+ All Categories
Home > Documents > Rheda2000 en 2011 eBook

Rheda2000 en 2011 eBook

Date post: 07-Apr-2018
Category:
Upload: bbtdf
View: 219 times
Download: 1 times
Share this document with a friend

of 20

Transcript
  • 8/3/2019 Rheda2000 en 2011 eBook

    1/20

    The wy to o.

    rheda 2000 ballastless track system

  • 8/3/2019 Rheda2000 en 2011 eBook

    2/20

    RHEDA 2000

    The basis or the RHEDA 2000 is a track design frst implemented in

    1972 on the line rom Bieleeld to Hamm, Germany, at a station named

    Rheda. This original solution has continuously been urther developed

    and optimized, without a change in basic principle. Over the past 10 ... 15

    years, ballastless track has developed rom a customized design or

    niche applications, to standard technology or railway tracks on lines

    used or transport at high speeds and with heavy loads.

    The RHEDA 2000 ballastless track was used or the frst time in Germany

    in 2000, as pilot project on the new rail line between Erurt and Halle-

    Leipzig, with a total length o approx. 1,000 m. Subsequently, it was in-

    stalled on a urther section 3 km long. As a result o the positive experi -ence gained in the project engineering, installation, and operation o the

    RHEDA 2000 sections, Deutsche Bahn decided to employ over 180,000

    patented bi-block sleepers, based on RHEDA technology, or new con-

    struction o the high-speed line with its demanding engineering re-

    quirements between Cologne and the Frankurt Airpor t complex. In ad-

    dition, new construction o the section o line between Nuremberg and

    Ingolstadt, as part o the Nuremberg-Munich connection, was completed

    in good time or the FIFA World Football Cup events in 2006 in Ger-

    many. On this newly constructed section as well, approx. 75 km long, the

    RHEDA 2000 system rom RAIL.ONE was installed. Fortunately, these

    national projects were quickly and satisactorily ollowed by a break-

    through o ballastless track technology in the orm o RHEDA 2000 on

    the international stage o rail transport. One o the largest railway inra-

    structure projects in Europe to date has been construction o the new

    Dutch high-speed rail line HSL-ZUID, rom Amsterdam, via Rotterdam, to

    the Dutch-Belgian border. With the exception o a short section, the en-

    tire line with a total length o 88 km was constructed completely with

    RHEDA 2000.

    In 2006 RAIL.ONE won the contract or delivery o the bi-block sleepersrequired or the RHEDA 2000 ballastless track system installed as part

    o new construction o the 28 km o double track in the Guadarrama Tun-

    nel on the high-speed line rom Madrid to Valladolid, in Spain. On this

    same line, an additional 12 km o track was executed as RHEDA 2000 in

    the San Pedro Tunnel. Since February o 2008, this high-speed line has

    been in operation or speeds o 350 km/h. Likewise, 15 km was installed

    in RHEDA 2000 or the Sant Joan Desp Tunnel on the line rom Madrid

    to Barcelona, which was placed into service in December o 2007. In ad-

    2

    3

    On ballastless track tOward railways OOur contribution to high-speed technology: the RHEDA 2000 ballastless track system is the

    direct way to railways o the uture. For heavy loads. At top speeds. With a maximum o saety.

  • 8/3/2019 Rheda2000 en 2011 eBook

    3/20

    the future

    dition, a number o ballastless track projects with an estimated length o

    15 to 20 km were completed in 2006 and 2007, as part o the Eje Atlan-

    tico Project. These lines can be later converted rom the Spanish to the

    European gauge. For the section o the high-speed line rom Perpignan

    to Figueras, RAIL.ONE delivered an additional 28,000 bi-block sleepers

    o the RHEDA 2000 system, as well as over 28,000 linear metres o

    turnout sleepers.

    Launching o ballastless track or high-speed rail trafc on the Asian

    market succeeded in 2004 with application o RHEDA 2000 in new con-

    struction o the high-speed line rom Taipei to Kaohsiung, in Taiwan. In

    addition to the installation o Japanese ballastless track technology onthe open track sections, the demanding areas near and in the train sta-

    tions (in a total o approx. 80 km track and 115 turnouts) were imple-

    mented with the RHEDA 2000 system. The RAIL.ONE Group additionally

    participated in construction o the double-track passenger-dedicated

    line (PDL) rom Wuhan to Guangzhou in southeast China. Almost the en-

    tire line, with a length o approx. 1,000 km, was built with RHEDA 2000.

