+ All Categories
Home > Documents > Research Article Hydraulic Transients in the Long...

Research Article Hydraulic Transients in the Long...

Date post: 16-Mar-2020
Category:
Upload: others
View: 7 times
Download: 0 times
Share this document with a friend
12
Research Article Hydraulic Transients in the Long Diversion-Type Hydropower Station with a Complex Differential Surge Tank Xiaodong Yu, 1 Jian Zhang, 1,2 and Ling Zhou 1 1 College of Water Conservancy and Hydropower Engineering, Hohai University, Nanjing 210098, China 2 College of Hydraulic and Civil Engineering, Xinjiang Agricultural University, Urumqi 830052, China Correspondence should be addressed to Jian Zhang; [email protected] Received 11 April 2014; Accepted 17 June 2014; Published 15 July 2014 Academic Editor: Linni Jian Copyright © 2014 Xiaodong Yu et al. is is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. Based on the theory of hydraulic transients and the method of characteristics (MOC), a mathematic model of the differential surge tank with pressure-reduction orifices (PROs) and overflow weirs for transient calculation is proposed. e numerical model of hydraulic transients is established using the data of a practical hydropower station; and the probable transients are simulated. e results show that successive load rejection is critical for calculating the maximum pressure in spiral case and the maximum rotating speed of runner when the bifurcated pipe is converging under the surge tank in a diversion-type hydropower station; the pressure difference between two sides of breast wall is large during transient conditions, and it would be more serious when simultaneous load rejections happen aſter load acceptance; the reasonable arrangement of PROs on breast wall can effectively decrease the pressure difference. 1. Introduction Various turbine operations such as load acceptance, load rejection, and combination conditions produce transients in hydropower station, which are directly related to the safety of whole hydropower station and local power grid, even resulting in substantial damage and human loss in some cases [13]. Study of hydraulic transients in hydropower stations attracts many researchers because of its complexity and significance in practice. Souza et al. [4] simulated transient flow in hydropower plants by considering a nonlinear model of the penstock and hydraulic turbine. Selek et al. [5] com- pared the computational results of transient pressures with measured data for the Catalan Power Plant in Turkey and the agreement is satisfactory. Calamak and Bozkus [6] studied the performance of two run-of-river plants during transient conditions. An et al. [7] presented an effective theory for safe control of air cushion surge chambers based on the numerical simulation of hydraulic transients in hydropower station. e impulse method was used to analyze hydraulic resonance in hydropower systems by Riasi et al. [8]. Except for the MOC [9], some new numerical methods have been used to simulate hydraulic transients in hydropower systems, such as dynamic orifice model [10], finite volume method [11], implicit method of characteristics [12], stochastic method [13], and 1-D-3-D coupling approach [14]. With the rapid exploitation of hydropower resources in some developing countries in recent years, as well as the advanced construction techniques, the arrangement of the pipe systems and hydraulic devices is more complicated. Some diversion-type hydropower stations have a fairly long headrace tunnel, and the water inertia is very large. In order to reduce the amplitude of water level oscillations in surge tanks and accelerate the attenuation, a new type of differential surge tank [15, 16] is designed. However, some undesirable transients may appear because of the complex arrangements and new hydraulic devices [17]. is work investigates the transients in a practical hydropower station with long headrace tunnel and com- plex differential surge tank. Some undesirable transients are mainly analyzed and the PROs are proposed to reduce the pressure difference on the breast wall. e results can provide reference for the design and operation of a similar project. Hindawi Publishing Corporation e Scientific World Journal Volume 2014, Article ID 241868, 11 pages http://dx.doi.org/10.1155/2014/241868
Transcript
Page 1: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

Research ArticleHydraulic Transients in the Long Diversion-Type HydropowerStation with a Complex Differential Surge Tank

Xiaodong Yu1 Jian Zhang12 and Ling Zhou1

1 College of Water Conservancy and Hydropower Engineering Hohai University Nanjing 210098 China2 College of Hydraulic and Civil Engineering Xinjiang Agricultural University Urumqi 830052 China

Correspondence should be addressed to Jian Zhang jzhanghhueducn

Received 11 April 2014 Accepted 17 June 2014 Published 15 July 2014

Academic Editor Linni Jian

Copyright copy 2014 Xiaodong Yu et al This is an open access article distributed under the Creative Commons Attribution Licensewhich permits unrestricted use distribution and reproduction in any medium provided the original work is properly cited

Based on the theory of hydraulic transients and the method of characteristics (MOC) a mathematic model of the differential surgetank with pressure-reduction orifices (PROs) and overflow weirs for transient calculation is proposed The numerical model ofhydraulic transients is established using the data of a practical hydropower station and the probable transients are simulated Theresults show that successive load rejection is critical for calculating the maximum pressure in spiral case and themaximum rotatingspeed of runner when the bifurcated pipe is converging under the surge tank in a diversion-type hydropower station the pressuredifference between two sides of breastwall is large during transient conditions and itwould bemore seriouswhen simultaneous loadrejections happen after load acceptance the reasonable arrangement of PROs on breast wall can effectively decrease the pressuredifference

1 Introduction

Various turbine operations such as load acceptance loadrejection and combination conditions produce transients inhydropower station which are directly related to the safetyof whole hydropower station and local power grid evenresulting in substantial damage and human loss in some cases[1ndash3] Study of hydraulic transients in hydropower stationsattracts many researchers because of its complexity andsignificance in practice Souza et al [4] simulated transientflow in hydropower plants by considering a nonlinear modelof the penstock and hydraulic turbine Selek et al [5] com-pared the computational results of transient pressures withmeasured data for the Catalan Power Plant in Turkey and theagreement is satisfactory Calamak and Bozkus [6] studiedthe performance of two run-of-river plants during transientconditions An et al [7] presented an effective theory for safecontrol of air cushion surge chambers based on the numericalsimulation of hydraulic transients in hydropower stationTheimpulse method was used to analyze hydraulic resonance inhydropower systems by Riasi et al [8] Except for the MOC[9] some new numericalmethods have been used to simulate

hydraulic transients in hydropower systems such as dynamicorificemodel [10] finite volumemethod [11] implicitmethodof characteristics [12] stochastic method [13] and 1-D-3-Dcoupling approach [14]

With the rapid exploitation of hydropower resources insome developing countries in recent years as well as theadvanced construction techniques the arrangement of thepipe systems and hydraulic devices is more complicatedSome diversion-type hydropower stations have a fairly longheadrace tunnel and the water inertia is very large In orderto reduce the amplitude of water level oscillations in surgetanks and accelerate the attenuation a new type of differentialsurge tank [15 16] is designed However some undesirabletransients may appear because of the complex arrangementsand new hydraulic devices [17]

This work investigates the transients in a practicalhydropower station with long headrace tunnel and com-plex differential surge tank Some undesirable transientsare mainly analyzed and the PROs are proposed to reducethe pressure difference on the breast wall The results canprovide reference for the design and operation of a similarproject

Hindawi Publishing Corporatione Scientific World JournalVolume 2014 Article ID 241868 11 pageshttpdxdoiorg1011552014241868

2 The Scientific World Journal

2 Mathematic Model and Calculation Method

21 Governing Equations and Solution Methods for Pres-surized Pipe Model The following equations describe one-dimensional transient flows [18]

Continuity equation

120597119867

120597119905+ 119881

120597119867

120597119909+1198862

119892

120597119881

120597119909+ 119881 sin 120579 = 0 (1)

Momentum equation

120597119867

120597119909+119881

119892

120597119881

120597119909+1

119892

120597119881

120597119905+119891 |119881|119881

2119892119863= 0 (2)

in which 119867 = piezometric head 119881 = flow velocity 119886 =

wave speed 119892 = acceleration due to gravity 119891 = Darcy-Weisbach friction factor 120579 = angle of the pipeline inclinedwith the horizontal119909 = distance along the pipelinemeasuredpositively in the downstream direction 119863 = diameter of thepipe and 119905 = time

The momentum and continuity equations governingtransient flow in closed conduits are classified as quasilinearhyperbolic partial differential equations (PDEs) for which noanalytical solutions are available for a general pipe systemThe method of characteristics (MOC) is widely employedto solve the set of PDEs and these two equations can betransformed into a couple of ordinary differential equations(ODEs) along the characteristic lines The friction item islinearized by using the trapezoidal rule which is of second-order accuracy and some small terms are dropped withoutloss in accuracy It is convenient to develop these equationswith the discharge 119876 instead of flow velocity 119881 as thedependent variable Then the equations can be transformedinto two algebraic equations for computer calculation afterintegration along the characteristic linesThe grid of pipelinesand the time interval follow Courant condition Δ119905 le Δ119909119886

22 Turbine Equations The equation for the acceleration ofthe rotating masses is [19]

119868119889120596

119889119905= 119879 minus 119879

119892 (3)

in which 119868 = the polar moment of inertia of rotating fluid andmechanical parts in the turbine-generator combination (119868 =1198821198772119892 where119882 = weight 119877 = radius of gyration) 120596 = the

angular speed of the unit 119879 = the torque produced by waterflowing through the unit and 119879

119892= the resistant torque from

the generatorWhen load rejection occurs the unit is instantly discon-

nected from the system and thus becomes isolated (ie119879119892=

0) Then the unit has to be quickly closed according to theemergency closure lawwhich is set to the governor in advanceto prevent extended periods of high overspeed which mayinduce severe spiral case pressure increments and draft tubepressure decrements This type of regulation is much severeand critical to the safety of the whole system which is

considered in this study Equation (3) can be transferredto algebraic equations by integration and Taylor expansionmethod which can be expressed as

119899119905= 1198991199050+Δ119905

119879119898

(151205731199050minus 05120573

1199050minusΔ119905) (4)

in which 119899 = the dimensionless rotating speed ratio 119873119873119903

120573 = the dimensionless torque ratio119879119879119903Δ119905 = time step and

119879119898= the mechanical starting time defined as 119879

119898= 1198681205962

119903119875119903

Equation (4) is explicit and the terms in the right-handside of the equation are known at any initial condition so therotating speed at each time step can be calculated Variationof the wicket gates (WG) opening during transients can beexpressed as

119910 = 1199100minusΔ119905

119879119888

(5)

where 119910 = the dimensionless WG opening 1199100= initial

dimensionless WG opening and 119879119888

= the closing timeconstant from full opening to closed

The equation for the head balance of turbine is

119867119879= (1198851+1199011

120574+12057211198811

2

2119892) minus (119885

2+1199012

120574+12057221198812

2

2119892) (6)

in which119867119879= head of turbine119885 = elevation of the turbine

119901 is pressure 119881 = flow velocity 120572 = the kinetic energycorrection coefficient which is generally equal to 1 120574 = unitweight of water 119892 = acceleration of gravity and the subscripts1 and 2 refer to the previous and latter section of the turbinerespectively

Positive compatibility equation of the inlet section is

1198671= 119862119875minus 119861119875119876 (7)

Negative compatibility equation of the outlet sectionis

1198672= 119862119872+ 119861119872119876 (8)

As is clear from the above equations the five parametersturbine head (119867

119879) discharge (119876) rotational speed (119873)

torque (119879) and dimensionlessWGopening (119910) are unknownFor the calculation of these unknown values at each time stepthe following procedure is used as well as the characteristiccurve of model turbine which is schematically shown inFigure 1 The computer model is encoded in the FORTRANprogramming language which has been used to simulatehydraulic transients in some practical hydropower stationsand the predictions agree well with the field test [20]

23 Boundary Conditions of Differential Surge Tankwith PROsand Overflow Weir The plan and profile of the differentialsurge tankwith overflowweir and PROs on the breast wall areshown in Figure 2119867 and119876 are the piezometric head and thedischargeThe subscripts 1 2 and 3 refer to the cross sections1 2 and 3 respectively 119885

119878119878and 119876

119878119878are the water level and

The Scientific World Journal 3

Yes

No

(y) from Eq (5)Calculate rotating speed (N) fromEq (4) with the known values of

the previous two time steps

Assume that turbine discharge (Q)is equal to the values of previoustime step (Q0)

Calculate turbine characteristics dataof the WG opening (y)

Calculate turbine head (HT)from Eqs ( 7) and (8)

Calculate unit speed n11

Calculate unit discharge Q11

by interpolation

Calculate turbine discharge (Q998400)and torque (T)

Print N y Q H and T

|Q998400minus Q| lt 10

minus4 Q = Q + 0001ΔQ|ΔQ|

Calculate WG opening

by interpolation

Figure 1 Flowchart of boundary condition for a turbine

Headrace tunnel

1

1

3

32

2

1

1

2

2

Throttle orifice

2 riser

1 riser

2 penstock

1 penstock

Main tankRiser

Overflow weir

PROsBreast wallMain tank

Q1

Q3

Q2

QSS

middotPQ1 Q2

QS1

QY

H1 H2

ZSS ZS1

QL

Figure 2 Schematic differential surge tank with PROs and overflow weir

the discharge in the main tank 119885119878119894and 119876

119878119894(119894 = the number

of the risers) are the water level and the discharge in the riser119876119884is the total discharge through the overflow weirs at the

top of the risers 119876119871is the total discharge through PROs of

the risersThemathematicmodels of the differential surge tankwith

PROs and overflow weir for transient calculation are

1198671+119876111987610

211989211986021

= 1198672+119876211987620

211989211986022

= 1198673+119876311987630

211989211986023

= 119885119904119904+ 1205851

100381610038161003816100381611987611990411990401003816100381610038161003816 119876119904119904

21198921198602TH1

= 1198851199041+ 1205852

1003816100381610038161003816119876119904101003816100381610038161003816 1198761199041

21198921198602TH2

= 1198851199042+ 1205853

1003816100381610038161003816119876119904201003816100381610038161003816 1198761199042

21198921198602TH3

1198761= 119876119904119904+ 1198761199041+ 1198761199042+ 1198762+ 1198763

1198671= 1198621198751minus 11986111987511198761

1198672= 119862119872

2+ 119861119872

21198762

4 The Scientific World Journal

Upstream reservoir

Downstream reservoir

Differential surge tank

Headrace tunnel

2 unit

1 unit

Penstock

Figure 3 Layout of the waterway and power generation system of the hydropower station

1198673= 119862119872

3+ 119861119872

31198763

d119885119904119904

d119905=119876119904119904+ 119876119884+ 119876119871

119860119904119904

d1198851199041

d119905=1198761199041minus (1198761198841+ 1198761198711)

1198601199041

d1198851199042

d119905=1198761199042minus (1198761198842+ 1198761198712)

1198601199042

(9)

where 1198601 1198602 and 119860

3are the cross-sectional areas of the

sections 1 2 and 3 respectively 119860119904119904 1198601199041 and 119860

1199042are the

cross-sectional areas of the main tank the riser 1 and theriser 2 respectively 119860TH1 119860TH2 and 119860TH3 are the cross-sectional areas of the throttle orifices at the bottom of themain tank the riser 1 and the riser 2 respectively 120585

