, 2005.
35. On 6 May 2008, in fulfillment of the contract, the PMC raised voucher #0997 and 0998 in the
name of MDMC EXPRESS Inc, and issued Ecobank check #787726 and #787727 in the amount
of US$167,525.00 and US$32,350.00 respectively in favor of MDMC. By this the county pre-
financed the project and made 100 percent payment to the contractor.
36. On 10 August 2008, MDMC General Manager John S. Youboty addressed a progress report on
the shipment of the equipment to the Grand Kru County PMC Chairman indicating that the
equipment will arrive at the Free Port of Monrovia from 25 September 2008 to 6 October 2008.
The equipment arrived and was held at the Port by the National Port Authority for duty payment
for over three months. MDMC however sought and obtained duty waiver through MIA as per the
contract. The equipment was cleared at the NPA but General Manager Youboty did not make
available delivery note to confirm that the equipment have been delivered to the PMC in keeping
with the contract.
37. Besides the truck and the bike, the rest of the equipment is currently at the MDMC yard on 13th
Street, Sinkor. The equipment arrived in November 2008 and has not been delivered, thus
creating an opportunity loss for the Government of Liberia and a denial of development for the
Citizens of Grand Kru. For years running the equipment have been on showcase, with no real
value added to the people of Grand Kru County. This is a two year material loss to the
Government of Liberia, because the equipment has not created jobs and development in Grand
Kru County, thus not impacting the lives of people in stranded Grand Kru, which is considered
cut-off from the rest of Liberia.
38. Superintendent Sneh provided a response that is not substantive to cure the deficiency noted.
She did not even bother to address the issue of the US$32,350.00 for fuel and lubricant for
which no accounting was made. Superintendent Sneh also did not provide material justification
for the payment for fuel and lubricant in advance when the equipment had not even arrived in
Liberia. The payment for fuel and lubricant cleared the Bank on 5 May 2008, while the
equipment arrived in Monrovia in November 2008 and has not been in operation as of date,
October 2010.
39. In her response to the draft management letter in October 2010, the Superintendent has
confirmed that the equipment is still in Monrovia since it was brought in November 2008. The
Superintendent maintained:
“A new management contract between Grand Kru County and MDMC for the transfer,
operation and management of the equipment has been concluded. The contract runs from
15th October 2010 to 14th December 2010.”
viii Promoting Accountability, Transparency, Integrity and Fiscal Probity
40. The equipment was fully paid for and was to be delivered in August 2008. Instead it was
delivered in November 2008. It has been in Monrovia since November 2008, depriving
development to the citizens of Grand Kru. This was a clear waste of public resources, as of date
(nearly 2 years later) the equipment is still not in use.
41. Superintendent Sneh also contended that the County has again entered another agreement with
the same company that purchased the equipment, allowing the company use of the equipment
for the period running between 15 October 2010 and 14 December 2010. Grand Kru County has
now entered the leasing business, as a lessor of equipment purchased with CDF for the
development of the County.
42. Examination of the Bank Statements, with the A/C # 1020136022019, revealed that a number
of payments were made to serving county officials and others, including Superintendent
Rosalind Sneh and Assistant Superintendent for Development T. Michael Wisseh in the tune of
US$16,260.00. There was no material justification and supporting documentation provided to
acquit these payments.
43. The Superintendent in her response provided an expenditure report of how she used the
US$14,633.00 noted in the audit report as payments made in her name. She stated that
US$14,633.00 was spent on labor cost without material justifications and supporting
documentation to acquit the expenditure. As noted in the Forensic Audit Report of 2005/2006,
out of the US$66,666.67 allocated to Grand Kru County, US$16,670.00 was deposited in the
Grand Kru County Development Fund Account bearing account number 10210136022019, held
at the Ecobank for labor and administrative costs.
44. Out of the amount of US$16,670.00 deposited in the CDF Account (Account
#10210136022019), the Superintendent and Assistant Superintendent for Development
withdrew US$16,260.00. As indicated in the 2005/2006 Forensic Audit Report, the
Superintendent provided receipts of expenditure in the tune of US$10,142.50, leaving a variance
of US$6,118.00 unaccounted for by the Superintendent and Assistant Superintendent for
Development. The Superintendent failed to provide receipts and material justifications for the
US$6,118.00 that she and her development Superintendent withdrew from the Bank.
45. I recommended that in future undertaking of CDF projects, the Minister of Internal Affairs
should coordinate with the Ministry of Public Works to approve architectural designs and inspect
construction work. I also recommended that the Minister of Internal Affairs also work with the
Director General of the General Services Agency to certificate all equipment purchased under
the CDF. In similar token, the Minister of Internal Affairs should increase oversight of CDF
projects by ensuring that engineer’s reports, certificates of completion and project assessment
reports are prepared before payments are made to contractors.
46. As noted in my audits of the Ministry of Public Works, there are Resident Engineers assigned by
the Ministry of Public works in each of the fifteen counties. There is a need that county
instrumentalities coordinate their efforts in the achievements of Government programs. I am of
the conviction that these engineers are stationed in the counties for the purpose of undertaking
such functions, but the lack of coordination between line ministries and agencies is creating
opportunities for illegally operated companies to defraud Government.
ix Promoting Accountability, Transparency, Integrity and Fiscal Probity
47. I have also recommended that all contracts under the CDF should have a clearly defined
requirement of a performance bond and remedial actions to include estimated penalties for
default in the execution of contracts. It is indicated throughout this report and other reports on
the CDF that officials, employees and businesses do not appreciate the concept of opportunity
cost. Nearly all the projects were not implemented within the timeframe stipulated in the
contracts, thus denying timely development to the citizens within a reasonable time frame.
48. The total irregularities noted in the audit amounted to US$131,484.00, representing
breach of contracts, irregular transactions, undocumented transactions and lack of
compliance with laws and regulations. The US$131,484.00 excludes US$50,745.24 which
was derived from the US$28,745.24 paid to County Builders for three projects and the
US$22,000.00 paid to LICOME Inc for which I have recommended that County Builders and
LICOME Inc should be held for breach of contracts and made to pay general damages.
49. Her Excellency, the President of the Republic of Liberia, and the Speaker, House of
Representatives and the President Pro-Tempore of the Senate, the above issues are
symptomatic of others noted in this report. Because of their impact on the management of
public finances of the Grand Kru County Administration, I advise that their resolution should be
considered urgently.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
2 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table of Contents
BACKGROUND .............................................................................................................................. 4
AUDIT OBJECTIVES ...................................................................................................................... 4
AUDIT SCOPE ............................................................................................................................... 4
METHODOLOGY ............................................................................................................................ 5
FINANCIAL RESOURCES OF GRAND KRU COUNTY ........................................................................... 5
PROJECTS RESOLUTION ................................................................................................................ 6
GRAND KRU COUNTY DEVELOPMENT FUND (CDF) PROJECTS STATISTICS ....................................... 7
COUNTY DEVELOPMENT SUPPORT SECRETARIAT (CDSS) UNCLEARED STATUS ................................ 8
DISTRICT DEVELOPMENT COMMITTEE (DDC) ................................................................................. 9
DETAILS OF GRAND KRU COUNTY DEVELOPMENT FUND PROJECTS ............................................... 12
TREMBO PROJECT ...................................................................................................................... 12
SIKLIO COMMUNITY PROJECT ..................................................................................................... 16
BARCLAYVILLE CITY HALL PROJECT ............................................................................................. 19
GBETAO PROJECT ....................................................................................................................... 23
GYABO PROJECT ......................................................................................................................... 26
NIFAO PROJECT ......................................................................................................................... 28
BARCLAYVILLE GENERATOR HOUSE PROJECT............................................................................... 34
PROJECT STATUS ....................................................................................................................... 34
BOLLOH PROJECT ....................................................................................................................... 37
BUAH PROJECT ........................................................................................................................... 39
FRAUDULENT SCHEME ................................................................................................................ 40
FORPOH PROJECT ...................................................................................................................... 41
JLOH PROJECT ........................................................................................................................... 42
JRAO (SASS TOWN) CITY PROJECT .............................................................................................. 44
KPLIO PROJECT .......................................................................................................................... 46
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
3 Promoting Transparency, Accountability, Integrity and Fiscal Probity
QUALOH COMMUNITY PROJECT ................................................................................................... 49
AUDITOR GENERAL’S POSITION .................................................................................................. 61
GRAND KRU COUNTY SPORTS FUND UNACCOUNTED FOR ............................................................. 63
MISSING COUNTY GENERATOR ................................................................................................... 65
COUNTY SOURCES OF INCOME .................................................................................................... 66
CELLCOM CONTRACT .................................................................................................................. 66
BANK STATEMENT ANALYSIS — FIRST ACCOUNT ......................................................................... 68
BANK STATEMENT ANALYSIS—SECOND ACCOUNT ........................................................................ 70
STATEMENT OF ACCOUNTABILITY ............................................................................................... 76
ACKNOWLEDGEMENT .................................................................................................................. 77
ACCOUNTABILITY SCHEDULES ……………………………………………………….…………………………………………78 EXHIBITS ………………………………………………………………………………………………………………………..…….. 79
Acronyms/Abbreviations/Symbols
Acronym/Abbreviation/Symbol Meaning
A/c # Account Number
A G Auditor General
BMC Building Material Center
CBO County Based Organization
CDF County Development Fund
CDSS County Development Support Secretariat
CSA Civil Service Agency
FY Fiscal Year
GAC General Auditing Commission
GOL Government of Liberia
GSA General Services Agency
L$/LD Liberian Dollar
LICOME, Inc
Liberia Construction and Maintenance Enterprises,
Incorporated
MIA Ministry of Internal Affairs
MoC Ministry of Commerce
MoF Ministry of Finance
MOU Memorandum of Understanding
MPW Ministry of Public Works
PMC Project Management Committee
PMT Project Management Team
PPC Public Procurement & Concessions
PPCC Public Procurement & Concessions Commission
SCDC Special County Development Council
US$/USD United States Dollar
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
4 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Background
1. On 16 December 2008, I commissioned a Special Forensic Audit of all county administrations of
the 15 political subdivisions of Liberia and county development projects undertaken by county
administrations. The audit of Grand Kru County covered monies provided in 2006/2007 and
2007/2008 County Development Fund to the tune of US$366,666.67 and other revenue and
expenditure.
Audit Objectives
2. The objectives of the Special Forensic Audit were to:
• Verify whether projects were executed in a transparent manner and that there was no fraud,
waste or abuse of Government of Liberia resources.
• Assure that financial transactions were in line with the Budget Law of 2006/2007 and
2007/2008, including sufficient appropriate documentation for expenditure.
• Assure that contracts awarded under the CDF and expenditure incurred from other funds
were consistent with various provisions in the Public Procurement & Concession (PPC) Act,
2005.
• Assure that appropriations for the CDF were not exceeded and funds expended were used
for the purposes of development in the County.
• Assure that professional due care was exercised during the awarding and implementation of
projects.
• Assure that contract execution was done consistent with contract terms and that sufficient
and timely remedial actions were taken in cases of defaults.
Audit Scope
3. The audit included the examination of several financial documents to meet reporting
requirements as defined in Section 53.7 of the Executive Law of 1972 as well as various
provisions of the Revenue Code of 2000 and Public Procurement and Concessions (PPC) Act,
2005. The following relevant financial and related information formed the integral part of the
audits:
• County Personnel & Payroll
• County Development Fund
• County Sports Development Fund
• Other revenues generated by the county administration
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
5 Promoting Transparency, Accountability, Integrity and Fiscal Probity
4. A separate report on Personnel and Payroll were jointly compiled by GAC and Civil Service
Agency (CSA) and submitted to the Minister of Internal Affairs, Minister of Finance and the
President on 5 April 2010.
Methodology
5. The audit approach included review and examinations of records pertaining to the contracting
and implementation of fifteen (15) projects financed by the CDF.
6. Conducted physical verifications of all 2006/2007 and 2007/2008 Projects funded under CDF.
7. Met and interviewed community members and members of Project Management Committee
(PMC), and relevant county authorities.
8. Audit Observation Memoranda (AOMs) were raised and issued to the Superintendent and other
relevant officials of the County. A Draft Management Letter was also issued to Superintendent
and relevant authorities, and where responses were received; they were duly evaluated and
incorporated verbatim in this report.
Financial Resources of Grand Kru County
Observation
9. A review of the 2006/2007 and 2007/2008 Budgets revealed that the Government of Liberia
appropriated for Grand Kru County US$812,237.66 as indicated in Tables 1 and 2 .
Table 1: Grand Kru County Budget Audited
Table 2: Grand Kru County Budget: Not Audited By GAC
Program
2006/2007 Budgetary Appropriatio
ns
2007/2008 Budgetary
Appropriations.
Opening of
Critical Roads MPW
Total
Appropriations
US$143,310.00 US$255,594.00 US$30,000 US$428,904.00
2006/2007
County
Developme
nt Fund
2007/2008
County
Developme
nt Fund
2006/2007
National
Football
Developme
nt
2007/2008
National
Football
Development
Total
US$166,667 US$200,000 US$3,333.33 US$13,333.33 US$383,333.66
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
6 Promoting Transparency, Accountability, Integrity and Fiscal Probity
10. The appropriations in the National Budget for County Administration and the funding for the re-
opening of critical road segments by the Ministry of Public Works (MPW) in Grand Kru County
were not audited by the GAC. A special audit will be conducted on the Critical Roads Budget and
an audit of MIA will include the audit of the County Administration Budget.
11. The County Development Fund and the National Football Development Budgets were audited.
Additionally, other sources of income identified in Grand Kru County including land leased to
GSM companies for installations of communication towers and municipal taxes collected there-
from were also audited.
Projects Resolution
Observation 12. After the transfer of the fund to the Grand Kru County Development Fund Account#
10210185022016 at the Eco Bank by GOL, the citizens of Grand Kru County under the banner of
head of delegates and delegates of the Special County Council met in Barclayville City, Grand Kru
County where they resolved and adopted the below resolution.
a. The Project Management Committee (PMC) be headed by:
• Johnson T. Wreh, Chairman
• Michael K. W. Tarwreh, Sr., Treasurer
• E. Nyewoti Wollor, Assistant Treasurer
b. An account should be opened at the Eco-bank Liberia, Ltd.
c. CDF in the amount of US366,666.67 is allocated and expended in the following manner:
Table 3: Projects Adopted Based Upon Resolution
Projects Amount (USD) Amount (USD) Purpose
CDF $366,666.67
Equipment $200,000.00
Operations and Maintaince of Basic
Roads
Community Development Initiate $120,000.00
US$10,000 to each community to be
spent and accounted for as Budget Act
Youth Development Initiative $10,000.00 Support to youth programs
Development of Capital City, layout and
meeting hall $22,000.00 Construction/Renovation
Administrartive work of the Project
Management Committee (PMC) $3,000.00 Remuneration/Benefits
Purchase of Motorbike for PMC $3,000.00 Remuneration/Benefits
Administrartive work of the Project
Management Teams (PMT) $2,000.00 Remuneration/Benefits
Reserved for Contigency $2,000.00 Meet unexpected expenditure
$4,000.00 $366,000.00
Balance 666.67
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
7 Promoting Transparency, Accountability, Integrity and Fiscal Probity
d. The Resolution also indicated that the Special County Council will reconvene at a time to be
determined by the Legislative Caucus in consultation with the county Superintendent. This was
intended to address the issue of the selection of the critical road segment.
Grand Kru County Development Fund (CDF) Projects Statistics
Observation 13. During my review of records in Grand Kru, I observed that 15 projects were awarded by the
PMC and the County Authorities to contractors, an unregistered business, the County Engineer,
PMT Members, and a number of individuals as indicated in the table below:
Table 4: Grand Kru Project Statistics
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
8 Promoting Transparency, Accountability, Integrity and Fiscal Probity
14. Of the 15 projects undertaken, I observed that six projects were not started at all, three projects
were at foundation level, four projects were incomplete, one project with only sticks planted in
the ground and the earth moving equipment/others though delivered by MDMC, but still at the
vendor’s office.
County Development Support Secretariat (CDSS) Uncleared Status
Observation
15. The County Development Support Secretariat (CDSS), a technical monitoring unit in the Ministry
of Internal Affairs (MIA), status at MIA is not clear. Though CDSS is housed within the MIA
compound and building with UNDP donated MIA assigned vehicles, its staff are not employees of
MIA. They are neither on MIA profile and organizational chart nor do they carry MIA
identification cards. CDSS has no legislative enactment, as it is not mentioned in the Budget
Law, 2007/2008 as it is the case with other institutional arrangements contained in the Budget
Law, such as the legal mandate to create a PMC.
16. Michael C. George is CDSS Program Manager. He took over from George Kollie who managed the
CDSS during the 100 Community Driven Projects in 2005/2006 when the Government of Liberia
initiated the County Development fund with the initial appropriation of US$1,000,000.00.
17. Program Manager George indicated that he received support from the following sources:
• US$5,000.00 contribution provided by each county from its annual county development fund
for 2006/2007 and 2007/2008. This was agreed through a reported consensus reached by
the 15 counties of Liberia. Exhibit 1.
• Program Manager George however indicated that though a consensus was reached between
the CDSS and the 15 counties of Liberia for every county to contribute US$5,000.00 each
from its annual County Development Fund as a support to the CDSS’ operational budget,
only five counties complied. Grand Kru County did not cooperate.
• I also observed the quarterly disbursement of non-taxable income of US$10,950.00 by MIA
Comptroller, Brown Sarlee from the MIA account for 9 (nine) CDSS staff as salaries. This
request for payment was made on salaries request form No. 048 dated 11 December 2008.
For this transaction, an unsealed and unnumbered voucher was prepared by the Comptroller
dated 12 December 2008 signed by the Comptroller and Minister Ambulai Johnson, and paid
on check #0428991. Exhibit 2.
18. For the period under audit, oversight by CDSS was not effective. Superintendents and other
county administration did not follow the Budget Law and the procedures established by MIA
through CDSS.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
9 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Risk 19. The undefined status of the CDSS could put its existence and operations at risk, because it
would work at the sole discretion of a Minister and discretionary practices could lead to fraud,
waste and abuse of public resources.
20. During the period under audit, CDSS did not have a written contract/MOU with the MIA to
support its activities but received funding from MIA and County Development Fund. This could
deny assurance on the regularity of the payments.
21. The lack of an MOU and operating manual could further increase the risk of conflict of interest to
the sole benefit of members of the CDSS to the detriment of the County Development Fund and
MIA Budget, as funding for CDSS could be arbitrarily increased to the disadvantage of the
counties.
Recommendation
22. MIA should legitimize the status of CDSS and strengthen or disband it with immediate effect.
23. Oversight by the Minister of Internal Affairs should be strengthened with enforced periodic
reporting and regularized monitoring of projects and program implementation.
Management’s Response to Audit Observation Memorandum and Draft management Letter
24. Audit observation was submitted to former Minister Ambullai Johnson, Program Manager Michael
George, and MIA Comptroller Sarlee. As of August 2010 no responses were provided by
management.
District Development Committee (DDC)
25. On 18 September 2007 an agreement was entered into between the United Nations
Development Program (UNDP) in Liberia and the District Development Committee (DDC) of all
the Districts in Grand Kru County.
26. The DDC was set up by the UNDP to assist in organizing and setting up the Project Management
Committee (PMC) and to monitor community based projects and other UNDP sponsored projects.
