+ All Categories
Home > Documents > REPORT ON DESIGN AND OPERATING PARAMETERS OF …

REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Date post: 12-Apr-2022
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
47
Programme Objectin Seri : PROBES/45/1Ϡ REPORT ON DESIGN A ND OPER ATING PA R AMETERS OF ELECTROSTATIC PRECIPITATORS Central Pollution Control Board East Arjun Nagar Delhi-110032
Transcript
Page 1: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Programme Objectin Series : PROBES/45/1992

REPORT ON DESIGN A ND OPER ATING PA R AMETERS

OF ELECTROSTATIC PRECIPITATORS

Central Pollution Control Board East Arjun Nagar Delhi-110032

Page 2: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Programme Objective Series : PROBES/45/1992

REPORT ON DESIGN A ND OPER ATING PA R AMETERS

OF ELECTROSTATIC PRECIPITATORS

Central Pollution Control Board East Arjun Nagar Delhi-110032

Page 3: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

1 .0

2.0

3.0

4.0

5.0

6.0

-- _ _ _ --- -�

CONTENTS

f.'lTRODUCTIO�

E.S.P. COMMITTEE

AIR POLLUTION CONTROL ACT

FLY ASH AND FLUE GAS CHARACTERISTICS

4.1 INTRODUCTION

4.2 COAL

4.3 FLUE GAS

4.4 GAS FLOW QUAi\rrrrY

4.5 FLY ASH

DESIGN CRITERIA FOR ELECfROSTATIC PRECIPITATORS

5. 1 INTRODUCTION

5.2 DESIGN CRITERIA

5.3 COLLECTION SURFACE

5.4 GAS VELOCITY

5.5 ASPECT' RATIO

5.6 TREATMENT TIME

5.7 HIGH TENSION SECI10NALISATION

5.8 NUMBER OF SERIES FIELDS

5.9 MIGRATION VELOCITY

PRECIPITATOR EQUIPMENT

6.) ELECTRODES

6.2 RAPPERS

PAGE

1

1

2

2

2

3

4

4

8

8

8

8

1 3

1 3

1 4

1 4

1 5

1 5

16

16

16

Page 4: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

PAGE

6.3 GAS FLOW DISTRIBUTION MEAr\S 17

6.4 GAS FLOW MODEL STUDIES 18

7.0 REVIEW OF PERFORMANCE OF INSTALLED ESP 18

7 .I INTRODUCfiON 18

7.2 PERFORMANCE OF ESPs !�STALLED EARLIER TO 1976 19

7.3 PERFORMANCE OF ESPs INSTALLED LATER THAN 1976 19

8.0 REASOf\S FOR POOR PERFOR.\1ANCE OF F.SP 25

�-· INTRODUCfiO� ., -_)

8.2 FL�DA�1ENTAL PROBLEMS 25

8.3 \1ECHANICAL PROBLEMS -,-_)

8.4 OPERA TlONAL PROBLE.\lS .,-_)

9.0 MEASL RES TO IMPROVE THE PERFORMANCE OF ESP IN OLD POWER Pl.A NTS ?..7

9.1 INTRODUCTION 27

9.2 r-ILLJ�G UP THE DUM:-.1Y FIELDS 27

9.3 REPLACEME'\T OF EXlSTING ESP BY NEW ESP 27

9.4 AUGMENTATION 017 COLLECTION SURFACE 27

9.5 IMPROVED ELECTRICAL E�ERGISATIO'l 28

9.6 FLUE GAS CO'\DITIO��G 28

10.0 �1EASL.RES TO L!\SCRE CO:--.:TI:\LATION OF I0;1TIAL GOOD

PERFORMANCE 29 '•

10.1 H\TRODLCTIO:--.: 29

10.2 .\LIGNMENT OF ELECfRODF SYSTEM 30

10.3 CLEA:\1:'\G OF ELECTRODES 30

Page 5: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

10.4 GAS TEMPERATURE

10.5 SPARK RATE

10.6 RAPPING FREQUENCEY

10.7 OIL COMBUSTION

10.8 AIR CONOfTTONING OF CONTROL CABrNS

10.9 HOPPER EVACUATION

10 . 10 DUST CONCENTRATION IN FLUE GAS

ANNEXURES - I

. II

- III

- IV

PAGE

30

30

3 1

3 1

3 1

3 1

32

33

35

36

37

Page 6: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

FOREWORD

The present repon on Design and Operating Parameters of Elecrrostatic Precipita­tors (ESP) was prepared by a committee constituted by the Central Board under tbe Chairmanship of Dr. Tata Rao. The repon also contains a review of performance of ESPs already installed in the country and discusses reasons for the poor performance

of some of them. The discussion is followed by suggested measures to improve and

maintain the initial good performance of ESPs. I believe the repon would be useful

for the Thermal Power Plants in the selection, operation and maintenance of ESPs.

I thank Dr. Tata Rao, Ex-Chairman of A.P. Electricity Board and Dr. B. Sengupta,

Member convener of E.S.P. committee and the other members of the Committee for the painstaking effons taken in preparing this repon.

Delhi 24. 10.91

N.S. TIWANA Chairman

Page 7: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

1.0 INTRODUCTION

An electrostatic precipitator (ESP) is a panicle control device that uses electrical forces

to move the panicles out of the flowing gas stream and onto collector plates. Basically

an electical precipita.tor provides three essential functions:

** the suspended panicles are given an electrical charge

** the panicles are subjected to an electric field to remove them from the gas stream

to a suitable collecting electrode and

** means are provided for removing the panicle layers from the electrode surfaces to

an outside receptacle with as little loss as possible.

Jn practice. electric charging of the particles is accomplished by means of ions produced

in the high voltage d-e corona. The collecung field is also provided b) the high voltge

d-e corona Removal of the collected particle layers 1s accompli<ihed by rapping (by

impact, or by virbation of the electrodes).

2.0 E.S.P. COMMITTEE

Chaim1an. Central Pollution Control Board constituted a committee comprising experts

and representatives of suppliers/manufacturers of the electrostatic precipitators in the

country to evaluate the performance of ESPs and to suggest measures for improvement.

The list of members of the committee has been g1vcn in 1\nnexure-I.

The tem1s of reference of the committee were:

1) To review the design criteria adopted by the manufacturers vis-a-vis the emission

standards evolved by Central Board.

2) To review the performance of the installed ESPs.

3) To identify the probable reasons for poor performance.

4) To suggest measures to improve performance.

5) To suggest measures to ensure continuation of initial good performance.

6) Any other matter considered relevant and assigned by the Chairman, Central

Board.

3.0 AIR POLLUTIO" CO:\'TROL ACT

Th�.: Air (Prevention and ContrOl of Pollution} Act, 1981 sripulates that no person shall

without the previous consem of Swte Board for prevcmion and contrOl of pollution

Page 8: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

operate any indusrrial plant for the purposes of any indu')try in an air pollution control area (clause 21 of the Act). Every per:.on to whom consent has been gramed by the State Pollution Control Board shall install the control equipment of such specification the Stat� Board may approve and aher/replce the existing control equipment, if any, in accordance with the direction of the State Board.

The Central Pollution Control Board has stipulated the following emission standards for thermal power station for pulverised coal boilers.

(Ref: Emission Regulation Part-1).

Boiler size Particulate matter, mg!Nm3

Old

Less than 200 MW 600

200 MW & above

New (After 1979)

350

150

Protected area

150

150

While the emission standards laid down can be adhered in respect of new thermal stations, the enure problem lies in complymg with the standards in case of already running stations where there are not adequate control equtpment installed or the existing conrrol equipment is inefficient. The designers as well as the power station authorities are confronted with the problem of rerrofitting new control equipment in the existing plant.

4.0 FLY -ASH AND FLUE GAS CHARACTERISTICS

4.1 INTROOUCfiON

Electrostatic precipitator performance depends fundamentally on the physical and chemical properties of the gas and particulates rreated. In a power plant. these properties are governed by the coal burned, the furnace design and the overall operation of the bOtler. The composition, temperature and pressure of the nue gas govern the basic corona ch.tracteristics of the precipitator. while panicle stze, partic1e concentration and electncal rcsisth,it) of the ash affect both the corona and the particle collecting prop­emes of the precipitator.

