+ All Categories
Home > Documents > Role of Synchronized Measurements In Operation of Smart Grids - bu. · PDF fileRole of...

Role of Synchronized Measurements In Operation of Smart Grids - bu. · PDF fileRole of...

Date post: 13-Feb-2018
Category:
Upload: vankien
View: 223 times
Download: 2 times
Share this document with a friend
54
Role of Synchronized Measurements Role of Synchronized Measurements In Operation of Smart Grids In Operation of Smart Grids Ali Abur Ali Abur Electrical and Computer Engineering Department Electrical and Computer Engineering Department Northeastern University Northeastern University Boston, Massachusetts Boston, Massachusetts Boston University Boston University CISE Seminar CISE Seminar November 12, 2010 November 12, 2010
Transcript

Role of Synchronized MeasurementsRole of Synchronized Measurements In Operation of Smart GridsIn Operation of Smart Grids

Ali AburAli AburElectrical and Computer Engineering DepartmentElectrical and Computer Engineering Department

Northeastern UniversityNortheastern UniversityBoston, MassachusettsBoston, Massachusetts

Boston UniversityBoston UniversityCISE SeminarCISE Seminar

November 12, 2010November 12, 2010

Operating States of a Power System

RESTORATIVE STATE

PARTIAL ORTOTAL BLACKOUT

SECURE or

INSECURE

OPERATIONAL LIMITSARE VIOLATED

EMERGENCY STATE

NORMAL STATE

Recommendation 12: Install Additional Recommendation 12: Install Additional TimeTime--Synchronized Recording Devices Synchronized Recording Devices as Neededas NeededA valuable lesson from the August 14 blackout is the importance of having time-

synchronized system data recorders. NERC investigators labored over thousands of data items to synchronize the sequence of events, much like putting together small pieces of a very large puzzle. That process would have been significantly improved and sped up if there had been a sufficient number of synchronized data recording devices.

NERC Planning Standard I.F —

Disturbance Monitoring does require location of recording devices for disturbance analysis. Often time, recorders are available, but they are not synchronized to a time standard. All digital fault recorders, digital event recorders, and power system disturbance recorders should be time stamped at the

point of observation with a precise Global Positioning Satellite (GPS) synchronizing signal. Recording and time-

synchronization equipment should be monitored and calibrated to assure accuracy and reliability.Time-synchronized devices, such as phasor measurement units, can also

be beneficial for monitoring a wide-area view of power system conditions in real-time, such as demonstrated in WECC with their Wide-Area Monitoring System (WAMS).

Recommendation 12a: The reliability regions, coordinated through the NERC Planning Committee, shall within one year define regional criteria for the application of synchronized recording devices

in power plants and substations. Regions are

requested to facilitate the installation of an appropriate number, type, and location of devices within the region as soon as practical to allow accurate recording of future system disturbances and to facilitate benchmarking of simulation studies by comparison to actual disturbances.

Recommendation 12b: Facilities owners shall, in accordance with regional criteria, upgrade existing dynamic recorders to include GPS time synchronization and, as necessary, install additional dynamic recorders.

Tenets of Smart Grid Operation(Department of Energy)

Self-healing from power disturbance events

Enabling active participation by consumers in demand response

Operating resiliently against physical and cyber attacks

Providing power quality for 21st century needs

Accommodating all generation and storage options

Enabling new products, services, and markets

Optimizing assets and operating efficiently

Role of State EstimationFacilitating Smart Grid Operation

Self-healing from power disturbance eventsFaster (scan rate) state estimation, wide-area observability, multi-level monitoring capability

Enabling active participation by consumers in demand responseMonitoring at lower voltage levels

Operating resiliently against physical and cyber attackRedundancy and strategic placement of measuring devices/sensorsDetection, identification and elimination of errors in data and models

Providing power quality for 21st century needsAccommodating all generation and storage optionsEnabling new products, services, and marketsWide-area monitoring to facilitate the feedback to address congestion, avoid spilling renewable energy, active market participation

Optimizing assets and operating efficientlyMonitoring dynamic line loading, equipment operating limits