27. After the agreement was signed, the UNDP provided the below assets valued US$4,114.85 to
each administrative district in Grand Kru County, where DDC maintains its presence:
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
10 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table 5: UNDP Assets Provided to each DDC
TRANSPORT
Item Qty Unit Cost Total in USD
Motorbike 1 3,000.00 3,000.00
STATIONARY
Item Qty Unit Cost Total in USD
Plain Paper 4 reams 5.00 20.00
Plain envelopes 2 boxes 5.00 10.00
Yellow
pad/steno pad
12 pcs 1.50 18.00
Pen 4 boxes 5.00 20.00
Pencil 4 boxes 5.00 20.00
Manual
sharpener
2 sets 25.00 50.00
Stapler 2 sets 6.00 12.00
Manual Type-
writer
1 set 282.00 282.00
Ribbons 4 pcs 1.40 5.60
Correction fluid 5 bottles 1.75 8.75
Dissolvent 2 bottles 1.75 3.50
Diaries 6 pcs 9.00 54.00
Wall Calendar 1pc 3.00 3.00
FURNITURE
Item Qty Unit Cost Total in USD
Small filing
cabinet
1 set 110.00 110.00
Wooden table 1 set 310.00 310.00
Chairs 1 pc 63.00 63.00
Desk 1 set 125.00 125.00
Total US$4,114.85
28. The assets represent assistance from UNDP, through its Community Based Recovery Program to
DDC through MIA. It was meant as a contribution to promote recovery, development and the
overall welfare of every district, referred to in the agreement.
29. A review of the agreement entered into between the DDC and UNDP, indicated that the DDC
acknowledged and agreed that the above listed UNDP donated assets valued at US$4,114.85
would be used solely for the purpose specified below:
• Monitor projects financed through the County Development Fund and donor sponsored
projects.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
11 Promoting Transparency, Accountability, Integrity and Fiscal Probity
• Failure of DDC to use the Assets solely for the purpose as specified in the Agreement may
subject UNDP to request that the Assets be returned to UNDP.
• Upon the transfer of the Assets, the DDC shall be solely liable for all maintenance for the
Assets, without any assistance or further obligation from UNDP to provide funding for the
operation and/or repairs at anytime during the life of the assets.
• The DDC acknowledged and agreed that UNDP is not obligated to provide addition assets or
to replace the assets upon any loss, damage or expiration of the assets.
• The DDC acknowledged and agreed that it is solely liable for all insurance coverage if any
that may be required to protect the assets against loss, theft or damage.
• The DDC accepted the assets from UNDP Liberia “as is” and agreed that UNDP offers no
warranty and is released from all liability relative to any claim, loss liability or damage arising
from the DDC use of the assets.
30. I established the existence of the UNDP donated assets in all of the districts in Grand Kru
County. It was however difficult to establish the operational effectiveness of the DDC, as I was
not provided with any evidence of reports submitted by the DDC to the Superintendent or CDSS.
Risk
31. The DDC may not achieve its objectives in the absence of demonstrated support by MIA.
32. DDC is assumed to provide a monitoring and oversight role, its reporting arrangement to the
Superintendent could lead to collusion and thereby undermine its effectiveness.
Recommendation 33. The Minister of Internal Affairs should provide support to the efforts of the District Development
Committees to make them more effective and responsive to the districts’ needs.
34. DDC should report to the Minister of MIA through the CDSS, with quarterly reports submitted on
its operation and status of development projects in the districts. The reporting should include
deviations and recommendation for remedial actions.
Management’s Response 35. Audit Observation Memorandum was submitted to former Minister Ambullai Johnson, Program
Manager George, and MIA Comptroller Sarlee. As of August 2010, no response was provided by
management. Management Letter was also submitted in August 2010 but no responses were
provided as of October 2010.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
12 Promoting Transparency, Accountability, Integrity and Fiscal Probity
DETAILS OF GRAND KRU COUNTY DEVELOPMENT FUND PROJECTS
Trembo Project
Observation
36. The Trembo Project was the construction of a Guest House in Behwan City, Grand Kru County by
NAFAPD, an unregistered company represented by its President and Supervisor, Fayiah Henneh.
The Ministry of Commerce informed me that NAFAPD does not exist as a legal entity to
conduct business in Liberia, as confirmed by the Ministry of Commerce and Industry on 22 July
2008.
37. In order to further authenticate the legal existence of NAFAPD, I wrote to the Ministry of
Commerce and Industry, a Government entity charged with the responsibility of regulating all
commerce and industry related activities in the country to confirm the legal status of the Liberia
Land Construction Company. The Ministry of Commerce and Industry replied and indicated that
NAFAPD does not exist as a legal entity, as per their Business Registry Data.
38. By entering into contractual agreement with the County Authorities, the Superintendent and PMC
breached Section 4.2 of Chapter 4 of the Business Law of Liberia. Section 4.2 of Chapter 4 states
“No person shall conduct or carry on a business unless he has registered such business with the
Assistant Minister, who shall perform his duties under this chapter subject to the direction and
control of the Minister of Commerce and industry. Any person violating the provisions of this
section shall be subject to a fine not less than US$10.00 and not more than US$1,000.00 or
imprisonment not less than one month or more than one year or both”. Section 32 of the PPC
Act, 2005 also requires that companies contracted for Government projects are duly registered
and have tax identifications.
39. The contract for this project was signed on 15 April 2008 between the Grand Kru County PMC
and NAFAPD at the cost of US$10,000.00 to construct a Guest House in Behwan, Trembo
Statutory District.
40. Article lll of the contract stipulated that the contractor shall effect all works on the contract
within a period of nine months whilst Article V stipulated that the contract shall be completed in
three months commencing from the date of the signing of the agreement. These two provisions
in the contract were contradictory as one provision indicated 9 months and the other indicated 3
months completion time frame.
41. It was stipulated that the first payment of 35 percent would be paid upon signing of the contract
to complete 40 percent of the work. The second payment of 35 percent would be paid after 75
percent completion of the project. Third & final Payment of 30 percent would be paid upon
completion of the project.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
13 Promoting Transparency, Accountability, Integrity and Fiscal Probity
42. The contract document further stipulated that “10
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contr
maintenance period”.
43. All these payment terms were violated, as indicated below:
Table 6: Gross Payment on the Trembo Project as per Voucher and Bank Statement
44. A payment voucher was raised on 1
contractor Fayiah Henneh of NAFAPD to the tune of US$9,650.08. This amount was booked on
the Bank Statement on
contractor Fayiah Henneh, repres
45. As noted the check number on the
the Bank Statement, but the payee and the amount on both the voucher and the Bank
Statement were the same.
Project Status
46. The Project was inspected in February 2009. Since 15 April 2008, the date the contract was
signed, the project has not started at all. Community members spoken to indicated that since
the contractor took their money and returned with five bundles of
seen him. See photo of the project site
Photo 1: Paramount Chief and Elder Stand at Designated Site of the Trembo Project
Date Payee
4/23/2008 Fayiah Henneh
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
The contract document further stipulated that “10% retention would
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
All these payment terms were violated, as indicated below:
Gross Payment on the Trembo Project as per Voucher and Bank Statement
A payment voucher was raised on 18 April 2008 with check number 7877
contractor Fayiah Henneh of NAFAPD to the tune of US$9,650.08. This amount was booked on
on 23 April 2008 on check number 787722 paid in the name of the
, representing 96.5 percent of the total contract
As noted the check number on the payment voucher was different from the check number on
the Bank Statement, but the payee and the amount on both the voucher and the Bank
Statement were the same.
Project was inspected in February 2009. Since 15 April 2008, the date the contract was
signed, the project has not started at all. Community members spoken to indicated that since
the contractor took their money and returned with five bundles of 14-gauge zinc, they have not
seen him. See photo of the project site and community members at the project site:
Paramount Chief and Elder Stand at Designated Site of the Trembo Project
Payee Check Number Amount
Fayiah Henneh 787722 $9,650.08
would be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
actor at the expiration of the
Gross Payment on the Trembo Project as per Voucher and Bank Statement
check number 787719 in the name of
contractor Fayiah Henneh of NAFAPD to the tune of US$9,650.08. This amount was booked on
on check number 787722 paid in the name of the
enting 96.5 percent of the total contract cost.
voucher was different from the check number on
the Bank Statement, but the payee and the amount on both the voucher and the Bank
Project was inspected in February 2009. Since 15 April 2008, the date the contract was
signed, the project has not started at all. Community members spoken to indicated that since
gauge zinc, they have not
project site:
Paramount Chief and Elder Stand at Designated Site of the Trembo Project
Amount
$9,650.08
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
14 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Photo 2: Paramount Chief and Community Members at Designated Site of the Trembo Project
Risk
47. Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
procurement schemes.
48. Conducting business with companies that do not have the potential and capacity to deliver could
undermine the effective and efficient
to deliver on contractual terms.
49. The lack of adherence to payment terms could lead
abscond with public monies without immediate remedy.
50. Lack of assessment reports and certificate
could lead to lack of completion of projects within stated time frame
51. The non-provision of supporting financial documents to support payments made to contractors
signals poor financial management, as funds could be disbursed without any authorization.
52. Contracts given to entities not registered could deny
developmental purposes, as an illegally operated company may not pay taxes.
Recommendation
53. The following persons should be held jointly and severally accountable for negligently awarding a
contract to an unregistered entity named NAFADP in contra
2005 and Section 4.2 of Chapter 4 of the Business
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
Paramount Chief and Community Members at Designated Site of the Trembo Project
Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
Conducting business with companies that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
The lack of adherence to payment terms could lead to situations wherein contractors
abscond with public monies without immediate remedy.
reports and certificates of completion show no evidence of supervision
could lead to lack of completion of projects within stated time frame.
provision of supporting financial documents to support payments made to contractors
financial management, as funds could be disbursed without any authorization.
given to entities not registered could deny Government of needed revenue required for
, as an illegally operated company may not pay taxes.
The following persons should be held jointly and severally accountable for negligently awarding a
contract to an unregistered entity named NAFADP in contravention of Section 32 of the PPC Act,
2005 and Section 4.2 of Chapter 4 of the Business Law of Liberia.
Paramount Chief and Community Members at Designated Site of the Trembo Project
Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
Conducting business with companies that do not have the potential and capacity to deliver could
use of public resources, as the company may not be able
situations wherein contractors could
of completion show no evidence of supervision. This
provision of supporting financial documents to support payments made to contractors
financial management, as funds could be disbursed without any authorization.
overnment of needed revenue required for
, as an illegally operated company may not pay taxes.
The following persons should be held jointly and severally accountable for negligently awarding a
tion of Section 32 of the PPC Act,
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
16 Promoting Transparency, Accountability, Integrity and Fiscal Probity
57. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification Numbers and current tax clearance.
58. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineer’s reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
59. The Minister of Internal Affairs should ensure that county officials implement projects on the
basis of the PPC Act, 2005, Budget Law and various financial laws including the PFM Act 2009,
Revenue Code, 2000 and CDF Guidelines prepared by MIA.
60. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
61. Minister of Internal Affairs should also ensure that all legally drawn contracts have a provision
for performance bond, duly probated by the Contractor.
Siklio Community Project
Observation
62. The Siklio Community Project is the construction of a US$10,000.00 Community Guest House in
Grand Cess City, Grand Kru County. The contract to construct this building was signed on 8 April
2008 between the Grand Kru County PMC and County Builders Construction Company, a
registered business within the Republic of Liberia, represented by its proprietor, Mr. Francis Nah
Nimene.
63. It was stipulated that the first payment of 35 percent would be paid upon signing of the contract
to complete 40 percent of the work. The second payment of 35 percent would be paid after 75
percent completion of the project. Third & final Payment of 30 percent is paid upon completion
of the project.
64. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
65. All these payment terms were violated, as indicated below:
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
17 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table 9: Gross Payment on the Siklio Project as per Voucher and Bank Statement
66. A payment voucher was raised on check number 787716 in the name of County Builders in the
tune of US$9,344.40. This amount was booked on the Bank Statement 28 May 2008,
representing 93.44 percent of the total contract sum.
Project Status 67. Inspection was done in February 2009. At the time of inspection, this project was still at
foundation level though the contract was signed on 8 April 2008 to be completed in three
months as of the date of signing the contract, meaning 8 July 2008. Below is the project that
was supposed to be completed on 8 July 2008 for which US$9, 344.40 was paid.
Photo 3: Siklio Community Guest House Project in Grand Cess City at a Standstill
Photo 4: Partial view of the Foundation of the Standstill Siklio Community Guest House in Grand Cess City
Date Payee Check Number Amount
5/28/2008 County Builders 787716 $9,344.40
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
18 Promoting Transparency, Accountability, Integrity and Fiscal Probity
68. The failure to complete the project in three months as of the date of signing the contract
constituted a breach by the contractor. My physical inspection of the project in February 2009
showed that the project was at foundation level and at a standstill.
69. Assessment report or an engineer’s report project was not availed for audit, though payments
were made. In the absence of an assessment report or an engineer’s report on the quality of
materials used during the construction, I cannot provide reasonable assurance that the
foundation was built to standard. I cannot also provide assurance that value for money is
achieved in the absence of an engineer’s report to determine whether the foundation is built to
standard.
Risk
70. Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
procurement schemes.
71. Conducting business with companies that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
72. The lack of adherence to payment terms could lead to situations wherein contractors abscond
with public monies without immediate remedy.
73. Lack of assessment reports and certificate of completion show no evidence of supervision, which
could lead to lack of completion of projects within stated time frame.
74. The non provision of supporting financial documents to support payments made to contractors
signals poor financial management, as funds could be disbursed without any authorization.
75. Contracts given to entities not registered could deny Government of needed revenue required for
developmental purposes, as an illegally operated company may not pay taxes.
Recommendation
76. Superintendent Rosalind Sneh Development Superintendent, J. Michael Wisseh, Project Planner,
PMC Chairman, Johnson T. Wreh and PMT Chairman Augustine N. Wollor are held accountable
for defaulting in their responsibilities to provide reasonable oversight of project implementation.
77. The following individuals should further be held accountable for violating payment terms:
• Superintendent Rosalind Sneh
• Development Superintendent J. Michael Wisseh
• Johnson T. Wreh, Chairman
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
19 Promoting Transparency, Accountability, Integrity and Fiscal Probity
• Michael K. W. Tarwreh, Sr., Treasurer
• E. Nyewoti Wollor, Assistant Treasurer
78. Francis Nah Nimene and his Company, County Builders, should be held for breach of contract
and made to pay general damages for such breach as the Siklio Guest House Project remains at
foundation level. County Builders was paid US$9,344.40 and failed to complete the Siklio Guest
House Project.
79. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification numbers.
80. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineering reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
81. The Minister of Internal Affairs should ensure that county officials implement projects on the
basis of the PPC Act, 2005, Budget Law and various financial laws including the PFM Law 2009,
Revenue Code, 2000 and CDF Guidelines prepared by MIA.
82. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
83. Minister of Internal Affairs should also ensure that all legally drawn contracts have a provision
for performance bond, duly probated by the Contractor.
Barclayville City Hall Project
Observation
84. The Barclayville City Hall project was awarded to LICOME, Inc. represented by its President Joel
V. Printers. This contract was entered into on 1 April 2008 to be completed in nine (9) months.
The total contract was valued at US$22,000.00.
85. It was stipulated that the first payment of 35 percent would be paid upon signing of the contract
to complete 40 percent of the work. The second payment of 35 percent would be paid after 7
percent completion of the project. Third & final Payment of 30 percent would be paid upon
completion of the project.
86. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
20 Promoting Transparency, Accountability, Integrity and Fiscal Probity
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
87. All these payment terms were violated, as indicated below:
Table 10: Gross Payment on the Barclayville City Hall Project as per Voucher and Bank Statement
88. As indicated the payment terms were violated. The first payment constituted 80.53 percent,
while the final payment constituted 19.47 percent.
Project Status
89. Inspection was conducted in February 2009. The project as seen below is roofed, no floor, no
windows, no doors and ceilings, and wall partly plastered. Also the adjoining offices at the back
have not been roofed. Beside the foundation of the hall and that of the adjoining offices which
were done with concrete blocks, the walls were constructed with dirt bricks.
90. Below is the building for which US$22,000.00 was paid and remains uncompleted as at February
2009:
Photo 5: Inside View of the Barclayville City Hall for which US$22,000.00 was paid
Date Payee Check Number Amount Percent of Total
4/4/2008 Lib Const. and Maint. Ent. Inc 787709 $17,717.00 80.53%
8/28/2008 Lib Const. and Maint. Ent. Inc 787740 $4,283.00 19.47%Total $22,000.00 100.00%
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
21 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Photo 6: External View of the Barclayville City Hall
91. The contractor blamed the delay of the project to difficulty encountered in getting construction
materials to Grand Kru. Review of financial request for the 2008/2009 fiscal period indicated that
another US$12,000.00 was requested by PMC and county officials to complete this building. This
brings the total cost to US$34,000.00, which represents 54.55 percent of increase over and
above the original contract cost.
92. No material justification and documentary evidence was provided to indicate that the contractor
should not be held accountable for not completing the project as schedule.
93. No Assessment Report, an Engineer’s Report or a Certificate of Completion of project was availed
for audit, though payments were made. In the absence of a certificate of completion, an
engineer’s report or an assessment report on the level of works done on the building, I cannot
provide reasonable assurance that the project was implemented satisfactorily. I cannot also
provide assurance that value for money was achieved in the absence of an engineer’s report to
determine whether the works done on the building were in accordance with standards.
Risk
94. Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
procurement schemes.
95. Conducting business with companies that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
22 Promoting Transparency, Accountability, Integrity and Fiscal Probity
96. The lack of adherence to payment terms could lead to situations wherein could tractors abscond
with public monies without immediate remedy.
97. Lack of assessment reports and certificate of completion show no evidence of supervision, which
could lead to incompletion of projects within stated time frame.
98. The absence of an engineer’s report, assessment report or a certificate of completion could
indicate that low quality material was used, thus denying value for money.
99. Contracts given to entities not registered could deny Government of needed revenue required for
developmental purposes, as an illegally operated company may not pay taxes.
Recommendations
100. Superintendent Rosalind Sneh, Development Superintendent, J. Michael Wisseh, Project Planner,
PMC Chairman, Johnson T. Wreh and PMT Chairman David Wichiey are held accountable for
defaulting in their responsibilities to provide reasonable oversight of project implementation.
101. The following individuals should further be held accountable for violating payment terms:
• Superintendent Rosalind Sneh
• Development Superintendent J. Michael Wisseh
• Johnson T. Wreh, PMC Chairman
• Michael K. W. Tarwreh, Sr., PMC Treasurer
• E. Nyewoti Wollor, PMC Assistant Treasurer.
102. LICOME Inc. and its President Joel V. Printers should be held for breach of contract and made to
pay general damages for such breach as the Barclayville City Hall Project remains incomplete.
LICOME Inc was paid US$22,000.00 for the Barclayville City Hall Project but failed to complete
the Project.
103. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification numbers.
104. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineer’s reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
23 Promoting Transparency, Accountability, Integrity and Fiscal Probity
105. The Minister of Internal Affairs should ensure that county officials implement projects on the
basis of the PPC Act, 2005, Budget Law and various financial laws including the PFM Act, 2009,
Revenue Code, 2000 and CDF Guidelines prepared by MIA.
106. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
107. Minister of Internal Affairs should also ensure that all legally drawn contracts have a provision
for performance bond, duly probated by the Contractor.
Gbetao Project
Observation
108. The Gbetao project is located in Picnic-Cess, Grand Kru County. It is the construction of a Town
Hall. The contract to construct Town Hall was awarded to County Builders Company represented
by its President, Francis Nah Nimene, on 7 April 2008 at the cost of US$10,000.00. The project
was to be completed in three months commencing from the date the agreement was signed, 7
July 2008. By 7 October 2008, the project should have been completed.
