WP 10543
REPORT NO. RDM/WMA16/01/CON1413
RESERVE DETERMINATION STUDIES FOR THE
SELECTED SURFACE WATER, GROUNDWATER,
ESTUARIES AND WETLANDS IN THE GOURITZ
WATER MANAGEMENT AREA
PROJECT REPORT 14
STUDY CLOSURE REPORT
November 2015
Department of Water and Sanitation
Chief Directorate: Water Ecosystems
Published by
Department of Water and Sanitation
Private Bag X313
PRETORIA, 0001
Republic of South Africa
Tel: +27 (12) 336 7500
Fax: +27 (12) 323 0321
Copyright reserved
No part of this publication may be reproduced in any manner
without full acknowledgement of the source
This report should be cited as:
Department of Water and Sanitation (DWS), 2015. Reserve Determination Studies for Surface
Water, Groundwater, Estuaries and Wetlands in the Gouritz Water Management Area: Study
Closure Report. Prepared by AECOM SA (Pty) Ltd in association with Scherman Colloty and
Associates cc. RDM/WMA16/01/CON/1413.
Compiled by:
AECOM SA (Pty) Ltd
Waterside Place
South Gate
Tyger Waterfront
Carl Cronje Drive
Bellville
7530
In association with:
Scherman Colloty & Associates cc
22 Somerset Street
Grahamstown
6139
Reserve Determination Studies – Gouritz WMA: Project Management Component Page i
Study Closure Report
DOCUMENT INDEX
Reports as part of this project:
INDEX NUMBER REPORT NUMBER REPORT TITLE
Report Number 01 RDM/WMA16/00/CON/0113 Inception Report
Report Number 02 RDM/WMA16/00/CON/0213 Desktop EcoClassification Report
Report Number 03, Volume 1 RDM/WMA16/00/CON/0313,
Volume 1 Delineation Report, Volume 1 (Groundwater,
Estuaries and Wetlands)
Report Number 03, Volume 2 RDM/WMA16/00/CON/0313,
Volume 2 Delineation Report, Volume 2 (Rivers)
Report Number 04 RDM/WMA16/02/CON/0413 Groundwater Report
Report Number 05 RDM/WMA16/03/CON/0513 Wetland Report
Report Number 06 RDM/WMA16/04/CON/0613 Estuaries RDM Report – Desktop Assessment
Report Number 07, Volume 1 RDM/WMA16/04/CON/0713,
Volume 1 Estuaries RDM Report – Rapid Assessment,
Volume 1 (Klein Brak Estuary)
Report Number 07, Volume 2 RDM/WMA16/04/CON/0713,
Volume 2 Estuaries RDM Report – Rapid Assessment,
Volume 2 (Wilderness System)
Report Number 08, Volume 1 RDM/WMA16/04/CON/0813,
Volume 1 Estuaries RDM Report – Intermediate
Assessment, Volume 1 (Duiwenhoks Estuary)
Report Number 08, Volume 2 RDM/WMA16/04/CON/0813,
Volume 2 Estuaries RDM Report – Intermediate
Assessment, Volume 2 (Gouritz Estuary)
Report Number 08, Volume 3 RDM/WMA16/04/CON/0813,
Volume 3 Estuaries RDM Report – Intermediate
Assessment, Volume 3 (Goukou Estuary)
Report Number 09 RDM/WMA16/00/CON/0913 Scenario Report
Report Number 10 RDM/WMA16/01/CON/1013 Rivers RDM Report – IntermediateAssessment
Report Number 11 RDM/WMA16/01/CON/1113 Rivers RDM Report – Rapid Assessment
(Duiwenhoks, Goukou, Doring and
Kammanassie Rivers)
Report Number 12 RDM/WMA16/00/CON/1213 Monitoring Report
Report Number 13 RDM/WMA16/00/CON/1313 Main Report
Report Number 14 RDM/WMA16/00/CON/1413 Study Closure Report
Bold indicates this report
Reserve Determination Studies – Gouritz WMA: Project Management Component Page ii
Study Closure Report
APPROVAL
TITLE: Reserve Determination Studies for the Selected Surface Water,
Groundwater, Estuaries and Wetlands in the Gouritz Water Management
Area: Study Closure Report
DATE: November 2015
AUTHORS: Le Grange A, Scherman P-A
REVIEWERS: Project Management Team
LEAD CONSULTANT: AECOM SA (Pty) Ltd in association with Scherman Colloty & Associates
cc.
REPORT NO: RDM/WMA16/01/CON/1413
FORMAT: MSWord and PDF
WEB ADDRESS: http://www.dws.gov.za
Approved for Scherman Colloty & Associates cc.:
_________________________________
Dr Patsy Scherman
Technical Team Leader
Approved for AECOM SA (Pty) Ltd.:
________________________________
Dr Aldu le Grange
Study Leader
Approved for the Department of Water and Sanitation by:
_____________________________ _____________________________
Ms Nancy Motebe Ms Barbara Weston
Deputy-Director: Groundwater Deputy-Director: Surface Water
Reserve Requirements Reserve Requirements
_____________________________
Mr Yakeen Atwaru
Director: Reserve Requirements
______________________________
Ms Ndileka Mohapi
Chief Director: Water Ecosystems
Reserve Determination Studies – Gouritz WMA: Project Management Component Page iii
Study Closure Report
ACKNOWLEDGEMENTS
The following individuals are thanked for their contributions to this project:
Project Co-ordinators
Yakeen Atwaru Department of Water and Sanitation Project Director
Barbara Weston Department of Water and Sanitation Project Manager: Surface Water
Nancy Motebe Department of Water and Sanitation Project Manager: Groundwater
Thapelo Machaba Department of Water and Sanitation Project Co-ordinator
Project Management Team
Aldu le Grange AECOM SA (Pty) Ltd Professional Service Provider Study Leader
Patsy Scherman Scherman Colloty & Associates Technical Study Team Leader
Simon von Witt AECOM SA (Pty) Ltd Professional Service Provider Study Coordinator
Members of Project Steering Committee
Names Affiliation
Ndileka Mohapi CD: Water Ecosystems (WE)
Yakeen Atwaru D: Reserve Requirements (RR)
Barbara Weston D: RR: Surface Water Reserve Requirements (SWRR)
Nancy Motebe D: RR: Groundwater Reserve Requirements (GWRR)
Thapelo Machaba D: RR: SWRR
Vuledzani Muthelo D: RR: SWRR
Gladys Makhado D: RR: SWRR
Happy Maleme D: RR: SWRR
Wietsche Roets D: Water Abstraction and Instream Use
Shane Naidoo D: Water Resources Classification
Vusi Mema D: Resource Directed Measures Compliance (RDMC)
Boitumelo Sejamoholo D: RDMC
Manelisi Ndima D: GWRR
Isa Thompson DWS: National Planning
Pieter Viljoen DWS: Water Quality Planning
Mennard Mugumo DWS: Options Analysis
Fanus Fourie DWS: Planning Groundwater
Nadene Slabbert DWS: Resource Quality Services (RQS)
Neels Kleynhans DWS: RQS
Gerhard CillIers/Nolu Jafta DWS: RQS
Rashid Khan DWS Western Cape (WC): Regional Director
Wilna Kloppers DWS WC: Resource Protection
Andrew Gordon DWS WC: Resource Protection
Bertrand van Zyl DWS WC: Operations
John Roberts/Hester Lyons DWS WC: Gouritz Catchment Manager
Frans Mouski DWS WC: Hydrology
Mike Smart DWS WC: Geo-Hydrology
André Roux Department of Agriculture Western Cape (DAWC)
Danie Swanepoel/
Francois Naude
Department of Environmental Affairs and Development Planning (DEADP)
Ian Russell/ South African National Parks Board (SANParks)
Reserve Determination Studies – Gouritz WMA: Project Management Component Page iv
Study Closure Report
Names Affiliation
Dirk Roux
Greg Palmer/
Andrew Turner/
Pierre de Villiers
CapeNature
Heidi Nieuwoudt South African National Biodiversity Institute (SANBI)
Jannie van Staden Breede Overberg Catchment Management Agency (BOCMA)
Vernon Gibbs-Halls Eden District Municipality
Harold Basson George Municipality
Alie Killian Oudtshoorn Municipality
Roy Parry Knysna Municipality
Johan du Preez Mossel Bay Municipality
Pikkie Lombard Bitou Municipality
Reggie Wesso Hessequa Municipality
Louw Smit/Christopher Wright Beaufort West Municipality
Richard Fransen/
Heinrich Mettler
Prince Albert Municipality
Jannie Venter Laingsburg Municipality
Aldu le Grange AECOM
Simon von Witt AECOM
Patsy Scherman SC&A
Cecilia Bester Agricultural Research Council
Carl Opperman Agri-Western Cape
Barry Levinrad Department of Land Affairs
Alwyn Lubbe Endangered Wildlife Trust
Connie Jonker Jonkersberg Plantation
Ayanda Matoti Marine and Coastal Management
Alan Boyd Marine Protected Area and Estuary Management
Reserve Determination Studies – Gouritz WMA: Project Management Component Page v
Study Closure Report
AUTHORS
The following person contributed to this report:
Authors Company
Le Grange, Aldu AECOM
Scherman, Patsy Scherman Colloty and Associates
REPORT SCHEDULE
Version Date
First draft November 2015
Final draft December 2015
Reserve Determination Studies – Gouritz WMA: Project Management Component Page vi
Study Closure Report
TABLE OF CONTENTS
DOCUMENT INDEX ........................................................................................................................ i APPROVAL .................................................................................................................................... ii ACKNOWLEDGEMENTS.............................................................................................................. iii AUTHORS ...................................................................................................................................... v TABLE OF CONTENTS ................................................................................................................ vi LIST OF APPENDICES ................................................................................................................. ix LIST OF TABLES ........................................................................................................................... x LIST OF FIGURES ........................................................................................................................ xi ACRONYMS ................................................................................................................................. xii 1 INTRODUCTION .............................................................................................................. 1-1 1.1 BACKGROUND ............................................................................................................... 1-1 1.2 PURPOSE OF THE STUDY ............................................................................................. 1-2 1.3 STUDY AREA OVERVIEW .............................................................................................. 1-2 1.4 STRUCTURE OF STUDY ................................................................................................ 1-5 1.5 PURPOSE OF THIS REPORT ......................................................................................... 1-5 1.6 OUTLINE OF THIS REPORT ........................................................................................... 1-6 2 STUDY ARRANGEMENTS .............................................................................................. 2-1 2.1 STUDY APPOINTMENT .................................................................................................. 2-1 2.2 STUDY DURATION ......................................................................................................... 2-1 2.2.1 Study Commencement ..................................................................................................... 2-1
2.2.2 Study End ........................................................................................................................ 2-1
2.3 STUDY MANAGEMENT .................................................................................................. 2-1 2.3.1 Client ................................................................................................................................ 2-2
2.3.2 Professional Service Provider .......................................................................................... 2-2
2.3.3 Technical Team ................................................................................................................ 2-4
2.3.4 Project Management Committee ...................................................................................... 2-4
2.3.5 Project Steering Committee .............................................................................................. 2-5
2.4 STUDY TEAMS ................................................................................................................ 2-7 2.4.1 Project management team ............................................................................................... 2-7
2.4.2 Technical Component Team ............................................................................................ 2-8
3 SCOPE OF WORK ........................................................................................................... 3-1 3.1 TERMS OF REFERENCE ................................................................................................ 3-1 3.2 AIMS, OBJECTIVES AND OUTCOMES OF THE STUDY ............................................... 3-1 3.3 PROJECT PLAN AND APPROACH ................................................................................ 3-2 3.4 PROJECT MANAGEMENT COMPONENT ...................................................................... 3-2 3.4.1 Objectives of the Project Management Component .......................................................... 3-2
3.4.2 Project Management Component Task Structure ............................................................. 3-2
3.5 TECHNICAL COMPONENT ............................................................................................. 3-4 3.5.1 Objectives of the Technical Component ........................................................................... 3-4
3.5.2 Technical Component Task Structure............................................................................... 3-4
3.6 VARIATION ORDER ........................................................................................................ 3-8 4 STUDY DELIVERABLES ................................................................................................. 4-1 4.1 STUDY PROGRAMME .................................................................................................... 4-1 4.2 MILESTONES AND DELIVERABLES ............................................................................. 4-1 4.3 STUDY REPORTS ......................................................................................................... 4-12 5 STUDY MEETINGS AND WORKSHOPS ...................................................................... 5-13 5.1 STUDY INITIATION MEETINGS .................................................................................... 5-13 5.2 PMC MEETINGS ............................................................................................................ 5-13 5.3 PSC MEETINGS ............................................................................................................ 5-14 5.4 STAKEHOLDER WORKSHOPS .................................................................................... 5-15
Reserve Determination Studies – Gouritz WMA: Project Management Component Page vii
Study Closure Report
5.5 TECHNICAL MEETINGS/ WORKSHOPS ...................................................................... 5-15 6 STUDY MONITORING AND REPORTING....................................................................... 6-1 6.1 OVERALL PERFORMANCE ........................................................................................... 6-1 6.2 PERFORMANCE MONITORING ..................................................................................... 6-1 6.2.1 Progress reporting ............................................................................................................ 6-1
6.2.2 Feedback at PMC/PSC meetings ..................................................................................... 6-2
6.2.3 Study reporting ................................................................................................................. 6-2
6.2.4 Report reviewing .............................................................................................................. 6-3
7 STAKEHOLDER PARTICIPATION .................................................................................. 7-1 7.1 STAKEHOLDER AWARENESS ...................................................................................... 7-1 7.2 IDENTIFICATION OF STAKEHOLDERS ......................................................................... 7-1 7.3 COMMUNICATION WITH STAKEHOLDERS .................................................................. 7-1 7.3.1 Background Information Document .................................................................................. 7-1
7.3.2 Stakeholder Newsletters .................................................................................................. 7-2
7.4 STAKEHOLDER WORKSHOPS ...................................................................................... 7-2 7.4.1 Stakeholder Workshop 1 .................................................................................................. 7-2
7.4.2 Stakeholder Workshop 2 .................................................................................................. 7-2
7.5 ISSUES/COMMENTS AND RESPONSE REGISTER ...................................................... 7-3 7.6 IMPROVED STAKEHOLDER INVOLVEMENT ................................................................ 7-3 8 TRAINING AND CAPACITY BUILDING .......................................................................... 8-1 8.1 BACKGROUND ............................................................................................................... 8-1 8.2 IDENTIFIED DWS TRAINEES: 2013 ............................................................................... 8-1 8.3 TRAINING OPPORTUNITIES .......................................................................................... 8-2 8.4 FEEDBACK FROM DWS TRAINEES .............................................................................. 8-4 9 FINANCIAL MANAGEMENT ........................................................................................... 9-1 9.1 APPROVED STUDY BUDGET ........................................................................................ 9-1 9.1.1 Original study budget ....................................................................................................... 9-1
9.1.2 Variation order .................................................................................................................. 9-1
9.1.3 Revised study budget ....................................................................................................... 9-1
9.2 DETAIL OF STUDY BUDGET ......................................................................................... 9-2 9.3 INVOICING ...................................................................................................................... 9-3 9.3.1 Invoicing procedure .......................................................................................................... 9-3
9.3.2 Invoicing per task ............................................................................................................. 9-3
9.3.3 Summary of project invoicing ........................................................................................... 9-3
9.4 CASHFLOW..................................................................................................................... 9-4 9.5 HDI PARTICIPATION ...................................................................................................... 9-7 10 STUDY FEEDBACK ...................................................................................................... 10-1 10.1 PROJECT MANAGEMENT COMPONENT .................................................................... 10-1 10.1.1 Study administration and coordination ............................................................................ 10-1
10.1.2 Scope management ....................................................................................................... 10-2
10.1.3 Communications management ....................................................................................... 10-3
10.1.4 Risk management .......................................................................................................... 10-4
10.1.5 Time and cost management ........................................................................................... 10-4
10.1.6 Quality management ...................................................................................................... 10-4
10.1.7 Integration management ................................................................................................ 10-5
10.2 TECHNICAL COMPONENT ........................................................................................... 10-5 10.2.1 Economic overview ........................................................................................................ 10-5
10.2.2 Rivers study overview .................................................................................................... 10-7
10.2.3 Estuaries study overview ................................................................................................ 10-8
10.2.4 Basic Human Needs Reserve (surface water) .............................................................. 10-10
Reserve Determination Studies – Gouritz WMA: Project Management Component Page viii
Study Closure Report
10.2.5 Wetlands ...................................................................................................................... 10-10
10.2.6 Groundwater ................................................................................................................ 10-11
10.2.7 Scenario development .................................................................................................. 10-11
10.2.8 Monitoring .................................................................................................................... 10-13
10.2.9 Preliminary Ecological Reserve Categories’ Conclusions ............................................. 10-13
10.3 REVIEW AND EVALUATION PROCESS .................................................................... 10-14 10.4 LIAISON WITH THE CLIENT ....................................................................................... 10-15 10.5 AVAILABILITY OF INFORMATION ............................................................................. 10-15 11 CONCLUSIONS ............................................................................................................. 11-1 11.1 ECOLOGICAL COMPONENT OF THE RESERVE ........................................................ 11-1 11.2 IMPORTANCE OF OPERATIONAL SCENARIOS ......................................................... 11-1 11.3 RIVERS: ECOCLASSIFICATION AND EWR ASSESSMENT ....................................... 11-2 11.4 ESTUARIES: ECOCLASSIFICATION AND EWR ASSESSMENT ................................ 11-2 11.5 GROUNDWATER .......................................................................................................... 11-5 11.6 ADDITIONAL RECOMMENDATIONS ........................................................................... 11-6 12 REFERENCES ............................................................................................................... 12-1
Reserve Determination Studies – Gouritz WMA: Project Management Component Page ix
Study Closure Report
LIST OF APPENDICES
APPENDIX A: CONTRACTUAL AGREEMENT
APPENDIX A.1: ORIGINAL CONTRACT
APPENDIX A.2: LETTER OF NOTIFICATION OF APPOINTMENT
APPENDIX A.3: VARIATION ORDER AND APPROVAL
APPENDIX B: STUDY PROGRAMME
APPENDIX C: BACKGROUND INFORMATION DOCUMENT
APPENDIX D: MINUTES OF STUDY INITIATION MEETINGS
APPENDIX E: MINUTES OF PROJECT MANAGEMENT COMMITTEE MEETINGS
APPENDIX F: MINUTES OF PROJECT STEERING COMMITTEE MEETINGS
APPENDIX G: ACTIONS/DECISIONS REGISTER
APPENDIX H: STAKEHOLDER INFORMATION
APPENDIX H.1: STAKEHOLDER LIST
APPENDIX H.2: STAKEHOLDER NEWSLETTERS
APPENDIX H.3: MINUTES OF STAKEHOLDER WORKSHOPS & ATTENDANCE REGISTERS
APPENDIX H.4: STAKEHOLDER ISSUES/CONCERNS AND RESPONSE REGISTER
APPENDIX I: STUDY BUDGET
APPENDIX J: COMMENTS AND RESPONSE REGISTER
Reserve Determination Studies – Gouritz WMA: Project Management Component Page x
Study Closure Report
LIST OF TABLES
Table 2.1: PMC Members ....................................................................................................... 2-5
Table 2.2: PSC members ....................................................................................................... 2-6
Table 2.3: Project management team members ................................................................... 2-8
Table 2.4: River Team ............................................................................................................ 2-9
Table 2.5: Estuaries Team ................................................................................................... 2-10
Table 2.6: Groundwater Team ............................................................................................. 2-10
Table 2.7: Wetlands Team ................................................................................................... 2-11
Table 3.1: Project Management Component tasks .............................................................. 3-3
Table 3.2: Technical Component task structure .................................................................. 3-5
Table 4.1: Integrated Study Milestones and Deliverables ................................................... 4-3
Table 4.2: Final list of reports produced for the GRDS ..................................................... 4-12
Table 5.1: Summary of PMC meetings ................................................................................ 5-13
Table 5.2: Summary of PSC meetings ................................................................................ 5-14
Table 5.3: Summary of Stakeholder Workshops ............................................................... 5-15
Table 5.4: Summary of technical meetings/workshops .................................................... 5-15
Table 6.1: Compilation and review process of study reports ............................................. 6-4
Table 8.1: Potential DWS trainees identified at Inception Stage ......................................... 8-1
Table 8.2: Training and capacity building opportunities ..................................................... 8-2
Table 9.1: Original approved study budget .......................................................................... 9-1
Table 9.2: Approved VO budget ............................................................................................ 9-1
Table 9.3: Revised study budget........................................................................................... 9-2
Table 9.4: Study budget distribution .................................................................................... 9-2
Table 9.5: Summary of study monthly invoicing record ..................................................... 9-4
Table 9.6: Cashflow comparison........................................................................................... 9-5
Table 10.1: Macro-economy of the Gouritz WMA ................................................................ 10-6
Table 10.2: Most dominant economic sector per economic region ................................... 10-6
Table 10.3: EWR river sites selected .................................................................................... 10-7
Table 10.4: EWR results as a percentage of the nMAR ....................................................... 10-8
Table 10.5: Summary reference of GRDS estuary study ..................................................... 10-8
Table 11.1: Summary of the Preliminary Reserve determination for estuaries in the
Gouritz WMA ....................................................................................................... 11-3
Reserve Determination Studies – Gouritz WMA: Project Management Component Page xi
Study Closure Report
LIST OF FIGURES
Figure 1.1 Study area ............................................................................................................. 1-4
Figure 9.1: Cashflow comparison........................................................................................... 9-6
Figure 10.1: Summary of PES of estuaries in the Gouritz WMA illustrating the
continuum in estuary condition. ........................................................................ 10-9
Figure 10.2: Type of mitigation measures that would be required to meet RECs ............. 10-10
Reserve Determination Studies – Gouritz WMA: Project Management Component Page xii
Study Closure Report
ACRONYMS
AGES African Geo-Environmental Services
BAS Best Attainable State
BGCMA Breede-Gouritz Catchment Management Agency
BHNR Basic Human Need Reserve
BID Background Information Document
CD: WE Chief Directorate: Water Ecosystems
CMA Catchment Management Area
CSIR Council for Scientific and Industrial Research
DAFF Department of Agriculture, Forestry and Fisheries
DAGEOS Deep Artesian Groundwater Exploration for Oudtshoorn Supply
DAWC Department of Agriculture Western Cape
DEA Department of Environmental Affairs
DM District Municipality
D: RR Directorate Reserve Requirements
DWA Department of Water Affairs (name change from DWAF applicable after April 2009)
DWAF Department of Water Affairs and Forestry
DWS Department of Water and Sanitation (name change from DWA applicable after May
22014)
EC Ecological Category
EIS Ecological Importance and Sensitivity
ER Economic Region
EWR Ecological Water Requirements
GDP Gross Domestic Product
GRDS Gouritz Reserve Determination Study
GRU Groundwater Resource Unit
GWRR Groundwater Reserve Requirement
HDI Histroical Disadvantaged Individual
IWR Institute for Water Reosurces
LM Local Municipality
MCM Million Cubic Metres
nMAR natural Mean Annual Runoff
NMMU Nelson Mandela Metropolitan University
NWA National Water Act
NWRC National Water Resource Classification
ODRS Outeniqua Reserve Determination Study
pMAR present Mean Annual Runoff
PC Potential Concern
PES Present Ecological State
PMC Project Management Comittee
PMT Project Management Team
PSC Project Steering Committee
PSP Professional Service Provider
Reserve Determination Studies – Gouritz WMA: Project Management Component Page xiii
Study Closure Report
RC Reference Condition
RDMC Resource Directed Measures Compliance
REC Recommended Ecological Category
RQS Resource Quality Objectives
RR Reserve Requirements
RRD Reserve Requirements Determinations
SANBI South African National Biodiversity Institute
SANParks South African National Parks Board
SC&A Scherman Colloty and Associates cc
SD Sub-Directorate
SWRR Surface Water Reserve Requirement
SWRD Surface Water Reserve Determination
SWRDR Surface Water Reserve Determination Requirements
SQ Sub-Quaternary catchment
TPC Threshold Potential Concern
WC Western Cape
WMA Water Management Area
WRC Water Resource Classification
WRCS Water Resource Classification System
WRUI Water Resource Use Importance
WRYM Water Resources Yield Model
Quat Quaternary catchment
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 1-1
Study Closure Report
1 INTRODUCTION
1.1 BACKGROUND
The National Water Act (Act No 36 of 1998) (NWA) is based on the principle that National
Government, through the Department of Water and Sanitation (DWS), has overall
responsibility for and authority over water resource management for the benefit of the public,
without affecting the functioning of the natural environment and in order to ensure that the
environment will be able to deliver the goods and services to society in a sustainable manner.
