Romfor International Ltd. CUT AND SLIP DRILLING LINE CUT AND SLIP DRILLING LINE CUT AND SLIP DRILLING LINE Backup Hand Backup Hand
Transcript

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

CU

T A

ND

SL

IP

DR

IL

LIN

G L

IN

E

Backup HandBackup Hand

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

Backup HandBackup Hand

Romfor International Ltd. Backup Hand

STEP SUB PROCEDURE REMARKS

BACKUP HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

1

PPE Requirements - Hardhat, Safety Glasses, Full

Face Shield, Work Gloves, Steel Toe Shoes, Back

Support and Fall Protection.

Review rig specific JSA’s on cutting and slipping

drilling line and hoisting personnel.

Inspect Equipment:

Anti-Fall equipment, block hanging line, bosun’s

chair, shackles ,block slings, line cutter and hand

tools used for the job.

READY TO HANG BLOCKS

(Assuming drill pipe is in rotary table)

Drill String should be positioned at bottom of last

casing string and well secured.

Ensure that well bore is static.

Assist in setting slips (with drill string at proper height).

After blocks are lowered, stand clear while elevators

are unlatched.

Assist as directed in inspecting drilling line, while

Driller is raising blocks.

After blocks are raised to proper position, assist in

using air / hydraulic hoist for installing safety valve.

Assist as directed in tightening drill pipe safety valve

to the proper make up torque (do not put tongs on

open / close area of drill pipe safety valve).

Stand clear while blocks are moved to the proper

position for installation of block hanging line.

Assist Derrickman, in attaching harness / bosun’s

chair to air / hydraulic hoist.

JSA’s should be rig specific.

Rig manager is required on the

floor when using bosun’s chair.

Use fall protection, 100% tie off

and avoid pinch points.

Operational issues may

change position of drill string.

Ensure that proper lifting

techniques are used.

Avoid pinch points and stay out

of Drillers view.

Keep hands clear while line is

spooling on drum.

Use full open lifting eye for

hoisting safety valve.

Avoid pinch points and ensure

floor is clear of trip hazards.

Ensure safety valve is in the

open position. Stay out of the

red zone (between rig tongs).

Ensure brake handle is locked

down after positioning blocks.

Attach directly to shackle.

1

2

0

1

2

3

4

5

6

7

8

9

STEP SUB PROCEDURE REMARKS

Backup Hand

BACKUP HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

2

Ensure tag line is attached to bosun’s chair.

While Derrickman is lifted, use tag line to position

Derrickman properly.

While Derrickman is lowered, use tag line to position

Derrickman properly.

Assist in removing air / hydraulic winch from harness

/ bosun’s chair and store for later use.

Assist with removal of guards from front of

drawworks.

Assist with removal of automatic driller / weight

indicator load cells off dead line.

Assist with removal of secondary safety clamp and

drilling line anchor clamp.

Assist in securing tag line to drilling line, use tag line

to pull initial drilling line from drum.

Assist in taping drilling line area being cut.

Assist in placing drilling line in line cutter properly.

Ensure drilling line is secured prior to cutting, to

avoid any recoil in line.

READY TO CUT DRILLING LINE

Assist in cutting drilling line, operate cutter from the

proper side (closed/pump side).

Assist in storing cutter properly.

Assist in pulling drilling line off drum and guide line

out V-door / beaver slide.

Ensure tag line is manned by

qualified person.

Ensure Derrickman’s feet and

hands are clear of catch points.

Ensure Derrickman’s feet and

hands are clear of catch points.

Avoid pinch points and store

guards in safe position.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Avoid pinch points.

Watch for burs / wickers.

Watch for burs / wickers, cover

line cutter.

Use proper PPE, Full-face

shield and avoid pinch points.

Avoid pinch points.

Watch for burs / wickers and

avoid pinch points. Do not let

drilling line slide through hands.

1

2

10

11

12

13

14

15

16

17

18

19

20

21

22

Romfor International Ltd. Backup Hand

STEP SUB PROCEDURE REMARKS

BACKUP HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

3

Assist in attaching air/hydraulic hoist to drilling line

when there is three wraps left on drum.

