+ All Categories
Home > Documents > Robert Smith· Techsec

Robert Smith· Techsec

Date post: 23-Jan-2022
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
25
CCOP /SOP AC Preliminary Report 12 August 1989 VIBRO AIRLIFT DEVELOPMENT AND TRIALS, LAUCALA BAY, FUI Robert Smith· Techsec Prepared by: Committee for Co-ordination of Joint Prospecting for Mineral Resources in South Pacific Offshore Areas (CCOP /SOPAC) Tonga Project: TG.6 •Contributed by: Commonwealth Fund for Technical Cooperation (CFTC) , and Australian International Development Assistance Bureau (AIDAB)
Transcript
Page 1: Robert Smith· Techsec

CCOP /SOP AC Preliminary Report 12

August 1989

VIBRO AIRLIFT DEVELOPMENT AND TRIALS,

LAUCALA BAY, FUI

Robert Smith·Techsec

Prepared by: Committee for Co-ordination of Joint Prospecting for Mineral Resources in SouthPacific Offshore Areas (CCOP /SOPAC)Tonga Project: TG.6

•Contributed by: Commonwealth Fund for Technical Cooperation (CFTC) , and AustralianInternational Development Assistance Bureau (AIDAB)

Page 2: Robert Smith· Techsec

[2]

Page 3: Robert Smith· Techsec

[3]

TABLE OF CONTENTS

Page

LIST OF FIGURES 4

ACKNOWLEDGMENT 5

INTRODUCTION 6

OBJECTIVE 6

HARDWARE EQUIPMENT

The A-frame 6

Airlift Drill and Components 8

DEPLOYMENT AND OPERATION 11LAUCALA BAY TRIALS 13

CONCLUSIONS 16RECOMMENDATIONS 16

APPENDICES

I A-frame Components 19

II Vibrocore Air Drill Components . . . . . . . . . . . . . . . . . . . . . . . . . .. 20

III Work Log. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 21IV Dewatering Cone & Bulk Sampling. . . . . . . . . . . . . . . . . . . . . . . .. 23

V Recommended Modifications to System 24VI Walking Beam Arrangement for Vibrolift . . . . . . . . . . . . . . . . . . . .. 25

Page 4: Robert Smith· Techsec

Figures1

2

34

5

67

[4]

LIST OF FIGURES

Page

Erected A-frame 7

Airlift drill and components 8

Drill bit assembly 9Sampler with eductor hose 10Deploying the vibro airlift 12

Coarse sand and coral fragments 13

Sample location map, Laucala Bay 15

Page 5: Robert Smith· Techsec

[5]

ACKNOWLEDGMENT

The development of this sampling system was made possible through the guidance andassistance of Dr Robert Woolsey and his engineering assistant. Their assistance is gratefullyacknowledged.

Page 6: Robert Smith· Techsec

[6]

INTRODUCTION

Previous sampling programmes using SOPAC's Geomarex vibrocoring system in coarse sand

and gravel deposits, of the type commonly used in building and construction materials, have met

with mixed success in that penetration depths achieved were minimal. The problem was

highlighted in discussions during the 17th Session of CCOP jSOPAC where a need to conduct

subsurface sampling of a possible offshore sand deposit in Tonga was identified. Because mining

of this material would require significant capital investment, it was therefore considered important

that the specifications and extent of the material are both well defined.

Dr Robert Woolsey of the Marine Minerals Technology Centre of the University of

Mississippi was present during these discussions. He has extensive experience developing and

using low technology subsurface sampling systems built from locally available materials. This

expertise was offered to CCOP jSOPAC to develop such a system for our needs.

As the Mineral Resources Department (MRD) research vessel Latui is no longer in service,

an alternative A-frame lifting system was needed which could be taken, set up, and used in

member countries on vessels of opportunity.

OBJECTIVE

1) Design and fabrication of an A-frame for vibrocorer and vibro airlift drill systems.

2) Fabricate an airlift system which would resolve problems previously found when sampling sand

and gravel deposits with CCOP jSOPAC's Geomarex vibrocorer.

3) Demonstrate the effectiveness of low technology systems to the CCOPjSOPAC Work

Programme.