1 1205852

and 1205853are the head loss coefficients of the throttle orifices

respectively which have different values for the flow into orout of the tank 119876

119884 1198761198841 and 119876

1198842are the discharge through

the overflow weir between the main tank and the risers119876119884= 1198761198841

+ 1198761198842 measured positively from the risers into

the main tank 119876119871 1198761198711 and 119876

1198712are the discharge through

the PROs on the breast wall 119876119871= 1198761198711

+ 1198761198712 measured

positively from the risers into themain tank Every parameterthat has a subscript 0 is a known value of a previous timestep

Discharge through the overflow weir can be given by theequation

119876119884119894=

0 119885119904119894lt 119885119884 119885119904119904lt 119885119884

11989611119861119884radic2119892(119885

119904119894minus 119885119884)15

119885119904119894ge 119885119884 119885119904119904lt 119885119884

11989612119861119884radic2119892(119885

119904119894minus 119885119904119904)15

119885119904119894ge 119885119904119904ge 119885119884

minus1198961015840

11119861119884radic2119892(119885

119904119904minus 119885119884)15

119885119904119894lt 119885119884 119885119904119904ge 119885119884

minus1198961015840

12119861119884radic2119892(119885

119904119904minus 119885119904119894)15

119885119904119904gt 119885119904119894ge 119885119884

(10)

in which 119885119884and 119861

119884are the elevation and the width of the

overflow weir respectively and 11989611and 11989612are the discharge

coefficients of free flow and submerged flow of the overflowweir respectively

Discharge through the PROs can be written as follows

119876119871119894119895

=

0 119885119904119894lt 119885119871119895 119885119904119904lt 119885119871119895

1205831119860119871119895radic2119892 (119885

119904119894minus 119885119871119895) 119885

119904119894ge 119885119871119895 119885119904119904lt 119885119871119895

1205832119860119871119895radic2119892 (119885

119904119894minus 119885119904119904) 119885

119904119894ge 119885119904119904ge 119885119871119895

minus1205831119860119871119895radic2119892 (119885

119904119904minus 119885119871119895) 119885

119904119894lt 119885119871119895 119885119904119904ge 119885119871119895

minus1205832119860119871119895radic2119892 (119885

119904119904minus 119885119904119894) 119885

119904119904gt 119885119904119894ge 119885119871119895

(11)

in which 119894 = 1-2 119860119871119895

(119895 = 1 minus 119870) are the cross-sectionalareas of the PROs and 119870 is the number of the PROs of eachriser 119885

119871119895(119895 = 1 minus 119870) are the elevations of the center of

the PROs and 1205831and 120583

2are the discharge coefficients of free

flow and submerged flow of the PROs respectively So thetotal discharge through the PROs on each breast wall may bewritten as

1198761198711=

119899

sum

119895=1

1198761198711119895 119876

1198712=

119899

sum

119895=1

1198761198712119895 (12)

Every variable of this boundary during transient processcan be derived with (9) to (12) employing the four-orderRunge-Kutta method

3 Case Study

The model is used to predict the hydraulic transients inthe practical hydropower station in China As shown inFigure 3 every two units share a common waterway systemwhich consists of the intake the gate shaft the headracetunnel the upstream differential surge tank penstock thetailrace tunnel and so on

The headrace tunnel has a length of 170 km with adiameter 119863 = 118m The differential surge tank with a ldquo119884rdquoshaped bifurcation pipe at the bottom is located at the end ofthe headrace tunnel The length of each penstock is 5300mand the diameter is 65mThe length of each tailrace tunnel is2600m and the diameter is 120mThe head loss coefficientsof the system are collected according to the project

The cross-sectional areas of the main tank and eachriser of the differential surge tank are 3464m2 and 346m2respectivelyThe cross-sectional areas of the throttle orifice atthe bottom of the main tank and each riser are 139m2 and190m2 respectively The elevation of the bottom of the maintank is 15752m while the elevation of the overflow weir atthe top of the riser is 16700m with the width 119861

119884= 60m

The Scientific World Journal 5

0

30

60

90

120

150

0 10 20 30 40 50Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless WG openingDimensionless rotating speedPressure head in spiral case

(a) Values of turbine parameters versus time

Time (s)

minus400

minus200

0

200

400

0 200 400 600 800 1000

Discharge flow in or out of main tankDischarge flow in or out of 1 riserDischarge flow in or out of 2 riserDischarge through overflow weirsDischarge through PROs

Disc

harg

e (m

3middotsminus

1)

(b) Discharge of surge tank versus time

Time (s)

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(c) Water level in surge tank versus time

Time (s)

minus20

minus10

0

10

20

30

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(d) Water level difference on breast wall versus time

Figure 4 Numerical results of simultaneous load rejection

According to the laboratory experiments the values ofthe parameters are as follows the discharge coefficient of freeoverflow from the riser into the well 119896

11= 05 The discharge

coefficient of free overflow from the main tank into the riser1198961015840

11= 053 The discharge coefficients of submerged flow 119896

12

and 119896101584012

approximate to 80 of the discharge coefficients offree overflow The head loss coefficient of the orifice at thebottom of the main tank 120585

1= 199 for the flow into the main

tank while 1205851= 132 for the flow out of the main tank The

head loss coefficients of the orifice at the bottom of the risers1205852= 1205853= 172 for the flow into the risers while 120585

2= 1205853= 323

for the flow out of the risersThe discharge coefficients of freeflow and submerged flow of the PRO 120583

1= 06 and 120583

2= 05

respectivelyThe rated output of each Francis turbine is 610MW Its

rated head is 288m rated rotating speed is 1667 rpm andrated discharge is 2286m3s The diameter of the runner

is 656m The installation elevation of turbine is 13168mThe inertia (1198661198632) of the turbine and generator is about75800 tm2

31 Simulation of Simultaneous Load Rejection Based on themathematicalmodel and numericalmethods presented in theabove section the computermodel of the hydraulic transientsin the hydropower station is encoded in the FORTRANprogramming language A critical operation that is likelyto occur several times during the life of the project issimulated The upstream water level is at EL 16460m andthe downstream water level is at EL 13331m Full load isrejected at time 119905 = 0 and the WG are closed with the closingtime 119879

119888= 13 seconds under governor control It should be

noted that the effect of the PROs is ignored in this simulationthat is the cross-section areas of the PROs are considered as0 The calculation is shown in Figure 4

6 The Scientific World Journal

The changes of the dimensionless rotating speed of therunner the dimensionless WG opening and the pressurehead in the spiral case are shown in Figure 4(a) Whenthe units reject full load the rotating speed of the runneris increased rapidly The WG are quickly closed accordingto the emergency closure law which is set to the governorin advance to prevent extended periods of high overspeedleading to serious water hammer pressure in the spiral caseThe pressure in the spiral case increases quickly during theclosing process accompanying the phenomena of the wavepropagation and reflection After the closure of theWGmostof the water hammer wave has attenuated and the pressurein the spiral case changes slowly because of the water levelvariation in the surge tank

Figures 4(b) and 4(c) show the changes of the dischargeand the water levels of the surge tank After the closure of theWG the discharge in penstock decreases rapidly The waterin the headrace tunnel flows into the surge tank through theorifices at the bottom of the main tank and the risers sothe water levels in them increase fast As the cross-sectionalarea of the riser is smaller than the main tankrsquos the waterlevel in the riser rises more quickly When the water levelin the riser reaches the elevation of the overflow weir thewater freely spills into the main tank from the riser andthe increasing speed of the water level in the riser becomesslower When the water level in the main tank reaches theelevation of the overflow weir the free flow becomes thesubmerged flow Then the discharge that flows from theriser into the main tank decreases leading to the secondquick increase of water level in the riser in a short periodof time As the discharge into the surge tank decreases theflow direction reverses and the inflow becomes the outflowThe water levels in the main tank and the risers decreaseafter reaching the highest elevation Similarly the water levelin the riser falls more rapidly because of the small cross-sectional area When the water level in the riser is lowerthan that in the main tank the water flows from the maintank to the riser and the flow pattern changes from thesubmerged flow to the free flow with the variation of thewater levels in the main tank and the riser If the water levelin the main tank is lower than the elevation of the overflowweir the overflow stops and the water level in the riser fallsrapidly The discharge through the PROs is always equal to0 during the transient because the area is set to 0 in themodel

Figure 4(d) stands for the water level difference betweenthe two sides of the riserrsquos breast wall during the transientprocess When the load rejection happens the water levelin the riser rises quickly because of the small cross-sectionalarea while the water level in the main tank increases slowlyso the corresponding pressure differencemeasured positivelyin this situation increases quickly When the water level inthe riser reaches the elevation of the overflow weir it risesslowly because of the overflow and the pressure differencereduces gradually Then the pressure difference reverses withthe decrease of thewater level in the riserUnder this transientsimulation the positive pressure difference between the twosides of the riserrsquos breast wall is about 30m while the negativeone is about 20mThepressure difference is significant so the

breast wall in this kind of surge tankmust be of good physicalstrength

As the headrace tunnel of the hydropower station is verylong the water inertia is large so the surge tank periodis very long the amplitude of the oscillations is large andthe attenuation is very slow The transient process causedby previous condition has not disappeared the followingcondition may happen which may make the result of thetransient more serious

32 Simulation of Successive Load Rejection As the layoutof water diversion systems of hydropower stations becomesmore complex as well as the operation of grid systemscombination operating conditions become very commonsuch as load rejection after load acceptance and load rejectionone by one Although the probability of some extremeconditions is very small once they happen the consequencesare very serious Therefore it is necessary to consider thesefactors in the design of hydropower stations

With respect to the water hammer pressure in combina-tion conditions successive load rejection is studied beforeThis operation condition can make the negative pressurein the draft tube more serious than that in simultaneousload rejection in a pumped storage hydropower station [21]The tailrace tunnel is short in a diversion-type hydropowerstation so the draft tube pressure will not reduce too muchduring this condition But successive load rejection mayresult in high overspeed of the runner and larger pressure inthe spiral case in a long diversion-type hydropower stationwith the bifurcated pipe at the bottom of the surge tank thatis there are two independent penstocks for the units from thesurge tank as shown in Figure 3

The calculations are shown in Figure 5 The water levelsof the reservoirs are the same as the previous section Firstlythe 1 turbine rejects its full load and when the water level ofthe surge tank reaches the highest level the 2 turbine rejectsits full load

The dimensionlessWGopening the dimensionless rotat-ing speed of the runner and the pressure head in thespiral case during successive load rejection are shown inFigure 5(a) When the 1 turbine rejects full load the waterlevel of the surge tank begins to rise As shown in Figure 5(b)when the water level of the surge tank reaches the highestlevel it rises about 30m whichmakes the static head of the 2turbine increase by 30m Otherwise the units connect withlarge power grid under normal conditions and the speed ofthe 2 turbinewill not change due to the stable grid frequencyso the opening of theWG keeps constant as well As the statichead of the 2 turbine rises the demand discharge of turbinealso increases When the water level of the surge tank reachesthe highest level after the load rejection of the 1 turbinethe 2 turbine rejects full load Compared with simultaneousload rejection the maximum pressure in the spiral case andthe maximum rotating speed of the 2 turbine are increasedwhich are shown in Table 1Therefore if the water way systemof a hydropower station is arranged as this form especiallyas the headrace tunnel is very long successive load rejectioncondition will make the maximum pressure of the spiral caseand themaximum rotating speed of the runner more serious

The Scientific World Journal 7

0

30

60

90

120

150

0 40 80 120 160 200Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless 1 WG openingDimensionless 2 WG openingDimensionless 1 rotating speedDimensionless 2 rotating speedPressure head in 1 spiral casePressure head in 2 spiral case

(a) Values of turbine parameters versus time

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(b) Water level in surge tank versus time

Figure 5 Numerical results of successive load rejection

Table 1 Comparisons between simultaneous and successive loadrejection

Operation conditionsMaximum

pressure of spiralcase

Maximumrotating speed rise

Simultaneous load rejection 3677m 432Successive load rejection 4021m 499

33 Simulation of Simultaneous Load Rejection after LoadAcceptance Because of the small cross-sectional area thewater level in the riser rises or falls rapidly during transientprocess which creates an accelerating or decelerating headon the tunnel in a short period of time This effect reducesthe amplitude of water level oscillations in the surge tank andaccelerates the attenuation However due to rapid water levelvariations in the risers and slow variations in the main tankthe pressure difference between the two sides of the riserrsquosbreast wall is significant If the structure cannot bear thispressure difference it may cause collapse of the breast wall[22] Thus it is very important to find the critical operationconditions and to simulate the possible maximum pressuredifference on the breast wall in the design stage which arethe basis for the structure calculation of the breast wall

Simultaneous load rejection after load acceptance iscommon in the operation of hydropower stations Duringthis simulation the water levels of the reservoirs are thesame as the previous section As shown in Figure 6(a) twounits accept load one by one which results in the fall of thewater levels in the surge tank When the water levels of thesurge tank reach the lowest level two units reject full loadsimultaneously The water levels in the risers rise rapidly tothe elevation of the overflow weirs while the water level inthemain tank rises slowly and the elevation of the initial water

Table 2 Maximum pressure difference on breast wall underdifferent conditions

Operation conditions Maximum pressure difference onbreast wall

Simultaneous load rejection 292mCombination conditionswithout PROs 509m

Combination conditions withPROs 319m

level is lower compared with the simultaneous load rejectioncase So the pressure difference on the breast wall is largerduring this combination operating condition As shown inFigure 6(b) the maximum pressure difference on the breastwall increases by 20m compared with simultaneous loadrejection

34 Control of the Pressure Difference on Breast Wall As itcan be seen from Table 2 the maximum pressure differencebetween two sides of the breast wall is close to 30m in simul-taneous load rejection while the difference can reach 50m incombination conditionsThis huge pressure difference bringsgreat challenge to the structural safety of the breast wall thushow to reduce the pressure difference between two sides of thebreast wall has become an issue to the design person

Guaranteeing adequate structural strength of the breastwall a row of the PROs can be set along height direction[23] When transient process occurs a large water leveldifference is created between the risers and the main tankin a differential surge tank The water level in the riser risesrapidly reaching the PROs then the water flows from theriser into the main tank through the orifices which slowingdown thewater level rise in the riser while speeding thewater

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 2: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

2 The Scientific World Journal

2 Mathematic Model and Calculation Method

21 Governing Equations and Solution Methods for Pres-surized Pipe Model The following equations describe one-dimensional transient flows [18]

Continuity equation

120597119867

120597119905+ 119881

120597119867

120597119909+1198862

119892

120597119881

120597119909+ 119881 sin 120579 = 0 (1)