State Estimation State Estimation

Analog MeasurementsPi , Qi

, Pf

, Qf

, V, I, θk

, δki

Circuit Breaker Status

State Estimator

(WLS)

Bad DataProcessor

NetworkObservability

Analysis

Topology Processor

V, θ

Assumed or Monitored

Pseudo Measurements[ injections: Pi , Qi

]

Load ForecastsGeneration Schedules

Measurement ModelMeasurement Model

Given a set of measurements, [z]Given a set of measurements, [z]and the correct network topology/parameters:and the correct network topology/parameters:

[z] = [h ([x]) ] + [e][z] = [h ([x]) ] + [e]

Measurements ErrorsSystemState

Network ObservabilityNetwork Observability[z] = [h ([x]) ] + [e][z] = [h ([x]) ] + [e]

Given [z], can [x] be estimated?Given [z], can [x] be estimated?

Which branch flows can be estimated?Which branch flows can be estimated?Unobservable branches separate Unobservable branches separate observable islands.observable islands.

How to merge observable islands?How to merge observable islands?Optimal measurement placement.Optimal measurement placement.Role of pseudo measurements.Role of pseudo measurements.

Observable IslandsObservable Islands

ISLAND 1 ISLAND 2

ISLAND 3

Loss of Observability due to Line SwitchingLoss of Observability due to Line Switching

OBSERVABLECLOSED CB

Loss of Observability due to Line SwitchingLoss of Observability due to Line Switching

UNOBSERVABLEBRANCHES IN RED

OPEN CB

Robustness Against Topology ChangesRobustness Against Topology Changes

ObservableObservable

Observable Unobservable

Base Case

Base Case

Meter PlacementGiven a set of measurements

z = h(x) + e

Must be able to estimate x using “z”

if

any one measurement is missing, or

any branch is disconnected

Accomplish the above with least cost metering upgrade

Three stage solution

Make the network minimally observable.Identify essential measurements

Find a set of candidate measurements.To fix each contingency ( a branch outage or loss

of a measurement).

Determine the optimal selection.To provide secure state estimation under single

contingencies.

Candidate Matrix [A]CANDIDATES

Contingencies

Optimal Selection

XC T minimize

bXA Subject to

0/1 Integer Programming

01

ijA If meas. j is a candidate for contingency iotherwise

01

iXIf meas. i is selectedotherwise

bT=[1 1 1 … 1]

0

iciC

cost of installing meas. iif meas. i already exist

30-Bus System Example

PMU Measurements:PMU Measurements:

Several channels measuring:Several channels measuring:

Phase angles or magnitudes of bus voltagesPhase angles or magnitudes of bus voltages

Phase angles or magnitudes of branch currentsPhase angles or magnitudes of branch currents

Use of synchronization signals from the Use of synchronization signals from the global positioning satellite (GPS) systems global positioning satellite (GPS) systems

Minimal time skew between measurementsMinimal time skew between measurements

CONSIDERATIONSCONSIDERATIONS

AlgorithmAlgorithm

Could it be modified / improved ? Could it be modified / improved ?

Measurement DesignMeasurement Design

Where to place new PMUs ?Where to place new PMUs ?

Impact Impact

Will the grid be better monitored ?Will the grid be better monitored ?

State Estimation with PMUsState Estimation with PMUsMathematical model Mathematical model

r

xhxh

xhxhxh

zzzzz

I

I

V

trad

I

I

V

trad

)()(

)()()(

)Im(

)Re(

)Im(

)Re(

rxhztoSubjectWrrxJMinimize T

)()(

Impact on Problem Solution:Impact on Problem Solution:

iterativeNonZRHRHX

eXHZtsMeasuremenPhasor

IterativeZRHRHX

eXhZtsMeasuremenalConvention

T

T

111

111

)(ˆ

)(ˆ)(

Removal of Slack (Ref) BusRemoval of Slack (Ref) Bus

Eliminate the reference phase angle from Eliminate the reference phase angle from the SE formulation. the SE formulation.

Bad data in conventional as well as PMU Bad data in conventional as well as PMU measurements can be detected and measurements can be detected and identified with sufficiently redundant identified with sufficiently redundant measurement sets. measurement sets.

