REPORT NO 151-08638-00_RPT-02_R2
RESOURCE ESTIMATION UPDATE AND TECHNICAL REPORT PAK LITHIUM PROJECT RED LAKE MINING DISTRICT, ONTARIO
MAY 2016
Houston Lake Mining Inc.
Project no: 151-08683-00_RPT-02_R2 Issue Date: May 10, 2016 Effective Date: March 4, 2016 Prepared by: Todd McCracken, P. Geo. – WSP Canada Inc. 2565 Kingsway, Unit 2 Sudbury, ON P3B 2G1
Phone: +1 705-674-0119 Fax: +1 705-674-0125 www.wspgroup.com
RESOURCE ESTIMATION UPDATE AND TECHNICAL REPORT
PAK LITHIUM PROJECT
Red Lake Mining District, Ontario
S I G N A T U R E S
PREPARED BY
“Original signed and stamped by Todd McCracken, P.Geo.” Todd McCracken, P. Geo. Manager - Geology
i
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
R E V I S I O N H I S T O R Y
Rev. No Issue Date Prepared by Description of Revision
0 April 22, 2016 Todd McCracken First draft for Client review
1 May 6, 2016 Todd McCracken For Client review
2 May 10, 2016 Todd McCracken Issued to Client
ii
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
TABLE OF CONTENTS 1 SUMMARY...................................................................................... 1
1.1 GEOLOGY ............................................................................................................. 1
1.2 CHANNEL SAMPLING AND DIAMOND DRILLING ............................................ 2
1.3 RESOURCE ESTIMATION ................................................................................... 2
1.4 RECOMMENDATIONS ......................................................................................... 4
2 INTRODUCTION ............................................................................. 5
3 RELIANCE ON OTHER EXPERTS ................................................ 6
4 PROPERTY DESCRIPTION AND LOCATION ............................... 7
4.1 LOCATION ............................................................................................................ 7
4.1 MINERAL DISPOSITION ...................................................................................... 7
4.2 TENURE RIGHTS ................................................................................................. 7
4.3 ROYALTIES AND RELATED INFORMATION ..................................................... 9
4.4 ENVIRONMENTAL LIABILITIES ........................................................................ 12
4.5 PERMITS ............................................................................................................. 12
4.6 OTHER RELEVANT FACTORS ......................................................................... 12
5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE, AND PHYSIOGRAPHY.............................. 13
5.1 ACCESS .............................................................................................................. 13
5.2 CLIMATE ............................................................................................................. 15
5.3 INFRASTRUCTURE ............................................................................................ 15
5.4 SITE TOPOGRAPHY, ELEVATION, AND VEGETATION ................................. 15
iii
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
6 HISTORY ...................................................................................... 16
6.1 ONTARIO GEOLOGICAL SURVEY PROGRAMS ............................................. 16
6.2 HISTORIC EXPLORATION ................................................................................. 16
7 GEOLOGICAL SETTING AND MINERALIZATION ..................... 19
7.1 REGIONAL GEOLOGY ....................................................................................... 19
7.2 PROJECT GEOLOGY ......................................................................................... 21
7.3 MINERALIZATION .............................................................................................. 25
8 DEPOSIT TYPES .......................................................................... 30
9 EXPLORATION ............................................................................ 34
10 DRILLING ..................................................................................... 36
10.1 2013 DRILL CAMPAIGN ..................................................................................... 36
10.2 2014 DRILL CAMPAIGN ..................................................................................... 40
10.3 2015 DRILL CAMPAIGN ..................................................................................... 44
10.4 QP’S OPINION .................................................................................................... 48
11 SAMPLE PREPARATION, ANALYSES AND SECURITY .................................................................................... 49
11.1 2013 SAMPLE PREPARATION .......................................................................... 49
11.2 2014 SAMPLE PREPARATION .......................................................................... 49
11.3 2015 SAMPLE PREPARATION .......................................................................... 50
11.4 2013 ANALYTICAL PROCEDURE ..................................................................... 50
11.5 2014 ANALYTICAL PROCEDURE ..................................................................... 51
11.6 2015 ANALYTICAL PROCEDURE ..................................................................... 52
11.7 2014 QUALITY ASSURANCE / QUALITY CONTROL (QA/QC) ....................... 53
11.8 2015 QUALITY ASSURANCE / QUALITY CONTROL (QA/QC) ....................... 59
11.9 QP’S OPINION .................................................................................................... 62
iv
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
12 DATA VERIFICATION .................................................................. 63
12.1 SITE VISIT ........................................................................................................... 63
12.2 INDEPENDENT SAMPLING ............................................................................... 63
12.3 DATABASE VALIDATION .................................................................................. 63
12.4 QP’S OPINION .................................................................................................... 63
13 MINERAL PROCESSING AND METALLURGICAL TESTING....................................................................................... 64
13.1 ELECTRON MICROPROBE STUDY OF SPODUMENE FROM THE PAKEAGAMA LAKE PEGMATITE ............................................................ 64
14 MINERAL RESOURCE ESTIMATES ........................................... 68
14.1 DATABASE ......................................................................................................... 68
14.2 SPECIFIC GRAVITY ........................................................................................... 69
14.3 TOPOGRAPHIC DATA ....................................................................................... 70
14.4 GEOLOGICAL INTERPRETATION .................................................................... 71
14.5 EXPLORATORY DATA ANALYSIS ................................................................... 79
14.6 SPATIAL ANALYSIS .......................................................................................... 81
14.7 RESOURCE BLOCK MODEL ............................................................................. 81
14.8 RESOURCE CLASSIFICATION ......................................................................... 84
14.9 MINERAL RESOURCE TABULATION .............................................................. 84
14.10 VALIDATION ....................................................................................................... 91
14.11 PREVIOUS ESTIMATES ..................................................................................... 97
v
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
15 ADJACENT PROPERTIES........................................................... 98
16 OTHER RELEVANT DATA AND INFORMATION ....................... 99
17 INTERPRETATIONS AND CONCLUSIONS .............................. 100
18 RECOMMENDATIONS ............................................................... 101
19 REFERENCES ............................................................................ 102
20 CERTIFICATE OF QUALIFIED PERSON .................................. 104
T A B L E S
TABLE 1.1 PAK LAKE RESOURCE SUMMARY ...................................................... 3
TABLE 4.1 SUMMARY OF MINERAL DISPOSITION .............................................. 9
TABLE 6.1 PROPERTY SUMMARY ....................................................................... 17
TABLE 9.1 2015 CHANNEL LOCATION SUMMARY ............................................. 34
TABLE 9.2 2015 CHANNEL RESULTS SUMMARY ............................................... 35
TABLE 10.1 DRILL COLLARS .................................................................................. 37
TABLE 10.2 2014 DRILL SUMMARY........................................................................ 41
TABLE 10.3 2015 DRILL RESULTS ......................................................................... 45
TABLE 11.1 2013 SAMPLE PREPARATION PROCEDURE - ACME ...................... 49
TABLE 11.2 2014 SAMPLE PREPARATION PROCEDURE - ACME ...................... 49
TABLE 11.3 SAMPLE PREPARATION PROCEDURE – ACTLABS AND AGAT..................................................................................................... 50
TABLE 11.4 2013 ANALYTICAL METHODOLOGY .................................................. 51
TABLE 11.5 ANALYTICAL DETECTION LIMITS ...................................................... 51
TABLE 11.6 2014 ANALYTICAL METHODOLOGY - ACME .................................... 52
TABLE 11.7 2014 ANALYTICAL DETECTION LIMITS - ACME ............................... 52
TABLE 11.8 2015 ANALYTICAL METHODOLOGY – ACTLABS AND AGAT..................................................................................................... 53
TABLE 11.9 2015 ANALYTICAL DETECTION LIMITS - ACTLABS AND AGAT..................................................................................................... 53
TABLE 11.10 COMPOSITION OF STANDARDS ....................................................... 58
TABLE 11.11 COMPOSITION OF STANDARDS ....................................................... 61
TABLE 12.1 CONVERSION FACTORS .................................................................... 63
TABLE 14.1 DATABASE SUMMARY........................................................................ 68
TABLE 14.2 PAK SPECIFIC GRAVITY SUMMARY ................................................. 70
vi
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
TABLE 14.3 WIREFRAME SUMMARY ..................................................................... 72
TABLE 14.4 SAMPLE SUMMARY BY DOMAIN ....................................................... 79
TABLE 14.5 GRADE CAPPING SUMMARY BY DOMAIN ....................................... 80
TABLE 14.6 COMPOSITING SUMMARY BY DOMAIN ............................................ 81
TABLE 14.7 SUMMARY OF PARENT BLOCK MODEL ........................................... 82
TABLE 14.8 SEARCH ELLIPSE SUMMARY ............................................................ 83
TABLE 14.9 ESTIMATION CRITERIA SUMMARY ................................................... 83
TABLE 14.10 UIZ MEASURED RESOURCE GRADE TONNAGE ............................. 85
TABLE 14.11 UIZ INDICATED RESOURCE GRADE TONNAGE .............................. 86
TABLE 14.12 UIZ INFERRED RESOURCE GRADE TONNAGE ............................... 86
TABLE 14.13 CIZ INDICATED RESOURCE GRADE TONNAGE .............................. 87
TABLE 14.14 CIZ INFERRED RESOURCE GRADE TONNAGE ............................... 87
TABLE 14.15 LIZ MEASURED RESOURCE GRADE TONNAGE ............................. 88
TABLE 14.16 LIZ INDICATED RESOURCE GRADE TONNAGE .............................. 88
TABLE 14.17 LIZ INFERRED RESOURCE GRADE TONNAGE ............................... 89
TABLE 14.18 PAK RESOURCE SUMMARY .............................................................. 90
TABLE 14.19 GLOBAL COMPARISON ...................................................................... 94
TABLE 14.20 COMPARISON OF PARAMETERS ...................................................... 97
TABLE 18.1 PHASE 1 BUDGET SUMMARY ......................................................... 101
TABLE 18.2 PHASE 2 BUDGET SUMMARY ......................................................... 101
F I G U R E S
FIGURE 4.1 LOCATION MAP ..................................................................................... 8
FIGURE 4.2 CLAIM MAP .......................................................................................... 11
FIGURE 5.1 PROPERTY ACCESS ........................................................................... 14
FIGURE 7.1 ARCHEAN SUB PROVINCES .............................................................. 19
FIGURE 7.2 REGIONAL GEOLOGY......................................................................... 20
FIGURE 7.3 PROPERTY GEOLOGY ....................................................................... 23
FIGURE 7.4 DETAILED PROPERTY GEOLOGY ..................................................... 24
FIGURE 7.5 UIZ ......................................................................................................... 26
FIGURE 7.6 CIZ ......................................................................................................... 27
FIGURE 7.7 LIZ ......................................................................................................... 28
FIGURE 8.1 TANCO PEGMATITE AND PAK PEGMATITE LOCATION ................. 30
FIGURE 8.2 DIVISION OF RARE METAL PEGMATITES ........................................ 31
FIGURE 8.3 DEPOSIT MODEL ................................................................................. 32
FIGURE 10.1 DIAMOND DRILL COLLAR LOCATIONS............................................. 38
FIGURE 11.1 2014 CESIUM BLANK CHART ............................................................. 54
FIGURE 11.2 2014 RUBIDIUM BLANK CHART ......................................................... 54
FIGURE 11.3 2014 TANTALUM BLANK CHART ....................................................... 55
vii
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
FIGURE 11.4 2014 LITHIUM BLANK CHART ............................................................ 55
FIGURE 11.5 2014 CESIUM DUPLICATE CHART .................................................... 56
FIGURE 11.6 2014 RUBIDIUM DUPLICATE CHART ................................................. 57
FIGURE 11.7 2014 TANTALUM DUPLICATE CHART ............................................... 57
FIGURE 11.8 2014 LITHIUM DUPLICATE CHART .................................................... 58