In order to achieve this objective, the NWA (Section 3) provides for the protection of and
sustainable use of water resources, including groundwater resources, through the
determination and implementation of the Reserve for these resources.
The NWA Section 3 requires that the Reserve be determined for water resources, i.e. the
quantity, quality and reliability of water needed to sustain both human use and aquatic
ecosystems, so as to meet the requirements for economic development without seriously
impacting on the long-term integrity of ecosystems. The Reserve is one of a range of
measures aimed at the ecological protection of water resources and the provision of basic
human needs (i.e. in areas where people are not supplied directly from a formal water service
delivery system and thus directly dependent on the resource according to Schedule 1 of the
NWA). The Chief Directorate: Water Ecosystems (CD: WE) within the DWS is tasked with the
responsibility of ensuring that the Reserve is considered before water allocation and licensing
can proceed.
The requirement for detailed Reserve studies in the Gouritz Water Management Area (WMA)
became apparent for the following reasons:
Various licence applications in the area;
Gaps that have been identified as part of the Outeniqua Reserve Determination
Study (ORDS) completed in 2010;
The conservation status of various priority water resources in the catchment and
existing and proposed impacts on them; and
Increasing development pressures and secondary impacts related from the
aforementioned and the subsequent impact on the availability of water.
For management and improved governance reasons, South Africa’s 19 WMAs have been
consolidated into nine (9) WMAs. The Gouritz WMA (previously WMA 16) now forms part of the
Breede WMA (WMA 8) and is known as the Breede-Gouritz WMA. It will be governed by the
Breede-Gouritz Catchment Management Area (CMA).
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 1-2
Study Closure Report
The DWS, through the CD: WE, subsequently commissioned, via a study that will address the
Preliminary Reserve Determination Studies for Selected Surface Water (Estuaries and
Wetlands) and Groundwater (Project WP 1054) in the Gouritz WMA 8 to undertake
preliminary Reserve determinations in the Gouritz WMA on various levels of detail. This study
will hereafter be referred to as the Gouritz Reserve Determination Study (GRDS).
1.2 PURPOSE OF THE STUDY
The DWS has completed a Preliminary Reserve determination at various levels of confidence
on a number of priority water resources (rivers, wetlands, estuaries and groundwater) in the
Outeniqua catchment (previously part of WMA 16, which was part of the Gouritz WMA). The
study was completed and approved by the deigated authority in 2010. Since the
amalgamation of the Gouritz and Breede WMA’s to establish the new WMA 8, the DWS
recognised that a number of priority water resources have not been addressed that forms part
of the new established WMA. Hence, the commissioning of the GRDS to address the gaps of
the remaining water resources and as recommended as an implementation action in the
Outeniqua Main Report. One of the priority catachments that has now been included is the
Touw River with its estuary at Wilderness and its whole integrated wilderness laes/wetland
system. Various of the inland water resources situated in the Olifnats, Groot, Gamka and
some of the coastal rivers have been included in the GRDS. A focus was also placed on the
inland groundwater resources.
The GRDS focused on the preliminary Reserve determination and strives to be a
comprehensive and integrated study of selected surface and groundwater resources,
estuaries and wetlands in the Gouritz WMA. Note that the term “preliminary” merely refers to
the Reserve before formalization through the Water Resource Classification System (WRCS)
process. The Reserve process is a scenario-based approach and thus the overall outcome of
the GRDS is envisaged as a series of Reserve scenarios that will be provided to the DWS
with the associated ecological and socio-economic consequences at the end of the study.
This will enable the DWS to make informed decisions regarding the management of selected
water resources. This is done in terms of the authorisation of future water use and the
magnitude of the impacts of the proposed developments.
1.3 STUDY AREA OVERVIEW
The Gouritz WMA ((WMA16) falls predominantly within the Western Cape Province, with
small portions in the Eastern Cape and the Northern Cape Provinces. It has a surface area of
approximately 53 000 km2 and consists of primary drainage region J (approximately 90
quaternary catchments), and part of primary drainage regions K (K1 to K7) and H (H8 to H9).
The WMA therefore consists of approximately 100 – 105 quaternary catchments. It consists of
the large dry inland area that is comprised of the Karoo and Little Karoo, and the smaller
humid strip of land along the coastal belt. The main rivers are the Gouritz and its major
tributaries, the Buffels, Touws, Groot, Gamka, Olifants and Kammanassie rivers, with smaller
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 1-3
Study Closure Report
coastal rivers draining the coastal belt. All the inland rivers drain via the Gouritz into the Indian
Ocean. As such, the WMA consists of the following five sub-areas:
Groot River (secondary catchment J1);
Gamka River (secondary catchment J2);
Olifants River (secondary catchment J3);
Western Coastal Rivers (secondary catchments H8, H9 and J4); and
Eastern Coastal Rivers (Secondary Catchments K1, K2, K3, K4, K5, K6 and K7).
The GRDS excludes the majority of the coastal catchment areas that were covered by the
ORDS and other Reserve studies done previously (e.g. Oudtshoorn (Olifants River and
tributaries), Sout and Matjies).
The mean annual precipitation varies from as high as 865 mm in the coastal areas, which
experience all-year-round rainfall, to as little as 160 mm in the drier areas inland to the north,
which experience late summer rainfall. A map of the study area is provided below (refer to
Figure 1.1).
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 1-4
Study Closure Report
Figure 1.1 Study area
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 1-5
Study Closure Report
1.4 STRUCTURE OF STUDY
The GRDS is structured into two main components, namely:
Project Management Component, and
Technical Component (Reserve determination studies).
The scope of work of the overall study, including both the Project Management and Technical
Components, comprised three sequential phases, namely:
Phase 1 : Study Initiation and Design;
Phase 2 : Study Implementation; and
Phase 3 : Study Termination.
The Inception component of this study formed part of the Initiation and Design Phase with the
main deliverable being the Inception Report. The Inception Report formed the blueprint of the study
as it paved the way for the execution and deliverables produced as part of the study. The study
budget, approach, technical methods used and capacity (human and financial) needed had been
confirmed and agreed on with the approval of the Inception Report. This phase provided the
opportunities for both the DWS and PSPs to address all uncertainties that have been identified after
the initiation of the study and the contracts have been signed. regarding the scope of work were
clarified and confirmed during this stage.
The Study Implementation Phase comprised of the implementation of the project plan developed
during the Inception Phase and the undertaking of the Technical Component(s) of the ecological
Reserve determination study.
The Study Termination Phase was an administrative and final reporting stage, during which the
project was finalised and completed and all deliverables produced as final documents and data
provided to the DWS in the specified formats.
1.5 PURPOSE OF THIS REPORT
This document represents the Study Closure Report and summarises the relevant scope of work,
study management arrangements, financial management, reporting and study feedback, including
lessons learned. In addition, the Study Closure Report’s intention is to provide feedback on the
financial status and timing of the project, and a reference point for future studies.
The purpose of this report is primarily to provide an overview of the study. The report attempts to
determine whether the study was undertaken with the aspects formulated in the Inception Report
with feedback in terms of the respective performances so as to ensure that the study was completed
efficiently and to the satisfaction of, and within the parameters set out by the DWS CD : WE.
The following information is provided and discussed in this report:
Study arrangements and responsibilities;
Scope of Work;
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 1-6
Study Closure Report
Study programme and deliverables;
Meetings and workshops;
Project monitoring and reporting;
Stakeholder participation;
Training and capacity building;
Financial aspects; and
Study feedback, including lessons learned.
1.6 OUTLINE OF THIS REPORT
The Study Closure Report has, for ease of reference, been structured as follows: Section 1 comprises a general introduction to the DWS Project WP 10543, i.e. the GRDS; Section 2 provides an overview of the study management arrangements of the GRDS, focussing largely on the various roles of different teams and studies; Section 3 refers back to the proposal on which the study has been approved by the DWS and the Scope of Works set out by the DWS and the variations that have been included in the Inception Report; Section 4 provides and overview of the study deliverables related to the study programme, deliverables and milestones; Section 5 contains a summary on all study related meetings and workshops; Section 6 discusses project monitoring and associated reproting; Section 7 provides a brief overview of stakehlder participation; Section 8 briefly refers to training and capacity building opportunities; and Section 9 contains an overview of the financial aspects of the project including budget, invoicing and cashflow. The following supporting documentation are attached: Appendix A: Contractual Agreement Appendix B: Study Programme Appendix C: Background Information Document Appendix D: Minutes of Study Initiation Meetings Appendix E: Minutes of Project Management Committee Meetings Appendix F: Minutes of Steering Committee Committee Meetings Appendix G: Actions/Decisions Register Appendix H: Stakeholder Information Appendix I: Study Budget
Appendix J: Comments and Response Register
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-1
Study Closure Report
2 STUDY ARRANGEMENTS
2.1 STUDY APPOINTMENT
Based on an official tender process which took place in September 2011, AECOM SA (Pty) Ltd
(AECOM) was appointed as the lead Professional Service Provider (PSP) responsible for the
execution of the GRDS on behalf of the DWS. Given the structure of the study, AECOM, as Lead
PSP, lead the Project Management Component, assisted by Milkwood Communications on
stakeholder participation related matters, while independent Specialist Advisors provided specialist
input and external review to oversee the technical compliance of the work undertaken by the
Technical Component. Reference to this team is hereafter made to as the Project Management
Team (PMT).
Scherman, Colloty and Associates cc (SC&A), supported by various specialists, provided support to
AECOM in leading the Technical Component in determining the Reserve for the various water
resource components.
All study related contractual agreemenst are included in Appendix A of this report. A copy of the
Letter of Notification of Appointment for the undertaking of the GRDS as issued on 23 February
2012 is attached as Appendix A.1. Both the original GRDS Terms of Reference (ToR) and the
Scope of Works, as was slightly amended during the Inception Phase, are detailed in the Inception
Report (DWA, 2014), with a copy of the original contract included as Appendix A.2.
2.2 STUDY DURATION
2.2.1 Study Commencement
An initial Project Inception Scoping Meeting took place at the DWS Offices, Pretoria, on 3 May
2012. However, a substantial delay was experienced with the finalization of the contractual
agreement between the DWS and AECOM, with the resulting official study commencement date as
7 May 2013. This was followed by a Project Initiation Meeting on 6 June 2013 at the AECOM
Offices, Bellville. The minutes of both meetings are included in Appendix D of this report.
2.2.2 Study End
The original time frame for the GRDS was set as 24 months with the intended study end date as 7
May 2015. However, based on a Variation Order (VO), as defined in Section 3.4, the study end
date was extended with six months to 7 November 2015.
2.3 STUDY MANAGEMENT
The study responsibilities in terms of managerial, technical and coordination functions are discussed
below, while details of the study team composition are provided in Section 2.4. Associated study
milestones and deliverables are discussed in Section 4.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-2
Study Closure Report
2.3.1 Client
2.3.1.1 Departmental responsibility
The DWS was the Client with the Directorate: Reserve Requirements Determinations (D: RRD)
within the CD: WE responsible for the execution of the overall GRDS and administrating the study.
2.3.1.2 Project Manager
The study resided under the responsibility of Mr Yakeen Atwaru, Director D:RR, while Mrs Barbara
Weston, Scientific Manager: Surface Water Reserve Determination (SWRD) acted as the DWS
Project Manager. Signing off on the Study and Technical reports resides with the DWS Project
Management Team.
2.3.1.3 Project Coordinator
Ms Thapelo Machaba assisted the DWS Project Manager as the DWS Project Coordinator. She
assisted with the coordination and administration of the study from the DWS’ perspective and was
responsible for administrative liaison with the PSP. She was, inter alia, responsible for:
Coordinating the study;
Coordinating inputs from other DWS directorates;
Approving of additional study team members, invoices and Variation Order(s); and
Relaying the results and recommendations from the study to the DWS Management.
Direct administrative matters and all correspondence to the DWS was also directed to her, whilst
copied to Mr Atwaru and Mrs Weston.
2.3.2 Professional Service Provider
2.3.2.1 Project Management Team
The role of the PMT was that of an ancillary to the DWS: CD: WE to ensure that the GRDS was
undertaken in an efficient and timeous manner within the allocated budget and framework of DWS
requirements. The review, monitoring and follow up on reports, invoices, approval of additional
members, cash flows and submission of variation orders all formed part of the PMT’s duties.
The PMT was responsible for the following project management and administrative functions:
Study secretariat and coordination;
Work programme coordination;
Stakeholder communication;
Financial administration;
Technical review; and
Administrative progress reporting.
In addition, the PMT recorded the proceedings of Project Management Committee (PMC)/ Project
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-3
Study Closure Report
Steering Committee (PSC) meetings and made presentations as required. The PMT also kept an
up-to-date record of all decisions taken during the execution of the study, identifying issues raised
and decisions taken. This was done through maintaining a Decision and Issue/Action Register (refer
to Section 6.2.3.2).
2.3.2.2 Study Leader
Dr Aldu le Grange from AECOM acted as the PSP Study Leader responsible for overall study
coordination between the DWS, the PMT and the Technical Team, as well as monitoring and
performance control of the PSP Team. This included review of study progress, monitoring of
financial expenditure versus technical progress, review of technical reports and liaison with and
management of the input by the Specialist External Reviewers. Overall was responsible for the day-
to-day execution of the study, concentrating on the compliance of the work undertaken in line with
the Inception Report as approved by the PMC, co-ordination of the PSP team and study
administration to ensure coordinated output at key milestone dates.
On the technical side he was supported by Dr Patsy Scherman from SC&A as the Technical Study
Leader and the various Specialist External Reviewers (refer to Section 2.3.2.7).
2.3.2.3 Study Coordinator
Mr Simon von Witt from AECOM initially acted as the PSP Study Coordinator responsible for the
day-to-day study coordination and administration from the PSP’s perspective, assisting with liaison
with the DWS and the Technical Team. This included arranging of meetings, recording of the
proceedings of meetings, distribution of agendas and minutes, maintaining the Decision and
Issue/Action Registers, data and document control, provision of feedback to the DWS and other
related administrative tasks.
Since he left the services of AECOM in April 2015, he was replaced by Ms Colleen Thomas, who in
turn was eventaully replaced by Ms Shoeshoe Letoao in July 2015 during the Study Termination
Stage, both from AECOM.
2.3.2.4 Study Administration
Study operational support was initially provided by Ms Louise Buys and Ms Nelda Visser, who was
respectively responsible for the financial and administrative tasks, including the arrangement of
PMC meetings and invoice compilation and submission.This task was, however, taken over by Ms
Thomas, and eventually Ms Letoao.
2.3.2.5 Stakeholder Communication
As part of the PMT Milkwood Communications assisted with the following defined stakeholder
activities:
Stakeholder identification and database compilation and maintenance;
Compilation of a Background Information Document (BID) and the distribution thereof;
Obtaining current knowledge information on stakeholder attitudes, values and expectations
towards water resources in the study catchment; and
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-4
Study Closure Report
Presentation of the study results in terms of scenarios, consequences and results to the
stakeholders and obtaining their feedback to be included in the final study documentation.
Assistance was also provided with the preparation and presentation of reports on the study to
stakeholder forums and other organisations with an interest in the Gouritz WMA.
2.3.2.6 Technical Review
The PMT was responsible for technical monitoring of activities and progress of the Technical
Component. In the case of the GRDS the PMT was extended to include Specialist External
Reviewers (see Table 2.3) supporting the PMT with specialist Reserve determination technical
monitoring capabilities and review of deliverables.
Technical monitoring was limited to the attendance of selected PMC/PSC meetings and the review
of technical reports. In some cases, such as groundwater, specialist discussion meetings and work
sessions were also attended.
2.3.3 Technical Team
The Technical Team, lead by Dr Patsy Scherman of SC&A, was responsible for the technical
Reserve determination studies for the various water resource components, i.e. rivers, wetlands,
estuaries and groundwater. As Technical Study Team Leader, Dr Patsy Scherman was responsible
for the technical coordination and management of the specialist studies, compilation of technical
reports, coordination of specialist workshops, and technical feedback at PMC/PSC Meetings as well
as to the DWS.
The composition of the Technical Team is provided in Section 2.4.2.
2.3.4 Project Management Committee
The study was carried out under the guidance of a PMC, comprising representatives from the DWS
CD: WE and other DWS directorate/departmental representatives nominated from time to time, as
well as the PMT and the Technical Study Leader, as summarised in Table 2.1. Where relevant,
Technical Task Leaders and PMT Specialist Advisors/ External Reviewers were invited to attend
specific PMC meetings.
The PMC was responsible for guidance and steering of the general management of the study to
steer twoards the effective and efficient formulation, execution and conclusion of the study. It also
represented the project interactions with other projects and organisations. Responsibilities of the
PMC were as follows :
Assessing the scope of work and objectives of the study;
Monitoring and assessing study progress;
Monitoring the study budget and expenditure against deliverables produced;
Evaluating all reports, including the format and scope of reports as agreed on as per the
Inception Phase;
Address issues that require the attention of the DWS; and
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-5
Study Closure Report
Provide recommendations on various aspects of the study where required.