PMUMeas.

OtherMeas.

State

Estimator &

Bad Data

Processor

Estimated/CorrectedPMU Meas.

Estimated State

Merging Observable IslandsMerging Observable Islands

PMU

PMU

PMU

3 Critical PMUs3 Critical PMUs Error in PMU at Bus 12Error in PMU at Bus 12

MeasurementNormalized

residual

0.01130.01120.00820.00760.0064

Test A

87p8p2q

1V

3q

NO BAD DATADETECTED

Adding 2 Current PMUsAdding 2 Current PMUs

PMU

PMU

PMU

Cur

Cur

3 Voltage, 2 Current PMUs3 Voltage, 2 Current PMUs

MeasurementNormalized

residual

3.263.212.892.761.22

Test B

12

612

136q1312

126q

BAD PHASE ANGLEMEASUREMENTAT BUS 12 IS DETECTED

A Practical AdvantageA Practical Advantage

PMUs can be placed at any bus in the PMUs can be placed at any bus in the observable island.observable island.

PseudoPseudo--measurements can merge measurements can merge observable islands only if they are incident observable islands only if they are incident to the boundary buses.to the boundary buses.

PMUs with Multiple Channels:PMUs with Multiple Channels:

PMUV phasorV phasor

I phasorsI phasors

PMU with multiple channels will measure:• V_phasor at the bus• I_phasors for all incident branches

Simple Illustration for Full ObservabilitySimple Illustration for Full Observability

Only Only 3 PMUs3 PMUs make the entire system observable.make the entire system observable.Note that Note that bus 7bus 7 is a is a zero injectionzero injection bus.bus.

PMUs with Two Channels:PMUs with Two Channels:

PMUV phasorV phasor

I phasorI phasor

PMU with two channels will measure:• V_phasor at the bus• I_phasor along a single branch

Simple Illustration of PMU PlacementSimple Illustration of PMU Placement for Full Observabilityfor Full Observability

Only Only 7 PMUs7 PMUs make the entire system observable.make the entire system observable.

PMU Placement ProblemPMU Placement Problem•

Can be formulated and solved efficiently using Can be formulated and solved efficiently using Integer Programming even for very large Integer Programming even for very large systems.systems.•• PMUs can also be placed to make one or more PMUs can also be placed to make one or more geographical zones or voltage levels geographical zones or voltage levels observable.observable.•• PMUs placement can take advantage of any PMUs placement can take advantage of any existing zero injection buses.existing zero injection buses.

Effects of considering zero injectionsEffects of considering zero injections

Systems No. of zero injections

Number of PMUs

Ignoring zeroInjections

Using zero injections

14-bus 1 4 3

57-bus 15 17 12

118-bus 10 32 29

Impact of Channel Limits on PMU Placement

How does the optimal placement change as a function of available number of channels?

Assume that one channel corresponds to one positive sequence measurement.

Number of neighbors of a bus usually has a small upper limit for typical power systems due to sparse interconnections.

6136126116106968677106710571048103911214151

530-bus

445444443552771

114-bus

Consider Zero Injections

Ignore Zero Injections ChannelsZero InjectionsSystem

Simulation Results

283292832828327283262832528324313333942257611

10118-bus

118

117

111761117511174121731419223291

1557-bus

Consider Zero Injections

Ignore Zero Injections Channels Zero InjectionsSystem

Simulation Results

How can PMUs help to improve Bad Data Detection?

A measurement is said to be “critical”

if the system becomes unobservable upon its removal.

Bad data appearing in critical measurements can NOT be detected.

Adding new measurements at strategic locations will transform them, allowing detection of bad data which would otherwise have been missed.

Illustrative ExampleIllustrative Example

P

Two Critical Two Critical MeasurementsMeasurements

NO Critical NO Critical MeasurementsMeasurements

IEEE 57IEEE 57--bus systembus systemCriticalCriticalMeas.Meas.