HARDWARE EQUIPMENT

The A-frame

Figure 1 is a photograph of the A-frame in its erected state. The frame is constructed

entirely out of aluminium providing a lightweight yet sturdy structure. It can be broken down into

Page 7: Robert Smith· Techsec

[7]

Figure 1. Erected A-frame

sections that can be handled by two men and can be transported to the investigation site on the

small boats typically found in the work region.

The A-frame has a span of 7 m which will allow either the 6 m drill barrel of the vibrocoringsystem or the airlift system to be handled. The frame is easily assembled and secured. Insecuring the A-frame, angle iron brackets bolt to the frame base and in turn these are welded to

the steel deck of a barge type platform. In the event of encountering a wooden deck the frame

could be bolted directly to the deck. Two stays running back from the top of the A-frame tower

provide extra strength and support with eye hooks and turnbuckles allowing for tensioning of stays.

A 5-ton hand winch fitted with 100 m of 9 mm steel wire rope is used to raise and lower the drillunits or sampling device. (See also Appendix I).

Page 8: Robert Smith· Techsec

[8]

Airlift Drill and Components (see also Appendix II)

The airlift drill (Figure 2) was fabricated from locally purchased materials which can be foundin most building hardware shops.

To allow for ease of transportation the airlift drill breaks down into three sections, the drill

bit (Figure 3), drill barrels, and the vibro motor head attachment (Figure 1). This arrangement

also allows for optional hole depths of 3 m, 6 m and 9 m simply by adding an additional 3 m

length of 76 mm (3 inch) schedule 80 black iron pipe.

eductor hose ----- :--- .•.....--------:.- air hose

water hose --~ __ ~

;...a.------- vibro motors

power cable

drill barrel

water pipe to drill bit

Figure 2. Airlift drill and components at site.

Page 9: Robert Smith· Techsec

[9]

The barrel or drill pipe (Figure 3) was fabricated from 76 mm (3 inch) black iron pipeschedule 80, a thick walled pipe which helped to increase the overall weight of the airlift.

airline----

drillbarrell---~

drillbit--_

Figure 3. Drill bit assembly.

The air and water line pipes were fabricated from 13 mm (0.5 inch) ID 'C' grade galvanised

pipe which was available in 6 m sections. The air and water pipes were cut into 3 m lengths and

threaded so the sections could be screwed together.

The air delivery line is a standard 13 mm (0.5 inch) rubber hose using a standard quick

release bayonet fitting for connections.

Page 10: Robert Smith· Techsec

[10]

The water hose is a 36 mm (1.5 inch) PR pressure hose with quick release camlock fittings

for attachment to the water pump and to the water pipe at the top of the drill unit.

The educt or hose or delivery hose for the drill cuttings comprises two sections of 76 mm (3inch) x 18 m reinforced wire ribbed transparent suction hose with camlock quick release fittings.

Present hose lengths allow us to drill in water depths of up to 14 m.

Finally the sampler was constructed from a 200 litre drum with 76 mm (3 inch) camlock

fitting welded to the top of the drum. The sampler is a very important part of the system as thevelocity of the incoming material must be reduced, and the excess water in the sample must be

removed, without losing all the sample (Figure 4).

Figure 4. The sampler with eductor hose hooked up.

Page 11: Robert Smith· Techsec

[11]

The only modification to this low technology airlift system was the inclusion of two Geomarex

electric vibrator motors which were bolted to the top of the drill column. The motors served two

purposes:

I) they added weight to the system and

2) they assisted with the penetration and retrieval of the airlift.

In addition to the above equipment, the following power units are needed to operate the

airlift:

I) Air compressor: An Ingersollrand 110 air compressor (Figure 1) is used. This unit

provides the necessary volume of air (110 cubic ft/min) that is needed to lift the

cuttings from the drill bit to the sampling hopper. This type of unit is used to drive

jack hammers commonly seen at construction road repair sites.

2) Water pump: This unit provides a jet of water which is used to break up the

sediment being penetrated as well as providing a fluid medium to move the drill

cutting to the surface. The unit used, a Honda 3 inch, is capable of a maximum

delivery rate of some 1,100 lit res per minute.

3) Vibrocore motors: Two electric submersible vibrocore motors were bolted to the

head of the drill unit to provide vibratory action in the drill string. This not only aids

penetration but the vibratory action is essential when extracting the drill bit and pipe

from the hole. Power source for the vibro motors is a 6.5KV A power chief 3-phase

generator.