Momentum equation

120597119867

120597119909+119881

119892

120597119881

120597119909+1

119892

120597119881

120597119905+119891 |119881|119881

2119892119863= 0 (2)

in which 119867 = piezometric head 119881 = flow velocity 119886 =

wave speed 119892 = acceleration due to gravity 119891 = Darcy-Weisbach friction factor 120579 = angle of the pipeline inclinedwith the horizontal119909 = distance along the pipelinemeasuredpositively in the downstream direction 119863 = diameter of thepipe and 119905 = time

The momentum and continuity equations governingtransient flow in closed conduits are classified as quasilinearhyperbolic partial differential equations (PDEs) for which noanalytical solutions are available for a general pipe systemThe method of characteristics (MOC) is widely employedto solve the set of PDEs and these two equations can betransformed into a couple of ordinary differential equations(ODEs) along the characteristic lines The friction item islinearized by using the trapezoidal rule which is of second-order accuracy and some small terms are dropped withoutloss in accuracy It is convenient to develop these equationswith the discharge 119876 instead of flow velocity 119881 as thedependent variable Then the equations can be transformedinto two algebraic equations for computer calculation afterintegration along the characteristic linesThe grid of pipelinesand the time interval follow Courant condition Δ119905 le Δ119909119886

22 Turbine Equations The equation for the acceleration ofthe rotating masses is [19]

119868119889120596

119889119905= 119879 minus 119879

119892 (3)

in which 119868 = the polar moment of inertia of rotating fluid andmechanical parts in the turbine-generator combination (119868 =1198821198772119892 where119882 = weight 119877 = radius of gyration) 120596 = the

angular speed of the unit 119879 = the torque produced by waterflowing through the unit and 119879

119892= the resistant torque from

the generatorWhen load rejection occurs the unit is instantly discon-

nected from the system and thus becomes isolated (ie119879119892=

0) Then the unit has to be quickly closed according to theemergency closure lawwhich is set to the governor in advanceto prevent extended periods of high overspeed which mayinduce severe spiral case pressure increments and draft tubepressure decrements This type of regulation is much severeand critical to the safety of the whole system which is

considered in this study Equation (3) can be transferredto algebraic equations by integration and Taylor expansionmethod which can be expressed as

119899119905= 1198991199050+Δ119905

119879119898

(151205731199050minus 05120573

1199050minusΔ119905) (4)

in which 119899 = the dimensionless rotating speed ratio 119873119873119903

120573 = the dimensionless torque ratio119879119879119903Δ119905 = time step and

119879119898= the mechanical starting time defined as 119879

119898= 1198681205962

119903119875119903

Equation (4) is explicit and the terms in the right-handside of the equation are known at any initial condition so therotating speed at each time step can be calculated Variationof the wicket gates (WG) opening during transients can beexpressed as

119910 = 1199100minusΔ119905

119879119888

(5)

where 119910 = the dimensionless WG opening 1199100= initial

dimensionless WG opening and 119879119888

= the closing timeconstant from full opening to closed

The equation for the head balance of turbine is

119867119879= (1198851+1199011

120574+12057211198811

2

2119892) minus (119885

2+1199012

120574+12057221198812

2

2119892) (6)

in which119867119879= head of turbine119885 = elevation of the turbine

119901 is pressure 119881 = flow velocity 120572 = the kinetic energycorrection coefficient which is generally equal to 1 120574 = unitweight of water 119892 = acceleration of gravity and the subscripts1 and 2 refer to the previous and latter section of the turbinerespectively

Positive compatibility equation of the inlet section is

1198671= 119862119875minus 119861119875119876 (7)

Negative compatibility equation of the outlet sectionis

1198672= 119862119872+ 119861119872119876 (8)

As is clear from the above equations the five parametersturbine head (119867

119879) discharge (119876) rotational speed (119873)

torque (119879) and dimensionlessWGopening (119910) are unknownFor the calculation of these unknown values at each time stepthe following procedure is used as well as the characteristiccurve of model turbine which is schematically shown inFigure 1 The computer model is encoded in the FORTRANprogramming language which has been used to simulatehydraulic transients in some practical hydropower stationsand the predictions agree well with the field test [20]

23 Boundary Conditions of Differential Surge Tankwith PROsand Overflow Weir The plan and profile of the differentialsurge tankwith overflowweir and PROs on the breast wall areshown in Figure 2119867 and119876 are the piezometric head and thedischargeThe subscripts 1 2 and 3 refer to the cross sections1 2 and 3 respectively 119885

119878119878and 119876

119878119878are the water level and

The Scientific World Journal 3

Yes

No

(y) from Eq (5)Calculate rotating speed (N) fromEq (4) with the known values of

the previous two time steps

Assume that turbine discharge (Q)is equal to the values of previoustime step (Q0)

Calculate turbine characteristics dataof the WG opening (y)

Calculate turbine head (HT)from Eqs ( 7) and (8)

Calculate unit speed n11

Calculate unit discharge Q11

by interpolation

Calculate turbine discharge (Q998400)and torque (T)

Print N y Q H and T

|Q998400minus Q| lt 10

minus4 Q = Q + 0001ΔQ|ΔQ|

Calculate WG opening

by interpolation

Figure 1 Flowchart of boundary condition for a turbine

Headrace tunnel

1

1

3

32

2

1

1

2

2

Throttle orifice

2 riser

1 riser

2 penstock

1 penstock

Main tankRiser

Overflow weir

PROsBreast wallMain tank

Q1

Q3

Q2

QSS

middotPQ1 Q2

QS1

QY

H1 H2

ZSS ZS1

QL

Figure 2 Schematic differential surge tank with PROs and overflow weir

the discharge in the main tank 119885119878119894and 119876

119878119894(119894 = the number

of the risers) are the water level and the discharge in the riser119876119884is the total discharge through the overflow weirs at the

top of the risers 119876119871is the total discharge through PROs of

the risersThemathematicmodels of the differential surge tankwith

PROs and overflow weir for transient calculation are

1198671+119876111987610

211989211986021

= 1198672+119876211987620

211989211986022

= 1198673+119876311987630

211989211986023

= 119885119904119904+ 1205851

100381610038161003816100381611987611990411990401003816100381610038161003816 119876119904119904

21198921198602TH1

= 1198851199041+ 1205852

1003816100381610038161003816119876119904101003816100381610038161003816 1198761199041

21198921198602TH2

= 1198851199042+ 1205853

1003816100381610038161003816119876119904201003816100381610038161003816 1198761199042

21198921198602TH3

1198761= 119876119904119904+ 1198761199041+ 1198761199042+ 1198762+ 1198763

1198671= 1198621198751minus 11986111987511198761

1198672= 119862119872

2+ 119861119872

21198762

4 The Scientific World Journal

Upstream reservoir

Downstream reservoir

Differential surge tank

Headrace tunnel

2 unit

1 unit

Penstock

Figure 3 Layout of the waterway and power generation system of the hydropower station

1198673= 119862119872

3+ 119861119872

31198763

d119885119904119904

d119905=119876119904119904+ 119876119884+ 119876119871

119860119904119904

d1198851199041

d119905=1198761199041minus (1198761198841+ 1198761198711)

1198601199041

d1198851199042

d119905=1198761199042minus (1198761198842+ 1198761198712)

1198601199042

(9)

where 1198601 1198602 and 119860

3are the cross-sectional areas of the

sections 1 2 and 3 respectively 119860119904119904 1198601199041 and 119860

1199042are the

cross-sectional areas of the main tank the riser 1 and theriser 2 respectively 119860TH1 119860TH2 and 119860TH3 are the cross-sectional areas of the throttle orifices at the bottom of themain tank the riser 1 and the riser 2 respectively 120585

1 1205852

and 1205853are the head loss coefficients of the throttle orifices

respectively which have different values for the flow into orout of the tank 119876

119884 1198761198841 and 119876

1198842are the discharge through

the overflow weir between the main tank and the risers119876119884= 1198761198841

+ 1198761198842 measured positively from the risers into

the main tank 119876119871 1198761198711 and 119876

1198712are the discharge through

the PROs on the breast wall 119876119871= 1198761198711

+ 1198761198712 measured

positively from the risers into themain tank Every parameterthat has a subscript 0 is a known value of a previous timestep

Discharge through the overflow weir can be given by theequation

119876119884119894=

0 119885119904119894lt 119885119884 119885119904119904lt 119885119884

11989611119861119884radic2119892(119885

119904119894minus 119885119884)15

119885119904119894ge 119885119884 119885119904119904lt 119885119884

11989612119861119884radic2119892(119885

119904119894minus 119885119904119904)15

119885119904119894ge 119885119904119904ge 119885119884

minus1198961015840

11119861119884radic2119892(119885

119904119904minus 119885119884)15

119885119904119894lt 119885119884 119885119904119904ge 119885119884

minus1198961015840

12119861119884radic2119892(119885

119904119904minus 119885119904119894)15

119885119904119904gt 119885119904119894ge 119885119884

(10)

in which 119885119884and 119861

119884are the elevation and the width of the

overflow weir respectively and 11989611and 11989612are the discharge

coefficients of free flow and submerged flow of the overflowweir respectively

Discharge through the PROs can be written as follows

119876119871119894119895

=

0 119885119904119894lt 119885119871119895 119885119904119904lt 119885119871119895

1205831119860119871119895radic2119892 (119885

119904119894minus 119885119871119895) 119885

119904119894ge 119885119871119895 119885119904119904lt 119885119871119895

1205832119860119871119895radic2119892 (119885

119904119894minus 119885119904119904) 119885

119904119894ge 119885119904119904ge 119885119871119895

minus1205831119860119871119895radic2119892 (119885

119904119904minus 119885119871119895) 119885

119904119894lt 119885119871119895 119885119904119904ge 119885119871119895

minus1205832119860119871119895radic2119892 (119885

119904119904minus 119885119904119894) 119885

119904119904gt 119885119904119894ge 119885119871119895

(11)

in which 119894 = 1-2 119860119871119895

(119895 = 1 minus 119870) are the cross-sectionalareas of the PROs and 119870 is the number of the PROs of eachriser 119885

119871119895(119895 = 1 minus 119870) are the elevations of the center of

the PROs and 1205831and 120583

2are the discharge coefficients of free

flow and submerged flow of the PROs respectively So thetotal discharge through the PROs on each breast wall may bewritten as

1198761198711=

119899

sum

119895=1

1198761198711119895 119876

1198712=

119899

sum

119895=1

1198761198712119895 (12)

Every variable of this boundary during transient processcan be derived with (9) to (12) employing the four-orderRunge-Kutta method

3 Case Study

The model is used to predict the hydraulic transients inthe practical hydropower station in China As shown inFigure 3 every two units share a common waterway systemwhich consists of the intake the gate shaft the headracetunnel the upstream differential surge tank penstock thetailrace tunnel and so on

The headrace tunnel has a length of 170 km with adiameter 119863 = 118m The differential surge tank with a ldquo119884rdquoshaped bifurcation pipe at the bottom is located at the end ofthe headrace tunnel The length of each penstock is 5300mand the diameter is 65mThe length of each tailrace tunnel is2600m and the diameter is 120mThe head loss coefficientsof the system are collected according to the project

The cross-sectional areas of the main tank and eachriser of the differential surge tank are 3464m2 and 346m2respectivelyThe cross-sectional areas of the throttle orifice atthe bottom of the main tank and each riser are 139m2 and190m2 respectively The elevation of the bottom of the maintank is 15752m while the elevation of the overflow weir atthe top of the riser is 16700m with the width 119861

119884= 60m

The Scientific World Journal 5

0

30

60

90

120

150

0 10 20 30 40 50Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless WG openingDimensionless rotating speedPressure head in spiral case

(a) Values of turbine parameters versus time

Time (s)

minus400

minus200

0

200

400

0 200 400 600 800 1000

Discharge flow in or out of main tankDischarge flow in or out of 1 riserDischarge flow in or out of 2 riserDischarge through overflow weirsDischarge through PROs

Disc

harg

e (m

3middotsminus

1)

(b) Discharge of surge tank versus time

Time (s)

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(c) Water level in surge tank versus time

Time (s)

minus20

minus10

0

10

20

30

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(d) Water level difference on breast wall versus time

Figure 4 Numerical results of simultaneous load rejection

According to the laboratory experiments the values ofthe parameters are as follows the discharge coefficient of freeoverflow from the riser into the well 119896

11= 05 The discharge

coefficient of free overflow from the main tank into the riser1198961015840

11= 053 The discharge coefficients of submerged flow 119896

12

and 119896101584012

approximate to 80 of the discharge coefficients offree overflow The head loss coefficient of the orifice at thebottom of the main tank 120585

1= 199 for the flow into the main

tank while 1205851= 132 for the flow out of the main tank The

head loss coefficients of the orifice at the bottom of the risers1205852= 1205853= 172 for the flow into the risers while 120585

2= 1205853= 323

for the flow out of the risersThe discharge coefficients of freeflow and submerged flow of the PRO 120583

1= 06 and 120583

2= 05

respectivelyThe rated output of each Francis turbine is 610MW Its

rated head is 288m rated rotating speed is 1667 rpm andrated discharge is 2286m3s The diameter of the runner

is 656m The installation elevation of turbine is 13168mThe inertia (1198661198632) of the turbine and generator is about75800 tm2

31 Simulation of Simultaneous Load Rejection Based on themathematicalmodel and numericalmethods presented in theabove section the computermodel of the hydraulic transientsin the hydropower station is encoded in the FORTRANprogramming language A critical operation that is likelyto occur several times during the life of the project issimulated The upstream water level is at EL 16460m andthe downstream water level is at EL 13331m Full load isrejected at time 119905 = 0 and the WG are closed with the closingtime 119879

119888= 13 seconds under governor control It should be

noted that the effect of the PROs is ignored in this simulationthat is the cross-section areas of the PROs are considered as0 The calculation is shown in Figure 4

6 The Scientific World Journal

The changes of the dimensionless rotating speed of therunner the dimensionless WG opening and the pressurehead in the spiral case are shown in Figure 4(a) Whenthe units reject full load the rotating speed of the runneris increased rapidly The WG are quickly closed accordingto the emergency closure law which is set to the governorin advance to prevent extended periods of high overspeedleading to serious water hammer pressure in the spiral caseThe pressure in the spiral case increases quickly during theclosing process accompanying the phenomena of the wavepropagation and reflection After the closure of theWGmostof the water hammer wave has attenuated and the pressurein the spiral case changes slowly because of the water levelvariation in the surge tank

