+ All Categories
Home > Documents > Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele...

Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele...

Date post: 09-Apr-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
14
Transcript
Page 1: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices
Page 2: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

209

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

PERFORMANCE EVALUATION OF GAS TURBINE

POWER STATION: OMOTOSHO PHASE 1

K K Ikpambese1*, J N Akaaza1 and A Iortsor

In this paper, performance evaluation of gas turbine power station of Omotosho phase 1 stationin Nigeria was carried out. The evaluation was carried out for a period of three years based onperformance indices such as availability, capacity, utilization and load factors. Others werethermal efficiency and percentage contribution of each unit to the total power generation of thestation. The indices showed that the plant was running at an average utilization of 32.9% asagainst the international best practices of over 95%. This data was confirmed by using ANOVA(analysis of variance) to analyze the factors /indices above at 5% significant level and it showedthere was no difference between the variables. Hence, the failure of the power station wasattributed to the environmental and technical problems as well as poor training of operation andmaintenance personnel.

Keywords: Performance evaluation, Performance indices, Omotosho power station, Gasturbine

*Corresponding Author: K K Ikpambese � [email protected]

INTRODUCTION

The significance of electricity as a source of

energy in the socio-economic development of

Nigeria cannot be over-emphasized. Over the

years concerted efforts have been made to

improve on the electricity generation and

distribution in the country. This, however, have

not yielded the required results as current installed

capacity for electric energy generation is put at

6200 MW while actual output hovers between

2500 MW and 3200 MW (Nigerian statistics

Bureau, 2007).

1 Department of Mechanical Engineering, University of Agriculture Makurdi -Nigeria.

Int. J. Engg. Res. & Sci. & Tech. 2014

ISSN 2319-5991 www.ijerst.com

Vol. 3, No. 3, August 2014

© 2014 IJERST. All Rights Reserved

Research Paper

The increasing concern about the lowelectricity generation capacity in Nigeria and itseffects on the socio-economic development ofthe country lead to the establishment ofOmotosho phase 1 power station with totalinstalled capacity of 335 MW to boost generation/distribution of electricity in Nigeria.

Omotosho gas turbine power station is locatedat Omotosho town along Lagos/Benin expressway in Ondo State, Nigeria. This location waschosen due to availability of fuel supplies forcombustion, fresh water for cooling, transmission

facilities and accessibility.

Page 3: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

210

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

In an attempt to improve on the capacity

utilization of Nigerian power stations, several

works have been carried out by different

researchers. Hart (1995) did a study on the “First

Decade of Large-Power Gas Turbine in Nigeria”.

In his study, he used Sapele gas turbine plant as

a case study. He evaluated the performance value

of the turbine sets and also their maintenance

history for the period under study. In his work he

found out that the gas turbine sets did not fare

well in the first ten years of installation. This was

mainly due to the peculiar environmental

conditions such as high ambient temperature,

large amount of dust in the air and instability of

the national grid system.

Odi-Owei (1992), also conducted a study on

the “Performance Appraisal of the Afam Gas

Turbine plant”. He evaluated the performance of

each turbine set for the various plants. He also

took a survey of trips based on the nature and

causes of the outages. In his research, he

discovered that the performance was below

expectations and attributed it to forced outages

caused by disturbances in the national grid and

internal problems in the gas turbine. He opined

that poor preventive maintenance as well as

overhaul history of the turbine and lack of funds

for replacement of damaged components were

responsible for the low performance.

Obodeh and Isaac (2011), also did a study on

the “Performance Analysis for Sapele Thermal

Power Station: A Case Study of Nigeria”. In this

work, performance indices as measured by

percentage shortfall of energy generated, load

factor, utilization factor and capability factor of

Sapele power station in the period of 1997 to 2006

was presented. They discovered that the large

gap between installed and actual operational

capacity of the plant may be due to ageing facilities

and poor maintenance of the plant. Measures to

improve the performance indices were

suggested, such as regular training of operation

and maintenance staff; improvement in operation

and maintenance culture, proper spare parts

inventory, regular management meetings and

good housekeeping of the plant.

Despite efforts made by previous researchers

in the area of power generation and distribution

in Nigeria, the fact remains that electricity

generation capacity utilization of Nigerian power

stations is still very low compared to their

designed output. This study carried out a detailed

performance evaluation of Omotosho Gas

Turbine plant in order to compare its actual with

designed values and recommend possible ways

of optimizing the plant in order to achieve better

output to boost the national grid. As the

contribution of this plant to the national grid would

go a long way in enhancing large scale production

in industries and improve socio-economic

activities in Nigeria.