Table 2.1: PMC Members
Names Affiliation
Ndileka Mohapi DWS: CD: WE
Yakeen Atwaru DWS: D: RR
Barbara Weston DWS: SD: Surface Water Reserve Determination Requirements (SWRDR)
Nancy Motebe DWS: SD: Groundwater Reserve Requirements (GWRR)
Thapelo Machaba DWS: D: SWRR
Wietsche Roets DWS: D: Water Abstraction and Instream Use
Shane Naidoo DWS: D: Water Resources Classification (WRC)
Vusi Mema DWS: D: Resource Directed Measures Compliance (RDMC)
Manelisi Ndima DWS: SD: GWRR
Isa Thompson DWS: National Planning
Pieter Viljoen DWS: Water Quality Planning
Mennard Mugumo DWS: Options Analysis
Fanus Fourie DWS: Planning Groundwater
Nadene Slabbert DWS: Resource Quality Services (RQS)
Neels Kleynhans/ Gerhard CillIers/ Nolu Jafta
DWS: RQS
Rashid Khan DWS Western Cape (WC): Regional Director
Wilna Kloppers/ Andrew Gordon
DWS WC : Resource Protection
Bertrand van Zyl DWS WC : Operations
John Roberts/ Hester Lyons DWS WC : Gouritz Catchment Manager
Frans Mouski DWS WC : Hydrology
Mike Smart DWS WC : Geo-Hydrology
Aldu le Grange AECOM
Simon von Witt/Colleen Thomas/Shoeshoe Letoao
AECOM
Patsy Scherman SC&A
2.3.5 Project Steering Committee
Although not defined by the original ToR, the need for a separate PSC was discussed during the Project Initiation Meeting of 6 June 2013. It was decided that for the purposes of the PSC, the PMC be enlarged to include additional stakeholders with a vested interest in the study area. The proposed composition of the PSC is indicated in Table 2.2:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-6
Study Closure Report
Table 2.2: PSC members
Names Affiliation
Ndileka Mohapi DWS: CD: WE
Yakeen Atwaru DWS: D: RR
Barbara Weston DWS: SD: SWRDR
Nancy Motebe DWS: SD: GWRR
Thapelo Machaba DWS: D: SWRR
Vuledzani Muthelo DWS: D: RR-SWRR
Gladys Makhado DWS: D: RR
Happy Maleme DWS: D: RR
Wietsche Roets DWS: D: Water abstraction and instream use
Shane Naidoo DWS: D: Water Resources Classification
Vusi Mema DWS: SD: Resource Directed Measures Compliance (RDMC)
Boitumelo Sejamoholo DWS: D: RDMC
Manelisi Ndima DWS: D: GWRR
Isa Thompson DWS: National Planning
Pieter Viljoen DWS: Water Quality Planning
Mennard Mugumo DWS: Options Analysis
Fanus Fourie DWS: Planning Groundwater
Nadene Slabbert DWS: Resource Quality Services (RQS)
Neels Kleynhans/ Gerhard CillIers/ Nolu Jafta
DWS: RQS
Rashid Khan DWS WC: Regional Director
Wilna Kloppers/ Andrew Gordon
DWS WC : Resource Protection
Bertrand van Zyl DWS WC : Operations
John Roberts/ Hester Lyons DWS WC : Gouritz Catchment Manager
Frans Mouski DWS WC : Hydrology
Mike Smart DWS WC : Geo-Hydrology
Andre Roux Department of Agriculture Western Cape (DAWC)
Danie Swanepoel/Francois Naude
Department of Environmental Affairs and Development Planning (Western Cape) (DEA))
Ian Russell/Dirk Roux South African National Parks Board (SANParks)
Greg Palmer/Andrew Turner/
Pierre de Villiers CapeNature
Heidi Nieuwoudt South African National Botanical Institute (SANBI)
Jannie van Staden Breede-Gouritz Catchment Management Agency (BGCMA)
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-7
Study Closure Report
Names Affiliation
Vernon Gibbs-Halls Eden District Municipality
Harold Basson George Municipality
Albertus Killian Oudsthoorn Municipality
Roy Parry Knysna Municipality
Johan du Preez Mossel Bay Municipality
Pikkie Lombard Bitou Municipality
Reggie Wesso Hessequa Municipality
Louw Smit/Christopher Wright Beaufort West Municipality
Richard Fransen/Heinrich Mettler
Prince Albert Municipality
Jannie Venter Laingsburg Municipality
Aldu le Grange AECOM
Simon von Witt/Colleen Thomas/Shoeshoe Letoao
AECOM
Patsy Scherman SC&A
Cecile Bester Agricultural Research Council
Carl Opperman Agri-Western Cape
Barry Levinrad Department of Land Affairs
Alwyn Lubbe Endangered Wildlife Trust
Connie Jonker Jonkersberg Plantation
Ayanda Matoti Marine and Coastal Management
Alan Boyd Marine Protected Area and Estuary Management
2.4 STUDY TEAMS
Senior and other key staff members of the respective Project Management and Technical
Components’ study teams, including changes, are defined in Sections 2.4.1 (Project Management
Component) and 2.4.2 (Technical Component).
2.4.1 Project management team
Details of the PMT members in terms of name, organisation and associated study responsibility are
provided in Table 2.3:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-8
Study Closure Report
Table 2.3: Project management team members
Team Member Organisation Role
Management Team:
Aldu le Grange AECOM Study Leader
Simon von Witt/Colleen
Thomas/Shoeshoe
Letoao
AECOM Study Coordinator
Louise Buys AECOM Financial Controller
Nelda Visser AECOM Study Administrator
Stakeholder Participation:
Bea Whittaker Milkwood Communications Stakeholder Participation Task
Leader
Mathabo Ntumba Milkwood Communications Stakeholder Particpation
Administrator
Specialist External Reviewers:
Johan Rossouw AECOM Yield modelling and system
analysis
Cate Brown Southern Waters Ecological
Research Rivers
Julian Conrad Geohydrological and Spatial
Solutions cc (GEOSS) Groundwater
Kai Whitthueser Delta-H Water Systems
Modelling Pty Ltd Groundwater
Angus Paterson South African Institute for
Aquatic Biodiversity (SAIAB) Estuaries
Justine Ewart-Smith The Freshwater Consulting
Group Wetlands
Given the above-mentioned PMT composition, it should be noted that those proposed as Specialist
Advisors at the Initiation and Design Stage merely acted as External Reviewers during the later
stages of the GRDS, and not as Specialist Advisors.
2.4.2 Technical Component Team
The Technical Component of the study was managed by Dr Patsy Scherman of SC&A as the overall
study Technical Leader. However, although the technical Reserve determination studies were
undertaken under the management of SC&A, various individual specialists formed part of the overall
larger Technical Team as sub-contracted PSPs.
The Technical Component comprises four sub-studies related to rivers, estuaries, groundwater and
wetlands. The relevant study teams for each of these are summarised in Tables 2.4 to 2.7 included
in Sections 2.4.2.1 to 2.4.2.4.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-9
Study Closure Report
2.4.2.1 River team
The river study team is listed in Table 2.4.
Table 2.4: River Team
Team members Organisation Role
Delana Louw Rivers for Africa
Rivers Task Leader; habitat
integrity and Environmnetal
Water Requirement (EWR)
integrator
Shael Koekemoer Koekemoer Aquatic Services Reporting and diatoms
Patsy Scherman SC&A Water quality
Estelle van Niekerk AECOM Hydrology and yield modelling
Stephen Mallory IWR Water Resources Yield modelling
Denis Hughes Institute for Water Research
(IWR), Rhodes University SPATSIM
Andrew Birkhead Streamflow Solutions Hydraulics
Mark Rountree Fluvius Consulting Geomorphology
Brian Colloty SC&A Riparian vegetation: Rapid sites
James Mackenzie Mackenzie Environmental
Development Solutions
Riparian vegetation:
Intermediate sites
Pieter Kotzé Clean Stream Biological
Services Fish: Intermediate sites
Anton Bok Anton Bok Aquatic
Consultants Fish: Rapid sites
Mandy Uys Laughing Water:
Macroinvertebrates Invertebrates
Greg Huggins Nomad Consulting Basic Human Needs Reserve
(BHNR), Ecosystem Services
William Mullins Mosaka Consulting Macro-economics
David Mosaka Mosaka Consulting Macro-economics
Kagiso Kwele AECOM Hydrology and yield modelling
Shileen Louw Rivers for Africa Administrative assistant
Khaya Mgaba IWR Trainee: Invertebrates
Nkosinathi Mazungula SAIAB Trainee: Fish
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-10
Study Closure Report
2.4.2.2 Estuaries team
The estuaries study team is listed in Table 2.5.
Table 2.5: Estuaries Team
Team members Organisation Role
Susan Taljaard Council for Scientific and
Industrial Research (CSIR)
Estuaries Task Leader and
water quality
Lara van Niekerk CSIR Hydrodynamics
Piet Huizenga Private Hydrodynamics
Stephen Mallory IWR Water Resources Yield modelling
Andre Theron CSIR Sediment modelling
Janine Adams
Nelson Mandela
Metropolitan University
(NMMU)
Macro- and micro flora
Gavin Snow NMMU Macro- and micro flora
Steve Lamberth
Department of Agriculture,
Forestry and Fisheries
(DAFF)
Fish
Jane Turpie Anchor Environmental Birds
Tris Wooldridge NMMU Invertebrates
Alistair Adonis CSIR Field Assistant and skipper
Chantel Petersen CSIR Assistant: Abiotic components
Alexis Olds Cape Nature Trainee: Estuarine invertebrates
Jean du Plessis Cape Nature Trainee: Fish
2.4.2.3 Groundwater team
The groundwater study team is listed in Table 2.6.
Table 2.6: Groundwater Team
Team members Organisation Role
Koos Vivier
Exigo ( previously Africa
Geo-Environmental Services
(AGES))
Groundwater Task Leader and
modelling
Jan Myburgh Exigo Structural geology &
geohydrology
Stephan Meyer Exigo Groundwater flow modelling
Megan Hill Exigo Field work and geophysics
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 2-11
Study Closure Report
Team members Organisation Role
Reuben Grobler Exigo Groundwater modelling
Frans Meyer Exigo Fieldwork
2.4.2.4 Wetlands team
The wetlands study team is listed in Table 2.7.
Table 2.7: Wetlands Team
Team member Organisation Role
Mark Rountree Fluvius Consulting Wetlands Task Leader and
EcoClassification
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-1
Study Closure Report
3 SCOPE OF WORK
3.1 TERMS OF REFERENCE
The GRDS ToR as included in the Inception Report (DWA, 2014) contains the Scope of Work for
both the Project Management and Technical Components of the GRDS. The ToR provides a clear
description of the work to be undertaken and the expected deliverables. However, based on
discussions during the Inception component of the Initiation and Design Phase, the Inception Report
formed the contractual basis upon which work has been undertaken.
Only one Variotion Order (VO) was submitted to the DWS during the course of the GRDS. This VO
is discussed in Section 3.4.
3.2 AIMS, OBJECTIVES AND OUTCOMES OF THE STUDY
With the purpose of the GRDS defined in Section 1.2, the study was aimed as an integrated study
to determine the Preliminary Reserves of selected surface (rivers, estuaries and wetlands) and
groundwater resources, estuaries and wetlands was undertaken for the Gouritz part of WMA 8. In
addition, the outcome of the study assisted in providing detailed ecological information as input to
Water Resource Classifcation (WRC), which will be initiated for the Breede-Gouritz WMA during
2016.
The focus of the GRDS was to determine the EWRs of resources in the study area. It was assumed
that scenario and economic steps of the process only focused on major developments in the
catchment.
Operational constraints and catchment requirements were incorporated into yield scenario
modelling, and catchment activities impacting on ecology were considered. The scenarios selected
considered the realities of the current and possible future ecological and socio-economic situation in
the study area as identified during a Scenario Workshop conducted with the DWS and local
municipalities on 25 August 2014. Stakeholder attitudes, values and expectations towards water
resources of the study area, as determined during Stakeholder Workshop No 1, were also taken into
account.
The Ecological Reserve Categories associated with the Preliminary Reserve values were arrived at
by following the recognized ecoclassification process to determine the said categories, considering
the driving ecological considerations in the study area, an evaluation of future developments and
the ecological consequences in response to. Further discussions with the DWS in September 2015,
and stakeholders at two meetings in October 2013 and 2015 also aided in determining the EC
based on Best Attainable State (BAS) principles. The final recommendations are presented in the
Main Report (DWS, 2015b) for priority rivers, estuarine systems, and for priority wetlands in the
study area. Of importance for the way forward and the implementation of the study results into
management action, are the EWR sites that have been created and used in the study. These are
now to be considered as primary monitoring sites for which ecological specifications have been set.
The latter will be used as indicators to measure the health status of these water resources and
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-2
Study Closure Report
provide baseline information as input to the upcoming classification and reporting on the state of the
relevant water resources.
The level of detail at which a study can be undertaken is dependent on the data available, i.e. the
more data available on a particular system, the more accurate the Ecological Category (EC), the
ecological flows (Ecological Reserve), as well as Ecological specifications (Ecospecs) can be set.
However, in instances where the lack of certain data sets poses uncertainties, a precautionary
approach was adopted, i.e. the Ecological Reserves were set conservatively. The levels of
assessments at which various river and estuarine systems were evaluated, were indicated where
relevant. It is acknowledged that the confidence in results are related to the data available,
particularly hydrological data.
3.3 PROJECT PLAN AND APPROACH
The GRDS was structured into two main components, namely:
Project Management Component, led by Dr Aldu Le Grange of AECOM, and
Technical Component (Reserve determination studies), led by Dr Patsy Scherman of SC&A.
Project-related activities were grouped into study tasks as defined for each of the Project
Management and Technical Components. The purpose and task structure of each component are
described below:
3.4 PROJECT MANAGEMENT COMPONENT
3.4.1 Objectives of the Project Management Component
The primary purpose of the Project Management Component assignment was to assist the DWS
CD: WE, i.e. the Client, with the coordination of all the activities required to achieve the objectives of
the Reserve determination study. In summary, the scope of the Project Management Component
professional services provided are:
Assistance with the overall study management functions to the DWS CD: WE and the
dissemination of information to serve their requirements;
Responsibility for all day-to-day management activities of the study as set out in the ToR,
and amended in the Inception Report;
Establishment and maintenance of an information framework;
Ensuring that all deliverables are produced on time and within budget; and
Support with reporting and communications to stakeholders.
3.4.2 Project Management Component Task Structure
A summary of the GRDS Project Management Component task structure undertaken is provided in
Table 3.1.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-3
Study Closure Report
Table 3.1: Project Management Component tasks
Task description
Task 1 : Study Initiation and Design
Task 1.1: Inception meetings
Task 1.2: Familiarisation with Scope of Work
Task 1.3: Familiarisation with historic and current Reserve studies
Task 1.4: Resource Monitoring Inventory
Task description
Task 1.5: Management Framework
Task 1.6: Project Monitoring and Control System
Task 1.7: Establishment of an Information Management System
Task 1.8: Support to the Technical Component PSP's
Task 1.9: Stakeholder Engagement, BID & Stakeholder Workshop No.1
Task 1.10: Phase 1 Close-out: Inception Report (including Project Plan)
Task 1.11: PMC Meeting No.1
Task 2: Study Implementation
Task 2.1: Project Management, including PMC and PSC meetings
Task 2.2: Client Liaison
Task 2.3: Technical Monitoring and Support
Task 2.4: Stakeholder Participation
Task 2.5: Status and Progress Reports
Task 2.6: Integration of Technical Results
Task 2.7: Provision of data, reports and supporting information
Task 3: Management and Review
Task 3.1: Review and Management of Deliverables
Task 3.2: Project Auditing
Task 3.3: Termination Strategy
Task 3.4: Newsletter
Task 3.5: Reserve Templates
Task 3.6: Feedback to DWS
Task 3.7: Final PMC & PSC Meetings
Task 3.8: Study Closure Report
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-4
Study Closure Report
3.5 TECHNICAL COMPONENT
3.5.1 Objectives of the Technical Component
The Technical Component was aimed at the actual coordination and execution of the Reserve
determination tasks to be undertaken for each water resource component as per the approved
Reserve steps for each sub-system.
The specific objectives and outcomes of the Reserve determination for the different aquatic
ecosystems were to:
Conduct a desktop EcoClassification (rivers) on a sub-qQuaternary scale to determine the
Present Ecological State (PES)1, Ecological Importance and Sensitivity (EIS),
Recommended Ecological Category (REC), causes and sources and identify hotspots2.
Conduct a reconnaissance field survey and together with the output of the desktop
EcoClassification, select Ecological Water Requirement (EWR) sites in selected rivers.
Determine the Reference Condition (RC), PES and RECs for each relevant section of the
rivers, estuaries, wetlands and groundwater components.
Determine and recommend Ecological Categories (ECs) for each relevant section of of the
rivers, estuaries, wetlands and groundwater components.
Determine EWR for the selected resources at the EWR sites.
Evaluate and select water resource operational scenarios for consideration during the study.
Determine the impact of scenarios on systems in question where information regarding the
scenarios was available.
Determine the ecological consequences of these scenarios.
Provide DWS with all information relevant to the RECs and Alternative ECs (where
available) to enable DWS to recommend an Ecological Reserve Category at the relevant
EWR site for the protection and management of the water resources in the study area. The
latter will be captured in the legal template to be approved and to be included in future water
allocation and operating rules from infrastructure.
Provide the ecological specifications associated with the selected EC, and provide vital
information as input into the development of monitoring programmes for water resources.
Prepare the surface and groundwater Basic Human Needs Reserve (BHNR) for water use
directly from rivers and boreholes.
Provide DWS with all relavent data (raw data, populated models and shape files used in the
generation of maps) in electronic format.
Provide CD: WE with the information required to prepare the Reserve templates, including
draft templates, for authorization.
Train selected DWS Directorate: Reserve Requirements (D:RR) staff in specific tasks
relating to Reserve determinations.
3.5.2 Technical Component Task Structure
1 PES: Health or integrity as compared to the natural or reference state
2 Hotspots: areas of ecological importance; an output of the Desktop EcoClassification process
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-5
Study Closure Report
A summary of the GRDS Technical Component task structure undertaken is provided in Table 3.2.
Table 3.2: Technical Component task structure
Task description
Task A: Project Management
Task A1: Technical team management and coordination
Task A2: PMC Meetings
Task A3: PSC Meetings
Task A4: Financial Management
Task A5: Technical team management - Rivers
Task A6: Technical team management - Estuaries
Task A7: Technical team management - Groundwater
Task description
Task A8: Presentation of study results to DWS
Task B: Project Inception (Planning and Process)
Task B1: Gather background information
Task B2: Design Project plan and produce Inception Report
Task B3: Mobilisation of study team
Task C: Desktop Ecoclassification - Rivers
Task C1: Ecosystem services
Task C2: Rivers ecological and water quality (workshop)
Task C3: Water Resource Unit Importance (WRUI)
Task C4: Desktop EcoClassification Report (including hotspots)
Task D: Reconnaissance River Surveys
Task D1: Survey 1
Task D2: Survey 2
Task E: Delineation Resource Units
Task E1: Rivers
Task E2: Estuaries
Task E3: Wetlands
Task E4: Groundwater
Task E5: Delineation Report
Task F: Field Surveys
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-6
Study Closure Report
Task F1: Estuary summer survey
Task F2: River survey 1
Task F3: River survey 2
Task F4: Additional high flow surveys
Task F5: Groundwater field survey (hydrocensus + groundwater sampling)
Task F6: Wetland (rapid) survey 1
Task F7: Wetland survey 2 - priority wetlands
Task G: Data Analysis - Estuaries
Task G1: Hartenbos, Blinde, Piesang, Groot (Wes) and Bloukrans
Task G2: Duiwenhoks, Klein Brak and Touw/Wilderness
Task G3: Goukou and Gouritz
Task description
Task H: Data Analysis - Rivers
Task H1: EcoClassification and EWR
Task H2: Hydraulic data analysis and modelling
Task I: Data Analysis - Wetlands
Task I1: Identification of priority wetlands and data collection
Task I2: Determining RC, PES, EIS
Task I3: Management recommendations and Wetlands Report
Task J: Rapid Reserve - Groundwater
Task J1: Data collection and analysis
Task J2: Develop a conceptual groundwater model
Task J3: Report on data gaps and groundwater sources/sinks
Task K: Reserve Determination of the Groundwater Component
Task K1: Update groundwater conceptual model
Task K2: Conduct Reserve assessment
Task K3: Groundwater Report
Task L: Hydrology, Yield Modelling and Operational Scenarios
Task L1: Evaluation of hydrology and compilation of flow records
Task L2: Systems modelling and yield analysis
Task L3: Water balances
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-7
Study Closure Report
Task L4: Liaison re: scenarios and defining scenarios
Task L5: Running scenarios and reporting
Task M: Estuary EWR Assesments
Task M1: EWR workshop 1
Task M2: EWR worskhop 2
Task N: River Ecoclassification and EWR Determination
Task N1: Intermediate specialist meeting
Task N2: Rapid assessment
Task N3: Reports
Task O: Basic Human Needs Reserve (surface water)
Task P: Consequences to Operational Scenarios
Task P1: Rivers - Consequences and reporting
Task description
Task P2: Estuaries
Task P3: Economics
Task P4: Ecosystem Services
Task Q: Estaury Reports (including monitoring)
Task Q1: Desktop Level Assessment reports
Task Q2: Rapid Level EWR reports
Task Q3: Rapid / Intermediate Level EWR reports
Task R: Ecological and other objectives
Task R1: EcoSpecs & Thresholds of Potential Concern (PCs) - Rivers
Task R2: Wetland objectives for priority wetlands
Task R3: Groundwater objectives and monitoring programme
Task S: Stakeholder Engagement
Task S1: Input to advertisements, Background Information Document (BID), etc.
Task S2: Public meeting at start of study
Task S3: Public meeting at end of study
Task T: Integrated Main Report
Task U: Training Workshops
Task U1: Training Worskhop 1 – Introduction and Rivers
Task U2: Training Worskhop 2 - Estuaries and Wetlands
Task U3: Training Workshop 3 - Modelling, Groundwater and Economics
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 3-8
Study Closure Report
Task U4: Reporting
3.6 VARIATION ORDER
Although the Letter of Notification of Appointment was issued on 23 February 2012, the finalisation
of the contractual agreement was delayed until 7 May 2013, i.e. more than a year’s delay and took
up unnecessary time. It also resulted in the GRDS being undertaken at the tendered rates of
November 2011, with no escalation, which is not considered as reasonable, considering the
Consumer Price Index.
