+ All Categories
Home > Documents > Review for Final in ISQS 7342

Review for Final in ISQS 7342

Date post: 18-Jan-2016
Category:
Upload: barny
View: 40 times
Download: 3 times
Share this document with a friend
Description:
Review for Final in ISQS 7342. Final will take place: Saturday, December 7, 2013, 10.30-1.00 p.m., this room – BA 021. Format. 7 5 multiple choice worth 50% 3 discussion problems worth 50% exam is closed notes/closed book Exam will be comprehensive - PowerPoint PPT Presentation
Popular Tags:
58
Review for Final in ISQS 7342 Final will take place: Wednesday, December 10, 2014, 7.30-10.00 a.m., this room – BA 025 Early Exam for those who signed on will be Saturday, December 6, 2014, 7.30-10.00 a.m., this
Transcript
Page 1: Review for Final in ISQS 7342

Review for Final in ISQS 7342

Final will take place:

Wednesday, December 10, 2014, 7.30-10.00 a.m., this room – BA 025Early Exam for those who signed on will be Saturday, December 6, 2014, 7.30-10.00 a.m., this room – BA 025

Page 2: Review for Final in ISQS 7342

Format

75-100 multiple choice worth 75% 2-3 discussion problems worth

25% exam is closed notes/closed book Exam will be comprehensive

• 70% of the exam will cover material since Exam 2

• 30% of the exam will cover prior material

No talking during the EXAM, please

Page 3: Review for Final in ISQS 7342

Bring

Pencils/Eraser Calculator Orange Scantron sheet

Page 4: Review for Final in ISQS 7342

Emphasis will be upon:

Human Resource Management Risk Management Procurement Management Communications Management Goldratt Concepts Finishing Projects Fast

Page 5: Review for Final in ISQS 7342

Possible Discussion Questions

Name ten characteristics of a project

Successful project management entails what exactly (4 ‘measures’)

Name the stages of the project lifecycle• Show their sequence

Why is project management important

Name the four core knowledge areas

Name the five facilitating knowledge areas

Page 6: Review for Final in ISQS 7342

More discussion questions

What is the tenth knowledge area and what is its purpose

Name some things we do poorly in projects

What term do we use to describe an event at which a major deliverable is completed?

What device or construct is often used to initiate a project?

What steps are used to launch critical chain project management?

Page 7: Review for Final in ISQS 7342

Typical discussion problems

Construct an activity on node network chart from a table; Determine duration, ES, EF, LS, LF and mark the critical path

Perform earned value analysis: BCWP, BCWS, ACWP, CV, SV, EV, PV, AC, CI, SI

Perform crashing of networks What are the five phases that make up

the CMMI? Illustrate the tradeoff triangle Assuming that half the durations are

safety, redraw a project network showing all feeding and project buffers and their lengths

Page 8: Review for Final in ISQS 7342

Multiple choice

Risk, Procurement, HR, and Communications knowledge mangement

Chapters 12, 14 of Burns Process maturity slides Finishing projects fast slides Critical chain concepts

Page 9: Review for Final in ISQS 7342

Why has Project Management become so in-vogue?

Diversity of new products and product markets

Shorter life span of products Rapid technological changes

Page 10: Review for Final in ISQS 7342

What are the major reasons for project failure?

Inadequate conceptualization and definition• Specifically, inadequate requirements

Absence of a plan Unavailable resources when

needed Scope and hope creep Unresponsive contractors who

deliver their product late

Page 11: Review for Final in ISQS 7342

What are the five stages of the project lifecycle?

STAGE 1:Initiating

STAGE 2:Planning

STAGE 3:Executing

STAGE 5:Closing

STAGE 4:Monitoring-and-Controlling

Page 12: Review for Final in ISQS 7342

In which of these stages is a WBS started?

Initiating (Conceptualizing and Defining)• First 3 levels

{The WBS is usually finished in the Planning and Budgeting stage}

Page 13: Review for Final in ISQS 7342

What are the ten knowledge areas?

Scope management Time management Cost management Quality managementIntegration management

Risk management Procurement management Human resource management Communications management Stakeholder Management

Page 14: Review for Final in ISQS 7342

In which stage is scope management most important?

The first stage: Initiating (Conceptualization and Definition) because that is where scope is defined

Page 15: Review for Final in ISQS 7342

Activity Definition (Define Activities) is ___

a subproject a process a problem a plan

WHICH???

Page 16: Review for Final in ISQS 7342

Activity Definition (Define Activities) is part of what knowledge area?