�.2 COAL

Precipitator design and performance are strongly dependant on the properties of the coal burned 1n the furnace. The major constituents of coal are moisture. volatile matter, fixed carbon and ash. Typical values for a range of Indian coals are listed in Table- I. All coals contain significant amounts of ash or residues of combustion consisting chiefly of inert oxides and silicates. These complicate furnace operation and give rise to the fine

2

Page 9: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

particles known as fly ash. The amount of fly ash produced in a given case depends

on the ash content, the hearing value and other properties of the coal. The variability

and uncertamty of coal properties reflect in the fly ash generated and can make the problem of fly ash collection singularly difficult. In order to cope successfully with

particulate air pollution from coal fired power plant it is necessary to apply consistently

a high order of technology.

Table I

Typical Properties of Indian Coals

Coal mines Moisture Volatile Fixed Ash Sulphur High heat value

Singareni coals { Upper Kusumunda Lower Kusumunda

Turra

Singmuli coal fields upper

lower

Jharia coal fields

�eyveli lignite

4.3 FLUE GAS

{

%

9

10

10

10-12

08-10

16

10

10

16

10

13

42.52

maner % carbon%

23.92 29.08

24.63 33.37

21.46 36.54

20-25 21-31

20-25 24-25

21.6 32.4

18.9 26.1

19.8 25.2

14.4 23

21.25 34.16

16.9 27.5

22-27 17-22

'*· % Kcal/Kg

38 0.36 3800

32 0.35 4300

32 0.38 4300

32-49 0.27-0.36 3130-4275

40-48 0.24-0.28 3530-4020

30 0.27 4050

45 0.45 3425

45 0.23 3450

46 6 0.34 2700

34.16 0.5 4000 27.5 0.41 3200

03-12 0.46-0.81 2500-3200

Combustion gases from coal fired boilers consist chtefly of carbon dioxide, water vapour, nitrogen, oxygen and minor constirutents such as sulphur oxtdes, nitrogen

oxides and arogon. The amount of water vapour is determined by the hydrogen and

moisture content of the coal and the humidity of the combustion air. Oxygen is present

as the result of the excess air used for combustion and air tn-leakage through the

furnace, ducts and air preheater. The sulphur trioxide (S03) produced in the combustion

process is imponant in electrostatic precipitator because of its effect in reducing the

resistivity of the fly ash. Dew point of the flue gas is substantially elevated by the

3

•.

Page 10: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

pressure of Soy The elevated dew point can have a profound effect on precipitator operation owing to the great reduction in fly ash resistivity induced by the adsorption of Lhe sulphur trioxide on the fly ash particles.

4.4 GAS FLOW QUANTITY

Gas flow rate is a fundamental factor in the design and performance of electrostatic precipitator. The quantity of combustion gas produced in the boiler depends on the composition and amount of coal burned, the excess air used for combustion and the air in-leakage through the furnace, flues and air-preheaters. The volume flow rate through the precipitator is also a function of gas temperature and pressure.

Dtscrepancies between gas flows measured by pHot rube methods and those calculated by heat balance or material balance methods frequently cause problems in practice because precipitator performance data banks are as a rule based on pitot tube measure­ments, whereas gas flow specifications for new precipitators commonly are calculated using the balance methods. Therefore, new precipitator designs may be based on gas flow figures which are too low by 10% or more unless adequate allowances are made for the differences. The actual deficiency may also be compounded by inadequate allowances for air in-leakage and the amount of excess air used for combustion. Actual operating gas flows may then exceed design as much as 15 to 20% thereby causing greatly increa"ied stack emissions.

4.5 FLY ASH

The amount of fly ash emiued from a furnace depends mainly on the amount and the composition of the coal burned, on furnace design and on furnace operation.

4.5.1 Chemical Composition

The chemical composition of fly ash varies widely and depends on the coal burned, the mining and the processing methods used and the degree of cleaning of the coal before burning. Major constituents of the fly ash are silica, alumina and iron oxides. Typical \alues of the constituents of Indian fly ash are given in Table-H.

4.5.2 Pa rticle Shape and Size

The particle shnpe is heterogenous and varies with the coal burned and the conditions of combustion.

Panicle size distribution is an important factor in the design and operation of precipi­tators. High efficiency removal of micron and sub-micron particles is of greatest im­portance in meeting today':, requiremems for essentially clean stacks. Particle size distributions of fly ash from representative power plants are shown in Table-III.

4

Page 11: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

�.5.3 Resisthity

Corona current from the high tension electrode must pass through collected dust layers on the plates to reach grounded plate surfaces. Passage of the corona current builds up a voltage across the dust layer in accordance wuh Ohm's law. Theory and experience indicate that when the dust resistivity exceeds a critical value of about 1010 ohm/em corona currents are limited by electric breakdown of the collected dust layers.

This in tum limits operating voltage and reduces precipitator efficiency. The loss in performance increases quite rapidly for resistivities greater than 10'0 ohm/cu.m and resistivity is, therefore, a major factor in precipitator technology.

Fly ash resistivity depends primarily on the chemical composition of the ash, the flue gas temperature and the water vapour and S03 in the flue gas. At air preheater outlet gas temperatures ( 135 Deg. to 160 Deg.C.), surface conducuon over the fly ash particles 1s the prevaihng mode and the conductivity depends mainly on the amounts of S03 and ,..,atcr "apour adsorbed on the particles. The resisuvuy 1s very sensuive to the presence of SO, and water vapour. Although most of the sulphur 111 the coal is oxidized to S02, about I ''t IS convened to so). In general, the amount of sol' produced increases with the coal sulphur content. but furnace operation and other factors also exen an influence, so that no one-to-one relation exists between coal sulphur and resistivity. Experience over many years has shown that fly ash from low sulphur coals usually has high resistivity and 1s difficult to precipitate whereas fly ash from high sulphur coals has low re�1s11vity and is relatively easy to collect. I Iowcvcr, the relationship is statistical

because of the presence of other variables. The sulphur content of the coals is classified in accord with the following scheme.

Low sulphur coal s < 1%

Medium sulphur coal 1%<S<2.5%

l ligh sulphur coal s > 2.5%

The relation between coal sulphur and fly ash conductivity is tempered by several factors. hrst. the amounr of S01 generated depend on furnace conditions as well as on the sulphur coment of the coal. Second, the amount of SO, adsorbed on the fly ash is greatly affected by the gas temperature and the surface cond111on� of the particles. There IS evidence that S03 adSOrption is greater for finer particles bi!Cause Of their greater specific -.urfacc. The variation of dust resistivity with temperature for varying sulphur content 1s shown in Figure-!.

Field invesugations show that flue gas temperature 1s the most imponant variable in addilion to �ulphur content of the coal in detemltntng the conductivity of the ash. Pigure-2 lllustr.Hes the temperature variation of tl} ash res1stivit}.

5

Page 12: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Table II

Typical Chemical Analysis of Fly Ash from Indian Coal

Chern teal Stngarcni Kusurnunda Smgrauli Jharia Neyveli consutucnt<; coals Upper Lower Turra Purcwa lignite

uppcr/lo" cr

Si02 59.3 59.77 59 60.15 62.45 56.7 60.9 64.6 57.5 58.2 57.22 65.2

Alp3 21.1 22.R9 22.15 27.�4 27.41 27.5 24.8 24.8 26.8 25.48 26.9 13.27

Fep1 7.526 8.23 8.4 5.6 4.96 6.4 7.7 5.1 10.16 10. L2 10.3 3.6

T102 1.53 1.88 1.9 1.9 1.5 1.52 1.28 1.51

Pp$ 0.53 0.55 1.1 0.5 0.5 0.83 0.8 0.84

CaO 6.51 3.16 7.06 1.43 1.42 1.8 0.9 0.9 1.76 I 74 1.85 11.2

MgO 3.034 1.72 2.05 0.91 1.03 1.0 1.0 0.8 0.61 0.59 0.62 5.0

so, 0.36 0.1 0.3 0.2 0.3 0.6 0.58 0.6 1.37

1'-iap 1.99 0.15 0.4 0.2 0.2 0.16 0.3 0.16 0.32

Kp 2.5 1.5 1.2 - 0.04

MnO 0.06 0.05

6

Page 13: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Table III

Particle size distribution of Fly-Ash from Typical

Power Plants, Measured by Bahco Classifier

RANGE OF PARTICLE PLANT-WISE DISTRIBUT ION

SIZE (MICRONS)

2 3 4

< 3.4 14.7 17.3 27.5 26.2

3.4 5.2 17.0 13.1 31.8 11.9

5.2 8.5 9.6 8.0 14.7 8.6

8.5 14.5 11.7 16.7 16.5 9.6

14.5 26.5 13.8 8.4 4.6 5.4

26.5 44.0 10.5 7.2 2.7 5.7

44.0 55.0 5.7 3.1 0.8 3.1

55.0 65.0 12.0 2.0 0.6 2.7

65.0 400.0 5.0 24.2 0.8 26.2

7

Page 14: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

The presence of sodium in the ash in amounts greater than about 1.5 to 2.0% as Na20 is sufficient to reduce resistivity of fly ash from low sulphur coal to below

1010 ohm/em. This effect is illustrated in Figure-3.