MATERIALS AND METHODS

Data were obtained from Omotosho power station’s

logbook. These are inventory records of monthly

energy generation between 2009 and 2011 and

operational statistics showing the period of major

outage and the time of maintenance. In processing

the data for this evaluation work, the main focus

was on the following diagnostic techniques/formulas

which were used to monitor and measure the

performance of the gas turbine plant: Load factor,

Capability factor, Utilization factor, Frequency factor,

Capacity factor, Availability factor and Percentage

contribution to station total output by units. The

station performance was assessed using the

following parameters determined on both monthly

and annual basis.

Page 4: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

211

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

( )Load Factor FL

AverageGenerationOutput

The peak load during the same period

=

...(1)

( )Capability Factor Fp

AvailableGenerationCapability

Net Installed Capacity

=

...(2)

( )

exp

UtilizationFactor Fu

EnergyActuallyproducedbyaunitinagiventime

Energythatcouldhavebeen ortedif theunitoperatedatitsinstalledcapacity

=

...(3)

( ) 100Energy Generated

Frequency Factor FcAvailable Energy

= ×

...(4)

The following parameters are used in

assessing individual unit’s performance:

( )cCapacityFactor F

Energyactuallyproducedbyaunitinagiventime

Energythatcouldhavebeenproducedif theunitoperatedatitsinstalledcapacity

=

...(5)

Availability Factor(F ) =a

Actual Time(running hpurns)the plant wasin service

Thetotal timeinterval under consideration

...(6)

int

PercentageContributiontoStationTotalOutput=

Total Energy generated byaunit ina giventime erval

Total energy generated bythestationinthesame period

...(7)

Another parameter used in this evaluation

work is Thermal efficiency of the Gas Turbine

Plant.

Note: average generation output =

Hours in a year =8760 h

Available generation capability = Capability x

number of units available

Available energy =Operating capacity x time

the machine actually run.

Energy that could have been generated at that

interval = Installed capacity x available time

RESULTS AND DISCUSSION

Energy Generated, Consumed andExported

The plant generated between 76MW and 152 MW

of electricity as seen in Figure 1 as against the

installed capacity of 335 MW. It was observed

that there was a constant decrease in generation

throughout the three years under review. The

station generated a total of 396,833 MWH in

2009,388,272 MWH in 2010 and 371,997 MWH

in 2011. This drop in generation could be attributed

to rising cost of machine inputs, e.g., cost of fuel

(gas), aging facilities coupled with poor

maintenance of the plant. Statistically, using

ANOVA it was observed that there was no

difference between the variables under analysis

for energy generated at 5% significant level.

The consumption of the generated energy

stood at 11,753 MWH in 2009, 14,169 MWH in

2010 and 13,352 MWH in 2011 as seen in Figure

2. It was again observed that statistically, there

was no difference between the variables using

ANOVA for energy consumed at 5% significant

level.

In terms of energy exported to the national grid

Page 5: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

212

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

Figure 1: Varuation of Energy Generated with Months

Figure 2: Varuation of Energy Consumed with Months

Page 6: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

213

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

Figure 3: Varuation of Energy Exported to the National Grid with Months

as observed from Figure 3 dropped from 385,080

MWH in 2009 to 381,333 MWH in 2010 and to

366,202.09 MWH in 2011, showing a decrease

of 0.97 % in 2010 and 3.4% in 2011. Statistically,

using ANOVA, there was no difference between

the variables under analysis for energy exported

at 5% significant level.

Availability and Capacity Factor

The variations of availability factor with each of

the gas turbine units are shown in Figure 4. It can

be seen that in 2009, GT4 had the highest

availability factor of 36.52%, while GT3 had the

lowest factor of 3.18%. In 2010, GT8 had the

highest availability of 50.4% while GT2 and GT4

recorded the lowest availability factor of 0% due

to generator differential fault. In 2011, GT1 had

the highest availability factor of 71.04% while GT2

and GT4 still had the lowest factor due to the

generator differential fault in 2010. This shows

that the performance of the various units could

not be improved since the availability was low.

Statistically using ANOVA, it was observed that

there was no difference between the variables

under analysis for availability factor at 5%

significant level.

