GOVERNMENT PROCUREMENT REFORM ACT REPUBLIC ACT NO. 9184
Transcript
Page 1: Report RA2

GOVERNMENT PROCUREMENT REFORM ACT

REPUBLIC ACT NO. 9184

Page 2: Report RA2

An act providing for the modernization, standardization and regulation of the procurement activities of the government and for other purposes.

Page 3: Report RA2

WHAT IS PROCUREMENT?  

Procurement refers to the acquisition of Goods, Consulting Services, and the

contracting for Infrastructure Projects by the Procuring Entity. (Article I, Sec. 5

(n), R.A. 9184)  

Procurement means the acquisition by any means of goods, construction or

services.

Page 4: Report RA2

1. Transparency2. Equal Opportunity(through

standardization)3. Streamlined Process4. Accountability5. Public Monitoring

Governing Principles of Procurement

Page 5: Report RA2

Coverage:Goods:

ItemsSuppliesMaterialsneeded in

Transaction of public businessPursuit of any government undertaking, project or

activity

Page 6: Report RA2

Still considered as goods:Services that are not consulting services

General Support Services(e.g. Janitorial, Security, Repair and Maintenance

Services)Related or Analogous Services(e.g. Lease of Office Space)Materials and supplies needed for such services

Page 7: Report RA2

General Rule (section 10, RA 9184):Competitive Bidding

Page 8: Report RA2

1. Method of procurement 2. Open to participation by any interested party 3.Consists of the following processes:

advertisement, pre-bid conference, eligibility screening of prospective bidders, receipt and opening of bids, evaluation of bids, post-qualification, and award of contract,

4. Specific requirements and mechanics of which shall be defined in the IRR to be promulgated under this Act

What is Competitive Bidding?[Section 5 (e), RA 9184]

Page 9: Report RA2

The General Processes of Competitive Bidding:

AdvertisementPre-bid conference

Eligibility screening of prospective biddersReceipt and opening of bids

Evaluation of bidsPost-qualificationAward of contract

Page 10: Report RA2

Head of Procuring Entity forbidden as Chairperson or

member of BAC

BAC Composition:

Page 11: Report RA2

BAC Composition: (for Agencies, GOCCs,

SUCs, GFIs,etc.)Regular Members:1. Chairman- at least third ranking

permanent official of procuring entity2. Member- procurement/legal/

administrative expertise and at least fifth ranking permanent official

3. Member- finance expertise and at least fifth ranking permanent official

Page 12: Report RA2

BAC Composition:Provisional Members:

1. Member- technical expertise in relevant to the procurement

2. Member- end user unit

Page 13: Report RA2

One (1) representative each From the regular offices under the office

of the local chief executive (e.g., Office of the Administrator, Budget Office, Legal Office, General Services, Engineering Service)

To be appointed by the local chief executive

BAC Composition: (for LGUs)

Page 14: Report RA2

BAC Composition:Observers: Two (2)1. At least one (1) shall come from a duly

recognized private group in a sector or discipline relevant to the procurement at hand

2. The other from a non-governmental organization (NGO)

COA Representative

Page 15: Report RA2

BAC Composition:

No. of Members:At least Five (5) but not more than

Seven (7)

COA Representative & Observers (non-members)

Page 16: Report RA2

honoraria to the BAC members in an amount not to exceed twenty-five

percent (25%) of their respective basic monthly salary subject to availability of

funds (Section 15)

Page 17: Report RA2

from a pool of technical, financial and/or legal experts assist in the procurement process particularly in the eligibility screening, evaluation of bids and postqualification

Technical Working Group

Page 18: Report RA2

Prepared by procuring entity Following the standard forms and

manuals prescribed by the GPPB(Government Procurement Policy

Board)

Bid Documents Preparation:

Page 19: Report RA2

Standardized Bidding Procedures for Goods

Pre-ProcurementConf. 2-wk advertisement Pre-Bid

Conference

Opening ofEligibility Env. &Eligibility Check

Opening ofTech. Env. &Prel. Exam.

Opening ofFinancial Env.

Submission ofEligibility Req. & Bid

Bid Evaluation& Ranking Postqualification Award of

Contract

Page 20: Report RA2

Invitation to Bid

1. Publication2. Website3. Posting

Page 21: Report RA2

Twice:1. Minimum 6 days maximum 14 days in

between publication2. Newspaper of general nationwide

circulation3. Newspaper published at least 2 years

prior to advertisement

Publication:

Page 22: Report RA2

Posting @ Website

1. Website of the procuring entity2. Website of the service provider of the

procuring entity, if available3. Maximum period of 14 days

Page 23: Report RA2

1. Conspicuous place2. Reserved for the purpose3. Certified by the BAC Secretariat of the procuring entity

Posting at premises

Page 24: Report RA2

BAC determines if each prospective bidder is eligible to participate

By examining the completeness of each prospective bidder’s eligibility requirements

Using a non-discretionary “pass/fail” criteria

Eligibility Check:

Page 25: Report RA2

Eligibility Documents:

Class “A” DocumentsClass “B” Documents

Page 26: Report RA2

What are these Class “A” Documents?

Legal Documents:1. DTI/SEC registration documents, as

applicable2. Mayor’s Permit/Municipal Licenses3. “Non-blacklisting” statements4. TIN5. Other appropriate Licenses/Permits

Page 27: Report RA2

What are these Class “A” Documents?