5.0 DESIGN CRITERIA FOR ELECTROSTATIC PRECIPITATORS

5.1 INTRODUCTION

A fundamental task in precipitation technology is the design of optimum precipitation systems for given application. Precipitator design has changed in character during the past several years from a rather routine and casual function to a more serious enterprise

involving high performance and high financial stakes. This change has been forced by

the implementation of stringent air pollution control standards which requires substan­

tially invisible stack emissions for new units. ll is, therefore, prudent that the design

criteria of electrostatic precipitators to meet a colJection efficiency of 99.5% and above

only are discussed.

5.2 DESIGN CRITERIA

The basic design criteria for electrostatic precipitators is the determination of the prin­

cipal parameters for precipitator sizing, electrode arrangement and electrical energisa­

tion needed to provide specified levels of performance. Auxiliary factors such as rap­

pers, gas flow control methods, dust removal system and performance monitoring must

also be considered.

5.3 COLLECTION SURFACE

The collection surface required for a given gas Dow and efficiency is usually computed

from the modified Deutsch-Andersson equation.

E = ( 1 - e ·(wlc.SCA)O.S) X 1 ()()

Where, E = Collection efficiency, per cent.

wk = Migration velocity. m/sec.

SCA = Specific Collection Area

= Total projected collecting electrode surface area (A,m2).

Gas flow rate (Y,m3/sec)

e = Naperian logrithmic base

The relation between SCA and efficiency for a range of values of WK is shown in

Figure 4.

8

Page 15: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

-- - .

X 0 I I f

� 0.75% SULPHUR I

X IN COAL :X:: 0 11

� 10

-

> I I /' "\..� \ - 1.75% t; { ....... &2 10 w 10 .x; E-� I I I y-- '� l \ \ i 2.?5% :J 0

130 150 170 210 250 FLUE GAS TEMPERATURE 0c

FIGURE -1: VARIATION OF DUST RESISTIVITI' WITH TEMPERATURE FOR VARYING SULPHUR CONTENT

Page 16: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

� 0

I

� :X:: 0

� -> ........ t;; ........ ll2 1&1 g:; t;; � Q

6.6 96 101 2 I WATER \

� D RY AIR I BYVOLUME •

/'"-* 11 I / 13.5 96 "', \ 10 "i/ WATER � �,,

� �� 10 I 10

9 10 1 > 95°C 1 2�0°C 1 1 s/o °C

TEMPERATURE - 0c FIGURE- 2. VARIATION OF DUST RESISTIVITY WITH TEMPERATURE

FOR VARYING MOISTURE CONTENT

Page 17: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

:E 0

I

:E :I: 0

� >-1-> t=�en w a:: :I: en < >-....1 LL

1014 --------------------------------------------------------------------------

1 Q13

1012

1011

1010

109 0.1 0.2 0.3 0.5 0. 7 1 3 5 7

SODIUM CONTENT AS Na20, PERCENT FIG. 3 VARIATION OF RESISTIVITY WITH SODIUM CONTENT FOR FLY

ASH FROM POWER PLANTS BURNING COALS

10

Page 18: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

... z w 0 a: w

99.9

99.5

Q.� 99.3 > () z w u 99.2 LL: LL. w z 0 t; 99.1 w ..J ..J 0 () <

99.0 100

wk = 0.30 m/sec.

wk = 0.20 m/sec.

wk = 0.15 m/sec.

125 150 175 200 SPECIFIC COLLECTION AREA, m2Jm3Jsec

FIG. 4 SCA V5 m FOR VARYING WK

225 250

Page 19: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

The specific collection area is expressed in m2/m3/sec. Pracucal values of SCA usually mnge between abour 140 and 250 m2/rn3/sec.

Considering the high resistivity of the fly ash encountered in our coals. the need for capturing submicron particles at higher efficiencies and to avoid defficient equipment, minimum specific collection area shown in Table 4 must be specified by the purchaser correspondmg to the collection efficiencies indtcated for the worst possible coal burnt

in Indian power plants.

Table 4

Minimum Specific Collection Area vs Efficiency

Collection efficiency (Per cent)

99.5

99.7

99.9 ----

SA GAS VELOCITY

Specific Collccuon Area

(m2/m1/sec )

140 - 150

170 - 180

235 - 250

The average gas velocity is calculated from the gas flow and the cross section of the precipitator. The cross-section is taken as the open area for gas flow between the collecting plates, disregarding the plate baffles. The importance of the gas velocity is its relation to rapping and re-entrainrnent losses. Above some critical velocity, these

losses tend to increase repidly because of the aerodynamic forces on the particle. The critical velocity depends on the quality of gas flow, plate configuration, precipitator size

and other factors, but for most fly ash precipitators does not exceed 1 . 1 m/sec. This setsa design limn on gas velocity of not more than OJ� m/sec. for high efficiency fly ash

precipitators.

5.5 ASPECT RATIO

Thts pammeter ts defined as the ratio of the total acuve length of the fields to the heightof the field. h 1s imponant in precipitator design because of Its effect on rapping loss. Collected dust released from the plates is carried forward b} the flow of the gas. If the tmal field length ts too shon compared to the height. �orne of the falling dust will be carried out of the precipitator before it reaches the hopper: thereby substantially increas­mg the dust loss. For efficiencies of 99.5% or higher, the aspect rauo should be as per

th�: followmg Table 5.

13

Page 20: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Collection efficiency, %

99.5 - 99.6

99.7 - 99.9

5.6 TREATMENT TIME

TAISL� 5

Aspect ratio (minimum)

1.4 - 1.6

1.8 - 2.4

This parameter 1s defined as time taken by the flue gas to pass through the length of the collecting electrode zone. For efficiencies of 99.5% and higher, the minimum treatment time should be at least as shown in the Table-6 below:

Collection efficiency, %

TABLE 6

Treatment time, (Sec.)

-------------------------------------------------- ----------------

99.5

99.7

99.9

5.7 HIGH TENSION SECTIONALISATION

20

24

33

Theory and practical experience confmn the fact that precipitator performance improves with degree of high tension sectionalisation. There are several fundamental reasons for th1s improvement. Small sections have less electrode area for sparks to occur. Electrode

alignment and spacing are inherently more accurate for smaller sections. The amount of sparking caused by dust build-up on the plates and by rapping is less for smaller sections. Smaller rectifier sets needed are inherently more stable under sparking con­ditions and the sparks which occur are less intense and damaging to perfonnance. Outages of one or two electrical sections has a much smaller effect on efficiency where a relatively large number of high tension section are used.

Prudent design criteria for modem high efficiency fly ash precipitators requires that the outage of two or three corona sections should not reduce collection efficiency below the guarantee level. Beyond this requirement, the optimum degree of high tension sectionahsation 1s a balance between the increase in efficiency obtained with more

section and the increased cost of providing the additional sections. This balance is h1ghly dependent on ash propenies, gas temperature and efficiency required. For effi­ciencies of 99.5% and higher, the number of high tension sections per 1 000m3/mt of gas flow rate small be as per the Table 7.

14

Page 21: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Table 7

Number of High Tension Sections ,.s Efficiency

Collection efficiency

%

99.5

99.7

99.9

65

5.8 NUMBER OF SERIES FIELDS

No. of high-tension

section per 1000 m3/mt

of gas flow rate

0.73 - 0.78

0.89- 0.94

1.22 - 1.30

The number of fields in series needed for a precipitator installation depends mainly on

the efficienc) reqUlred and on the redundancy necessary to ensue performance with

secuon outages. For high collection efficiencies and h1gh ash concenrrations the ash

loadmg in the gas stream changes greatly between the inlet and outlet of the precipi­

tator. At the precipitator inlet the corona current denslly is significantly reduced because

of space charge suppression in the gas srrearn and the heav) collection of ash on the

plates.

At the precipitator outlet the amount of ash is very small so that both these effects are

negligible and the corona current density approximates that of the clean gas. Good

design practice based on field experience calls for at least 5 or 6 separately energised

series of high tension sections for efficiencies of 99.5% and above.

