Resettlement Planning Document
This resettlement due diligence report has been prepared by the Punjab Heritage and Tourism Promotion Board, IDIPT –Punjab, Chandigarh for the Asian Development Bank and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB. This resettlement due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 40648-023 July 2016
IND: Infrastructure Development Investment Program for Tourism (IDIPT) - Tranche 1 Sub Project : Package no. PB/ASR/COM3/UISI/07A-Provision of multi-dispersed car parking areas around walled city circular road and tourist destinations in Amritsar-parking facility at Attari
Submitted by
Punjab Heritage and Tourism Promotion Board, IDIPT –Punjab, Chandigarh
DUE DILIGENCE REPORT ON SOCIAL SAFEGUARDS
INFRASTRUCTURE DEVELOPMENT INVESTMENT PROGRAM FOR
TOURISM (TRANCHE 1) STATE OF PUNJAB
PROVISION OF MULTI-DISPERSED CAR PARKING AREAS AROUND
WALLED CITY CIRCULAR ROAD AND TOURIST DESTINATIONS IN
AMRITSAR-PARKING FACILITY AT ATTARI (NO.
PB/ASR/COM3/UISI/07A)
MAY 2016
Prepared by
The Government of Punjab for the Asian Development Bank
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari I
CONTENTS
1. INTRODUCTION............................................................................................................................ 3
2. DESCRIPTION OF SUB-PROJECT ............................................................................................ 3
2.1.1 Resettlement Framework (RF) ................................................................................................ 4
3. OBJECTIVE OF DUE DILIGENCE REPORT ........................................................................... 6
4. REQUIREMENT OF DUE DILIGENCE REPORT ................................................................... 6
5. SCOPE OF DUE-DILIGENCE EXERCISE ................................................................................. 6
6. APPROACH AND METHODOLOGY ......................................................................................... 6
6.1 ACTIVITY 1: REVIEW AND APPRAISAL OF SUB-PROJECT REPORTS AND DOCUMENTS .................................. 6
6.2 ACTIVITY 2: CONSULTATIONS WITH THE PIU & CONTRACTOR ................................................................................. 7
6.3 ACTIVITY 3: SITE VISIT AND ON-SITE OBSERVATIONS ................................................................................................... 7
6.4 ACTIVITY 4: DUE DILIGENCE REPORT PREPARATION.................................................................................................... 7
7. SOCIAL SAFEGUARD DUE DILIGENCE ................................................................................. 7
7.1 ASSESSMENT/REVIEW OF SOCIAL ISSUES ............................................................................................................................ 7
7.2 DETAILS OF LAND ............................................................................................................................................................................ 7
7.3 RESETTLEMENT IMPACTS ............................................................................................................................................................ 8
7.4 IMPACT ON SCHEDULED TRIBE / INDIGENOUS POPULATION ..................................................................................... 9
7.5 GENDER ISSUES ................................................................................................................................................................................ 9
7.6 WAGES AND LABOUR REGISTER .............................................................................................................................................. 9
7.7 LABOUR CAMP SITE ...................................................................................................................................................................... 10
7.8 PUBLIC CONSULTATION ............................................................................................................................................................. 10
7.8.1 HIV/AIDS Awareness ............................................................................................................ 11
7.8.2 Child Labour .......................................................................................................................... 12
7.9 PROJECT ORGANIZATION STRUCTURE ................................................................................................................................ 12
7.10 GRIEVANCE REDRESSAL MECHANISM ................................................................................................................................ 12
7.11 EMPLOYMENT POTENTIAL ........................................................................................................................................................ 12
7.12 DISCLOSURE PROCESS FOLLOWED FOR SAFEGUARD AND OTHER RELATED DOCUMENTS ..................... 13
7.13 COMPLIANCE TO SOCIAL IMPACTS MITIGATION............................................................................................................ 13
8. SUMMARY FINDINGS/ RECOMMENDATION ..................................................................... 14
LIST OF FIGURES
Figure 1: Project Location of Attari Parking .......................................................................................................................... 5
LIST OF TABLES
Table 1: Project Social Safeguards Impact Categorization ....................................................................................................... 4
Table 2: Stakeholder Consultation at Attari Parking ............................................................................................................. 10
Table 3: Photographs during Stakeholder Consultation at Attari Parking ................................................................................ 11
Table 4: Compliance to Social Impacts Mitigation ............................................................................................................... 13
LIST OF APPENDIX
Appendix 1: Involuntary Resettlement Impact Categorization Form
Appendix 2: Ingenious People Categorization Form
Appendix 3: Asian development bank’s Approval of Attari Parking Subproject and no RP Required
Appendix 4: Attendance Sheet of Participants (Men & Women)
Appendix 5: Project Management Structure (as Proposed in PAM)
Appendix 6: Grievance Redressal Mechanisms
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari II
ABBREVIATIONS
ADB --- Asian Development Bank
AF --- Affected Family
AP --- Affected Person
BPL --- Below Poverty Line
CDO --- Community Development officer
CPRs --- Community Property Resources
DSC --- Design Supervision Consultant
EA --- Executing Agency
FGD --- Focused Group Discussion
GoI --- Government of India
GoP --- Government of Punjab
HH --- Household
MFF --- Multi-tranche financing facility
NGO --- Non-Government Organization
PH --- Physical Handicapped
PHTPB --- Punjab Heritage and Tourism Promotion Board
PIU --- Project Implementation Unit
PMU --- Project Management Unit
R&R --- Resettlement and Rehabilitation
ROW --- Right of Way
RP --- Resettlement Plan
SC --- Schedule Caste
ST --- Schedule Tribe
ToR --- Terms of Reference
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 3
SOCIAL SAFEGUARD DUE DILIGENCE
1. INTRODUCTION
1. ADB is aiding India to develop tourism as a driver of sustainable and inclusive economic growth in
three states through Infrastructure Development Investment Program (IDIPT). The first tranche of a multi-
tranche financing facility (MFF) will upgrade infrastructure and services, and support policy reforms in
states of Himachal Pradesh, Punjab and Uttarakhand. Loan 1 (first tranche) includes the states of Himachal
Pradesh and Punjab. It will enhance the quality of natural and cultural attractions and increase community
involvement in tourism. The Loan Agreement and Project Agreement of Loan 2676 – IND Tranche 1 were
signed on 20th July, 2011 and made effective from 26th October, 2011. In Punjab, Tranche 1 consists 24
sub-projects of civil work, 9 of goods and 5 of consultancy. One community based activity package has also
been identified. Out of total 24 subprojects, 20 are in Amritsar and 4 in Gurdaspur districts. Tranche 1 of
Investment Program is under different stages of implementation.