    Since December o 2009, trains use this high-speed line at speeds o

    350 km/h.

  • 8/3/2019 Rheda2000 en 2011 eBook

    4/20

    RHEDA 2000

    4

    5

  • 8/3/2019 Rheda2000 en 2011 eBook

    5/20

    The exbe wy o tos The RHEDA 2000 ballastless track system is ideal or applications on embankments,

    on bridges, in tunnels, as well as or turnouts and with vibration-optimized mass-spring systems. Installation o noise absorbers

    attenuates noise rom wheel-rail rolling and vehicle power-plant operation.

    Official apprOval and prOvn Tm

    RHEDA 2000 combines high levels o saety and long-term

    track positioning, with avourable construction costs and low

    maintenance expenses. The system accordingly ulfls all re-

    quirements or application on heavily travelled high-speed

    rail lines, and simultaneously assures optimal ride comort.

    RAMS analyses conducted according to international stan-

    dards confrm these benefts. In addition, RHEDA 2000 can

    be easily modifed to optimally ft all types o substructure.

    RHEDA 2000 has obtained General Approval rom the Ger-

    man Federal Bureau o Railways (EBA), as well as the User

    Declaration rom Deutsche Bahn AG, or application in high-

    speed trafc. In February o 2006, RHEDA 2000 urthermore

    achieved initial quality approval, in accordance with European

    Union Directive 96/48 EG or high-speed rail trafc. These

    qualifcations highlight the innovation capability and the per-

    ormance o RAIL.ONE as an international provider o high-

    tech or railway track design and construction.

    fo the ey be, rHda tehooy s syste

    souto o the ost e o use equeets

    hs oe the tes o ooth tk e-

    s.The crucial modifcations o RHEDA 2000 with respect

    to the original system consist, frst, o the employment o an

    especially integrated bi-block lattice-truss sleeper. Second,

    the latest version combines in situ concrete and a reinorced-

    concrete trough slab that are produced in one working step.

    The nonprestressed reinorcement bi-block sleeper, with op-

    timized concrete elements, likewise orms a monolithic struc-

    ture with the surrounding concrete o the track concrete layer.

    This structure can be uniormly implemented with extremely

    low structural height, on all kinds o suitable track substruc-

    ture.

    unified systems engineering and

    lOw track structural heightUse o RHEDA 2000 enables appreciable time and cost savings or project en-

    gineering and installation.

  • 8/3/2019 Rheda2000 en 2011 eBook

    6/20

    RHEDA 2000

    TOR = 0.00

    -493

    2650 - 3200

    3400 - 3800

    sleeper B 355distance 650 mm

    HBL

    The stes o eeoet o rHda tehooy beoe eet oso o the ous tk oss-setos.

    RHEDA (Classic)

    RHEDA (Sengeberg)

    RHEDA-BERLIN Hgv

    RHEDA 2000

    V2

    V3

    V1

    6

    7

    develOpment stages

    Of the rheda design

  • 8/3/2019 Rheda2000 en 2011 eBook

    7/20

    rHda 2000 s exbe syste tht be uy

    te to the se equeets the u

    ostts o eh ojet.The basic system structure, how-

    ever, always consists o modifed bi-block sleepers which are

    securely and reliably embedded in a monolithic concrete slab.

    Highly elastic rail astenings are essential to achieve the verti-

    cal rail deection required or load distribution and or smooth

    train travel.

    TH B 355-m lpr

    The B 355-M sleeper represents the core o the RHEDA 2000

    system. Due to mass production o these precast components,

    the sleeper provides both maximum concrete quality and high-

    est precision, especially at the most critical rail seat area. Theconcrete blocks can be individually designed to enable use o

    all conventional elastic astening systems and anchor fttings.

    The lattice truss reinorcement between the concrete sleeper

    blocks, the result o long years o development, takes ull ac-

    count o the stability aspects o transport and construction,

    and o eective embedding or great system reliability and

    durability.

    TH cOncrT Trac-ppOrTing lar

    The concrete track-supporting layer is the major load-distributing

    element o the system. Since it is cast-in-place, it can be individu-

    ally adapted to any substructure type and condition. For embank-

    ments, it is designed as a continuous slab with ree crack orma-

    tion. For highly compacted soil which is strongly advised or

    ballastless tracks to prevent settlement the slab can be con-

    structed in unit dimensions o 2.8 m x 0.24 m.

