Robust Project Planning & Documentationin
Large-scale deployment of IEC 61850
IEC 61850 Europe 2014
Prague 2014-10-16Confidentiality - None (C1)
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
Content
• Background
• Driving forces for standardization
• IEC 61850 process based on a pilot concept
• Robust project planning and documentation with third party tool
• Large scale deployment of IEC 61850
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
Background
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
• Rapidly aging substation automation systems
(SAS)
• Limited life time of modern DSAS devices
• Unique solutions because of functional purchase
• Need a new standardized concept to efficiently
replace SAS
• Strategic direction within Vattenfall Distribution to
standardize DSAS by implementing IEC 61850
Driving forces for standardization
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
Future-proofinvestments
Sustainable asset management
Uniform structure
Pilot SS Upplands Väsby
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
Vattenfall IEC 61850 Process supported by Specification and Lifecycle Management Tool
FunctionLibrary
Formal System
Specification
GeneralSpecifications
SignalList
GeneralSpecification
IEC61850
SSD
System
Design IEC61850
SCDSignal
List
Design Review
(FAT)
Re-import Delivery to
Specification ToolValidation against
Specification
Delivery
Review(SAT)
IEC61850
SCD
Signal
List
Maintenance
Cycles
Commissioning
As Build
Doc
Specification
Design
As Build
Vendor independent Specification Tool
(HELINKS STS)
Specification& Integration Tool
Vendor SpecificTools (IED & System
Integration
Colors indicate
tool usage
Data Flow & Workflow
Iterations and Feedback Flow
Export from
Specification ToolImport to Integration Tool
Commis-
sioning
• Develop work processes for IEC 61850- Test a new model for project execution (based on SCL files) for
IEC 61850 SAS that covers the whole life cycle of the substation
- Specification with top-down architecture by using 3rd party
software
• New technology and new concept- Test new equipment for process bus IEC 61850-9-2 to collect sampled
values
- Developing and testing Vattenfall standard Service PC solution, including a Remote Access solution
- Critical substation functions as blockings, interlockings, bfp, collection
and triggering of disturbance files and information from/to IEDs to
gateway is done via the station bus
Vattenfall Distribution Project Model
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
• Vattenfall is an organization which purchasenew substations based on functionalrequirements, ie we do not decide the construction
• All design and construction is done by external contractors
• The Vattenfall IEC 61850 process developedis therefore focused on the activities:
- Specification
- Acceptance of delivery
- Final documentation for O&M activities
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
IEC 61850 Process supported by tools
3
IED configurationtools
IID
SCD
6SCD
with Substation Structure
& SignalNames
SS/VL/Bay/OC_4PTOC.Str.general
DOI Description: Imax/Start
Scada Signal List
SSD
Only Substation Structure
SCL: SS/VL/Bay
Functions&SignalNames
SS/VL/Bay/PTOC.Str.general
+ Imax/Start
2
8
Project
Documentation
System Integration
tool
IEDs
Logical Nodes
DataObjects
Map with
Function &
Signalname
Substation Structure
4
Co
mm
unic
ation
En
gin
ee
ring5
Initial Vattenfall Engineering Workflow
VF Third-party tool
IEDs
Logical Nodes
DataObjects
104 Addresses
Scada Attributes
De
sig
n
Va
lida
tion
7
Substation Structure
Functions
Logical Nodes
DataObjects
1VF Library
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
Use of three different signal naming principles in third-party tool
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
• Apart from the IEC 61850 product and functional names VF also uses a third
naming based on classical company names for functions and signals. This to
minimize the knowledge gap
Function Library
• Reflecting Vattenfall standards
• Combines IEC 61850 elements with no IEC 61850 elements
• Creation of substation specific signal list from the library
• Library exchange as ZIP-file between users
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
Design review
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
• Comparision of specified signals with the implemented signals
• IED by IED review to get an overview of the quality of delivery
• Following statuses are added for every signal:
Specified, Implemented as specified, Implemented differently and Implemented
Visualization of GOOSE exchange at the functional level
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
• The aim is to vizualize GOOSE functions in the third-party tool from a functional perspective instead of a communiation view
Desired visualization Status today
Advantages for Vattenfall with the new IEC 61850 process
• Minimize errors caused by humans
• Standardized and scalable solutions
• Increased efficiency
• Clear and coherent utility/contractor relationship
• Larger volumes of standardized solutions
• Increased future possibilities
• Uniform structure
• Sustainable substation management
• Future proof investments
Robust Project Planning & Documentation in Large scale deployment of IEC 61850 | Berkan Kapkac | 2014-10-16
Future proof our assets
-MISSION
Master
IEC 61850
OTHER OBJECTIVES
New business
opportunities
Modern way of work
Game Plan – IEC61850 deployment at Vattenfall
CRITICAL SUCCESS
FACTORS
Implementnew process IT infra-
structure in place
Fast experiencefeed back
Developinhouse
knowledge
Management
commitment
& support
Strong connection to
ordinarybusiness
RESOURCES
• Prtoection &
Automation
Engineers
• Project
managers
• Communication Specialists
• Process
development
team
• Management
• IT-department
• Change
Management
• Purchase
department
• Maintenancedepartment
Prepare large-scale deploym.
• Impl new process
• Update the governing doc
• Coord technical guidelines & tool library
• Education & training
• Inform Entrepreneurs
• Plan for multiple substations
• Pre-studies for software and file management
• Communicate
Impl large-scale
deployment
• BAU in process-organisationen
• IEC61850-knowledge relevant at recruitment
• Measure & Followup
• Incentive for increaseddevelopment ofDSAS
• Develop SW and file mgmt solutions
• Communicateinternally & externally
• Pilot substation
• Develop concept
• Develop process
• Test tools (Third-party tool & ServicePC)
• Evaluate overall
• Risk Analysis
Develop
conceptRefine the
concept
• Complete and
refine process
• Improve tools
• Acceptance Test
• Business Case
• Clarify decision making and strate-
gic direction
• DEMT decision
• Software and file management solutions in place
• Valid for all substation projects
• New procurement strategy
• New maintenance strategy