2. The department of Tourism (DoT), Government of Punjab (GoP) is the Executing Agency (EA) and
Punjab Heritage and Tourism Promotion Board (PHTPB) is the implementation agency (IA) for the IDIPT
for Punjab and the PMU has been set up at the PHTPB. LEA Associates South Asia Private Limited,
(LASA) in association with Simpson & Brown Architects (UK) and Addyman Archeology, UK (UK) has
been retained as Project Management Consultant (PMC) for PHTPB and Shah Technical Consultants Private
Limited in association with Grassroots Research and Consultancy (India) has also been engaged as Design
Supervision Consultant (DSC) by the PHTPB (the Implementing agency (IA)).
3. The purpose of this report is to present the Social Safeguard Due Diligence study conducted for sub-
projects “Provision of Multi-Dispersed Car Parking Areas around Walled City Circular Road and
Tourist Destinations in Amritsar–Parking Facility at Attari (Package no. PB/ASR/COM3/UISI/07A)”,
taken up under Tranche-1.
2. DESCRIPTION OF SUB-PROJECT
4. The Subproject is part of the Western Circuit which is located in the north-western segment of the
state, in the district of Amritsar. The circuit borders Pakistan in the west and the River Beas flows in the
eastern part. Amritsar City is identified as a Gateway destination by the Ministry of Tourism, GOI. It is the
main international air gateway to Punjab, containing the State’s major pilgrimage and heritage attractions, and has the largest tourism draw. The district of Amritsar is part of the Sikh Heritage Trail, the Freedom
Struggle Trail and the Grand Trunk Trail which starts from Ambala in Haryana and ends at Wagah –Attari
Border. (Source: As per Punjab Tourism Development Master Plan, 2008-2023; United Nations World
Tourism Organization (UNWTO)).
5. Amritsar is a district headquarters, which is located at an approximate distance of 250 Km from
Chandigarh (the state capital). The city of Amritsar symbolizes the spiritual heritage of Punjab. It is located
in the north-west of Punjab State and is well connected with rail and road network. It is a major trade and
tourist centre. The city has developed around the most sacred religious place for the Sikhs, namely the
Golden Temple (Harmandir Sahib). There are 12 gates to enter into the walled city which is a rich heritage
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 4
zone. This zone comprises of Katras, courtyard houses and bazaars. The importance of the holy city Amritsar
is due to the presence of the Golden Temple and the Akal Takht, one of the five Takhts of the Sikh religion.
Parking Facility at Attari
6. The sub-project is needed to strengthen the tourism potential of the Attari Border area as it is having
significant cultural importance. This is the Indo-Pak Border area where “Beating Retreat” is played every day by Indian and Pakistan Army with great patriotic enthusiasm in the presence of thousands of visitors
(approximately 8000 visitors per day) of both the sides.
7. The proposed sub project comprises construction of a new multi-level parking (G+1) facility for 237
two wheelers and 1138 four wheelers and 44 buses. Sensor - based parking system has been proposed
wherein the parking bay will be allotted to the vehicle at the token booth itself at the point of entry to the
parking premises. Public facilities such as separate toilets for women and men have been proposed. Lifts &
staircases have also been proposed for vertical circulation. The structure will be an RCC structure with post
and beam type construction. There shall be no infill walls and only railings shall be installed for safety
reasons. The building/structure shall be erected 50 mts. away from the border fence for security reasons. The
proposed sub-project location is shown in Figure 1.
8. Based on the Subproject Appraisal Report (SAR), the tranche 1 subproject including the ‘Parking
Facility at Attari’ have been categorized as “C” for Involuntary Resettlement (IR) as well as Indigenous
People Development as per ADB’s Safeguard Policy Statement (SPS-2009). Table no. 2, presents the social
safeguards impact categorisation based on the detailed screening forms for Resettlement Categorization and
Indigenous People, which are placed at Appendix 1 and 2.