5.9 MIGRATION VELOCITY (wk)

The most 1mponant variables which determine \\.k in t!nginecring pr.tctice are: resistiv­

it) and panicle size distribution of the fly ash, gas "elocHy distnbution through the

precipitator, particle losses due to re-entrainment, rappmg and gas leakage, precipitator.

Gas velocity distribution and particle losses due to re-entrainment etc. are controlled

through proper design of the precipitator and associated nues. Precipitator electrical

conditions can be optimised b} maintaining accurate electrode ahgnmem. sufficient

high tensiOn secuonalisanon and lhe use of appropnate rectifier sets and automatic

control systems. In practice, the values of migration velocny arc determined by the

various precipitator manufacturers from bodies of experience accumulated over the

years.

15

Page 22: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

6.0 PRECIPJT ATOR EQUIPMENT

6.1 ELECTRODES

Precipitators for fly ash collection are of the duct type because of the relatively large

gas flows treated, the high collection efficiencies necessary and the great amounts

of fly ash to be handled. Collecting electrode spacings range between 250 mm and

500 mm, wirh the wider spacings preferred for installations having very large collecting

plates. Wider spacings help maintain electrode spacings and alignment tolerances. Wide

spacings also reduce corona cu!Tent densities at the plate surfaces which is a significant

advantage when collecting higher resistiviry ashes.

Collecting elecrrodes probably have received even more attention than corona elec­

trodes. fundamentally there are four basic technical requirements for effective collect­

ing electrode design:

a) high sparkover vohage characteristics

b) aerodynamic shielding of collecting surfaces to prevent particle re-entrainment

c) good rapping characteristics

d) high mechanical strength coupled with light-weight construction.

1L seems evident that collecting electrodes should be rated in terms of these properties.

Solid sheet collecting plates with structural stiffeners are standard throughout the indus­try.

In some design these stiffeners have contours designed to improve gas flow and to

lower gas turbulence in the collecting space near the place surfaces. Aerodynamic

effectiveness of the baffles can be important in minimising re-enrrainment losses. Srruc­

rural rigidity of the plates should be sufficient to maintain electrode spacing tolerances

of properly mounted plates within acceptable limits. Distorted and misaligned elec­trodes whether due to inadequate design or to improper installation lead to reduced

operating voltages and loss of efficiency.

6.2 RAPPERS

Removal of the accumulated deposits of fly ash from the electrodes is an essential

feature of efficient elecrrostatic precipitator. This is necessary not only to remove the

collected material from the precipitator but also to maintain optimum ele.crrical condi­

tions in the precipitator zones. The deposits are dislodged by mechanicaJ impulse or

vibrations of the electrodes, a process generally known as rapping. A rapping system

must be highly reliable, adjustable as to inrensity and/or frequency and capable of

maintaining uniform rapping over long periods of rime without attention.

16

Page 23: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Substantial differences exist between the various rapping methods and philosophy adopted by different manufacturers. In the case of magnetic impulse rappers, a steel

plunger 1s raised by a current pulse in a coil and lhen allowed to drop back by gravity,

striking a rapper rod connected inside the precipitator to a number of plates. Both the

intensity and frequency are easily adjusted through the electrical control system for the rappers. Mechanical rappers consist of hammers mounted on a rotating shaft in such a way that the hammers drop by gravity and strike anvils attached to the collecting plates. Rapping tntensity is governed by the weight of the hammers and length of the hammer mounting arm. The frequency of rapping can be changed through electrical control system of the rappers.

Rapping intensity of the hammer rappers has been much greater than that of magnetic

impulse type1• The later type generally is designed with sufficiem power to provide

intense blows but in pracnce is operated at low intensities to m1mmise rapping losses of the collected fly ash. An argument sometimes putforth for heavy rapping is lhat the

plates are kept cleaner which could be an advantage when dealing with high resistivity ash. However, it is well known lhat it is impossible to keep the plates clean no matter how heavy rapptng blows are used and even thtn layers of htgh res1stivny ash can cause heavy sparking and back corona.

It is necessary to rap the corona electrodes also, to prevent build-up of excessive ash deposits which interfere with the corona. Particle deposus on wires frequently tend to

form 'doughnuts' These formations interfere with the corona dtscharge and thereby

reduce collectton effic1ency.

6.3 GAS FLOW DISTRIBUTION MEANS

Optimum performance of precipitators requires well balanced flow distribution through

the precipitator zones and a lower level of turbulence. However, tn practice the quality

of gas now in a precipitator depends only slightly on the precipitator itself, but strongly on the plant flue duct system and its connections to the precipitator. Because of space

limitations and equipment location constraints, the flue connections to the precipitator

in a typical power plant usually are contorted, asymmetrical and otherwise unfavourable

to good gas flow. For these reasons, special means and studies are nearly always

necessary lO achieve the level of gas flow quality needed for high efficiency perfor­

mance. Poor gas flow can cause any or all of the following adverse effects viz.

l. (a) "Eicctroswuc Prcctpiwion of ny ash from Io� sulphur coal in power swtions" hy Mr. A.N. Lamb

& Mr. K.S. Watson, Electricity commission of New South Wales, Australta. Symposium on the

"Changmg Tcchnolog}' of clectroswtic Precipiwuon" Adclatde, \lovcmbcr 1974.

(b) " Role of Elcctro�lal.tc Precip itators in particulate control - A rctrospcct•vc and pro.,pcclivc view"

HafT) J White sympos1um on Elcctroswtic Prectpt!Altors for the control ol fine paruclcs, Pensacola

Dcach, Flonda, September 1974.

17

•.

Page 24: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

a) lower collection rates of the particles from the gas stream

b) re-entrainment of collected panicles due to aerodynamic scouring of the collecting

plates

c) excessive rapping losses

d) gas sneakage past the collecting zones and

e) loss of dust from the hoppers.

Techniques available for controlling and correcting gas flow patterns include chiefly the

use of guidevanes to change gas flow direction, flue transitions to couple flues of

different sizes and shapes and various types of diffusion screens and device to reduce

turbulence. Guidevanes are used to prevent the flow separation which would otherwise

occur at turns and changes in flue cross sections. Diffusion screens are effective in

reducing turbulence and improving the uniformity of flow. Basically, a diffusion screen

comprises plate/plates with a periodic pattern of holes. The effect of the diffuser is to

breakup large scale turbulence into a large number of small scale turbulent zones. These

in turn decay rapidly and in a shon distance coleaps into a relatively low intensity

turbulent flow field. In some situations 2 or 3 diffusion plates may be used in series

to provide better flow distribution and lower turbulence than could be achieved with

only one diffuser.

6.4 GAS FLOW MODEL STUDIES

Many years of experience have shown that precipitator gas flow systems can seldom

be successfully designed by intuitive methods. The cramped space and asymmeo-ic

irregular shaped flues ntle out mathematical and fluid dynamic design methods. This

leaves scale model laboratory studies as the most reliable and practical approach to

precipitator gas flow systems. Model techniques are well documented and the close

correlation between model study results and field gas flow performance has been

demonstrated by experience with many insrallations. The models are usually con­

structed of transparent plastics such as plexiglass for easy visualisation. Accuracy of

constntction is paramount and all significant parts of the flue system are included.

Geometric sirnilarity is maintained using typically a l: 1 0 scale.

Gas flow model studies are mandatory for modem high efficiency fly ash precipitatOrs

where the stakes are high and the cost of non-perfom1ance intolerable.

7.0 REVIEW OF PERFORMANCE OF INSTALLED E.S.P.

7.1 INTRODUCTION

The review of the perfom1ance of the installed electrostatic precipitators in various

thermal power stations must be considered under atleast two categories viz.

18

Page 25: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

i) the perfonnance of the precipitators installed earlier to 1976 and

ii) the perfonnance of the precipitators installed later than 1976 and in particular after

the enactment of pollution control act.

7.2 PERFORMANCE OF THE PRECIPATORS £:\STALLED EARLIER TO 1976

Many of the ex1sting generating stations installed earlier to 1976 were initially designed

and erected with minimal dust collection equipment. The boiler units supplied have

either mechanical dust collectors having a collection efficiency of 80% or a combina­

tion of mechanical and electrostatic precipitators having an efficiency of 95%. These

dust collecting plants were required only for the functional reqUirement of the boiler

viz. to reduce the erosion of the impellers of the induced draft fans and consequent

down time of the boiler. These dust collectors therefore, do not meet the requirement

of air pollution control regulations. Due to the many problems faced with inenial and

combination dust collectors like high power consumption. inadequate size, poor relia­

bilit} of the system etc. many of these dust collectors have been retrofitted with

electrostatic pn!clpitators of adequate size.