The late study commencement resulted in the study starting in the winter instead of summer as
planned, delaying the anticipated completion of technical tasks (e.g. field surveys) due to the
seasonal variation. An extension of time was therefore required to complete the technical work,
undertake additional hydrological modeling, review of reports and amendments before the approval
of the final deliverables.
In terms of hydrological modelling and system yield assessment, a detailed Water Resources Yield
Model (WRYM) is essential for any Reserve study. It is the foundation upon which all other
conclusions and risk assessments related to the ecology is made. It was determined that the EWR
sites selected for the GRDS were located on small tributaries with small catchments which were not
covered in any existing yield model. Since all the scenarios for the study were highly dependent on
accurate hydrology, additional hydrological work was required and the yield model had to be refined
to accommodate the total study area as a system. The information required was critical for the
Reserve process to increase the study confidence and assist in informative decision making.
Further to this, additional hydrological modeling results were crucial information required for the
future upcoming Water Resource Classification Process. The advantage of this additional modelling
is not only a vital peace of information that will aid the upcoming Classification studies’ operational
scenario evaluation, but the complete yield model set up with the additions will be provided to the
DWS to be used in water resources and other related studies.
As a result of the above, a VO was submitted to the DWS on 30 January 2015 and approved by the
DWS on 8 May 2015. The VO and the approval thereof are included in Appendix A.3. This resulted
in the GRDS to be extended with six months from 24 months to 30 months up to 7 November 2015
and a budget increase of R 1 057 030.80 (VAT inclusive), i.e. an 8.53% increase.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-1
Study Closure Report
4 STUDY DELIVERABLES
4.1 STUDY PROGRAMME
The overall study programme was to a large extent determined by the schedule of activities of
the Technical Component. Due to the contractual delay experienced, the GRDS commenced
during winter 2013 instead of an envisaged earlier summer start. As a result the Technical
Component study programme had to be amended to cater for the seasonal variation. This
resulted in the Initiation and Design Phase to be longer than anticpated.
However, the different study phases were not entirely independent and could overlap with
each other, depending on the different technical approaches. Therefore, some Technical
Component Implementation Phase tasks already commenced in November/December 2013.
The initial study programme, providing for both the Project Management and Technical
Components, is included in Appendix B.
Although it was previously planned that the technical input would be completed by February
2015 with the study completion by May 2015, the seasonal delay variation, additional
hydrology work required as well as opposing opinions with regard to the groundwater aspects
caused the study to be delayed and extended to 7 November 2015.
On completion of the GRDS, it is clear that the six month extension was not sufficient to
finalise and wrap up the study. The general study delay and delay in review feedback caused
that most reports only be finalised during the Termination Stage. This again impacted on the
compilation and finalisation of the final study reports, such as the Monitoring, Main and Study
Closure Reports. Although these reports were submitted in draft format on or about 7
November 2015, the outstanding review thereof resulted in these reports to only be finalised
during December 2015.
In terms of similar type of studies cognisance should in future be taken of the time of
tendering, proposed study programme and contractual agreement finalisation, not causing the
kind of delays experienced during the commencement of the GRDS.
4.2 MILESTONES AND DELIVERABLES
The study scheduling, in terms of milestones and deliverables, was based on that of the of the
Technical Component programming.
Although study-related milestones and deliverables were set duirng the Initiation and Design
Phase, some challenges, as stated above, were experienced during study inception. Changes
in deadlines were, however, requested in October 2014 with a further scheduling was in May
2015. Final scheduling of deliverables took place during PMC Meeting No 5 on 4 August 2015.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-2
Study Closure Report
The revised associated milestones and deliverables are presented in Table 4.1. Q refers to
the relevant DWS yearly quarter of three months, i.e. Q1 refers to April to June, Q2 refers to
July to September, Q3 refers to October to December and Q4 refers to January to March. Q1-
13 would therefore refer to the quarter of April to June in 2013.
The deliverable deadlines presented in Table 4.1 are based on:
Project extension from 7 May 2015 to 7 November 2015.
DWS quarterly deliverables for internal auditing purposes.
Realistic and specific dates (as requested) for remaining meetings with DWS. This has
also taken into account the availability of the technical team to attend meetings. Note
that the PMC and PSC meetings planned for March 2015 were delayed by a couple of
months, and then fell over a period when the Technical Team Leader and other
members of the technical team were not available. The DWS was informed about this
delay and the subsequent consequences during the beginning of 2015.
The slow rate at which review comments have been provided to the Technical Team.
This includes comments from both the PMT and DWS. In general, the review process
was, however, subject to the availability of final draft reports. In the case of the DWS,
internal capacity challenges related to the technical availability of reviewers and the
complexity, number, and extent of report delays, review delays have been experienced
receiving comments, dealing with the comments and finalising reports.
Change in date for the delivery of the Monitoring Report, based on the final monitoring
objectives only being available once results have been presented to DWS (done on 11
September 2015) and final decisions have been made regarding the management of
water resources of the study area.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-3
Study Closure Report
Table 4.1: Integrated Study Milestones and Deliverables
Deliverables, Reports, Field Surveys, Workshops, Meetings
Date Q Requested
date change (October 2014)
Date undertaken
Deliverable comment
Study contractual commencement May 2013 Q1-13 7 May 2013
Initiation Meeting June 13 Q1-13 6 June 2013
Inception Report: Draft 1 September
2013 Q2-13
Draft September 2013; Final February
2014
Info for stakeholder engagement, e.g. Background Information Document (refer to Appendix C)
September/ October
2013 Q3-13
October 2013
PMC Meeting 1 October
2013 Q3-13
2 October 2013
Stakeholder Workshop 1 October
2013 Q3-13
3 October 2013
Prepare spreadsheet templates November/ December
2013 Q3-13
EcoSystem services input to Desktop EcoClassification December
2013 Q3-13
Water Resource Use Importance (WRUI) December
2013 Q313
Water quality, wetlands input to Desktop EcoClassification
December 2013
Q3-13
Estuary field survey December
2013 Q3-13
3 – 9 December
2013
Desktop EcoClassification (rivers) workshop January
2014 Q4-14
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-4
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops, Meetings
Date Q
Requested
date change
(October 2014)
Date undertaken
(refer to Table 6.1)
Deliverable comment
Reconnaissance river survey 1 January
2014 Q4-14
Reconnaissance river survey 2 February
2014 Q4-14
Results spreadsheets: Desktop EcoClassification February
2014 Q4-14
Groundwater Reserve hydrocensus and field survey March–May
2014
Q4-14/Q1-15
28 – 30 May 2014
PMC Meeting 2 March 2014 Q4-14 4 March
2014
Outputs from groundwater Rapid Reserve study: spreadsheet, short report & BHNR (groundwater)
March 2014 Q4-14
Desktop EcoClassification Report March 2014 Q4-14 Draft April
2014; Final July 2014
Delineation Report March 2014 Q4-14
Draft April 2014;
August/ September
2014
Report comprises two volumes
Training Workshop 1 (Overview and rivers) May 2014 Q1-14 30
September 2014
River Reserve survey 1: Winter rainfall area April 2014 Q1-14 8 – 12 April
2014
Liaison regarding scenarios June 2014 Q1-14
Completed templates: Desktop estuaries August 2014 Q2-14
Preparation of basic hydrology May - June
2014 Q1-14
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-5
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops,
Meetings Date Q
Requested
date change
(October 2014)
Date
undertaken
(refer to
Table 6.1)
Deliverable comment
BHNR (surface water) May - June
2014 Q1-14
River Reserve survey 2: Summer rainfall area June 2014 Q1-14 23 – 26 June
2014
SPATSIM preparation: rivers June 2014 Q1-14
Hydraulic look-up tables: rivers June 2014 Q1-14
PMC Meeting 3 July 2014 Q2-14 23 July 2014
PSC Meeting 1 July 2014 Q2-14 24 July 2014
Specialist Workshop 1: Rivers (Rapids) July 2014 Q2-14 28 July – 1
August 2014
Completed info templates & reports: Rapid Level
estuaries
October
2014 Q3-14
Groundwater Report August 2014 Q2-14 November 2014
(Q3-14)
1st Draft
December
2014; 2nd
Draft March
2015; 3rd
Draft May
2015; Final
November
2015
Report was subject to
extensive review by DWS,
External Reviewers (GEOSS
(Julian Conrad) and Delta-H)
and Umvoto Africa
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-6
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops,
Meetings Date Q
Requested
date change
(October 2014)
Date undertaken
(refer to
Table 6.1)
Deliverable comment
Set up and run scenarios through yield model June –
August 2014
Q1/Q2-
14
Completed river models: Rapid sites July 2014 Q2-14
Scenario workshop August 2014 Q2-14 24 August
2014
Wetland field survey: rapid assessment
August -
September
2014
Q2-14
November 2014
(Q3-14)
17 – 19
December
2014
Groundwater monitoring programme September
2014 Q2-14
January 2015
(Q4-14)
Completed as part of
Monitoring Report
PMC Meeting 4 September
2014 Q2-14
3 December
2014
PSC Meeting 2 September
2014 Q2-14
Postponed Took place on 5 August 2015
Completed river models: Intermediate sites September
2014 Q2-14
Specialist Workshop 2: Rivers (Intermediates)
September
2014 Q2-14
8 -12
September
2015
Training Workshop 2 (estuaries and wetlands) September
2014 Q2-14
1 October
2014
Wetland field survey: priority wetlands September
2014 Q2-14 November 2014
(Q3-14)
17 – 19
December
2014
Estuary workshop: Desktop / Rapid sites November
2014 Q3-14
17 – 21
November
2014
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-7
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops,
Meetings Date Q
Requested
date change
(October 2014)
Date undertaken
(refer to
Table 6.1)
Deliverable comment
Completed templates & specialist reports:
Rapid/Intermediate Level estuaries
November
2014 Q3-14
River input to Scenario Report
November
2014 Q3-14
May 2015
Wetlands Report
November
2014
Q3-14
January 2015
(Q4-14)
1st Draft April
2015, 2nd
Draft July
2015; Final
November
2015
General delay in terms of
report completion
PMC Meeting 5 November
2014 Q3-14
Postponed Took place on 4 August 2015
Estuary Report: Desktop assessment December
2014 Q3-14
Febraury
2015
EWR Report: Rapid sites, rivers December
2014 Q3-14
Draft May
2015; Final
Octoberr
2015
Groundwater meeting with DWS and Umvoto Africa January
2015 Q4-14
26 January
2015
Estuary workshop: Intermediate sites
January/
February
2015
Q4-14
16 – 29
January
2015
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-8
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops,
Meetings Date Q
Requested
date change
(October 2014)
Date undertaken
(refer to
Table 6.1)
Deliverable comment
Estuary Report: Rapid assessment January
2015 Q4-14
1st Draft
December
2014; 2nd
drfat
February
2015; Final
October/
November
2015
Report comprises two
volumes, i.e. one each for
the Klein Brak and
Wilderness estuaries
Economic consequences of scenarios: Input to
Scenario Report
January
2015 Q4-14
Not undertaken as there
were no river scenarios to
evaluate
Goods & Services consequences of scenarios: Input to
Scenario Report
January
2015 Q4-14
Not undertaken as there
were no river scenarios to
evaluate
Training Workshop (yield modelling, groundwater,
socio-economics)
January
2015 Q4-14
29 – 30
September
2015
PMC Meeting 6 January
2015 Q4-14
Postponed Took place on 15 October
2015
PSC Meeting 3
January
2015 Q4-14
Postponed Decided on 5 August 2015 to
have a joint PSM Meeting No
3 and Stakeholder Workshop
No 2 on 16 October 2015
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-9
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops,
Meetings Date Q
Requested
date change
(October 2014)
Date undertaken
(refer to
Table 6.1)
Deliverable comment
Scenario Report
January
2015 Q4-14
April 2015 (Q1-
15)
1st
Draft June
2015; 2nd
Draft
October
2015.
2nd
Draft submitted at end
October 2015 as final
deliverable subject to review
by DWS.
EcoSpecs, TPCs and qualitative statements: rivers January
2015 Q4-14
February 2015 End April
2015
Wetlands EcoSpecs January
2015 Q4-14
February 2015 July 2015
EWR Report: Intermediate sites, rivers February
2015 Q4-14
1st Draft May
2015; Final
October
2015
Presentation of results to DWS February
2015 Q4-14
11
September
2015
Agreed to presentation date
on 4 August 2015
Estuary Report: Intermediate assessment March 2015 Q4-14
1st Draft
Decmber
2014 &
February
2015; Final
October/
November 2015
Report comprises four
volumes, i.e. one each for
the Duiwenhoks, Goukou,
Gouritz and Keurbooms
estuaries
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-10
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops,
Meetings Date Q
Requested
date change
(October 2014)
Date
undertaken
(refer to
Table 6.1)
Deliverable comment
Monitoring Report March 2015 Q4-14
1st Draft
November
2015
This report has to follow the
Presentation of results to
DWS, as monitoring
recommendations have to
follow final decision-making;
subject to review by DWS.
PMC Meeting 7 March 2015 Q4-14 Not required Not required
Task inputs for Main Report April 2015 Q4-14 Throughout 2015
Main Report May 2015 Q1-15
1st Draft
November
2015
This report could only be
finalised and submitted at the
end of the study and once
the results have been
presented to DWS as final
recommendations are
included in the Main Report;
subject to review by DWS
PMC Meeting 8 May 2015 Q1-15 Did not take
place
Not required
PSC Meeting 4 May 2015 Q1-15 Did not take
place
Not required
Stakeholder Workshop 2 May 2015
Q1-15 16 October
2015
Agreed to date on 4 August
2015
Templates: Draft
May 2015 Q1-15 This deliverable is not
possible in time due to the
delays in meetings and
reviews.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-11
Study Closure Report
Deliverables, Reports, Field Surveys, Workshops,
Meetings Date Q
Requested
date change
(October 2014)
Date
undertaken
(refer to
Table 6.1)
Deliverable comment
Templates: Final
May 2015 Q1-15 This deliverable is not
possible due to the delays in
meetings and reviews.
Study Closure Report May 2015
Q1-15
1st Draft
November
2015
This report could only be
finalised and submitted at the
end of the study; subject to
review by DWS
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 4-12
Study Closure Report
4.3 STUDY REPORTS
The final list of reports compiled and produced for the GRDS is, together with the relevant index and
report numbers, summarized in Table 4.2:
Table 4.2: Final list of reports produced for the GRDS
INDEX NUMBER REPORT NUMBER REPORT TITLE
Report Number 01 RDM/WMA16/00/CON/0113 Inception Report
Report Number 02 RDM/WMA16/00/CON/0213 Desktop EcoClassification Report
Report Number 03, Volume 1 RDM/WMA16/00/CON/0313, Volume 1 Delineation Report, Volume 1 (Groundwater,
Estuaries and Wetlands)
Report Number 03, Volume 2 RDM/WMA16/00/CON/0313, Volume 2 Delineation Report, Volume 2 (Rivers)
Report Number 04 RDM/WMA16/02/CON/0413 Groundwater Report
Report Number 05 RDM/WMA16/03/CON/0513 Wetland Report
Report Number 06, Volume 1 RDM/WMA16/04/CON/0613, Volume 1 Estuaries RDM Report – Desktop Assessment
Report Number 06, Volume 2 RDM/WMA16/04/CON/0613, Volume 2 Estuaries RDM Report – Desktop Re-
evaluation of the 2008 EWR Study on the
Keurbooms Estuary
Report Number 07, Volume 1 RDM/WMA16/04/CON/0713, Volume 1 Estuaries RDM Report – Rapid Assessment,
Volume 1 (Klein Brak Estuary)
Report Number 07, Volume 2 RDM/WMA16/04/CON/0713, Volume 2 Estuaries RDM Report – Rapid Assessment,
Volume 2 (Wilderness System)
Report Number 08, Volume 1 RDM/WMA16/04/CON/0813, Volume 1 Estuaries RDM Report – Intermediate
Assessment, Volume 1 (Duiwenhoks Estuary)
Report Number 08, Volume 2 RDM/WMA16/04/CON/0813, Volume 2 Estuaries RDM Report – Intermediate
Assessment, Volume 2 (Gouritz Estuary)
Report Number 08, Volume 3 RDM/WMA16/04/CON/0813, Volume 3 Estuaries RDM Report – Intermediate
Assessment, Volume 3 (Goukou Estuary)
Report Number 09 RDM/WMA16/00/CON/0913 Scenario Report
Report Number 10 RDM/WMA16/01/CON/1013 Rivers RDM Report – Intermediate
Assessment
Report Number 11 RDM/WMA16/01/CON/1113 Rivers RDM Report – Rapid Assessment
Report Number 12 RDM/WMA16/00/CON/1213 Monitoring Report
Report Number 13 RDM/WMA16/00/CON/1313 Main Report
Report Number 14 RDM/WMA16/00/CON/1413 Study Closure Report
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 5-13
Study Closure Report
5 STUDY MEETINGS AND WORKSHOPS
5.1 STUDY INITIATION MEETINGS
As indicated in Section 2.2.1, an initial Project Inception Scoping Meeting took place at the DWS
Offices, Pretoria, on 3 May 2012. Subsequent to the finalization of the contractual agreement
between the DWS and AECOM, and with the official study commencement date as 7 May 2013, a
Project Initiation Meeting took place on 6 June 2013 at the AECOM Offices, Bellville. The minutes of
both meetings are included in Appendix D.
5.2 PMC MEETINGS
Nine (9) PMC meetings were originally envisaged. In addition to the Study Initiation Meeting of 6
Jnue 2013, seven (7) further PMC meetings, including a special PMC meeting during which the
study results were presented to the DWS, took place during the study.
A summary of the PMC meetings in terms of date and venue is provided in Table 5.1, while copies
of the relevant meeting minutes are included in Appendix E.
Table 5.1: Summary of PMC meetings
PMC Meeting No Date of Meeting Meeting Venue
Meeting 1 2 October 2013 Pearl of Oudsthoorn Hotel, Oudtshoorn
Meeting 2 4 March 2014 Main Boardroom, AECOM Offices, Bellville
Meeting 3 23 July 2014 Boardroom, DWS Regional Offices,
George
Meeting 4 3 December 2014 Main Boardroom, AECOM Offices, Bellville
Meeting 5 4 August 2015 Protea King George Hotel, George
Special Meeting 11 September 2015 Emanzini Room 335, DWS Head Offices,
Pretoria
Meeting 6 15 October 2015 Hotel Wilderness, Wilderness
PMC meeting attendance was earmarked by irregular attendance by PMC members. Although the
meetings were attended by the core PMC members, some of the PMC members indicated in Table
2.1. only attended selective meetings, whilst other identified PMC members did not attend any
meetings at all.
Although the intention was to have PMC meetings at specific study milestone dates, challenges
were experienced around this, amongst other, the availability of PMC members to meet on targeted
dates. This resulted in prolonged periods between the sequential PMC meetings, which in turn
resulted in its own set of challenges. It was identified that an additional meeting between PMC
Meetings 4 (December 2014) and 5 (August 2015), which was eight months apart, for instance
would have aided in providing guidance on intervention actions to get the study on track again. In
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 5-14
Study Closure Report
this regard it is to be noted that a PMC meeting was originally planned for March 2015 but was
delayed due to the unavailability of DWS officials, and then postponed for a period when the
Technical Team Leader and other members of the technical team were not available.
5.3 PSC MEETINGS
It was originally planned envisaged that there will be in the order of four (4) to five (5) PSC
meetings, with the intention that the PSC meetings follow the PMC meetings on the same or
following day. However, only three PSC meetings took place during the study. In addition, and
based on time limitations and associated cost savings, PSC Meeting 3 and Stakeholder Workshop 2
were held jointly.
A summary of the PSC meetings in terms of date and venue is provided in Table 5.2, while copies
of the relevant meeting minutes of PSC Meetings 1 and 2 are included in Appendix F. Minutes of
PSC Meeting 3 was compiled as Stakeholder Workshop minutes and is included in Appendix H.
Table 5.2: Summary of PSC meetings
PSC Meeting No Date of Meeting Meeting Venue
Meeting 1 24 July 2014 Protea King George Hotel, George
Meeting 2 5 August 2015 Protea King George Hotel, George
Meeting (jointly with
Stakheholder Workshop 2)
16 October 2015 Hotel Wilderness, Wilderness
PSC meeting attendance was earmarked by poor attendance and participation by local authorities
and government and/or semi-government institutions other than DWS. As a result the PSC
meetings was predominantly attended by DWS representatives (refer to attendance list as per the
relevant meeting minutes included in Appendix F). Considering the proposed PSC composition as
indicated in Table 2.2, the attendance of PSC meetings by a wider representative grouping would
aided specific challenges experienced during the study. Such missing interest and involvement is a
concern. It needs to be indicated that the two dedicated PSC meetings were not attended by
organisations such as SANParks, DAFF, DAWC and specific local authorities. Given the local
issues raised by stakeholders, i.e. the lack of attendance by key stakeholders, has resulted in
conflicts, related to specific areas such as Swartvlei, Lemoenshoek and the Keurbooms and Bitou
Reserve study results,to mention but a few. Hence, instead of identifying these and similar issues
early in the study and providing opportunity for discussions around possible solutions, it resulted in
ministerials and various complaints addressed to the DWS, causing PSPs to address specific issues
outside the scope of the study, leading to low confidence desktop results and confrontation with
stakeholders instead of consultation as intended with the stakeholder process.