FIGURE 11.9 2015 CESIUM BLANK CHART ............................................................. 59
FIGURE 11.10 2015 RUBIDIUM BLANK CHART ......................................................... 60
FIGURE 11.11 2015 TANTALUM BLANK CHART ....................................................... 60
FIGURE 11.12 2015 LITHIUM BLANK CHART ............................................................ 61
FIGURE 13.1 THIN SECTION LOCATION ................................................................. 66
FIGURE 14.1 SPECIFIC GRAVITY STATION ............................................................ 69
FIGURE 14.2 PAK TOPOGRAPHIC IMAGE ............................................................... 70
FIGURE 14.3 UIZ WIREFRAME (LOOKING SOUTHEAST - NOT TO SCALE) ................................................................................................. 73
FIGURE 14.4 UIZ WIREFRAME (LOOKING NORTHWEST - NOT TO SCALE) ................................................................................................. 74
FIGURE 14.5 CIZ WIREFRAME (LOOKING SOUTHEAST - NOT TO SCALE) ................................................................................................. 75
FIGURE 14.6 CIZ WIREFRAME (LOOKING NORTHEAST - NOT TO SCALE) ................................................................................................. 76
FIGURE 14.7 LIZ WIREFRAME (LOOKING SOUTHWEST – NOT TO SCALE) ................................................................................................. 77
FIGURE 14.8 LIZ WIREFRAME (LOOKING NORTHEAST – NOT TO SCALE) ................................................................................................. 78
FIGURE 14.9 PAK VALIDATION SECTION 00SE ...................................................... 91
FIGURE 14.10 PAK VALIDATION SECTION 050 NW ................................................. 92
FIGURE 14.11 PAK VALIDATION SECTION 150 SE ................................................... 93
FIGURE 14.12 LI2O SWATH PLOT ............................................................................... 95
FIGURE 14.13 TA2O5 SWATH PLOT ............................................................................ 95
FIGURE 14.14 CS2O SWATH PLOT ............................................................................. 96
FIGURE 14.15 RB2O SWATH PLOT ............................................................................. 96
A P P E N D I X
APPENDIX A – CONTROL CHARTS
viii
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
A B B R E V I A T I O N S
UNITS OF MEASURE
above mean sea level ................................. amsl acre ................................................................. ac ampere ............................................................. A annum (year) .................................................... a billion ................................................................ B billion tonnes ................................................... Bt billion years ago ............................................. Ga British thermal unit .......................................BTU Centimetre ..................................................... cm cubic centimetre............................................ cm
3
cubic feet per minute .................................... cfm cubic feet per second ................................... ft
3/s
cubic foot ........................................................ ft3
cubic inch ......................................................... in cubic metre .................................................... m
3
cubic yard ...................................................... yd3
Coefficients of Variation ................................Cvs day .................................................................... d days per week ............................................. d/wk days per year (annum) .................................. d/a dead weight tonnes ....................................DWT decibel adjusted ............................................. Ba decibel ........................................................... dB degree ............................................................... ° degrees Celsius .............................................. °C diameter ............................................................ ø dollar (American) ......................................... US$ dollar (Canadian) ...................................... CDN$ dry metric ton ................................................ dmt foot .................................................................... ft gallon ............................................................. gal gallons per minute ....................................... gpm Gigajoule ........................................................ GJ Gigapascal .................................................. GPA Gigawatt ........................................................ GW Gram ................................................................. g grams per litre ................................................ g/L grams per tonne.............................................. g/t greater than ...................................................... > hectare (10,000 m
2) ........................................ ha
hertz ............................................................... Hz horsepower ..................................................... hp hour ................................................................... h hours per day ................................................. h/d hours per week ........................................... h/wk hours per year ................................................ h/a inch .................................................................. in
kilo (thousand)................................................... k kilogram ........................................................... kg kilograms per cubic metre ......................... kg/m
3
kilograms per hour .......................................kg/h kilograms per square metre ...................... kg/m
2
kilometre ......................................................... km kilometre ......................................................... km kilometres per hour .....................................km/h kilopascal ..................................................... kPa kiloton ............................................................... kt kilovolt ............................................................ kV kilovolt-ampere ............................................. kVa kilowatt .......................................................... kW kilowatt hour ................................................ kWh kilowatt hours per tonne ............................ kWh/t kilowatt hours per year ............................. kWh/a less than ........................................................... < litre ................................................................... L litres per minute............................................ L/m megabytes per second ................................Mb/s megapascal ................................................. Mpa megavolt-ampere ......................................... Mva megawatt ...................................................... MW metre ............................................................... m metres above sea level ............................... masl metres Baltic sea level ................................ mbsl metres per minute .....................................m/min metres per second ........................................ m/s microns .......................................................... µm milligram ........................................................ mg milligrams per litre ...................................... mg/L millilitre .......................................................... mL millimetre ...................................................... mm million .............................................................. M million bank cubic metres .......................... Mbm
3
million bank cubic metres per annum .... Mbm3/a
million tonnes ................................................. Mt minute (plane angle) .......................................... ' minute (time) ................................................. min month ............................................................ mo ounce .............................................................. oz pascal ............................................................. Pa centipoise ................................................. mPa∙s parts per million ........................................... ppm parts per billion ............................................. ppb percent ............................................................ % pound(s) ........................................................... lb
ix
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
pounds per square inch ................................. psi revolutions per minute ..................................rpm second (plane angle) ........................................ " second (time) .................................................... s short ton (2,000 lb) .......................................... st short tons per day ......................................... st/d short tons per year ........................................ st/y specific gravity ............................................... SG square centimetre ......................................... cm
2
square foot ...................................................... ft2
square inch ..................................................... in2
square kilometre .......................................... km2 square metre .................................................. m
2
three-dimensional........................................... 3D tonne (1,000 kg) (metric ton) ............................. t tonnes per day ............................................... t/d tonnes per hour .............................................. t/h tonnes per year .............................................. t/a tonnes seconds per hour metre cubed .... ts/hm
3
volt .................................................................... V week ............................................................... wk weight/weight ............................................... w/w wet metric ton ............................................... wmt
ACRONYMS
CIM .................................................................... Canadian Institute of Mining, Metallurgy and Petroleum CIZ ................................................................................................................... Central Intermediate Zone DSO ............................................................................................................................ Direct Shipping Ore DTM ......................................................................................................................... Digital Terrain Model GPS .............................................................................................................. Global Positioning Satellites GSC ............................................................................................................ Geological Survey of Canada HLM ......................................................................................................................... Houston Lake Mining ID
2 ..................................................................................................................... Inverse Distance Squared
ISO .................................................................................................. International Standards Organization LCT ................................................................................................................... Lithium Cesium Tantalum LIZ ......................................................................................................................Lower Intermediate Zone LRC ................................................................................................................... Lithium Rubidium Cesium MMI ................................................................................................................................. Mobile Metal Ion MNDM ................................................................................ Ministry of Northern Development and Mines NI ............................................................................................................................... National Instrument NN ............................................................................................................................... Nearest Neighbour NSR ........................................................................................................................... Net Smelter Royalty OGS .................................................................................................................Ontario Geological Survey P. Geo. ............................................................................................................... Professional Geoscientist PFS ........................................................................................................................... Pre-Feasibility Study the Property .................................................................................................... PAK Rare Metals Property QA / QC ............................................................................................ Quality Assurance / Quality Control QP ................................................................................................................................... Qualified Person REE .......................................................................................................................... Rare Earth Elements SG ..................................................................................................................................... Specific Gravity SQUI .................................................................................................... Spodumene + Quartz Intergrowth TDC ............................................................................................................................... Top Dead Centre UIZ .....................................................................................................................Upper Intermediate Zone VLF ........................................................................................................................... Very Low Frequency WSP .............................................................................................................................. WSP Canada Inc.
