Jan. 8-9 – Traveled from Manila to Aparri.
Site inspection of the Municipal Hall roof.
Courtesy call to Hon. Ismael V. Tumaru, Municipal Mayor (middle), with Ms. Saripa May Hiccup (second from the right,
WFP Field Monitor of Cagayan), Engr. Rolando Liberato (left most, municipal engineer),and Mr. Raymond Cao (second
from the left, SolaRain staff).
A meeting was held with key people after the site inspection. The water system was intended for the disaster or
evacuation center that will be built in three months. However, it was agreed that the clean water system be temporarily
installed at the back of the municipal hall and transferred to the disaster/evacuation center once it is constructed.
Jan. 10 – Installation of solar powering components.
Procurement and cleaning of six 200-liter drums