As for the originally planned March 2015 PMC meeting, it is to be noted that the PSC meeting
planned for March 2015 was delayed similarly as the PMC meeting.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 5-15
Study Closure Report
5.4 STAKEHOLDER WORKSHOPS
Stakeholder participation is discussed in Section 7. However, a summary of stakeholder workshops
in terms of date and venue is provided in Table 5.3. Copies of the relevant meeting minutes are
included in Appendix H.
Table 5.3: Summary of Stakeholder Workshops
Stakeholder Workshop Date of Meeting Meeting Venue
Workshop 1 3 October 2014 Pearl of Oudsthoorn Hotel, Oudtshoorn
Workshop 2 16 October 2015 Hotel Wilderness, Wilderness
5.5 TECHNICAL MEETINGS/ WORKSHOPS
Various Technical Component meetings/workshops were conducted. A summary of these meetings
in terms of type, date, venue and an indication of available minutes are provided in Table 5.4.
Table 5.4: Summary of technical meetings/workshops
Meeting/Workshop
Description
Date of
Meeting/Workshop
Meeting/Workshop
Venue
Comments
Wetlands Meeting 7 August 2013
Room 440, DWS
Regional Offices,
Bellville
Refer to Wetlands
Report for
minutes
Desktop
EcoClassification
Workshop (Rivers)
January 2014 Pearly Beach
Groundwater Meeting
with Umvoto Africa and
Oudtshoorn Municipality
16 January 2014 Umvoto Africa
Offices, Muizenberg
Unofficial notes
on discussion are
available
Hydrology and Yield
Modelling Requirements
Meeting
19 June 2014
Pretoria
River Specialist
Workshop 1: Rapid Sites
28 July – 1 August
2014 East London
Scenario Meeting
24 August 2014 Main Boardroom,
AECOM Offices,
Bellville
Groundwater/Wetlands
Meeting
26 August 2014 Pretoria
Unofficial notes
are available
River Specialist
Workshop 2:
Intermediate Sites
8 – 12 September
2014 East London
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 5-16
Study Closure Report
Meeting/Workshop
Description
Date of
Meeting/Workshop
Meeting/Workshop
Venue
Comments
Estuary Specialist
Workshop 1
17 – 21 November
2014 CSIR, Stellenbosch
Estuary Specialist
Workshop 2
16 – 29 January
2015 CSIR, Stellenbosch
Groundwater Specialist
Meeting with Umvoto
Africa and DWS
26 January 2015 DWS Regional
Offices, Bellville
Unofficial
memoranda, etc.
are available
Preparation of EcoSpecs 20 - 24 April 2015 Pearly Beach
Preparation of Main
Report
13 – 15 October
2015 Pearly Beach
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 6-1
Study Closure Report
6 STUDY MONITORING AND REPORTING
6.1 OVERALL PERFORMANCE
The main function of the PMT was to direct and co-ordinate the efforts of the Technical
Component, both pro-actively and reactively, on a daily basis with a specific focus on
delivering decision support information to the DWS. Based on that, the GRDS was
managed to ensure that all objectives are achived on time, within budget and as per the
stipulated briefs. As a result standard protocols such as project status and progress reports
to monitor progress and to ensure that required deliverables are provided were introduced.
This, however, did not detract from the responsibility of the Technical Team to manage the
activities within their assignment.
In addition, regular communication between the PMT and the Technical Team as well as
with the DWS ensured continuous progress feedback.
6.2 PERFORMANCE MONITORING
Performance monitoring and reporting during the GRDS was based on four components,
i.e. monthly progress and status reports, feedback at PMC/PSC meetings and study
reporting. Each of these is briefly discussed below:
6.2.1 Progress reporting
The intention at Inception Stage was that detailed progress reports, with the purpose of
reporting to the PMC, had to be submitted to the PMC two weeks prior to each PMC
meeting. However, based on a request from DWS during PMC Meeting No 2, this approach
changed due to an internal DWS request by the Deputy Director General for monthly
reports. As a result, brief progress reports in e-mail format for each of the Project
Management and Technical Components were submitted to the DWS Project Coordinator
on a monthly basis, accompanying the monthly invoices. These progress reports basically
summarised the activities undertaken during the period of invoicing.
In addition to the above-mentioned monthly progress reporting, monthly project status
reporting was introduced for auditing purposes of interim payment claims compared with
task related progress. This reporting was submitted as part of the monthly invoice
submission to the DWS and provided an indication of work done, progress and percentage
completed, fees claimed and HDI participation related to a specific task for which a
payment claim was submitted.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 6-2
Study Closure Report
Furthermore four detail progress feedback reports were submitted during the study to the
DWS. Integrated progress reports were submitted in November 2013, February 2014 and
December 2014 whilst a technical progress report was submitted in July 2015.
6.2.2 Feedback at PMC/PSC meetings
6.2.2.1 Presentations at meetings
Each of the six PMC meetings held during the study included progress feedback in terms of
both the Project Management and Technical Components in the form of presentations. The
Project Management Component primarily concentrated on administrative and financial
matters, while technical progress feedback on the Technical Component was discussed in
detail. The latter not only included progress feedback, but also covered discussions on
matters in question and the associated way forward.
Feedback at the two PSC meetings primarily concentrated on the Technical Component
progress and findings. The aim was also to obtain feedback from stakeholder concerns and
recommendations with specific reference to potential water resource developments,
resources that require priority protection as well as measures for coordinating management
efforts to potect and manage water resources.
6.2.2.2 Actions and Decisions Register
The control of all action items discussed and decisions taken at PMC/PSC meetings during
the Initiation and Design Phase as well as Implementation Phase was considered to be of
utmost importance. As susch, action items and decisions resulting from PMC Meetings No
1 to 5 and PSC Meetings 1 and 2 were recorded in an Actions and Decisions Register. The
purpose of such a register was to keep record of all decisions taken and follow up on the
progress on any outstanding action items. A copy of this Actions and Decisions Register is
included in Appendix G.
It is to be noted that, although most of the listed actions and decisions refer to the GRDS,
there are some which either refer to another process outside the scope of, or could not be
addressed during the GRDS.
6.2.3 Study reporting
Various project reports, representing the work undertaken and completed, were produced
during the course of the GRDS. The main reports regarded as study deliverables were
determined in consultation with the DWS during the Initiation and Design Phase, followed
by minor adjustments, such as the introduction of reporting volumes, etc.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 6-3
Study Closure Report
Report standards related to report numbering, report format, report references and a report
review mechanism that was set in consultation with the DWS. Relevant study related report
numbers were confirmed with the DWS.
A summary of these reports are provided in Table 4.2.
6.2.4 Report reviewing
Except for the Inception and Study Closure Reports, the Technical Team was responsible
for the integrated compilation of technical reports, subject to input by specialists. In terms
of monitoring, the draft study reports were reviewed by the PMT, External Reviewers and
the PMC/DWS. Although the original intention was that the draft technical reports were
subject to a single parallel round of review of comments by the PMT, Specialist External
Reviewers, PMC/DWS, feedback on the review process was diversive and took much
longer than anticpated. As a result, various versions of the reports were compiled and it
took much longer than anticipated to finalise the study reports. As such, each report
contains a report schedule indicating the various versions and date of compilation.
In addition to the review by the PMT and the DWS, external specialist review (refer to Table
2.3) of the Technical Component reporting was undertaken as follows:
Groundwater Report
External specialist review by Julian Conrad from GEOSS and Prof Kai Whiithueser
of Delta-H Water Systems Modelling
Additional external review by Umvoto Africa
Wetlands Report
External specialist review by Dr Justine Ewart-Smith from The Freshwater
Consulting Group
Estuaries Reports
External specialist review by Dr Angus Paterson from SAIAB
Rivers Reports
External specialist review by Dr Cate Brown from Southern Waters Ecological
Research
A summarised overview of the report review, including the review by the PMT, Specialist
External Reviewers as well as the DWS, and completion process is provided in Table 6.1
below:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 6-4
Study Closure Report
Table 6.1: Compilation and review process of study reports
Report No.
Report number Report title Date of 1st Draft
Date of 2nd Draft
Date of 3rd Draft
Date Finalised
Comments
1 RDM/WMA16/00/CON/0113 Inception Report September 2013
February 2014
April 2014
2 RDM/WMA16/00/CON/0213 Desktop EcoClassification Report
April 2014 July 2014 July 2014 Report available on DWS & GRDS website
3 RDM/WMA16/00/CON/0313 Delineation Report
Volume 1 April 2014 May 20144 August 2014
Report available on DWS & GRDS website
Volume 2 April 2014 September 2014
September 2014
Report available on DWS & GRDS website
4 RDM/WMA16/02/CON/0413 Groundwater Report December 2014
March 2015 May 2015 November 2015
Final comments received from DWS, Julian Conrad, Umvoto Africa & Kai Whitthuesser incorporated.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 6-5
Study Closure Report
Report No.
Report number Report title Date of 1st Draft
Date of 2nd Draft
Date of 3rd Draft
Date Finalised
Comments
5 RDM/WMA16/03/CON/0513 Wetlands Report Incomplete draft: April 2015
July 2015 November 2015
Report available on DWS & GRDS website
6 RDM/WMA16/04/CON/0613 Estuaries RDM Report – Desktop assessment
February 2015
October/ November 2015
Reports available on DWS & GRDS website
7 RDM/WMA16/04/CON/0713 Estuaries RDM Report – Rapid assessment
Klein Brak December 2014
February 2015
Wilderness
December 2014
February 2015
8 RDM/WMA16/04/CON/0813
Estuaries RDM Report – Intermediate assessment
Duiwenhoks December 2014
February 2015
Goukou February 2015
Gouritz February 2015
Keurbooms Estuary: Professional Opinion and Re-assessment of 2008 Rapid Reserve
February 2015
9 RDM/WMA16/00/CON/0913 Scenario Report June 2015 October 2015
Report available on DWS & GRDS website
10 RDM/WMA16/01/CON/1013 Rivers RDM Report – Intermediate assessment
May 2015
October 2015
Report available on DWS & GRDS website
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 6-6
Study Closure Report
Report No.
Report number Report title Date of 1st Draft
Date of 2nd Draft
Date of 3rd Draft
Date Finalised
Comments
11 RDM/WMA16/01/CON/1113 EWR Report - Rapid assessment
December 2014
May 2015 September 2015
Report available on DWS & GRDS website
12 RDM/WMA16/00/CON/1213 Monitoring Report November 2015
December 2015
Report available on DWS & GRDS website
13 RDM/WMA16/00/CON/1313 Main Report November 2015
December 2015
Report available on DWS & GRDS website
14 RDM/WMA16/00/CON/1413 Study Closure Report November 2015
December 2015
Report available on DWS & GRDS website
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 7-1
Study Closure Report
7 STAKEHOLDER PARTICIPATION
7.1 STAKEHOLDER AWARENESS
The ToR required that the GRDS include limited public awareness activities. Specific reference was
made to a stakeholder meeting during the Implementation Phase so as to involve stakeholders from
the beginning of the study. However, experience gained during the ORDS indicated that an
extended stakeholder participation is more appropriate. As a result two Stakeholder Workshops
were proposed for the GRDS (refer to Section 7.4).
Given the extended GRDS stakeholder particpation programme, Milkwood Communications was
included as part of the PMT during the Initiation and Design Phase to assist with stakeholder
activities.
The PMT assisted with the following during the Study Initiation and Design Phase:
Stakeholder identification;
Compilation and distribution of a BID;
Organisation of the Initial Stakeholder Workshop; and
Compilation of an Issues/Comments and Response Register.
Stakeholder participation during the Implementation Stage was limited to responses to queries,
progress update and maintenance of the Issues/Comments and Response Register. The
Termination Stage included a further newsletter and a final stakeholder workshop.
More detail related to the stakeholder activities are provided below: 7.2 IDENTIFICATION OF STAKEHOLDERS
Milkwood Communications updated the ORDS stakeholder database with input from the DWS,
AECOM and SC&A as well as other databases relevant to previous Gouritz WMA related studies. In
addition, members of the public and other potential stakeholders not identified yet were given
opportunity via advertisements placed in various newspapers to register as official stakeholders in
the GRDS in order to be able to receive study related information.
A detail stakeholder list is included in Appendix H.
7.3 COMMUNICATION WITH STAKEHOLDERS
7.3.1 Background Information Document
In consultation with AECOM and SCA, Milkwood Communications compiled and distributed a BID in
October 2013, providing the background and purpose as well as the time frame of the study,
explaining the sudy components and introducing the team to be involved. The BID also provided
DWS and PSP contact details where further study related enquires could be made explaining the
basics of the study. This was distributed to identified stakeholders to enlighten them of what is
underway with respect to the GRDS and inform them of the way forward. A copy of the BID bid is
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 7-2
Study Closure Report
included in Appendix C.
7.3.2 Stakeholder Newsletters
Two newsletters were compiled by the study team and distributed to stakeholders.
The aim of the first newsletter during November 2013 was to inform stakeholders of the GRDS
scenarios to be considered during the operational and scenario phase. The ecological implications
of applying those scenarios will be briefly discussed in the newsletter. The primary objective of the
newsletter, however, is to discuss the recommended scenarios for future management strategies
with the DWS as the client and custodian for the Reserve study.
The aim of the second newsletter of October 2015 was to provided stakeholders of an overview of
the results of the GRDS to be discussed at the second stakeholder workshop.
Copies of the two stakeholder newsletters are included in Appendix H.
7.4 STAKEHOLDER WORKSHOPS
Two Stakeholder Workshops were held during the GRDS. The intention of these workshops was to
gain stakeholder input durng the Initiation and Design Phase and to present the study results and
obtain stakeholder buy-in by the time the Termination Stage has been reached.
7.4.1 Stakeholder Workshop 1
The first Stakeholder Workshop took place on 3 October 2013 in Oudtshoorn. The purpose of the
workshop was to introduce the GRDS to stakeholders, provide background on the study area,
explain the process, discuss the study approach and to obtain input and comments from
stakeholders that will aid the GRDS, especially related to the development of realistic scenarios,
needed as vital input to the system hydrological and yield modelling and assessing the ecological
consequences on the Present Ecological State (PES) of water resources and associated future
development
Stakeholders included on the provisional stakeholder list were initially invited to the workshop by e-
mail on 5 September 2013. In addition, further invitations were sent to those stakeholders who
registered in response to newspaper advertisements. As a result 80 delegates attended Stakeholder
Workshop 1.
The Attendance Register and Minutes of the Stakeholder Workshop 1 are included in Appendix H.
7.4.2 Stakeholder Workshop 2
The second Stakeholder Workshop was initially planned for May 2015. However, due to the study
delay and resulting extension, the second Stakeholder Workshop took place during the Termination.
Phase. It was decided during PSC Meeting No 2 on 5 August 2015 that the last Stakeholder
Workshop and PSC Meeting 3 will be a joint event on 16 October 2015 at Wilderness. During this
workshop the various scenarios and ecological consequences were presented to the stakeholders
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 7-3
Study Closure Report
present, with their feedback and comments discussed and documented.
Stakeholder Workshop 2 was attended by about 75 delegates.The Attendance Register and
Minutes of the Stakeholder Workshop No 2 is included in Appendix H.
7.5 ISSUES/COMMENTS AND RESPONSE REGISTER
In response to the initial Stakeholder Workshop, an Issues/Comments and Response Register was
compiled and regularly updated to monitor enquiries and feedbacks. A copy of this
Issues/Comments and Response Register is included in Appendix H.
7.6 IMPROVED STAKEHOLDER INVOLVEMENT
The stakeholders living within the study area possessed a wealth of knowledge of the area, its
attributes, water resources and also engineering specifications required. These stakeholders should
have been more actively involved through having a representative from each or the towns located
within the study area or through more regular workshopping with the respective stakeholders and
the distribution of both minutes and reports to these stakeholders.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 8-1
Study Closure Report
8 TRAINING AND CAPACITY BUILDING
Training and capacity building building is discussed in detail in the GRDS Main Report, Appendix A
(DWS, 2015b). This includes an overview of the GRDS training and capacity building opportunities,
the attendance thereof as well as feedback from trainees.
A brief overview on training opportunities is provided below:
8.1 BACKGROUND
Although defined as study objective in the ToR, the budgetary constraints imposed by the project
did not allow for sufficient training opportunities. Training is therefore included as the participation of
DWS trainees in workshops and field trips and specific training opportunities as identified per Table
3.2, Task U.
All training opportunities presented focussed on DWS personnel from both the Head Office and WC
Regional Office. In addition, PSP trainees also attended workshops and field surveys, but did so at
their own cost.
Information sharing was also provided by circulating progress reports and extending invitations to
attend meetings and workshops to the DWS WC Regional Office (RO) and the DWS CD: WE
Project Coordinator (Ms Machaba). Ms Machaba coordinated training events for DWS
representatives in liaison with Dr Scherman and Ms Wilna Kloppers and Dr Andrew Gordon from
DWS WC.
8.2 IDENTIFIED DWS TRAINEES: 2013
At the GRDS Inception Stage the DWS personnel as indicated in Table 8.1 were identified as
potential trainees per water resource (refer to Inception Report; DWS, 2014):
Table 8.1: Potential DWS trainees identified at Inception Stage
Water source Identified trainee
Rivers
Thapelo Machaba
Happy Maleme
Vuledzani Muthelo
Gladys Makhado
Estuaries
Thapelo Machaba
Happy Maleme
Gladys Makhado
Vuledzani Muthelo
Wetlands Vuledzani Muthelo
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 8-2
Study Closure Report
Water source Identified trainee
Gladys Makhado
Happy Maleme
Groundwater
Lawrence Maluleke
Netshiendeulu Ndivhuwo
Khoza Philani
Kutama Rotondwa
Tichatonga Gonah
8.3 TRAINING OPPORTUNITIES
Training and capacity building opportunities provided during the GRDS and attendance thereof are
summarised in Table 8.1. Agendas for the training workshops are included in the Main Report,
Appendix A (DWS, 2015b).
Table 8.2: Training and capacity building opportunities
Opportunity Description Date Attendance
Estuaries
Estuary field survey:
Goukou, Duiwenhoks, Gouritz, Klein
Brak, Wilderness, Keurbooms
3 – 9 December
2013
DWS: Gladys Makhado, Happy
Maleme, Thapelo Machaba, Nolu
Jafta
Other attendees:Nompumelelo
Thwala (DEA), Alexis Olds
(CapeNature), Corne Erasmus,
Carlo Williamson (DAFF)
Estuary Specialist Workshop 1:
Duiwenhoks, Klein Brak,
Touw/Wilderness, Hartenbos, Blinde,
Groot, Piesang, Bloukrans
7 – 21 November
2014
DWS: Gladys Makhado, Happy
Maleme, Thapelo Machaba, Nolu
Jafta, Esther Lekalake, Gerhard
Cilliers, Sibusiso Majola
Other attendees:Nompumelelo
Opportunity Description Date Attendance
Thwala (DEA), Alexis Olds
(CapeNature), Corne Erasmus,
(DAFF), Chantal Petersen,
Christo Rautenbach, Hellen Mpe,
Janine & Marileen (interns)
(CSIR)
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 8-3
Study Closure Report
Estuary Specialist Workshop 2:
Goukou, Gouritz, Keurbooms,
EcoSpecs and monitoring
16 – 29 January
2015
DWS: Gerhard Cilliers, Sibusiso
Majola, Nolu Jafta, Wina
Kloppers, Thembela Bushula,
Pumza Buwa
Other attendees:Jean du
Plessis, Alexis Olds
(CapeNature), Chantal Petersen
(CSIR), Angus Paterson (SAIAB:
Specialist Advisor/External
Reviewer), Jill Slinger (TU Delft)
Rivers
Rivers field survey 1:
Gouritz, Doring, Touws, Buffels,
Gamka
8 – 12 April 2014
DWS: Thembela Bushula,
Andrew Gordon, Earl Herdien,
Fezile Daniel, Caroline Tlowana,
Gladys Makhado,Gloria Muthelo,
Happy Maleme, Thapelo
Machaba
Rivers field survey 2:
Duiwenhoks, Kammanassie,
Goukou, Olifants, Keurbooms
23 – 26 June 2014
DWS: Thembela Bushula,
Andrew Gordon, Gladys
Makhado,Gloria Muthelo, Happy
Maleme, Thapelo Machaba
Other attendees: Khaya Mgaba,
Nkosinathi Mazangula (IRW,
Rhodes University)
River Specialist Workshop 1:
Rapid Sites – Duiwenhoks, Doring,
Goukou, Kammanassie
28 July – 1 August
2014
DWS: Thembela Bushula,
Andrew Gordon
Other attendees: Khaya Mgaba,
Nkosinathi Mazangula (IRW,
Rhodes University)
River Specialist Workshop 2:
Intermediate Sites – Touws, Buffels,
Gamka, Gouritz, Keurbooms
8 – 12 September
2014 DWS: Thembela Bushula,
Andrew Gordon
Opportunity Description Date Attendance
Groundwater
Goundwater field survey 28 – 30 May 2014 DWS: Manelisi Ndima, Netshiendeulu
Ndivhuywo, Philani Khoza
Wetlands
Wetlands field survey 17 – 19 December
2014
DWS: Manelisi Ndima, Vuledzani
Muthelo, Shaddai Daniels
Specific training
Workshop 1:
Overview and River Reserve
30 September 2014 DWS:
Resource Protection: Thembela
Bushula, Bentley Engelbrecht,
Graeme Williams, Poppy Bhele,
Shaddai Daniels, Andrew
Gordon, Pumza Buwa, Rafieka
Workshop 2:
Estuary and Wetland Reserve
1 October 2014
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 8-4
Study Closure Report
Johaar, Earl Herdien, Searle
Korasie, Fezile Daniel, Richard
Phaiphai, Bheki Cele, Wilna
Kloppers
Berg Section:
Bonelwa Mabowu, Nkosinathi
Mkonto, Tshiliszi Mnavhela,
Hester Lyons
Geo-Hydrology: Vuyi Tumana
BGCMA: Zama Mbunquka
CD :WE (SWRR): Thapelo
Machaba
Workshop 3:
Groundwater, Economics and Yield
Modelling
29 - 30 September
2015
DWS: Phlani Khoza; Manelisi
Ndima, Nwabisa Makiwane,
Ntsoakaleng Nakin, Vuyoazi
Jezile, Ashton van Niekerk,
Fezile Daniel, Pumza Buwa,
Imelda Haines, Mzukhisi
Naqhamza, Bentley Engelbrecht,
Bulelani Rolinyathi, Bheki Cele,
Grant Williams, Richard
Phaiphai, Thembela Bushula,
Andrew Gordon, Nancy Motebe,
Esther Lekalake, Mike Smart,
Thapelo Machaba, Nomvuyiseko
Tumara, Bonelwa Mabovu,
Busiswa Matyou, Mashiedu
Mushovi
8.4 FEEDBACK FROM DWS TRAINEES
Main gaps identified by DWS trainees during the feedback regarding the training provided include:
No proper training programme was in place, thus it was difficult to measure the effectiveness
of the training provided.