4) Winch: To deploy and retrieve the airlift a 5-ton hand winch with 100 m of 9 mm

steel cable is used.

DEPLOYMENT AND OPERATION

Figure 5 is a photograph of the airlift all ready for deployment. To begin, the water pump is

primed and started. Once the water jet is visible at the drill bit, the air compressor and vibro

motors are started and the airlift is then lowered to the seabed. Once the drill bit has penetrated

the seabed the unit is continually lowered until the desired penetration depth is achieved. As the

airlift is penetrating the seabed, the cuttings are sampled at the sampling hopper by collecting all

Page 12: Robert Smith· Techsec

[12]

Figure 5. Deploying of vibro airlift.

cuttings for the designated sampling interval in a suitable container. For example, if the sampling

interval were 1 m, the airlift would be lowered until a metre of penetration was achieved and then

stopped briefly, allowing for flushing and circulation of that interval. At that point the sample and

catcher would be removed from the sampling hopper and a clean container inserted to collect the

next sample. This process would be continued until the hole was completed. During the drillingprocess the air compressor, water pump, and vibro motors would be kept running from the time

the airlift spudded the hole until completion of the hole. One drawback to this system is that if

any of the power units fail, the drill string may become stuck in the hole, depending on depth of

penetration at the time of failure.

Page 13: Robert Smith· Techsec

[13]

LAUCALA BAY TRIALS

The airlift and the A-frame were mounted on a barge hired from Fiji Industries and towed to

a drill location in Laucala Bay.

The airlift was then tested in three different environments (see Appendix III for Work Log).The first was in shallow water, 70 em deep, approximately 0.5 km east of the present Fiji

Industries carbonate sand dredging site. Here approximately 2 m of penetration was achieved

before rock was encountered. Figure 6 illustrates the material penetrated which consisted of a

very coarse sand and gravel with large shell fragments and broken pieces of staghorn coral.

Because of the large compressor used the cuttings were able to be lifted through a head of some6 to 7 m.

Figure 6. Coarse sand and coral fragments.

The second location was in a water depth of 12 m and it was here that full penetration wasachieved, approximately 6.5 m. Cutting returns were a coarse carbonate sand with some coral

Page 14: Robert Smith· Techsec

[14]

rock, shell and staghorn fragments. At this site the lifting potential of the air was greatly

increased because of the pressure differential due to the 12 m water depth. Round trip time for

the hole, that is deployment to retrieval, was 30 minutes. The third location was west of theVunidawa river. Here three holes were drilled as indicated in Figure 7. Full penetration of

6.5 m was achieved in all three holes. The substrate drilled was a fine sand to mud with some

clay bands. Round trip time for each hole varied from 30 minutes for the first hole to 14 minutesfor the last hole.

Page 15: Robert Smith· Techsec

[15]

LEGENDH Vibro CAirlif-t SCAMple S-tCA-tion

SCALEGrid Co-ior cls. UTM (in Me-tres)

o 1000

SUVA

3000 METRES

LAUCALA BAY

Inltlo.!test site

655000

o DELAITUBANI

\

H 2H 3 0

o

REW'A DELTA

NUKUBUCD REEF

~MAKULUVA Is

660000

Figure 7. Sample location map, Laucala Bay

7997<400

7992400

Page 16: Robert Smith· Techsec

[16]

CONCLUSIONS

The trials with the airlift and A-frame were very successful and the desired results were being

achieved. The system worked better than anticipated in the coarse sand and gravel deposit, and

equally well in the softer silt sand and mud deposits. For future CCOP jSOPAC workprogrammes requiring the sampling of sand and gravel deposits, or bulk sampling for placer

deposit, this airlift system may be the best suited system as compared with the vibrocorer or theAcker drill rig.

With some modification the airlift depth of penetration can be increased to 9 m, but thiswould only be considered after more operational experience had been gained using the 6.5 m

assembly. A 20 minute video tape, showing the airlift operations in Laucala Bay, is available at

CCOP jSOPAC Techsec.

RECOMMENDATIONS

The following are recommended improvements to the system assembled at Techsec and tested

in Laucala Bay, February 1989.

1) Purchase a suitable compressor of same capacity used in trials (110 cm Ingersollrand).