The annual variation of capacity factor is

shown in Figure 5. It was observed that in 2009,

GT4 had the highest capacity factor of 23.06%

while GT3 had the lowest factor of 2.06%. In 2010,

GT8 had the highest capacity factor of 41.01%

while GT2 and GT4 had 0%. In 2011, GT1 had

the highest capacity factor of 42.85% while GT2

and GT4 had 0%.

The above data has shown that the plant

performance was far below the international best

practices of between 50% and 80%. The capacity

and utilization factors are the main pointers to

the wellbeing of the plant in terms of output. A low

capacity factor signifies that the average energy

generation from the plant is low. This could also

Page 7: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

214

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

Figure 4: Varuation of Availability Factors with Gas Turbine Units

Figure 5: Varuation of Availability Factors with Gas Turbine Plants for 2009, 2010 and 2011

Page 8: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

215

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

mean that plant failure is high hence low capacity

utilization during the year leading to high cost of

operating the plant. High capacity factor is desired

for economic operation of the plant (Obodeh and

Isaac, 2011). Statistically, using ANOVA, it was

observed that there was no difference between

the variables under analysis for capacity factor

at 5% significant level.

Utilization Factor and Load Factor

The maximum utilization factor for 2009 was

87.37% and the minimum was 10.84% as shown

in Figure 6. In 2010, the highest utilization factor

was 51.68% and minimum of 11%. In 2011, it was

60.27% maximum and minimum of 4.21%. The

average utilization factor for the years under

review 2009, 2010 and 2011 are 31.54%, 34.64%

and 32.56%, respectively.

This data falls far below the international best

practices of over 95% (Obodeh and Isaac, 2011).

This was due to the fact that some of thegenerating equipments were not utilized at all,while some were under utilized for reasons ofroutine inspection and maintenance. Statisticallyusing ANOVA, it was observed that there was nodifference between the variables under analysisfor utilization factor at 5% significant level.

Figure 7 shows load factor for the period underreview. The load factor is an indication of theutilization of power plant capacity. A high loadfactor means that the total plant capacity isutilized for most of the time as is desirable fromthe point of view of reducing cost of generationper unit of energy produced (Obodeh and Isaac,2011). The maximum load factors for 2009, 2010and 2011 were 87.96%, 80.64%, and 84.23%,

respectively. This shows that the little available

plant capacity was well utilized within the period

Figure 6: Variations of Utilization Factor with Months

Page 9: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

216

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

Figure 7: Variations of Load Factor with Months for 2009, 2010, and 2011

and conforms to International best practices of

80%. However, the plant could not run all the time

at this acceptable rate, hence the minimum load

factors for 2009, 2010 and 2011 were 22.26%,

13.02% and 41.13%, respectively.

Statistically, using ANOVA, it was observed that

there was no difference between the variables

under analysis for load factor at 5% significant

level.

Gas Consumed Thermal Efficiency andPercentage Contribution to the NationalGrid

Figure 8 shows the variations of gas consumed

with each month of the year under review. The

station consumed a total of 4359, 116,936 scf of

fuel in 2009, 5,190,460,760 scf in 2010, and

4,395,938,025.60 scf of fuel in 2011. Statistically,

using ANOVA it was observed that there was no

difference between the variables under analysis

for gas consumed at 5% significant level.

Figure 9 shows the variation of thermal

efficiency with months in the years under review.

The average thermal efficiency for the year

2009, 2010 and 2011 was 34.226%, 30.32% and

30.48%, respectively. This compares favorably

with the designed cycle thermal efficiency of

32.4% and 48.2% under cold-air-standard

assumptions.

Figures 10, 11 and 12 show the percentage

contribution of each unit to the station total

generation for 2011, 2010 and 2009 respectively.

In 2011, GT1 made the highest contribution of

157,216 MWH representing 42.03% of the total

generation. GT2 and GT4 were not working at all,

while GT5 contributed only 201 MWH which is

0.05% of total generation.

In 2010, GT8 made the highest contribution of

150,469 MWH representing 38.72% of total

generation. GT3 made the lowest contribution of

only 9 MWH In 2009, GT4 made the highest

contribution of 84,577 MWH representing 21.31%

Page 10: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

217

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

Figure 8: Variation of Energy Consumed with Months for 2009, 2010, and 2011

Figure 9: Variations of Thermal Efficiency with Months

Page 11: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

218

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

Figure 10: Percentage Contribution of Each Gas Turbine Unit to Station's Total in 2009

Figure 11: Percentage Contribution of Gas Turbine Units to Station's total in2010

Page 12: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

219

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

Figure 12: Percentage Contribution of Each Gas Turbine Unit to Station's Total in 2009

of station total. All the plants were in operation

with GT3 making the lowest contribution of 7,581

MWH representing 1.91%. Statistically, using

ANOVA, it was observed that there was no

difference between the variables under analysis

for percentage contribution by each GT unit at

5% significant level.