    To assure the required durability, the minimum strength o the

    concrete layer must be 30/37 MPa (cube/cylinder). Ater almost

    40 years o experience and countless applications o various

    Rheda track types, the concrete mix design o RHEDA 2000 has

    now reached a very high degree o perection. It ulfls even the

    most stringent demands or durability and reliability under a greatvariety o climatic conditions and applicable concrete standards.

    system design and

    cOmpOnents

    RHEDA 2000

    -773 ... -793

    *) Depending on the sub-grade and

    the properties of the supporting layer

    slab concrete C 30/37

    240*)

    300

    *)

    500*)

    -473 ... -493

    -233 ... -253

  • 8/3/2019 Rheda2000 en 2011 eBook

    8/20

    RHEDA 2000

    reinforcement accordingto static requirements

    protection layer

    reinforcement accordingto static requirements

    protection layer

    end-tO-end system

    structure On embankments,

    in tunnels, and On bridgesUniorm track concrete layers with low structural height ensure

    simplifed line routing and installation.

    rHda 2000 s hteze by xu eee

    o exbty. Thouhout ths tk y, the ooooets e the bs syste stutue, the oe

    b-bok seees, the ooth st--e su-

    ot oete sb. This basic system is varied in accor-

    dance with various sub-grade types, structural-engineering re-

    quirements, rail-support conditions, as well as cost-eective

    installation processes.

    On embankments, an additional bonded support layer oten

    a hydraulically bonded layer is installed in order to conorm

    to the permitted levels o stress in the supporting layers and

    on the subgrade.

    In tunnels, with the great stiness o the tunnel oors, only

    very slight stresses develop in the track structure by the mere

    nature o the confguration. As a result, no additional track

    supporting layers are required. In such cases, the concrete

    track-supporting layer is installed directly onto the track sub-

    structure. Further optimisation measures are possible both inthe concrete layer-thickness as well as in the content o rein-

    orcement. The end-to-end characteristics o the basic system

    ensure, during installation, that neither the undamental con-

    struction procedures nor the components must be exchanged

    or modifed. This assures a constant high level o quality,

    throughout, including the construction work as well.

    In most cases, dilatation joints are provided at the ends o

    bridges, and the track itsel is also interrupted over these

    joints. In addition, economical and technical considerations

    oten make it advantageous to decouple the track rom the

    bridge supporting structure. In such cases, RHEDA 2000 o-

    ers various possibilities or horizontal separation, and or as-

    tening by means o the concrete humps on the sleepers, or by

    patented steel bolt anchors.

    inTallaTiOn On Bridg

    Connection o the track concrete layer with the bridge structure by means

    o negative cam plates

    Connection o the track concrete layer with the bridge structure by means

    o positive cam plates in protection layer

    8

    9

  • 8/3/2019 Rheda2000 en 2011 eBook

    9/20

    reinforcement accordingto static requirements

    9

    levelling concrete

    TH dfiniT advanTag Of rHda 2000 ar a fOllO:

    A maximum o cost eectiveness and reliability by utilisation o concrete sleepers as superior-quality precast

    concrete building components in the critical area o the rail-seat zone

    Great precision o track-geometry parameters by application o precise concrete sleepers

    Great adaptability to all types o substructure and models executed, by means o application o cast-in-placeconcrete or the concrete track-supporting layer

    Great reliability as a result o technologically mature concrete engineering o the track-supporting layer or a

    great diversity o climatic conditions and concrete standards

    Flexible, high-perormance installation procedures on the basis o simple installation steps that are reproducible

    or both manual as well as automated procedures

    Great added value by local production possibilities

    Connection o the track concrete layer with the bridge structure by means

    o anchor dowels

    Track concrete layer, installed on levelling concreteTrack concrete layer, installed on tunnel-oor fll

    inTallaTiOn in Tnnl

  • 8/3/2019 Rheda2000 en 2011 eBook

    10/20

    RHEDA 2000

    additiOnal system sOlutiOns

    TrnOT iTH OpTimid TrcTral-

    dign TcHnOlOg

    With the objective o end-to-end system engi-

    neering or tracks and turnouts or the RHEDA

    2000 ballastless track system, extensive ad-

    aptation to reduced track structural height rep-

    resented an essential step in sleeper design.