Table 1: Project Social Safeguards Impact Categorization
Name of Project IDIPT, Punjab Loan No. No. 2676– IND
Type of contract Regular Design Build Combined
Safeguards Categorization A B C
IR (Involuntary Resettlement Impact Categorization) NA NA C
IP (Indigenous people Categorization) NA NA C
2.1.1 Resettlement Framework (RF)
9. A Resettlement Framework is in place for guidance in preparation of resettlement plans and overall
safeguards management under IDIPT. The RF prepared for IDIPT has been modified to include the
development with respect to The Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013. This RF is applicable to all sub-projects under IDIPT and is
subjected to review and updating, ensuring relevance and consistency with applicable country/state legal
framework and ADB’s SPS, 2009. The following web link may be referred for Resettlement Framework
Document. http://www.adb.org/sites/default/files/project-document/148689/40648-034-rf-02.pdf.
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 5
Figure 1: Project Location of Attari Parking
Amritsar
Attari – Wagha Border
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 6
3. OBJECTIVE OF DUE DILIGENCE REPORT
10. Objective of Due Diligence Report is to:
To determine whether the subproject is free of Involuntary Resettlement impact such as land
acquisition, displacement, adverse impact on income and livelihood, community properties or any
other impacts.
To review whether the social safeguard implementation of this subproject is compliance with ADB’s
Safeguard Policy Statement (SPS) 2009.
4. REQUIREMENT OF DUE DILIGENCE REPORT
11. Since Attari Parking building is not having any encroachment, land acquisition and resettlement.
Therefore, no expected impacts on private/public land, structures etc. or no negative impacts on livelihood
are envisaged. Hence, no Resettlement Plan is needed and Due Diligence Report fulfils the requirement of
ADB’s safeguards.
5. SCOPE OF DUE-DILIGENCE EXERCISE
12. The scope of Due Diligence Exercise covers the following activities while preparing the DDR:
To monitor the process if government land transfer involved, the process followed for making
such land available to the project and the land-use of those government lands and description of
any encumbrances;
To gather the documentation regarding agreement reached with or consultation held to reach
agreement, in case of purchase of land directly from the community / panchayat;
To verify R&R provisions made applicable to the project;
To collect the details of grievance redress mechanism followed for the project, mentioning if any
grievances received from the local people and the action taken against those grievances;
To review the details of institutional arrangement for social safeguard implementation;
To review the details of the community consultation or development Activities, if carried out by
the PIU/contractor;
To verify the compliance with respect to Resettlement Framework (RF);
To review the disclosure process followed for safeguard and other related documents;
To gather any other information and data related to social impacts;
To suggest suitable measures for identified gaps and shortcomings in mitigating the social
impacts, if any, based on the due diligence exercise.
6. APPROACH AND METHODOLOGY
13. The methods followed for the preparation of due diligence report has been discussed in this section.
6.1 Activity 1: Review and Appraisal of Sub-Project Reports and Documents
14. The reports and relevant documents related to the social safeguards available with the PMU has been
reviewed and appraised. The documents included (i) Loan Agreement- ADB and Punjab State Government,
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 7
(ii) Project Agreement-ADB and Punjab State Government; (iii) Sub-project Appraisal Report (SAR), (iv)
Initial Environmental Examination (IEE) Report, (v) Resettlement Framework, and (vi) Contract Documents
etc. Apart from these documents the review of land transfer procedure to Tourism Department Punjab from
Ministry of Home Affairs (MHA) has also been done.
6.2 Activity 2: Consultations With the PIU & Contractor
15. Two-stage consultation process has been conducted towards preparation of the due diligence report,
(i) consultation with PIU officials prior to the site visit to appraise about the project, and (ii) consultation
after the site visit to ascertain the compliance procedures adopted or planning to be adopted by the
PIU/Contractor for various safeguard issues observed at the site.
6.3 Activity 3: Site Visit and On-Site Observations
16. Visit to the sub-project site have been an integral part of the preparation of due diligence report. In
compliance to it, the PMC’s social safeguards specialist have visited the project site on 19th Jan 2016 and had
discussions with the Community Development Officer at PIU Amritsar etc.
6.4 Activity 4: Due Diligence Report Preparation
17. Based on field visit, data/report review, consultation with CDO, PIU Amritsar, due diligence report
have been prepared. Apart from IR & IP impacts review, the due diligence report also cover the other
safeguard measures such as public consultation, grievance mechanism, labour welfares, health & safety,
potable water and sanitations, gender activities, awareness about the HIV/AIDS etc.
7. SOCIAL SAFEGUARD DUE DILIGENCE
7.1 Assessment/review of Social Issues
18. The Tranche-1 sub-project has been categorized as “C” for involuntary resettlement (IR) as well as for Indigenous People Development as per ADB’s Safeguard Policy Statement (SPS-2009). The sub-project
is being executed within the land notified for dedicated parking to accommodate the vehicles at Attari. The
civil works of Attari Parking is progressing and construction of ground floor of the parking is completed.
The boundary wall of land proposed for Attari parking has been constructed and no encroachment has been
noticed. Formally the Civil Contract has been signed and the LOA was issued on 6th August 2014. The
contract starts on 14th September 2018 and completion date was 09th March 2016 (18 months from start
date).
7.2 Details of Land
19. The sub-project is executed in the 12.8 acres (12 acres, 6 kanals and 11 marlas) of land owned by
Department of Tourism (DoT). Previously, DoT owned about 12 acres of land and a building at Attari, which
was taken over by the Ministry of Home Affairs (MHA), Government of India (GoI) for establishment of an
Integrated Check Post at Wagha Border, Attari. In lieu of this this land, compensation amount was provided
by the MHA, GoI for acquisition of alternative land for construction of parking facility in the vicinity of the
venue of the beating retreat ceremony at Attari. Accordingly, 12.8 acres of land for which compensation has
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 8
been paid at significantly higher rate to 17 people was acquired following public hearing with stakeholders.