1
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
1 SUMMARY The PAK Lithium Property (the Property) is located approximately 175 km north of Red Lake, in
northwestern Ontario.
Houston Lake Mining Inc. (TSX.V: HLM) owns the 100% rights to the Property claims. HLM’s land
holdings in the area comprise 417 contiguous unsurveyed claim units for a total of 6,672 hectares.
Two separate royalty agreements are in place for specific claim units and are subject to buyout
clauses.
There has been no commercial production and little exploration prior to HLM’s involvement on the
Property.
WSP Canada Inc. (WSP) was commissioned by HLM in August 2015 to complete an update to the
resource estimation on the Property based on additional diamond drilling and a bulk sample. WSP
prepared this report in accordance with National Instrument 43-101 (NI 43-101) Standards of
Disclosure for Mineral Projects.
1.1 GEOLOGY
The Property area is situated along the boundary between the Berens River and Sachigo
Subprovinces (Card and Ciesielski, 1986 and Card, 1990) of the Archean Superior Province of the
Canadian Shield.
The Property is underlain by the northwestern extension of the North Spirit Lake greenstone belt.
The greenstone belt within the Property boundary is bounded to the north by biotitic tonalities and
granites of the Whiteloon Lake Batholith (Sachigo Subprovince), and to the south by gneissic
granodiorites and granites of the Bear Head Lake Batholith (Berens River Subprovince).
The three main lithological domains on the Property are: metasedimentary units composed of pelitic
sediments, iron formation and conglomerate to the north; mafic metavolcanic and related
metasedimentary rocks to the south; and the Pakeagama Lake peraluminous granite and mica pluton
emplaced along the unconformable contact between metasedimentary and metavolcanics
metasedimentary rocks.
The Pakeagama Lake granitic pegmatite is a highly evolved, zoned, complex-type, petalite-subtype
Lithium Cesium Tantalum (LCT) pegmatite with highly anomalous values of lithium, cesium, tantalum,
and rubidium.
The Pakeagama Lake pegmatite is the second largest complex-type petalite subtype pegmatite dyke
in Ontario (Breaks et al, 1999).
Peter Vanstone, P. Geo., former chief geologist at the Tanco Mine, consolidated the pegmatite zones
using commonly accepted pegmatite nomenclature and Tanco zone mineralogical criteria. The three
main pegmatite zones identified in this work are (from northwest to southwest and perpendicular to
the strike of the pegmatite) the Central Intermediate Zone (CIZ – tantalum, rubidium, and cesium
enriched), Upper Intermediate Zone (UIZ - lithium and rubidium enriched), and the Lower
Intermediate Zone (LIZ – lithium and rubidium enriched). There is also a Wall Zone and Border Zone
but their extent is limited.
2
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
The Property deposit model is a highly evolved, granitic, rare-element lithium cesium- tantalum
bearing (LCT), complex Type – Spodumene or Petalite Subtype pegmatite similar to the Tanco
pegmatite in the Bird River belt in southeastern Manitoba, which is the best known and a world-class
example of this type of deposit model.
1.2 CHANNEL SAMPLING AND DIAMOND DRILLING
A total of 29 channels totaling 218 metres were cut and samples collected between 2001 and 2015.
A total of 24 NQ diamond drillholes totaling 4,693 metres were completed between 2013 and in 2015.
A series of percussion holes were drilled for the bulk sample. Sample collection, sample preparation,
and sample analysis were completed to industry standards.
A Quality Assurance / Quality Control (QA/QC) program was in place for the diamond drilling
programs and the channel programs after 2011. The 2001 channel program did not include
standards and relied on the Analytical Laboratory’s internal QA/QC program.
1.3 RESOURCE ESTIMATION
The geological dataset generated by HLM, consisting of data derived from diamond drilling and
surface channel sampling, has been deemed suitable to support geological interpretation and
resource estimate.
The estimation of the three domains was completed using capped and composited sample data on a
2.5 m x 2.5 m x 2.5 m block. The estimation was completed using Inverse Distance Squared (ID2)
with Nearest Neighbour (NN) as a validation purposes.
The PAK mineral resource was developed on three domains at a Li2O equivalent cut-off grade of
0.4% and contains a Measured and Indicated Resource of approximately 7.9 Mt with an average
grade of 1.58% Li2O, 104 ppm Ta2O5, 0.04% Cs2O, and 0.31% Rb2O. There is an additional Inferred
Resource of approximately 0.3 Mt with an average grade of 1.20% Li2O, 103 ppm Ta2O5, 0.06%
Cs2O, and 0.36% Rb2O (Table 1.1). The effective date of the resource is March 4, 2016.