TypeType

11 F41F41--4343

22 F36F36--3535

33 F42F42--4141

44 F40F40--5656

55 II--1111

66 II--2424

77 II--3939

88 II--3737

99 II--4646

1010 II--4848

1111 II--5656

1212 II--5757

1313 II--3434

P

P

Number of Critical Meas.Number of Critical Meas. Number of PMU neededNumber of PMU needed

1313 22

IEEE 118IEEE 118--bus systembus systemNumber of Critical Meas.Number of Critical Meas. Number of PMU neededNumber of PMU needed

2929 1313

P

P

P

P

P

P

P

P

P

P

P

P

P

Impact on Covariance of the State (GImpact on Covariance of the State (G--11))No PMUNo PMU 10% 10%

PMUPMU 20%PMU20%PMU 30%PMU30%PMU 40%PMU40%PMU Only Only PMUsPMUs

Power InjectionsPower Injections 3838 3838 3838 3838 3838 00Power Flows Power Flows 5656 5656 5656 5656 5656 00

Voltage magnitudeVoltage magnitude 11 11 11 11 11 00PMU ( 1 v, 3 currents )PMU ( 1 v, 3 currents ) 00 33 66 99 1212 1010

--PMU ExamplePMU Example--

1PMU Measurement 1PMU Measurement =1Voltage + 3 Currents=1Voltage + 3 Currents

Power InjectionPower Injection

Power FlowPower Flow

----MeasurementMeasurement----

PMUPMU

Simulation Results for IEEE 30BusSimulation Results for IEEE 30Bus--System:System:

Simulation Results for IEEE 30BusSimulation Results for IEEE 30Bus--System:System:

Impact of PMUs onImpact of PMUs on Parameter Error IdentificationParameter Error Identification

When a network parameter is wrong:When a network parameter is wrong:

Can it be identified ? How ?Can it be identified ? How ?

Are there cases where errors in certain Are there cases where errors in certain parameters can not be identified without parameters can not be identified without synchronized phasor measurements ?synchronized phasor measurements ?

Current PracticeCurrent Practice

Augment the state vector with the Augment the state vector with the suspected set of parameterssuspected set of parameters

Simultaneously estimate the states and Simultaneously estimate the states and parameters parameters

pxxxv n |,...,, 21AUGMENTED STATE VECTOR

Multiple SolutionsMultiple Solutions

What happens when more than one set of What happens when more than one set of parameters satisfies all measurements?parameters satisfies all measurements?

Multiplicity of solutions for [p].Multiplicity of solutions for [p].

Illustration of Multiple SolutionsIllustration of Multiple Solutions

),,(),,( 2121 ppxJppxJ

k lkl

kl

Px

lm

mllm x

P

' 'kl k l

kl k l

xx

' 'lm l m

lm l m

xx

l mlm

lm

Px

kl

lkkl x

P

Identifying Parameter Errors Identifying Parameter Errors by Phasor Measurementsby Phasor Measurements

: Parameter Error: Parameter Error : PMU: PMU

TEST A:TEST A:NO PMUsNO PMUs

TEST B:TEST B:WITH PMUsWITH PMUs

Simulation ResultsSimulation ResultsTest A Test B

Meas /Par. RN / N Meas /Par. RN / N

XX10-11 27.5040 XX

1313--1414 29.0162

XX13-14 27.3629 XX

99--1414 26.0467

XX6-11 27.9763 XX

1010--1111 20.1385

XX9-14 24.4732 XX

66--1111 20.1349

XX9-10 20.2291 XX

99--1010 17.0387

Final RemarksFinal Remarks

SE performance have significant impact on SE performance have significant impact on all other application functions related to all other application functions related to smart grid operationsmart grid operation

PMUs can improve SE performance in the PMUs can improve SE performance in the following areas:following areas:

Bad data detectionBad data detection

Reduced variance of estimated stateReduced variance of estimated state

Merging observable islandsMerging observable islands

Identifying network parameter errorsIdentifying network parameter errors

To download the software:To download the software: http://http://www.ece.neu.edu/~abur/www.ece.neu.edu/~abur/

pet.htmlpet.html

For further information:For further information:http://www.ece.neu.edu/~abur


Recommended