The approval letter regarding the subproject consideration in tranche 1 issued on 16th July 2013 from ADB
INRM is attached with the report as Appendix-3. ADB’s special project administration mission on 11th June
2013 observed that the acquired land was not used for agricultural purposes, and hence did not cause any
loss of livelihood and the trees and structures were compensated. Based on the statement from DoT, the
ADB mission also noted that (i) there were no claim or legal case against the land acquisition process till
date and the land was free from any encroachments, (ii) the land was not acquired in anticipation of ADB
supported project, and (iii) the social impacts are acceptable and the risks of past resettlement activity are
manageable.
Boundary/Fencing for Attari Parking Area
Construction work is in progress
7.3 Resettlement Impacts
20. There are no resettlement impacts due to the sub-project. Encroachment of any form, squatting or
any informal use of land of the Attari parking is not observed.
Details of affected properties: There is no impact on built-up structure or other properties.
Impact on Trees: No trees have been affected due to this sub-project.
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 9
No title holder is affected due to the project.
7.4 Impact on Scheduled Tribe / Indigenous Population
21. Indigenous peoples (IPs) are not affected due to the sub-project. All the proposed construction
activities are being carried out within the land allotted for the sub-project. This sub-project is categorized as
“C” for Indigenous Peoples. Amritsar district is not part of the notified Fifth Schedule Area1. Further, as
mentioned in the Indigenous Peoples Planning Framework of ADB (July 2010) Scheduled tribes are in all
States and Union Territories except in the States/Union Territories of Haryana, Punjab, Delhi, Pondicherry,
and Chandigarh.
7.5 Gender Issues
22. The proposed project does not have any adverse impact on women. RF suggests carrying out
continuous consultation with women community throughout project implementation to create awareness
among the upcoming development activities and their livelihood opportunities. This is with the objective to
ensure participation in income generating and livelihood enhancing entities. Accordingly, CDO with the help
of Safety Officer has carried out consultations at site. 28 women labours out of total 70 labours attended the
stakeholder consultation held on 3rd March 2016 at Attari parking site. At this subproject site average 28
woman labourers are engaged daily in unskilled work by the contractor. Labourer shelters along with water
and sanitation, separate toilets for men and women, crèche facility, electricity connection etc have been
provided by the contractor. Medical camp and awareness campaign has also been conducted by CDO in a
regular interval.
Social Safeguard Specialist, PMC & DSC visited Attari Parking and discussed with women labourers
7.6 Wages and Labour Register
23. The Labour Register is being maintained in this sub - project in which the names of men as well as
women labourers have been mentioned. Contractor’s personnel revealed that minimum and equal wages for
equal works are being paid to the labourers without any gender discrimination. There are no women involved
in skilled work.
1 Fifth Schedule under Article 244(1) of Constitution defines “Scheduled Areas” as such areas as the President may by order declare to be Scheduled
Areas after consultation with the Governor of that State. The criteria for declaring any area as a “Scheduled Area” under the Fifth Schedule are; (a) preponderance of tribal population, (b) compactness and reasonable size of the area, (c) a viable administrative entity such as a district, block or
Taluka, and (d) economic backwardness of the area as compared to the neighbouring areas.
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 10
7.7 Labour Camp Site
24. The due diligence related consultations have revealed that mostly migrant labourers from Bihar,
Uttar Pradesh and Madhya Pradesh are working in the sub-project site. The contractor has provided labour
shelters within the project site. Due to construction of boundary wall and levelling of surface contractor has
planned to shift all the shelters in back side of building where most of the work has been completed. Regular
consultations with labourers especially women are being done by CDO and other PIU officials at site.
7.8 Public Consultation
25. Consultation has been done with the contractor’s safety officer and support engineer during due
diligence field visit by safeguard specialist PMC and various issues discussed related to safeguard
implementation on 19th Jan 2016. Apart from discussion held on site, monthly stakeholder meetings with the
labour and safety officer at Attari parking is being carried out by CDO, PIU Amritsar and same shall be
reflecting in Social Monitoring Reports. Table no. 2 presents the issues discussion in the stakeholder
consultation meeting and attendance sheets of participants are placed as Appendix 4.
Table 2: Stakeholder Consultation at Attari Parking
Date, time and Venue
of consultation
Participants Details Issues discussed
20th November 2015,
10:00 am at Attari
Parking (Package 07)
70 Labours (42 Men
and 28 Women)
CDO, PIU Amritsar,
Support Engineer
(PIU), Representative
of DSC and M/s.
Srishti Construction
(Attendance sheet
attached appendix 4)
Safeguards to be implemented as per SPS, 2009 under the
Asian Development Bank (ADB) assisted infrastructure
Development Investment Program for Tourism (IDIPT)
projects.
All the stakeholders should ensure to project Implementation
as per social environment safeguards and gender action plan.
All the measures under Environment Mitigation Plan (EMP)
should be implemented on the site, including ban on use of
firewood on site, Debris Disposal Plan, stacking of the
construction material at appropriate storage areas.
All labourers should use appropriate Personal Protective
Equipment (PPEs) while performing construction activities.