109. It was stipulated that the first payment of 35 percent would be paid upon signing of the contract
to complete 40 percent of the work. The second payment of 35 percent is paid after 75 percent
completion of the project. Third & final Payment of 30 percent would be paid upon completion of
the project.
110. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
111. All these payment terms were violated, as indicated below:
Table 11: Gross Payment on the Gbetao Project as per Voucher and Bank Statement
112. As indicated the payment terms were violated. The first payment constituted 94.48 percent of
the total contract value. Payment voucher was raised and check was booked on the Bank
Statement on 28 May 2008.
Date Payee Check Number Amount5/28/2008 County Builders 787712 $9,479.41
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
24 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Project Status
113. The project was inspected in February 2009. This project as seen below is still at foundation
level, and poorly attended to by the contractor. PMT Chairman N. Juwle Toe interviewed in
Picnic-Cess revealed that he was worried about the contractor lack of commitm
project. The PTM Chairman indicated that he sent a written complaint to the PMC Chairman in
Barclayville who awarded the contract. This is the project for which US$9,479.41 was paid:
Photo 7: The Status of the
114. No Assessment Report, an Engineer’s Report
availed for audit, though payments were made. In the absence of
engineer report or an assessment report
work done on the foundation was
for money was achieved in the absence of an enginee
building was built to standard.
Risk
115. Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
procurement schemes.
116. Conducting business with companies that do not have the
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
117. The lack of adherence to payment terms could lead to situations wherein contractors coul
abscond with public monies without immediate remedy.
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
roject was inspected in February 2009. This project as seen below is still at foundation
level, and poorly attended to by the contractor. PMT Chairman N. Juwle Toe interviewed in
Cess revealed that he was worried about the contractor lack of commitm
PTM Chairman indicated that he sent a written complaint to the PMC Chairman in
Barclayville who awarded the contract. This is the project for which US$9,479.41 was paid:
The Status of the Gbetao Town Hall project in Picnic Cess up to the time of GAC’s Inspection
, an Engineer’s Report or a Certificate of Completion of
though payments were made. In the absence of a certificate of com
or an assessment report, I cannot provide reasonable assurance that the
work done on the foundation was done satisfactorily. I cannot also provide assurance that value
achieved in the absence of an engineer’s report to determine whether the
built to standard.
Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
Conducting business with companies that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
The lack of adherence to payment terms could lead to situations wherein contractors coul
abscond with public monies without immediate remedy.
roject was inspected in February 2009. This project as seen below is still at foundation
level, and poorly attended to by the contractor. PMT Chairman N. Juwle Toe interviewed in
Cess revealed that he was worried about the contractor lack of commitment towards the
PTM Chairman indicated that he sent a written complaint to the PMC Chairman in
Barclayville who awarded the contract. This is the project for which US$9,479.41 was paid:
Gbetao Town Hall project in Picnic Cess up to the time of GAC’s Inspection
Certificate of Completion of the foundation was
certificate of completion, an
, I cannot provide reasonable assurance that the level of
satisfactorily. I cannot also provide assurance that value
r’s report to determine whether the
Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
The lack of adherence to payment terms could lead to situations wherein contractors could
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
25 Promoting Transparency, Accountability, Integrity and Fiscal Probity
118. Lack of assessment reports and certificate of completion show no evidence of supervision, which
could lead to lack of completion of projects within stated time frame.
119. The absence of an engineer’s report, assessment report or a certificate of completion could
indicate that low quality material was used, thus denying value for money.
120. Contracts given to entities that are not taxpayers could deny Government of needed revenue
required for developmental purposes.
Recommendation
121. Superintendent Rosalind Sneh, Development Superintendent, J. Michael Wisseh, Project Planner,
PMC Chairman, Johnson T. Wreh and PMT Chairman are held accountable for defaulting in their
responsibilities to provide reasonable oversight of project implementation.
122. The following individuals should further be held accountable for violating the contract payment
terms when they raised a payment voucher and paid to County Builders 94.48 percent of the
total contract sum as first payment when the contract stipulated 35 percent. This has put at risk
public resources as the project is abandoned:
• Superintendent Rosalind Sneh
• Development Superintendent J. Michael Wisseh
• Johnson T. Wreh, Chairman
• Michael K. W. Tarwreh, Sr., Treasurer
• E. Nyewoti Wollor, Assistant Treasurer
123. Francis Nah Nimene and his company, County Builders, should be held for breach of contract
and made to pay general damages for such breach as the Gbetao Town Hall Project remains at
the foundation level. County Builders was paid US$9,479.41, by the Grand Kru County
Authorities, but failed to complete the Gbetao Town Hall Project.
124. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification numbers.
125. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineer’s reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
126. The Minister of Internal Affairs should ensure that county officials implement projects on the
basis of the PPC Act, 2005, Budget Law and various financial laws including the PFM Act, 2009,
Revenue Code, 2000 and CDF Guidelines prepared by MIA.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
26 Promoting Transparency, Accountability, Integrity and Fiscal Probity
127. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
128. Minister of Internal Affairs should also ensure that all legally drawn contracts have a provision
for performance bond, duly probated by the Contractor.
Gyabo Project
Observation
129. The Gyabo Community Project was the construction of a Town Hall in Garraway City, Trehn
District, Grand Kru County. The contract for this project was awarded to the Behwan Contractor,
NAFAPD represented by its President, Fayiah Henneh. The contract was signed on 15 April 2008
and the project was to be completed in three months as of the date of signing, meaning the
project was to be completed 15 July 2008. The contract sum was US$10,000.
130. As indicated in preceding paragraphs, NAFAPD is not a legal entity in Liberia, as confirmed by
the Ministry of Commerce.
131. It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second payment of 35 percent is paid after 75 percent
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
project.
132. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
133. All these payment terms were violated, as indicated below:
Table 12: Gross Payment on the Gyabo Project as per Voucher and Bank Statement
134. As indicated the payment terms were violated. The first payment constituted 93.44 percent of
the total contract value. Payment voucher was raised and check was booked on the bank
statement on 23 April 2008.
Date Payee Check Number Amount
4/23/2008 Fayiah Henneh 787723 $9,344.44
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
27 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Project Status
135. This project has not started. Gyabo PMT indicated that the contractor puts the blame on bad
road condition but promised to construct the Town hall during the dry season beginning October
2009. Contractor Fayiah did not start the project.
Risk
136. Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
procurement schemes.
137. Conducting business with companies that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
138. The lack of adherence to payment terms could lead to situations wherein contractors abscond
with public monies without immediate remedy.
139. Contracts given to entities not registered could deny Government of needed revenue required for
developmental purposes, as an illegally operated company may not pay taxes.
Recommendation
140. The following persons should be held jointly and severally accountable for negligently awarding a
contract to a non-registered and an illegally operated business entity named NAFADP in
contravention Section 4.2 of the Business Law and Section 32 of the PPC Act, 2005:
• Superintendent Rosalind Sneh
• Development Superintendent J. Michael Wisseh
• PMC Chairman, Johnson T. Wreh
• PMT Chairman, Thomas K. Nugba
141. Superintendent Rosalind Sneh Development Superintendent, J. Michael Wisseh, Project Planner,
PMC Chairman, Johnson T. Wreh and PMT Chairman are held accountable for defaulting in their
responsibilities to provide reasonable oversight of project implementation.
142. The following individuals should further be held accountable for violating the payment terms
when they raised a payment voucher and paid to Fayiah Henneh of the illegal company NAFAPD
96.5 percent of the total contract sum as first payment when the contract stipulated 35 percent.
This has put at risk public resources as the project has not started:
• Superintendent Rosalind Sneh
• Development Superintendent J. Michael Wisseh
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
28 Promoting Transparency, Accountability, Integrity and Fiscal Probity
• Johnson T. Wreh, Chairman
• Michael K. W. Tarwreh, Sr., Treasurer
• E. Nyewoti Wollor, Assistant Treasurer
143. The following individuals should further be held jointly and severally accountable and made to
restitute US$9,344.44. This amount represents the total payment to the illegally operated
company, NAFAPD.
• Superintendent Rosalind Sneh
• Development Superintendent J. Michael Wisseh
• PMC Chairman, Johnson T. Wreh
• Treasurer, Michael K. W. Tarwreh, Sr.
• Assistant Treasurer, E. Nyewoti Wollor
144. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification numbers.
145. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineering reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
146. Minister of Internal Affairs should ensure that county officials implement projects on the basis of
the PPC Act, 2005, Budget Law and various financial laws including the PFM Act, 2009, Revenue
Code, 2000 and CDF Guidelines prepared by MIA.
147. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
148. Minister of Internal Affairs should also ensure that all legally drawn contracts have a provision
for performance bond, duly probated by the Contractor.
Nifao Project
Observation
149. The Nifao Project is the construction of a clinic in Po-River Middle Town, Trehn District, Grand
Kru County. The contract for this project was again awarded to County Builders Construction
Company, represented by its contractor, Francis Nah Nimene. The contract was signed on 10
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
29 Promoting Transparency, Accountability, Integrity and Fiscal Probity
April 2008 with a completion term of three months, meaning 10 July 2008. The total contract
was valued at US$10,000.
150. It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second payment of 35 percent is paid after 7 percent
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
project.
151. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
152. All these payment terms were violated, as indicated below:
Table 13: Gross Payment on the Nifao Project as per Voucher and Bank Statement
153. As indicated the payment terms were violated. The first payment constituted 96.51 percent of
the total contract value. Payment voucher was raised and check was booked Bank Statement on
5 May 2008.
Project Status
154. I inspected the project in February 2009 and at the time of inspection, contractor had not
commenced work, even though it was paid 96.51 percent of the contract sum and the check
cleared the bank on 5 May 2008.
Risk
155. Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
procurement schemes.
156. Conducting business with companies that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
157. The lack of adherence to payment terms could lead situations wherein contractors could abscond
with public monies without immediate remedy.
158. Contracts being given to entities not registered could deny government of needed revenue
required for developmental purposes.
Date Payee Check Number Amount5/28/2008 Francis N Nimene 787717 $9,651.43
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
30 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Recommendation
159. Superintendent Rosalind Sneh, Development Superintendent, J. Michael Wisseh, Project Planner,
PMC Chairman, Johnson T. Wreh and PMT Chairman Amasie Sieka are held accountable for
defaulting in their responsibilities to provide reasonable oversight of project implementation.
160. The following individuals should further be held accountable for violating payment terms when
they raised a payment voucher and paid to County Builders 96.51 percent of the total contract
sum as first payment when the contract stipulated 35 percent. This has put at risk public
resources as the project is abandoned:
• Superintendent Rosalind Sneh
• Development Superintendent J. Michael Wisseh
• PMC Chairman, Johnson T. Wreh
• Treasurer, Michael K. W. Tarwreh, Sr.
• Assistant Treasurer, E. Nyewoti Wollor
161. Francis Nah Nimene and his company, County Builders, should be held for breach of contract
and made to pay general damages for such breach as the contractor failed to commence work
on the Project up to the time of physical inspection. Francis Nah Nimene and his company,
County Builders, were paid US$9,651.43 but failed to implement the Project.
162. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification Numbers.
163. The Minister of Internal Affairs should ensure that county officials implement projects on the
basis of the PPC Act, 2005, Budget Law and various financial laws including the PFM Act, 2009,
Revenue Code, 2000 and CDF Guidelines prepared by MIA.
164. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
165. Minister of Internal Affairs should also ensure that all legally drawn contracts have a provision
for performance bond, duly probated by the Contractor.
Superintendent Rosalind Sneh’s Response to the Draft Management Letter
CDF Community Projects 166. The GAC holds me accountable for defaulting in my responsibility to provide reasonable
oversight of the projects. I am also held liable for violating contract terms and for payment to
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
31 Promoting Transparency, Accountability, Integrity and Fiscal Probity
some illegal entities such as NAFAPD. That I along with others should restitute certain amount as
indicated on pages 11, 14, 19, 26, 27, and 37.
167. Response: In keeping with section 8 of the Budget Law governing County Development Funds,
Roman # X, the primary mandate of the PMC shall be to serve as the technical arm of the
Council in identifying and costing of projects; to oversee, coordinate and monitor the
implementation of approved projects; to ensure that all financial transaction documents are in
conformity with the public procurement regulations; to make quarterly report and submit said to
the County Superintendent, the County Legislative Caucus and the Council. Exhibits 2
168. Therefore, it is the statutory responsibility of the PMC to provide that oversight. The PMT
elected by the community selects their contractor and presents same to the PMC. Once the PMC,
as the technical arm certifies the contractor, the Superintendent cannot reject. The PMC again
prepares the contract with all the payment terms stipulated and once the contract is signed by
all parties the Superintendent countersign same.
169. The actual payments are by the PMC even though the Superintendent approves the voucher. So
when I asked about the payment terms on the voucher, I am told by the PMC that due to the
difficulty in transporting the materials to Grand Kru County, the payment was ordered once,
instead of three installments. Therefore, I Rosalind Sneh cannot be held accountable for the
PMC’ responsibility.
Auditor General’s Position 170. I have noted the Superintendent response and appreciate the explanation provided. But such
explanation was not substantive to cure the opportunity loss to the citizens of Grand Kru County.
Instead of responding to the substantive issues raised in the report, Superintendent Sneh
blamed PMC and the PMT.
171. The Superintendent in her response provided a material justification why she and other Grand
Kru County officials should be held liable. She rightly indicted herself by saying:
“Therefore, it is the statutory responsibility of the PMC to provide that oversight. The PMT elected by the community selects their contractor and presents same to the PMC. Once the PMC, as the technical arm certifies the contractor, the Superintendent cannot reject. The PMC again prepares the contract with all the payment terms stipulated and once the contract is signed by all parties the Superintendent countersign same. “ “The PMC again prepares the contract with all the payment terms stipulated and once the contract is signed by all parties the Superintendent countersign same. The actual payments are by the PMC even though the Superintendent approves the voucher. So when I asked about the payment terms on the voucher, I am told by the PMC that due to the difficulty in transporting the materials to Grand Kru County, the payment was ordered once, instead of three installments.”
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
32 Promoting Transparency, Accountability, Integrity and Fiscal Probity
172. The Superintendent admitted counter-signing the contracts, meaning that she was aware of the
status of the contractors. She also authorized payments to the contractors and cannot divorce
herself from the legal and financial dealings on the projects. Superintendent Sneh placed her
legal reliance on the Budget Law 2007/2008. But she failed to also note that there is no
provision in the Budget Law 2007/2008 that provides her the substantive authority to attest to
contracts or approve payment vouchers. The Budget Law only provides that the Superintendent
serves as the second A signatory to the CDF bank account, signing checks only in the event that
the Assistant Superintendent for Development is absent.
173. As noted in the observation, payments were to be made in three installments, but examination
of the Bank Statement and vouchers revealed that a total of US$69,469.28 of the total contract
cost in the tune of US$72,000.00 were paid on six projects . This represents 96.49 percent of
the total contract sum of the projects. These payments were made without much regard to the
payment terms in the contracts, contracts that were attested by Superintendent Sneh.
Superintendent Sneh provide the following unsubstantiated excuse for her lack of oversight:
“So when I asked about the payment terms on the voucher, I am told by the PMC that due to the difficulty in transporting the materials to Grand Kru County, the payment was ordered once, instead of three installments.”
174. By her own admission, Superintendent Sneh is indicating that she was aware that contract
payments terms were being violated. Instead of insisting on the payment terms to protect public
resources in the event of a default on the part of the contractor, she duly approved all the
payments. Superintendent Sneh did not produce a single document to support her contention
that she queried the violation of the payment terms.
175. A Fayiah Henneh, President and Supervisor of NAFAPD abandoned the projects and fled from
Grand Kru County. NAFAPD, as confirmed by the Ministry of Commerce and Industry, is an illegal
establishment. Mr. Henneh did not perform on the contracts, though the Superintendent and her
officials made a total payment of US$18,994.44 on the two projects. County Builders
Construction Company also defaulted in the implementation of the Gbeatao Town Hall Project
and Nifao Clinic Project after receiving US$19,130.84. The Gbeatao Project is at foundation level
whereas the contractor has not commenced work on the Nifao Town Project. This has denied
the citizens of Grand Kru timely benefit of development projects financed by the Government of
Liberia. Superintendent and her officials did not provide any evidence of a legal action taken to
enforce performance by the contractors.
176. By not doing a simple background check on the NAFAPD, the Superintendent and her officials
violated Section 32 (1f) of the PPC Act, 2005 by knowingly awarding contract to an illegal entity.
A violation of the PPC Act, 2005 is punishable under Section 138 (1) of the PPC Act, 2005. They
also violated Section 4.2 of the Business Law. Section 4.2 of Chapter 4 states “No person shall
conduct or carry on a business unless he has registered such business with the Assistant
Minister, who shall perform his duties under this chapter subject to the direction and control of
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
33 Promoting Transparency, Accountability, Integrity and Fiscal Probity
the Minister of Commerce and industry. Any person violating the provisions of this section shall
be subject to a fine not less than $10.00 and not more than $1,000.00 or imprisonment not less
than one month or more than one year or both”.
177. Superintendent Sneh provided the following non-material justification to explain her lack of
oversight:
“Therefore, it is the statutory responsibility of the PMC to provide that oversight. The PMT elected by the community selects their contractor and presents same to the PMC. Once the PMC, as the technical arm certifies the contractor, the Superintendent cannot reject”.
178. By her assertions, Superintendent Sneh recognized the statutory responsibility of the PMC and
PMT to provide oversight but failed to recognize her own statutory responsibility. She is the
Superintendent of the County and a signatory to the CDF account. She counter-signed a
contract in which there is a clause that clearly indicated that NAFAPD is a company duly
registered and operating under the laws of Liberia. This was a material misinformation as it is
confirmed that NAFAPD does not exist as a legal company in Liberia.
179. By Superintendent Sneh inaction to remedy material breaches in contract performance and her
lack of oversight, the Government of Liberia was exposed to fraudsters operating illegal
companies for the purpose of stealing funds from Government coffers through fraudulent
procurement schemes. Superintendent Sneh should accept full responsibility for the role she
played on the CDF, as she signed contracts and financial documents.
180. Superintendent Sneh’s reliance on the Budget Law 2007/2008 was unsupported as the same
Budget Law did not make provision for her to sign contracts and financial documents. By affixing
her signature to contracts and financial documents in contravention of the Budget Law
2007/2008, she became an active participant in the expending of CDF monies to illegally
operated contractors, and contractors that have not performed, although received payments.
181. Superintendent Sneh failed to note that the doctrine of impossibility, impracticability, and
frustration of purpose excuse performance only if a supervening circumstance was not
reasonably contemplated or foreseeable when the contract was made. Unreasonable rain and
deplorable road condition in April to November 2008 is not such a circumstance in Liberia, much
less Grand Kru County. Bad road condition is an ordinary business risk in Grand Kru County. Bad
road condition is no news in Liberia, much less a county that is deemed as the “forgotten”
County due to its bad road and poor infrastructure. Additionally, the purchase of materials in
Monrovia is noted business practice in Liberia and therefore cannot be used as excuse to
contravene provisions of contracts and agreements.
182. Superintendent Sneh’s responses are therefore not substantive. They cannot be sustained
administratively or judicially when challenged on the merits. I maintain all my recommendations.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
34 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Barclayville Generator House Project
Observation
183. Barclayville City has two projects: The construction of a generator house, and a City Hall in
Barclayville, Grand Kru County.
184. The generator house project was not among the original projects budgeted for in the County
Resolution. It was however financed from the contingency
various projects earmarked in the County’s resolution.