No proper direction from the DWS on the requirements for the capacity building and skills
transfer.
No specific tasks given to the trainees and this makes the trainees move from one activity to
the other without building a proper skill. Other trainees then appear sluggish and show a lack
of interest during the site survey.
No sufficient time during the field surveys to train DWS personnel on how to use the
instruments and no proper explanation on the methodology used for assessments during the
site surveys. This contributed to the minimal skills transfer.
PSPs were concerned about their time schedule and meeting the deadlines, thus not paying
attention to the trainees and this also contributed to minimal capacity building.
Due to budget constrains within the DWS, the personnel were not able to attend the full
activities as planned. There was no continuation of the training.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 9-1
Study Closure Report
9 FINANCIAL MANAGEMENT
9.1 APPROVED STUDY BUDGET
9.1.1 Original study budget
The original approved GRDS budget, Value Added Tax (VAT) inclusive, is indicated in Table 9.1.
Table 9.1: Original approved study budget
Study Component VO Budget
(R – VAT inclusive) % of Budget
Project Management 3 689 427.60 29.8
Technical 8 698 815.60 70.2
Total 12 388 243.20 100.0
9.1.2 Variation order
In addition to the original approved study budget, a single VO was approved by the DWS on 7 May
2015. As discussed in Section 3.4, this VO related to both additional work and an extension of time.
A breakdown of the VO budget allocation, Value Added Tax (VAT) inclusive, is indicated in Table
9.2:
Table 9.2: Approved VO budget
Study Component Approved Budget
(R – VAT inclusive) % of Budget
Project Management 803 950.80¹ 76.06
Technical 253 080.00 23.94
Total 1 057 030.80 100.0
¹Including hydrology and yield modelling done by AECOM for Technical Component
The approved VO budget of R 1 057 030.80 (VAT inclusive) respresents an increase of 8.53% of
the originally approved study budget.
9.1.3 Revised study budget
Given the approved original budget and VO, as discussed in Sections 9.1.1 and 9.1.2, respectively,
the revised study budget is summarised in Table 9.3:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 9-2
Study Closure Report
Table 9.3: Revised study budget
Study Component Revised Approved Budget
(R – VAT inclusive) % of Approved Budget
Project Management 4 493 378.40 33.42
Original 3 689 427.60
29.8
VO 803 950.80 76.06
Technical 8 951 895.60 66.58
Original 8 698 815.60
70.2
VO 253 080.00 23.94
Total 13 445 274.00 100 100
In addition to the above-mentioned differentiation between the Project Management and Technical
Components’ budgets, a further R 132 787.80 (VAT inclusive) was transferred from the Project
Management Component budget to that of the Technical Component, with the primary aim to
financially assist with the additional groundwater work undertaken due to the various rounds of
review, including discussions with Umvoto Africa (refer to Sections 10.1. and 5.4.2). As a result the
final budget distribution is provided in Table 9.4.
Table 9.4: Study budget distribution
Study Component Revised Approved Budget
(R – VAT inclusive) % of Approved Budget
Project Management 4 360 590.60 32.43
Original 3 689 427.60
29.8
VO 671 072.00 63.49
Technical 9 084 774.40 67.57
Original 8 698 815.60
70.2
VO 253 080.00
36.51 Transfer from
Project
Management
Component
132 878.80
Total 13 445 274.00 100 100
9.2 DETAIL OF STUDY BUDGET
The financial management of the GRDS was based on a detail task breakdown. The detail
breakdown of the revised study budget, covering both the Project Management and Technical
Components, and based on the defined study tasks, is included in Appendix I.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 9-3
Study Closure Report
9.3 INVOICING
9.3.1 Invoicing procedure
Study invoicing was aimed at monthly submissions to the DWS, based on the following procedure:
The Technical Component and Specialist Reviewers, submitted, as applicable, monthly
invoices to the PMT;
Invoicing for work done in a specific month was preferably to be done at the end of the same
nth to reach the PMT by no later than the 7th of the following month;
Invoices received by the PMT were checked for confirmation that the costs incurred were
realistic in relation to the work done;
All claims for disbursements were verified against proof provided. Records of all
disbursements were attached to the monthly invoices;
Invoices were then forwarded to the DWS Project Coordinator for checking, certification and
payment approval, and
All monthly invoices were supported by monthly status reports (refer to Section 6.2.2).
9.3.2 Invoicing per task
Monthly invoices submitted were detailed in accordance with the study task breakdown. The detail of the study breakdown is provided in Appendix I. Monthly invoices also contained a status report summary as indicated in Appendix I, whereby information was provided in terms the original allocated task budget, invoicing per task, HDI expenditure per task, over/under-spending per task, etc. 9.3.3 Summary of project invoicing
A summary of the monthly study invoicing and payments received is provided in Table 9.5:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 9-4
Study Closure Report
Table 9.5: Summary of study monthly invoicing record
Invoice no.
Submission date Period covered Amount invoiced
(VAT inclusive) Date paid
1 12 November 2013 Up to 1 November 2013 R 936 133.22 20 December 2013
2 6 February 2014
2 November 2013 -
31 January 2014 R 569 423.00 12 March 2014
3 15 February 2014 31 January - 7 February2014 R 447 134.54 12 March 2014
4 28 February 2014 8 - 21 February 2014 R 355 195.24 24 March 2014
5 25 April 2014 22 February - 18 April 2014 R 224 579.08 10 June 2014
6 22 May 2014 18 April - 22 May 2014 R 359 630.61 1 July 2014
7 17 June 2014 22 May - 13 June 2014 R 675 799.95 30 July 2014
8 11 July 2014 14 June - 11 July 2014 R 317 391.13 22 August 2014
9 29 August 2014 12 July - 19 August 2014 R 705 771.87 29 September 2014
10 8 September 2014 20 August - 5 September 2014 R 574 820.44 13 October 2014
11 27 October 2014 5 September - 27 October 2014 R 790 918.70 12 November 2014
12 21 November 2014 28 October - 21 November 2014 R 502 921.10 22 December 2014
13 9 December 2014 21 November - 9 December 2014 R 847 652.65 20 January 2015
14 17 February 2015 10 December - 4 February 2015 R 845 396.46 10 March 2015
15 11 March 2015 5 February - 06 March 2015 R 1 141 473.21 31 March 2015
16 13 April 2015 7 March 2015 - 08 Apr 2015 R 126 803.91 8 May 2015
17 19 May 2015 09 Apr - 08 May 2015 R 320 797.39 29 June 2015
18 2 July 2015 09 May - 05 Jun 2015 R 142 259.65 17 August 2015
19 24 July 2015 08 Jun - 10 Jul 2015 R 164 302.50 2 September 2015
20 31 August 2015 13 July -21 August 2015 R 379 318.10 23 September 2015
21 28 September 2015 21 August - 18 September 2015 R 617 781.92 21 October 2015
22 23 October15 20 September - 16 October 2015 R 1 633 235.10 3 December 2015
23 5 November 2015 19 - 30 October 2015 R 442 161.97 30 November 2015
24 6 November 2015 2 - 6 November 2015 R 324 136.20 3 December 2015
Total R 13 445 037.94
9.4 CASHFLOW
Based on the amended study programme at Study Initiation and Design Phase (refer to Appendix
C), a provisonal cashflow for study financial management comparison purposes was included in the
GRDS Inception Report.
However, although the study has officially commenced in May 2013, the study programme was
delayed as discussed in Sections 2.2 and 4.1, with contractual agreements between the various
service providers to be agreed to, resulting in the actual technical work only to start later. As a result
the first invoice was only submitted in November 2013, with an immediate impact on the study
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 9-5
Study Closure Report
cashflow projection.
Due to the impact of the December 2013/January 2014 and December 2014/January 2015 holiday
breaks, no invoices were submitted for December 2013 and January 2015.
A summary of the actual study cashflow, based on invoicing and payment received, is provided in
Table 9.5 and Figure 9.1. The initial study delay impacted severely on the envisaged study
programme and cashflow, resulting in a lot of effort required during the Termination Phasee of the
study, i.e. August 2015 to November 2015 to complete the study in time.
Table 9.6: Cashflow comparison
Month
Projected monthly cashflow
(VAT inclusive)
Projected cumulative cashflow
(VAT inclusive)
Actual monthly invoicing
(VAT inclusive)
Actual cumulative invoicing
(VAT inclusive)
Monthly payment received
(VAT inclusive)
Cumulative payment received
(VAT inclusive)
May 2013
June 2013 R 22 344.00 R 22 344.00
July 2013 R 22 344.00
August 2013 R 27 972.34 R 50 316.34
September 2013 R 74 142.34 R 124 458.69
October 2013 R 320 193.43 R 44 652.11
November 2013 R 162 053.99 R 606 706.10 R 936 133.22 R 936 133.22 R 936 133.22 R936 133.22
December 2013 R 1 100 223.38 R 1 706 929.48
January 2014 R 459 648.51 R 2 166 577.99 R 569 423.00 R 1 505 556.22 R 569 423.00 R 1 505 556.22
February 2014 R 392 103.51 R 2 558 681.50 R 447 134.54 R 1 952 690.76 R 447 134.54 R 1 952 690.76
March 2014 R 290 501.01 R 2 849 182.50 R 355 195.24 R 2 307 886.00 R 355 195.24 R 2 307 886.00
Aprril 2014 R 492 888.47 R 3 342 070.97 R 224 579.08 R 2 532 465.08 R 224 579.08 R 2 532 465.08
May 2014 R 445 228.82 R 3 787 299.80 R 359 630.61 R 2 892 095.69 R 359 630.61 R 2 892 095.69
June 2014 R 1 225 113.68 R 5 012 413.48 R 675 799.95 R 3 567 895.64 R 675 799.95 R 3 567 895.64
July 2014 R 440 292.08 R 5 452 705.56 R 317 391.13 R 3 885 286.77 R 317 391.13 R 3 885 286.77
August 2014 R 701 317.88 R 6 154 023.44 R 705 771.87 R 4 591 058.64 R 705 771.87 R 4 591 058.64
September 2014 R 836 309.62 R 6 990 333.07 R 574 820.44 R 5 165 879.08 R 574 820.44 R 5 165 879.08
October 2014 R 1 097 046.08 R 8 087 379.15 R 790 918.70 R 5 956 797.78 R 790 918.70 R 5 956 797.78
November 2014 R 1 297 234.42 R 9 384 613.57 R 502 921.10 R 6 459 718.88 R 502 921.10 R 6 459 718.88
December 2014 R 340 406.55 R 9 725 020.12 R 847 652.65 R 7 307 371.53 R 847 652.65 R 7 307 371.53
January 2015 R 1 076 424.02 R 10 801 444.15
February 2015 R 383 132.48 R 11 184 576.63 R 845 396.46 R 8 152 767.99 R 845 396.46 R 8 152 767.99
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 9-6
Study Closure Report
Figure 9.1: Cashflow comparison
Month
Projected monthly
cashflow (VAT inclusive)
Projected cumulative
cashflow (VAT inclusive)
Actual monthly invoicing
(VAT inclusive)
Actual cumulative
invoicing (VAT inclusive)
Monthly payment received
(VAT inclusive)
Cumulative payment received
(VAT inclusive)
March 2015 R 290 667.62 R 11 475 244.25 R1 141 473.21 R 9 294 241.20 R 1 141 473.21 R 9 294 241.20
April 2015 R 237 493.68 R 11 712 737.94 R 126 803.91 R 9 421 045.11 R 126 803.91 R 9 421 045.11
May 2015 R 484 168.51 R 12 196 906.45 R 320 797.39 R 9 741 842.50 R 320 797.39 R 9 741 842.50
June 2015 R 127 010.90 R 12 323 917.34 R 142 259.65 R 9 884 102.15 R 142 259.65 R 9 884 102.15
July 2015 R 64 325.86 R 12 388 243.20 R 164 302.50 R 10 048 404.65 R 164 302.50 R10 048 404.65
August 2015 R 264 257.70 R 12 652 500.90 R 379 318.10 R 10 427 722.75 R 379 318.10 R10 427 722.75
September 2015 R 264 257.70 R 12 916 758.60 R 617 781.92 R 11 045 504.67 R 617 781.92 R11 045 504.67
October 2015 R 264 257.70 R 13 181 016.30 R 1 633 235.10 R 12 678 739.77 R 1 633 235.10 R 12 678 739.77
November 2015 (1) R 264 257.70 R 13 445 274.00 R 442 161.97
R 13 120 901.74 R 442 161.97
R 13 120 901.74
November 2015 (2) R 13 445 274.00 R 324 136.20
R 13 445 037.94 R 324 136.20
R 13 445 037.94
Total R 13 445 274.00 - R 13 445 037.94 R 13 445 037.94
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 9-7
Study Closure Report
9.5 HDI PARTICIPATION
The ToR defined HDI participation as the ratio of professional fees apportioned to HDIs. The
minimum target HDI participation was specified as 25%.
Based on the task related information provided in Appendix I the HDI ratio of professional fees at
study completion were 43.35%, more than required.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-1
Study Closure Report
10 STUDY FEEDBACK
In addition to the information presented in the previous sections, general feedback on the GRDS is
provided below in the following categories:
Project Management Component
Technical Component
Time frame of the study
Review and evaluation process
Capacity building
Financial considerations
Liaison with the Client
Other aspects
10.1 PROJECT MANAGEMENT COMPONENT
In general, project management entails the planning, organising, monitoring and controlling of all
project related aspects in a continuous process to achieve the stated objectives. As such, the GRDS
Project Management Component covered the following project management and administrative
activities:
10.1.1 Study administration and coordination
The administrative aspects of the study were handled as timeously and efficiently as possible by the
PMT, but was negatively impacted on by the departure of Mr Simon von Witt, who acted as PMT
Study Coordinator. Mr von Witt was also previously involved in the ORDS in a similar capacity and
has always conducted his work at a high standard with enthusiasm, efficiency and dedication. The
DWS has reported at varios occasions their satisfaction with his work. When he left, he left a great
gap that had to be filled in a short period of time.
In April 2015 Ms Colleen Thomas, was appointed on the project to replace Mr von Witt. However,
she resigned from AECOM in July 2015. As a result Ms Shoeshoe Letoao took over as Study
Coordinator at a difficult stage at the commencement of the Termination Phase in August 2015,
All PMC/PSC meetings and stakeholder workshops were well organised and catered for with well
structured agendas. Meeting agendas were, in general, compiled in advance by the PMT in
consultation with the Technical Study Leader, i.e. Dr Patsy Scherman, and then submitted to the
DWS Project Coordinator, Ms Thapelo Machaba, for amendments/approval. Therafter agendas
were distributed to meeting attendees at least a week prior to the meetings. In doing so, PMC/PSC
meetings kept to the agendas sent out prior to the meeting, without wasting time on topics, which
bore little direct significance to the study.
The capturing of the proceedings from PMC/PSC meetings and stakeholder workshops in the form
of minutes was done in an accurate and well structured manner, capturing most of the key issues
highlighted during the meetings. A recommendation for future studies is that minutes be compiled as
soon as possible after a meeting in order to be distributed within a week or two from the date of the
meeting.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-2
Study Closure Report
Furthermore continual liaison and follow up work was done by the PMT requesting input from
specifically PMC members for their input into PMC related minutes, notes and the Action/Decision
Register.
10.1.2 Scope management
Given the original set study period and budget, it was important that the GRDS scope of work be
managed in line with the ToR requirements agreed to at the Study Initiation and Design Phase. This
kicked-off with the Study Initiation Meeting on 6 June 2013, i.e within a month of the study
commencement.
In addition, various initial workshops as part of the Technical Component were conducted during the
early stages of the GRDS to define the specific task requirements (refer to Table 5.4). Feedback
from these workshops and progress were presented in progress reports as well as duirng PMC
meetings. PMC meetings presented the opportunity to discuss the scope undertaken and/or any
deviation thereof.
Two scope aspects, however, need to be highlighted, i.e. groundwater and the additional
hydrological and yield modelling:
The groundwater task undertaken during the GRDS resulted in much more work than
envisaged to be done. This was primarily as a result of the different approaches followed by
Umvoto Africa during their previously undertaken Deep Artesian Groundwater Exploration for
Oudtshoorn Supply (DAGEOS) study and that of Exigo, the Technical Component
Groundwater Specialist, during the GRDS.
Although not part of the GRDS PSP team, Umvoto Africa was, based on their involvement
with the DAGEOS project and the Development of Reconciliation Strategies for all Towns in
the Southern Planning Region System (DWS, 2014), invited by Ms Isa Thompson of DWS to
attend the GRDS PMC Meeting 4 of 3 Dember 2014. As a result they requested to be
provided the opportunity to review the GRDS groundwater work undertaken.
This difference in approach and opinion about groundwater yield availability resulted in the
exchange of opposing correspondence, almost derailing the GRDS groundwater task and
required a detail workshop discussion on 26 January 2015, attended by DWS, Umvoto
Africa, Exigo, the External Groundwater Reviewer (Mr Julian Conrad of GEOSS) and the
GRDS leadership, represented by Drs Aldu le Grange of AECOM and Patsy Scherman of
SC&A. Given the ongoing difference of opinion, AECOM decided in August 2015 to involve
Dr Kai Whittueser from Delta-H Water Systems Modelling Pty Ltd as additional specialist
external reviewer.
Given the difference in approach and opinion, the scope of the groundwater task originally
envisaged changed dramatically to include a lot of additional rearch, review and rewriting of
the Groundwater Report, with a resulting over-expenditure on the task related budget.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-3
Study Closure Report
A detailed Water Resources Yield Model (WRYM) is, in terms of hydrological modelling and
system yield, essential for any Reserve study as it is the foundation upon which all other
conclusions and risk assessments related to the ecology is made. In June 2014 it was
determined that the EWR sites selected for the GRDS were located on small tributaries with
small catchments which were not covered in any existing yield model. Since all the scenarios
for the study were highly dependent on accurate hydrology, additional hydrological work was
required and the yield model had to be refined to accommodate the total study area as a
system.
The information required was, however, critical for the Reserve process to increase the
study confidence and assist in informative decision making. This resulted in additional work
and budget approved as discussed in in Section 3.4.
10.1.3 Communications management
Communication refers to the overall written study management related communication, including
letters, faxes, e-mail, etc., as opposed to general technical communication within the Technical
Component, and the dissemination thereof. In this regard, the following specific communication was
identified to be managed:
Communication between the DWS and PSP;
Communication between the DWS and the PMT;
Communication between the PMT and the Technical Team;
Communication within the PMT, between the PMT Lead, Stakeholder Participation Task
Leader and Specialist Advisors/External Reviewers; and
Communication with stakeholders.
In order for the PMT to be informed of study management and deliverable related activities, the
following communication arrangements were proposed at Study Initiation and Design Stage:
All communication between the DWS and overall study team needs to be through the PMT;
All communication related to team changes, scope variation and motivations for additional
budget should be through the PMT;
All communication potentially affecting costs and programme and relating to quality should
be copied to the PMT; and
Electronic communication to the PMT should be copied to both Aldu le Grange and Simon
von Witt (later replaced by Colleen Thomas/Shoeshoe Letoao).
This protocol was, in general, followed throughout the duration of the study, although there were
isolated instances where the PMT was not informed and communication was done directly between
the DWS and the Technical Team Leader, which caused unnecessary confusion between the DWS,
PMT and Technical Team and uncertainty with the PMT.
In addition to the above,stakeholder communication was managed through Milkwood
Communications by means of a BID, two stakeholder newsletters and a Stakeholder
Issues/Comments and Response Register.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-4
Study Closure Report
10.1.4 Risk management
Considering the GRDS, three potential risks were identified, i.e. results of the groundwater task,
additional hydrological and system yield modelling and scenario development. The risk associated
with the groundwater task as well as the required additional hydrological and system yield modelling
is discussed in Section 10.1.2. The risk associated with scenario development is discussed in
Section 10.2.7.