Figures 4(b) and 4(c) show the changes of the dischargeand the water levels of the surge tank After the closure of theWG the discharge in penstock decreases rapidly The waterin the headrace tunnel flows into the surge tank through theorifices at the bottom of the main tank and the risers sothe water levels in them increase fast As the cross-sectionalarea of the riser is smaller than the main tankrsquos the waterlevel in the riser rises more quickly When the water levelin the riser reaches the elevation of the overflow weir thewater freely spills into the main tank from the riser andthe increasing speed of the water level in the riser becomesslower When the water level in the main tank reaches theelevation of the overflow weir the free flow becomes thesubmerged flow Then the discharge that flows from theriser into the main tank decreases leading to the secondquick increase of water level in the riser in a short periodof time As the discharge into the surge tank decreases theflow direction reverses and the inflow becomes the outflowThe water levels in the main tank and the risers decreaseafter reaching the highest elevation Similarly the water levelin the riser falls more rapidly because of the small cross-sectional area When the water level in the riser is lowerthan that in the main tank the water flows from the maintank to the riser and the flow pattern changes from thesubmerged flow to the free flow with the variation of thewater levels in the main tank and the riser If the water levelin the main tank is lower than the elevation of the overflowweir the overflow stops and the water level in the riser fallsrapidly The discharge through the PROs is always equal to0 during the transient because the area is set to 0 in themodel

Figure 4(d) stands for the water level difference betweenthe two sides of the riserrsquos breast wall during the transientprocess When the load rejection happens the water levelin the riser rises quickly because of the small cross-sectionalarea while the water level in the main tank increases slowlyso the corresponding pressure differencemeasured positivelyin this situation increases quickly When the water level inthe riser reaches the elevation of the overflow weir it risesslowly because of the overflow and the pressure differencereduces gradually Then the pressure difference reverses withthe decrease of thewater level in the riserUnder this transientsimulation the positive pressure difference between the twosides of the riserrsquos breast wall is about 30m while the negativeone is about 20mThepressure difference is significant so the

breast wall in this kind of surge tankmust be of good physicalstrength

As the headrace tunnel of the hydropower station is verylong the water inertia is large so the surge tank periodis very long the amplitude of the oscillations is large andthe attenuation is very slow The transient process causedby previous condition has not disappeared the followingcondition may happen which may make the result of thetransient more serious

32 Simulation of Successive Load Rejection As the layoutof water diversion systems of hydropower stations becomesmore complex as well as the operation of grid systemscombination operating conditions become very commonsuch as load rejection after load acceptance and load rejectionone by one Although the probability of some extremeconditions is very small once they happen the consequencesare very serious Therefore it is necessary to consider thesefactors in the design of hydropower stations

With respect to the water hammer pressure in combina-tion conditions successive load rejection is studied beforeThis operation condition can make the negative pressurein the draft tube more serious than that in simultaneousload rejection in a pumped storage hydropower station [21]The tailrace tunnel is short in a diversion-type hydropowerstation so the draft tube pressure will not reduce too muchduring this condition But successive load rejection mayresult in high overspeed of the runner and larger pressure inthe spiral case in a long diversion-type hydropower stationwith the bifurcated pipe at the bottom of the surge tank thatis there are two independent penstocks for the units from thesurge tank as shown in Figure 3

The calculations are shown in Figure 5 The water levelsof the reservoirs are the same as the previous section Firstlythe 1 turbine rejects its full load and when the water level ofthe surge tank reaches the highest level the 2 turbine rejectsits full load

The dimensionlessWGopening the dimensionless rotat-ing speed of the runner and the pressure head in thespiral case during successive load rejection are shown inFigure 5(a) When the 1 turbine rejects full load the waterlevel of the surge tank begins to rise As shown in Figure 5(b)when the water level of the surge tank reaches the highestlevel it rises about 30m whichmakes the static head of the 2turbine increase by 30m Otherwise the units connect withlarge power grid under normal conditions and the speed ofthe 2 turbinewill not change due to the stable grid frequencyso the opening of theWG keeps constant as well As the statichead of the 2 turbine rises the demand discharge of turbinealso increases When the water level of the surge tank reachesthe highest level after the load rejection of the 1 turbinethe 2 turbine rejects full load Compared with simultaneousload rejection the maximum pressure in the spiral case andthe maximum rotating speed of the 2 turbine are increasedwhich are shown in Table 1Therefore if the water way systemof a hydropower station is arranged as this form especiallyas the headrace tunnel is very long successive load rejectioncondition will make the maximum pressure of the spiral caseand themaximum rotating speed of the runner more serious

The Scientific World Journal 7

0

30

60

90

120

150

0 40 80 120 160 200Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless 1 WG openingDimensionless 2 WG openingDimensionless 1 rotating speedDimensionless 2 rotating speedPressure head in 1 spiral casePressure head in 2 spiral case

(a) Values of turbine parameters versus time

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(b) Water level in surge tank versus time

Figure 5 Numerical results of successive load rejection

Table 1 Comparisons between simultaneous and successive loadrejection

Operation conditionsMaximum

pressure of spiralcase

Maximumrotating speed rise

Simultaneous load rejection 3677m 432Successive load rejection 4021m 499

33 Simulation of Simultaneous Load Rejection after LoadAcceptance Because of the small cross-sectional area thewater level in the riser rises or falls rapidly during transientprocess which creates an accelerating or decelerating headon the tunnel in a short period of time This effect reducesthe amplitude of water level oscillations in the surge tank andaccelerates the attenuation However due to rapid water levelvariations in the risers and slow variations in the main tankthe pressure difference between the two sides of the riserrsquosbreast wall is significant If the structure cannot bear thispressure difference it may cause collapse of the breast wall[22] Thus it is very important to find the critical operationconditions and to simulate the possible maximum pressuredifference on the breast wall in the design stage which arethe basis for the structure calculation of the breast wall

Simultaneous load rejection after load acceptance iscommon in the operation of hydropower stations Duringthis simulation the water levels of the reservoirs are thesame as the previous section As shown in Figure 6(a) twounits accept load one by one which results in the fall of thewater levels in the surge tank When the water levels of thesurge tank reach the lowest level two units reject full loadsimultaneously The water levels in the risers rise rapidly tothe elevation of the overflow weirs while the water level inthemain tank rises slowly and the elevation of the initial water

Table 2 Maximum pressure difference on breast wall underdifferent conditions

Operation conditions Maximum pressure difference onbreast wall

Simultaneous load rejection 292mCombination conditionswithout PROs 509m

Combination conditions withPROs 319m

level is lower compared with the simultaneous load rejectioncase So the pressure difference on the breast wall is largerduring this combination operating condition As shown inFigure 6(b) the maximum pressure difference on the breastwall increases by 20m compared with simultaneous loadrejection

34 Control of the Pressure Difference on Breast Wall As itcan be seen from Table 2 the maximum pressure differencebetween two sides of the breast wall is close to 30m in simul-taneous load rejection while the difference can reach 50m incombination conditionsThis huge pressure difference bringsgreat challenge to the structural safety of the breast wall thushow to reduce the pressure difference between two sides of thebreast wall has become an issue to the design person

Guaranteeing adequate structural strength of the breastwall a row of the PROs can be set along height direction[23] When transient process occurs a large water leveldifference is created between the risers and the main tankin a differential surge tank The water level in the riser risesrapidly reaching the PROs then the water flows from theriser into the main tank through the orifices which slowingdown thewater level rise in the riser while speeding thewater

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 3: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

The Scientific World Journal 3

Yes

No

(y) from Eq (5)Calculate rotating speed (N) fromEq (4) with the known values of

the previous two time steps

Assume that turbine discharge (Q)is equal to the values of previoustime step (Q0)

Calculate turbine characteristics dataof the WG opening (y)

Calculate turbine head (HT)from Eqs ( 7) and (8)

Calculate unit speed n11

Calculate unit discharge Q11

by interpolation

Calculate turbine discharge (Q998400)and torque (T)

Print N y Q H and T

|Q998400minus Q| lt 10

minus4 Q = Q + 0001ΔQ|ΔQ|

Calculate WG opening

by interpolation

Figure 1 Flowchart of boundary condition for a turbine

Headrace tunnel

1

1

3

32

2

1

1

2

2

Throttle orifice

2 riser

1 riser

2 penstock

1 penstock

Main tankRiser

Overflow weir

PROsBreast wallMain tank

Q1

Q3

Q2

QSS

middotPQ1 Q2

QS1

QY

H1 H2

ZSS ZS1

QL

Figure 2 Schematic differential surge tank with PROs and overflow weir

the discharge in the main tank 119885119878119894and 119876

119878119894(119894 = the number

of the risers) are the water level and the discharge in the riser119876119884is the total discharge through the overflow weirs at the

top of the risers 119876119871is the total discharge through PROs of

the risersThemathematicmodels of the differential surge tankwith

PROs and overflow weir for transient calculation are

1198671+119876111987610

211989211986021

= 1198672+119876211987620

211989211986022

= 1198673+119876311987630

211989211986023

= 119885119904119904+ 1205851

100381610038161003816100381611987611990411990401003816100381610038161003816 119876119904119904

21198921198602TH1

= 1198851199041+ 1205852

1003816100381610038161003816119876119904101003816100381610038161003816 1198761199041

21198921198602TH2

= 1198851199042+ 1205853

1003816100381610038161003816119876119904201003816100381610038161003816 1198761199042

21198921198602TH3

1198761= 119876119904119904+ 1198761199041+ 1198761199042+ 1198762+ 1198763

1198671= 1198621198751minus 11986111987511198761

1198672= 119862119872

2+ 119861119872

21198762

4 The Scientific World Journal

Upstream reservoir

Downstream reservoir

Differential surge tank

Headrace tunnel

2 unit

1 unit

Penstock

Figure 3 Layout of the waterway and power generation system of the hydropower station

1198673= 119862119872

3+ 119861119872

31198763

d119885119904119904

d119905=119876119904119904+ 119876119884+ 119876119871

119860119904119904

d1198851199041

d119905=1198761199041minus (1198761198841+ 1198761198711)

1198601199041

d1198851199042

d119905=1198761199042minus (1198761198842+ 1198761198712)

1198601199042

(9)

where 1198601 1198602 and 119860

3are the cross-sectional areas of the

sections 1 2 and 3 respectively 119860119904119904 1198601199041 and 119860

1199042are the

cross-sectional areas of the main tank the riser 1 and theriser 2 respectively 119860TH1 119860TH2 and 119860TH3 are the cross-sectional areas of the throttle orifices at the bottom of themain tank the riser 1 and the riser 2 respectively 120585

1 1205852

and 1205853are the head loss coefficients of the throttle orifices

respectively which have different values for the flow into orout of the tank 119876

119884 1198761198841 and 119876

1198842are the discharge through

the overflow weir between the main tank and the risers119876119884= 1198761198841

+ 1198761198842 measured positively from the risers into

the main tank 119876119871 1198761198711 and 119876

1198712are the discharge through

the PROs on the breast wall 119876119871= 1198761198711

+ 1198761198712 measured

positively from the risers into themain tank Every parameterthat has a subscript 0 is a known value of a previous timestep

Discharge through the overflow weir can be given by theequation

119876119884119894=

0 119885119904119894lt 119885119884 119885119904119904lt 119885119884

11989611119861119884radic2119892(119885

119904119894minus 119885119884)15

119885119904119894ge 119885119884 119885119904119904lt 119885119884

11989612119861119884radic2119892(119885

119904119894minus 119885119904119904)15

119885119904119894ge 119885119904119904ge 119885119884

minus1198961015840

11119861119884radic2119892(119885

119904119904minus 119885119884)15

119885119904119894lt 119885119884 119885119904119904ge 119885119884

minus1198961015840

12119861119884radic2119892(119885

119904119904minus 119885119904119894)15

119885119904119904gt 119885119904119894ge 119885119884

(10)

in which 119885119884and 119861

119884are the elevation and the width of the

overflow weir respectively and 11989611and 11989612are the discharge

coefficients of free flow and submerged flow of the overflowweir respectively

Discharge through the PROs can be written as follows

119876119871119894119895

=

0 119885119904119894lt 119885119871119895 119885119904119904lt 119885119871119895

1205831119860119871119895radic2119892 (119885

119904119894minus 119885119871119895) 119885

119904119894ge 119885119871119895 119885119904119904lt 119885119871119895

1205832119860119871119895radic2119892 (119885

119904119894minus 119885119904119904) 119885

119904119894ge 119885119904119904ge 119885119871119895

minus1205831119860119871119895radic2119892 (119885

119904119904minus 119885119871119895) 119885

119904119894lt 119885119871119895 119885119904119904ge 119885119871119895

minus1205832119860119871119895radic2119892 (119885

119904119904minus 119885119904119894) 119885

119904119904gt 119885119904119894ge 119885119871119895

(11)

in which 119894 = 1-2 119860119871119895

(119895 = 1 minus 119870) are the cross-sectionalareas of the PROs and 119870 is the number of the PROs of eachriser 119885

119871119895(119895 = 1 minus 119870) are the elevations of the center of

the PROs and 1205831and 120583

2are the discharge coefficients of free

flow and submerged flow of the PROs respectively So thetotal discharge through the PROs on each breast wall may bewritten as

1198761198711=

119899

sum

119895=1

1198761198711119895 119876

1198712=

119899

sum

119895=1

1198761198712119895 (12)

Every variable of this boundary during transient processcan be derived with (9) to (12) employing the four-orderRunge-Kutta method

3 Case Study

The model is used to predict the hydraulic transients inthe practical hydropower station in China As shown inFigure 3 every two units share a common waterway systemwhich consists of the intake the gate shaft the headracetunnel the upstream differential surge tank penstock thetailrace tunnel and so on

The headrace tunnel has a length of 170 km with adiameter 119863 = 118m The differential surge tank with a ldquo119884rdquoshaped bifurcation pipe at the bottom is located at the end ofthe headrace tunnel The length of each penstock is 5300mand the diameter is 65mThe length of each tailrace tunnel is2600m and the diameter is 120mThe head loss coefficientsof the system are collected according to the project

The cross-sectional areas of the main tank and eachriser of the differential surge tank are 3464m2 and 346m2respectivelyThe cross-sectional areas of the throttle orifice atthe bottom of the main tank and each riser are 139m2 and190m2 respectively The elevation of the bottom of the maintank is 15752m while the elevation of the overflow weir atthe top of the riser is 16700m with the width 119861

119884= 60m

The Scientific World Journal 5

0

30

60

90

120

150

0 10 20 30 40 50Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless WG openingDimensionless rotating speedPressure head in spiral case

(a) Values of turbine parameters versus time

Time (s)

minus400

minus200

0

200

400

0 200 400 600 800 1000

Discharge flow in or out of main tankDischarge flow in or out of 1 riserDischarge flow in or out of 2 riserDischarge through overflow weirsDischarge through PROs

Disc

harg

e (m

3middotsminus

1)

(b) Discharge of surge tank versus time

Time (s)

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(c) Water level in surge tank versus time

Time (s)

minus20

minus10

0

10

20

30

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(d) Water level difference on breast wall versus time