185. This was based on a memorandum from the Minister of Internal Affairs inst
use US$5,317.00 of its development fund to construct the generato
administration building in Barclayville City when the County, besides the Development fund, has
allotment within its budget for such project.
186. The PMC however yielded to the MIA request and awarded the contract to County Engineer
Nyandeh Sieh, on 19 April 2008 at the cost of US
US$4,000.00 for contingency and disbursed same to Mr. Sieh. The check was booked on the
bank on 24 April 2008:
Table 14: Gross Payment on the Barclayville City Generator
and Bank Statement
Project Status 187. Inspection was conducted in February 2009. The 30KVA UNDP donated generator has been
installed in this building. The building is under construction and needs steel door to complete
Below is the status of the project for which US$4,000.00 was paid to County Engineer Sieh:
Photo
Date
4/24/2008 Nyandeh Sieh
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
Barclayville Generator House Project
has two projects: The construction of a generator house, and a City Hall in
Barclayville, Grand Kru County.
The generator house project was not among the original projects budgeted for in the County
Resolution. It was however financed from the contingency fund of US$4,
various projects earmarked in the County’s resolution.
This was based on a memorandum from the Minister of Internal Affairs inst
317.00 of its development fund to construct the generato
administration building in Barclayville City when the County, besides the Development fund, has
allotment within its budget for such project.
The PMC however yielded to the MIA request and awarded the contract to County Engineer
andeh Sieh, on 19 April 2008 at the cost of US$5,317.00. The PMC however only had
US$4,000.00 for contingency and disbursed same to Mr. Sieh. The check was booked on the
Gross Payment on the Barclayville City Generator House Project as per Voucher
was conducted in February 2009. The 30KVA UNDP donated generator has been
installed in this building. The building is under construction and needs steel door to complete
Below is the status of the project for which US$4,000.00 was paid to County Engineer Sieh:
Photo 8: Barclayville Generator House @ US$4,000.00
Payee Check Number
Nyandeh Sieh 787724
has two projects: The construction of a generator house, and a City Hall in
The generator house project was not among the original projects budgeted for in the County
,000.00 allocated for the
This was based on a memorandum from the Minister of Internal Affairs instructing the County to
317.00 of its development fund to construct the generator house to the county
administration building in Barclayville City when the County, besides the Development fund, has
The PMC however yielded to the MIA request and awarded the contract to County Engineer
5,317.00. The PMC however only had
US$4,000.00 for contingency and disbursed same to Mr. Sieh. The check was booked on the
House Project as per Voucher
was conducted in February 2009. The 30KVA UNDP donated generator has been
installed in this building. The building is under construction and needs steel door to complete.
Below is the status of the project for which US$4,000.00 was paid to County Engineer Sieh:
Barclayville Generator House @ US$4,000.00
Amount
$4,000.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
35 Promoting Transparency, Accountability, Integrity and Fiscal Probity
188. No Assessment Report, an Engineer’s Report or a Certificate of Completion of project was availed
for audit, though payments were made. In the absence of a certificate of completion, an
engineer report or an assessment report, I cannot provide reasonable assurance that the project
was implemented satisfactorily. I cannot also provide assurance that value for money was
achieved in the absence of an engineer’s report to determine whether the building was built to
standard.
Conflict of Interest
189. I observed that Sieh, besides being an individual without attachment to any registered
construction company, is an employee of Grand Kru County Administration with payroll number
07-77-111-0007. I further observed that though Sieh was employed by the MIA in 2006 as
Engineer, but he is on the EDP payroll as Development Coordinator. This is a gross violation
of Article 90 (b) of the Constitution and Section 131 (1C), 4, and 5 of the PPC Act, 2005.
190. MIA educational qualification listing indicates that Mr. Sieh is a high school graduate serving as
county engineer.
Risk
191. The use of the CDF projects contingency fund to construct a generator house that could be
financed from the funding provided the county through the National Budget could undermine the
undertaking of urgent development projects financed with funding earmarked under
contingency.
192. Conflict of interest could undermine value for money decision making, as contracts could be
awarded on the basis of familial and professional relationship rather than in the general interest
of the citizen of Grand Kru County.
Recommendation
193. The Minister of Internal Affairs should ensure that the development funds are used for
development purposes and that the Council decisions are respected.
194. County Engineer Nyandeh Sieh should be held accountable for contravening Section 131 (1c), 4,
and 5 of the PPC Act, 2005 and Article 90 (b) of the 1986 Constitution, which prohibit conflict of
interest.
195. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification numbers.
196. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineer’s reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
36 Promoting Transparency, Accountability, Integrity and Fiscal Probity
197. Minister of Internal Affairs should ensure that county officials implement projects on the basis of
the PPC Act, 2005, Budget Law and various financial laws including the PFM Law 2008, Revenue
Code 2000 and CDF Guidelines prepared by MIA.
198. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
Superintendent Rosalind Sneh’s Response
Barclayville Generator House:
199. As you rightly indicated, the construction of the generator house for the Administrative Building
from the CDF was authorized by the Minister of Internal Affairs with acquiesce of the Caucus.
The project was given to the County Authority to implement .The BOQ and the Cost Estimate of
the project was done by UNOPS and MIA with no workmanship or labor cost included. The
County Authority therefore used an employee, a general builder who was the County Engineer.
200. The person who held the post before tenure was Development Coordinator. This is why it was
on the EDP payroll. It was the very MIA, though its template that changed the title to County
Engineer. This is not conflict of interest. The house is concrete materials, very spacious and only
needs steel door for final completion. The total cost was US$5,317.00 and US$4,000.00 paid; the
balance US$1,317.00 is needed to purchase, transport and install the steel door. Exhibits 3.
Auditor General’s Position 201. I noted the Superintendent response that the project was predicated on an instruction from the
Ministry of Internal Affairs. I also noted her response that the BOQ and cost estimate of the
project was done by UNOPs and MIA with no workmanship or labor cost included
202. The Superintendent in her response failed to address the substantive issue and according to her
awarding contract to an employee is not conflict of interest. The Superintendent stated that “The
County Authority therefore used an employee, a general builder who was the County Engineer.
The person who held the post before tenure was Development Coordinator. This is why it was
on the EDP payroll. It was the very MIA, though its template that changed the title to County
Engineer. This is not conflict of interest.”
203. Nyandeh Smith is the County Engineer of Grand Kru County. He was also the vendor on the
project paid US$4,000.00. This is conflict of interest and a violation of Article 90(a) of the
Constitution of Liberia and Section 131 (1c) of the PPC Act, 2005 punishable under Section 138
(1) of the PPC Act, 2005. Payments were made in the name of County Engineer and the
Superintendent failed to produce receipts of materials purchased by the County Engineer.
204. Though the project was instructed by MIA, payment for the purchase of materials for this project
should have been made to vendor and not the County Engineer. The County Engineer is an
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
37 Promoting Transparency, Accountability, Integrity and Fiscal Probity
employee of Grand Kru County with an assigned payroll number. He should not be paid for
services rendered the county, because he is just performing his duties for which he is receiving
pay. The action of the Superintendent and her officials to pay the County Engineer was also a
breach of Article 90 (a) of the Constitution of Liberia.
Bolloh Project
Observation
205. The Bolloh community project is the construction of a school building in Barfowin Town, Doro
Statutory District, Grand Kru County. The Statutory District Superintendent is D. Slaymu Blamoh.
206. The Bolloh contract was entered into on 7 April 2008 between the Bolloh Community
represented by its Project Management Team Chairperson, F. Greenfield Bropleh, and the
contractor, Mr. Dennis Wiah who is a member of the PMT. The contract was stipulated to
be completed in 3 months, which was 7 July 2008. The contract value US$10,000.00.
207. It was stipulated that the first payment of 35 percent would be paid upon signing of the contract
to complete 40 percent of the work. The second payment of 35 percent would be paid after 75
percent completion of the project. Third & final Payment of 30 percent would be paid upon
completion of the project.
208. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
209. All these payment terms were violated, as indicated below:
Table 14: Gross Payment on the Bolloh Project as per Voucher and Bank Statement
210. The first payment constituted 94.72 percent of the total contract value. Payment voucher was
raised on 9 April 2008 and check was booked on 18 April 2008.
Conflict of Interest
211. A review of the contract file presented by the Grand Kru County PMC revealed that Mr. Dennis T.
Wiah, the contractor, is a member of the Bolloh Community PMT serving in the capacity as a
Project Technician. This is gross violation of Article 90 of the Constitution and Sections 131 (1C),
4 and 5 of the PPC Act, 2005 which prohibit conflict of interest.
Date Payee Check Number Amount4/18/2008 Dennis Wiah 787710 $9,472.30
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
38 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Project Status 212. Project was inspected in February 2009
abandoned. Below is the structure for which US$9,472.30 was paid
the yard:
Photo 9: Bolloh District School Project in Barfow
Risk
213. Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
procurement schemes.
214. Conducting business with individuals that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
215. The lack of adherence to payment terms could lead
with public monies without immediate
216. Lack of assessment reports and certificate of completion show no evidence of supervision, which
could lead to lack of completion of projects within stated time frame and cost over runs.
Recommendation
217. PMT Project Technician Dennis Wiah should
US$9,472.30 for not delivering on contractual terms.
218. PMT Project Technician Dennis Wiah should be held accountable for contravening Article 90 of
the Constitution and Sections 131 (1C), 4, and 5 of the
interest.
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
Project was inspected in February 2009 and during my inspection, the project
abandoned. Below is the structure for which US$9,472.30 was paid with only sticks planted in
Bolloh District School Project in Barfowin Town School @ US$9,472.30
Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
Conducting business with individuals that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
to deliver on contractual terms.
The lack of adherence to payment terms could lead to situations wherein contractors abscond
with public monies without immediate remedy.
Lack of assessment reports and certificate of completion show no evidence of supervision, which
could lead to lack of completion of projects within stated time frame and cost over runs.
PMT Project Technician Dennis Wiah should be held accountable and made to restitute
US$9,472.30 for not delivering on contractual terms.
PMT Project Technician Dennis Wiah should be held accountable for contravening Article 90 of
the Constitution and Sections 131 (1C), 4, and 5 of the PPC Act 2005 for engaging in conflict of
and during my inspection, the project has been
with only sticks planted in
in Town School @ US$9,472.30
Failure to adhere to the provisions of the PPC Act, 2005 could lead to various forms of fraudulent
Conducting business with individuals that do not have the potential and capacity to deliver could
undermine the effective and efficient use of public resources, as the company may not be able
situations wherein contractors abscond
Lack of assessment reports and certificate of completion show no evidence of supervision, which
could lead to lack of completion of projects within stated time frame and cost over runs.
d accountable and made to restitute the entire
PMT Project Technician Dennis Wiah should be held accountable for contravening Article 90 of
PPC Act 2005 for engaging in conflict of
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
39 Promoting Transparency, Accountability, Integrity and Fiscal Probity
219. The Minister of Internal Affairs should ensure that contracts are awarded only to entities that are
registered with the Ministry of Commerce as well as those that have Articles of Incorporation and
Tax Identification numbers.
220. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineering reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
221. Minister of Internal Affairs should ensure that county officials implement projects on the basis of
the PPC Act, 2005, Budget Law and various financial laws including the PFM Act, 2009, Revenue
Code, 2000 and CDF Guidelines prepared by MIA.
222. Particular attention should be paid to legal capacity, professional and technical qualifications,
demonstrable past performance, and financial resources and condition of companies seeking to
do projects under the CDF.
Superintendent and PMC’s Response to Audit Observation Memorandum and Draft
Management Letter
223. An audit observation memorandum and the draft management letter were submitted. The
Superintendent and County officials did not provide a response as of 26 October 2010 when this
report was being compiled.
Buah Project
Observation
224. The Buah project is the construction of a US$10,000.00 Guest House in Buah, Gee City, Grand
Kru County. It was awarded to D. Wah Hne on 14 April 2008 for a total contract sum of
US$10,000.00.
225. It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second payment of 35 percent would be paid after 7
percent completion of the project. Third & final Payment of 30 percent would be paid upon
completion of the project.
226. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
227. All these payment terms were violated, as indicated below:
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
40 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table 15: Gross Payment on the Buah Project as per Voucher and Bank Statement
228. The first payment constituted 93.46 percent of the total contract value. Payment voucher was
raised and check booked on bank statement on 30 April 2008.
Fraudulent Scheme 229. The contractor, D. Wah Hne, after receiving check # 00787718, took it to the office of Grand Kru
County Electoral District #1 Representative, Gbenimah B. Slopadoe. Representative Slopadoe
instructed his Administrative Assistant, G. Sakargepo Chea to accompany Hne to EcoBank in
Monrovia to cash the check and return to his office with the full amount.
230. Statutory Superintendent Thomas Dugbe informed me that there was a specific instruction from
a purported Buah people for the contractor to take the funds to the Buah District Representative
Office so that Representative Slopadoe and the contractor could jointly purchase the project
materials in Monrovia. But after encashing the check and while en route back to the Capitol
Building, the contractor D. Wah Hne absconded with the cash and has not been seen.
Promissory Note
231. Representative Slopadoe indicated he wanted to settle the matter. On 2 June 2008; he took
responsibility to restitute the money at the end of June 2008 and then personally go after the
contractor to recover. I was further told that he took responsibility on ground that he
recommended Hne. Exhibit 3—Promisory Note.
232. Despite the promissory note, I noted that Representative Slopadoe up to the writing of this
report is yet to fulfill his promise to restitute the entire amount of US$9,436.09.
Legal Action
233. I also learned from the Grand Kru County PMC Chairman, Johnson T. Wreh, in Barclayville that
legal action was instituted against the contractor, D. Wah Hne, in Monrovia where it was ruled
that his house in Monrovia be sold for US$10,000.00 to restitute the fund. Representative
Slopadoe confirmed the ruling but indicated that no buyer has shown an interest in the house.
Both the PMC Chairman and the Representative Slapadoe did not adduce documentary evidence
to support their assertions.
234. On 19 February 2009, Assistant Superintendent Wisseh issued a receipt indicating that
Representative Slopadoe has paid US$5,000.00 of the US$9,436.09. This amount was deposited
into the CDF account #10210185022016 on 2 February 2010; nearly a year after the receipt was
issued.
Date Payee Check Number Amount
4/30/2008 D. Wah Nhe 787718 $9,436.09
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
41 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Status of Project
235. This project did not start due to the absence of the contractor.
Risk
236. The awarding of contracts to individuals without adequate background check could lead to
awarding to unscrupulous individuals whose sole purpose is to defraud Government.
237. Awarding of a contract on a mere recommendation by a Legislator could deny value for money
decision and put public resources at risk of misappropriation.
Recommendation
238. Grand Kru County Electoral District # 1 Representative, Hon. Gbenimah B. Slopadoe, be made to
restitute the US$4,436.09 as per his promissory note.
239. Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
the PPC Act, 2005.
Forpoh Project
Observation
240. The Forpoh project is the construction of a US$10,000.00 Town Hall in Parluken Town, Forpoh
District, Grand Kru County. This contract was awarded to one Matthew Jugbo who was described
in the contract as a “professional person.”
241. It was a three month contract signed on 30 April 2008 to complete the construction of the Town
Hall. The contractor was paid the following:
Table 16: Gross Payment on the Forpoh Project as per Voucher and Bank Statement
242. The check was paid and was booked on the bank statement on 28 July 2008. This one- time
payment constituted 94.38 percent of the total contract sum.
Status of the Project
243. The contractor has abandoned the project after signing the contract. This project should have
been completed within three (3) months period as per the agreement on 28 July 2008, but has
not started.
Risk
244. The awarding of contracts to individuals without adequate background check could lead to
awarding to unscrupulous individuals whose sole purpose is to defraud Government.
Date Payee Check Number Amount7/28/2008 Mathew Jugbo 787728 $9,437.92
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
42 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Recommendation
245. Superintendent Rosalind Sneh, Assistant Superintendent for Development J. Michael Wisseh, PMC Chairman Johnson T. Wreh, Treasurer Michael K. W. Trawreh, Sr. and E. Nyewoti Wollor Should be made to restitute US$9,437.92 representing money paid to Matthew Jugbo for the construction of the Forpoh Town Hall Project for which Matthew Jugbo did not perform.
246. Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
the PPC Act, 2005.
Superintendent and PMC’s Response to Audit Observation Memorandum and Draft
Management Letter
247. An Audit Observation Memorandum and a Management Letter were submitted to the
Superintendent and County officials. No responses were provided.
Jloh Project
Observation
248. The Jloh Project is located in Betu City, Jloh Statutory District, Grand Kru County. It is a major
renovation of a school building. The Jloh/Betu contract was entered into between the PMC and
Abacus K. Nimene on 2 April 2008. Mr. Nimene was given four (4) months to complete and turn
over this project to the PMT/Community, by 2 August 2008.
249. The Project Management Team (PMT) was established to coordinate the planning of all activities
relating to the project and the processing and presentation of project documents to relevant and
concerned entities. The PMT reported to the citizens of the District. Abacus K. Nimene is a
member of the Betu PMT.
Conflict of Interest
250. The awarding of contract to a member of the PMT constitutes conflict of interest. As indicated,
the Jloh/Betu contract was entered into between the PMC and Abacus K. Nimene who is also a
member of the Betu PMT.
251. PMC and the County Authority in Barclayville had the listing of the Betu PMT members sent to
them by the Betu citizens on TCM Form dated 11 December 2007. This form listed Abacus K.
Nimene as Project Technician and yet still a contract was awarded to him.
252. It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second payment of 35 percent is paid after 7 percent
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
project.
253. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
43 Promoting Transparency, Accountability, Integrity and Fiscal Probity
The aggregate retention monies shall be
maintenance period”.
254. All these payment terms were violated, as indicated below:
Table 17: Gross Payment on the Jloh Project as per Voucher and Bank Statement
255. As indicated the payment terms were violated. The first payment constituted 94.46 percent of
the total contract value. The p
statement on 22 April 2008.
Legal Action
256. The contractor, PMT Abacus
US$10, 000.00 and failing to implement the project, was sued by the community for failing to
adhere to the completion term of the contract and for abandoning the job.
257. Development Chairman of Bet
magisterial court in Nifu where US
project by defendant Abacus K. Nimene was retrieved. This material was turned over to a ne
contractor, Joseph Nimene, hired by the community.
258. J. Jasper further indicated that their Statutory Superintendent, Amos Peter, who baffled the case
after the complaint was first reported to him, was also sued by the community along with
Abacus Nimene. This was a positive demonstration of a citizens’ action to right a wrong.
Status of Project
259. Work on this project is on
second contractor, Mr. Joseph Nimene. This is the building for which
Date
4/22/2008 Abacus K Nimene
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
The aggregate retention monies shall be released to the contractor at the expiration of the
All these payment terms were violated, as indicated below:
: Gross Payment on the Jloh Project as per Voucher and Bank Statement
As indicated the payment terms were violated. The first payment constituted 94.46 percent of
The payment voucher was raised and the check was booked on bank
statement on 22 April 2008.
The contractor, PMT Abacus Nimene, after receiving US$9,446.35 of the contract cost of
US$10, 000.00 and failing to implement the project, was sued by the community for failing to
adhere to the completion term of the contract and for abandoning the job.
Development Chairman of Betu City, J. Jasper indicated that the legal action was instituted in the
magisterial court in Nifu where US$7,446.35 worth of construction materials purchased for the
project by defendant Abacus K. Nimene was retrieved. This material was turned over to a ne
contractor, Joseph Nimene, hired by the community.
J. Jasper further indicated that their Statutory Superintendent, Amos Peter, who baffled the case
after the complaint was first reported to him, was also sued by the community along with
This was a positive demonstration of a citizens’ action to right a wrong.