3
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Table 1.1 PAK Lake Resource Summary
Cut-off
Resource Category
Commodity Geologic Zone Tonnes (t)
Li2O (%)
Ta2O5 (ppm)
Cs2O (%)
Rb2O (%)
Contained Li2O (t)
Contained Ta2O5 (t)
Li2O EQ (%)
0.4
% L
i 2O
eq
Me
asu
red
Lithium Upper Intermediate Zone (UIZ) 333,500 3.94 58 0.03 0.12 13,136 19 4.02
Lithium Lower Intermediate Zone (LIZ) 683,100 1.87 90 0.03 0.29 12,797 62 2.00
Lithium Total Lithium Zone 1,016,600 2.55 80 0.03 0.23 25,933 81 2.67
Tantalum / Rubidium Central Intermediate Zone (CIZ) - - - - - - - -
Lithium / Tantalum / Rubidium Bulk Pegmatite 1,016,600 2.55 80 0.03 0.23 25,933 81 2.67
0.4
% L
i2O
eq
Ind
ica
ted
Lithium Upper Intermediate Zone (UIZ) 304,600 3.19 69 0.04 0.23 9,720 21 3.29
Lithium Lower Intermediate Zone (LIZ) 5,526,200 1.61 109 0.04 0.29 88,699 601 1.76
Lithium Total Lithium Zone 5,830,800 1.69 107 0.04 0.28 98,419 622 1.84
Tantalum / Rubidium Central Intermediate Zone (CIZ) 1,039,700 0.78 114 0.07 0.57 n/a 119 n/a
Lithium / Tantalum / Rubidium Bulk Pegmatite 6,870,500 1.43 108 0.04 0.33 98,419 740 1.59
0.4
% L
i 2O
eq
Me
asu
red
+In
dic
ate
d
Lithium Upper Intermediate Zone (UIZ) 638,100 3.58 63 0.04 0.17 22,856 40 3.67
Lithium Lower Intermediate Zone (LIZ) 6,209,300 1.63 107 0.04 0.29 101,496 662 1.79
Lithium Total Lithium Zone 6,847,400 1.82 103 0.04 0.28 124,352 703 1.96
Tantalum / Rubidium Central Intermediate Zone (CIZ) 1,039,700 0.78 114 0.07 0.57 n/a 119 n/a
Lithium / Tantalum / Rubidium Bulk Pegmatite 7,887,100 1.58 104 0.04 0.31 124,352 821 1.73
0.4
% L
i 2O
eq
Infe
rre
d
Lithium Upper Intermediate Zone (UIZ) 1,800 2.61 67 0.06 0.18 47 0 2.70
Lithium Lower Intermediate Zone (LIZ) 226,880 1.54 98 0.05 0.30 3,505 22 1.69
Lithium Total Lithium Zone 228,700 1.55 98 0.05 0.30 3,552 22 1.69
Tantalum /Rubidium Central Intermediate Zone (CIZ) 66,900 0.81 119 0.07 0.54 n/a 8 n/a
Lithium / Tantalum / Rubidium Bulk Pegmatite 295,600 1.20 103 0.06 0.36 3,552 30 1.35
4
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
1.4 RECOMMENDATIONS
It is WSP’s opinion that HLM is ready to commence a Pre-Feasibility Study (PFS) to assess the
viability of producing lithium, tantalum, and mica product concentrates. There is sufficient resource in
the measured and indicated categories to warrant the study. Two separate programs are proposed.
The successful completion of Phase 1 will have an impact on how Phase 2 is conducted.
1.4.1 PHASE 1
Phase 1 is to initiate a PFS to determine the economic viability of producing lithium, tantalum, and
muscovite product concentrates. Phase 1 will involve additional work designed to expand and infill
the current resource on the Property. This would include diamond drill testing below the current
resource on the north-west extent with a target of additional tonnage that would be amenable to open
pit mining methods. Other work in Phase 1 includes the continuation of baseline environmental work,
the completion of metallurgical testing, and a geotechnical review of the core for support of the PFS
based on producing lithium, tantalum, and muscovite mica product concentrates.
A budget of $850,000 is estimated to be required to complete the Phase 1 program, which would
include the PFS, diamond drilling, and continued environmental monitoring.
1.4.2 PHASE 2
Phase 2 is designed to further delineate and test the resource based on results and
recommendations from the PFS. Work should include step-out diamond drilling of the deposit and a
larger advanced exploration bulk sample of the UIZ for industrial testing purposes of the UIZ as a
direct shipping ore (DSO) for the ceramic-thermal glass and the frits and glaze industries.
The budget for Phase 2 is estimated to be $1,500,000, which includes portion of the advanced
exploration sample plus additional diamond drilling, and ongoing metallurgical and environmental
work.
5
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
2 INTRODUCTION The Property is a lithium-tantalum-bearing pegmatite system located approximately 175 km north of
Red Lake, in northwestern Ontario. The claims are currently owned 100% by HLM.
No exploration work had been conducted on the Property prior to HLM’s acquisition of the Property in
1999. All previous work in the region was government-funded mapping projects.
To date, HLM has delineated three mineralized domains within the PAK pegmatite on the Property
through the compilation of mapping, channel sampling, and diamond drill data.
The objectives of this report are to:
Prepare a technical report on the PAK Property in accordance with NI 43-101 summarizing land tenures, exploration history, and drilling;
Update the mineral resource;
Provide recommendations and budget for additional work.
This report has been prepared in accordance with NI 43-101, Form 43-101F1 and Companion Policy
43-101CP.
All work is completed using the metric system and all values are in Canadian dollars unless otherwise
stated.
All data reviewed for the report was provided by HLM in digital format, with access to paper reports
and logs when requested. The work completed by HLM encompasses surface exploration, including
mapping, sampling, trenching, and geological/structural modeling. HLM has completed four rounds of
diamond drilling on the Property.
Historical work conducted in the region has been compiled by HLM and was available for review.
The author of this report and qualified person (QP), Mr. Todd McCracken, P.Geo. is a professional
geologist with 24 years of experience in exploration and operations, including several years working
in intrusive hosted deposits. Mr. McCracken visited the Property between October 1 and 2, 2013 and
again between July 14 and 15, 2015. Mr. McCracken visited the core farm located at 2736 Belisle
Drive in Val Caron, Ontario on June 7, 2014 and again on June 20, 2015 to review the core with
Mr. Garth Drever, P. Geo., Vice President Exploration for HLM, and Mr. Peter Vanstone, P. Geo. and
independent QP to HLM.
WSP considers the site visit current, per NI 43-101CP, Section 6.2, on the basis that the work
completed on the Property has been reviewed by the QP and all practices and procedures
documented were reviewed.
6
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
3 RELIANCE ON OTHER EXPERTS WSP has reviewed and analyzed data and reports provided by HLM, together with publicly available
data, drawing its own conclusions augmented by direct field examination.
This report includes technical information, which required subsequent calculations to derive subtotals,
totals, and weighted averages. Such calculations inherently involve a degree of rounding and
consequently introduce a margin of error. Where these occur, the QP does not consider them to be
material.
The QP who prepared this report relied on information provided by experts who are not QPs. The QP
believes that it is reasonable to rely on these experts, based on the assumption that the experts have
the necessary education, professional designations, and relevant experience on matters relevant to
the technical report.
Todd McCracken, P.Geo., relied upon Trevor Walker, President of HLM for information pertaining to mineral claims as disclosed in Section 4.0. The information pertaining to mineral claims was confirmed by the Ontario Ministry of Northern Development and Mines CLAIMaps website (www.mndm.gov.on.ca).
7
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
4 PROPERTY DESCRIPTION AND LOCATION 4.1 LOCATION
The Property is located 175 km north of Red Lake, Ontario in the Red Lake Mining Division and is
on Crown Land (Figure 4.1). The centre of the Project is located on National Topographic System
map sheet reference is 53C/11 at approximately 52°36’N latitude and 93°23’W longitude near
Pakeagama Lake.
4.1 MINERAL DISPOSITION
The Property is composed of 33 claims (436 contiguous un-surveyed claim units) for a total of
6,976 hectares (17,238 acres) as can be seen in Table 4.1 and on Figure 4.2. All mining claims are
currently in good standing.
The Property is presently owned 100% by HLM. In late March of 1999, HLM entered into an option
agreement to earn a 100% interest from John Gregory Brady. Upon complying with the terms of the
agreement, HLM exercised their option and acquired a 100% interest in the claim.
On December 8, 2010, HLM entered into a 6-year agreement with two private individuals,
Michael Desmeules (50%) and Karin Smith (50%) to acquire 100% of three mining claims (each
16 unit claims) collectively called the Pakeagama South-East. In 2015, HLM completed the earn-in
by issuing a total of 500,000 common shares and payment of $110,000.
Fourteen additional claims were staked in 2014 to the northwest and southeast, and in 2015 two
more claims were staked to the west to make up the current land tenure.
4.2 TENURE RIGHTS
Surface rights to Property currently remain with the Crown. The Ontario Mining Act (2010) grants
access to a mineral claim without having the surface rights.
8
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Figure 4.1 Location Map
9
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
4.3 ROYALTIES AND RELATED INFORMATION
The terms of the royalty require payment of a 2.5% NSR for the original claim 1232441. HLM has a
provision to reduce the royalty to 1.5% at a cost of $1,000,000. A similar royalty agreement is in
place for claims 4224922, 4224923, and 4224924 with a 2.5% NSR and the ability to reduce the
royalty to 1.0% for $1,500,000.
