Rio Canoas Energia – Diversion of the River
2 OPENING OF THE CANAL
Rio Canoas Energia – Diversion of the River
3
Rio Canoas Energia – Garibaldi Power Plant
WATER FLOW CONTROL CHANNELS
4 CANOAS RIVER PASSING THROUGH WATER FLOW CONTROL CHANNELS
Rio Canoas Energia – Diversion of the River
5
Rio Canoas Energia – Diversion of the River
OPENING OF THE CANAL
6
Rio Canoas Energia – Diversion of the River
CANAL OPEN – DIVERSION OF RIVER CONCLUDED
7
Rio Canoas Energia – Diversion of the River
8
Rio Canoas Energia - Concession
Garibaldi Power Plant
Installed capacity – 177.9 MW;
Physical Guarantee – 83.1 average MWh;
70% of energy sold;
Bid in July 2010;
Located at Abdon Batista and Cerro Negro, Santa Catarina
state, Southern Brazil.
Concession rights: 35 years
Capex to date R$452 million in June 20122
Rio Canoas
Contact
Email: [email protected]