Work on this project is on-going as timbers are being prepared and nailed for roofing by the
second contractor, Mr. Joseph Nimene. This is the building for which US$9,446.35 was paid:
Photo10: Status of the Jloh Project in Betu
Payee Check Number
Abacus K Nimene 787711
released to the contractor at the expiration of the
: Gross Payment on the Jloh Project as per Voucher and Bank Statement
As indicated the payment terms were violated. The first payment constituted 94.46 percent of
check was booked on bank
Nimene, after receiving US$9,446.35 of the contract cost of
US$10, 000.00 and failing to implement the project, was sued by the community for failing to
adhere to the completion term of the contract and for abandoning the job.
u City, J. Jasper indicated that the legal action was instituted in the
7,446.35 worth of construction materials purchased for the
project by defendant Abacus K. Nimene was retrieved. This material was turned over to a new
J. Jasper further indicated that their Statutory Superintendent, Amos Peter, who baffled the case
after the complaint was first reported to him, was also sued by the community along with
This was a positive demonstration of a citizens’ action to right a wrong.
going as timbers are being prepared and nailed for roofing by the
US$9,446.35 was paid:
Amount
$9,446.35
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
44 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Photo11: GAC Staff in Jloh at the Jloh Project site in discussion with Mr. J. Jasper, Betu Development Chairman
Risk
260. The awarding of contracts to individuals without
awarding to unscrupulous individuals whose sole purpose is to defraud Government.
Recommendation
261. Abacus K. Nimene should be made to restitute US$2,000.00, representing the balance
unaccounted for after court action.
262. Abacus K. Nimene should be
undermined and delayed
interest was a direct contravention of Article 90
and 5 of the PPC Act, 2005.
263. Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
the PPC Act, 2005.
Superintendent and PMC’s
Management Letter
264. An Audit Observation Memorandum and a Management L
Superintendent and County officials. No responses were provided
Jrao (Sass Town) City Project
Observation
265. The Jrao (Sass Town) project was the renovation of the Administrative Building in Jekwikpo City,
Jrao (Sass Town) Statutory District, Grand Kru County. Adolphus
Superintendent for this district.
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
GAC Staff in Jloh at the Jloh Project site in discussion with Mr. J. Jasper, Betu Development Chairman
The awarding of contracts to individuals without adequate background check
unscrupulous individuals whose sole purpose is to defraud Government.
Abacus K. Nimene should be made to restitute US$2,000.00, representing the balance
after court action.
Abacus K. Nimene should be held accountable for engaging in conflict of interest which
and delayed a development project financed with taxpayers’ funds
interest was a direct contravention of Article 90 (a) of the Constitution and Sections 131 (1C), 4
and 5 of the PPC Act, 2005.
Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
’s Response to Audit Observation Memo
An Audit Observation Memorandum and a Management Letter were submitted to the
Superintendent and County officials. No responses were provided by 28 October 2010
Jrao (Sass Town) City Project
Town) project was the renovation of the Administrative Building in Jekwikpo City,
Jrao (Sass Town) Statutory District, Grand Kru County. Adolphus
Superintendent for this district.
GAC Staff in Jloh at the Jloh Project site in discussion with Mr. J. Jasper, Betu Development Chairman
adequate background checks could lead to
unscrupulous individuals whose sole purpose is to defraud Government.
Abacus K. Nimene should be made to restitute US$2,000.00, representing the balance
accountable for engaging in conflict of interest which
project financed with taxpayers’ funds. This conflict of
of the Constitution and Sections 131 (1C), 4
Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
Response to Audit Observation Memorandum and Draft
etter were submitted to the
by 28 October 2010.
Town) project was the renovation of the Administrative Building in Jekwikpo City,
Togba, Jr is Statutory
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
45 Promoting Transparency, Accountability, Integrity and Fiscal Probity
266. The Jrao project was awarded to a local contractor,
construction company nor is he a member of any legally registered entity. He was awarded the
contract by the PMT, PMC and the County Authority. The contract was awarded on 3 April 2008
and it was to be completed in
contract. The schedule completion
267. It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second p
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
project.
268. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the ex
maintenance period”.
269. All these payment terms were violated, as indicated below:
Table 19: Gross Payment on the Jrao Project as per Voucher and Bank Statement
270. The first payment constituted 98 percent of the total contract value.
raised and the check was booked on
Status of Project
271. The Jrao project as seen below is abandoned. The contractor blamed the delay on the
unavailability of power saw to saw timbers for the building.
US$9,800 was paid:
Photo12: Status of Jrao District project in Sasstown @ 9,800.00
Date
4/29/2008 Paul Tregbe
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
The Jrao project was awarded to a local contractor, Paul Tregbe who neither has a registered
construction company nor is he a member of any legally registered entity. He was awarded the
contract by the PMT, PMC and the County Authority. The contract was awarded on 3 April 2008
be completed in three months commencing from the date of
contract. The schedule completion date was 3 July 2008.
It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second payment of 35 percent is paid after 7
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the ex
All these payment terms were violated, as indicated below:
Table 19: Gross Payment on the Jrao Project as per Voucher and Bank Statement
The first payment constituted 98 percent of the total contract value. The p
check was booked on the bank statement on 29 April 2008.
The Jrao project as seen below is abandoned. The contractor blamed the delay on the
unavailability of power saw to saw timbers for the building. Below is the project for which
Status of Jrao District project in Sasstown @ 9,800.00
Payee Check Number
Paul Tregbe 787715
Paul Tregbe who neither has a registered
construction company nor is he a member of any legally registered entity. He was awarded the
contract by the PMT, PMC and the County Authority. The contract was awarded on 3 April 2008
three months commencing from the date of the signing the
It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
ayment of 35 percent is paid after 75 percent
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
Table 19: Gross Payment on the Jrao Project as per Voucher and Bank Statement
The payment voucher was
bank statement on 29 April 2008.
The Jrao project as seen below is abandoned. The contractor blamed the delay on the
Below is the project for which
Status of Jrao District project in Sasstown @ 9,800.00
Check Number Amount
787715 $9,800.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
46 Promoting Transparency, Accountability, Integrity and Fiscal Probity
272. The excused the contractor provided was challenged by the Statutory District Superintendent
Adolphus Togba who informed me that US$1,800.00 was allocated in the contract materials
listing to purchase one German made power saw but the contractor did not buy it. The
contractor admitted to the assertion made by District Superintendent Togba’s when he indicated
to me, “I used the money on transportation”.
Risk
273. The awarding of contracts to individuals without adequate background checks could lead to
awarding of contract to unscrupulous individuals whose sole purpose is to defraud Government.
Recommendation
274. Superintendent Rosalind Sneh, Assistant Superintendent Johnson T. Wreh, PMC Chairman
Michael Wesseh, PMC Treasurer Michael J. K. Trawreh and PMC Assistant Treasurer Nyewoti
Wollor should be made to restitute US$9,800.00, representing the amount paid to the local
contractor, “Paul Tugbe. The local contractor did not perform as the project remains incomplete.
275. Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
the PPC Act, 2005.
Management’s Response
276. An Audit Observation Memorandum and a Management Letter were submitted to the
Superintendent and other County Officials, but no responses were provided.
Kplio Project
Observation
277. The Kplio project is the rehabilitations of the roads from Kayken to Big Fleneken and from Big
Suehn to Filoken, Barclayville Chiefdom, Barclayville District. The contract for this project was
awarded to Nyandeh Sieh, an employee of MIA on 4 April 2008. This was a three (3) months
contract to be completed on 4 July 2008.
278. It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second payment of 35 percent is paid after 75 percent
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
project.
279. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
280. All these payment terms were violated, as indicated below:
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
47 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table 20: Gross Payment on the Kplio Project as per Vo
281. The first payment constituted 95.50 percent of the total contract value. Payment voucher was
raised and check was booked on
Conflict of Interest
282. Sieh who signed the contract is a member of the KPLIO PMT. Besides, Nyandeh Sieh works with
the Ministry of Internal Affairs (MIA) Grand Kru County Administration as an Engineer, while a
contractor on the CDF. This is a gross violation of Article 90
131 (1C), 4 and 5 of the PPC Act, 2005.
Project Status
283. This project is yet to start. Nothing has been done by the contractor
representing 95.5 percent of contract sum has been paid
Photo 13: Status of Kplio Project: Road Rehabilitation from Kayken to Big Fleneken
Date
4/24/2008 Nyandeh Sieh
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table 20: Gross Payment on the Kplio Project as per Voucher and Bank Statement
The first payment constituted 95.50 percent of the total contract value. Payment voucher was
raised and check was booked on the Bank Statement on 24 April 2008.
Sieh who signed the contract is a member of the KPLIO PMT. Besides, Nyandeh Sieh works with
the Ministry of Internal Affairs (MIA) Grand Kru County Administration as an Engineer, while a
contractor on the CDF. This is a gross violation of Article 90 (a) of the Constitution and Sections
131 (1C), 4 and 5 of the PPC Act, 2005.
This project is yet to start. Nothing has been done by the contractor
representing 95.5 percent of contract sum has been paid. See photo of road b
Status of Kplio Project: Road Rehabilitation from Kayken to Big Fleneken
Payee Check Number
Nyandeh Sieh 787714
ucher and Bank Statement
The first payment constituted 95.50 percent of the total contract value. Payment voucher was
Sieh who signed the contract is a member of the KPLIO PMT. Besides, Nyandeh Sieh works with
the Ministry of Internal Affairs (MIA) Grand Kru County Administration as an Engineer, while a
the Constitution and Sections
This project is yet to start. Nothing has been done by the contractor, although US$9,550.00
. See photo of road below:
Status of Kplio Project: Road Rehabilitation from Kayken to Big Fleneken
Check Number Amount
787714 $9,550.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
48 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Photo14: Status of Filorkin Road up to the time of Inspection by GAC
284. It was revealed that the citizens of the community have being brushing the Filorken -Fleneken
roads on their own
Risk
285. The awarding of contracts to individuals without adequate background checks could lead to
awarding of contracts to unscrupulous individuals whose sole purpose is to defraud Government.
Recommendation
286. Nyandeh Sieh should be made to restitute US$9,550.00, representing the amount he received
and did not perform.
287. Nyandeh Sieh should further be held accountable and legally sanction for contravening Article
90(a) and Sections 131 (1C), 4 and 5 of the PPC Act, 2005.
288. Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
the PPC Act, 2005.
Superintendent Rosalind Sneh’s Response to the Draft Management Letter
Kplio Project: 289. Your observation (225) on this project is very correct.
290. Response: When it was brought to our attention that our employee, Nyandeh Sieh signed a
contract with the PMC for the Kplio Road Rehabilitation Project, and entered into contract with
the German Agro Action (GAA), we immediately requested Mr. Nyandeh Sieh to resign his post
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
49 Promoting Transparency, Accountability, Integrity and Fiscal Probity
with government because this particular case is conflict of interest. Mr. Nyandeh Sieh complied
and resigned on March 6, 2009.Exhibit 4
Auditor General’s Position 291. I have noted the Superintendent’s response that the act was a conflict of Interest. I have also
noted the action taken by the Superintendent in calling for the resignation of the County
Engineer. But the Superintendent did not adduce any evidence that Nyandeh Sieh has restituted
the US$9,550.00 paid to him for which no work was done on the roads from Kayken to Big
Fleneken and from Big Suehn to Filoken, Barclayville Chiefdom, Barclayville District.
292. She also did not provide any evidence showing that the county has taken legal action against
Nyandeh Sieh. All efforts should be made to ensure that County Engineer Sieh make immediate
restitution and pay general damages as well for the opportunity loss to the Government of
Liberia in terms of timely delivery of a development project financed by taxpayers’ monies for
which no work was performed.
Qualoh Community Project
Observation
293. The Qualoh Community Project is the construction of a School building in Gbanken, Wedabo
Chiefdom. The contract for this project was signed on 4 April 2008. The Qualoh Community was
represented by PMT Chairman, Mr. Nathaniel Kowoh, while Samuel M. Nyemah, II signed as
the contractor.
294. Project Management Team Co-chairman D. Wiefue Nyanneh indicated that the school project
comprises of twelve (12) classrooms. This project was stipulated to be completed in three
months on 4 July 2008.
295. It was stipulated that the first payment of 35 percent is paid upon signing of the contract to
complete 40 percent of the work. The second payment of 35 percent is paid after 75 percent
completion of the project. Third & final Payment of 30 percent is paid upon completion of the
project.
296. The contract document further stipulated that “10% retention shall be held from each
installment payment to cover latent defects that may be found to exist in the works completed.
The aggregate retention monies shall be released to the contractor at the expiration of the
maintenance period”.
297. All these payment terms were violated, as indicated below:
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
50 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table 21: Gross Payment on the Qualoh
Statement
298. As indicated the payment terms were violated. The first payment constituted 97.85 percent of
the total contract value. Payment voucher was raised and check was booked on
statement on 29 May 2008.
Project Status
299. The project was inspected in February 2009. From the photo the foundation for this project was
dug just few days before the audit team arrival, and as indicated this project was paid to be
completed on 4 July 2008. Below is the statu
Photo 15: Qualoh Community School Project in Gbanken, Webbo Chiefdom
300. The project was to be completed in three (3) months as of the date of signing the contract. The
contract was signed on 4t
completing the project.
Risk
301. The awarding of contracts to individuals without adequate background check could lead to
awarding of contracts to unscrupulous individuals whose sole purpose is to defraud Government.
Recommendation
302. Superintendent Rosalind Sneh, Assistant Superintendent Johnson T. Wreh, PMC Chairman
Michael Wesseh, PMC Treasurer Michael
and PMT Chairman Nathaniel Kowoh
amount paid to a “Samuel M. Nyemah”
Date Payee5/29/2008 Samuel M. Nyemah
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table 21: Gross Payment on the Qualoh Community Project as per Voucher and Bank
As indicated the payment terms were violated. The first payment constituted 97.85 percent of
the total contract value. Payment voucher was raised and check was booked on
008.
roject was inspected in February 2009. From the photo the foundation for this project was
dug just few days before the audit team arrival, and as indicated this project was paid to be
4 July 2008. Below is the status of the project for which US$9,785.17
Qualoh Community School Project in Gbanken, Webbo Chiefdom
The project was to be completed in three (3) months as of the date of signing the contract. The t April 2008. But contrary to this, the contractor, Nyemah II, is far from
The awarding of contracts to individuals without adequate background check could lead to
unscrupulous individuals whose sole purpose is to defraud Government.
Superintendent Rosalind Sneh, Assistant Superintendent Johnson T. Wreh, PMC Chairman
sseh, PMC Treasurer Michael K. W. Trawreh, PMC Assistant Treasurer Nyewot
and PMT Chairman Nathaniel Kowoh should be made to restitute US$9,785.17, representing the
paid to a “Samuel M. Nyemah” for which only the foundation of the Project was dug.
Payee Check NumberSamuel M. Nyemah 787721
Community Project as per Voucher and Bank
As indicated the payment terms were violated. The first payment constituted 97.85 percent of
the total contract value. Payment voucher was raised and check was booked on the bank
roject was inspected in February 2009. From the photo the foundation for this project was
dug just few days before the audit team arrival, and as indicated this project was paid to be
US$9,785.17 was paid:
Qualoh Community School Project in Gbanken, Webbo Chiefdom
The project was to be completed in three (3) months as of the date of signing the contract. The
April 2008. But contrary to this, the contractor, Nyemah II, is far from
The awarding of contracts to individuals without adequate background check could lead to
unscrupulous individuals whose sole purpose is to defraud Government.
Superintendent Rosalind Sneh, Assistant Superintendent Johnson T. Wreh, PMC Chairman
PMC Assistant Treasurer Nyewoti Wollor
be made to restitute US$9,785.17, representing the
for which only the foundation of the Project was dug.
Amount$9,785.17
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
51 Promoting Transparency, Accountability, Integrity and Fiscal Probity
303. Minister of Internal Affairs should ensure that County Officials award contracts on the basis of
the PPC Act, 2005.
Superintendent and PMC’s Response to Audit Observation Memorandum and Draft
Management letter
304. An Audit Observation Memorandum and a Management Letter were submitted to the
Superintendent and County officials. No responses were provided.
Purchase of Road Equipment
305. The citizens of Grand Kru County decided to purchase an earth moving equipment, one dump
truck, one new double cabin pick-up, one new motor bike, fuel oil and lubricants. This was the
major project in the County with a cost of US$199,875.00.
306. The contract was awarded to Monrovia Developer Management Corporation (MDMC). I checked
with PPCC and it was confirmed that Grand Kru did not obtained a No Objection as the
Threshold Schedule of the PPC Act, 2005 indicates that an amount above US$100,000.00 for
goods should be internationally competitively bided. This was not done and therefore led to a
violation of the Threshold provisions of the PPC Act, 2005
307. Again, the contract was sole sourced. On 7 April 2008, the Grand Kru PMC and the Monrovia
Developer Management Corporation (MDMC) entered into a contractual Agreement for the
purchase of one dump truck, one new double cabin pick-up, one new motor bike, fuel oil and
lubricants at the cost of US$199, 875.00: The table below shows the cost breakdown in the
contract:
Table 22: Contract Cost Breakdown on the Purchase of Equipment
308. The contract indicated that MDMC was to procure the equipment and deliver same to the Grand
Kru County PMC at the Freeport of Monrovia no later than 90 days after issuance of the letter of
credit by the parties. MDMC was paid on 28 May 2008 and 9 June 2008.
Item Description Qty Unit Price Total Cost (USD)
1 Pre-owned Front End Loader 1 $46,290.00 $46,290.00
2 Pre-owned Motor Grader 1 $40,760.00 $40,760.00
4 Pre-owned Dump Truck 1 $49,575.00 $49,575.00
5 New Double Cabin Pick-Up 1 $28,500.00 $28,500.00
6 New Motor Bikes 1 $2,400.00 $2,400.00
7 Fuel Oil 3000 gals $4.00 $11,700.00
9 Lubricants L/S $3,650.00
10 Administration L/S $17,000.00
Total Contract Cost $199,875.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
52 Promoting Transparency, Accountability, Integrity and Fiscal Probity
309. The contract was signed by MDMC CEO and General Manager, John S. Youboty for MDMC. The
Superintendent, Development Superintendent, PMC Treasurer and Chairman of the Legislative
Caucus signed on behalf of Grand Kru County.
310. On 6 May 2008, in fulfillment of the contract, the PMC raised voucher #0997 and 0998 in the
name of MDMC EXPRESS Inc, 73 Carey Street, Monrovia, Liberia and issued Ecobank check
#787726 and #787727 in the amount of US$167,525.00 and US$32,350.00 respectively in favor
of MDMC to pre-finance the project in line with the agreement:
Table 23: Gross Payment on the Purchase of Road Equipment as per Voucher and Bank Statement
311. As indicated, the first check was booked on the Bank Statement on 5 May 2008 and the second
check was booked on 9 June 2008. The payment included US$32,350.00 for fuel oil, lubricants
and administration. This amount was not accounted for as the equipment is still in Monrovia.
Analysis of Grand Kru Equipment to be procured by MDMC
312. On 10 August 2008, MDMC General Manager John S. Youboty addressed a progress report on
the shipment of the equipment to the Grand Kru County PMC Chairman indicating that the
equipment will arrive at the Free Port of Monrovia from 25 September 2008 to 6 October 2008.
Exhibit 4.
313. The equipment arrived and was held at the Port by the National Port Authority for duty payment
for over three months. MDMC however sought and obtained duty waiver through MIA as per the
contract. The equipment was cleared at the NPA but General Manager Youboty did not make
available delivery note to confirm that the equipment have been delivered to the PMC in keeping
with the contract.