7.3 PERFORMANCE OF THE PRECIPITATORS INSTALLED LATER THAN 1976

For units installed in late seventies and onwards, the indigenous manufacturer M/s.

BHEL has supphed the 1mproved design of electrostatic precipitators. A bener under­

standing of the "anous propenies of coal and fly ash parucles that profoundly influence

the selection and sizing of the precipitators, rev1ew of various design philosophies and

methods used earlier in the engineering design of precipitators for fly ash panicularly

in the light of increased unit ratings and environmental standards and the need to meet

increasingly higher efficiencies and much greater reliability have witnessed the intro­

duction of precipitators with large specific collection area. The precipitators designed

and installed afler 1976 have been found to provide a satisfactory performance with

efficiencies between 99.5% and 99.9%.

Precipitator practice is best illustrated by means of data for a variety of power plants.

The example listed in Tables 8 to 11 co"er the main features and provide a broad cross

secuon of design pracuces. Some point:> of particular 1n1erest to be noted are the great

increases m gas now rate capacity and collecuon efficiencies over the years.

19

Page 26: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Table 8

Summary of Desigh data for Representative Fly-Ash Precipitators

Unit Rating : 500 MW

SL PA!{A�iETER SI�GRALU KORBA RA.'AAG UNDA.'.1 RIHA.'lD FARAKKA CHANDRAPUR

No.

01. Gas now rate, m3/scc. 980 1030 710 768 785 750

02. 1 cmpcraLurc of flue gao;, •c 140 140 ns 140 133 123

03. Inlet dusL concenLralion, 73.5 82.56 42 54.08 70.2 74.51

gm/Nm1

04. Efficiency, % 99.5 99.52 99.9 99.81 99.95 99.93

05. :-.:o. of casings 4 4 4 4 2 4

06. f'.o. of scncs lields 7 6 6 6 6 6

07. Manufacturer of ESP BH.EL BHEL BHEL LODGE.- MARTIN- BHEL

COTfRELL ELL!

U.K. C01TRELL,

ITALY

'•

20

Page 27: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Table 9

Summary of Design data for Representath·c Fly-Ash Precipitators

Unit Rating : 200/210 MW

SL. PARAMETER VIJAYAWADA MEJIA GANDHINAGAR RAICHUR KORBA CHANDRAPUR

No. 3&4 3&4 3 WEST 1&2 3&4

01. Gas now rate, m1/SJX 382 380 338 352 367 356

02. TemperaLurc of gas, •c 146 142 136 148 144 137

03. lnlcL dust concentration 90 56 58 73 57 39

gm/Nm,

04. Efficicncy,<J �

99.89 99.73 99.74 99.88 99.48 99.24

05. No. of casings 4 2 2 2 2 2

06. No. of series fields 6 6 7 6 6 5

07. ManufaclUrcr of ESP BHEL BHEL BHEL BHEL BHEL BHEL

21

Page 28: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Sl . PARAMETER RAMA· DADRI ROPAR KOTA METIUR ANPARA KOLA- KOLA No. GUN DAM 3&4 3&4 GHAT GHAT

5&6 1,2&3

0 I. Gas now rate. m3/sec. 341 332 370 347 361 361 356 306

02. Temperature of ga._, ·c 145 134 127 134 145 145 133 141

03. Inlet du�t concentration 62 62 62 39 42 43 51 51

gm/Km1

04. Efficiency.% 99.52 99.9 99.75 99.62 99.6-t 99.3 99.7 98.5

05. :\o. of casmgs 2 4 2 .., 2 2 2 2

06. �o. of scric� fields 4 6 7 6 6 '7 5 4

07. Manuracturcr of ESP Flakt, BHEL BHEL BHEL BHEL BHEL BHEL VOLTAS

Il.aly.

22

Page 29: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Table 10

Summary of Design data for Representative Fly-Ash Precipitators

Unit Rating : 100/110/120 MW

SL P ARA�1F1T:.R MUZAFFAR· SABAR· KORADI KALCO 8\SORE PARICIIA I'A'IiKI SIKKA OUR-'lio. PUR \1ATIIY GAPUR

PROJ.

Ecrs LTD

0 1 . Gas now rate. m '/sec. 202 197 242 217 275 207 230 220 182

02. Temperature or gas. •c 145 152 180 140 200 143 180 137 142

03. Inlet dust concentration 50 40 50 43 70 4 1 62 72 78

gm/Nml

04. Efficiency. % 99.50 99.74 99.7 99.4 99.R6 99.1 99 84 99.79 99

05. No. of casings 2 2 2 2 2 2

06 No or �eric.� field 7 6 4 6 6 6 4 6 5

07. Manufacturer of ESP BHEL BHEL BHEL BHEL BHEL BHEL BHEL BHEL VOL-

TAS

23

Page 30: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Table 1 1

Summary of Design data for Representative Fly-Ash Precipitators

Unit Rating : 60/62.5/67.5 MW

SL PARAMETER RAMAGU RAJG- INDRAP· ENN- CESC RENu- KOlliA· KOTiiA

NO. NOAM 'B' HAT RASTHA ORE SARAR GUDAM GUO AM

0 1 . Gas now rate, mlfs 132 132 150 150 143 145 106 106

02. Temperature of gas, °C 152 138 150 200 140 160 ISO 150

03. Inlet dust concemn. 9-1 66 66 70 68 85 108 108

gm/Nm'.

04. Effictency, % 99.63 99.8 99.81 99.86 99.8 99.8 99.63 99.61

05. No. or casings 2 2 2 2 2

06. No. or series fields 4 5 4 6 5 5 4 4

07. Manufacturer of ESP BHEL BHEL BliEL BHEL BHEL BHEL A PH MEL VOLT AS

24

Page 31: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

8.0 REASONS FOR POOR PERFORMANCE OF ESPs

8.1 INTRODU<..IION

Many year� of experience have shown that problem of some magnirude are encountered in a s•gnificant percentage of fly ash precipitators These problems fall into three major categories: Fundamental, mechanical and operational. The underlying causes of poor performance are attributable to deficiencies m one or more of these

pnmary areas. Diagnosis and cure of problem proceeds most smoothly and expe­ditiously by sc1entific and systematic methods. A list of frequently encountered

problems 1s given in Table-12.

8.2 FUNDA \1ENTAL PROBLEMS

Fundamental difficulties include high resJsuvuy particles, panicle re-entrainment, poor gas flow, poor rapping, badly designed electrode equipment and i n some

cases undersize precipitators. Scientific procedures exist for determining and isolaung these difficulties.

8.3 MECHA "'-ICAL PROBLEMS

�echamcal troubles comprise principally poor alignment of clecmxles, vibrating

or swinging corona wires, bowed or distorted collecting plates, excessive dust

build up or deposits on the collecting and corona electrodes, air in leakage in

hoppers, gas ducts etc. and dust mountains or piles in connecting gas ducts. The

correction of these difficulties usually is fairly obvious, once they are located. Again,

systematic methods based on symptoms, measurements and observations are most

effective.

8.4 OPERATIONAL PROBLEMS

Difficulties attributable to operational factors cover such items as hoppers full or overflowing with collected dust poor electrical settings, failure to empty hoppers,

over loading precipitator equipment by excessive gas flow or dust

concentration and upsets in operation of boiler to which the precipitator is con­

nected.

Table 12

Summary of Precipitator Problems and Difficulties

A. Fundamental problems

0 I . lligh resistivity particles

02. Rc-enrrainmenl of collected panicles

25

Page 32: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

03. Poor gas flow

04. Inadequate rapping equipment

05. Badly designed electrode systems

06. insufficient or unstable rectifier equipment

07. Insufficient number of corona sections

08. Undersize precipitators

09. Gas velocity too high

10. Aspect ratio too small

B. Mechanical problems

0 1 . Poor electrode alignment

02. Vibrating or swinging corona wires

03. Distoned or skewed collecting plates

04. Excessive dust deposits on collecting electrode and corona electrodes

05. Air in leakage into hoppers, shells or gas ducts

06. Formation of dust mountains in precipitator inlet and outlet ducts.

07. Gas sneakage through hoppers and around precipitator zones.

C. Operational problems

01. Full or overflow hoppers

02. Shoned corona sections

03. Precipitator overloaded by excessive gas now

04. Predpitator overloaded by excessive dust concentration

05. Process upsets (poor cumbusrion, steam leaks etc)

06. Rectifier sets or controls poorly adjusted

07. Poor adju�tment of rapper intensity/frequency.

26

Page 33: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

9.0 MEASURES TO IMPROVE THE PERFORMANCE OF ESP I N OLD POWER

PLANTS

9.1 INTRODt:CfiON

As demands on particulate erruss10ns become more and more stringent in order

to comply with the requirements of pollurion control act, many electricity boards and power generating corporations have to improve the efficiency of the existing

electrostatic precipitator. In electrostatic precipitator technology it is called

upgrading/retrofitting.