    The key aspect o this development was design

    and dimensioning o a concrete turnout sleeper

    based on the B 355 bi-block sleeper. The GWS

    05 lattice-truss turnout sleeper currently rep-

    resents the optimized state o system develop-

    ment. With its end-to-end system engineering,

    this sleeper assures eective provision o the re-

    cesses below the base o the rail that are neces-

    sary or the turnout drive, as well as the contin-

    rail paniOn OinT

    The turnout sleeper or the RHEDA 2000 bal-

    lastless track system also oers a sae, reliable,

    robust, and at the same time exible basis or

    various types o rail expansion joints. The GWS

    05 sleeper is the heart o the system, and pro-

    vides stable, requirement-satisying, and ex-

    act mounting points - especially or the respec-

    tive installation components o a rail expansion

    joint. The monolithic concrete track layer can

    be adapted to the special requirements encoun-

    tered, especially in the immediate vicinity o the

    bridge joint. A number o major projects have al-

    ready been planned and executed in the RHEDA

    2000 system with special transition elements.

    uous reinorcement o the track concrete layer

    (approximately in the centre o the track cross-

    section). This solution achieves homogeneous

    height confguration in track and turnouts, and

    correspondingly reduces the weight involved.

    For project engineering and installation on the

    construction site, this means considerable time

    savings and cost reduction. The uniorm systems

    engineering eatures allow integration o all

    track substructure variations and conditions into

    the design. In Taiwan, or example, RAIL.ONE im-

    plemented complete train-station systems with

    a great number o turnouts and platorm connec-

    tions, on viaducts by means o pile-supported

    constructions, or in tunnel areas.

    10

    11

    subsoil

  • 8/3/2019 Rheda2000 en 2011 eBook

    11/20

    TraniTiOn

    The installation o ballastless track systems de-

    mands special attention or the transitions be-

    tween ballasted and ballastless track systems.

    With the RHEDA 2000 system, numerous sys-

    tem-optimized details enable stiness adaptation

    in the rail astenings and in the ballast, at such

    transitions rom ballastless to ballasted track.

    As a rule, these solutions include the frst step o

    multistage gluing o the ballast, in addition to an

    extension o the hydraulically bonded layer. This

    technique increases the stiness o the ballasted

    track system. In addition, a special pre-stressed

    sleeper with highly elastic rail astening is in-

    stalled in the ballasted track. This arrangement

    enables an increase in stiness, in several stages,

    between the ballastless track and the ballasted

    section. As an option, it is also possible to confg-

    ure auxiliary rails: both or these special turnouts,as well as on the ballastless track. This likewise

    reduces the difculties otherwise encountered at

    the interaces between ballasted and ballastless

    sections. The RHEDA 2000 system accordingly

    oers an optimal solution, with uniorm system

    engineering or all areas o application.

    lcTrOmagnTic cOmpaTiBiliT (mc)

    Ballastless tracks, with their reinorced concrete

    layers, have substantial electromagnetic proper-

    ties. In their development, it is necessary to con-

    sider eective measures against lightning and

    catenary line breakage. These measures involve

    grounding elements (equipotential bonding).

    Modifcations or extensions necessitate regular

    inspection o these elements.

    In high-speed rail trafc, unrestricted compati-

    bility is absolutely essential between train con-

    trol systems and the ballastless track. Control

    systems operate with transmission systems and

    use electromagnetic signal transmitters and/or

    signal receivers. These control systems unction

    directly in the reinorced-concrete track layers

    themselves (e.g., LZB and ETCS), or in the direct

    vicinity o these layers (e.g., UM 71 etc.). It is cru-

    cial to study the eects o longitudinal reinorce-ment, since it represents the primary attenuat-

    ing element.

    The RHEDA 2000 system has been tested or

    the most widely employed train control and man-

    agement systems: i.e., or the LZB in Germany,

    the ETCS trans-European high-speed train net-

    work, and the UM 71 in France and Asia. The

    RHEDA 2000 system has been approved as ob-

    serving the respective stipulated parameters.