10.1.5 Time and cost management
As stated in Section 4.2 , the overall study progress was determined by the Technical Component
activities. As such, and based on the initial study programme, specific study-related milestones and
deliverables were set at the Study Initiation and Design Stage. However, due to the study delay
experienced, milestones dates had to be revised. Changes in deadlines were requested in October
2014, and then a final scheduling was done in May 2015. Final milestones for outstanding
deliverables were agreed on during PMC Meeting 5 on 4 August 2015 with the revised associated
milestones and deliverables presented in Table 4.1.
Revision of the milestone deadlines can be ascribed to:
Project extension from 7 May 2015 to 7 November 2015;
DWS quarterly deliverables for internal auditing purposes;
Realistic and specific dates (as requested) for remaining meetings with DWS;
The slow rate at which reviewer comments have been provided;
Technical team members’ availablility;
Late compliation of some technical reports without reason; and
Change in date for the deliverables, based on results presented to DWS on 11 September
2015 and final decisions regarding the management of water resources of the study area.
Cost management was done through the process described in Section 9.3, and managed by
means of project status reporting described in Section 6.2.2. Each monthly invoice also included a
cash flow summary to date as indicated in Section 9.4.
10.1.6 Quality management
Quality management by the PMT was based on four tiers:
Technical review of technical reports by External Reviewers;
Review of technical report layout, format, grammar, etc. and compatability with other study
reports;
Verification and validation of the Technical Componnet invoices; and
Overall financial auditing and control.
All report review information management was managed in terms collection, storage and
dissemination to the Technical Stusy Leader. In terms of financial auditing a thorough checking
system was put in place where all invoices and related documents submitted to the DWS by the
PMT were subjected to a thorough internal checking process by the PMT Study Leader and Study
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-5
Study Closure Report
Coordinator.
10.1.7 Integration management
Integration management during the GRDS was primarily limited to enginering assistance in terms of
scenario development, compilation of minutes of PMC meetings during which the study progress
and resuls were presented and discussed, monthly progress reporting as well as liaison between
the DWS, PMT and Technical Team to facilitate the timeous delivery of accurate and technically
sound technical reports.
Given the GRDS scope with diversive activities, the compilation of the PMC minutes, and specific
those related to the PMC Meetings 5 and 6, as well as the presentation of results to DWS presented
an extreme challenge to integrate all presentations to reflect the correct discussions and decisions.
Considering, the delayed study progress, the presentation of results to DWS, the final stakeholder
feedback and the finalisation of study reports, only took place late during the Study Termination
Stage, resulting in an integrated effort to effectively deal with all events and milestones, requiring a
structured and efficient information flow between the DWS, the PMT and Technical Team and
stakeholders.
10.2 TECHNICAL COMPONENT
Although it is acknowledged that the Breede and Gouritz WMA have been consolidated, the focus of
the GRDS was the Gouritz River and its associated catchments, and the Reserve component
ecological requirements. The study area was therefore described in terms of the original WMA, the
Gouritz WMA, i.e. WMA 16.
The purpose of this section is to provide a summarised overview of the main results of the GRDS,
and the information provided below is from the Main Report (DWS, 2015b), as it outlines the
technical activities undertaken during the GRDS:
10.2.1 Economic overview
The Gouritz WMA is classified in terms of five identified economic regions (ERs):
ER 1: Coastal (Tertiary catchments K10, K20, K30, K40, K50, K60 and K70);
ER 2: Olifants (Tertiary catchments J31, J32, J33, J34 and J35);
ER 3: Gamka (Tertiary catchments J21, J22, J23, J24 and J25);
ER 4: Goukou/Gouritz/Duiwenhoks) (Tertiary catchments J40, H80 and H90; and
ER 5: Touws/Buffels/Groot) (Tertiary catchments J11, J12 and J13).
The status quo of the five identified economic regions in the WMA represented by the economic
sector related water dependent activities expressed in macro–economic parameters is summarised
in Table 10.1:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-6
Study Closure Report
Table 10.1: Macro-economy of the Gouritz WMA
Economic Sector
GDP (R million) Employment (Numbers) Household Income (R million)
Direct Indirect
and Induced
Total Direct Indirect
and Induced
Total Total Medium Low
Agriculture 1 483.26 1 519.66 3 002.92 17 559 14 875 32 434 3 071.00 2 251.54 819.46
Commercial Forestry
294.76 193.61 488.38 3 266 1 697 4 963 350.47 226.97 123.50
Saw Mills - - - - - - - - -
Mining - - - - - - - - -
Electricity - - - - - - - - -
Industry 13 386.63 9 220.76 22607.38 5 007 34 174 39 181 15392.76 9 038.98 6 50.82
Tourism 3 225.14 2 840.76 6 065.90 28 722 9 896 38 618 4 970.51 3 663.03 130748
Total 18 389.79 13774.79 32164.58 54 554 60 643 11517 23784.74 15180.52 860126
The contribution by water to economic growth in the WMA as represented by direct Gross Domestic
Product (GDP) is over R18 000 million per annum, mainly driven by Mossgas in the industry sector.
Overall in the Gouritz WMA tourism is the major direct employment creator with 28 700, followed by
agriculture with 17 500, industry with 5 000 and commercial forestry, lagging far behind, with 3 200
employment opportunities. Table 10.2 shows the most dominant sector per ER:
Table 10.2: Most dominant economic sector per economic region
ER1 ER2 ER3 ER4 ER5
Tourism by far followed by forestry and
industry (saw mills, dairy factories and
Mossgas)
Agriculture leads by far followed by
tourism
Tourism and Agriculture virtually share the honour
Agriculture leads by far followed by limited tourism
Agriculture leads by far followed by
tourism
In the coastal ER, i.e. ER 1, tourism dominates and is the most prominent economic sector in the
WMA with forestry also making some contribution. Agriculture is the main economic sector in ERs
2, 4 and 5. Tourism and agriculture are the dominant sectors in ER 3. The dominant activity for the
total catchment is the tourism followed by agricultural related industry.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-7
Study Closure Report
10.2.2 Rivers study overview
Ten EWR sites, as listed in Table 10.3, were selected in the study area (the letters following the
MRU description are part of the description and delineation and not the REC, being a standard
format followed):
Table 10.3: EWR river sites selected
EWR site name SQ
1
reach River MRU
2 Latitude Longitude
Eco-
Region
(Level II)
Geo3
Zone Altitude
(m) Quat
4
H8DUIW-EWR1 H80E-09314 Duiwen-hoks
MRU Duiwenhoks C
S34.25167 E20.99194 22.02 E Lower Foothills
15 H80E
H9GOUK-EWR2 H90C-09229 Goukou MRU Goukou A
S34.09324 E21.29300 22.02 E Lower Foothills
87 H90C
J1TOUW-EWR3 J12M-08904 Touws MRU Touws B
S33.72707 E21.16507 19.07 E Lower Foothills
271 J12M
J2GAMK-EWR4 J25A-08567 Gamka MRU Gamka B
S33.36472 E21.63051 19.09 E Lower Foothills
375 J25A
J1BUFF-EWR5 J11H-08557 Buffels MRU Buffels B
S33.38452 E20.94169 19.09 E Lower Foothills
499 J11H
J4GOUR-EWR6 J40B-09106 Gouritz MRU Gouritz A
S33.90982 E21.65233 19.08 E Lower Foothills
121 J40B
J1DORI-EWR7 J12L-09895 Doring S33.79137 E20.92699 19.07 E Lower Foothills
370 J12L
K6KEUR-EWR8 K60C-09882 Keur-booms
MRU Keurbooms B
S33.88955 E23.24392 20.02 D Upper Foothills
161 K60C
J3OLIF-EWR9 J31D-08592 Olifants MRU Olifants A
S33.43813 E23.20587 19.01 E Lower Foothills
621 J31D
J3KAMM-EWR10
J34C-8869 Kamma-nassie
MRU Kammanassie A
S33.73286 E22.69740 19.01 E Lower Foothills
445 J34C
1 Sub Quaternary 2 Management Resource Unit 3 Geomorphic 4 Quaternary catchment
The EWR results are shown in Table 10.4 as a percentage of the nMAR:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-8
Study Closure Report
Table 10.4: EWR results as a percentage of the nMAR
Site EcoStatus nMAR
(MCM)1
pMAR2
(MCM)
Low flows (MCM)
Low flows (%)
High flows (MCM)
High flows (%)
Total flows (MCM)
Total
flows
(%)
H8DUIW-EWR1 PES; REC: D 83.7 79.8 14.2 17 8.2 10.2 22.4 27.2
H9GOUK-EWR2 PES; REC: C/D 54.1 46 7.1 13.1 4.3 13.9 11.4 27.0
J1TOUW-EWR3 Instream: C 45.20 22.26 1.15 2.6 11.54 25.6 12.69 28.2
J2GAMK-EWR4 PES: C/D 85.54 61.69 3.94 4.6 17.44 20.4 21.38 25.0
J1BUFF-EWR5 PES; REC: C 29.31 18.67 1.37 4.7 6.85 23.3 8.22 28.0
J4GOUR-EWR6 PES; REC: C 543.52 310.35 27.12 5.0 102.47 18.8 129.59 23.8
J1DORI-EWR7 PES; REC: C/D 4.52 2.01 0.386 8.5 0.644 14.3 1.03 22.8
K6KEUR-EWR8 Instream PES: C 49.81 30.45 10.66 21.4 8.66 17.4 19.32 38.8
Instream REC: B 49.81 30.45 13.93 28.0 9.27 18.6 23.3 46.6
J3OLIF-EWR9 PES; REC: C 13.76 11.32 0.54 3.9 3.05 22.2 3.59 26.1
J3KAMM-EWR10
PES; REC: C/D 20.6 19.6 1.8 8.9 2.8 13.5 4.6 22.4
1 Million Cubic Metres 2 Present Day Mean Annual Runoff
10.2.3 Estuaries study overview
The Gouritz WMA includes 21 estuaries stretching from the Duiwenhoks Estuary in the west to the
Bloukrans Estuary in the east. Within this WMA, 11 estuaries have been assessed as part of
previous EWR studies. The GRDS therefore focused on the remaining 10 estuaries (refer to Table
10.5). Of the 11 estuaries that was assessed previously, EWR assessments on eight of those did
not define Ecological specifications (referred to in this document as EcoSpecs) and TPCs, nor were
monitoring programmes provided. Therefore, the GRDS also defined such parameters and
programmes for those eight estuaries as indicated in Table 10.5.
Table 10.5: Summary reference of GRDS estuary study
Estuary EWR level EcoSpecs/TPCs Monitoring programme
Duiwenhoks Intermediate (GRDS study)
Goukou Intermediate (GRDS study)
Gourits Intermediate (GRDS study)
Blinde Desktop (GRDS study)
Hartenbos Desktop (GRDS study)
Klein Brak Rapid (GRDS study)
Maalgate Desktop (previous EWR)
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-9
Study Closure Report
Estuary EWR level EcoSpecs/TPCs Monitoring programme
Gwaing Desktop (previous EWR)
Kaaimans Desktop (previous EWR)
Wilderness Rapid (GRDS study)
Goukamma Rapid (previous EWR)
Noetsie Desktop (previous EWR)
Piesang Desktop (GRDS study)
Keurbooms Rapid (previous EWR)
Matjies Intermediate (previous EWR)
Sout (Oos) Intermediate (previous EWR)
Groot (Wes) Desktop (GRDS study)
Bloukrans Desktop (GRDS study)
Only about 9% of the estuaries in the WMA are in excellent health (Category A), while about half the
systems (52%) are in a good state (Category B and B/C). An additional 40% is in a fair state
(Categories C to D). The remainder of the estuaries in the region are in a poor state as reflected by
9% in Category D/E. Figure 10.1 provides a summary of PES of estuaries in the Gouritz WMA
illustrating the continuum in estuary condition.
Figure 10.1: Summary of PES of estuaries in the Gouritz WMA illustrating the continuum in
estuary condition.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-10
Study Closure Report
The Recommended Ecological Categories (RECs) allocated to the various estuaries show that 74%
of estuaries (17 systems) need to improve in health condition in order to achieve overarching
biodiversity and related ecosystem services objectives. This high percentage is driven by the high
number of estuaries in protected areas, or desired protected areas in the region. The type of
mitigation measures that would be required to meet RECs are summarised in Figure 10.2 below:
Figure 10.2: Type of mitigation measures that would be required to meet RECs
10.2.4 Basic Human Needs Reserve (surface water)
The prescribed minimum standard of water supply services necessary for the reliable supply of a
sufficient quantity and quality of water to households, including informal households, to support life
and personal hygiene from run-of-river, is provided in Section 18 of the Main Report (DWS, 2015b).
The BHNR demand (for year 2011 and by extension, given the no growth scenario, also for 2014) is
estimated at 659 065 m3/per annum and 1 316 114 m3/per annum for the 25 and 50 litre limits,
respectively.
10.2.5 Wetlands
Two high priority wetlands, the Duiwenhoks unchannelled valley bottom, a large palmiet-dominated
wetland, and the Bitou floodplain, were assessed in the field. Both wetlands had a moderate
importance. The Duiwenhoks was in a PES of a D EC, largely due to extensive erosion of the
palmiet wetland. The Bitou wetland was in a PES of a C EC, largely attributable to landuse
conversion. Like many wetlands across the WMA, the impacts of invasive alien vegetation were
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-11
Study Closure Report
ubiquitous and the removal and control of woody alien trees could greatly reduce or even reverse
some of the wetland degradation in the region.
Quaternary catchments with 0.5% area or more of wetlands within them were identified using
available wetland maps, and average EIS and PES conditions for wetlands within these catchments
were also estimated using a desktop assessment tool.
10.2.6 Groundwater
Objectives of the groundwater study were as follows:
Perform a Desktop-Rapid level groundwater Reserve determination for the entire Gouritz
WMA to identify hotspots/areas of water resource concern and areas in the WMA where
limited groundwater is available after the Reserve is allocated;
Perform Intermediate groundwater Reserve determinations for selected
catchments/Groundwater Resource Units (GRUs) that are classified as stressed based on
the classification of the desktop Reserve; and
Report on groundwater Reserve figures and findings for the WMA and selected GRUs and
make recommendations on where more detailed future studies should be performed.
A few key findings from the Intermediate Reserve results were as follows:
Alien vegetation has the potential to reduce groundwater recharge/groundwater potential
significantly;
Irrigation also has one of the biggest influences on the groundwater balance. When irrigation
land use and typical irrigation water use is considered, the volumes are so large that it was
concluded that there must be large surface water dams, river abstraction or irrigation canals
present to justify these volumes. An assumption was made that 10-15% of all irrigation
comes from groundwater;
The Gouritz WMA is indicated to be stressed in a number of areas, more specifically in the
Great Karoo basin as well as the Klein Karoo area and H90E. In the coastal areas further
east, e.g. K50B and K60G, less groundwater stress is experienced due to the availability of
surface water;
The groundwater quality of the regional area is generally good but influenced by the local
geology;
Groundwater development potential is possible in ±70% of the catchments. The allocable
groundwater potential is between a minimum of 31 million m3/a, and 60 million m3/a if
advantage can be taken from reducing losses; and
Conjunctive use between surface water and groundwater and artificial recharge are two
future water use strategies that would be important to explore.
10.2.7 Scenario development
Operational constraints and catchment requirements were incorporated into yield scenario
modelling, and catchment activities impacting on ecology were considered. The scenarios selected
considered the realities of the current and possible future ecological and socio-economic situation in
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-12
Study Closure Report
the study area as identified during a Scenario Workshop conducted with the DWS and local
municipalities. Stakeholder attitudes, values and expectations towards water resources were also
taken into account. However, it I sto be noted that:
Level of determination is data dependent.
Scenarios in Reserve to tests sensitivities and provide some information for planning prior to
Classification.
Focus to be on highly likely (feasibility level) scenarios.
Operational scenarios cannot evaluate future developments if sufficient technical data are
not available.
The risk associated with scenario development refers to the overarching aim of the scenario
evaluation process to find the appropriate balance between the level of environmental protection
and the use of the water to sustain socio-economic activities. Once the preferred scenario has been
selected, the EC for managing the resource into the future is defined by the level of environmental
protection embedded in that scenario.
Since scenario assessments are an important part of the National Water Resource Classification
(NWRC) process, the following are important regarding operational scenarios:
Estuaries: A range of scenarios is required to ensure that one can test the sensitivity of
ecological categories;
The scenario step in the Reserve process is primarily to test sensitivities and to provide
some information for planning prior to Classification. The focus should therefore be on highly
likely scenarios as Classification will assess other planning recommendations;
Operational scenarios do not evaluate impacts of small developments such as single
licenses;
Operational scenarios are not a wish or shopping list for possible pie-in-the-sky
developments;
Operational scenarios cannot evaluate future developments if sufficient technical data are
not available; and
High resolution scenario evaluation requires Ecological Water Requirement (EWR) sites in
the river (hotspot process) and selected estuary with reasonable confidence level
information (e.g. suitable water level and measured hydrological data).
The following approach was followed during the Scenario Workshop of 24 August 2014:
Identify the relevant systems in which scenarios will be selected;
Identify the variables to be considered in the scenario; and
Design a matrix showing the range of scenarios each consisting of some or all of the
variables which are in place.
Although referred to, information of proposed water source development was not available at the
workshop or subsequent to the workshop to properly follow the approach above. When detailed
information was sought for the scenarios identified on 24 August 2014, little was available. The
proposed developments for which detailed information was available were limited to those outlined
in the following reports:
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-13
Study Closure Report
Preliminary Design Report for the regional integration of the bulk water supply systems of the
Knysna and Bitou Municipalities, which focuses on the Wadrif Dam (Eden DM, 2014);
Development of Reconciliation Strategies for all Towns in the Southern Planning Region,
referring to increasing supply to the Riversdal area from the Korinte/Vet river system (DWS,
2014); and
Feasibility and Implementation Ready Study Ladismith, referring to the proposed Swartberg
Dam for increased water supply to Ladismith (Element Consulting Engineers, 2013).
Little other information regarding estuary scenarios, e.g. the building of the proposed dam on the
Goukou River, could be located. As the estuary team have to evaluate scenarios to assess the
sensitivity of their ecological categories, some assumptions were made. The proposed position of the
Duiwenhoks Dam was obtained from DWS’ Mr John Roberts, but not that of the dam on the Goukou
River. A likely position was assumed for modelling and production of scenarios. This approach was
followed where information were not available, and signed off during PMC Meeting No 4 on 3
December 2015.
The approach, reasons why river scenarios were not evaluated and results of the estuary scenario
assessments, together with a list of potential development projects identified at the Scenario
Workshop in August 2014, are outlined in the Scenario Report (DWS, 2015a).
10.2.8 Monitoring
The GRDS Monitoring Report includes EcoSpecs and TPCs for habitat and biota for rivers and
estuaries, as well as guidelines for the development of monitoring programmes.
An approach is also outlined for desktop monitoring (using available wetland maps, Google Earth
imagery and available landcover records to compare the baseline (2015) records with the most
recent available imagery at the time of assessment) of priority and key wetlands in the study area.
The groundwater monitoring component included an assessment of the availability of monitoring
boreholes, and recommendations on where in the WMA additional monitoring boreholes would be
prudent. There should also be an attempt to include current active monitoring conducted by
consultants into the DWS active monitoring boreholes database.
10.2.9 Preliminary Ecological Reserve Categories’ Conclusions
The Ecological Reserve Categories represent the final management decisions reached by
consulting with the DWS in September 2015 and presenting results to stakeholders in October
2015. Recommended Reserve Categories were arrived at by following the recognized
EcoClassification process to determine the said categories considering the driving ecological
considerations in the study area, an evaluation of future developments and the ecological
consequences in response to future developments and associated scenarios. The final
management recommendations are presented in the Main Report (DWS, 2015b) for priority river,
estuarine and wetland systems, and the groundwater resource in the study area. Riverine EWR
sites and designated estuaries are now to be considered as primary monitoring sites for which
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-14
Study Closure Report
ecological specifications have been set. The latter will be used as indicators to measure the health
status of these water resources and provide baseline information as input to the upcoming
Classification study, as well as reporting on the state of the relevant water resources.
10.3 REVIEW AND EVALUATION PROCESS
Technical report review was undertaken by the PMT, External Reviewers and the DWS. As
indicated in Section 6.2.4, the intention was that the draft technical reports were subject to a single
parallel round of review by the PMT, External Reviewers and the DWS. However, this approach was
not successful as all review feedback was not received in time. It is acknowldeged that some study
reports was not submitted on time, but it needs to be emphasised that the review feedback received
from the DWS, in general, exceeded the three week review period as was agreed during the Project
Initiation Meeting of 6 June 2013. As a result the finalisation of final reports was completed later
than envisaged. In terms of similar type of studies, the DWS should attempt to adhere to the set
report review period.
The approach followed by submitting draft reports for review resulted in some cases in a further
draft version of a specific report to be compiled and reviewed again. This, together with the above-
mentioned delay in review feedback resulted in additional report editing and a longer report
compilation and finalisation period. As a result, most reports, previously in a draft format, could only
be finalised during the Study Termination Phase. Given the various versions of a specific report,
each report contains a report schedule indicating the various versions and date of compilation.
Wheras the PMT primarily focussed on editorial, formatting and grammar aspects, the Specialist
External Reviewers for the river, estuary, wetlands and groundwater related reports provided
invaluable technical input. In addtion, DWS representatives also provided constructive technical and
value added review input.