2) Purchase a stronger eductor hose. This should avoid the crimping problems that were foundwhen working in the shallower water environment. There the hose weight was not supportedby the water, as it was when used in deeper water.

3) Construct an additional air manifold and bit assembly as a spare.

4) Purchase a bigger water pump. The Yanmar YDP diesel powered series model. YDP 4E isrecommended - principally because of the wet working environment.

5) Construct a dewatering core for bulk sampling (Appendix IV).

6) Increase water supply pipe to 1.5 inches and the jet to 1 inch ID (Appendix V) to increasewater volume and pressure which would aid the breaking up of the sediments being drilled.

7) Add cleats to the ropes used to support and manoeuvre the pipe string and hoses.

8) Add a T-bar arrangement or walking beam (Appendix VI) which is a manual pull down typearrangement to help penetration in coarser and more consolidated sediments.

9) Provide hinged points at the foot of the A-frame to aid standing of the tower.

10) Extend winch handle to allow two men to crank winch.

Page 17: Robert Smith· Techsec

[17]

11) Fit a sounder transducer to the drillhead, to measure the penetration. The preferred type is apipeless type unit with good water proofing qualities, because of the potential wet and dirtyworking conditions.

12) Construct an additional system of only the drill barrel, water and air pipes, the drill bit, andmanifold assembly.

Page 18: Robert Smith· Techsec

[18]

Page 19: Robert Smith· Techsec

[19]

APPENDIX I

A-FRAME COMPONENTS

"A" FRAME__

l.2.3.4.5.6.7.8.9.

10.ll.12.13.14.15.16.17.18.

TOP CROSS MEMBERTOP "A" FRAME x 2BOTTOM "A" FRAME x 2"A" FRAME SUPPORT FRONT x"" "REAR" If " "WINCH MOUNTNG BRACKET x 2

BASE MOUNTING BRACKET x 20PULLEY PIN x 210" PULLEY x 3CONNECTING PLATE x 4 (4" x 8" x 1/2")"A" FRAME BOLTS & NUTS 98 x 1/2""A" FRAME HOLDING DOWN BOLTSPULLEY PIN x 2PIN LOCK PLATE x 2STAY LUGS x 6STAY WIRE x 2SHACKELS 1/2" x 4

II

7 (FROM DRAWING BY JOE MAUSIO)

8

Page 20: Robert Smith· Techsec

CAMlOCKI •

• I'zI~ PIPE

I;; PIPE

[20]

APPENDIX II

VIBROCORE AIR DRILL COMPONENTS

VI BROCORE AIR DRILL (GUN)

oo

CAMLOCKT~'~.~£=:::r'C GRADE

PIPE 8\".1.

.•.• 11---6'74 CLEARANCE

_-1- 1 HOLE

3,; Mis PLATE

o

o ooo

-+-----2

-H~+----- 3 ----+-1

1+-++-1----- 4 ----H~I

I~·COLLER

o 0 5---++4-I •

4'z PIPE x 20 LENGTH

--+-----6

, I "21',z PIPE x 21:lz LENGTH

II;COLLERo

8'

-4-----7---4189

I:t-~~.c::::::.-.---IO "II~HOLE

~§- \ x3" BOLTS and NUTS

I VIBROCORE MOUNTING2 TOP CORE TUBE3 TOP WATER TUBE4 TOP AIR TUBE5 ALLAN SCREW x 8

115" 6 BOnOM CORE TUBE7 AIR TUBE HOUSING8 AIR TUBE SLEEVE

9 DRILL BIT10 WATER JETII Mis BOLTS and NUT'S x 16

3 •127<t

(FROM DRAWING BY JOE MAUSIO)

Page 21: Robert Smith· Techsec

December-January 1989

January 23-31

February 11

February 13-17

February 20

February 21

February 22

1250

1325

1445

1530

1700

February 23

1200

[21]

APPENDIX III

WORK LoG

Design and fabrication of A-frame and ancillary equipment atMaxlane Engineers.

Negotiations with Fiji Industries for the use of barge for vibro airlifttrials.

Locating items as supplied by list necessary for vibro airliftconstruction.

Mobilisation of equipment and training MRD Offshore staff at thesame time as collecting background geophysical data for vibro airlifttrials.