    On the basis o its simple structure and con-

    struction methods, it is possible to quickly and

    economically conorm to all the requirements otrain control systems now in use.

    rOad-vHicl acc Tm

    New saety regulations in Europe stipulate that

    access or vehicles must now be ensured in rail-

    way tunnels or all types o road vehicles (pas-

    senger cars and lorries). As a result, a road-vehi-

    cle access system was developed or the RHEDA

    2000 ballastless track system. As an adaptive

    measure, this access system can be installed di-

    rectly onto the track. The emplacement o pre-

    cast concrete slabs onto B 355 bi-block sleepers

    provides an operating surace or road vehicles

    at a defned level below the top o rail. This de-

    velopment allows passenger cars and lorries

    with up to 10-tonne axle loads to use the sur ace

    as a roadway without restriction. An additional

    advantage o the precast parts results rom the

    act that smaller connecting elements in the vi-

    cinity o the rails and the rail-astening elements

    can be removed to allow easy perormance oobligatory maintenance on these components.

  • 8/3/2019 Rheda2000 en 2011 eBook

    12/20

    RHEDA 2000

    nOise and vibratiOnprOtectiOn

    nOi prOTcTiOn

    For signifcant reduction o airborne noise prop-

    agation, it is possible to install special noise-ab-

    sorber systems or ballastless track systems.This solution achieves good noise-engineering

    parameters, even or hal-surace installation in

    the outdoor areas o the rails.

    viBraTiOn prOTcTiOn

    The increase in train speeds, axle loads, and

    trafc volumes on current train lines has also led

    to increases in the noise and vibration to which

    the surroundings are subjected. Irregularities

    between rail and wheels, as well as the dynamic

    deormation o tracks when rolling stock passes,

    introduce vibrations into the subgrade. These

    vibrations are propagated into adjoining build-

    ing structures, which vibrate to lesser or greater

    degree. Secondary airborne noise can likewise

    produce disturbances. One o the most eective

    measures against the development o structural-

    borne noise and vibrations is mass-spring sys-

    tems. These systems attenuate the transmission

    o vibrations into the surroundings. The charac-

    teristics o the amplifcation unction o single-

    mass oscillators play a key role in the design omass-spring systems. The use o mass-spring

    systems is advisable especially in densely devel-

    oped areas sensitive to vibrations.

    Mass-spring systems can be implemented in

    light, medium-heavy, or heavy models. Light

    mass-spring systems are mounted on either

    strip supports or entire-surace supports made

    o elastomer matting. For heavy mass-spring

    systems, individual supports in the orm o elas-

    tomer blocks or steel springs are employed. The

    deeper the requency o the vibration to be re-

    duced, the higher the required mass o the mass

    track concrete layer. Here, the structure o

    the RHEDA 2000 ballastless track system o-

    ers benefts to the entire system: the appreci-

    able mass o the track concrete layer, with its

    bi-block sleepers embedded in concrete, con-

    tributes signifcantly to attenuation o vibrations.

    In addition, the RHEDA 2000 system as a re-

    sult o its structural properties insensitive to wa-

    ter and erosion is well suited or application

    both on open track sections, as well as in tun-nels. As a result, many and various orms o the

    mass-spring system are easible: light, medium-

    heavy, or heavy models, with the respectively re-

    quired support types o individual, strip, and en-

    tire-surace elastomer support.

    This great degree o design and adaptation ex-

    ibility makes the RHEDA 2000 ballastless track

    system on a mass-spring system an optimal solu-

    tion or satisying all requirements placed on vi-

    bration protection and operational unctionality.

    The RHEDA 2000 ballastless track system on a

    mass-spring system has already been installed

    in numerous projects, in the orm o various

    models: e.g., in the Cologne-Bonn Airport Link

    (as a heavy mass-spring system), in the Ber-

    lin North-South Link (with light to heavy mass-

    spring systems), and in the S-Bahn heavy-rail

    urban transit system in Unteroehring, on the

    outskirts o Munich (light mass-spring system).

    12

    13

    Application o the single-mass oscillator principle in the RHEDA 2000 track type on a mass-spring system

  • 8/3/2019 Rheda2000 en 2011 eBook

    13/20

    rHda ciT

    The RHEDA CITY track system has been de-

    signed especially or use with tram systems.

    This system is based on the same undamentalunctional principles as all track models in the

    RHEDA amily, especially the RHEDA 2000 sys-

    tem. The simple installation techniques produce

    good track positioning over the long term, with-

    out reworking. The system can be covered with

    asphalt, concrete, or paving stones, as desired.