Time management

Page 17: Review for Final in ISQS 7342

Project Scope Management Processes

Collect Requirements Define Scope Create WBS Verify Scope Control Scope

Page 18: Review for Final in ISQS 7342

Project Time Management Processes

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

Page 19: Review for Final in ISQS 7342

Project Cost Management Processes

Estimate Costs Determine Budget Control Costs

Page 20: Review for Final in ISQS 7342

Project Quality Management Processes

Plan Quality Perform Quality Assurance Perform Quality Control

Page 21: Review for Final in ISQS 7342

The main purpose of a project plan is to ____

acquire resources guide project execution. meet standards expectations. reduce risk.

Page 22: Review for Final in ISQS 7342

The most important output of project execution is

Not---change requests Not—the WBS Not—project plan Not—requirements doc

But—work products—the deliverables of the project

Page 23: Review for Final in ISQS 7342

The Principle…

That work tends to fill up the time allotted for it is known as…..

Page 24: Review for Final in ISQS 7342

Most core knowledge areas have a

Planning process

And a

Control process

Page 25: Review for Final in ISQS 7342

During the …

Conceptualization and definition stage, it is important that the project manager get

Page 26: Review for Final in ISQS 7342

What are the five steps of the Theory of Constraints (Goldratt)?

IDENTIFY the project constraint Decide how to EXPLOITE that

constraint SUBORDINATE everything to that

decision ELEVATE the system’s constraint Go back to step a

Page 27: Review for Final in ISQS 7342

NOT…

SUBORIDNATE that decision to everything else

Page 28: Review for Final in ISQS 7342

According to Goldratt…

Team players put too much ____ into their estimated durations

Page 29: Review for Final in ISQS 7342

As Goldratt sees it, ….

The ultimate constraint in projects is….

Page 30: Review for Final in ISQS 7342

Which of the following does Goldratt regard as a positive thing

Safety Multitasking Student syndrome Lose/lose contracting None of the above

Page 31: Review for Final in ISQS 7342

An activity has probabilistic completion times of 20, 50 and 80 for the optimistic, most likely and pessimistic durations. What is the average time

(duration) assuming a beta distribution?

30 40 50 60 70

Page 32: Review for Final in ISQS 7342

You should know

How to construct a NETWORK chart from a table

How to construct a Gantt chart from a table

How to perform NETWORK crashing

How to do EVAAll of the above

Page 33: Review for Final in ISQS 7342

A work package…

Has $100,000 budgeted for it Is 50% complete What is its BCWP = EV?? $30,000 $40,000 $50,000 $60,000

Page 34: Review for Final in ISQS 7342

A task with a $10,000 budget has a start date in the future

Its BCWS (planned value) is• $0• $5,000• $10,000• Can’t be determined

Page 35: Review for Final in ISQS 7342

A task with a $10,000 budget has a stop date in the past.

Its BCWS (planned value) is• $0• $5,000• $10,000• Can’t be determined

Page 36: Review for Final in ISQS 7342

A task with a $10,000 budget and a 6 day duration has just finished day 3

Its BCWS = PV is• $0• $5,000• $10,000• Can’t be determined

Page 37: Review for Final in ISQS 7342

A task has a budget of $20,000 and a scheduled duration of 5 days

What is its daily burn rate? $4,000 What is its PV rate? $4,000 If the project is 20% complete

what is its BCWP? $4,000

Page 38: Review for Final in ISQS 7342

A task has a budget of $20,000 and a scheduled duration of 5 days

What is its PV rate? $4,000 If the project is 20% complete

what is its BCWP? $4,000 If day three has just transpired,

what is the BCWS? $12,000 What is the task’s SV (schedule

variance)? -$8,000 Is the task ahead or behind

schedule???

Page 39: Review for Final in ISQS 7342

Questions about MS Project

Which key for subordination?• The Indent arrow

Which key for linking, for sequencing?• The linking tool

How to view project duration and cost on the project information dialog box?• Click on the Project tab and then the

Project Information Icon

Page 40: Review for Final in ISQS 7342

Questions about MS Project

How to see all of the cost and duration detail in the entry table in the ? view, including total PROJECT cost and duration

How to see all of the activity costs

Page 41: Review for Final in ISQS 7342

For MS Project to cost your project, it needs to know

Resource hourly costs• Specified in what view????

– The Reource sheet

Activity fixed costs• Specified on the Cost table

THIS IS ALL

Page 42: Review for Final in ISQS 7342

In MS Project, durations/costs of phases (summary tasks) …..