CONCLUSION

Having evaluated the performance of Omotosho

Phase 1 gas Turbine Power Plant from 2009 to

2011; it is obvious that the plant performed below

average capacity throughout the period under

review. The station had low availability factor, low

capacity factor, and low utilization factor which

ranged from 31.54% to 34.64% as against the

International best practice of over 95%.

The following causes were identified as being

responsible for the low performance indices and hence

the general poor performance of the power plant.

1. Generator differential fault which brought

down GT2 and GT4 during 2010-2011.

2. GT3 and GT6 were not available due to high

bearing vibration and both were shutdown

in April and May 2010, respectively.

3. Excitation and high vibration problems were

reasons for low performance of GT5 and

GT6 in 2011.

4. High idle time for some plants in the name

of routine inspection /maintenance.

5. National Grid related problems also

contributed to low performance.

6. Others were environmental conditions such

as high ambient temperature and large

amount of dust in the air.

7. Lack of consumables like spares and

materials for repairs.

8. The plant is an old one as well as the

Page 13: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

220

This article can be downloaded from http://www.ijerst.com/currentissue.php

Int. J. Engg. Res. & Sci. & Tech. 2014 K K Ikpambese et al., 2014

technology. This culminated in the frequent

breakdowns and equipments failures.

Consequently, there was high rate of repairs

and maintenance activities leading to high

man hour lost and low productivity of the plant.

9. The Chinese language used in the

operational manuals also caused difficulties

for maintenance crew to understand what

should be done in times of equipment failure.

10. The removal of fuel subsidy by the President

in 2011 also affected output due to increased

cost of plant operation as a result of high

cost of fuel.

RECOMMENDATIONS

The following measures have been proffered to

improve performance of Omotosho Phase 1

power plant:

1. Provision of enough running spares as well

as proper spare parts inventory control.

2. Training and retraining of the operation and

maintenance personnel who could be more

vast in the operation of the plant, rather than

depending on the Chinese Technicians which

increased cost of operation and caused delays

in solving problems.

3. Translation of the operational manuals from

Chinese to English would go a long way in

reducing down time of the plant.

4. The compressed air unit should be rehabilitated

to blow out dust particles trapped in the air

using an automatic inlet filter instead of the

manual cleaning that takes a lot of time to do.

5. Planned maintenance programs should be

established and strictly followed to improve

reliability and plant performance.

6. Constant supply of gas to the plant should be

ensured at an affordable rate.

7. Energy conservation of the plant by way of

reinjection of heat from the plants to run the

turbines. This will also solve the environmental

problem of pollution by exhaust gases which

affect the ozone layer.

REFERENCES

1. Adigwe C (2006), “Construction of 335 MW

(iso) Gas Turbine Power Plant at

Omotosho, Ondo State”, NSE Report.

2. ECN (Ed.) (2003), The Nigerian Energy

Policy, Energy Commission Publication

Abuja NG.

3. Edeoja A ( 2010), Thermodynamics lecture

notes.1. PHCN, Omotosho Power Station

Annual Report, Ondo State, Nigeria, 2009-2011.

4. Hart H I (1995), “First Decade of Large –

Power Gas Turbines in Nigeria”, Applied

Energy Journal, No. 3, Vol. 51, pp. 213-214.

5. Ibitoye F I andAdenikinju A (2007) “Future

Demand for Electricity in Nigeria”, Applied

Energy Journal, Vol. 84, No. 5, pp. 492-504.

6. Nigerian Statistics Bureu (Ed.) (2007),

Nigerian Statistical Information. http:// www.

nigerianstat.gov.ng

7. Obodeh O and Isaac F O (2011),

“Performance Analysis for Sapele Thermal

Power Station”, Journal of Energy Trends

in Engineering and Applied Sciences

(JETEAS), Vol. 2, No. 1, pp. 166-171.

8. Yungus A C and Michael A B, Thermo

dynamics, an engineering approach, Fifth

Edition, pp. 532-538.

Page 14: Research Paper PERFORMANCE EVALUATION OF GAS TURBINE · the “Performance Analysis for Sapele Thermal Power Station: A Case Study of Nigeria”. In this work, performance indices

Recommended