    The latest development o RHEDA CITY is the

    vegetated (green) variation.

    mar TO rdc Tra crrnT

    Within the context o railway engineering, stray

    currents are currents that do not ow through

    the running rails o the track, as intended, but

    along other paths back to the rectifer substa-

    tions: e.g., through the earth. Stray current can

    cause considerable corrosive damage not only

    to the running rails, but also to nearby acili-

    ties that do not belong to the railway operations

    themselves: or example, the reinorcement o

    concrete elements, and piping made o metal.

    In order to reduce stray current and the negative

    eects that it causes, RAIL.ONE has placed great

    emphasis on eective electrical insulation o therunning rails with respect to the earth, in the de-

    velopment o its ballastless track system RHEDA

    CITY, or employment with tram systems in ur-

    ban transit. The primary design principle im-plemented here was the eective combination

    o electrically insulating system components

    such as rail-base coating, rail chamber ele-

    ments, and rail joint flling compound.

    RHEDA CITY has been installed in numerous cit-

    ies. Laboratory studies and measurements on

    rail lines in operation have verifed the eective-

    ness o the above-stated measures or reduction

    o stray current.

    rHda mrT

    The RHEDA MRT ballastless track system was

    especially developed or use with underground

    and surace mass rapid transit networks. The ba-

    sic principle corresponds to the RHEDA 2000

    high-speed system, with modifcation o the in-

    dividual components to meet the requirements

    o urban mass rapid transit: adaptation that has

    signifcantly reduced the structural height and

    weight o the system. The system is thereore

    optimally suited or use in tunnels, with simulta-

    neous enhancement o quality, saety, and per-

    manence. The MRT models can also be imple-mented as mass-spring systems.

    urban transit

  • 8/3/2019 Rheda2000 en 2011 eBook

    14/20

    RHEDA 2000

    design & engineering

    14

    15

    Bstess tk systes e se stutues tht e

    hstoy st ey eet oso to oe-to -eee woks suh s o bus,

    bes, tues. In many cases they cannot be de-

    signed and tested according to the generally accepted rules

    o good engineering practice. Particularly in the area o high-

    speed rail trafc, they are subject to extremely high saety

    standards. With respect to the budgetary and time-schedul-

    ing constraints applied in major international projects, alter-

    natives are available to long-term test series: i.e., other meth-

    ods that have or many years now been successully practiced

    in other felds o railway work such as train control and man-agement systems. For implementation o these methods - or

    example, as set orth in CENELC standards, particularly in EN

    50126 - track design must ollow a process that verifably as-

    sures the saety and the reliability o the entire system and its

    sub-systems, in addition to conormity with purely engineer-

    ing requirements. This process must above all satisy two as-

    pects: reliable break-down o the system into components,

    as well as step-by-step development, detailing, and checking.

  • 8/3/2019 Rheda2000 en 2011 eBook

    15/20

    Quality management

    Ta invOlvd in Trac aliT aranc:

    Checking o detail design and construction drawings, and

    o the geodetic project

    Verifcation o the quality management o the manuactur-

    ers o sleepers and other components

    Certifcation o the concrete supplier(s) or the track

    Checking, documenting, and clearance o the track-posi-

    tioning state beore concreting

    Checking o delivery documents and conormity o the con-

    crete suppliedChecking o the concrete technology, processing, and cur-

    ing in the track

    Supervision o rail handling: laying, welding, and grinding

    Re-checking o the track position

    Checking o the fnal documentation

    Preparation o the quality report

    Turnover with the line operator and other participants

    To quty oes wthout sy o rail.On, hs

    bee oe eeet o oote oy o the be-. Convincing evidence here is certifcation in accor-

    dance with DIN EN ISO 9001: all work processes are subject

    to continuous monitoring beginning with planning and engi-

    neering, including production, and extending to logistics and

    delivery. Documentation is by RAIL.ONEs own concrete lab-

    oratories, all o which are monitored by ofcial testing bu-

    reaus. The prime objective o the RAIL.ONE quality manage-

    ment system is the assurance o conormity o all delivered

    products, and ongoing enhancement o the satisaction o its

    customers. Deutsche Bahn AG has likewise recognized the

    competence and reliability o RAIL.ONE: classifcation as Q1

    provider is the highest quality level, achieved or years by

    RAIL.ONE. Ongoing RAMS tests or systems and system com-

    ponents urther highlight the reliability and availability o

    RAIL.ONE products.