There are various approaches available to upgrade the electrostatic precipi­

tators. The technical and organisational capabilities required by major retrofit

projects are similar to or even more complicated than those required by new systems.

9.2 FILLING UP TilE DUMMY FIELDS

A number of earlier precipitator installations have been provided with an added

feature of a dummy field (empty section) at inlet/outlet end of the precipitator.

This was included in case it proved desirable to increase precipitator size at a later

date.

The empty secuons can be filled with electrodes to provide additional collection

surface needed. Annexure-II furnishes a list of projects where th1s philosophy has been

adopted.

9.3 REPLACEMENT OF EXISTING ESP BY NKW ESP

Many of the existing generating stations were located in urban areas necessitating

a compact plant general arrangement. When these stations were· initially designed and

erected, minimal dust collection equipment only were installed and no provisions

have been made for future installations. The dust collecting plants installed were

required only for the functional requirement of the boiler viz. to reduce the erosion

of the impellers of induced draft fans and consequent downtime of the boiler.

Consequent to the awareness on controlling particulate emission control, the existing

precipitators which were found inadequate to meet the emission regulations have

been replaced with adequately sized elecrrostauc precipitator. Annexure-ill

furnishes a list of projects taken up under this category.

9.4 AUGME"JTATION OF COLLECTION SVRFACE

This approach entails the installation of additional retrofit electrostatic precipitators

after thorough study of site conditions by prov1ding more collection area and

thereby reducing the emission. This approach has the unique advantage in that the new

27

•.

Page 34: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

equ1pment can be erected without disturbing the operation of the boiler. The installation of additional precipitator independent of the existing boiler system is

advantageous from the point of vie"' of reduced downtime and consequent loss of revenue. Prior to the installation of the new additional precipitator a detailed

stud)' of the effect of the additional pressure drop in the ducong and the precipitator on the operation of the boiler unit will have to be essentially carried out to ascenain the suitability of the induced draft fan to meet the present requirement.

Many of the renovation of electrostatic precipitators carried out by reputed

manufacturers of electrostatic precipitators fall under this category of approach. A list of projects where such renovation through augmentation of collection area has been

taken up is furnished in Annexure-TV.

9.5 IMPROVED ELECTRICAL ENERGISATION

Being an electrical equipment, the electrostatic precipitaLOr will work only if the electrical equipment and particularly the rectifiers work. The technology incorporating

the sem1pulse and multi-pulse concepts yield 1mproved precipitation, increased rehabiluy and unparalleled convenience for the operation These advantages are often

ach1eved with substantially reduced power consumption.

9.5.1 Semipulse Energisation

By changing the mode of operation of transformer rectifier control. an appropriate number of half waves can be blocked between the firing of the rectifier thyristOrs. Thus the charging of the precipitator is made an an mtermment \\ay which means

that a pulsating corona with pulse width of some milli-seconds IS fom1ed in the ESP.

D1fferent charging modes can be switched on from a pmentiometer to suit the

andtvidual field. Semi-pulse energisation is today in operation in many power plants and a lot of experience has been achieved.

9.5.2 Multi-Pulse Energisation

Pulsed encrgisation of elecrrostatic precipitator is a way of improving the perform­

ance of the precipitator especially when high resisti\it} dusts are present The equipm�;nt bemg used creates pulses of shon duration of approximately 1 00 mtcro

s�;conds High spark over \:Oltages compared to convcnuonal energisation can, thl!reforc, be usl!d. A reduction m power consumpuon when switchmg to pulsed

encrgisation can also be achieved. The serious drawbacks for the pulsed TR sets so

far have been high cost comparen to conventional eqUipment. If the precipitator can be made smaller. the total cost is attractive however.

9.6 FLUE GAS CONDITIONING

Control if particle resistivuy by moisture and chemical condl!loning of the earner gases is achtcved by adsorption of moisture and chemical substances. The

28

Page 35: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

- -----

adsorpuon and hence the conductivity is a surface effects and ts greater at lower temperatures.

9.6.1 Moisture Conditioning

Conditioning by steam injection or \\Jter sprays is a standard method and can be more effective at temperatures below about ISO Deg. Cent. as would be expected because of the grl!ater adsorption of the water vapour on the panicles at these tempera­tures.

9.6.2 Chemical Conditioning

Chemtcal agl:nts such as S03, NH3 and t-\aCI have found considerable use as condition­ing agents but have definite limitations owing to cost and apphcation factors. By far the most 1,\:idely used conditiomng agent i'\ SO, (or H2S04). However, the application ol SO, conditioning to large coal fired power plants burning low sulphur coals is beset wuh a number of problems. These are related to the handling of the large quantities of the chemicals required. maintenance problems. the unfamiliarity of power plant engineers with chemical techniques and under some conditions the posstble cmtssion of sol.

Ammonia conditioning was tried m one of the power plants but showed no observable effect of any kind.

10.0 MEASLRES TO E'St;RE CO�T�UATION OF 11\ITIAL GOOD PERFORM­

ANCE

10.1 11\IRODU(.IION

The number of elcctro<;tatic precipitator mstallations have grown at an accelerated pace. While much has been discussed and ,., ritten on attaining collecting performance with the precipitator, a major '01d has occurred in the idennfication and transfer of infonmllion needed to keep reduce maintenance costs and to prevent deterioration of the collector perfom1ance through the failure of C<.tUtpment. This section is intended to highlight many of the repllitive problems that have plagued the users of precipitators. The existence of these problems could be related to the complexity of the process or to a le1ck of well defined operating techniques among other reasons.

The perfonnance of the precipitator is influenced by a number of factors, many of wh1ch an.: controllable. Bas1cally a precipitator may seem to be a rather static piece·of e4uipment. involving only a few moving pans. Howt!vcr. the mtemals are rather heavily loaded and operate in a dirty environment under relatively high and unfavour­able temperature conditions.

29

Page 36: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

10.2 ALIGNMENT OF ELECTRODE SYSTEM

Accurate alignment of corona and collecting electrode is of major importance for good performance. Off-center and misaligned elecrrodes may easily result in a loss of 10% or 15% in operating voltage of a precipitator. Electrode alignment should be one of the major checks to be made by operators during equipment outage and overhaul periods.

10.3 CLEANJNG OF ELECTRODES

The performance of an electrostatic precipitator depends on the amount of elecrrical power absorbed by the system. The highest collection efficiency is achieved when maximum possible elecrrical power for a given set of operating conditions is utilised in the precipitation process. During the operation of a precipitator, the applied vollage is reduced by the potential drop across the deposited dust layer on the collecting electrodes due to the current flowing through it. This results in reduction of the effective voltage which consequently reduces the collection efficiency. Too thick a dust layer on the collecting electrodes will also lead to unstable operating conditions. The dust deposited on the emitting wires results in non-uniform corona. Therefore, the efficiency decreases with increased or abnormal dust deposits on the collecting and emiuing electrodes. This necessitates that the rapping system of both collecting and emitting electrodes are kept in working conditions.

10.4 GAS TEMPERATURE

Operation of the precipitator at gas temperaturs below the acid dew point results in the following:

- Failure of emining electrodes due to stress corrosion cracking

- Corrosion of the internals

- Collection of wet dust on the electrodes leading to fonnation of 'hard-to-rap' layers and consequent reduction in the performance of ESP.

10.5 SPARK RATE

The operating voltage and current keep changing with operating conditions. This is taken care of by an automatic voltage controller in the electronic controller unit. Too high a flash-over rate will not only result in reduction of useful power and interruption of precipitation process but will also cause snapping of emitting electrodes due to elecrrical erosion. It is recommended that for the best performance the flash-over rate shall not exceed 5 sparks per minute.