Table 4.1 Summary of Mineral Disposition
Property Name Mining Claim (KRL)
Units Date Recorded
Next Due Date
Recorded Owner
Area (Ha)
Pakeagama Lake 1232441 16 1998/07/30 2018/07/30 HLM (100%) 256
sub-total 16 256
PAK Southeast 4224922 16 2009/08/12 2016/08/12 HLM (100%) 256
4224923 16 2009/08/12 2016/08/12 HLM (100%) 256
4224924 16 2009/08/12 2016/08/12 HLM (100%) 256
sub-total 48 768
PAK Northeast 4274173 12 2013/03/19 2017/03/19 HLM (100%) 192
4274663 16 2013/03/19 2017/03/19 HLM (100%) 256
sub-total 28 448
PAK Northwest 4272452 16 2012/09/25 2016/09/25 HLM (100%) 256
4272453 16 2012/09/25 2016/09/25 HLM (100%) 256
4272454 16 2012/09/25 2016/09/25 HLM (100%) 256
4274766 15 2014/07/10 2016/07/10 HLM (100%) 240
4274767 15 2014/07/10 2016/07/10 HLM (100%) 240
4274768 12 2014/07/10 2016/07/10 HLM (100%) 192
4274769 15 2014/07/10 2016/07/10 HLM (100%) 240
4274776 15 2014/07/10 2016/07/10 HLM (100%) 240
4274777 15 2014/07/10 2016/07/10 HLM (100%) 240
4274778 15 2014/07/10 2016/07/10 HLM (100%) 240
4274779 15 2014/07/10 2016/07/10 HLM (100%) 240
sub-total 165 2,640
PAK River Extension 4244431 15 2014/03/11 2017/03/11 HLM (100%) 240
4244432 15 2014/03/11 2017/03/11 HLM (100%) 240
4244433 15 2014/03/11 2017/03/11 HLM (100%) 240
4244434 15 2014/03/11 2017/03/11 HLM (100%) 240
4244435 15 2014/03/11 2017/03/11 HLM (100%) 240
4274680 12 2013/03/19 2017/03/19 HLM (100%) 192
4274685 12 2013/02/21 2017/02/21 HLM (100%) 192
4274686 12 2013/03/19 20176/03/19 HLM (100%) 192
4274687 12 2013/03/19 2017/03/19 HLM (100%) 192
sub-total 123 1,968
10
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Property Name Mining Claim (KRL)
Units Date Recorded
Next Due Date
Recorded Owner
Area (Ha)
PAK South-Southwest 4245780 1 2014/03/11 2017/03/11 HLM (100%) 16
4274681 4 2013/02/21 2017/02/21 HLM (100%) 64
4274682 12 2013/02/21 2017/02/21 HLM (100%) 192
4274683 8 2013/02/21 2017/02/21 HLM (100%) 128
4274684 12 2013/02/21 2017/02/21 HLM (100%) 192
4283825 16 2015/06/10 2017/06/10 HLM (100%) 256
4283826 3 2015/06/10 2017/06/10 HLM (100%) 48
sub-total 56 896
Grand Total 436 6,976
11
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Figure 4.2 Claim Map
12
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
4.4 ENVIRONMENTAL LIABILITIES
No industrial activities such as mineral processing have been conducted on the Property.
Disturbance on the Property has been limited to drill trails, drill pad set ups and a bulk sample.
WSP did not observe or is not aware of any environmental liabilities on the Property.
4.5 PERMITS
All permits required to conduct exploration on the Property are current.
4.6 OTHER RELEVANT FACTORS
The PAK Lithium Project is not currently subject to any formal First Nation agreements. The
development of the Project will incorporate hiring practices for the employment of North Spirit Lake
and Deer Lake people and services.
The Pakeagama Lake pegmatite is currently delineated on the Pakeagama Lake Property which lies
directly within the trapline area designated as RL 122. The trapping area is currently held by a
resident of Deer Lake. The PAK River Extension Property to the southeast is within the trapline
designated as RL 121, which is currently held by a resident of North Spirit Lake.
In 2013 Phase II of the Ontario Mining Act modernization was implemented whereby Aboriginal
notification and consultation is mandated prior to exploration plans and permits for mineral exploration
is granted by the government.
HLM submitted for an exploration permit for the Project by which the Ministry of Northern
Development and Mines (MNDM) have identified the Aboriginal communities of Deer Lake First
Nation and North Spirit Lake First Nation to be notified about HLM’s planned activities. A copy of the
exploration permit proposal was sent to the above-noted Aboriginal communities on December 2,
2013, advising them that their comments, with respect to potential adverse effects of the proposed
activities on their Aboriginal and treaty rights be provided.
During the 2014 drilling program, representatives from the North Spirit Lake band council visited the
Property, updated on the progress to date and were provided with a tour of the pegmatite area and
the operating diamond drill.
On July 14, 2015, representatives from North Spirit Lake visited the Property and were provided a
tour of the drill camp and outcrop area including the site where the bulk sample was extracted.
In December 2015, both Deer Lake and North Spirit Lake Councils were provided with a draft
proposal for an exploration agreement with HLM.
13
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE, AND PHYSIOGRAPHY
5.1 ACCESS
Access to the Property is available year-round by chartered ski or float equipped aircraft from Red
Lake, Ontario (175 km) to the south of Pakeagama Lake.
The project is located in a relatively isolated area of northwestern Ontario where infrastructure is
absent except for a winter road, which services the communities of Deer Lake, Sandy Lake, and
North Spirit Lake. The winter road is located adjacent to the west side of the claim group (Figure 5.1)
and vehicle access can be gained to the Property from this winter road in February and March.
Bearskin Airlines and Wasaya Air service the nearby communities of Deer Lake, North Spirit Lake,
and Sandy Lake with daily flights year-round.
Access to the Property is available year-round if required.
14
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Figure 5.1 Property Access
15
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
5.2 CLIMATE
Four climate data stations operated by Environment Canada are located at Island Lake in Manitoba,
and Red Lake, Pickle Lake and Big Trout Lake in Ontario. The average mean annual temperature is
-0.9°C. The average daily temperature in summer is from 8.9°C to 19.2°C while in winter the average
range is from - 20.3°C to -11.6°C. Average yearly precipitation for the area is 655 mm
(www.climate.weather.gc.ca).
5.3 INFRASTRUCTURE
Water sufficient for mining operations is present within the Property. Surface rights sufficient for a
mining operation can be readily obtained, and the necessary area for mining and processing
infrastructure exists.
Currently no electric power is available on the Property, nor does a power line come within close
proximity of the Property.
There is no immediate skilled labour force close to the Property. The location of the Property within
northwestern Ontario and proximity to the Red Lake mining camp and Manitoba ensures that skilled
mining personnel can be found.
5.4 SITE TOPOGRAPHY, ELEVATION, AND VEGETATION
The Property is located in an area of variable topographic relief, with a series of ridges with the
extensive development of cliff faces parallel the general regional strike of the geology surrounded by
low lying areas covered by swamps, lakes, and rivers. The mean elevation on the Property is
approximately 320 masl.
The Property lies at the northern boundary of the Lac Seul Upland eco-region and the southern
boundary of the Hayes River Upland eco-region of the Boreal Shield. The region is classified as
having a sub-humid mid-boreal eco-climate (Ecological Stratification Working Group, 1998).
The dominant vegetation is coniferous forest. Higher elevations are covered by stands of jack pine
up to 6 m high while swampy areas are dominated by black spruce. Upland areas are covered with
discontinuous deposits of acidic sandy tills while thin lacustrine clay deposits tend to cap the tills in
low-lying areas. The resulting deadfall from a 1995 forest fire inhibits easy foot travel. Another forest
fire burned a portion of the Pakeagama Lake project area in 2008, including the area around the
pegmatite.
16
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
6 HISTORY A. P. Low of the Geological Survey of Canada (GSC) completed the first geological reconnaissance
mapping of the region in 1886. Additional geological surveys were carried out by G. V. Douglas
(1925) and M. E. Hurst (1928) of the Ontario Department of Mines.
Most of the exploration activity in the region has been centred on the Favourable and Setting Net
Lakes area located 25 to 40 km to the northwest of the Property. While prospecting, K. C. Murray
identified gold in the Favourable Lake area in 1927. The gold property was developed as the Berens
River Mine and produced 4,451 kg Au, 160,926 kg Ag, 2,770 t Pb, and 815,147 kg Zn from
508,665 tons of ore between 1939 and 1948 (Stone, 1998). Subsequent exploration by Golsil Mines
Limited, Zahavy Mines Limited, Getty Mines Limited, and Noramco Mines Ltd. was carried out until
the early 1990s.
Geological mapping of portions of the region was carried out by Ayres (1970, 1972a). He noted
spodumene in a pegmatite dyke and holmquistite within granitic rocks near Setting Net Lake (25 km
WNW of Pakeagama Lake). A grab sample from the pegmatite dyke contained 0.52% Li (Ayres,
1972b).
An airborne reconnaissance gamma-ray spectrometer survey was flown over the Pakeagama Lake
area in 1977 as part of a regional coverage program by the Ontario Geological Survey (OGS) and the
GSC in 1979. The survey was flown at a 120 m terrain clearance with 5 km line spacing and a
2.2 km station interval. No significant radiometric anomalies were detected in the immediate vicinity
of Pakeagama Lake.