    Production in oreign countries requires in all cases harmo-

    nisation o the standards and technical terms o delivery

    applicable in Germany and in the respective oreign coun-

    tries. The requirements resulting rom this harmonisation de-

    cide the choice o local raw materials, concrete qualities, and

    production processes. Proo o conormity o raw materials,

    the concrete quality achieved, and the sleeper quality with

    the requirements used as basis as well as certifcation oproduction as per DIN EN ISO 9001: all o this leads to ofcial

    national approval.

    The low structural height, the high track-geometry quality

    or assurance o unctionality and long lie cycles, as well as

    the permanent bonding o track concrete layer and sleeper

    reinorcement these are the quality characteristics o the

    RHEDA 2000 ballastless track system. Satisaction o these

    strict demands requires perect interaction o good system

    design with awless execution o construction. Integrated

    quality assurance guarantees RAIL.ONE objectives: close su-

    pervision o the entire process beginning with engineering, in-

    cluding in-house production monitoring, up to execution onthe construction site.

  • 8/3/2019 Rheda2000 en 2011 eBook

    16/20

    RHEDA 2000

    pOiBl ind Of fOrmOr

    Individually / manually (on site) manuac-

    tured ormwork (e.g., timber ormwork)

    Pre-abricated ormwork system elements

    (usually o steel)

    Pre-abricated (steel) ormwork system

    elements with integrated rails or

    construction vehicles

    mBanmnT

    Placing o the rost protection layer

    using conventional construction

    machines

    Placing o the hydraulically bonded

    layer using conventional construction

    machines

    civil TrcTr

    n Preparation o the civil structure

    surace and the possible track fxation

    elements according to the individual

    sub-/superstructure design

    amBl On iT

    Placing reinorcement

    Placing o single sleepers and installa-

    tion o track reinorcement

    Installation o rails (temporary or inal)

    pr-amBl

    Pre-assembly o the track panels on

    special sites

    Transport and placing o the complete

    track panels to the fnal installation

    location

    manal rOgH alignmnT

    Liting and rough alignment o the track

    panel using manual devices (rail jacks,

    track alignment rames, etc.) and survey

    instruments

    aTOmaTic rOgH alignmnT

    Liting and rough alignment o the track

    panel using automatic devices: e.g.,

    rough alignment machines, remotely

    controlled by electronic surveying

    instruments

    installatiOn techniQues

    The spreader-bar adjustment system involves a combined technique con-

    sisting o the ollowing two elements: vertical adjustment by means o

    spindles attached at the ends o the sleepers, and horizontal adjustment

    by special spreader bars at the centre o the sleepers. The spindle adjust-

    ment supports the track panel directly at the rail base and enables both

    vertical as well as horizontal track-panel alignment.

    With both techniques, the adjustment procedures are completed with ap-

    proval granted by the survey engineer. The next step includes the casting

    o the sleepers into a track concrete layer. Here, two measured points onthe rail may at intervals o 5 m have position or height dierences o no

    The et joty o the b-bok seees o the rHda 2000 sys-

    te e oue oy esey ostute outo ts.

    This arrangement reduces transport costs to a minimum. As a result o the

    simple installation technology, which does not require special equipment,

    local track and civil -engineering companies can install the RHEDA 2000. In

    addition, a surveying technique especially developed or the RHEDA 2000

    system assures great exactness o track position and geometry. The align-

    ment techniques used here using spreader bars and spindle -base adjust-

    ment units enable precise alignment and securing o the track panel, evenunder the most unavourable o construction-site installation conditions.