Containing one or more subordinate tasks can be specified only by MS Project

Is it a good idea to assign resources to summary tasks as well as to subordinate tasks?

No!!! Never!!

Page 43: Review for Final in ISQS 7342

Summary Tasks…..

Always appear in black or in blue?

Occur when….

Black, always

There are tasks subordinate to it

Page 44: Review for Final in ISQS 7342

Task info is entered in which view of MS Project, usually??

The Network View The Gantt view, using the Entry

Table The Resource Sheet The Tracking Gantt view

Page 45: Review for Final in ISQS 7342

When using the standard calendar, MS Project assumes

a. 8-hour work daysb. No work on Sat or Sunc. Two persons can do the work in

half o f the timed. All of the above

Page 46: Review for Final in ISQS 7342

Questions over CRITICAL CHAIN

Major conclusions, recommendations

Goldratt’s view of EVA What to Measure What to Focus on

Page 47: Review for Final in ISQS 7342

More Questions on CRITICAL CHAIN

To avoid non critical paths from becoming critical you should…

Critical chain is the sequence of tasks performed by key persons both on and off the critical path

Page 48: Review for Final in ISQS 7342

Measurements should

Induce the parts to always do what is good for the system as a whole

Page 49: Review for Final in ISQS 7342

Why does Goldratt not like BCWP, BCWS, ACWP?

Because they have no sensitivity to the critical path

Page 50: Review for Final in ISQS 7342

If you have a task on the critical path and …..

Your time to complete that task has arrived, then Goldratt recommends that you drop everything and just focus (150%) on that task until you get it done!! • No multitasking• No procrastination (student syndrome)

Page 51: Review for Final in ISQS 7342

Project Performance Measurement and Control

The first step is to…. SET A BASELINE…. The second step is to MEASURE PROGRESS AND

PERFORMANCE The third step is to COMPARE PLAN AGAINST

PERFORMANCE

Page 52: Review for Final in ISQS 7342

Project Performance Measurement and Control

The last step is TAKE APPROPRIATE ACTION

Project schedule status is usually communicated with a

Tracking Gantt Chart showing a progress line

Page 53: Review for Final in ISQS 7342

Notes on shortening project durations

This should be done in the Planning and Budgeting stage

Crashing• Reducing the duration of tasks on the

critical path Fast-tracking

• Starting tasks sooner Adding resources?? Checking for parallelism opportunities in

the schedule• Pull as much work off of the critical path as

you can

Page 54: Review for Final in ISQS 7342

More Tips on shortening project durations

REUSE, REUSE, REUSE Do it right the first time Avoid enhancements to

requirements Instead, consider scrubbing

requirements (reducing scope) If its early in the project, consider

• outsourcing some project work• Adding resources in-house• Using overtime

Page 55: Review for Final in ISQS 7342

More techniques for shortening projects

Scrub the requirements, as we mentioned• Remove from the requirements those items

that add little or no value, but nevertheless are significant contributors to cost

• Remember the Pareto principle—80% of the value comes from 20% of the functionality

Do everything right the first time (AGAIN)

REMOVE SAFETY--GOLDRATT

Page 56: Review for Final in ISQS 7342

Crashing Problem (Burns, Ch. 8)

For the network diagram below, find the best crashing strategy considering that you have $1300 in the crashing budget and the following:

Task Crash cost/da

y

Minimum duration

Duration

A $200 8 10B $300 10 12C $300 8 10D $400 10 13E $400 6 10F $350 5 7G $100 6 10Note from above that A can only be crashed

2 days, from 10 down to 8 days, etc.

10 22 22 35 0 0 10 22 22 35 0 10 35 42 42 52 0 0 0 0 10 35 42 42 52 10 20 20 30 5 5 15 25 25 35

A/10 F/7 G/10

B/12 D/13

C/10 E/10

PATHS LENGTH (Days)

CRASH G 6 Days

CRASH A 2 Days

CRASH B 1 Day

ABDFG 52 46 44 43 ABDG 45 39 37 36 ACEFG 47 41 39 39 ACEG 40 34 32 32 BUDGET SPENT 0 $600 $400 $300 BUDGET LEFT $1,300 $700 $300 $0

Page 57: Review for Final in ISQS 7342

Network diagrams, drawn by commercial software

Do they use • Activity-on-Node, or • Activity-on-Arrow representations?

Page 58: Review for Final in ISQS 7342

That’s all folks

{I enjoyed having you as a class—one of the best classes I’ve had)


Recommended