Figure 4 Numerical results of simultaneous load rejection

According to the laboratory experiments the values ofthe parameters are as follows the discharge coefficient of freeoverflow from the riser into the well 119896

11= 05 The discharge

coefficient of free overflow from the main tank into the riser1198961015840

11= 053 The discharge coefficients of submerged flow 119896

12

and 119896101584012

approximate to 80 of the discharge coefficients offree overflow The head loss coefficient of the orifice at thebottom of the main tank 120585

1= 199 for the flow into the main

tank while 1205851= 132 for the flow out of the main tank The

head loss coefficients of the orifice at the bottom of the risers1205852= 1205853= 172 for the flow into the risers while 120585

2= 1205853= 323

for the flow out of the risersThe discharge coefficients of freeflow and submerged flow of the PRO 120583

1= 06 and 120583

2= 05

respectivelyThe rated output of each Francis turbine is 610MW Its

rated head is 288m rated rotating speed is 1667 rpm andrated discharge is 2286m3s The diameter of the runner

is 656m The installation elevation of turbine is 13168mThe inertia (1198661198632) of the turbine and generator is about75800 tm2

31 Simulation of Simultaneous Load Rejection Based on themathematicalmodel and numericalmethods presented in theabove section the computermodel of the hydraulic transientsin the hydropower station is encoded in the FORTRANprogramming language A critical operation that is likelyto occur several times during the life of the project issimulated The upstream water level is at EL 16460m andthe downstream water level is at EL 13331m Full load isrejected at time 119905 = 0 and the WG are closed with the closingtime 119879

119888= 13 seconds under governor control It should be

noted that the effect of the PROs is ignored in this simulationthat is the cross-section areas of the PROs are considered as0 The calculation is shown in Figure 4

6 The Scientific World Journal

The changes of the dimensionless rotating speed of therunner the dimensionless WG opening and the pressurehead in the spiral case are shown in Figure 4(a) Whenthe units reject full load the rotating speed of the runneris increased rapidly The WG are quickly closed accordingto the emergency closure law which is set to the governorin advance to prevent extended periods of high overspeedleading to serious water hammer pressure in the spiral caseThe pressure in the spiral case increases quickly during theclosing process accompanying the phenomena of the wavepropagation and reflection After the closure of theWGmostof the water hammer wave has attenuated and the pressurein the spiral case changes slowly because of the water levelvariation in the surge tank

Figures 4(b) and 4(c) show the changes of the dischargeand the water levels of the surge tank After the closure of theWG the discharge in penstock decreases rapidly The waterin the headrace tunnel flows into the surge tank through theorifices at the bottom of the main tank and the risers sothe water levels in them increase fast As the cross-sectionalarea of the riser is smaller than the main tankrsquos the waterlevel in the riser rises more quickly When the water levelin the riser reaches the elevation of the overflow weir thewater freely spills into the main tank from the riser andthe increasing speed of the water level in the riser becomesslower When the water level in the main tank reaches theelevation of the overflow weir the free flow becomes thesubmerged flow Then the discharge that flows from theriser into the main tank decreases leading to the secondquick increase of water level in the riser in a short periodof time As the discharge into the surge tank decreases theflow direction reverses and the inflow becomes the outflowThe water levels in the main tank and the risers decreaseafter reaching the highest elevation Similarly the water levelin the riser falls more rapidly because of the small cross-sectional area When the water level in the riser is lowerthan that in the main tank the water flows from the maintank to the riser and the flow pattern changes from thesubmerged flow to the free flow with the variation of thewater levels in the main tank and the riser If the water levelin the main tank is lower than the elevation of the overflowweir the overflow stops and the water level in the riser fallsrapidly The discharge through the PROs is always equal to0 during the transient because the area is set to 0 in themodel

Figure 4(d) stands for the water level difference betweenthe two sides of the riserrsquos breast wall during the transientprocess When the load rejection happens the water levelin the riser rises quickly because of the small cross-sectionalarea while the water level in the main tank increases slowlyso the corresponding pressure differencemeasured positivelyin this situation increases quickly When the water level inthe riser reaches the elevation of the overflow weir it risesslowly because of the overflow and the pressure differencereduces gradually Then the pressure difference reverses withthe decrease of thewater level in the riserUnder this transientsimulation the positive pressure difference between the twosides of the riserrsquos breast wall is about 30m while the negativeone is about 20mThepressure difference is significant so the

breast wall in this kind of surge tankmust be of good physicalstrength

As the headrace tunnel of the hydropower station is verylong the water inertia is large so the surge tank periodis very long the amplitude of the oscillations is large andthe attenuation is very slow The transient process causedby previous condition has not disappeared the followingcondition may happen which may make the result of thetransient more serious

32 Simulation of Successive Load Rejection As the layoutof water diversion systems of hydropower stations becomesmore complex as well as the operation of grid systemscombination operating conditions become very commonsuch as load rejection after load acceptance and load rejectionone by one Although the probability of some extremeconditions is very small once they happen the consequencesare very serious Therefore it is necessary to consider thesefactors in the design of hydropower stations

With respect to the water hammer pressure in combina-tion conditions successive load rejection is studied beforeThis operation condition can make the negative pressurein the draft tube more serious than that in simultaneousload rejection in a pumped storage hydropower station [21]The tailrace tunnel is short in a diversion-type hydropowerstation so the draft tube pressure will not reduce too muchduring this condition But successive load rejection mayresult in high overspeed of the runner and larger pressure inthe spiral case in a long diversion-type hydropower stationwith the bifurcated pipe at the bottom of the surge tank thatis there are two independent penstocks for the units from thesurge tank as shown in Figure 3

The calculations are shown in Figure 5 The water levelsof the reservoirs are the same as the previous section Firstlythe 1 turbine rejects its full load and when the water level ofthe surge tank reaches the highest level the 2 turbine rejectsits full load

The dimensionlessWGopening the dimensionless rotat-ing speed of the runner and the pressure head in thespiral case during successive load rejection are shown inFigure 5(a) When the 1 turbine rejects full load the waterlevel of the surge tank begins to rise As shown in Figure 5(b)when the water level of the surge tank reaches the highestlevel it rises about 30m whichmakes the static head of the 2turbine increase by 30m Otherwise the units connect withlarge power grid under normal conditions and the speed ofthe 2 turbinewill not change due to the stable grid frequencyso the opening of theWG keeps constant as well As the statichead of the 2 turbine rises the demand discharge of turbinealso increases When the water level of the surge tank reachesthe highest level after the load rejection of the 1 turbinethe 2 turbine rejects full load Compared with simultaneousload rejection the maximum pressure in the spiral case andthe maximum rotating speed of the 2 turbine are increasedwhich are shown in Table 1Therefore if the water way systemof a hydropower station is arranged as this form especiallyas the headrace tunnel is very long successive load rejectioncondition will make the maximum pressure of the spiral caseand themaximum rotating speed of the runner more serious

The Scientific World Journal 7

0

30

60

90

120

150

0 40 80 120 160 200Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless 1 WG openingDimensionless 2 WG openingDimensionless 1 rotating speedDimensionless 2 rotating speedPressure head in 1 spiral casePressure head in 2 spiral case

(a) Values of turbine parameters versus time

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(b) Water level in surge tank versus time

Figure 5 Numerical results of successive load rejection

Table 1 Comparisons between simultaneous and successive loadrejection

Operation conditionsMaximum

pressure of spiralcase

Maximumrotating speed rise

Simultaneous load rejection 3677m 432Successive load rejection 4021m 499

33 Simulation of Simultaneous Load Rejection after LoadAcceptance Because of the small cross-sectional area thewater level in the riser rises or falls rapidly during transientprocess which creates an accelerating or decelerating headon the tunnel in a short period of time This effect reducesthe amplitude of water level oscillations in the surge tank andaccelerates the attenuation However due to rapid water levelvariations in the risers and slow variations in the main tankthe pressure difference between the two sides of the riserrsquosbreast wall is significant If the structure cannot bear thispressure difference it may cause collapse of the breast wall[22] Thus it is very important to find the critical operationconditions and to simulate the possible maximum pressuredifference on the breast wall in the design stage which arethe basis for the structure calculation of the breast wall

Simultaneous load rejection after load acceptance iscommon in the operation of hydropower stations Duringthis simulation the water levels of the reservoirs are thesame as the previous section As shown in Figure 6(a) twounits accept load one by one which results in the fall of thewater levels in the surge tank When the water levels of thesurge tank reach the lowest level two units reject full loadsimultaneously The water levels in the risers rise rapidly tothe elevation of the overflow weirs while the water level inthemain tank rises slowly and the elevation of the initial water

Table 2 Maximum pressure difference on breast wall underdifferent conditions

Operation conditions Maximum pressure difference onbreast wall

Simultaneous load rejection 292mCombination conditionswithout PROs 509m

Combination conditions withPROs 319m

level is lower compared with the simultaneous load rejectioncase So the pressure difference on the breast wall is largerduring this combination operating condition As shown inFigure 6(b) the maximum pressure difference on the breastwall increases by 20m compared with simultaneous loadrejection

34 Control of the Pressure Difference on Breast Wall As itcan be seen from Table 2 the maximum pressure differencebetween two sides of the breast wall is close to 30m in simul-taneous load rejection while the difference can reach 50m incombination conditionsThis huge pressure difference bringsgreat challenge to the structural safety of the breast wall thushow to reduce the pressure difference between two sides of thebreast wall has become an issue to the design person

Guaranteeing adequate structural strength of the breastwall a row of the PROs can be set along height direction[23] When transient process occurs a large water leveldifference is created between the risers and the main tankin a differential surge tank The water level in the riser risesrapidly reaching the PROs then the water flows from theriser into the main tank through the orifices which slowingdown thewater level rise in the riser while speeding thewater

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 4: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

4 The Scientific World Journal

Upstream reservoir

Downstream reservoir

Differential surge tank

Headrace tunnel

2 unit

1 unit

Penstock

Figure 3 Layout of the waterway and power generation system of the hydropower station

1198673= 119862119872

3+ 119861119872

31198763

d119885119904119904

d119905=119876119904119904+ 119876119884+ 119876119871

119860119904119904

d1198851199041

d119905=1198761199041minus (1198761198841+ 1198761198711)

1198601199041

d1198851199042

d119905=1198761199042minus (1198761198842+ 1198761198712)

1198601199042

(9)

where 1198601 1198602 and 119860

3are the cross-sectional areas of the

sections 1 2 and 3 respectively 119860119904119904 1198601199041 and 119860

1199042are the

cross-sectional areas of the main tank the riser 1 and theriser 2 respectively 119860TH1 119860TH2 and 119860TH3 are the cross-sectional areas of the throttle orifices at the bottom of themain tank the riser 1 and the riser 2 respectively 120585

1 1205852

and 1205853are the head loss coefficients of the throttle orifices

respectively which have different values for the flow into orout of the tank 119876

119884 1198761198841 and 119876

1198842are the discharge through

the overflow weir between the main tank and the risers119876119884= 1198761198841

+ 1198761198842 measured positively from the risers into

the main tank 119876119871 1198761198711 and 119876

1198712are the discharge through

the PROs on the breast wall 119876119871= 1198761198711

+ 1198761198712 measured

positively from the risers into themain tank Every parameterthat has a subscript 0 is a known value of a previous timestep

Discharge through the overflow weir can be given by theequation

119876119884119894=

0 119885119904119894lt 119885119884 119885119904119904lt 119885119884

11989611119861119884radic2119892(119885

119904119894minus 119885119884)15

119885119904119894ge 119885119884 119885119904119904lt 119885119884

11989612119861119884radic2119892(119885

119904119894minus 119885119904119904)15

119885119904119894ge 119885119904119904ge 119885119884

minus1198961015840

11119861119884radic2119892(119885

119904119904minus 119885119884)15

119885119904119894lt 119885119884 119885119904119904ge 119885119884

minus1198961015840

12119861119884radic2119892(119885

119904119904minus 119885119904119894)15

119885119904119904gt 119885119904119894ge 119885119884

(10)

in which 119885119884and 119861

119884are the elevation and the width of the

overflow weir respectively and 11989611and 11989612are the discharge

coefficients of free flow and submerged flow of the overflowweir respectively

Discharge through the PROs can be written as follows

119876119871119894119895

=

0 119885119904119894lt 119885119871119895 119885119904119904lt 119885119871119895

1205831119860119871119895radic2119892 (119885

119904119894minus 119885119871119895) 119885

119904119894ge 119885119871119895 119885119904119904lt 119885119871119895

1205832119860119871119895radic2119892 (119885

119904119894minus 119885119904119904) 119885

119904119894ge 119885119904119904ge 119885119871119895

minus1205831119860119871119895radic2119892 (119885

119904119904minus 119885119871119895) 119885

119904119894lt 119885119871119895 119885119904119904ge 119885119871119895

minus1205832119860119871119895radic2119892 (119885

119904119904minus 119885119904119894) 119885

119904119904gt 119885119904119894ge 119885119871119895

(11)

in which 119894 = 1-2 119860119871119895

(119895 = 1 minus 119870) are the cross-sectionalareas of the PROs and 119870 is the number of the PROs of eachriser 119885

119871119895(119895 = 1 minus 119870) are the elevations of the center of

the PROs and 1205831and 120583

2are the discharge coefficients of free

flow and submerged flow of the PROs respectively So thetotal discharge through the PROs on each breast wall may bewritten as

1198761198711=

119899

sum

119895=1

1198761198711119895 119876

1198712=

119899

sum

119895=1

1198761198712119895 (12)

Every variable of this boundary during transient processcan be derived with (9) to (12) employing the four-orderRunge-Kutta method

3 Case Study

The model is used to predict the hydraulic transients inthe practical hydropower station in China As shown inFigure 3 every two units share a common waterway systemwhich consists of the intake the gate shaft the headracetunnel the upstream differential surge tank penstock thetailrace tunnel and so on

The headrace tunnel has a length of 170 km with adiameter 119863 = 118m The differential surge tank with a ldquo119884rdquoshaped bifurcation pipe at the bottom is located at the end ofthe headrace tunnel The length of each penstock is 5300mand the diameter is 65mThe length of each tailrace tunnel is2600m and the diameter is 120mThe head loss coefficientsof the system are collected according to the project

The cross-sectional areas of the main tank and eachriser of the differential surge tank are 3464m2 and 346m2respectivelyThe cross-sectional areas of the throttle orifice atthe bottom of the main tank and each riser are 139m2 and190m2 respectively The elevation of the bottom of the maintank is 15752m while the elevation of the overflow weir atthe top of the riser is 16700m with the width 119861

119884= 60m

The Scientific World Journal 5

0

30

60

90

120

150

0 10 20 30 40 50Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless WG openingDimensionless rotating speedPressure head in spiral case