Arrival of Dr Bob Woolsey and Engineering Assistant.

Purchase and fabrication of vibro airlift at Techsec HO. Machinework done at IMEL, Walu Bay.

Mobilisation of equipment onto Fiji Industries barge.

Set up A-frame. Vibro airlift ready for towing to drill locations.

Towed to location, moor barge. Prepare to drill first hole.

Start water pump compressor vibro motors. Drill hole (WD 8 m).

Retrieve system drilled (1.5 m hit rock). Site was on reef slope intolagoon.

Reposition barge - start water pump compressor, etc. Drill hole onreef top (WD 70 cm).

Stop all systems. Water pump died. Retrieve vibro airlift. Drilled2m.

Shut down, secure barge for night. Return to RSYC.

Obtain water pump from Dive Centre as CCOP/SOPAC pump needscomplete overhaul. Require new fittings for water line.

On location prepare to test system.

Page 22: Robert Smith· Techsec

[22J

1310 Start drilling. Hit rock at 2 m on slope to lagoon floor(WD 10-11 m).

Reposition barge, secure.

1350 Start system.

1430 Retrieve airlift. Full penetration of 6 m achieved. (WD 12 m).Demonstrate system to John Harper and Bruce Richmond.

1730 Secure barge for night. Return to RSYC.

February 24

0915 Fiji Industries tug tows barge to drill location west of Vunidawachannel.

10331050

Site 1 :Start system (WD 2 m).Stop system, secure barge to prevent driftduring drilling.

Start system (WD 3 m).Stop system after drill retrieved. Drilled 6 m.Sampled every 2 m.

11071139

1220Site 2 :Start system (WD 2 m).Stop system, drilled 6 m. Visit by Director and staff of Techsec.Also MRD engineering staff visit to observe operations.Transportation by Beranaliva.

13261340

Site 3 :Start system (WD 2 m).Stop system drilled 6 m.Sampled every 2 m. Tests very successful.

1430 Secure barge for tow back to Lami base.

1630 Secure barge on mooring at Lami for weekend.

February 25

February 27

Departure of Dr Bob Woolsey.

Demobilisation of A-frame and drill system, cleaning and storage atTechsec HQ.

Page 23: Robert Smith· Techsec

[23]

APPENDIX IV

DEWATERING CONE 8 BULK SAMPLINGfrom a sketch by Dr Woolsey

os-,

76mm"~---I

a'5m

Inlet6mm pipe with ~camlack fitling /'

10gauge or Immsheet metal

os-,C Sample catchment trough

SIDE VIEW

Battel

76mm 0 pipewafer overflow

sample 0oullet

SampleInlet '---

lJv''"'--------=--~~tack welded

76mm » pipe withcamlock fitting PLAN VIEW

Page 24: Robert Smith· Techsec

[24]

APPENDIX V

RECOMMENDED MODIFICATIONS TO SYSTEM

Some Recommended Modifications to System by Dr Woolsey

1. Water System

Using the volume type pumps, the volume and pressure may be increased by increasing thewater hose and supplying pipe to 1.5 inch (38 mm) and jet to 1 inch (25 mm) J.D.

EXAMPLEthreads in

I" (25mm)set pipe JE~: ~:;: :::::::::::,::::~,::::~36·75 mm

galvanized pipe

36·75 mm x 24·5mm bell reducer

2. Preparation of Coarse Coral Material and Deep Drilling Applications

a) The present system can be modified for drilling coarse grained material by adopting ahammer lift action as drilling takes place and by adapting the winch and A-frame to handle awalking beam. See Appendix III figure.

b) For deeper drilling (15 to 20 m) in consolidated material the system can be modified bychanging the upper 3 m section which is fitted with vibrator engine mounts to a straightsection of pipe.

Example : 3 x 0.076 m section pipe.

EXAMPLE3 x 0·076 m section pipe

-. UP

Page 25: Robert Smith· Techsec

TI

41

IIII

IIIIIIIII...i.

[25]

APPENDIX VI

1"2" PIPE"T-HANDLE" TOP VIEW

411 Channel

/STOP BAR: fixed to frame SIDE VIEW

WALKING BEAM

(

WINCH

Pivot point(on winch tromel-:

WALKING BEAM ARRANGEMENTfor Vibrolift System


Recommended