Project Status
314. The team also observed that besides the truck and the bike, the rest of the equipment are still at
the MDMC yard on 13th Street, Sinkor. The equipment below arrived on November 2008 and has
not been delivered, thus creating an opportunity loss for the Government of Liberia and a denial
of development for the citizen of Grand Kru:
Date Payee Check Number Amount
6/9/2008 MDMC Express Inc 787726 $167,525.00
5/28/2008 MDMC Express Inc 787727 $32,350.00Total $199,875.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
53 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Photo
Photo
Photo18:
On the Grand Kru County Administration: FY 2006/07 & 2007/08
Promoting Transparency, Accountability, Integrity and Fiscal Probity
Photo16: Road Equipment Purchased for Grand Kru County
Photo17: Caterpillar Purchased from Grand Kru CDF
Photo18: Dump Truck Purchased from Grand Kru CDF
Road Equipment Purchased for Grand Kru County
ru CDF
Dump Truck Purchased from Grand Kru CDF
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
54 Promoting Transparency, Accountability, Integrity and Fiscal Probity
315. No assessment report or engineer’s report was provided to ensure that the equipment was
delivered within standard and specifications. As of 11 August 2010, the equipment was still in
Monrovia, although it was brought into Liberia in November 2008.
Risk
316. The delay in completing projects on time could deny citizens development and multiply the loss
opportunity for the Government of Liberia.
317. The lack of adequate planning for projects under the CDF could undermine timely deliverables.
Recommendation
318. The Legislative Caucus and the County officials make all efforts to ensure that the equipment is
delivered to Grand Kru to be used for development purposes.
319. MDMC CEO and General Manager, John S. Youboty for MDMC should be made to restitute
US$32,350.00 paid for administration, fuel and lubricants for which no material justification and
supporting documents were provided to acquit the payment, as the equipment was still in
Monrovia and not in the use.
320. MDMC CEO and General Manager, John S. Youboty for MDMC should be made to pay general
damages for not delivering the equipment within the specified time frame as per the contract.
321. The Superintendent, Development Superintendent, PMC Treasurer and PMC Chairman signed on
behalf of Grand Kru. They should be sanctioned for negligent oversight of CDF projects, as they
failed to take immediate remedial actions to ensure that the equipment was delivered to Grand
Kru in a timely fashion.
322. The Minister of Internal Affairs should increase oversight of CDF projects by ensuring that
engineering reports, certificates of completion and project assessments reports are done in
conjunction with the Minister of Public Works.
323. Minister of Internal Affairs should ensure full compliance by County officials with the provisions
in the PPC Act, 2005 to ensure value for money and avoid situation that could encourage conflict
of interest in procurement.
Superintendent Rosalind Sneh’s Response to the Draft Management Letter
Grand Kru Road Equipment: 324. GAC recommendation (281) calling on the County Authority and the Legislative Caucus to ensure
that the equipment is delivered to Grand Kru County for development purposes is quite in place.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
55 Promoting Transparency, Accountability, Integrity and Fiscal Probity
325. Response: A new management contract between Grand Kru County and MDMC for the transfer,
operation and management of the equipment has been concluded. The contract runs from 15th
October 2010 to 14th December 2010. Exhibit 5.
Auditor General Position
326. The Superintendent has confirmed that the equipment is still in Monrovia since it was brought in
November 2008. The Superintendent maintained:
“A new management contract between Grand Kru County and MDMC for the transfer, operation
and management of the equipment has been concluded. The contract runs from 15th October
2010 to 14th December 2010.”
327. The equipment was fully paid for and was to be delivered in August 2008. Instead it was
delivered in November 2008. It has been in Monrovia since November 2008, depriving
development to the citizens of Grand Kru County. This was a clear waste of public resources, as
of date (nearly 2 years later) the equipment is still not in use.
328. Superintendent Sneh contends that the County has again entered another agreement with the
same company that purchase the equipment, allowing the company use of the equipment for
period running between 15 October 2010 and 14 December 2010. Gran Kru County has now
entered the leasing business, as a lessor of equipment purchased with CDF for the development
of the County.
329. Superintendent Sneh provided a response that is not substantive to cure the deficiency noted. I
therefore maintain all my recommendations, as she did not even bothered to address the issue
of the US$32,350.00 for fuel and lubricant etc for which no accounting was made.
Superintendent Sneh also did not provide material justification for the payment for fuel and
lubricant in advance when the equipment had not even arrived in Liberia. The payment for fuel
and lubricant cleared the bank on 5 May 2008, while the equipment arrived in Monrovia in
November 2008 and has not been put in operation as of date, October 2010.
PMC Chairman Johnson T. Wreh’s Response to Audit Observation Memorandum
330. The project management committee of Grand Kru County extends thanks and acknowledge of
copies of the audit report for the various community projects under the County Development
Funds for FY o6/07/08. In compliance thereto we present to you our response as follow:
331. The audit observation revealed that the projects under the CDF failed in Grand Kru County.
Contrary to what has been reported in the audit report, project in Grand Kru County are
ongoing. The delay of these projects to be implemented as scheduled are due to the bad road
condition across the county which sometimes for materials to arrive at project sites, This
situation is not only affecting the CDF projects, but UN and other UN and other NGOs projects in
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
56 Promoting Transparency, Accountability, Integrity and Fiscal Probity
the county. At present, the status of these projects has improved since the team visited the
project sites.
332. The report carries it that some contracts are PMT members or public which has been considered
as a conflict of interest. However, there is no provision of the PPCC Act of the FY
06/07/08 Budget Laws forbidding any PMT from becoming a contractor. Since indeed
it has been stressed in the audit report PMT members who are contractor has been asked to
resign from the PMT and election be held within 30 days beginning March 15, 2009.
333. Bad roads are major constraint in implementing projects in Grand Kru County; yet
commitment and seriousness are guiding principle in our drive to successfully implement projects
in the County.
334. The PPCC Act: It is clear which of the provision of the PPCC Act was breached according to the
audit report. The PPCC provide transactions under exception for SINGLE SOURCE (Chapter 3:
3.2b; 5:2c; 13.3).
335. All PMT members and the contractors are mandated to complete all projects within five (5)
calendar months beginning April 1, 2009.
336. That contract s are signed between the communities through their PMT’s and contractors but not
the PMC as being reported in the audit observation report.
337. The PMT’s were not aware of Mr. Nyandeh Sieh Jr. position at the Superintendent’s office at the
time he signed the contract. Therefore, Mr. Sieh has been ask to resign as PMT member from
the Kplio Community on or before 25th March 2009.
338. Recommendation:
• That the Auditing team provides information indicating the provision of PPCC Act which was
breached;
• That the Auditing team should understanding that the community projects are not failed but
delayed.
Auditor General’s Position
339. PMC Chairman Johnson T. Wreh’s responses were not substantive. Instead he attempted to
blame the lack of performance on bad roads. Monies were paid in contravention with the
payment terms in the contract but these projects are not completed. These projects were to be
completed by latest December 2008 but during the physical verification it was noted they were
not completed by February 2009.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
57 Promoting Transparency, Accountability, Integrity and Fiscal Probity
340. PMC Chairman Johnson T. Wreh also did not provide any material evidence to indicate that UN
and other NGOs were also facing difficulties implementing projects because of bad roads. PMC
Chairman Johnson T. Wreh lives and work in Grand Kru. He is therefore quite knowledgeable of
the weather condition in Grand Kru County. The Project Management Committee and the County
authorities awarded the contracts in April and made payments in May and June 2008. PMC
Chairman Johnson T. Wreh could have waited until the dry season to award the contracts. By his
argument, he did not exercise due care as the contractors were paid in advance, again in
contravention of the payment terms.
341. PMC Chairman Johnson T. Wreh failed to note that the doctrine of impossibility, impracticability,
and frustration of purpose excuse performance only if a supervening circumstance was not
reasonably contemplated or foreseeable when the contract was made. Unreasonably rain and
deplorable road condition in April to November 2008 is not such a circumstance in Liberia, much
less Grand Kru. Bad road condition is an ordinary business risk in Grand Kru County.
342. It is welcomed that PMC Chairman Johnson T. Wreh has indicated that those members of the
PMT who have received contracts are being asked to resign. His position however that there is
no provision in the PPC, 2005 Act against conflict of interest is not supported. Section 131 (1c), 4
and 5 of the PPC Act, 2005 prohibit conflict of interest in procurement. Article 90 of the Liberian
Constitution also forbids conflict of interest.
343. PMC Chairman Johnson T. Wreh further maintained, “All PMT members and the contractors are
mandated to complete all projects within five (5) calendar months beginning April 1, 2009.” The
funding was made available in 2008 and the contractors did not deliver. Two projects did not
even start. All the contracts awarded to Fayiah Henneh did not start, although monies were paid
in advance.
344. PMC Chairman Johnson T. Wreh’s contention that he was not aware that Nyandeh Sieh, Jr was
an employee of the MIA at the time he obtained the contract is without merit. It was conflict of
interest and a contravention of Section 131 (1c), 4 and 5 of the PPC Act, 2005.
345. PMC Chairman Johnson T. Wreh’s mere explanations therefore cannot be sustained
administratively and judicially when challenged on the merits, because they are not supported by
documents, material justifications, and substantive authorities. I maintain all my
recommendations.
Assistant Superintendent for Development T. Michael Wisseh ‘s Response to Audit
Observation
346. The Audit conducted on Grand Kru Development Fund by the General Auditing Commission
Team headed by Mr. Philip M. Massaquoi provided an education as a guide of how PMC and
County Administration are to manage, disburse and account for taxpayers’ money. However,
there is a need to make some clarification on counts as indication in the report.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
58 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Count I: Failure to implement Projects
347. The CDF projects in Grand Kru County have actually failed to be implemented according to the
term and condition signed between the communities and the various contractors. However,
there are conditions in Grand Kru County that normally impede implementation in the County
that worse noting. The County is one of the most difficult counties in term of accessibility.
348. Most building materials are brought to the County sometimes by sea due to bad road condition
and when the sea gets rough; transportation by sea can also be difficult if not impossible. This is
no justification for the extreme delayed of these projects on the part of the contractors.
349. Moreover, the conditions of these projects have changed as compared to how there were when
the Auditors visited them. The problem of the CDF projects are general problem that other UN
sponsored projects in the County face. For example; the administration Building funded by
UNOPS/MIA/MPW started in March 2007 and was to complete and turn over to the County in
June 2007 but the Building was completed in 2008 and officially turn over to the County
February 2009. The projects were delayed by 16 months. Therefore we all should understand
the condition of doing project in the County. Besides the Administration Building, other projects
such as the Grand Kru women resource center, the police station, etc suffered similar
impediments due to bad roads and other associated problems
Count II: Failure to Adhere to Payment Schedule
350. The decision taken to pay various contractors as indicated in the audit report contravened the
term and condition of the contracts. We agreed with that. However, the contractors were paid
the total projects materials cost to purchase their materials at once instead of going to Monrovia
at some point in time which have the propensity of consuming nearly half of the total projects
cost due to huge transportation paying of bringing building materials to the County.
351. The contract did not reflect the realities of the County which lead to the contravention. We
promised to draw out future contracts base on realities of grand Kru County.
352. Meanwhile, the report pointed out that the PPCC Act was breached without indicating the
provision for the act that was breached to serve as guidance for future financial transactions.
Count III: Conflict of Interest
353. The project management Committee (PMC) has been informed to make show that all those who
are serving on the project management teams of the various communities and recommended by
the them as contractors should made to resign on or before March 2009 and a new election be
held to replace those affected PMT members without delay.
354. Additionally, Mr. Nyanded Sieh who is serving as employee of the Ministry of internal Affairs and
at the same contractor for GAA/BMZ was asked to resign as contractor for GAA/BMZ or
employee of MIA on or before march 15, 2009 and return to the Klipo Road Project on or before
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
59 Promoting Transparency, Accountability, Integrity and Fiscal Probity
March 20, 2009. The PMT of the Klipo Traditional Community and the Klipo people should take
the initiative to make sure that the contractor implement the project or refund the money. The
PMC and county Administration will support this action when taken.
Recommendation
• That the PMC member make sure that all those PMC member who recommended by their
various traditional Communities to serve as contractors be made to resign and new election be
held to replace them.
• That the PMC mount pressure on the PMT and the various communities to make sure that
contractors implement the projects for which they received money within the period of three
months beginning April 2009.
Assistant Superintendent for Development Wisseh’s Response to the Draft Management
Letter
355. Clarification: Failure to implement Projects: The strategy of encouraging and facilitating citizen’s
participation in community development is new; but after nearly four years of practice, it is
beginning to create a sense of responsibility and accountability at the community, district and
county levels.
356. As far as implementation of community projects in Grand Kru County is concerned, we admit
that there have been serious delays, but certainly, there is no evidence of attempt to abuse and/
or misapply the County Development Fund (CDF). Grand Kru is making every effort to comply
with the governing the use of its CDF.
357. Our response to the GAC draft audit report should be viewed in the context of the following
checklist:
• Were the CDF funds allocated to the communities by the special County Council as required
by the Budget Act: Yes;
• Did the citizens in the target area meet to decide what they wanted to do with their
development funds, and did they appoint their PMT as required by the law: Yes;
• Did the various PMTs find, and sign, contracts with contractors they honestly believe could
do the works? Yes.
• Have the projects been started: Yes (except for one out of 16)
358. Contract were endorsed/ attested/ approved by the PMC and the county authorities against the
background of three major assumptions:
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
60 Promoting Transparency, Accountability, Integrity and Fiscal Probity
• That PMT members at the community level understood what is implied in contractual
arrangements;
• That those who presenting themselves at the town level as contractors had the competency
and expertise to execute the works; and
• That the usual practice of moving objects and supplies on the head and by foot into
communities in Grand Kru could suffice for major development initiatives.
359. All these assumptions proved to be wrong. Had the PMC and the county authorities not assumed
as indicated above, the situation with implementation of the project in Grand Kru would have
been different. For us, it is a case of lessons-learnt.
360. Payment not consistent with payment terms of the contracts: This problem affects only those
projects that were the value of US$10,000.00 Payments for all other projects were made in
compliance with the contract terms. For projects value at US$10,000.00, all the contractors
complained verbally that three payment terms (35%; 35% and 30%) at different stages of
implementation made it difficult for them to procure and transport materials to various project
sites. In response to the reality and with the hope of expediting implementation, the PMC and
the county authorities, paid the contractor amounts beyond the stipulated payment schedule of
the contracts. Technically, this amounted to that effect in all the cases.
361. That the PMC and the County Authority did not document the change in payment term of the
contracts is the problem that the GAC is holding onto. This was an oversight; it is now a case of
lesson-learnt; it will not be repeated.
362. Breach of PPCC Act: GAC observation that the PPCC Act was breached is not precise. To the best
of our knowledge, all PPCC requirements were followed, except for payment outside the terms of
the US$10,000.00 contracts as discussed above.
363. Conflict of Interest. Mr. Nyanneded Sieh who is serving as employee of the Ministry of Internal
Affairs at the same time contractor for GAA/BMZ has resigned as County Construction Engineer,
he is no longer in the employ of the Ministry. Mr .Dennis Wiah who is the contractor for the Blloh
PMT has resigned from the PMT.
364. Clarification: Restitution of funds: Except for the case of the Buah Community in which the
contractor (D. Y. Nhe) absconded with the amount of US$9,436.09, no other amount from the
CDF of Grand Kru County has been misapplied or stolen. Representative, Slopadoe has
intervened in this matter – the PMC and the County authority are not liable. In general, the PMC
and the county authority have fully accounted for the CDF. Through it oversight, the PMC has
confirmed that materials have been purchased, projects have been started and at different
stages of progress.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
61 Promoting Transparency, Accountability, Integrity and Fiscal Probity
365. In almost all cases, the size of projects initiated by the various communities requires released of
the additional funds that have been approved by the Council, but are on hold.
Auditor General’s Position 366. Assistant Superintendent T. Michael Wisseh admitted that “the CDF projects in Grand Kru County
have actually failed to be implemented according to the term and condition signed between the
communities and the various contractors.” But then he defended these contractors on the same
basis that the road condition was bad when in fact some of the contractors did not start.
367. As indicated in the evaluation of the responses from PMC Chairman Johnson T. Wreh, Assistant
Superintendent Wisseh lives and works in Grand Kru County. He is keenly aware of the road
condition but contracts were awarded and monies paid in advance in April-June 2008 time
frame.
368. Assistant Superintendent T. Michael Wisseh contended, “most building materials are brought to
the County sometimes by sea due to bad road condition and when the sea gets rough,
transportation by sea can also be difficult if not impossible. This is no justification for the
extreme delayed of these projects on the part of the contractors.” This is paradoxical as
Assistant Superintendent Wisseh attempted to provide mere justifications but then pretended not
be providing justifications. The failure to deliver on time when monies were paid in advance is a
material breach. These material breaches denied timely development in the counties and created
a loss opportunity for the Government of Liberia.
369. Assistant Superintendent Wisseh further indicated, “For example; the administration Building
UNOPS/MIA/MPW started in March 2007 and was to complete and turn over to the County in
June 2007 but the Building was completed in 2008 and officially turn over to the County
February 2009. The projects were delayed by 16 months.” Assistant Superintendent Wisseh did
not provide any documentation to indicate that it took 16 months to finish the building by
UNOPS/MIA/MPW. He also did not provide document to indicate time frame for completion, as
that information will assist in evaluating the purported 16 months delayed. Furthermore, a delay
on a joint project is not sufficient material justification for delay on all contracts awarded and for
which full payment were made in advance.
370. Assistant Superintendent Wisseh contended that, “the decision taken to pay various contractors
as indicated in the audit report contravened the term and condition of the contracts. We agreed
with that. However, the contractors were paid the total projects materials cost to purchase their
materials at once instead of going to Monrovia at some point in time which have the propensity
of consuming nearly half of the total projects cost due to huge transportation paying of bringing
building materials to the County.” This is not a material justification as all the contractors were
paid in advance of performance, as he had admitted. His explanation that the payments were
made to enable contractors to purchase all the materials in Monrovia at once is not supported,
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
62 Promoting Transparency, Accountability, Integrity and Fiscal Probity
as some of the contractors did not even start the projects. There were also no material
modifications to the contract for the advance payments.
371. Assistant Superintendent Wisseh failed to note that the doctrine of impossibility, impracticability,
and frustration of purpose excuse performance only if a supervening circumstance was not
reasonably contemplated or foreseeable when the contract was made. Unreasonable rain and
deplorable road condition in April to November 2008 is not such a circumstance in Liberia, much
less Grand Kru. Bad road condition is an ordinary business risk in Grand Kru. Bad road condition
is no news in Liberia, much less a county that is deemed as the “forgotten” County due to its
bad road and poor infrastructure. Additionally, the purchase of materials in Monrovia is noted
business practice in Liberia and therefore cannot be used as excuse to contravene provisions of
contracts and agreements.
372. I have provided the provisions in the PPC Act, 2005 that were breached. Section 131 (1C), 4 and
5 prohibits conflict of interest. The threshold Schedule required competitive bid for goods
procure above US$100,000.000. Section 32 (1) stipulated nine (9) requirements, which include
ensuring that all contractors demonstrate legal capacity and financial condition to deliver on
contractual terms.
373. Assistant Superintendent Wisseh indicated further that, “additionally, Mr. Nyandeh Sieh who is
serving as employee of the Ministry of internal Affairs and at the same contractor for GAA/BMZ
was asked to resign as contractor for GAA/BMZ or employee of MIA on or before march 15, 2009
and return to the Klipo Road Project on or before March 20, 2009.” This is not a material
justification to cure the deficiency noted as regard the noted conflict of interest. As of the date,
the issue of the conflict of interest was a material deficiency and a reportable issue.