6.1 ONTARIO GEOLOGICAL SURVEY PROGRAMS
Geological mapping of the region was completed by D. Stone of the OGS in 1990 (Stone et al., 1993;
Stone, 1998). Tourmaline-rich samples from the vicinity of Pakeagama Lake returned anomalous
levels of Li, Cs, Ta, and Be during this work. Five rare metal mineral occurrences were detected over
a 35 km trend along the Bear Head Lake Fault Zone, however, the Pakeagama Lake pegmatite
occurrence became the main focus of detailed work.
In 1998 and 1999, Dr. F. Breaks and Dr. A. Tindle of the OGS, studied the Pakeagama pegmatite.
Approximately 2,186 analyses had been conducted to establish that the Pakeagama rare metals
pegmatite is potentially a world-class pegmatite suggesting the presence of a Tanco type mineralizing
system. At the time, the Pakeagama pegmatite was thought to vary in width from 30 to 125 m with a
strike length of at least 260 m (open in both directions) that may extend another 300 m to an aplite
dyke showing on the shores of Pakeagama Lake. “The detailed documentation of a variety of
tantalum-rich minerals coupled with the presence of pollucite (main cesium ore mineral) renders the
Pakeagama Lake pegmatite and adjoining area one of the best exploration targets for tantalum and
cesium in Northwestern Ontario” (Breaks, 1999).
6.2 HISTORIC EXPLORATION
There has been little exploration by publicly traded or private companies prior to HLM’s involvement.
Table 6.1 summarizes the work that has been completed on the Property. The information has been
gathered from various assessment reports.
17
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Table 6.1 Property Summary
Year Company Activity Highlights
1886 GCS First recorded Work First Reconnaissance work.
1926 ODM Reconnaissance Survey Reconnaissance scale mapping.
1929 ODM Geological Mapping Reconnaissance scale mapping; gold identified in Favourable Lake area.
1937 ODM Geological Mapping Gold property developed as Berens River Mine.
1970-1972 ODM Geological Mapping Identified spodumene near Net-Setting Lake.
1977 OGS‐GSC Airborne Radiometrics Regional survey; 5 km line spacing at 2.2 km stations. No significant anomalies identified in the Pakeagama Lake area.
1977‐1988 OGS Geological Mapping Systematic mapping of the region.
1990-1993 OGS Geological Mapping Identified anomalous Li, Cs, Ta, and Be in tourmaline-rich samples at Pakeagama Lake and discovered 5 rare metal occurrences over 35 km along the Bear Head Fault Zone.
1998-1999 OGS Geological Mapping - Channel Sampling
Completed detailed mapping and geochemistry (grab and channel samples) to establish Pakeagama Lake Pegmatite as world-class with Tanco-type mineralization. Significant mineralized zones were identified (285 ppm Ta2O5, 0.59% Rb2O, 967 ppm Cs2O, and 1.15% Li2O over 11.0 m).
1999 HLM Geological Mapping and Sampling
Confirmed work completed by the OGS.
2001 HLM Ground Geophysics 26-km magnetic and VLF survey; the survey was unsuccessful in delineating the pegmatite zone, however, defined the contacts between metasedimentary and granitic rock that contains the pegmatites in overburden covered areas.
2001 EFR Geological Mapping and Sampling
Mapped and sampled the area immediately to the northwest of the pegmatite. No anomalies noted.
2001 HLM Geological Sampling (Channel Sampling)
Identified and confirmed high-grade lithium in the "Core Zone" of 4.5% Li2O over 13.9 m.
2008 HLM Line Cutting - Soil Sampling
Re-established the grid for mapping the pegmatite and surrounding area. An Enzyme Leach survey was completed showing an apparent continuity of the anomalous zones away from the pegmatite to the southeast and east. This is most apparent with Cs, V, Ta, Li, Ga, and Nb.
2010 HLM Acquisition of Claims by option agreement
Three claims secured the land holdings immediately to the south and east of the pegmatite covering most of Pakeagama Lake.
18
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Year Company Activity Highlights
2011 HLM MMI soil sample survey The regional survey was somewhat successful in delineating elevated cesium, lithium, and rubidium MMI concentrations both to the northwest and southeast directions coincident with the assumed orientation of the Pakeagama Lake pegmatite.
2012 HLM Channel Sampling; Staking
Historical and 2 new channels were sampled across portions of the pegmatite verifying historical grades by using certified standards. Increased land tenure to the southeast along the pluton.
2013 HLM Phase I Diamond Drilling; Staking
Completed the first diamond drilling on the Property totaling 955 m in 6 holes. Intersected 154 m wide pegmatite zone grading 1.22% Li20, 111 ppm Ta2O5, and 0.41% Rb2O and a high-grade Lithium zone of 18 m grading 4.22% Li2O. Continued staking along the pluton.
2013 HLM Spodumene Study Completed an electron microprobe study confirming low-inherent iron content of the spodumene at the Pakeagama Lake Pegmatite.
2014 HLM Phase II Diamond Drilling; Staking
Completed 1,489 m in 9 holes which confirmed continuity of the high-grade UIZ and extended the strike length and depth extent of the mineralized pegmatite zones. Continued staking to the southeast.
2014 HLM Channel Sampling; Staking
Completed the twinning of outstanding historical channels and cut two new channels confirming the grades and width of the UIZ at surface. Staked to the northwest.
2015 HLM Phase III Diamond Drilling Completed 1,641m in 8 holes which confirmed continuity of the grades and extended the strike length and depth extent of the mineralized pegmatite zones.
2015 HLM Bulk Sample of UIZ In late February and early March a drill-blast program of 67 holes was completed with an approximately 300-tonne sample extracted and hauled to Red Lake for crushing and transported to SGS in Lakefield, ON for final processing as a direct shipping ore product (DSO) for an industrial test in Europe.
2015 HLM Initiated Baseline Sampling, Staking
Established water sampling and monitoring stations within the PAK project area to be sampled three times annually (Spring freshet, late Summer, and Winter). Also initiated flora and fauna study including species lists. Staked two additional claims along the access trail to the winter road.
2015 HLM Phase IV Diamond Drilling Completed 608 m in 2 holes which tested the eastern extension of the pegmatite. As predicted, the pegmatite body is continuous and plunging to the east at roughly 45 degrees.
2015 HLM Channel Sampling Stripped overburden and extended surface exposures of the high-grade UIZ to the WNW and completed 70 m of new channel cuts in 8 separate channels.
EFR - Emerald Fields Resources GSC - Geological Survey of Canada HLM - Houston Lake Mining ODM - Ontario Department of Mines OGS - Ontario Geological Survey
19
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
7 GEOLOGICAL SETTING AND MINERALIZATION
7.1 REGIONAL GEOLOGY
The Project area is situated along the boundary between the Berens River and Sachigo Subprovinces
(Card and Ciesielski, 1986 and Card, 1990) of the Archean Superior Province of the Canadian Shield
(Figure 7.1). These subprovinces comprise a series of relatively isolated volcano-sedimentary
(greenstone) belts surrounded by extensive granitic and gneissic suites of rock. The subprovinces
are separated by the Bear Head Lake Fault Zone (Figure 7.2).
Figure 7.1 Archean Sub Provinces
20
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Figure 7.2 Regional Geology
21
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Two of the greenstone belts that are located along the Bear Head Lake Fault Zone are the
Favourable-Setting Net Lakes and the North Spirit Lake greenstone belts located to the northwest
and southeast of the Property, respectively. The belts are connected through the Pakeagama Lake
area by the Bear Head Lake Fault system. The main assemblages of volcanic and sedimentary rocks
that are identified in each belt are, in part, correlated between the two belts (Stone et al, 1993). The
assemblages of the Favourable Lake and North Spirit Lake greenstone belts have been
metamorphosed under greenschist facies conditions, however an increase to amphibolite facies
occurs in proximity to the Bear Head Lake Fault Zone. Amphibolite facies is the predominant
metamorphic grade in the Project area outside of the greenstone belts.
The Bear Head Lake Fault is the dominant structural feature in the region and has been traced for
over 140 km from NW-SE. The fault is composed of a several hundred metres thick zone of mylonite.
The presence of cataclastites, tension gashes infilled by vuggy quartz-epidote-adularia, and potassic
alteration indicate that brittle deformation has been superimposed on the mylonites. A dextral
transcurrent dislocation of the Bear Head Lake Fault has been interpreted from microstructures
(Germundson, 2008). The regional gneissosity trends NW-SE and generally are steeply dipping
inward towards the core of the volcano-sedimentary assemblage in the vicinity of Pakeagama Lake.