(a) Values of turbine parameters versus time

Time (s)

minus400

minus200

0

200

400

0 200 400 600 800 1000

Discharge flow in or out of main tankDischarge flow in or out of 1 riserDischarge flow in or out of 2 riserDischarge through overflow weirsDischarge through PROs

Disc

harg

e (m

3middotsminus

1)

(b) Discharge of surge tank versus time

Time (s)

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(c) Water level in surge tank versus time

Time (s)

minus20

minus10

0

10

20

30

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(d) Water level difference on breast wall versus time

Figure 4 Numerical results of simultaneous load rejection

According to the laboratory experiments the values ofthe parameters are as follows the discharge coefficient of freeoverflow from the riser into the well 119896

11= 05 The discharge

coefficient of free overflow from the main tank into the riser1198961015840

11= 053 The discharge coefficients of submerged flow 119896

12

and 119896101584012

approximate to 80 of the discharge coefficients offree overflow The head loss coefficient of the orifice at thebottom of the main tank 120585

1= 199 for the flow into the main

tank while 1205851= 132 for the flow out of the main tank The

head loss coefficients of the orifice at the bottom of the risers1205852= 1205853= 172 for the flow into the risers while 120585

2= 1205853= 323

for the flow out of the risersThe discharge coefficients of freeflow and submerged flow of the PRO 120583

1= 06 and 120583

2= 05

respectivelyThe rated output of each Francis turbine is 610MW Its

rated head is 288m rated rotating speed is 1667 rpm andrated discharge is 2286m3s The diameter of the runner

is 656m The installation elevation of turbine is 13168mThe inertia (1198661198632) of the turbine and generator is about75800 tm2

31 Simulation of Simultaneous Load Rejection Based on themathematicalmodel and numericalmethods presented in theabove section the computermodel of the hydraulic transientsin the hydropower station is encoded in the FORTRANprogramming language A critical operation that is likelyto occur several times during the life of the project issimulated The upstream water level is at EL 16460m andthe downstream water level is at EL 13331m Full load isrejected at time 119905 = 0 and the WG are closed with the closingtime 119879

119888= 13 seconds under governor control It should be

noted that the effect of the PROs is ignored in this simulationthat is the cross-section areas of the PROs are considered as0 The calculation is shown in Figure 4

6 The Scientific World Journal

The changes of the dimensionless rotating speed of therunner the dimensionless WG opening and the pressurehead in the spiral case are shown in Figure 4(a) Whenthe units reject full load the rotating speed of the runneris increased rapidly The WG are quickly closed accordingto the emergency closure law which is set to the governorin advance to prevent extended periods of high overspeedleading to serious water hammer pressure in the spiral caseThe pressure in the spiral case increases quickly during theclosing process accompanying the phenomena of the wavepropagation and reflection After the closure of theWGmostof the water hammer wave has attenuated and the pressurein the spiral case changes slowly because of the water levelvariation in the surge tank

Figures 4(b) and 4(c) show the changes of the dischargeand the water levels of the surge tank After the closure of theWG the discharge in penstock decreases rapidly The waterin the headrace tunnel flows into the surge tank through theorifices at the bottom of the main tank and the risers sothe water levels in them increase fast As the cross-sectionalarea of the riser is smaller than the main tankrsquos the waterlevel in the riser rises more quickly When the water levelin the riser reaches the elevation of the overflow weir thewater freely spills into the main tank from the riser andthe increasing speed of the water level in the riser becomesslower When the water level in the main tank reaches theelevation of the overflow weir the free flow becomes thesubmerged flow Then the discharge that flows from theriser into the main tank decreases leading to the secondquick increase of water level in the riser in a short periodof time As the discharge into the surge tank decreases theflow direction reverses and the inflow becomes the outflowThe water levels in the main tank and the risers decreaseafter reaching the highest elevation Similarly the water levelin the riser falls more rapidly because of the small cross-sectional area When the water level in the riser is lowerthan that in the main tank the water flows from the maintank to the riser and the flow pattern changes from thesubmerged flow to the free flow with the variation of thewater levels in the main tank and the riser If the water levelin the main tank is lower than the elevation of the overflowweir the overflow stops and the water level in the riser fallsrapidly The discharge through the PROs is always equal to0 during the transient because the area is set to 0 in themodel

Figure 4(d) stands for the water level difference betweenthe two sides of the riserrsquos breast wall during the transientprocess When the load rejection happens the water levelin the riser rises quickly because of the small cross-sectionalarea while the water level in the main tank increases slowlyso the corresponding pressure differencemeasured positivelyin this situation increases quickly When the water level inthe riser reaches the elevation of the overflow weir it risesslowly because of the overflow and the pressure differencereduces gradually Then the pressure difference reverses withthe decrease of thewater level in the riserUnder this transientsimulation the positive pressure difference between the twosides of the riserrsquos breast wall is about 30m while the negativeone is about 20mThepressure difference is significant so the

breast wall in this kind of surge tankmust be of good physicalstrength

As the headrace tunnel of the hydropower station is verylong the water inertia is large so the surge tank periodis very long the amplitude of the oscillations is large andthe attenuation is very slow The transient process causedby previous condition has not disappeared the followingcondition may happen which may make the result of thetransient more serious

32 Simulation of Successive Load Rejection As the layoutof water diversion systems of hydropower stations becomesmore complex as well as the operation of grid systemscombination operating conditions become very commonsuch as load rejection after load acceptance and load rejectionone by one Although the probability of some extremeconditions is very small once they happen the consequencesare very serious Therefore it is necessary to consider thesefactors in the design of hydropower stations

With respect to the water hammer pressure in combina-tion conditions successive load rejection is studied beforeThis operation condition can make the negative pressurein the draft tube more serious than that in simultaneousload rejection in a pumped storage hydropower station [21]The tailrace tunnel is short in a diversion-type hydropowerstation so the draft tube pressure will not reduce too muchduring this condition But successive load rejection mayresult in high overspeed of the runner and larger pressure inthe spiral case in a long diversion-type hydropower stationwith the bifurcated pipe at the bottom of the surge tank thatis there are two independent penstocks for the units from thesurge tank as shown in Figure 3

The calculations are shown in Figure 5 The water levelsof the reservoirs are the same as the previous section Firstlythe 1 turbine rejects its full load and when the water level ofthe surge tank reaches the highest level the 2 turbine rejectsits full load

The dimensionlessWGopening the dimensionless rotat-ing speed of the runner and the pressure head in thespiral case during successive load rejection are shown inFigure 5(a) When the 1 turbine rejects full load the waterlevel of the surge tank begins to rise As shown in Figure 5(b)when the water level of the surge tank reaches the highestlevel it rises about 30m whichmakes the static head of the 2turbine increase by 30m Otherwise the units connect withlarge power grid under normal conditions and the speed ofthe 2 turbinewill not change due to the stable grid frequencyso the opening of theWG keeps constant as well As the statichead of the 2 turbine rises the demand discharge of turbinealso increases When the water level of the surge tank reachesthe highest level after the load rejection of the 1 turbinethe 2 turbine rejects full load Compared with simultaneousload rejection the maximum pressure in the spiral case andthe maximum rotating speed of the 2 turbine are increasedwhich are shown in Table 1Therefore if the water way systemof a hydropower station is arranged as this form especiallyas the headrace tunnel is very long successive load rejectioncondition will make the maximum pressure of the spiral caseand themaximum rotating speed of the runner more serious

The Scientific World Journal 7

0

30

60

90

120

150

0 40 80 120 160 200Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless 1 WG openingDimensionless 2 WG openingDimensionless 1 rotating speedDimensionless 2 rotating speedPressure head in 1 spiral casePressure head in 2 spiral case

(a) Values of turbine parameters versus time

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(b) Water level in surge tank versus time

Figure 5 Numerical results of successive load rejection

Table 1 Comparisons between simultaneous and successive loadrejection

Operation conditionsMaximum

pressure of spiralcase

Maximumrotating speed rise

Simultaneous load rejection 3677m 432Successive load rejection 4021m 499

33 Simulation of Simultaneous Load Rejection after LoadAcceptance Because of the small cross-sectional area thewater level in the riser rises or falls rapidly during transientprocess which creates an accelerating or decelerating headon the tunnel in a short period of time This effect reducesthe amplitude of water level oscillations in the surge tank andaccelerates the attenuation However due to rapid water levelvariations in the risers and slow variations in the main tankthe pressure difference between the two sides of the riserrsquosbreast wall is significant If the structure cannot bear thispressure difference it may cause collapse of the breast wall[22] Thus it is very important to find the critical operationconditions and to simulate the possible maximum pressuredifference on the breast wall in the design stage which arethe basis for the structure calculation of the breast wall

Simultaneous load rejection after load acceptance iscommon in the operation of hydropower stations Duringthis simulation the water levels of the reservoirs are thesame as the previous section As shown in Figure 6(a) twounits accept load one by one which results in the fall of thewater levels in the surge tank When the water levels of thesurge tank reach the lowest level two units reject full loadsimultaneously The water levels in the risers rise rapidly tothe elevation of the overflow weirs while the water level inthemain tank rises slowly and the elevation of the initial water

Table 2 Maximum pressure difference on breast wall underdifferent conditions

Operation conditions Maximum pressure difference onbreast wall

Simultaneous load rejection 292mCombination conditionswithout PROs 509m

Combination conditions withPROs 319m

level is lower compared with the simultaneous load rejectioncase So the pressure difference on the breast wall is largerduring this combination operating condition As shown inFigure 6(b) the maximum pressure difference on the breastwall increases by 20m compared with simultaneous loadrejection

34 Control of the Pressure Difference on Breast Wall As itcan be seen from Table 2 the maximum pressure differencebetween two sides of the breast wall is close to 30m in simul-taneous load rejection while the difference can reach 50m incombination conditionsThis huge pressure difference bringsgreat challenge to the structural safety of the breast wall thushow to reduce the pressure difference between two sides of thebreast wall has become an issue to the design person

Guaranteeing adequate structural strength of the breastwall a row of the PROs can be set along height direction[23] When transient process occurs a large water leveldifference is created between the risers and the main tankin a differential surge tank The water level in the riser risesrapidly reaching the PROs then the water flows from theriser into the main tank through the orifices which slowingdown thewater level rise in the riser while speeding thewater

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 5: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

The Scientific World Journal 5

0

30

60

90

120

150

0 10 20 30 40 50Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless WG openingDimensionless rotating speedPressure head in spiral case

(a) Values of turbine parameters versus time

Time (s)

minus400

minus200

0

200

400

0 200 400 600 800 1000

Discharge flow in or out of main tankDischarge flow in or out of 1 riserDischarge flow in or out of 2 riserDischarge through overflow weirsDischarge through PROs

Disc

harg

e (m

3middotsminus

1)

(b) Discharge of surge tank versus time

Time (s)

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(c) Water level in surge tank versus time

Time (s)

minus20

minus10

0

10

20

30

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(d) Water level difference on breast wall versus time

Figure 4 Numerical results of simultaneous load rejection

According to the laboratory experiments the values ofthe parameters are as follows the discharge coefficient of freeoverflow from the riser into the well 119896

11= 05 The discharge

coefficient of free overflow from the main tank into the riser1198961015840

11= 053 The discharge coefficients of submerged flow 119896

12

and 119896101584012

approximate to 80 of the discharge coefficients offree overflow The head loss coefficient of the orifice at thebottom of the main tank 120585

1= 199 for the flow into the main

tank while 1205851= 132 for the flow out of the main tank The

head loss coefficients of the orifice at the bottom of the risers1205852= 1205853= 172 for the flow into the risers while 120585

2= 1205853= 323

for the flow out of the risersThe discharge coefficients of freeflow and submerged flow of the PRO 120583

1= 06 and 120583

2= 05

respectivelyThe rated output of each Francis turbine is 610MW Its

rated head is 288m rated rotating speed is 1667 rpm andrated discharge is 2286m3s The diameter of the runner

is 656m The installation elevation of turbine is 13168mThe inertia (1198661198632) of the turbine and generator is about75800 tm2

31 Simulation of Simultaneous Load Rejection Based on themathematicalmodel and numericalmethods presented in theabove section the computermodel of the hydraulic transientsin the hydropower station is encoded in the FORTRANprogramming language A critical operation that is likelyto occur several times during the life of the project issimulated The upstream water level is at EL 16460m andthe downstream water level is at EL 13331m Full load isrejected at time 119905 = 0 and the WG are closed with the closingtime 119879

119888= 13 seconds under governor control It should be

noted that the effect of the PROs is ignored in this simulationthat is the cross-section areas of the PROs are considered as0 The calculation is shown in Figure 4

6 The Scientific World Journal

The changes of the dimensionless rotating speed of therunner the dimensionless WG opening and the pressurehead in the spiral case are shown in Figure 4(a) Whenthe units reject full load the rotating speed of the runneris increased rapidly The WG are quickly closed accordingto the emergency closure law which is set to the governorin advance to prevent extended periods of high overspeedleading to serious water hammer pressure in the spiral caseThe pressure in the spiral case increases quickly during theclosing process accompanying the phenomena of the wavepropagation and reflection After the closure of theWGmostof the water hammer wave has attenuated and the pressurein the spiral case changes slowly because of the water levelvariation in the surge tank

Figures 4(b) and 4(c) show the changes of the dischargeand the water levels of the surge tank After the closure of theWG the discharge in penstock decreases rapidly The waterin the headrace tunnel flows into the surge tank through theorifices at the bottom of the main tank and the risers sothe water levels in them increase fast As the cross-sectionalarea of the riser is smaller than the main tankrsquos the waterlevel in the riser rises more quickly When the water levelin the riser reaches the elevation of the overflow weir thewater freely spills into the main tank from the riser andthe increasing speed of the water level in the riser becomesslower When the water level in the main tank reaches theelevation of the overflow weir the free flow becomes thesubmerged flow Then the discharge that flows from theriser into the main tank decreases leading to the secondquick increase of water level in the riser in a short periodof time As the discharge into the surge tank decreases theflow direction reverses and the inflow becomes the outflowThe water levels in the main tank and the risers decreaseafter reaching the highest elevation Similarly the water levelin the riser falls more rapidly because of the small cross-sectional area When the water level in the riser is lowerthan that in the main tank the water flows from the maintank to the riser and the flow pattern changes from thesubmerged flow to the free flow with the variation of thewater levels in the main tank and the riser If the water levelin the main tank is lower than the elevation of the overflowweir the overflow stops and the water level in the riser fallsrapidly The discharge through the PROs is always equal to0 during the transient because the area is set to 0 in themodel