All labourers have been instructed regarding maintenance of
personal hygiene and sanitation in and around the construction
site and labour hutments.
They have been further provided awareness on sexual transmit
disease (STD) and HIV/AIDS through posters and display
material.
Above activities were conducted with a unique way. To
understand safeguards measure easily by labourer that’s need to be implemented, PHTPB has invented snake and ladder
game. Through this stakeholders can understand dos and
don’ts.
30th December 2015,
10:00 am at Attari
Parking (Package 07)
3rd March 2016, 10:00
am at Attari Parking
(Package 07)
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 11
Table 3: Photographs during Stakeholder Consultation at Attari Parking
7.8.1 HIV/AIDS Awareness
26. Considering the possible presence of labourers from distance locations for construction work, EA/IA
should take proper care during construction to conduct information and education campaigns on the risks of
HIV/AIDS and other health issues, targeting construction workers at campsites time to time. The civil works
contractors require (i) to disseminate information at worksites on risks of sexually transmitted diseases and
(ii) HIV/AIDS awareness as part of health and safety measures for those employed during construction.
During due diligence visit such board, signage and safety slogans are in place.
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 12
7.8.2 Child Labour
27. Child labour has not been observed during the due diligence visit. EA/IA ensures that the civil
contractors are not employing children in the civil works or any other works in this sub-project. .
7.9 Project Organization Structure
28. There are two Project Implementation Units (PIU’s) has been established by the Implementing
Agency (IA) PHTPB - Each PIU is responsible for the implementation and monitoring of sub-projects
happening in Eastern and Western circuits respectively. Each PIU has been headed by a Project Manager
(PM) comprising of professionals / officers from various disciplines including architecture, engineering,
contract specialist, community development officers (CDO) etc. CDO’s further supported by community mobilisers. PMU functioning at Chandigarh also comprising the Social and Environment Safeguard
Specialists along with Community Development Specialists, joined recently. All the experts reporting
progress of safeguards to the Forest Conservation Specialist (FCS)/Additional Project Director and Project
Director.
29. The key role of the CDO’s includes effective implementation of the safeguard measures proposed in
RF and ensures the safeguard compliance provisions of the investment program. The CDO’s will report the safeguard implementation status to the PM (PIU) and Safeguard Specialists (Environmental and Social)
PMU through monthly/ quarterly monitoring reports. Environment Safeguards Specialist and Social
Safeguards Specialist, PMU is further reporting to GoP and ADB as per agreed reporting schedule. Detailed
project organisation structure as proposed in PAM is placed at Appendix-5. Social Safeguard Specialist from
PMC and DSC team are further supporting in monitoring and implementation of safeguard measures as per
RF and IEE.
7.10 Grievance Redressal Mechanism
30. During preparation of social due diligence exercise, the RF and IEE report have been reviewed and it
is noted that RF has proposed effective and interactive mechanism in which participation of the community
is ensured through dialogues and frequent meetings with town/village heads, with respect to any grievances.
Grievance Redress Committee (GRC) has been formed and member representative has also been nominated
from Deputy Commissioner and Municipal Commissioner, Amritsar. Further, PMU has issue the necessary
instruction along with the formats and procedure to note any type of grievance to PIUs. CDO is responsible
to monitor the grievance register and complaint submission forms to be maintained by the representative of
contractor. The GRC structure proposed in RF documents is placed in Appendix-6.
7.11 Employment Potential
31. The proposed sub-project ‘Parking Facility at Attari’ will create direct and indirect employment
opportunities. Approximately 40-45 skilled and unskilled labour will be employed during the construction
work apart from other technical staff. Recently during Stakeholder Consultation among labourers, it was
noted that total 70 labourers (42 Men and 28 Women) attended the event on 3rd March 2016. Appendix 4
witnessed 70 labours attendance sheet during stakeholder’s consultation at Attari parking site.
32. In addition to that, other types of employment can also be generated by suppliers of construction
materials, tractor/dumper operators, etc., during construction phase. During operation phase, indirect
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 13
employment creation is envisaged for local shopkeepers, tourist guides, taxi operators, rural artisans etc. The
overall components of the subprojects will enhance livelihood opportunities for the local community.
7.12 Disclosure Process followed for Safeguard and Other Related Documents
33. Resettlement Framework has proposed that public consultation meetings need to be undertaken
throughout the implementation stage. Report suggests disclosure of safeguard documents at prominent places
for public information. Electronic version of RF has been disclosed on ADB’s website (the web link is http://www.adb.org/sites/default/files/project-document/148689/40648-034-rf-02.pdf). RF document in local
(Punjabi) language has not been yet disclosed. However, the Project related information have been provided
at prominent location at this subproject along with information of PIU, contact nos. for any grievance /
complaint, contractor’s information, First Aid Box, emergency nos. like fire, police, medical, ambulance etc
has been displayed at Attari Parking.
7.13 Compliance to Social Impacts Mitigation
34. Based on the above assessment the Compliance to social impacts mitigation during project planning,
design and implementation stages.
Table 4: Compliance to Social Impacts Mitigation
Sl.
No.
Social Safeguard
Issues
Findings Remarks
1 Impact minimization
measures The selected sites are exists on
government land. Livelihood
pattern of the any person will not
affect due to the project.
The project categorized as “C” for involuntary resettlement (IR) as well as
Indigenous people development as per
ADB’s Safeguard Policy Statement (SPS-
2009).
2 Census and socio-
economic survey As no impact noticed, hence not
carried out.