The Bear Head Lake Fault Zone appears to be the locus for a peraluminous suite of granitic plutons.
Five major plutons consisting of two-mica granites (fertile granites) are documented over the 140 km
strike length of the fault. Fertile granites are interpreted to be the parental rocks that give rise to rare
metal pegmatites.
7.2 PROJECT GEOLOGY
The Property is underlain by the northwestern extension of the North Spirit Lake greenstone belt.
The greenstone rocks are approximately 2 km wide in the vicinity of the Property (Figure 7.3).
The greenstone belt within the Property boundary is bounded to the north by biotitic tonalities and
granites of the Whiteloon Lake Batholith (Sachigo Subprovince) and to the south by gneissic
granodiorites and granites of the Bear Head Lake Batholith (Berens River Subprovince of the
Superior Province).
There are three main lithological domains. To the northeast, rocks with metasedimentary origins are
composed of pelitic sediments, iron formation and conglomerate. The southwest region is comprised
dominantly of mafic metavolcanic and related metasedimentary rocks. The elongate, 2.5 by 15 km,
Pakeagama Lake peraluminous granite and mica pluton trending northwest-southeast was emplaced
along the unconformable contact between metasedimentary and metavolcanic-metasedimentary rocks.
The Pakeagama Lake granitic pegmatite is a highly evolved, zoned, complex-type, petalite-subtype LCT
pegmatite with highly anomalous values of lithium, cesium, tantalum and rubidium (Breaks et al., 1999).
The pegmatite body outcrops near the northwestern margins of the Pakeagama Lake pluton
(Figure 7.3). On surface, a metasedimentary sequence with banded iron formation forms an apparent
northern boundary to the pegmatite. Muscovite and tourmaline-bearing pegmatites and aplites occur up
to 1 km from the main pegmatite mass (Breaks et al, 1999). The Pakeagama Lake pegmatite is the
second largest complex-type petalite subtype pegmatite in Ontario (Breaks et al, 1999).
The relatively fresh-appearing pegmatite has irregular, steeply dipping contacts with the weakly
foliated garnet-muscovite-biotite granite host rock. A 130°strike is inferred from the coincidence of
the exposed 260 m strike length, the weak foliation in the host granite and the general trend of the
Bear Head Lake Fault. The pegmatite is open along strike in both directions.
22
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
The exposed outcrop area was mapped initially by Dr. F. Breaks in 1999 and at least 5 separate
zoned phases were identified (Breaks et al 1999). More recently P. Vanstone, former chief geologist
at Tanco, was contracted by HLM and consolidated the pegmatite zones using commonly accepted
pegmatite nomenclature and Tanco zone mineralogical criteria. (Figure 7.4). The three main
pegmatite zones identified in this work are (from northwest to southwest and perpendicular to the
strike of the pegmatite) the Central Intermediate Zone (CIZ – tantalum, rubidium, and cesium
enriched), Upper Intermediate Zone (UIZ - lithium and rubidium enriched), and the Lower
Intermediate Zone (LIZ – lithium and rubidium enriched). A lower and upper wall zone has also been
described but not included as a separate mapped unit.
23
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Figure 7.3 Property Geology
24
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Figure 7.4 Detailed Property Geology
25
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
7.3 MINERALIZATION
7.3.1 UPPER INTERMEDIATE ZONE (UIZ)
The Upper Intermediate Zone (“UIZ”) represents the lithium zone within the pegmatite and is
dominated by “SQUI” (Spodumene + Quartz Intergrowth), a term used to describe an isochemical
reversion resulting in the replacement of primary petalite by oriented spodumene + quartz intergrowth
(London, 1984), with lesser grey K-feldspar and primary white spodumene in quartz (Figure 7.5).
Phosphate minerals such as montebrasite (Breaks et al., 1999) and apatite, and lithian mica are
common accessory minerals.
7.3.2 CENTRAL INTERMEDIATE ZONE (CIZ)
The Central Intermediate Zone (“CIZ”) is located in structurally higher portions of the pegmatite and
represents the tantalum and rubidium zone of the pegmatite. The CIZ is in contact with both the
Upper Intermediate Zone (UIZ) and Upper Wall Zone, and persists to the southeast edge of the
outcrop where it is believed the pegmatite continues under the till cover. To the southeast, the CIZ is
intersected by channels CH-1 and CH-7 where it consists of similarly sized fragments of randomly
oriented coarse K-feldspar + mica + quartz. Micas appear to alter primary K-feldspar. Blue apatite
prisms up to 1 cm wide and several cm’s long accompany the mica-rich zones. In the adjoining area
to the northeast of CH-7, the K-feldspars are more or less completely replaced with lithian mica +
quartz. In this area veinlets and patches of lepidolite are common. Channel 1 (CH-1) contains the
highest tantalum grades found to date in the exposed pegmatite, which persist in the subsurface in
drill holes PL13-001 and -006, in addition to high rubidium and elevated cesium grades. To the
northwest, channels CH-8 and CH19 intersect the central portion of the exposed CIZ where it
consists of predominantly grey K-feldspar with minor lithian mica + quartz alteration. Drill holes PL13-
004 and -003 confirm the extension of the CIZ into the subsurface in this area, where it features
notable cm-scale blebs of the rare cesium mineral pollucite, and high Ta and Rb grades. Figure 7.6
shows an outcrop and photomicrograph of the CIZ.
7.3.3 LOWER INTERMEDIATE ZONE (LIZ)
The Lower Intermediate Zone (LIZ) comprises the bulk of the exposed pegmatite and is considered
an intermediate stage zone with significant lithium, tantalum and rubidium. The zone comprises
predominantly K-feldspar, Na-feldspar, SQUI and lithian muscovite (Figure 7.7). Pollucite also occurs
in an intersection of LIZ in drill hole PL13-005. The zone has undergone both ductile and brittle
deformation at the apparently structurally lowest portions of the pegmatite. Ductile deformation is
manifested as a banded appearance on surface, where seams of oriented mica provide a planar
fabric.
26
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Figure 7.5 UIZ
27
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Figure 7.6 CIZ
28
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Figure 7.7 LIZ
29
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
7.3.4 WALL ZONES
The Wall Zones (upper and lower) of complex LCT type pegmatites are generally characterized by
the occurrence of brick-red K-feldspar (perthite) and simple mineralogy (Černý, 2005, Černý and
Vanstone 1996). The zone mineralogy is simple, but the brick-red colouration of the K-feldspar is
more common in the portion of the pegmatite in close proximity to the metasediments. The same
colouration does generally not occur where the pegmatite is in contact with the granite. In this latter
case, the sections of Wall Zone display a light to medium grey K-feldspar. It is assumed lower
inherent iron levels of the Pakeagama Lake granite, unlike the metasediments, were not sufficient to
generate the K-feldspar colour change in the adjoining pegmatite.
The Upper Wall Zone found in the southwest portion of the pegmatite exposure, is in contact with the
lithium rich UIZ and is composed of quartz with lesser pale-red coloured K-feldspar, minor
phosphates and accessory beryl and lithian mica. The exposure of this zone is limited.
The Lower Wall Zone is mineralogically similar to the Upper Wall Zone. A common feature of the
footwall Wall Zone in the more complex LCT-type pegmatites is the presence of bands of sodic aplite
(“footwall aplite”). These sodic bands are generally not common in the Upper Wall Zone. The
Pakeagama Lake pegmatite is somewhat more complex as bands of what appears to be pre-existing
banded sodic aplites are found throughout the pegmatite. The contact with the LIZ is gradational and
is defined by the general absence of SQUI within the wall zones and the change in colour of the
K-feldspars from pale-red to the light grey commonly found throughout the pegmatite. Like the LIZ,
this zone has undergone deformation.
30
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
8 DEPOSIT TYPES HLM’s target or deposit model is the highly evolved, granitic, rare-element lithium-cesium-tantalum
bearing (LCT) complex type, petalite subtype pegmatite. The Tanco pegmatite situated in the Bird
River belt in southeastern Manitoba, is the best known and a world-class example of this type of
deposit model. Figure 8.1 shows the location of the Tanco pegmatite relative to the geological
subprovinces of the western Superior Craton and Pakeagama Lake.
Figure 8.1 Tanco Pegmatite and PAK Pegmatite Location
31
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Granitic pegmatites are relatively common and widespread, and have been divided into five classes
based on the pressure-temperature conditions that characterize their host rock suites (Černý and
Ercit, 2005). Criteria, including mineral assemblages, geochemical signature and conditions of
consolidation or combinations thereof, are used to further divide the classes into sub-classes, types,
and subtypes (Figure 8.2).