Technical Documents:Statement of the prospective bidder of all its ongoing and completed government and private contracts within the relevant period, including contracts awarded but not yet started, if any

Page 28: Report RA2

What are these Class “A” Documents?

Financial Documents:1. Audited financial statements, stamped

“received” by the BIR or its duly accredited and authorized institutions, for the immediately preceding calendar year, showing, among others, the prospective bidder’s total and current assets and liabilities

Page 29: Report RA2

What are these Class “B” Documents?

1. Valid joint venture agreement, in case of a joint venture

2. Letter authorizing the BAC or its duly authorized representative/s to verify any or all of the documents submitted for the eligibility check

Page 30: Report RA2

Procedure:

1. Late bids shall not be accepted2. Opening of Technical Envelopes3. Counter-checking compliance of

Technical Envelope with requirements4. Opening of Financial Envelope5. Counter-checking compliance of

Financial Envelope with requirements

Page 31: Report RA2

6. Bid Evaluation7. Ranking8. Lowest Calculated Bid

Page 32: Report RA2

Bids above the ABC are automatically disqualifiedNo Floor PricesIf failed Technical Envelope, cannot open the Financial EnvelopeBid shall include all taxes

Note:

Page 33: Report RA2

Post-QualificationTo determine whether the

bidder concerned complies with and is responsive to all the requirements and conditions for eligibility, the bidding of the contract, as specified in the bidding documents

Page 34: Report RA2

Post-Qualification

BAC shall verify, validate and ascertain all statements made and documents submitted by the bidder with the Lowest Calculated Bid/Highest Rated Bid.

Page 35: Report RA2

Post-QualificationPeriod:

Within seven (7) calendar days from determination of the Lowest Calculated Bid

In exceptional cases, the seven (7) calendar day period may be extended by the GPPB (Government Procurement Policy Board)

Page 36: Report RA2

Result:

Lowest Calculated Bid becomes

“Lowest Calculated and Responsive Bid”

Page 37: Report RA2

Recommendation of the Award to the Head of the Procuring Entity

Action of Head on Recommendation:

1. Approve2. Disapprove

Page 38: Report RA2

Action of Head on Recommendation:

Disapproval based only on valid, reasonable and justifiable grounds to be expressed in writing, copy furnished the BAC. (Bids and Awards Committee)

Page 39: Report RA2

Republic Act No. 9184

If approval:Head issues the Notice of Award

BAC notifies the losing bidders of the decision

Page 40: Report RA2

Contract Preparation and Signing

Time Period:

Ten (10) days from receipt of Notice of Award by Winning Bidder

Page 41: Report RA2

1. No Bids are received2. No bid qualifies as the Lowest

Calculated Responsive Bid or Highest Rated Responsive Bid

3. Refusal of winning bidder to accept the award of contract

Failure of Bidding:

Page 42: Report RA2

Alternative Modes of Procurement

Limited Source Bidding Direct Contracting

Repeat OrderShopping

Negotiated Procurement

Page 43: Report RA2

Alternative Modes of ProcurementLimited Source Bidding or Selective Bidding

A method of procurement of goods and consulting services, that involves direct invitation to bid by the concerned procuring entity from a set of pre-selected suppliers or consultants with known experience and proven capability on the requirements of the particular contract

Page 44: Report RA2

Alternative Modes of ProcurementLimited Source Bidding or Selective

Bidding

Procurement of highly specialized types of goods and consulting servicesProcurement of major plant components to maintain uniform quality and performance of the plant as a whole

Page 45: Report RA2

Alternative Modes of ProcurementDirect Contracting or Single Source

Procurement

Applies only to procurement of goodsDoes not require elaborate bidding documentsSupplier is simply asked for a price quotation or a pro-forma invoice with the conditions of saleOffer may be accepted immediately or after some negotiations

Page 46: Report RA2

Alternative Modes of ProcurementDirect Contracting or Single Source

Procurement

1. Proprietary items2. Critical plant components from a specific

manufacturer3. Sold by an exclusive dealer or

manufacturer with no suitable substitute

Page 47: Report RA2

Alternative Modes of ProcurementRepeat Order

Need to replenish goods Procured under a contract previously awarded through Competitive Bidding

Page 48: Report RA2

Alternative Modes of ProcurementRepeat Order

1. Same contract prices2. Not a result of splitting3. Within six (6) months from the date of the

Notice to Proceed of the original contract4. Not to exceed twenty-five percent (25%) of

the quantity of each item in the original contract

Page 49: Report RA2

Alternative Modes of Procurement

Shopping

Submission of price quotations Readily available off-the-shelf goods or ordinary/regular equipment Procured directly from suppliers of known qualifications

Page 50: Report RA2

Alternative Modes of Procurement

Shopping1. Unforeseen contingency requiring

immediate purchase but not to exceed P50,000.00

2. Ordinary or regular office supplies and equipment not available in the Procurement Service not to exceed P250,000.00

Page 51: Report RA2

Alternative Modes of Procurement

Negotiated Procurement

Directly negotiates a contract with a technically, legally and financially capable supplier, contractor or consultant Conditions in law and IRR are exclusive


Recommended