3 Land acquisition Department of Tourism is in
possession of the land in which the
sub-project is being implemented.
DoT acquired the land by giving
significantly higher compensation
to 17 people through the process of
public consultation with the
stakeholders. .
Approval Note of ADB’s Special Project Administration Mission on 11th June 2013
is attached as Appendix 3.
4 Entitlements ADB’s policy of IR shall be applicable, if any impact seen.
5 Public consultation
and disclosure Public consultation has been carried
during the project preparation and
implementation stage
Impacts on livelihood and people
resettlement issues are not envisaged as
part of the project.
6 Medical facility at site First Aid Box has been provided
and necessary training in case of
emergency have also been provided
by CDO
CDO PIU is visiting the site in a regular
interval and all the time she organising the
awareness meeting with labourer
especially with women
7 Safety of Labourers Personal protection equipment has
been provided by the contractor.
Most of workers/labours are seem
to use Personal Protection
Equipment (PPE).
Contractor’s representative has been
advice to encourage to put on PPE to the
labourers. Mosquito nets have also been
provided to prevent malaria etc.
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 14
8 Impact on tribal
people Impact on tribal people is not
envisaged as part of the project.
Amritsar district as such is not part
of the notified Fifth Schedule Area.
-
9 Resettlement sites Resettlement site not envisaged.
10 Socio-economic
rehabilitation
measures
Not applicable
11 Implementation
arrangement Social safeguard implementation is
part of the contract of IDIPT. PMU
along with the PIU personnel is the
core group responsible for social
safeguard implementation at the
project site. PMU and PIU is
assisting in overall implementation
of social safeguards.
Environment Safeguards Specialist and
Social Safeguards Specialist are positioned
at PMU along with Community
Development Specialist and 1 Community
Development Officer also supporting from
each PIU to PMU in implementation.
12 Grievance Redressal
Mechanism GRC has been formed.
8. SUMMARY FINDINGS/ RECOMMENDATION
35. In this Sub-Project intervention, full or partial, permanent or temporary, physical and economic
displacements were absent. There will not be any adverse impact on people, livelihood, land or structure and
common property resources. The land was acquired in lieu of the DoT’s land which was taken by MHA for
Integrated Check-Post. It is concluded from this due diligence study that, the proposed Attari Parking
development has not changed substantially the present land use; there was no issue or litigation of land
acquisition and resettlement. IR and IP impact are absent for this subproject.
36. The key observation of the Due Diligence for the social impacts are summarised as follows
The land is in the name of Tourism Department, GoP and is free from all encumbrances.
The sub-project does not involve any land acquisition or removal of encroachments.
The project site is neatly fenced with boundary wall and hence encroachment of land has been
prevented.
As per ADB SPS 2009, the sub –project has been categorised as “C” type project, having no Involuntary Resettlement (IR) and Indigenous People Development (IP).
The requisite mentioned in the RF has been fulfilled during the project implementation, which
includes maintaining gender equality, equal wages, community consultations etc.
GRC formation is in process and necessary steps have been taken
Disclosure of RF document in local language not yet done
37. The due diligence study concludes that the project does not involve any outstanding social
safeguards issues. At the same time, PMU/PIU may urge the DSC / Contractors to address the issues
identified during the due diligence exercise.
Project Management Consultant for Punjab
Heritage and Tourism Promotion Board, Punjab
Infrastructure Development Investment
Program For Tourism , Tranche-1
Social Safeguards Due Diligence Report- Parking Facility at Attari 15
APPENDICES
LIST OF APPENDIX
APPENDIX 1: INVOLUNTARY RESETTLEMENT IMPACT CATEGORIZATION FORM
APPENDIX 2: INGENIOUS PEOPLE CATEGORIZATION FORM
APPENDIX 3: ASIAN DEVELOPMENT BANK’S APPROVAL OF ATTARI PARKING SUBPROJECT AND NO RP REQUIRED
APPENDIX 4: ATTENDANCE SHEET OF PARTICIPANTS IN STAKEHOLDER CONSULTATION
APPENDIX 5: PROJECT MANAGEMENT STRUCTURE (AS PROPOSED IN PAM)
APPENDIX 6: GRIEVANCE REDRESSAL MECHANISMS
Project Management Consultant for PHTPB, Punjab Appendix -1
Involuntary Resettlement Categorization Form
APPENDIX 1: INVOLUNTARY RESETTLEMENT CATEGORISATION FORM
Project Management Consultant for PHTPB, Punjab Appendix -2
Indigenous People Categorization Form
APPENDIX 2: INDIGENOUS PEOPLE CATEGORISATION FORM
Project Management Consultant for PHTPB, Punjab Appendix -2
Indigenous People Categorization Form
Project Management Consultant for PHTPB, Punjab Appendix -3
APPENDIX 3A: ASIAN DEVELOPMENT BANK’S APPROVAL OF ATTARI PARKING SUBPROJECT AND NO RP REQUIRED
Project Management Consultant for PHTPB, Punjab Appendix -4
APPENDIX 4: ATTENDANCE SHEET OF PARTICIPANTS IN STAKEHOLDERS CONSULTATION
Project Management Consultant for PHTPB, Punjab Appendix -4
Project Management Consultant for PHTPB, Punjab Appendix -4
Project Management Consultant for PHTPB, Punjab Appendix -4
Project Management Consultant for PHTPB, Punjab Appendix -4
Project Management Consultant for PHTPB, Punjab Appendix -4
APPENDIX 4: ATTENDANCE SHEET OF PARTICIPANTS (WOMEN)
Project Management Consultant for PHTPB, Punjab Appendix -4
Project Management Consultant for PHTPB, Punjab Appendix -4
Project Management Consultant for PHTPB, Punjab Appendix -4
Project Management Consultant for PHTPB, Punjab Appendix -5
APPENDIX 5: PROJECT ORGANIZATION STRUCTURE (AS PROPOSED IN PAM)
The Project management flow chart showing the reporting lines and key organizations involved in
implementation is shown in Figures 1.