    Maximum precision during installation ensures exact

    and long-lasting track positioning

    gee oeew o rHda 2000 outo sequees, osst o u ehse stes o wok

    assembly Of the

    track panel

    preparatiOn Of

    the substructure

    rOugh alignment

    Of the track panel

    installatiOn Of

    the track fOrmwOrk

    lOgistic activities

    16

    17

  • 8/3/2019 Rheda2000 en 2011 eBook

    17/20

    vrTical final alignmnT

    Vertical fnal alignment using the vertical

    adjustment spindles o the spindle

    brackets

    Alignment o the required superelevation,

    with adjustment o the proper angle o

    the base plates o the spindle brackets

    HOriOnTal final alignmnT

    Horizontal fnal alignment using the

    horizontal adjustment screws o the

    spindle brackets

    manal cOncrT placing

    Manual concrete placing using concrete

    bucket and crane

    Manual concrete placing using concrete

    pump

    aTOmaTic cOncrT placing

    Concrete placing using an automatic

    concrete placing unit: e.g.,

    concreting unit

    cOncrT cring

    Wetting o the concrete surace

    Coating o the concrete surace with

    curing liquid

    Covering o the concrete surace with

    plastic or textile sheets

    avOiding Tr in nT cOncrT

    Loosening o the rail astenings

    final alignment Of

    the track panel

    placing Of the track

    cOncrete

    lOgistic activities

    supplementary

    wOrking steps

    more than 2 mm with reerence to each other dimensions that demand

    a maximum o exactness in concrete construction. The top-down installa-

    tion procedure inherent to this system can optimally satisy these exact-

    ing requirements. Production o special sleepers by RAIL.ONE with man-

    uacture and installation o the RHEDA 2000 system by local construction

    companies allows optimal economical cost/beneft relationship: both or

    RAIL.ONE as well as or the local industry.

  • 8/3/2019 Rheda2000 en 2011 eBook

    18/20

    RHEDA 2000

    18

    19

  • 8/3/2019 Rheda2000 en 2011 eBook

    19/20

    TH nT TcHnOlOgical Tp: BallaTl Trac

    iTHOT cOnTinO rinfOrcmnT

    An additional system solution is the new ballastless track sys-

    tem without continuous reinorcement. In its structural de-sign and unctional principle, it matches the current state

    o the art in construction o transportation inrastructure

    whereas, in contrast to the RHEDA 2000 system until now,

    it has eliminated continuous reinorcement. This elimination

    o reinorcement enables shortening o construction time and

    reduction in costs. This modifcation has also minimized un-

    wanted eects o the reinorcement on railway signalling sys-

    tems and on the electrical grounding acilities. Analogous to

    roadway construction, this new track system eatures provi-

    sion o lateral dummy joints that enable controlled ormation

    o cracks in the concrete track-supporting layer. These joints

    are sealed to prevent the intrusion o water. The transer o

    lateral orces, previously enabled by aggregate interlock, is

    now provided by bolt anchors. Furthermore, the higher con-

    crete grade C35/45 can be used, instead o the grade C30/37

    employed until now. This achieves greater resistance to rost,

    which in turn leads to longer lie cycles. Ballastless track with -

    out continuous reinorcement can be executed either with or

    without a hydraulically bonded layer.

    maimm rliaBiliT and afT in planning,

    cOnTrcTiOn, and OpraTiOn

    Over the past 40 years, ballastless railway track has devel-

    oped rom a niche product to internationally proven standardtechnology in the new construction o railway lines with spe-

    cial requirements. One o the most inuential systems or ap-

    plication o ballastless track with main-track sleepers is the

    RHEDA amily o ballastless tracks. RAIL.ONE holds the pat-

    ents or the latest and highest development stage o the

    RHEDA 2000 model and o the RHEDA Berlin system.

    The RHEDA 2000 system, as well as other models with

    RHEDA technology, have until now been installed in more than

    10 countries, in more than 2,000 km o tracks, and or more

    than 150 turnouts and rail expansion joints. The required of-

    cial approval has been obtained or each o the applications o

    RHEDA 2000, including a Certifcate o Conormity in accor-

    dance with European Union Directive 96/48 (Version 2001), or

    the line rom Amsterdam to the Belgian border. The use o the

    RHEDA 2000 system or the most widespread high-speed

    train systems the Shinkansen, TGV/Thalys und ICE and or

    the LZB, ETCS, and UM 71 signal systems verifes the com-

    patibility o this ballastless system. On the basis o the ex-

    tensive and widely varied experience gained with the RHEDA

    2000 system, it oers a maximum o security or every user:

    starting with the planning and approval phase, including in-

    stallation, and extending to operation.

    rheda 2000 a prOven systemwith wOrldwide reference prOjects

    provision of bolt anchorfittings for the joints

    concrete track-supporting

    layer 240 mm

    hydraulically bonded layer 300 mm

    ballast supporting layer

    track joints (filled with

    sealing compound)

  • 8/3/2019 Rheda2000 en 2011 eBook

    20/20

    April2011/0003416A-PROMO/V8-werbeagentur.de

    /Wereservetherighttomaketechnicalmodifcationswithoutpriornotice

    rail.On gbH | Ingolstaedter Strasse 51 | D-92318 NeumarktTel +49 9181 8952-250 | Fax +49 9181 8952-5050i il | il


Recommended