WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer
1
Big Data with Many
Stakeholders
WREF 2012 • May 17 • Denver, Colorado USALeslie Martel Baer, MS, MA, Strategist
RESA Reporting in Colorado
May 17, 2012
2
Many FunctionsRESA Reporting
May 17, 2012WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 3
Fundamental FunctionsShow the IOU is Collecting RESA
funds appropriately
Distributing them to qualifying projects
Purchasing/selling RECs appropriately
Meeting the RES (generation projects)
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 4
RESA & Ratepayers 2%—no more, no
less—is collected from retail customers
See your bill
RESA reports give aggregate picture
May 17, 2012
I Want Cheap Clean Energy
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 5
RESA & the IOUs Proof of RES
compliance Fiduciary
responsibility to investors
Express future intent through Compliance Plans
Would like reduced frequency
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 6
RESA & Administrators,Policy Makers PUC
Ensures RES is metResponsible to
ratepayers○ Advisory Board:
provides information and guidance to the
○ Trial Staff: determine if reporting is accurate and if an audit is warranted
State Policy Makers
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 7
RES & RE Business Looking for unused
capacity in programs How rapidly the
market responds to new programs and other changes
The extent of competition as measured by numbers of installations
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 8
RESA & NGOs Industry trade
associations: working for members
Non-governmental organizations: furthering the “cause” of technologies
Monitor implementation of programs and accomplishment of the RES
RE market Program market impacts
May 17, 2012
9
Process Fundamentals
May 17, 2012WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 10
Xcel’s Monthly Process Pull data from
databases “Manually” sort
and filter Produce reports Process designed
for 34 MW of capacity
Now over 100 MW
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 11
The Bad
The Process Needs to Be Modernized and Transparent
Up to 3-month lag in reporting
Lack of Automation
Audits are voluntary; PUC can call for audits if deemed necessary
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 12
The Bad & The Good
The Process Needs to Be Modernized and Transparent
Some Effort is Underway for Modernization, Transparency
Up to 3-month lag in reporting
Lack of Automation
Audits are voluntary; PUC can call for audits if deemed necessary
All parties use same data set (Xcel, PUC, public)
Pursuing more automation with Community program
Xcel does conduct internal audits and it has caught errors this way
May 17, 2012
13
Issues of Contention
May 17, 2012WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 14
A Budgetary Shortfall Solar*Rewards
extremely popular Up-front
incentives caused high outflows
Issue resolvedSwitch to
performance based incentives
Legal agreement for a loan from Xcel
Series1
Doing OkayWhoopsGetting Back on Track
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 15
RESA Rider Cap Set at 2% of retail
electricity Avoided costs
paid for under Electric Commodity Adjustment
Only incremental cost of RE is paid for by RESA
May 17, 2012
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 16
Incremental Cost Calculation High gas prices =
wind credit to RESA
Low gas prices = wind charge to RESA
Comparison supposed to include new gas plant build out
Usually only rampingMay 17, 2012
17
Stakeholders:Getting It or Getting Dumped?
May 17, 2012WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer 18
Big Data, Minimal Reporting Business, NGOs
may not be getting the details they want
Self-reported dataConsensus on trustLittle examination
outside Xcel More detail
coming More
accessibility?May 17, 2012
19
Thank You!
Colorado Solar Energy Industries AssociationColorado Public Utilities CommissionXcel EnergyVote Solar
May 17, 2012WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer
WREF 2012 • Colorado RESA Reporting: Big Data, Many Stakeholders • Leslie Martel Baer
20
Please Contact Mewith Questions
WREF 2012 • May 17 • Denver, Colorado USALeslie Martel Baer, MS, MA, [email protected]
RESA Reporting in Colorado
May 17, 2012