Project Implementation Organizations – Roles and Responsibilities
Implementation
Organization
Management Roles and Responsibilities
Executing agency Government of Punjab through Department of Tourism (DOT)
Assume overall responsibility for the execution of the MFF and reporting;
Engage adequate permanent or fixed-term staff to implement the MFF;
Setup a state-level project management unit and project implementation units;
Provide overall strategic guidance on technical supervision and project execution;
and
Ensure overall compliance with the loan covenants.
Implementing agency Punjab Heritage and Tourism Promotion Board (PHTPB)
Project planning and budgeting;
Day-to-day assistance, supervision and guidance for the project implementation
units and their consultants;
Review subprojects for due diligence requirements and approve subproject
proposals;
Bidding, evaluation and contract award;
Managing and disbursing funds;
Review compliance with loan covenants, contract specifications, work plans and
quality control;
Consolidate and submit progress reports, finance and accounting / audit reports, and
matters requiring higher-level decision to state level empowered committee (SLEC)
and ADB
ADB Loan processing activities and signing of loan agreement;
Recruitment of implementation capacity development consultant;
Procurement supervision;
Disbursement;
Project administration reviews and missions;
Reviewing compliance with loan covenants;
Change in project scope or implementation arrangements; and
Reallocation of loan proceeds.
State-Level Empowered
Committee (SLEC)
act as a policy making body;
Provide overall advice and guidance to the state's EA and PMU; and
Accord all approvals under the MFF.
State Level Project Empowered Committee.
State-Level Empowered Committee (SLEC) have been established in Punjab, chaired by Chief Secretary, Govt.
of Punjab with Principal Secretary/Secretary of the Department of Tourism as member secretary and comprised of
secretaries from relevant line departments as indicated in the Facility Administration Manual (FAM). The SLEC
have been empowered to take all decisions on behalf of the State and will (i) act as a policy making body, (ii)
provide overall advice and guidance to the State’s executing agency and project management unit (PMU), and (iii) accord all approvals under the Project.
The members of SLEC for the Punjab are as follows: Chief Secretary (Chair); the Principal Secretary / Secretary
of the Department of Tourism; the Principal Secretary / Secretary of Finance; Finance Commissioner, Department
of Forests and Wildlife Preservation; Principal Secretary / Secretary, Public Works Department; Principal
Project Management Consultant for PHTPB, Punjab Appendix -5
Secretary / Secretary, Department of Local Government; Secretary, Department of Rural Development and
Panchayat; Principal Secretary / Secretary, Irrigation; Director, Department of Cultural Affairs, Archives,
Archaeology and Museum; Representative, Archaeological Survey of India; Principal Secretary / Secretary,
Department of Fisheries; Director, Department of Tourism; and Principal Secretary/Secretary, Department of
Housing and Urban Development.
Executing Agencies:
The Department of Tourism (DOT), Government of Punjab is the executing agencies of the Punjab. All necessary
powers to: (i) assume overall responsibility for the execution of the tranche; (ii) engage adequate permanent or
fixed-term staff to implement the tranche; (iii) setup a state-level PMU and project implementation units (PIUs);
(iv) provide overall strategic guidance on technical supervision and project execution; and (v) ensure overall
compliance with the loan covenants, will be delegated to the respective executing agencies. The Project
Implementation flow chart showing the reporting lines and key agencies involved in implementation is shown in
Figure below.
Implementing Agency:
The Punjab Heritage and Tourism Promotion Board (PHTPB) is the implementing agency in Punjab
Project Management Unit:
PHTPB have a PMU, headed by a full-time Program Director (PD), and consisting of personnel drawn from
relevant line departments and market. The PMU is being supported by a team of consultants including
Environmental Safeguard Specialist. The PMU is the nodal agency for overall management of all program
activities and are responsible for: (i) project planning and budgeting; (ii) providing day-to-day assistance,
supervision and guidance for the project implementation units (PIUs) and their consultants; (iii) reviewing
subprojects to satisfy ADB’s due diligence requirements and approving subproject proposals submitted by PIUs
and line departments; (iv) bidding, evaluation and contract award; (v) managing and disbursing funds; (vi)
reviewing compliance with loan covenants, contract specifications, work plans and quality control; (vii)
consolidating and submitting progress reports, finance and accounting/audit reports, and matters requiring higher-
level decision, to the SLEC and ADB.
The State shall ensure that (i) specific divisions in the Project management units is staffed for financial
management; (ii) transparent procedures are established for financial transactions; (iii) the PMUs follow
government rules and procedures for all expense and revenue items including cash and for proper and accurate
maintenance of financial records; and (iv) a project website remains established to provide information on Project
implementation including procurement.