374. In the response to the draft management letter, Assistant Superintendent Wisseh did not adduce
any new substantive information beyond what he provided in the response to the audit
observation memorandum. He accepted the material deficiencies in the following responses:
“All these assumptions proved to be wrong. Had the PMC and the county authorities not
assumed as indicated above, the situation with implementation of the project in Grand Kru would
have been different. For us, it is case of lessons-learnt.”
“That the PMC and the County Authority did not document the change in payment term of the
contracts is the problem that the GAC is holding onto. This was an oversight; it is now a case of
lesson-learnt; it will not be repeated.”
“Breach of PPCC Act: GAC observation that the PPCC Act was breached is not precise. To the
best of our knowledge, all PPCC requirements were followed, except for payment outside the
terms of the US$10,000.00 contracts as discussed above.”
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
63 Promoting Transparency, Accountability, Integrity and Fiscal Probity
375. Merely indicating that “to the best of our knowledge” PPCC requirements were followed is not
material evidence. Assistant Superintendent Wisseh did not submit bill documents or a No
Objection from PPCC for the purchase of the equipment. Section 32 of the PPC Act, 2005 also
required that all companies that are contracted are legally registered companies in Liberia. This
was not the case in Grand Kru, as NAFADP is not a registered company in Liberia. Section 131 of
the PPC Act, 2005 also prohibits conflict of interest. Superintendent Sneh and Assistant
Superintendent Wisseh have admitted that indeed there was evidence of conflict of interests on
the part of County Officials and members of the PTM securing contracts on the CDF.
376. Assistant Superintendent Wisseh provided the following material false information:
“Clarification: Restitution of funds: Except for the case of the Buah Community in which the
contractor (D. Y. Nhe) absconded with the amount of US$9,436.09, no other amount from the
CDF of Grand Kru County has been misapplied or stolen. Representative, Slopadoe has
intervened in this matter – the PMC and the County authority are not liable. In general, the PMC
and the county authority have fully accounted for the CDF. Through it oversight, the PMC has
confirmed that materials have been purchased, projects have been started and at different
stages of progress.”
377. It is indicated in the report that Representative Gbenimah B. Slopadoe has paid US$5,000.00 of
the US$9,436.09. Development Superintendent T. Micheal Wisseh issued a receipt to
Representative Slopadoe, dated 19 February 2009.
378. It is further instructive to note that the Assistant Superintendent did not provide any
documentation to support his contention that besides the Buah Community, “the CDF of Gran
Kru County has been misapplied or stolen.” Assistant Superintendent did not provide proof of
recovery of monies given Fayiah Hinneh for which no work was performed, nor did he provide
evidence and material justification for funds paid to MMDC in the tune of US$32,350.00 for fuel
and lubricant when the equipment had not even arrived. Besides the Generator House, not a
single project in Grand Kru succeeded but funds were paid.
379. Assistant Superintendent Wisseh mere explanations therefore cannot be sustained
administratively and judicially when challenged on the merits, because they are not supported by
documents, material justifications, and substantive authorities. I maintain all my
recommendations.
Grand Kru County Sports Fund Unaccounted For
Observation
380. The Government of Liberia in its 2006/2007 and 2007/2008 National Budgets allocated
US$3,333.00 and US$13,333.00 respectively for National Football Development to every county
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
64 Promoting Transparency, Accountability, Integrity and Fiscal Probity
for sports. The two allotments were appropriated in the budget of the Ministry of Youth and
Sports (MY&S) for Sports Development in Grand Kru County.
381. A review of MY&S report revealed that the disbursement for 2006/2007 was signed for by Grand
Kru Sports Commission on check 103342#. The 2007/2008 appropriation in the amount of
US$8,321.00 was also disbursed on check # 225954.Exhibit 5.
Table24: Grand Kru County Sports Allotment and Disbursement for 2006/2007 &
2007/2008
382. I also observed that the Grand Kru County Sports Commission was appointed by the County
Authority to liaise with the MY&S to sign for funds made available for county sports. I further
extended my examination to the Ministry of Youths and Sports where it was confirmed that for
2006/2007, the amount of US$1,800.00 was disbursed on check #225954 to the Grand Kru
County Sports Commission, headed by Senator Cletus Wotorson.
383. The disbursement for 2007/2008 was again made to the Grand Kru Sport Commission in the
amount of US$8,321.00 on check #103342 and received by Grand Kru Sports Commission.
384. All efforts to get expenditure reports from the Grand Kru County Administration for funds
disbursed to them by MY&S for the county proved futile.
Risk
385. Undocumented and unsubstantiated financial transactions could expose public resources to
fraud, waste and abuse.
386. Undocumented and unsubstantiated transactions could also undermine public sector
accountability, transparency and probity in the management of public resources.
Recommendation
387. The Minister of Youth and Sports consult with the County Authority to appoint a Sport
Coordinator for the County.
388. The Minister of Internal Affairs should put in place a system that would discourage county
authorities from serving in dual or multiple capacities in Grand Kru County, especially as it relates
to financial management for effective check and balances.
Period Appropriation for Grand Kru
County Share of MY&S Funding
Disbursement
by MY&S to
Grand Kru
Budget variance
2006/2007 $3,333.00 $1,800.00 $1,533.00
2007/2008 $13,333.00 $8,321.00 $5,012.00
Total $16,666.00 $10,121.00 $6,545.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
65 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Superintendent and PMC’s Response to Audit Observation Memorandum and Draft
Management Letter
389. An audit observation was submitted followed by Draft management Letter but as of 28 October
2010, no responses were provided.
Missing County Generator
Observation
390. Grand Kru County was among five counties (Grand Kru, Lofa, River Gee, Grand Bassa and Grand
Cape Mount Counties) in Liberia that benefited from a 60KVA generator donated by Eugene H.
Shannon on behalf of the President of the Republic of Liberia, Madam Ellen Johnson Sirleaf, after
the general and presidential elections in Liberia.
391. During my asset verification in Grand Kru, the generator could not be located or traced. I
contacted the County Superintendent Rosalind Sneh. She referred me to the Grand Kru County
Caucus. I contacted Senate Pro-temp Cletus Wotorson in the presence of Senator Blamo Nelson,
Rep. Slopadoe and others. He indicated that the generator was traded in for three smaller ones.
The three smaller ones were destined for Barclayville, Grand Cess and Buah.
392. In Barclayville, a 12KVA KDE-14 Star KIPOR generator was seen at the County Superintendent’s
residence. This generator is currently used to light the Superintendent’s residence.
393. I also visited Grand Cess and Buah Statutory District to locate the other generators but to no
avail. Representative Slopadoe, when contacted, confirmed having the generator intended for
Buah but indicated that it was in Karloken, River Gee County. He did not provide material
justification why a generator given to Grand Kru was in another county, River Gee.
394. Upon the team returned to Monrovia, a follow up was made at the Ministry of Lands and Mines
with Minister Eugene Shannon who donated them. Minister Shannon confirmed that the
generators were given to him by a personal friend and he turned them over to the President of
Liberia for distribution.
395. Minister Shannon further indicated that Senator Wotorson and others approached him to have
the generator split into three smaller ones but he told them that he did not want to be part of
that decision. He therefore referred them to the store to do their own negotiation.
Risk
396. The generators could have been traded for a lower quality, thus increasing maintenance cost.
397. Missing two generators could have been diverted for personal use instead of the purpose for
which they were donated and distributed.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
66 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Recommendation
398. Representative Slopadoe should be made to produce the generator he indicated was in River
Gee County for audit inspection. This generator should be verified by the Superintendent when it
is recovered and evidence submitted to the GAC for audit.
399. Chairman of the Legislative Caucus Senator Wotorson should make all reasonable efforts to
ensure that the individual that received the other generator make full accounting for it, with the
necessary legal means employ to ensure to ensure full restitution. This generator should be
verified by the Superintendent when it is recovered and evidence submitted to the GAC for audit.
Superintendent Rosalind Sneh’s Response to Draft Management Letter
Missing County Generator:
400. GAC recommends that I Rosalind Sneh should be made to restitute the County generator
diverted to my residence.
401. Response: The Audit Team headed by Mr. Philip M. Massaquoi physically examined the 12 KVA
generator, which supplied current to the Superintendent residence. But what they failed to
mention is that the 12 KVA generator also provided street lighting in the City of Barclayville. In
fact, the generator was transported to the County at my own expense and not government
funds. It sounds so devilish to say that government owned generator should only supply the
residence of the City, while the County Superintendent lives in darkness. For evidence, you can
interview the residence of Barclayville City. Therefore, the Superintendent, Rosalind Sneh did not
divert government property to private use, but rather to my official residence in Barclayville City.
Auditor General’s Position 402. I have accepted Superintendent Sneh’s contention and have appropriately modified the
recommendation not make her to restitute the full value of the generator being used at her
residence. My initial recommendation was predicated on the fact that the generator is being
used at her personal residence, not an officially provided housing for the Superintendent.
403. I maintain my recommendation that the other two generators are recovered and use for the
benefit of the county.
County Sources of Income
Cellcom Contract
Observation
404. On 17 March 2008, the citizens of Barclayville, Grand Kru County represented by Superintendent
Rosalind Sneh and Cellcom Telecommunications, Inc., represented by its Chief executive officer,
Avner Nachmani entered into a fifteen (15) years lease agreement (1st April 2008-28th February
2023) for the construction of one Cellcom Towel in Barclayville at an annual rent of US$300.00.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
67 Promoting Transparency, Accountability, Integrity and Fiscal Probity
405. The agreement was only signed by the two party representatives, Rosalind Sneh and Avener
Nachmani without being witnessed by any other person from either side. Moreover, I also
observed that Superintendent Sneh as per the agreement received US$900.00 representing
advance payment for three years but failed to deposit the fund into the county’s account.
406. Superintendent Sneh presented cash receipt No. 6006 in the amount of US$900.00 for six (6)
bundles of #10 wire purchased to wire some parts of Barclayville. The receipt presented does
not bear the name of any business entity for external confirmation.
407. Besides, the receipt is dubiously written. The payment is done by the Grand Kru County
Superintendent in the amount of US$900.00 as payment for wires and the Superintendent again
signed as receiver. This is equivalent to being payer and the vendor at the same time.
Risk
408. The signing of the contract between two persons without a witness, and the failure of the
Superintendent to deposit the amount received into the Grand Kru County Account, puts the
cash at a risk of misappropriation.
409. Undocumented transactions could lead to fraud, waste and abuse of public resources.
Recommendation
410. Superintendent Rosalind Sneh is made to restitute the full amount of US$900.00 received from
the venture.
411. All funds received by county officials should be duly deposited and expended with complete
documentation.
412. The Minister of Internal Affairs should document and report on the total revenue available to
county officials so as to more truly determine the actual financial position of each county,
including Grand Kru County.
Superintendent Rosalind Sneh’s Response to the Draft Management Letter
CELLCOM Contract:
413. GAC requests that I Rosalind Sneh be made to restitute US$900.00 received from the CELLCOM
Contract.
414. Response: The US$900.00 representing rent for 3 years by CELLCOM was not deposited in
Grand Kru Development Account because the property (parcel of land) occupied by CELLCOM is
for the people of Barclayville, whom I represent in the contract. The funds were expended to
purchase wires to electrify the City of Barclayville as mentioned supra. This was done in
consultation with the City Mayor and his Council and in the interest of the citizens to see and
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
68 Promoting Transparency, Accountability, Integrity and Fiscal Probity
enjoy electricity for the very first time in their existence as a community. Exhibit 5: Receipt with
GAC.
415. GAC claims the receipt was dubiously written. The vendor signed the receipt for receiving the
cash for 6 bundles of wires and the Superintendent signed the receipt for receiving the item
because the vendor did not have “pay In Full and Delivered” stamp. GAC cannot prove that there
is no vendor signature on that receipt. What is dubious about the receipt?
Auditor General’s Position 416. The Superintendent’s contention that “the US$900.00 representing rent for 3 years by CELLCOM
was not deposited in Grand Kru Development Account because the property (parcel of land)
occupied by CELLCOM is for the people of Barclayville, whom I represent in the contract “ is not
a material justification for not depositing the proceeds into the bank account. Representing
citizens and depositing funds into an authorized bank account and expending it therefore
are not mutually exclusive initiative.
417. Superintendent Sneh did not provide any receipt showing that a six bundle of wire was
purchase. In the absence of documentary evidence, the noted deficiency cannot be
cured. I therefore maintain all my recommendations.
Bank Statement Analysis — First Account
418. I independently obtained two Bank Statements for Grand Kru County CDF. The initial Bank
Statement provided was account #102101850222016. I noted on this Bank Statement that the
US$366,666.67 for period 2006/2007 and 2007/2008 was deposited. In the other Bank Account,
Account # 10210136022019, I also noted the following deposits of which the amount of
US$100,000.00 was deposited for fiscal period 2009/2010, as detailed:
Table 25: Total Credit transaction
419. It is indicated in the table above that the US$100,000.00 was deposited on 6 July 2010. No
material justification was provided by Superintendent Rosalind Sneh and Assistant
Superintendent T. Michael Wisseh for depositing this CDF into this account when all other CDF
monies were deposited into a different account. Superintendent Rosalind Sneh and Assistant
Superintendent T. Michael Wisseh are the two signatories to this account. Exhibit 6.
Total Credit Transactions
Book Date Type of Credit Check # Amount
10/16/2006 Cash Deposit $500.00
11/20/2006 Deposit 46155 $16,000.00
9/5/2007 Deposit 46192 $670.00
7/6/2010 CDF 125468 $100,000.00
Total $117,170.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
69 Promoting Transparency, Accountability, Integrity and Fiscal Probity
420. An amount of US$17,170.00 was also deposited into this Account. As noted in my Forensic Audit
Report of 2005/2006, a total of US$16,670 was deposited into the Grand Kru County
Development Fund Account Number 10210136022019, held at the Ecobank for labor and
administrative cost. The Superintendent has also informed me that the US$500.00 was her
personal money deposited into this account.
421. As noted in the 2005/2006 Forensic Account Report, Expenditure receipts submitted by the
Superintendent of Grand Kru County (justifying the US$16,670.00 deposited into the Grand Kru
County Development Account for labor and administrative cost) totaled US$10,142.50, leaving a
balance of US$6,527.50 unaccounted for by the Superintendent and the Assistant
Superintendent for Development.
422. Reexamination of the Bank Statement revealed that US$16,260.00 was withdrawn from this
account in the name of the Superintendent and Assistant Superintendent for Development. As
stated, the Superintendent provided receipts of expenditure in the tune of US$10,142.50, leaving
a variance of US$6,118.00 unaccounted for by the Superintendent and Assistant Superintendent
for Development. The indicated withdrawals made by the Superintendent and Assistant
Superintendent for Development are detailed in the table below:
Table26: Withdrawals Made By Superintendent Sneh & Asst. Superintendent for Development Wisseh
423. I further noted the charges to Ecobank in the tune of US$1,354.47. This amount reflected below
minimum charges, debit interest charges and end of month charges.
424. The net balance in the account as of 6 July 2010 was US$99,555.53.
Risk
425. Multiple CDF accounts could be used as means to launder monies as well as siphon funds from
the Government of Liberia.
426. Undocumented and unsubstantiated withdrawals could indicate that fraud has occurred and
county officials could use multiple CDF accounts to conceal the fraudulent payments.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
70 Promoting Transparency, Accountability, Integrity and Fiscal Probity
427. Payment made to serving county officials who are already on Government payroll could
undermine the Financial Rules and create condition for misappropriation of development funds.
428. Non-adherence to the regulation set by the CDSS could make accounting for and transparent
use of the public resources difficult, as discretionary decision making could lead to fraud, waste
and abuse.
Recommendation
429. Superintendent Rosalind Sneh and Assistant Superintendent for Development T. Michael Wisseh
should be made to jointly and severally restitute US$6,118.00 representing amount paid in their
name for which no substantive authority, material justification and supporting documents were
provided during the course of the audit.
430. Account #10210136022019 is immediately closed down and the balance of US$99,555.53 is
transferred to the CDF main account at the Ecobank bank, account number 10210118522016.
Bank Statement Analysis—Second Account
431. I obtained the second account in August 2010, CDF account number 10210185022016. The total
amount deposited into the account for the period under review was US$369, 666.67, as depicted
below:
Table27: Total Credit Transaction
432. As indicated in the table above, US$366,666.67 was from the CDF and US$3,00.00. The source
of the US$3,000.00 was not disclosed.
433. The total withdrawals and direct debits were US$363,492.99. I noted US$100.00 for direct
charges. I further noted that US$19,720.40 was withdrawals. Of this amount, US$18,640.00
without material justifications, substantive authorities and supporting documentation:
Total Credit Transactions
Book Date Type of Credit Check # Amount
2/20/2008 CDF 255218 $100,000.00
5/23/2008 CDF 313570 $100,000.00
6/5/2008 CDF 46200 $166,666.67
11/11/2008 Deposit 428935 $3,000.00
Total $369,666.67
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
71 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Table28: Withdrawals without Substantive Authority & Supporting Justification
434. The table below showed amounts paid to various universities:
Table29: Grand Kru County Payment to Universities
435. As indicated in the preceding table, four (4) universities were paid in the tune of US$3,400.00. It
was further indicated that the payment of US$500.00 was a repayment to Superintendent Sneh
for her initial deposit to open the old CDF account.
Risk
436. Multiple CDF accounts could be used as means to launder monies as well as siphon funds from
the Government of Liberia.
437. Undocumented and unsubstantiated withdrawals could indicate that fraud has occurred and
county officials could use the CDF to conceal the fraudulent payments.
438. Payment made to serving county officials who are already on Government payroll could
undermine the Financial Rules and create condition for misapplication of development funds.
439. Non-adherence to the regulation set by the CDSS could make accounting for and transparent
use of the public resources difficult, as discretionary decision making could lead to fraud, waste
and abuse.
3/27/2008 M & Y Enterprise 787703 $580.40
3/26/2008 Michael K.W. Tawreh 787704 $7,540.00
9/2/2008 Michael K.W. Tawreh 787737 $5,000.00
9/2/2008 Michael K.W. Tawreh 787735 $1,300.00
9/2/2008 Michael K.W. Tawreh 787741 $1,800.00
11/7/2008 Michael K.W. Tawreh 787743 $3,000.00
$18,640.00
12/5/2008 Rosalind Sneh 787736 $500.00
$19,720.40
Date Payee Check Number Amount
9/4/2008 A.M.E University Sudsidy 787732 $800.00
9/8/2008 African Methodist University 787733 $800.00
9/5/2008 UL Forex Subsidy 787730 $1,000.00
9/8/2008 United Methodist University 787731 $800.00
$3,400.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
72 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Recommendations
440. PMC Treasurer Michael K.W. Tarwreh and Assistant Superintendent for Development J. Michael
Wisseh should be made to restitute US$18, 640.00 representing amount paid in his name for
which no substantive authority, material justification and supporting documents were provided
during the course of the audits to acquit the payments.
441. Assistant Superintendent Wisseh should be held accountable and punish for submitting fake
receipts to conceal a material misappropriation of checks written in the name of PMC Treasurer
Michael K.W. Tawreh. His action is a contravention of Section 12.31 of the Penal Law and
Regulation N-3 of the PFM Act, 2009.
Superintendent Rosalind Sneh’s Response to the Draft Management Letter
First Account:
442. That Superintendent Rosalind Sneh be made to restitute US$14,600.00 representing payments
for which no authority, justification and supporting documents were provided.