30

Page 37: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

10.6 RAPPI'JG FREQliENCY

The frequency and sequence of rapping of collecting and emitting electrodes are

programmed by the synchronous programme/master controller.

The time intervals between the raps for the various fields can be optimally chosen to

permit build-up of sufficiently thick layer so that when rapped, the dust is dislodged

in the form of agglomerates.

Too high a rapping frequency will dislodge the dust layer before formation of agglo­

merates, resulting m a re-enrrainment and puffs through the stack.

10.7 OIL COMBUSTION

The quality of oil used during start-up or stabilisation of coal firing can have an

important impact on precipitator operation. Unburnt oil if passed into ESP can coat the collecting and emitting electrodes.

This fouling of ch:ctrodes deteriorates the electncal conditions 1.e. reduces the pre­

cipitator operating voltage due to high electrical resisuvity and consequently the

ESP performance deteriorates. The precipitator performance remains poor untill the oil vaponses and the layer gers rapped off, which usually takes a few weeks time.

Also the unbumt oil in the ESP poses the danger of fire hazard. Hence. 1m .. · current

settings (without any flashover) are recommended during oil firing.

10.8 AIR CONDITIONING OF CONTROL CABINS

The ESP control room houses sophisticated electronic controls apart from the related switch gear and control gear. The reliable operation of these controls directly reflects

on the precipitator performance. In order to ensure the controls in proper working

conditions, it is essential to maintain a dust free atmosphere with conrrolled

ambient conditions. Therefore. the air conditioners should be kept in proper working

condition.

10.9 HOPPER EVACUATION

Improper/incomplete hopper evacuation is a major cause for the prectpitator mal­

function. If the hoppers are not emptied regularly, the dust will build up to the

high tension emitting system causing shons. Also the dust can push the internals

up causing misalignment of the electrodes. Though the hoppers have been designed

for a storage capacity of 8 hours under MCR condiuons. this provision shalJ be used only in the case of emergency. Normally the hoppers should not be tre<hed as

storage space for the collected dust.

3 1

Page 38: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

10.10 DUST CONCENTRATION IN FLUE GASES

The dust concentration in the gases is much higher in the front part of the precipitator

than in the rear. The current distribution is influenced by the dust concentration. Where

it is high, the current is suppressed i.e. inlet fields will rake less current than the outlet

fields.

32

Page 39: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

LIST OF MEMBERS OF ESP COMMITTEE

Dr. N. Tata Rao

Ex-Chairman

Andhra Pradesh State Elecoiciry Board

Vidyt Soudha

Hyderabad-500 049

Sri A. Raman

Director

Central Electricity Authority

Sewa Bhawan

R.K. Puram

New Delhi- 1 1 0 066

Sri R.K. Narayan

General Manager

National Thermal Power Corporation Ltd.

Sk1pper House

62 - 69 Nehru Place

New Delhi - 1 1 0 019.

Sri S.N. Krishna

Addl. General Manager

Boiler Auxiliaries Plant

Bharat Heavy Elecrricals Ltd.

Ranipet-632 406

Sn S. Balagurunathan

Engg & Devpt Manager

Air Quality Conrrol Systems

Engineering & Development Centre

Bharat Heavy Electricals Limited

Ranipet-632 406.

Sri M.S.K. Prasad

Chief Engineering Manager

Engineering Projects Division

Manakji Building

127 Mahatma Gandhi Road

Bombay - 400 023

33

ANNEXURE - I

. . . . Chairman

. . . . Member

. . . . Member

. . . . Member

. . . . Member

. . . . Member

Page 40: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Sri Anup Guha

General Manager

M/s. Andrew Yule & Co. Ltd.,

Air Pollution Control Unit

225-E, A. J. Chandra Bose Road Calcutta - 700 020

Sri S. Ghosh

Manager

ESP Depanment

M/s. F1akt (India) Ltd.,

Post Box 4 1 1

Calcuua - 700 02 1 .

Sri N. Bagchi Director (CP)

Ministry of Environment & Forests

'Paryavaran Bhawan'

C.G.O. Complex

Locii Road

New Delhi - 1 10 003

Dr. B. Sengupta

Senior Scientist

Central Pollution Control Board

Ministry of Environment & Forests East Arjun Nagar

Delhi- 1 1 0 032.

. . . . Member

. . . . Member

. . . . Member

. . . . Member Convener

34

Page 41: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

ANNEXURE-ll

LIST OF THERMAL POWER STATIONS WHERE THE DUMMY FIELDS EXISTED IN THE PRECIPITATOR HAVE BEEN/ ARE BEING FILLED UP

SL. Plant Name/ Capacity

No. Unit No(s). (MW)

0 1 . Turicorin 1,2 2 x 210

02. Kolhagudam 7,8 2 x 1 10

03. Koradi 5 1 x 200

04. Bhusawal 2 1 x 2 10

05. Parli 3 1 x 210

06. Nashik 3,4,5 3 x 210

35

Page 42: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

A!'iNEXURE-111

LIST OF THERMAL STATIONS VVHERE TilE ELECTROSTATIC PRECIPITATORS

OF INADEQUATE SIZE HAVE BEE1'i/ARE BEil\G REPLACED WITH ONES OF

ADEQUATE SIZE TO J\.1EET THE EMISSION REGULATIONS

SL. Plant �arne/ Capacity (MW)

No. Unit No(s)

0 1 . Koradi 1 ,2,3,4 4 x 120

02. Ennore 1 ,2 2 x 60

03. Ennore 3,4,5 3 X 1 10

04. Panki 3,4 2 x 1 10

OS. Faridabad I ,2 2 x 60

36

Page 43: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

ANNEXURE-IV

LIST OF THERMAL STATIONS WHERE RENOVATION OF ELECTROSTATIC

PRECIPITATORS THROUGH AUGME:\TA TIO� OF COLLECTION AREA

HAVE BEEN/ ARE BEING TAKEN UP

SL. Plant ::-\arne/ Capacity (MW)

No. Unit �o(s)

OL Gandhinagar I ,2 2 x 120

02. Bada.rpur 1 .2.3 3 x 100

03. Gurunanak Dev 1 ,2,3.4 4 x 100

04. Al)larkamak 3.4 2 x 120

05. Indraprastha 2.3,4.5 4 x 60

06. Kothagudam 5.6 2 x l l0

07. Pathrathu 7,8 2 x 1 10

37

Page 44: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

l.IST OF PUBLICATIONS CONTROL OF URBAN POLLUTION SLRJCS

l . Union Territory of Delhi (Detailed): CUPS 2 1978-79 2. Industrial Survc} Lmon Territo!) of Delhi: CUPS 3 1 978-79 3. Waste\\ater Collection. Treatment & Dtsposal m Class I

Ciue� CliPS 4 1 978-79 4. Status of Water Suppl) and Wastewater Collection. Treatment &

Disposal in class-11 TO\\ns m lndta: CCPS 6 1979-�0 5. Inventory & Assessment of Pollution Emission in and Around

Agra-Mathura Reg10n (Abridged): CUPS/7' 198 1 -82 6. Umon Territor} of Chandigarh:Prelimmar) Rcpon:CUPS 8 1981 -82 7. Union Territory of Pondichcrr): CUPS 9/1 9R3-f<� 8. Vehicular Air Pollutton m Delhi - A Preliminan study

1982-83:CLPS 1 0/1982-83 9. Asstmilation Capactt} of Point Pollution Load. The River

Yamuna, U.T of Delhi:CUPS1 12fl982-83 10. A Method to Determination of Minimal Stack Height: CUPS/ 1 3/ 1984-g5

PROGRAMME OBJECTIVE SERlE.�

1 . Episodal Pollution: A case study Union Territory of a Goa: PROBES

Rs. 80/­Rs. 40/-

Rs. 100/-

Rs. 100/-

Rs. 50/­Rs. 50 -Rs 50 -

Rs. 40/-

Rs. 40/-

511979-80 Rs. 1 5 -.., Proceedings of the Workshop on Biological Indicators and Indices

on Emironmental Pollution: PROBES 6 1982-83 R�. 65 -3. Ocean Outfall for Pondicherr} Paper Ltd. A Case Study Union

fcrritory of Pondtcherry: PROBES 7 1982-83 Rs. 30/-4 lmtial En'vironmental Evaluation - Otl Drilling and Group Gathcnng

Station�: PROBFS g 1981 -82 Rs 30/-5 Stmplc Guide CodL of Pracucc for Bcuer Hou e Keeping and