Project Implementation Units:
The Implementing Agency had already established two PIUs, one for each circuit (Eastern and Western) at
Rupnagar (Ropar) and Amritsar respectively for the implementation and monitoring of subprojects. It comprises
the personnel drawn from relevant line departments and outsourced, and each headed by a project manager and
supported by Community Development Officer (CDO) for effective implementation of the RF and ensures the
safeguard compliance provisions of the investment program. The PIUs are responsible for: (i) prioritizing and
preparing subproject proposals; (ii) providing day-to-day assistance, supervision and guidance to the design and
supervision consultants (DSC); (iii) conducting detailed assessments and surveys including public consultation
and input from stakeholders; (iv) preparing detailed designs, specifications, schedule of quantity, bidding
documents, and related documentation; (v) implementing civil works and related activities; (vi) reporting to
Project Management Consultant for PHTPB, Punjab Appendix -5
PMU; (vii) preparing regular progress reports for the SLEC, the executing agency and ADB through PMU; (viii)
supervising construction, conducting quality control, approving progress payments to contractors; and (ix)
maintaining records and accounts on an up-to-date basis and making these available to ADB, its missions, or
auditors for inspection.
Asian Development Bank Government of India
Government of Punjab
State Level Empowered
Committee
Department of Tourism
Mission Director - Principal
PUNJAB HERITAGE & TOURISM
PROMOTION BOARD
PROJECT MANAGEMENT UNIT
Design &
Supervision
Consultants,
Amritsar
Project
Implementation
Unit,
Amritsar
Project
Implementation
Cell, State Forest
Department
Project
Implementation
Unit,
Ropar
Design &
Supervision
Consultants,
Ropar
Project Management & Design
Consultants
District Level Committees
Chairperson- Deputy Commissioners
Forest & Wildlife
Public Works
Local Government
Rural Development
Irrigation
Culture, Arts & Museum
Archaeological Survey
Northern Railways
Fisheries
Housing & Urban
LINE AGENCIES
Third Party Quality Audit
Consultants, Benefit Monitoring &
Evaluation Consultants,
External Monitoring & Evaluation
Consultant
EXECUTING AGENCY
POLICY ADVISORY & APPROVALS
IMPLEMENTING AGENCY
Project Management Flow Chart
Project Management Consultant for PHTPB, Punjab Appendix -6
APPENDIX 6: GRIEVANCE REDRESSAL MECHANISMS
The structure suggested of Grievance Redress Committee (GRC) in RF at PIU is as follows. For all the IDIPT sub
projects, the affected person/aggrieved party can give their grievance verbally to Site Engineer or in written to the
Project Manager of PIU. Grievances of affected person will first be brought to the attention of the Site Engineer
PIU, who can resolve the issue at site level. If the matter is not solved within 7 days period at site, it will be
brought to the Grievance Redress Committee (GRC) constituted for the purpose in PIU. This GRC shall discuss
the issue in its monthly meeting and resolve the issues within one month of time after receiving the grievance. If
the matter is not resolved by GRC at PIU level within stipulated time, it shall be referred to GRC at PMU level by
Project Manager PIU. If the matter is still not addressed, the same may refer to Executive Committee / State Level
Empowered Committee (SLEC). The grievance redress process flow chart is shown in Figure.
In each PIU, there shall be one GRC, which will include mentioned members;
Project Manager (PIU), Chairperson
District Tourist Officer of Department of
Tourism, Govt. Of Punjab,
Community Development Officer of PIU,
Nominated representative of Deputy
Commissioner and
Nominated representative of Municipal
Commissioner.
The committee required to meet at least once
in every month. Agenda of meeting shall be
circulated to all the members and affected
persons/aggrieved party along with venue,
date and time; informed in written at least 7
days in advance of meeting. The matters
shall remain with GRC at PIU level for one
month and if grievance is not resolved
within this time period, the matter shall be
referred to GRC at PMU.
Grievance Redress Committee (GRC) at
PMU. The matters not resolved by the GRC
at PIU level within one month shall come under GRC at PMU. GRC at PMU will include:
Additional Project Director (APD),
Community Development Specialist, and
Environment Safeguards Specialist of PMU.
The Committee shall be headed by APD of PMU. This committee shall look at the matters, which are referred to
and not resolved by GRC at PIU level.
GRC at PMU shall discuss the issue and try to resolve it and inform the PIU accordingly. If the matter is not
resolved by the GRC at PMU level within one month of time, the aggrieved person/party can bring the matter to
GRC at PIU
Aggrieved
Person/Party
Minor
Grievances
GRC at PMU
Executive Committee / State Level
Empowered Committee
Grievances Addressed
Major
Grievances
PIU/NGO
(Project Manager)
Grievances
Addressed
Grievances Addressed
Grievances not addressed
Grievances not addressed
Grievances not addressed
Grievance Redress Mechanism Flow Chart
Project Management Consultant for PHTPB, Punjab Appendix -6
The SLEC. The PIU shall keep records of all grievances received including contact details of complainant, date of
receiving the complaint, nature of grievance, agreed corrective actions and the date these were affected and final
outcome.
NECESSARY INSTRUCTIONS ISSUED FROM ADDITIONAL PROJECT DIRECTOR to PIUs
Project Management Consultant for PHTPB, Punjab Appendix -6
Project Management Consultant for PHTPB, Punjab Appendix -6
Project Management Consultant for PHTPB, Punjab Appendix -6
Project Management Consultant for PHTPB, Punjab Appendix -6
Project Management Consultant for PHTPB, Punjab Appendix -6