443. Response: The first Grand Kru County Development Funds Account (102101360-22019) was
opened when the GOL provided US$66,000.00 to each county under the 100-Community
Development Project of the Ministry of Internal Affairs. Of the US$66,000.00, the MIA
purchased all the road rehabilitation tools, a vehicle (pick-up), a motorbike, power-saw,
fuel/gasoline and lubricants for the project. Grand Kru County under my administration identified
the reopening of the Barclayville-Sasstown Road, which was closed for over 17 years. The MIA
reserved US$ 16,000.00 for workmanship or labor cost, which was deposited in this account on
November 20, 2006. The Superintendent and the Development were the only signatories. Earlier
I Rosalind Sneh as Superintendent was in charged with the responsibility to open the account. I
did so with US$500.00 of my own money on October 16, 2006 as initial deposit. This amount
was refunded to me from the US$16,000.00 leaving a “Balance Brought Forward” of
US$15,500.00 to be used for labor cost the project.
444. The MIA through CDSS assigned a Project Coordinator called Emmanuel Kollie, who was
responsible to pay workers on the field. The workers included Power-saw operators, side-
brushing and log bridges construction. The project was completed on March 17, 2007 when a
fleet of vehicles headed by project pick-up and followed UNMIL vehicles entered Sasstown to the
jubilation of the people of the district.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
73 Promoting Transparency, Accountability, Integrity and Fiscal Probity
Supported Withdrawals from the Account (Exhibit (6)
445. Since the passage of the 2007/2008 Budget Act commencing July 2007, a new account has been
opened (10-2101850-22-016) where all CDF monies are now being deposited.
446. Moreover, the GAC audit period does not include the 100-Community Project 2006 and therefore
should not have been mentioned in this Management Letter.
Assistant Superintendent for Development Wisseh’s Response to the Draft Management
Letter
447. Clarification for Eco Bank Account #101-101-360-220-19: Sometime in mid 2007, County
Superintendent Rosalind Tonneh Sneh and County Development Superintendent T. Michael
Wisseh opened this account in the name of “Grand Kru County Development Fund”. According to
Development Superintendent, Wisseh, Superintendent Sneh told him that the amount of
US$500.00, which was used to open the account, was her personal money and she has since
been reimbursed.
448. Shortly after the passage of the FY/06-07 budget and prior to establishment of the Project
Management Committee (PMC), Government appropriated US$66,000.00 as Grand Kru allotment
for the 100-Community Driven Project Program. Of this amount, only US$16,670.00 was
received in two checks issued by the Ministry of Finance in the name of the County:
(US$16,000.00 and US$670.00). Both checks were deposited in the account, which already had
a beginning balance of US$500.00 to make a total available balance of US$17,170.00. All funds
in this account, less the US$500.00 from the Superintendent Sneh, were intended to be used on
activities relating to the 100-C.
449. The FY/07-08 Budget Act provided for the establishment of the PMC and the opening of a new
account titled: “Grand County Development Fund Account”. The new account was opened at the
EcoBank with the number 102-101-850-220-16. With the opening of the account, all CDF from
FY/06-07-10 are deposited to this new account, instead of the Community Driven Project
Account of 101-101-360-220-19.
Date Payee Purpose Check# Amount (US$
01/23/2007 Rosalind Sneh Labor Cost 00507451 5,333.00
02/19/2007 Rosalind Sneh Labor Cost 00507452 5,000.00
04/18/2007 Rosalind Sneh Labor Cost 00507453 4,000.00
Total Withdrawal 14,633.00
Bank Balance 867.00
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
74 Promoting Transparency, Accountability, Integrity and Fiscal Probity
450. We were taken by surprise when we read in the draft report that on June 6, 2010, PMC
Treasurer, Mr. Michael K. W. Tarwreh, made a deposit of US$100,000.00 related to FY/09-10
into the old account. A further examination of our records prompted by the draft audit report
revealed that, on July 30, 2010 County Superintendent Rosalind Sneh also deposited a check in
the same old account for US$50,000.00 issued by the Ministry of Finance to the county
representing Grand Kru share of some SDF in the FY/09-10 budget.
451. We realize that both deposits were made in the old account by error due to the close similarity of
the account titles. We have since written the bank (copy attached) requesting transfer of all
deposits in the old account to the current CDF Account Titled: Grand Kru County Development
Fund Account#102-101-850-220-16.
452. We submit that the error was not intended. As you will notice, no withdrawal was ever
attempted or carried from the account since its dormancy. This is a clear indication that the
County Administration has no dealing any more with the Account Title: Grand Kru County
Development Fund bearing account #10-2101-36022019.
453. Clarification: US$3,000.00 Deposited into 102-101-850-220-16: the Ministry of Internal Affairs
provided this amount by check for the holding of the special County Council. It was deposited,
withdrawn in the name of County Superintended Rosalind Sneh, and used to pay for expenses
relating the convening of the said Council.
454. Clarification: US$500.00: PMC records do not show any payment of this amount to either PMC
Chairman Johnson T. Wreh or to Assistant Superintendent T. Michael Wisseh or to anybody.
455. Clarification: Money paid to Universities: In June 2009, the PMC did submit to the GAC the list of
beneficiaries and receipts of money paid to Universities. All the documents presented at the time
was examined and stamped by the Auditor. Copies are here with attached.
Community projects
456. Clarification on US$1, 627.00 issued in the name of T. Michael Wisseh: This amount was
intended to buy spare parts and pay for the repair of motor bike assigned to him (DS Wisseh) at
the time; and for two county power saws, which were being used to assist some of the
communities with their bridge repairs and roadside brushing work. One Kamara Aseku
repaired the motor bike from Plebo; the two power saws were repaired by Jerry Roberts from
Harper (see receipt attached).
Auditor General’s Position 457. The Superintendent in her closing stated that “the GAC Audit does not include 100-Community
Project 2006 and therefore should not have been mentioned in this Management Letter”. Her
contention cannot be supported by law or auditing standards. I am empowered to report on all
matters that come to my attention during the course of the audit. Subsequent discovery of a
material fact is one such instance. Accepting her contention would indicate that an auditor will
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
75 Promoting Transparency, Accountability, Integrity and Fiscal Probity
not report an observed fraudulent transaction, although not in the period under audit. It would
have been therefore appropriate for Superintendent Sneh to concentrate on addressing the
undocumented transactions, by providing documentation and material justifications to acquit the
payments made in her name.
458. The Superintendent in her response provides an expenditure report of how she used the
US$14,633.00 noted in the audit report as payments made in her name. She stated that
US$14,633.00 was spent on labor cost without material justifications and supporting
documentation to acquit the expenditure. As noted in the Forensic Audit Report of 2005/2006,
out of the US$66,666.67 allocated to Grand Kru County, US$16,670.00 was deposited in the
Grand Kru County Development Fund Account bearing account number 10210136022019, held
at the Ecobank for labor and administrative costs.
459. Out of the amount of US$16,670.00 deposited in the CDF Account, the Superintendent and
Assistant Superintendent for Development withdrew US$16,260.00. As stated in the 2005/2006
Forensic Audit Report, the Superintendent provided receipts of expenditure in the tune of
US$10,142.50, leaving a variance of US$6,118.00 unaccounted for by the Superintendent and
Assistant Superintendent for Development. The Superintendent failed to provide receipt of
US$6.118.00 she and her development Superintendent withdrew from the Bank.
460. Superintendent Sneh’s contended, “the project was completed on March 17, 2007 when a fleet
of vehicles headed by project pick-up and followed UNMIL vehicles entered Sasstown to the
jubilation of the people of the district.” The “jubilation of the people” is not documentary
evidence of how the CDF was expended.
461. I took note of Assistant Superintendent Wisseh information that the US$100,000.00 was made
deposit in error in the old CDF account and that the appropriate steps have been taken to
transfer the funds into the actual CDF account. On the issue of accounting for funds paid in his
name, Assistant Superintendent Wisseh provided this unsupported explanation:
“Clarification on US$1, 627.00 issued in the name of T. Michael Wisseh: This amount was
intended to buy spare parts and pay for the repair of motor bike assigned to him (DS Wisseh) at
the time; and for two county power saws, which were being used to assist some of the
communities with their bridge repairs and roadside brushing work. One Kamara Aseku
repaired the motor bike from Plebo; the two power saws were repaired by Jerry Roberts from
Harper (see receipt attached).”
462. By his own admission, Assistant Superintendent Wisseh is not sure as to who repair the motor
bike; as he indicated “one Kamara Aseku” repair the bike. The receipt issued also indicated no
name of business or contact information for me to independently verify the authenticity of his
assertions.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
76 Promoting Transparency, Accountability, Integrity and Fiscal Probity
463. The payment voucher submitted for the students at the various indicated US$1,300.00 for 13
students, with 7 at TNIMA and 6 students at Stella Maris Polytechnic. But the attached listing
indicated 16 students purportedly received monies for TNIMA. There is no listing for Stella Maris
Polytechnic. This US$1,300.00 receipt was meant to acquit part of the undocumented payments
in the tune of US$18,640.00 paid in the name of PMC Treasurer Michael K.W. Tawreh. It is also
indicated on the Listing that U$450.00 was provided to 16 students, US$100.00 for union and
travel fees and US$150.00 for expediter and facilitator fees. This gave a combined total of
US$700.00 as reflected on the payment voucher. But interestingly, the purported receipt number
45599 issued by JFK Medical Center and stamped by TNMIA Business Manager’s office indicated
US$700.00. This means that TNMIA also received payment for union and travel fees, and
expediter and facilitator fees. The inconsistent on the unapproved Student Listing and payment
voucher denied assurance on the reliability of the document submitted.
464. I further examined the receipts submitted by Stella Maris Polytechnic. It was signed Jefferson T.
Nagbe on 09/04/08. Independent confirmation to Stella Maris indicated that a Jefferson T.
Nabge is not in the employed of Stella Maris. This clearly showed that Assistant Superintendent
Wisseh manufactured the receipts and submitted them for audit. This is a contravention of
Section 12.31 of the Penal Code, which forbids the altering, forging and submission of
documents that is known to be lacking authenticity. Regulation N-3 of the PFM Regulation also
prohibits the submission of false documents to acquit expenditure in Government.
465. In the absence of documentary evidence, the US$6,118.00 cannot stand as a charge to the
consolidated account. I have modified my recommendation. Instead of holding the
Superintendent and Assistant Superintendent for US$16,260.00, I now recommend that they
should be jointly and severally held to restitute US$6,118.00, representing undocumented
transactions.
Statement of Accountability
466. In this report, it is required that I hold people accountable for public monies entrusted to them
for the purposes of providing services to the taxpayers. Section 53.7 of the Executive Law of
1972 defined the minimum reporting requirements in my audits. Section 53.7 requires me to
report the following:
• Any officer or employee who has willfully or negligently failed to collect or receive monies
belonging to the Government.
• Any public monies not duly accounted for and paid into an authorized depository.
• Any appropriation that was exceeded or applied to a purpose or in manner not authorized by
law.
• Any deficiency or loss through the fraud, default or mistake of any person.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
77 Promoting Transparency, Accountability, Integrity and Fiscal Probity
• Inadequate or ineffective internal control of public monies and assets. When appropriate, the
report shall also include recommendations for executive action or legislation deemed
necessary to improve the receipt, custody, accounting and disbursement of public monies
and other assets.
• The total irregularities noted in the audit amounted to US$131,484.00, representing breach
of contracts, irregular transactions, undocumented transactions and lack of compliance with
laws and regulations. The US$131,484.00 excludes US$50,745.24 which was derived
from the US$28,745.24 paid to County Builders for three projects and the US$22,000.00
paid to LICOME Inc for which I have recommended that County Builders and LICOME Inc
should be held for breach of contracts and made to pay general damages.
Acknowledgement 467. I acknowledge the cooperation and assistance provided to the GAC by the Ministry of Internal
Affairs, Ministry of Commerce and the Ministry of Finance during the course of the audits. I
would also like to acknowledge the maximum cooperation provided by Ecobank. I would further
like to thank the Engagement Manager, the audit team and the staff of the GAC that supported
me in finalizing this report.
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
78 Promoting Transparency, Accountability, Integrity and Fiscal Probity
ACCOUNTABILITY SCHEDULE
NO. NAME POSITION PROJECT TITLE/TOPIC No supporting
document/not
accounted for
Unpaid Tax USD Misappropriation USD REF. PERAGRAPH COMMENT
1 Rosalind Sneh , J. Michael
Wisseh, Johnson T. Wreh Michael
K. W. Tarwreh Sr, & Nyewoti
Wollor
Superintendent, Assistant
Superintendent for
Development, PMC
Chairman,PMC Treasuerer &
PMC Assistant Treasurer
Trembo Project 9,650.08 56 Should be made to restitute US$9,650.08
representing payment made to the illegally operated
company, NAFAPD. NAFAPD failed to deliver on the
Trembo Project. Work on the Trembo Project was not
started.
2 Rosalind Sneh, Johnson T. Wreh ,
J. Michael Wisseh, Michael K. W.
Tarwreh, Sr and Nyewoti Wollor
Superintendent,
Development
Superintendent, Chairman,
Treasurer & Assistant
Treasurer
Gyabo Community Project the
construction of a Town Hall in
Garraway City, Trehn District,
Grand Kru County
$9,344.44 143 Should be made to restitute the US$9,344.44 paid to
NAFAPD, an illegally operated company. This amount
represents the total payment to the illegally operated
company, NAFAPD for the implementation of the
Project but work on the Project was not started.
3 Dennis Wiah PMT Project Technician Bolloh Community Project 9,472.30 217 Should be made to restitute the US$9,472.30 for not
delivering on contractual terms as he only planted
sticks in the ground.
4 Gbenimah B. Slopadoe Grand Kru County Electoral
District # 1 Representative
Buah project construction of a
Guest House in Buah, Gee City
4,436.09 238 Failing to live up to the terms of his promisory
note.No work was done on the project.
5 Rosalind Sneh, Johnson T. Wreh ,
J. Michael Wisseh, Michael K. W.
Tarwreh, Sr and Nyewoti Wollor
Superintendent, Assistant
Superintendent for
Development, PMC
Chairman,PMC Treasuerer &
PMC Assistant Treasurer
Forpoh project construction of
a Town Hall in Parluken Town,
Forpoh District,
9,437.92 245 Should be made to restitute US$9,437.92
representing money paid to Matthew Jugbo for the
construction of the Town Hall for which Matthew
Jugbo did not perform.
6 Abacus K. Nimene Contractor Jloh Project renovation of a
school building in Betu City,
Jloh Statutory District
2,000.00 261 Should be made to restitute US$2,000.00
representing balance unaccounted. The project is
incomplete.7 Rosalind Sneh, J. Michael
Wisseh, Johnson T. Wreh,
Michael J. K. Trawreh & Nyewoti
Wollor
Superintendent, Assistant
Superintendent for
Development, PMC
Chairman,PMC Treasuerer &
PMC Assistant Treasurer
Jrao (Sass Town) project the
renovation of the
Administrative Building in
Jekwikpo City
9,800.00 274 Should be made to restitute US$ 9,800.00
representing the amount paid to the local contractor
for the Project and the local contractor did not
perform. The Project remains incomplete.
8 Nyandeh Sieh Contractor Kplio project the rehabilitations
of the roads from Kayken to Big
Fleneken and from Big Suehn
to Filoken, Barclayville
Chiefdom
9,550.00 286 Should be made to restitute US$9,550.00
representing the amount he received for the Project
and did not perform. No work was done on the
Project.
9 Rosalind Sneh, J. Michael
Wesseh, Johnson T. Wreh,
Michael J. K. Trawreh & Nyewoti
Wollor
Superintendent, Assistant
Superintendent for
Development, PMC
Chairman,PMC Treasuerer &
PMC Assistant Treasurer
Qualoh Community Project the
construction of a School
building in Gbanken, Wedabo
Chiefdom
9,785.17 302 Should be made to restitute US$ 9,785.17
representing money paid for the implementation of
the Project. The Project remains at foundation level.
10 John S. Youboty MDMC CEO and General
Manager
Purchase an earth moving
equipment, one dump truck,
one new double cabin pick-up,
one new motor bike, fuel oil
and lubricants
32,350.00 319 Should be mde to restitute US$32,350.00
representing money paid for administration, fuel and
lubricants for which no material justification and
supporting documents were provided to acquit the
payment, as the equipment was still in Monrovia and
not in the use
11 Rosalind Sneh Superintendent, Grand Kru
County
CELLCOM CONTRACT 900 410 Should be made to restitute US$ 900.00 representing
money she received from the contractual agreement
for the construction of one Cellccom Tower in
Barclayville
ACCOUNTABILITY SCHEDULE
NO. NAME POSITION PROJECT TITLE/TOPIC No supporting
document/not
accounted for
Unpaid Tax USD Misappropriation USD REF. PERAGRAPH COMMENT
12 Rosalind Sneh and T. Michael
Wisseh
Superintendent and
Assistant Superintendent for
Development
Bank Statement
Analysis—First Account
6,118.00 429 Should be made to restitute US$6,118.00
representing amount paid in their name for which no
substantive authority, material justification and
supporting documents were provided during the
course of the audit
13 Michael K.W. Tawreh PMC Treasurer Bank Statement
Analysis—Second Account
18,640.00 440 Should be made to restitute US$18,640.00
representing amount paid in his name for which no
substantive authority, material justification and
supporting documents were provided during the
course of the audits to acquit the payments
SUB TOTAL 24758 $106,726.00
TOTAL 131,484.00
NO. NAME POSITION PROJECT TITLE/TOPIC Misappropriation USD REF. PERAGRAPH COMMENT
1 County
Builders/Francis
Nah Nimene
Contractor/Owner Siklio Community project 9,344.40 78 Should be held for breach of contract and made to pay
general damages for such breach as the Siklio Guest House
Project remains at foundation level. County Builders was paid
US$9,344.40 and failed to complete the Siklio Guest House
Project.
2 LICOME Inc/Joel
V. Printers
Contractor/President Barclayville City Hall Project 22,000.00 102 Should be held for breach of contract and made to pay
general damages for such breach as the Barclayville City Hall
Project remains incomplete.LICOME Inc was paid
US$22,000.00 for the Barclayville City Hall Project but failed
to complete the Project.
3 County
Builders/Francis
Nah Nimene
Contractor/Owner Gbetao Town Hall Project 9,749.41 123 Should be held for breach of contract and made to pay
general damages for such breach as the Gbetao Town Hall
Project remains at the foundation level. County Builders was
paid US$9,479.41, by the Grand Kru County, but failed to
complete the Gbetao Town Hall Project.
4 County
Builders/Francis
Nah Nimene
President County
Builders Company
Nifao Project the construction of
a clinic in Po-River Middle
Town, Trehn District, Grand Kru
County
9,651.43 161 Should be held for breach of contract and made to pay
general damages for such breach as the Nifao Project was
not started. County Builders was paid US$9,651.41, by the
Grand Kru County, but failed to commence work on the
NifaoTown Project.
Total 50,745.24
Accountability Schedule
Report of the Auditor General On the Grand Kru County Administration: FY 2006/07 & 2007/08
79 Promoting Transparency, Accountability, Integrity and Fiscal Probity
EXHIBITS
EXHIBIT-6EXHIBIT-1
EXHIBIT-6 Cont'dEXHIBIT-1 Cont'd
EXHIBIT-2
EXHIBIT-2 Cont'd
EXHIBIT-3
EXHIBIT-4
EXHIBIT-24EXHIBIT-5
EXHIBIT-6
EXHIBIT-6 Cont'd