Pollution Control in Electroplating lndustl) ( Engitsh Hindi): PROBES 9 1981 -82 Rs. OS -

6 Water Pollution Control - An Ovcrvie\\ . PROBES/ I I 1 982-83. 7 Report on Caustic Soda untls: Hindustan Heavy Chemicals:

West Bengal. PROBES/ 12 / 1982-83 Rs. 20/-8 . Status of Environmental Pollution: Kcsoram Rayon. West Bengal

PROBES 13 1982-83 Rs. 25 -9. Pt!rformance Study of Wastcv.aLer Treatment Plant of Gancsh

Floor Mills. PROBES 1 5 1982-83 1 0. Environmental Status: Barapani Lake. Meghala}a. PROBES 1 7/1 983-84 I I . Assessment of Generation and Control of Water Pollution in

J . . K. Rayon Industry. Kanpur:PROBES/18/1 982-83 Rs. 1 5'-1 2. Pollutton Control m Man-Made Ftbrc Industry wtth special Reference

to Zmc. at Harihar ?oly-hbre. Karnataka. A Case Stud) : PROBLS 19 19 3-84 Rs. 1 5 -

1 3. Procced1r.gs of the National Workshop on \tarine Outfall::. (April 26-2 1984. Panaji. Goa): PROBES 20 1983-84 Rs. 50 -

1 4 Dust Pollution From Stone Crushers (Sohna Tourist Camp. Gurgaon Distl. Haryana: PROBES 2 1 1 983-84 Rs. 30,-

1 5. Performance Study of Vanaspati Wastewater Treatment Plant at M/s Shriram roods and Fertilizer� lndustr;.. PROBES 22 1983-8� Rs. 30/-

1 6 State of Progress of ProJect "Operation Pollution Control in Damodar Rt\erN As on March 3 1 .1 984: PROBES 23 1984-85.

1 7 . Charactensttcs and Treatment of Waste\\ater From on Electric Bulb Manufactunng L'nit: PROBES 24 1983-84.

1 8. Control of Air Pollution from Coal Fired Reverberatory 1-urnal:c· PROBES/25/ 1984-85.

Page 45: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

19. Brochure on Effiuenl Treatment Plant Built in Karnataka State. As in 1984: PROBES 26 1985.

20. Zonal Committee Repon on Assessment of Pollution Control Measures in Chlor-Alkali Industries (Mercuf) Cell): PROBES 27 1985.

2 1. National Inventory of Water Polluting Industries and Effiuent Treatment Plant Status: PROBES 28 1984-85.

22. An Assessment of Mercury Problem at Kothari lndustnes Ltd. Madras - A case study. PROBES 29 1985.

23. Episodal Pollution caused by a Barrier Across Eloor branch of Periyar River PROBES 14/ 1982-83.

24. Performance study of Wastewater Treatment Plant at Mother Datry PROBES/ 16/ 1982-83.

25. Performance study of Ton-Exchange Resin Treatment System for Mercury Removal From Wastewater at Gujarat Alkalies and Chemicals Limited, Baroda, GuJarat PRO BES/30/ 1985-86.

26. A Study on the Environmental Damage Due to Lethal Chemical Catastrophe in Bhopal PROBES 3 1 1985.

27. Report on Identification of Import component of Waste Treatment Technolog} and Know-how PROBES 32/1985-86.

28. Impact Study and Evaluation of Pollution Status of Oil Dnlling and Group Gathering Stations of Assam PROBES 33/1985.

29. Groundwater Quahty in the Union Territory of Delhi - Abridged Repon PROBES/34/ 1985-86

COMPREHENSIVE INDUSTRY DOCUMENT SERIES

1 . Comprehensive Industry Document Man-Made Fibre Industry: COINDS/ 1/1979-80

2. Minimal National Standards Man Made Fibre I ndustry: COIN DSt2/ 1979-80

3. Comprehensive Industry Document Oil Refineries: COINDS 3,1981-82 4. Minimal National Standards: COINDS/4 1981-82 5. Comprehensive Industry Document, Chlor-Alkali (Abridged) Industry:

COINDS/5/1979-80 6. Minimal National Standards Caustic Soda Industry: COINDS

6 1979-80 7. Comprehensive Industf) Document Khandsari Sugar Industry:

Rs. 100/-

Rs. 40/­Rs. 100.'­Rs. 40/-

Rs. 50 -

Rs. 40/-

CO E'•-i OS 7 1980-8 1 Rs. 40 -8. Minimal �attonal Standards Sugar Industl): COII\DS 9 1980-8 1 Rs. 50 -9. Comprehenst\'e Industry Document Fermcntauon (Moltcnes. Breven� and

Distilleries) Industr} Series: COINDS 10/198 1-82 Rs. 100/-10. Mmimal Nat10nal Document Fermentation (Moltenes, Breweries and

Distillenes) Industry Series: 1 1. Emission RegulatiOns (July 1984) Part I : COJNDS/17/1983-84

12. Minimum National Standards Pesticide Manufacturing and Formulating Industry COINDS!l5/ 1985-86

13. Emission RegulatiOns (July. 19H5) Part II: COINDS 18. 1984-85

Rs. 20 -Rs. 20t-

Page 46: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

14 Minimal li,Jational Standards Straight Phosphatic fertiliser Industry COIND() '1 91 1984-85

\SSLSS:\-1£:\T & DE\ E.LOP:\IL''T Sf 0\' OF RIVI:I� BA ' I� SERlE...�

I . Un'c.r Territory of Daman. Dadra & '\.Jgar 1-fa ... eli (Abridged): A DSORBS I 1 ?78-79 Rs. 40 -

2. Basm Sub-Basm Inventor) of \Vater Pollution. The ganga Basin part One. The 'r umun .. Sub-Basin: ADSORBS 2 1978-79 R:-t. lOO -

3. Scheme for Zoning ana Cl<.ts�ification ot Indian Rhcrs Estuaries and Coastal Waters (Pt. One Sweet Water). ADSORBS 3 1978-79 Rs. 40 -

4. Comprehensive Pollution Survey and Studies of Ganga River Basin m West Bengal: ADSORBS14/1980-8 1 Rs. 200/-

5 Union Territory o.' Goa. Daman and Diu (Dist. Go<.t) Abridged: ADSORBS 5/1982-83 Rs. 50 -

6. Stream Water Quality in Major Rivers (Gujarat St •. tc} During Btennium 1979-80 Survey: ADSORBS/6/1 982-83 Rs. 50/-

7. Ganga Basin Report (Part If-Entire Ganga Bastn): ADSORBS/7 1982-83 Rs. 500 -8. Ionic Balance of ·water Quality at Uttarakhand Ganga Forming

Tributaric�: ADSORBS 9 1 982-83 Rs. 50 -9. Quality and Trend of River ) amuna 1979-�Q: ADSORBS 10 1 982-83 10. Basm Sub-Basin Inventory of Water Pollution: The Brahmaputra Basin

Part-1. The Dilli-Disanl! Sub Basm: ADSORBS I I 1983-8.., Rs. 25 -I I . Water Quality Monito.mg . . \n Indian Experience: ADSORBS 12 19R4- 5 R!). 20 -1 2. \Va c Po'lu 'on from Mass-Bathing - Case Studic.;; in Ganga

ADSORBS 8 1983-84 13. Atlas (River Ba�in)

ADSORBS/1 3/ 1984-85

COASTAL POLLl!TIO� CO:\TROI. SERIES

l . lJse Classification of Indtan Coast and ConOtcts Part I : Tamil Nadu Coast: COPOCS/ 1 ' 1982-83

2. Use Classification of India Coast and Conflicts Part I I . Kanya Kumari to Goa: COPOCS 2 1984-85

RESOURC� RECYCLING SERIES (RERES)

1 . Recycling of Sewage and Industrial Effiuent on Land - Monitoring and Survcillanc.� Report on Chandigarh Sewage Fam1 RER ES I /1985

LABORATORY <\NALYTICAL TECHN1QUES SERIES (I.ATS)

1 . Measurem�:nts of Mercuf) by Cold Vapour Atomic A b orption Technique LATS/ 1 / 1 985-86

2. Lindane Analysis by Gas Chromatograph Technique LA TS 2/1 985-86

Rs. 550 -

Page 47: REPORT ON DESIGN AND OPERATING PARAMETERS OF …

Printed at SHAKTI PRIMTING PRESS 5A/8, Ansari Road, Darya Ganj, New Delhi-1 10 002 Phone : 3272837, 3261533


Recommended