October, 2012 Rio Canoas Energia – Diversion of the River
Transcript
Page 1: Rio canoas energia   river diversion

October, 2012

Rio Canoas Energia – Diversion of the River

Page 2: Rio canoas energia   river diversion

2 OPENING OF THE CANAL

Rio Canoas Energia – Diversion of the River

Page 3: Rio canoas energia   river diversion

3

Rio Canoas Energia – Garibaldi Power Plant

WATER FLOW CONTROL CHANNELS

Page 4: Rio canoas energia   river diversion

4 CANOAS RIVER PASSING THROUGH WATER FLOW CONTROL CHANNELS

Rio Canoas Energia – Diversion of the River

Page 5: Rio canoas energia   river diversion

5

Rio Canoas Energia – Diversion of the River

OPENING OF THE CANAL

Page 6: Rio canoas energia   river diversion

6

Rio Canoas Energia – Diversion of the River

CANAL OPEN – DIVERSION OF RIVER CONCLUDED

Page 7: Rio canoas energia   river diversion

7

Rio Canoas Energia – Diversion of the River

Page 8: Rio canoas energia   river diversion

8

Rio Canoas Energia - Concession

Garibaldi Power Plant

Installed capacity – 177.9 MW;

Physical Guarantee – 83.1 average MWh;

70% of energy sold;

Bid in July 2010;

Located at Abdon Batista and Cerro Negro, Santa Catarina

state, Southern Brazil.

Concession rights: 35 years

Capex to date R$452 million in June 20122

Rio Canoas

Page 9: Rio canoas energia   river diversion

Contact

Email: [email protected]

+55 11 2169 3999

Rua Olimpíadas, no 205, Conjunto 142/143 Vila Olímpia - São Paulo - CEP: 04551-000

www.triunfo.com/ir

9


Recommended