Figure 4(d) stands for the water level difference betweenthe two sides of the riserrsquos breast wall during the transientprocess When the load rejection happens the water levelin the riser rises quickly because of the small cross-sectionalarea while the water level in the main tank increases slowlyso the corresponding pressure differencemeasured positivelyin this situation increases quickly When the water level inthe riser reaches the elevation of the overflow weir it risesslowly because of the overflow and the pressure differencereduces gradually Then the pressure difference reverses withthe decrease of thewater level in the riserUnder this transientsimulation the positive pressure difference between the twosides of the riserrsquos breast wall is about 30m while the negativeone is about 20mThepressure difference is significant so the

breast wall in this kind of surge tankmust be of good physicalstrength

As the headrace tunnel of the hydropower station is verylong the water inertia is large so the surge tank periodis very long the amplitude of the oscillations is large andthe attenuation is very slow The transient process causedby previous condition has not disappeared the followingcondition may happen which may make the result of thetransient more serious

32 Simulation of Successive Load Rejection As the layoutof water diversion systems of hydropower stations becomesmore complex as well as the operation of grid systemscombination operating conditions become very commonsuch as load rejection after load acceptance and load rejectionone by one Although the probability of some extremeconditions is very small once they happen the consequencesare very serious Therefore it is necessary to consider thesefactors in the design of hydropower stations

With respect to the water hammer pressure in combina-tion conditions successive load rejection is studied beforeThis operation condition can make the negative pressurein the draft tube more serious than that in simultaneousload rejection in a pumped storage hydropower station [21]The tailrace tunnel is short in a diversion-type hydropowerstation so the draft tube pressure will not reduce too muchduring this condition But successive load rejection mayresult in high overspeed of the runner and larger pressure inthe spiral case in a long diversion-type hydropower stationwith the bifurcated pipe at the bottom of the surge tank thatis there are two independent penstocks for the units from thesurge tank as shown in Figure 3

The calculations are shown in Figure 5 The water levelsof the reservoirs are the same as the previous section Firstlythe 1 turbine rejects its full load and when the water level ofthe surge tank reaches the highest level the 2 turbine rejectsits full load

The dimensionlessWGopening the dimensionless rotat-ing speed of the runner and the pressure head in thespiral case during successive load rejection are shown inFigure 5(a) When the 1 turbine rejects full load the waterlevel of the surge tank begins to rise As shown in Figure 5(b)when the water level of the surge tank reaches the highestlevel it rises about 30m whichmakes the static head of the 2turbine increase by 30m Otherwise the units connect withlarge power grid under normal conditions and the speed ofthe 2 turbinewill not change due to the stable grid frequencyso the opening of theWG keeps constant as well As the statichead of the 2 turbine rises the demand discharge of turbinealso increases When the water level of the surge tank reachesthe highest level after the load rejection of the 1 turbinethe 2 turbine rejects full load Compared with simultaneousload rejection the maximum pressure in the spiral case andthe maximum rotating speed of the 2 turbine are increasedwhich are shown in Table 1Therefore if the water way systemof a hydropower station is arranged as this form especiallyas the headrace tunnel is very long successive load rejectioncondition will make the maximum pressure of the spiral caseand themaximum rotating speed of the runner more serious

The Scientific World Journal 7

0

30

60

90

120

150

0 40 80 120 160 200Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless 1 WG openingDimensionless 2 WG openingDimensionless 1 rotating speedDimensionless 2 rotating speedPressure head in 1 spiral casePressure head in 2 spiral case

(a) Values of turbine parameters versus time

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(b) Water level in surge tank versus time

Figure 5 Numerical results of successive load rejection

Table 1 Comparisons between simultaneous and successive loadrejection

Operation conditionsMaximum

pressure of spiralcase

Maximumrotating speed rise

Simultaneous load rejection 3677m 432Successive load rejection 4021m 499

33 Simulation of Simultaneous Load Rejection after LoadAcceptance Because of the small cross-sectional area thewater level in the riser rises or falls rapidly during transientprocess which creates an accelerating or decelerating headon the tunnel in a short period of time This effect reducesthe amplitude of water level oscillations in the surge tank andaccelerates the attenuation However due to rapid water levelvariations in the risers and slow variations in the main tankthe pressure difference between the two sides of the riserrsquosbreast wall is significant If the structure cannot bear thispressure difference it may cause collapse of the breast wall[22] Thus it is very important to find the critical operationconditions and to simulate the possible maximum pressuredifference on the breast wall in the design stage which arethe basis for the structure calculation of the breast wall

Simultaneous load rejection after load acceptance iscommon in the operation of hydropower stations Duringthis simulation the water levels of the reservoirs are thesame as the previous section As shown in Figure 6(a) twounits accept load one by one which results in the fall of thewater levels in the surge tank When the water levels of thesurge tank reach the lowest level two units reject full loadsimultaneously The water levels in the risers rise rapidly tothe elevation of the overflow weirs while the water level inthemain tank rises slowly and the elevation of the initial water

Table 2 Maximum pressure difference on breast wall underdifferent conditions

Operation conditions Maximum pressure difference onbreast wall

Simultaneous load rejection 292mCombination conditionswithout PROs 509m

Combination conditions withPROs 319m

level is lower compared with the simultaneous load rejectioncase So the pressure difference on the breast wall is largerduring this combination operating condition As shown inFigure 6(b) the maximum pressure difference on the breastwall increases by 20m compared with simultaneous loadrejection

34 Control of the Pressure Difference on Breast Wall As itcan be seen from Table 2 the maximum pressure differencebetween two sides of the breast wall is close to 30m in simul-taneous load rejection while the difference can reach 50m incombination conditionsThis huge pressure difference bringsgreat challenge to the structural safety of the breast wall thushow to reduce the pressure difference between two sides of thebreast wall has become an issue to the design person

Guaranteeing adequate structural strength of the breastwall a row of the PROs can be set along height direction[23] When transient process occurs a large water leveldifference is created between the risers and the main tankin a differential surge tank The water level in the riser risesrapidly reaching the PROs then the water flows from theriser into the main tank through the orifices which slowingdown thewater level rise in the riser while speeding thewater

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 6: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

6 The Scientific World Journal

The changes of the dimensionless rotating speed of therunner the dimensionless WG opening and the pressurehead in the spiral case are shown in Figure 4(a) Whenthe units reject full load the rotating speed of the runneris increased rapidly The WG are quickly closed accordingto the emergency closure law which is set to the governorin advance to prevent extended periods of high overspeedleading to serious water hammer pressure in the spiral caseThe pressure in the spiral case increases quickly during theclosing process accompanying the phenomena of the wavepropagation and reflection After the closure of theWGmostof the water hammer wave has attenuated and the pressurein the spiral case changes slowly because of the water levelvariation in the surge tank

Figures 4(b) and 4(c) show the changes of the dischargeand the water levels of the surge tank After the closure of theWG the discharge in penstock decreases rapidly The waterin the headrace tunnel flows into the surge tank through theorifices at the bottom of the main tank and the risers sothe water levels in them increase fast As the cross-sectionalarea of the riser is smaller than the main tankrsquos the waterlevel in the riser rises more quickly When the water levelin the riser reaches the elevation of the overflow weir thewater freely spills into the main tank from the riser andthe increasing speed of the water level in the riser becomesslower When the water level in the main tank reaches theelevation of the overflow weir the free flow becomes thesubmerged flow Then the discharge that flows from theriser into the main tank decreases leading to the secondquick increase of water level in the riser in a short periodof time As the discharge into the surge tank decreases theflow direction reverses and the inflow becomes the outflowThe water levels in the main tank and the risers decreaseafter reaching the highest elevation Similarly the water levelin the riser falls more rapidly because of the small cross-sectional area When the water level in the riser is lowerthan that in the main tank the water flows from the maintank to the riser and the flow pattern changes from thesubmerged flow to the free flow with the variation of thewater levels in the main tank and the riser If the water levelin the main tank is lower than the elevation of the overflowweir the overflow stops and the water level in the riser fallsrapidly The discharge through the PROs is always equal to0 during the transient because the area is set to 0 in themodel

Figure 4(d) stands for the water level difference betweenthe two sides of the riserrsquos breast wall during the transientprocess When the load rejection happens the water levelin the riser rises quickly because of the small cross-sectionalarea while the water level in the main tank increases slowlyso the corresponding pressure differencemeasured positivelyin this situation increases quickly When the water level inthe riser reaches the elevation of the overflow weir it risesslowly because of the overflow and the pressure differencereduces gradually Then the pressure difference reverses withthe decrease of thewater level in the riserUnder this transientsimulation the positive pressure difference between the twosides of the riserrsquos breast wall is about 30m while the negativeone is about 20mThepressure difference is significant so the

breast wall in this kind of surge tankmust be of good physicalstrength

As the headrace tunnel of the hydropower station is verylong the water inertia is large so the surge tank periodis very long the amplitude of the oscillations is large andthe attenuation is very slow The transient process causedby previous condition has not disappeared the followingcondition may happen which may make the result of thetransient more serious

32 Simulation of Successive Load Rejection As the layoutof water diversion systems of hydropower stations becomesmore complex as well as the operation of grid systemscombination operating conditions become very commonsuch as load rejection after load acceptance and load rejectionone by one Although the probability of some extremeconditions is very small once they happen the consequencesare very serious Therefore it is necessary to consider thesefactors in the design of hydropower stations

With respect to the water hammer pressure in combina-tion conditions successive load rejection is studied beforeThis operation condition can make the negative pressurein the draft tube more serious than that in simultaneousload rejection in a pumped storage hydropower station [21]The tailrace tunnel is short in a diversion-type hydropowerstation so the draft tube pressure will not reduce too muchduring this condition But successive load rejection mayresult in high overspeed of the runner and larger pressure inthe spiral case in a long diversion-type hydropower stationwith the bifurcated pipe at the bottom of the surge tank thatis there are two independent penstocks for the units from thesurge tank as shown in Figure 3

The calculations are shown in Figure 5 The water levelsof the reservoirs are the same as the previous section Firstlythe 1 turbine rejects its full load and when the water level ofthe surge tank reaches the highest level the 2 turbine rejectsits full load

The dimensionlessWGopening the dimensionless rotat-ing speed of the runner and the pressure head in thespiral case during successive load rejection are shown inFigure 5(a) When the 1 turbine rejects full load the waterlevel of the surge tank begins to rise As shown in Figure 5(b)when the water level of the surge tank reaches the highestlevel it rises about 30m whichmakes the static head of the 2turbine increase by 30m Otherwise the units connect withlarge power grid under normal conditions and the speed ofthe 2 turbinewill not change due to the stable grid frequencyso the opening of theWG keeps constant as well As the statichead of the 2 turbine rises the demand discharge of turbinealso increases When the water level of the surge tank reachesthe highest level after the load rejection of the 1 turbinethe 2 turbine rejects full load Compared with simultaneousload rejection the maximum pressure in the spiral case andthe maximum rotating speed of the 2 turbine are increasedwhich are shown in Table 1Therefore if the water way systemof a hydropower station is arranged as this form especiallyas the headrace tunnel is very long successive load rejectioncondition will make the maximum pressure of the spiral caseand themaximum rotating speed of the runner more serious

The Scientific World Journal 7

0

30

60

90

120

150

0 40 80 120 160 200Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless 1 WG openingDimensionless 2 WG openingDimensionless 1 rotating speedDimensionless 2 rotating speedPressure head in 1 spiral casePressure head in 2 spiral case

(a) Values of turbine parameters versus time

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(b) Water level in surge tank versus time

Figure 5 Numerical results of successive load rejection

Table 1 Comparisons between simultaneous and successive loadrejection

Operation conditionsMaximum

pressure of spiralcase

Maximumrotating speed rise

Simultaneous load rejection 3677m 432Successive load rejection 4021m 499

33 Simulation of Simultaneous Load Rejection after LoadAcceptance Because of the small cross-sectional area thewater level in the riser rises or falls rapidly during transientprocess which creates an accelerating or decelerating headon the tunnel in a short period of time This effect reducesthe amplitude of water level oscillations in the surge tank andaccelerates the attenuation However due to rapid water levelvariations in the risers and slow variations in the main tankthe pressure difference between the two sides of the riserrsquosbreast wall is significant If the structure cannot bear thispressure difference it may cause collapse of the breast wall[22] Thus it is very important to find the critical operationconditions and to simulate the possible maximum pressuredifference on the breast wall in the design stage which arethe basis for the structure calculation of the breast wall

Simultaneous load rejection after load acceptance iscommon in the operation of hydropower stations Duringthis simulation the water levels of the reservoirs are thesame as the previous section As shown in Figure 6(a) twounits accept load one by one which results in the fall of thewater levels in the surge tank When the water levels of thesurge tank reach the lowest level two units reject full loadsimultaneously The water levels in the risers rise rapidly tothe elevation of the overflow weirs while the water level inthemain tank rises slowly and the elevation of the initial water

Table 2 Maximum pressure difference on breast wall underdifferent conditions

Operation conditions Maximum pressure difference onbreast wall

Simultaneous load rejection 292mCombination conditionswithout PROs 509m

Combination conditions withPROs 319m

level is lower compared with the simultaneous load rejectioncase So the pressure difference on the breast wall is largerduring this combination operating condition As shown inFigure 6(b) the maximum pressure difference on the breastwall increases by 20m compared with simultaneous loadrejection

34 Control of the Pressure Difference on Breast Wall As itcan be seen from Table 2 the maximum pressure differencebetween two sides of the breast wall is close to 30m in simul-taneous load rejection while the difference can reach 50m incombination conditionsThis huge pressure difference bringsgreat challenge to the structural safety of the breast wall thushow to reduce the pressure difference between two sides of thebreast wall has become an issue to the design person

Guaranteeing adequate structural strength of the breastwall a row of the PROs can be set along height direction[23] When transient process occurs a large water leveldifference is created between the risers and the main tankin a differential surge tank The water level in the riser risesrapidly reaching the PROs then the water flows from theriser into the main tank through the orifices which slowingdown thewater level rise in the riser while speeding thewater

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 7: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

The Scientific World Journal 7

0

30

60

90

120

150

0 40 80 120 160 200Time (s)

Dim

ensio

nles

s WG

ope

ning

dim

ensio

nles

s rot

atin

g sp

eed

()

200

250

300

350

400

Pres

sure

hea

d (m

)

Dimensionless 1 WG openingDimensionless 2 WG openingDimensionless 1 rotating speedDimensionless 2 rotating speedPressure head in 1 spiral casePressure head in 2 spiral case

(a) Values of turbine parameters versus time

1600

1618

1636

1654

1672

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(b) Water level in surge tank versus time

Figure 5 Numerical results of successive load rejection

Table 1 Comparisons between simultaneous and successive loadrejection

Operation conditionsMaximum

pressure of spiralcase

Maximumrotating speed rise

Simultaneous load rejection 3677m 432Successive load rejection 4021m 499

33 Simulation of Simultaneous Load Rejection after LoadAcceptance Because of the small cross-sectional area thewater level in the riser rises or falls rapidly during transientprocess which creates an accelerating or decelerating headon the tunnel in a short period of time This effect reducesthe amplitude of water level oscillations in the surge tank andaccelerates the attenuation However due to rapid water levelvariations in the risers and slow variations in the main tankthe pressure difference between the two sides of the riserrsquosbreast wall is significant If the structure cannot bear thispressure difference it may cause collapse of the breast wall[22] Thus it is very important to find the critical operationconditions and to simulate the possible maximum pressuredifference on the breast wall in the design stage which arethe basis for the structure calculation of the breast wall