The review of the Groundwater Report needs to be highlighted as a concern.With reference to the
difference in opinion between Exigo and Umvoto Africa, as indicated in Section 10.1.2, the
groundwater task required much more effort as envisaged. Given the review of Umvoto Africa, as
representative DAGEOS stakeholder, and associated comments on the groundwater work
undertaken, the Groundwater Report report was subject to various rounds of review with detail
feedback from the PMT, External Reviewer, DWS and Umvoto Africa. As a result the Groundwater
Report underwent three rounds of review, including a further external review by Dr Kai Whitthueser.
With reference to PMC Meeting No 2 it was decided that, as part of the report review process, each
report should include a comments/response register or some form of proof of changes be included
in reports to see which comments have and/or have not been addressed. Reasons should be
provided by the author for not including comments received from the PMC and/or Specialist External
Reviewers in the final report.
For future studies it is advised that reviewers be alerted of only one review period given and the
importance of their input and actively encouraged to provide comments on the report.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 10-15
Study Closure Report
10.4 LIAISON WITH THE CLIENT
In general, the relationship during the GRDS between the PSP and the DWS, as the Client was, in
general, considered as efficient. The slow report review feedback at times, as referred to in Section
10.3, posed some challenges in terms of complying with target dates for deliverables. It is, however,
realised that the DWS has limited capacity in terms of technical staff to review the bulky and large
number of technical reports produced during a study of this nature. Although not in time, the DWS
received were, however, in most cases constructive and added value to the final products to be
approved by the DWS. Both the PMT and the Technical Study Leader had regular contact with the
DWS project management team comprising Mr Yakeen Atwaru, Ms Barbara Weston and Ms
Thapelo Machaba.
Mr Atwaru was always willing to listen to and address any problems experienced during the GRDS.
In addition, he managed PMC and PSC meetings efficiently and strictly according to the set
agendas.
With her experience Ms Barbara Weston was very helpful in the technical review of study reports
and general day-to-day difficulties experienced during the study. In general, her reviews provided
the backbone of the DWS review, being constructive and adding value.
As DWS Project Coordinator, Ms Thapelo Machaba assisted the PMT and the Technical Study
Leader a lot with the the general study proocal, setting of meeting agendas, contact with DWS PMC
members, availability of DWS PMC members to attend meetings, collection of comments on
minutes and reports, etc.
In addition, the assistance provided by the following DWS officials is also acknowledged:
Ms Nancy Motebe – dealing with the groundwater aspects in terms of difference of opinion
and review of the groundwater report;
Mr Mike Smart - dealing with the groundwater aspects in terms of difference of opinion and
review of the groundwater report;
Dr Andrew Gordon – general report review assistance; and
Mr Johan Knoetzen – hosting study meetings at the DWS George Regional Office.
10.5 AVAILABILITY OF INFORMATION
Information from previous studies was often found to be outdated or references to potential
developments insufficient for truly accurate studies to be undertaken and Technical Team had to
make do with the available data and make certain assumptions. This could be seen as a common
problem in many studies and will continue to be so. The only manner to get around this would be to
provide more budget to do more monitoring of the water resources within this and other study areas.
It could be an opportunity to provide local people with jobs and actively involve the community within
the respective areas, however, funding is seen as the major obstacle to achieve this.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 11-1
Study Closure Report
11 CONCLUSIONS
The GRDS is an integrated study during which the Preliminary Reserves of selected surface
angroundwater resources, estuaries and wetlands in the Gouritz part of WMA 8 were determined.
The focus of the GRDS was on providing detailed ecological information as per Section 17 of the
NWA to address gaps not covered in the ORDS, to determine ecological specifications for the
priority water resources that are critical input to the future monitoring of the priority water resources
and ultimately provide the ecological baseline information as input to Water Resource Classifcation
(WRC) as required per Section 17 of the NWA. The latter study will be initiated for the Breede-
Gouritz WMA during 2016. As such the study focused on the ecological aspect of a Reserve study,
as is appropriate within the broader framework of Classification.
While the summarised aims, objectives and proposed outcomes of the GRDS are described in
Section 3.5.1, some conclusions and recommendations are provided below:
11.1 ECOLOGICAL COMPONENT OF THE RESERVE
The level of detail at which the GRDS could be undertaken, including the level of Reserve
determination (Rapid, Intermediate and Comprehensive) applied, was dependent on the data
available, i.e. the more data available on a particular system, the more accurate the EC, the
ecological flows (Ecological Reserve), as well as Ecospecs can be set. However, in instances where
the lack of certain data sets poses uncertainties, a precautionary approach was adopted, i.e. the
Ecological Reserves were set conservatively. The levels of assessments at which various river and
estuarine systems were evaluated, were indicated where relevant. It is acknowledged that the
confidence in results are related to the data available, particularly hydrological data.
The level of detail at which the GRDS could be undertaken was dependent on the data available,
i.e. the more data available on a particular system, the more accurate the Present ecological
category can be derived and the REC, ecological flows (Ecological Reserve), as well as the
Ecospecs can be set. However, in instances where the lack of certain data sets posed uncertainties,
a precautionary approach was adopted, i.e. the Ecological Reserves were set conservatively. The
levels of assessments at which various river and estuarine systems were evaluated, were indicated
where relevant. It is acknowledged that the confidence in results are related on the data available,
particularly hydrological data.
11.2 IMPORTANCE OF OPERATIONAL SCENARIOS
A range of operational scenarios was used to test and assess the ecological sensitivities and
responses to future and current developments. This information is also key to determine the
ultimate Ecological Management Category (REC or PES) to be used as input into the Reserve legal
templates. The EWR volumes and time series are vital information for the operational rules of
infrastructure and water use licence conditions. In general, the focus should be on highly likely
(feasibility level) scenarios, i.e. potential developments. In the case of the GRDS, very little such
information was available.(refer to Section 10.2.7). Therefore, operational scenarios could, in
general, not be used to evaluate future developments.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 11-2
Study Closure Report
Although some technical feedback is provided in Section 10, the major water resources’ related
conclusions and recommendations are summarised below:
11.3 RIVERS: ECOCLASSIFICATION AND EWR ASSESSMENT
The confidence in the EcoClassification results was generally Moderate which was acceptable for a
Rapid to Intermediate assessment. Furthermore, no further work on EcoClassification was required
as it would not influence the EWR determination. However, monitoring is essential to ensure that the
ecological objectives are achieved.
The confidence in all the parameters, used during EWR quantification, was generally Moderate, for
most sites, except:
A low confidence for hydrology was at J1DORI-EWR7 was linked to the available hydrological
model for the Doring River which was out of date.
The low confidence for hydrology at J3OLIF-EWR9 was linked to the absence of a reliable
gauge in the area and in turn influenced the overall confidence in low flows.
Low confidence dominated the biotic responses to low flow parameters for J1TOUW-EWR3
due to non-sensitive fish species naturally present in this reach.
Confidence in the hydraulic modelling results overrode the confidence in the biophysical responses,
except at J1TOUW-EWR3. The confidence was generally Moderate, for all the EWR sites with High
confidence in the high flow determination. The low confidence for low flow determination achieved at
some sites was because measured flow data used for calibrating the hydraulic model was higher
than the low flow EWR determination. Further work to improve the hydraulics would require
additional measured calibration at very low flows.
The most effective way of improving confidence is linked to monitoring the ecological status of the
rivers and, if required, improving the hydraulics for low flows at selected sites as part of the
monitoring programme. However, this can only be successful if good reliable hydrological
measurements are available. No specific studies to improve any confidences other than monitoring
are therefore recommended.
11.4 ESTUARIES: ECOCLASSIFICATION AND EWR ASSESSMENT
An overview of the Preliminary Reserve determination of estuaries in the Gouritz WMA (i.e.
Duiwenhoks to Bloukrans estuaries), as derived from the GRDS, as well as previous EWR studies,
is presented in Table 11.1.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 11-3
Study Closure Report
Table 11.1: Summary of the Preliminary Reserve determination for estuaries in the Gouritz WMA
Estuary
Co
nfi
de
nce
EcoClassification
Recommended mitigation measures
Water Land-use and development Fisheries
PE
S
Imp
ort
an
ce
Pro
tec
tio
n S
tatu
s
RE
C
Re
sto
re b
as
e f
low
s
Re
sto
re F
loo
ds
Imp
rov
e W
ate
r Q
ua
lity
Re
sto
re c
on
ne
cti
vit
y/ h
yd
rolo
gic
al
fun
cti
on
ing
Imp
rov
e m
ou
th m
an
ag
em
en
t
Re
ha
bil
ita
te r
ipa
ria
n a
rea
s/ w
etl
an
ds
Re
mo
ve
ali
en
ve
ge
tati
on
Imp
lem
en
t ca
ttle
ex
clu
sio
n z
on
e
Co
ntr
ol
hu
man
dis
turb
an
ce
of
bir
ds
Imp
ort
an
t n
urs
eri
es
Re
mo
ve
/red
uc
e f
ish
ing
pre
ss
ure
/ b
ait
co
lle
cti
on
Re
mo
ve
ali
en
fis
h
Duiwenhoks M C 5 1 B
Goukou M C 5 5 B
Gouritz M C/D 4 5 B
Blinde VL C 3 1 C
Tweekuilen1 D/E 4 1 D
Gericke1 D/E 3 1 D
Hartenbos VL D 4 1 C
Klein Brak L C 3 1 C
Groot Brak2 D 4 1 C
Maalgate2 B/C 3 1 B
Gwaing2 B/C 3 1 C
Kaaimans B 3 5 A/B
Wilderness L B/C 5 5 B
Swartvlei2 B 5 5 B
Goukamma2 B 4 5 A
Knysna2 B 5 5 B
Noetsie2 B 3 5 A
Piesang VL D 4 5 B/C
Keurbooms M A/B 5 5 A/B
Matjies2 B 3 1 B
Sout (Oos) 2 A 3 5 A
Groot (Wes) VL B 4 5 A
Bloukrans VL A 3 5 A
1 Micro estuaries identified as part of recent WRC project (Van Niekerk et al., 2014).
2 Obtained from previous EWR studies.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 11-4
Study Closure Report
The summary includes:
The PES and REC.
Estuary Importance (rated as 3 = “Average Importance” (Importance score 0 – 60), 4 =
“Important” (Importance score 61 – 80) or 5 = “High Importance” [Importance score > 80).
Priority estuaries identified in the South African National Estuary Biodiversity Plan are
allocated a rating of 5 for protection status); and
Recommended mitigation measures to achieve the REC, organised in the various
management sectors, namely water, land-use and development, and fisheries.
With reference to Section 10.2.3, when analysed according to “estuarine area” rather than the
number of estuaries, 79% is in a good condition (Category B and B/C), while about 21% of the
estuarine area in the WMA is in a fair state (Category C to D). This indicates that the high number of
near pristine estuaries in this WMA is of a very small size. The high percentage good condition
systems in the WMA are reflecting the state of the large estuarine lakes that dominate from an
estuarine habitat perspective.
From an estuarine importance perspective 26% (6 systems) of the estuaries in this WMA are rated
as “highly important”, while an additional 26% (6 systems) are rated as “important”, with the
remaining 48% (11 systems) rated as of “average to low importance”. Further, about 57% (13
systems) of estuaries are either in formally protected areas or form part of the core set of estuaries
required to meet biodiversity targets for the region.
From the water sector perspective, about 35% of estuaries in the WMA require some restoration in
base flow condition (especially during the low flow period), while 52% needs improvement in water
quality. From the land-use and development sector outlook, 9% of systems require increased
connectivity with the sea and/or improved hydrological functioning, while 17% requires an
improvement in mouth management operations. Nearly 13% of estuaries requires rehabilitation of
the riparian habitat and/or restoration of floodplain/wetland habitat, while 9% require the removal of
alien vegetation from their surrounding environs. About 26% of systems require some control of
recreational activities, such as boating or hiking, to reduce disturbance to birds. From the fisheries
sector perspective, about 39% of estuaries require the reduction/removal of fishing effort (i.e. no-
take estuaries, zonation for closed areas, or closed periods such as night fishing ban), while about
9% of estuaries required the removal of alien fish species to allow for the recovery of indigenous
populations.
It is recommended that the implementation of the EWR (e.g. mitigations, additional baseline surveys
and long-term monitoring programmes) be undertaken in collaboration with various responsible
departments in the DWS, as well as other national and provincial departments and institutions
responsible for estuarine resource management such as DAFF, Department of Environmental
Affairs (DEA): Oceans and Coasts, South African National Biodiversity Institute (SANBI),
CapeNature, SANParks as well as relevant municipal authorities. It is recommended that the
estuarine management planning process and the associated institutional structures (as required
under the Integrated Coastal Management Act 2008) be used as a mechanisms through which to
facilitate the implementation these programmes.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 11-5
Study Closure Report
11.5 GROUNDWATER
Whilst key findings of the groundwater assessment are presented in Section 10.2.6, the following
recommendations, which largely relate to either improving groundwater availability through certain
actions and interventions, or additional work to verify issues which remain unclear, are proposed:
Alien vegetation must be monitored and eradicated as far as possible in the Gouritz WMA. The
catchments that classified as the highest GRDM index should be targeted first. Alien vegetation
should preferably be removed first in riparian-, spring- and wetland-areas.
Groundwater monitoring should be performed across the WMA, but with preference in the
hotspot (or focus) areas and catchments that classified with high GRDM stress indices.
The general authorizations in the 28 potentially stressed catchments must be reviewed and
reduced to sustainable levels and in some cases it may be zero.
Detailed groundwater investigations and numerical flow management models using models
such as MIKE SHE and Finite Element subsurface FLOW system (FEFLOW), should be
developed to characterise catchments H90E, J33E and J33F to verify the role that groundwater
storage can play in the buffering of dry cycles. It will be important to verify the water use
quantities. The deep Peninsula Aquifer will require a detailed three dimensional numerical
groundwater flow model to refine and verify the yield.
The yield of the semi-confined shallow aquifer (GRU 1) and the deep confined Peninsula
Aquifer (GRU 2) must be quantified using detailed 3D numerical groundwater flow models
based on the latest data sets. The potential constraints of protected areas and surface water
features, e.g. streams and dams such as the George Dam, must be evaluated and
environmental impacts qualified. It will be important to manage the groundwater abstraction
from both GRU 1 and GRU 2 so as to ensure that the environmental flow requirements are met.
The groundwater contribution to baseflow should be verified in the catchments that flagged with
a high GRDM index rating. Sampling of the water quality changes and parameter tracing based
on hydrogeochemical mixing models can be considered to achieve this.
Detailed field investigations and models should be used to determine a buffer zone to mitigate
saline water intrusion. This aspect should be further investigated at K40D, K50B, K40E and
K10A.
More research is required to determine under which conditions more groundwater may be
available if losses can be reduced.
Additional groundwater development in the hotspot- and stressed-areas should be prevented if
the stressed situation is verified. Options to regionally distribute groundwater abstraction to
alleviate local concentrated abstraction should be investigated.
The Intermediate Reserve EWR must be refined as it could be less than the volumes that were
conservatively estimated in this study.
Conjunctive use strategies between surface water and groundwater should be investigated and
a guideline document be compiled that would account for the constraints in each catchment.
Artificial recharge should be considered as a future water management option. Notable artificial
recharge case studies include Prince Albert and Plettenberg Bay that fall within the Gouritz
WMA.
The water management strategy for the deep confined TMG aquifers should be reviewed and a
guideline document be compiled to ensure sustainable development and utilisation of the deep
groundwater systems.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 11-6
Study Closure Report
Shale gas exploration (fracking) in the Karoo formations should be done with due diligence and care
should be taken not to adversely affect the groundwater quality and supplies. The level of
information on the hydrogeology of the deep Karoo Aquifers is currently too limited to make
informed decisions on this aspect. Recent progress has been made in improving knowledge on the
processes of deep groundwater circulation in Karoo aquifers and their flow mechanisms.
11.6 ADDITIONAL RECOMMENDATIONS
In addition to the general recommendations included under study feedback in Section10, the
following general recommendations are proposed:
Few large-scale scenarios were available for evaluation. It would have been valuable to the
technical team if DWS specialists had engaged earlier in the study so as to advise of potential
developments (e.g. the proposed Swart River Dam). The impact of such a dam cannot be
undertaken with any level of confidence if a downstream EWR site is not available. A site on
this river was not included as the Swart River had not come out of Desktop EcoClassification
as an ecological hotspot. If the team had been informed of the proposed development, the site
would have been included as an additional hotspot.
An important outcome of the study is the need for a revision of the Operating Rules for
Gamkapoort Dam, so as to meet the Ecological Reserve and irrigation demans. It is presumed
that this action will be undertaken by DWS.
Rules for operationalizing the Reserve for the Keurbooms Estuary was also highlighted as an
item to be undertaken by DWS, with the assistance of the CSIR. AURECON has also
undertaken work on this system and should be included in operationalizing steps. Note that
improvements to the upstream river system must also be undertaken (see the Main Report for
the study).
One of the major recommendations of the GRDS is around additional work needed regarding
the long-term viability of aquifers in the study area. This aspect caused controversy, but
should be considered if the precautionary principle is to be adhered to.
DWS is strongly recommended to allocate training budgets on future projects. Although
always an important aspect of the study, the focus for the technical specialists is on getting the
job done in the time allocated, which means that the training is not covered as
comprehensively as required during field trips and workshops. The DWS personnel input on
the GRDS training (Appendix A of the Main Report) was a very good initiative. Their
comments and issues should now be addressed in future projects.
None of the recommedations made or studies undertaken during the GRDS will be of any
value if monitoring is not instituted, and management interventions are not undertaken. This is
outside of the ambit of the GRDS, and must be undertaken by the relevant organizations as
specificied in the Main Report and templates produced for the study.
The importance of good quality hydrological data, gauging weirs and water level recorders in
estuaries is emphasized in the technical reports of the study.
Following and various discussions during the study, it is recommended that Reserve studies
should not be conducted outside of Classification. It is much easier to take Reserves,
Classification and RQOs on as a package deal.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 11-7
Study Closure Report
Although the GRDS started slowly, and required input was not always available exactly when
needed, the technical team is of the opinion that a good working relationship was developed with
the DWS (particularly the regional officers) and other key stakeholders. The stakeholder database
developed, and interest shown by stakeholders, should provide a solid support base for the
Classification study to be initiated in WMA8.
Reserve Determination Studies – Gouritz WMA: Project Management Component Page 12-1
Study Closure Report
12 REFERENCES
Department of Water Affairs (DWA), 2014. Reserve Determination Studies for the Selected Surface
Water, Groundwater, Estuaries and Wetlands in the Gouritz Water Management Area: Inception
Report. Prepared by AECOM SA (Pty) Ltd in association with Scherman Colloty & Associates cc.
Report no. RDM/WMA16/00/CON/0113.
Department of Water and Sanitation (DWS), 2014. Development of Reconciliation Strategies for
all Towns in the Southern Planning Region. Riversdal, Hessequa LM, Eden DM, Western Cape,
Version 2.
Department of Water and Sanitation (DWS), 2015a. Reserve Determination Studies for Surface
Water, Groundwater, Estuaries and Wetlands in the Gouritz Water Management Area: Monitoring
Report. Prepared by AECOM SA (Pty) LTD, CSIR and Scherman Colloty and Associates cc. Report
no. RDM/WMA16/00/CON/0913.
Department of Water and Sanitation (DWS), 2015b. Reserve Determination Studies for Surface
Water, Groundwater, Estuaries and Wetlands in the Gouritz Water Management Area: Main
Report. Prepared by Scherman Colloty and Associates cc. Report no. RDM/WMA16/00/CON/1313.
Eden District Municipality, 2014. Feasibility Study of the Regional Integration of the Bulk Water
Supply Systems of Knysna and Bitou Municipalities, Phase 2B: Preliminary Design Report.
Compiled by Aurecon. Eden DM Ref No BID/01/12-13.
Element Consulting Engineers, 2013. RBIG: Feasibility and Implementation Readiness Study
Ladismith. Module 8: Construction of a new storage dam. Project No 12061.Prepared by Retief
Kleynhans from Gorra Water.
APPENDIX A: CONTRACTUAL AGREEMENT
APPENDIX A.1: ORIGINAL CONTRACT
APPENDIX A.2: LETTER OF NOTIFICATION OF APPOINTMENT
APPENDIX A.3: VARIATION ORDER AND APPROVAL
APPENDIX B: STUDY PROGRAMME
APPENDIX C: BACKGROUND INFORMATION DOCUMENT
APPENDIX D: MINUTES OF STUDY INITIATION MEETINGS
APPENDIX E: MINUTES OF PROJECT MANAGEMENT COMMITTEE
MEETINGS
APPENDIX F: MINUTES OF PROJECT STEERING COMMITTEE
MEETINGS
APPENDIX G: MINUTES OF SCENARIO WORKSHOP
APPENDIX G: ACTIONS/DECISIONS REGISTER
APPENDIX H: STAKEHOLDER INFORMATION
APPENDIX H.1: STAKEHOLDER LIST
APPENDIX H.2: STAKEHOLDER NEWSLETTERS
APPENDIX H.3: MINUTES OF STAKEHOLDER WORKSHOPS &
ATTENDANCE REGISTERS
APPENDIX H.4: STAKEHOLDER ISSUES/CONCERNS AND RESPONSE
REGISTER
APPENDIX I: STUDY BUDGET
APPENDIX J: COMMENTS & RESPONSE REGISTER