Figure 8.2 Division of Rare Metal Pegmatites
Of the five classes, the rare-element class is the group with the most attractive economic potential
and can represent economic sources of tantalum, ceramic grade spodumene, rubidium, and the main
cesium ore mineral, pollucite. The lithium rich, rare-element pegmatites are not common and
comprise
32
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
Figure 8.3 Deposit Model
The internal structure of pegmatites varies from simple or un-zoned to complexly zoned. Zonation, or
the lack thereof, provides the starting point for the pegmatite internal anatomy which is largely what
distinguishes pegmatites from other ordinary plutonic igneous rocks and is manifested by variations in
the spatial distribution of grain size, mineral assemblage, crystal habit, and / or rock fabric.
Pegmatites crystalizing from very highly fractionated melts have the most evolved internal structure.
These highly fractionated pegmatitic melts are enriched in fluxes such as H, B, P and F, in addition to
water, lithium, rubidium, cesium, tantalum, and beryllium which make the melts less viscous than a
granitic melt and thus able to migrate farther from the source pluton (London, 2008, p. 259).
The complex-type, petalite and spodumene subtype pegmatites are the products of the most highly
fractionated melts and as such, are the most complexly zoned with up to eleven different zones
characterized by variable textures and mineral modes (Černý, 1991; Černý, 2005). As an example,
the Tanco pegmatite has nine zones and its most notable geochemical anomalies being its high
tantalum content along with high cesium and phosphorus contents, the latter two being the hallmark
of a pelitic metasedimentary source (London, 2008 p. 109).
33
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
The economic concentrations of the lithophile rare-elements will occur in pegmatites crystalizing from
the most highly evolved melts. Some of the lithophile rare-elements may occur in separate zones,
which may allow for selective exploitation. Economic tantalum mineralization can be complex and the
host mineralogy for rubidium can be different in different zones, but pollucite is the main cesium
mineral and according to Kesler et al (2012) spodumene is the most economically important lithium
mineral.
Figure 8.3 shows the internal zonation of a pegmatite from the outer border zone to the central core
zone. The intermediate zones at the Pakeagama pegmatite appears to be similar to Tanco with
respect to mineralogy and concentrations of Li, Ta, Cs, and Rb (Vanstone, 2013).
34
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
9 EXPLORATION Eight new channels (Channel 22 to 29) totaling 69.8 m were completed in the summer of 2015.
(Figure 9.1). A total of 73 samples were collected.
Sampling was completed by HLM personnel along with personnel from Haveman Brothers of
Kakabeka Falls, Ontario.
The channels were oriented perpendicular to the strike of the pegmatite’s internal mineralogical zones
and were cut continuously across the zones. The length of a channel was determined by the width of
the pegmatite zone being sampled. The original cuts completed in 2001 consisted of a series of
offset channels to achieve a full section across a zone.
The channels were wet-cut approximately 3.5 to 4 cm wide and 9 to 10 cm deep with a motorized
circular diamond saw. Sample lengths were typically one metre or less, depending on zone
mineralogy and boundaries. After cutting, the channels were washed to mitigate cross-contamination
by the cuttings. The samples were then removed using a hammer and chisel. The samples were laid
out in order next to the channel and were geologically described, washed, assigned a sample
number, and then bagged. The sample number was also etched on a metal tag that was secured to
the outcrop at the beginning of each sample cut. The start of each channel was assigned a GPS
coordinate and the cut channel assigned a bearing.
Each sample bag was sealed using a plastic zip tie. The poly bags were then placed into rice bags,
which were then labeled and closed off with zip ties. HLM personnel transported the bags of samples
to Val Caron where sample blanks and standards were inserted into the sample stream. All samples
were then shipped to Actlabs or AGAT laboratories in Sudbury, Ontario.
Table 9.1 summarizes the location of the 2015 channels, and Table 9.2 summarizes the results for
the 2015 channel program.
Table 9.1 2015 Channel Location Summary
Channel No. Easting Northing Elevation (masl) Azimuth Length (m) No. of Samples
CH-22 474476 5827978 324 30 13 13
CH-23 474523 5827959 324 207 17 17
CH-24 474518 5827942 324 203 2 2
CH-25 474514 5827941 322 215 9 10
CH-26 474498 5827965 324 29 7 7
CH-27 474491 5827976 323 26 4 4
CH-28 474503 5827974 323 27 13.8 16
CH-29 474497 5827966 323 206 4 4
35
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Table 9.2 2015 Channel Results Summary
Channel ID From (m)
To (m)
Length (m)
Li2O (%)
Cs2O (%)
Ta2O5 (ppm)
Nb2O5 (ppm)
SnO2 (ppm)
Rb2O (%)
Zone Sampled
Channel 22 0 13 13 3.21 0.062 111 43 51 0.19 UIZ/LIZ
including 0 6.2 6.2 4.21 0.023 51 28 39 0.07 UIZ
including 6.2 13 6.8 2.29 0.098 166 57 62 0.30 LIZ
Channel 23 0 17 17 4.71 0.017 49 13 33 0.05 UIZ
Channel 24 0 2 2 4.20 0.036 111 77 52 0.16 UIZ
Channel 25 0 9 9 3.91 0.057 86 47 74 0.27 UIZ
Channel 26 0 7 7 4.69 0.018 51 13 30 0.02 UIZ
Channel 27 0 4 4 4.59 0.035 67 22 23 0.05 UIZ
Channel 28 0 13.8 13.8 2.49 0.036 108 56 131 0.32 LIZ/UIZ
including 0 11 11 2.29 0.040 114 59 68 0.34 LIZ
including 11 13.4 2.4 3.59 0.020 71 40 63 0.23 UIZ
Channel 29 0 4 4 3.35 0.026 52 36 86 0.11 UIZ/WZ
including 1 4 3 4.40 0.024 54 36 100 0.08 UIZ
36
WSP Resource Estimation Update and Technical Report No 151-08683-00_RPT-02_R2 Houston Lake Mining Inc.
10 DRILLING Four phases of drilling have been completed on the Property since 2013. Table 10.1 provides the
collar information for all four phases of the drilling program. Figure 10.1 illustrates the location of the
drill collars.
10.1 2013 DRILL CAMPAIGN
During the period February 19 to March 3, 2013, HLM completed a 6-hole diamond drill program,
totaling 955 m, as a follow-up to the high-grade mineralization defined in the UIZ, LIZ, and CIZ zones
during the 2012 Channel Sample Program. The objectives of the drill program were to determine the
orientation, thickness, and zonation of the pegmatite and to refine the mineralogical characterization
of these zones by better establishing the Li, Ta, Rb, and Cs potential.
Haveman Brothers of Kakabeka Falls, Ontario was contracted to provide camp logistics for the drill
program. A 10-person winter camp was established next to the winter road 25 km northwest of the
North Spirit Lake community. Element Drilling Ltd. of Gimli, Manitoba was awarded the diamond
drilling contract. Drilling was completed using a skid mounted Boyles 37 drill using NQ (47.6 mm)
rods for all holes. A D6 Caterpillar moved the drill from camp to the first drill site and between holes.
Drill core was geologically logged and tagged for sampling in the Core Logging Facility at the
campsite.
Under HLM’s QA/QC procedures, the diamond drill contract specified NQ-sized drill core providing a
47.6 mm diameter sample. The drill holes were oriented perpendicular to the strike of the pegmatite
and drilled continuously across it.
Full disclosure of the results from the 2013 drill campaign was provided in the previous technical
report (McCracken, 2014).
37
Resource Estimation Update and Technical Report WSP Houston Lake Mining Inc. No 151-08683-00_RPT-02_R2
Table 10.1 Drill Collars
DDHNo Date Drilled UTM Zone 15N (NAD83) Collar Orientation Metres Drilled
Start_Date End_Date Easting Northing (masl) Azimuth Dip Start End
Ph
as
e I
PL-13-001 20/02/2013 03/03/2013 474,558 5,827,832 319.5 20 -45 0 213.3
PL-13-002 22/02/2013 24/02/2013 474,451 5,827,832 323.2 30 -45 0 191
PL-13-003 24/02/2013 25/02/2013 474,421 5,827,963 327.6 30 -45 0 104
PL-13-004 25/02/2013 27/02/2013 474,492 5,827,908 325.9 30 -45 0 167
PL-13-005 27/02/2013 28/02/2013 474,526 5,828,046 320.8 210 -45 0 161
PL-13-006 01/03/2013 02/03/2013 474,608 5,827,944 316.6 210 -45 0 119
Total metres drilled 955