Simultaneous load rejection after load acceptance iscommon in the operation of hydropower stations Duringthis simulation the water levels of the reservoirs are thesame as the previous section As shown in Figure 6(a) twounits accept load one by one which results in the fall of thewater levels in the surge tank When the water levels of thesurge tank reach the lowest level two units reject full loadsimultaneously The water levels in the risers rise rapidly tothe elevation of the overflow weirs while the water level inthemain tank rises slowly and the elevation of the initial water

Table 2 Maximum pressure difference on breast wall underdifferent conditions

Operation conditions Maximum pressure difference onbreast wall

Simultaneous load rejection 292mCombination conditionswithout PROs 509m

Combination conditions withPROs 319m

level is lower compared with the simultaneous load rejectioncase So the pressure difference on the breast wall is largerduring this combination operating condition As shown inFigure 6(b) the maximum pressure difference on the breastwall increases by 20m compared with simultaneous loadrejection

34 Control of the Pressure Difference on Breast Wall As itcan be seen from Table 2 the maximum pressure differencebetween two sides of the breast wall is close to 30m in simul-taneous load rejection while the difference can reach 50m incombination conditionsThis huge pressure difference bringsgreat challenge to the structural safety of the breast wall thushow to reduce the pressure difference between two sides of thebreast wall has become an issue to the design person

Guaranteeing adequate structural strength of the breastwall a row of the PROs can be set along height direction[23] When transient process occurs a large water leveldifference is created between the risers and the main tankin a differential surge tank The water level in the riser risesrapidly reaching the PROs then the water flows from theriser into the main tank through the orifices which slowingdown thewater level rise in the riser while speeding thewater

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 8: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

8 The Scientific World Journal

1580

1602

1624

1646

1668

1690

0 200 400 600 800 1000Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

Time (s)

minus20

0

20

40

60

0 200 400 600 800 1000

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(b) Water level difference on breast wall

Figure 6 Numerical results of simultaneous load rejection after load acceptance

rise in the main tank Therefore the pressure difference onthe breast wall can be reduced The locations the quantityand the diameter of the PROs are fixed during this simulationfor easy comparison of the results In this case the elevationof the bottom floor is 15752m The first orifice is set at theelevation of 1585m on the breast wall with the rest PROssetting every 12m upwards and the breast wall of each riser isinstalled with 6 orifices namely 1ndash6 in turn and the diameterof each PRO is 10m The calculation condition is the sameas the former section and the numerical results are shown inFigure 7

Figure 7(a) shows the variation of the water levels inthe surge tank after setting the PROs on the breast wallCompared with the results in Figure 6(a) that no PROs areset on the breast wall the amplitude of water level oscillationsand surge attenuations in the surge tank is almost the samewhile the rising speed of the water level in the riser is slowingdown obviously

Figure 7(b) shows the discharge through each PRO in the1 riser during the transients When the units accept load thewater level falls quickly in the riser but slowly in the maintank which forms negative water level difference on the twosides of PROs and causes the water to flow from the maintank into the riser As the initial water levels in both the maintank and the risers are above the elevation of the highest PROthat is the 6 PRO submerged flow occurs in the PROs 1ndash6 when the water level difference appears When the waterlevels in the risers fall below the elevation of the 6 PROthe flow pattern at the 6 PRO turns from the submergedflow to the free flow with the water level in the main tankcontinuing to fall the discharge decreases gradually whenthewater level in themain tank falls below the elevation of the6 PRO the discharge through the 6 PRO turns to 0 Similarphenomenon could be seen in other PROs when the waterlevels continue to fall In addition the flow pattern is alwaysthe submerged flow at 1 PRO because of its low elevation

When the water level reaches its lowest elevation in thesurge tank two units reject full load at the same time In

this condition the water level in the riser rises quickly andthe positive water level difference is formed in the 1 PROcausing the water to flow from the riser into the main tank inthe type of submerged flow When the water level in the riserrises to the 2 PRO the water flows from the riser to the maintank in the type of free flow with the water level in the risercontinuing to rise the discharge through the PROs increasesgradually When the water in the main tank reaches the 2PRO the free flow here turns to a submerged one with thewater level in the main tank continuing to rise the dischargedecreases gradually A similar phenomenon occurs in otherPROs subsequently When the water level in the main tank isover the 6 PRO submergedflowoccurs in every PROand thedischarge is the same because of the equal pressure differenceon the two sides of each PRO

Figure 7(c) shows the water level difference on the twosides of the breast wall of the riser Because of the PROsthe water level changes slower in the riser but quicker inthe main tank which reduces the pressure difference on thebreast wall of the riser As shown in Table 2 the maximumwater level difference between the two sides of the breast wallis reduced almost by 20m compared with the results withoutPROs on the breast wall Therefore setting appropriate PROscan effectively reduce the pressure difference between the twosides of the breast wall It should be noted that more PROsand bigger diameters are effective to reduce the pressuredifference on the breast wall but too many or too bigPROs would affect the differential effect of the surge tankthereby increasing the maximum surge and reducing thesurge attenuation in the surge tank

4 Conclusions

This paper provides a mathematical model for the differentialsurge tank with PROs and overflow weirs for transientcalculations The numerical model of hydraulic transientsis established using the data of a practical hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 9: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

The Scientific World Journal 9

0 10008006004002001580

1602

1624

1646

1668

1690

Time (s)

Wat

er le

vel i

n su

rge t

ank

(m)

Water level in main tankWater level in 1 riserWater level in 2 riser

(a) Water level in surge tank versus time

minus10

minus5

0

5

10

15

0 1000800600400200

Discharge through 1 PRODischarge through 2 PRODischarge through 3 PRODischarge through 4 PRODischarge through 5 PRODischarge through 6 PRO

Time (s)

Disc

harg

e (m

3middotsminus

1)

(b) Discharge through PROs versus time

0 1000800600400200Time (s)

minus20

0

20

40

60

Wat

er le

vel d

iffer

ence

(m)

Water level difference on 1 breast wallWater level difference on 2 breast wall

(c) Water level difference on breast wall versus time

Figure 7 Numerical results of simultaneous load rejection after load acceptance with PROs on breast wall

station and the probable operation conditions are simulatedand analyzed The proposed mathematical model and thevalues of some coefficients used in the simulation canprovide reference for the simulation of hydraulic transientsin this type of hydropower station In a long diversion-typehydropower station with the bifurcated pipe at the bottomof the surge tank successive load rejection condition canmake the maximum pressure in the spiral case and themaximum rotating speedmore serious comparedwith simul-taneous load rejection Additionally the pressure differenceon the breast wall is significant during transients especiallyduring the combination condition that simultaneous load

rejection after load acceptance while setting appropriatePROs can reduce the pressure difference effectively Note thatthe present mathematical model and numerical applicationsneed field test verification which will be conducted in theadditional investigation

Notation

MOC Method of characteristicsODE Ordinary differential equationPDE Partial differential equation

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 10: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

10 The Scientific World Journal

PRO Pressure-reduction OrificeWG Wicket gates119886 Wave velocity119860 Cross-sectional area of pipe119860119878 Cross-sectional area of riser

119860119878119878 Cross-sectional area of main tank

119860TH Cross-sectional area of throttle orifice119861119872 119861119875 Known constants in compatibility equa-tions

119861119884 Width of overflow weir

119862119872 119862119875 Known constants in compatibility equa-tions

119891 Darcy-Weisbach friction factor1198661198632 Moment of inertia of unit

119867 Piezometric head119867119879 Turbine head

11989611 Discharge coefficient of free overflow

through overflow weir11989612 Discharge coefficient of submerged over-

flow through overflow weir119899 Dimensionless rotating speed119876 Discharge through pipe119876119871 Discharge through PROs

119876119878 Discharge in riser

119876119878119878 Discharge in main tank

119876119884 Discharge through overflow weirs

119879 Torque on turbine119879119888 Closing time constant from full opening to

closed119879119898 Mechanical starting time

119910 Dimensionless WG opening119885119871 Elevation of the center of PRO

119885119878 Water level in riser

119885119878119878 Water level in main tank

119885119884 Elevation of overflow weir

120573 Dimensionless torque120585 Head loss coefficient of throttle orifice1205831 Discharge coefficients of free flow of PRO

1205832 Discharge coefficients of submerged flowof

PRO

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This paper was supported by the National Natural Sci-ence Foundation of China (Grant no 51379064) the Nat-ural Science Foundation of Jiangsu Province (Grant noBK20130839) the Open Research Fund Program of State KeyLaboratory ofWater Resources andHydropower EngineeringScience (Grant no 2013B116) and the Fundamental ResearchFunds for the Central Universities of China (grant no2013B06114)

References

[1] A Adamkowski ldquoCase study lapino powerplant penstockfailurerdquo Journal of Hydraulic Engineering vol 127 no 7 pp 547ndash555 2001

[2] J Yang K Zhao L Li and PWu ldquoAnalysis on the causes of units7 and 9 accidents at Sayano-Shushenskaya hydropower stationrdquoJournal of Hydroelectric Engineering vol 30 no 4 pp 226ndash2342011 (Chinese)

[3] A Bergant A R Simpson and A S Tijsseling ldquoWater hammerwith column separation a historical reviewrdquo Journal of Fluidsand Structures vol 22 no 2 pp 135ndash171 2006

[4] O H Souza Jr N Barbieri and A H M Santos ldquoStudy ofhydraulic transients in hydropower plants through simulationof nonlinear model of penstock and hydraulic turbine modelrdquoIEEE Transactions on Power Systems vol 14 no 4 pp 1269ndash1272 1999

[5] B Selek M S Kirkgoz and Z Selek ldquoComparison of computedwater hammer pressures with test results for the Catalan powerplant in Turkeyrdquo Canadian Journal of Civil Engineering vol 31no 1 pp 78ndash85 2004

[6] M Calamak and Z Bozkus ldquoComparison of performance oftwo run-of-river plants during transient conditionsrdquo Journal ofPerformance of Constructed Facilities vol 27 no 5 pp 624ndash6322013

[7] J F An J Zhang and A Hazrati ldquoSafe control of air cushionsurge chambers in hydropower systemsrdquo Scientia Iranica vol20 no 6 pp 1605ndash1611 2013

[8] A Riasi A Nourbakhsh and M Raisee ldquoNumerical modelingfor hydraulic resonance in hydropower systems using impulseresponserdquo Journal of Hydraulic Engineering vol 136 no 11 pp929ndash934 2010

[9] M S Ghidaoui M Zhao D A McInnis and D H AxworthyldquoA review of water hammer theory and practicerdquo AppliedMechanics Reviews vol 58 no 1ndash6 pp 49ndash75 2005

[10] H Ramos and A B Almeida ldquoDynamic orifice model onwaterhammer analysis of high or medium heads of smallhydropower schemesrdquo Journal of Hydraulic Research vol 39 no4 pp 429ndash436 2001

[11] T Kolsek J Duhovnik and A Bergant ldquoSimulation of unsteadyflow and runner rotation during shut-down of an axial waterturbinerdquo Journal of Hydraulic Research vol 44 no 1 pp 129ndash137 2006

[12] M H Afshar M Rohani and R Taheri ldquoSimulation oftransient flow in pipeline systems due to load rejection and loadacceptance by hydroelectric power plantsrdquo International Journalof Mechanical Sciences vol 52 no 1 pp 103ndash115 2010

[13] Q K Zhang B Karney L Suo and A F Colombo ldquoStochasticanalysis of water hammer and applications in reliability-basedstructural design for hydro turbine penstocksrdquo Journal ofHydraulic Engineering vol 137 no 11 pp 1509ndash1521 2011

[14] X X Zhang and Y G Cheng ldquoSimulation of hydraulictransients in hydropower systems using the 1-D-3-D couplingapproachrdquo Journal of Hydrodynamics vol 24 no 4 pp 595ndash604 2012

[15] S Y Wu G Wang and J Wang ldquoOptimization of the typeof upstream surge chamber in Jinping Hydropower StationrdquoSichuan Water Power no 6 pp 93ndash96 104 2008 (Chinese)

[16] S R Wang T X Liu and W L Zou ldquoThe advantage ofnew differential surge chamber and its applicationrdquo Journal ofTsinghua University vol 2 pp 73ndash84 1988 (Chinese)

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 11: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

The Scientific World Journal 11

[17] X D Yu J Zhang and A Hazrati ldquoCritical superpositioninstant of surge waves in surge tank with long headrace tunnelrdquoCanadian Journal of Civil Engineering vol 38 no 3 pp 331ndash3372011

[18] E B Wylie V L Streeter and L S Suo Fluid Transients inSystems Prentice-Hall Englewood Cliffs NJ USA 1993

[19] M H Chaudhry Applied Hydraulic Transients Springer NewYork NY USA 2013

[20] J ZhangDWang J Hu J Zhou and J Fang ldquoStudy on field testand simulating calculation following load rejections of tongbaipumped storage power stationrdquo in Proceedings of the ASMEFluids Engineering Division Summer Conference vol 2 pp 349ndash354 August 2008

[21] J Zhang W Lu B Fan and J Hu ldquoThe influence of layout ofwater conveyance system on the hydraulic transients of pump-turbines load successive rejection in pumped storage stationrdquoJournal of Hydroelectric Engineering vol 27 no 5 pp 158ndash1622008 (Chinese)

[22] N S Wang D Q Zheng and Y C Fan ldquoStudy on the differ-ential surge tank in a power plant with a long approach tunnelunder the most unfavouiable operation conditionrdquo Journal ofHydraulic Engineering no 6 pp 23ndash29 1995 (Chinese)

[23] J X Zhou andDY Liu ldquoDifferential pressure and surge analysisof differential surge tank with interconnecting holesrdquo Journalof Hohai University (Natural Sciences) no 5 pp 587ndash591 2007(Chinese)

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Page 12: Research Article Hydraulic Transients in the Long ...downloads.hindawi.com/journals/tswj/2014/241868.pdf · Research Article Hydraulic Transients in the Long Diversion-Type Hydropower

TribologyAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

FuelsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal ofPetroleum Engineering

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Industrial EngineeringJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Power ElectronicsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Advances in

CombustionJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Renewable Energy

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

StructuresJournal of

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Hindawi Publishing Corporation httpwwwhindawicom Volume 2014

International Journal ofPhotoenergy

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear InstallationsScience and Technology of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Solar EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Wind EnergyJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Nuclear EnergyInternational Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

High Energy PhysicsAdvances in

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014


Recommended