Assist in pulling remaining drilling line off drum with

air / hydraulic hoist.

Assist with proper removal of drilling line clamp and

inspect for wear.

Assist in removing the remainder of drilling line from

drum using air/hydraulic hoist.

Assist in lowering cut off drilling line down beaver-

slide / V–door and store properly for disposal.

Assist in Installation of drilling line in drum.

Stand clear while drum rotates forward to proper

position for installation of drilling line clamp.

Assist in installation of drilling line clamp.

Assist in attaching snatch block to fast line and raise

with air / hydraulic hoist to keep proper tension on

drilling line while spooling drilling line on drum.

Assist with removal of snatch block and air / hydrau-

lic hoist.

Ensure line is slipping through anchor properly.

Have adequate communications from rig floor to

drilling line stand / anchor area (use mechanical

assist to feed line off of drilling line spool).

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wicker’s and

avoid pinch points. Use proper

hand tools to remove clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Use tag line.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Use tag line.

Avoid pinch points and use

proper tools.

Ensure brake handle is locked

down. Watch for burs / wickers

and avoid pinch points. Use

proper hand tools to install

clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

1

2

23

24

25

26

27

28

29

30

31

32

STEP SUB PROCEDURE REMARKS

Backup Hand

BACKUP HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

4

33

34

35

36

37

38

39

40

41

42

Assist in installing drilling line anchor clamp and

secondary anchor safety clamp.

Stand clear while blocks are raised to proper height

for removal of block hanging line.

Assist Derrickman, in attaching harness / bosun’s

chair to air/hydraulic hoist.

Ensure tag line is attached to bosun’s chair.

While Derrickman is being lifted to proper position,

pay attention to hand signals and verbal direction

from the Derrickman.

Ensure block hanging line is disconnected from top

of the blocks and placed in stored position.

Assist in lowering Derrickman to proper position,

paying attention to hand signals and verbal direction.

Assist in removing air / hydraulic winch from harness

/ bosun’s chair and store properly.

Assist with removal of drill pipe safety valve. Lift drill

pipe safety valve with air / hydraulic hoist.

Assist Driller in checking crown-o-matic for proper

setting on first stand of tubulars.

END OF PROCEDURE

Inspect all clamping devices on

anchor (brass inserts, anchor

bolts and nuts) tighten to

proper torque in sequence (use

torque wrench). After initial trip

in re-torque anchor clamping

device.

Attach directly to shackle.

Ensure tag line is manned by

qualified personnel.

Ensure Derrickmans feet and

hands are clear of catch points.

Spool line on air / hydraulic

winch properly to prevent

fouling.

Use verbal communication.

Ensure Derrickman’s feet and

hands are clear of catch points.

Store under Rig Managers

control.

Avoid pinch points and ensure

floor is clear of trip hazards.

Ensure safety valve is in the

open position. Stay out of the

red zone (between rig tongs).

Use full open lifting eye for

hoisting safety valve.

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

CU

T A

ND

SL

IP

DR

IL

LIN

G L

IN

E

DerrickmanDerrickman

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

DerrickmanDerrickman

Romfor Internatinal Ltd. Derrickman

STEP SUB PROCEDURE REMARKS

DERRICKMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

. 1

PPE Requirements – Hardhat, Safety Glasses, Full

Face Shield, Work Gloves, Steel Toe Shoes, Back

Support and Fall Protection.

Review rig specific JSA’s on cutting and slipping

drilling line and hoisting personnel.

Inspect Equipment:

Anti-Fall equipment, block hanging line, bosun’s

chair, shackles ,block slings, line cutter and hand

tools used for the job.

READY TO HANG BLOCKS

(Assuming drill pipe is in rotary table)

Drill String should be positioned at bottom of last

casing string and well secured.

Assist Driller to ensure that well bore is static.

Assist as directed in inspecting drilling line, while

Driller is raising blocks.

Prepare to secure hanging line to top of blocks.

Locate proper tools for job.

Inspect and put on proper size lifting harness /

bosun’s chair.

Attach harness / bosun’s chair to air/hydraulic hoist.

Ensure tag line is attached to bosun’s chair.

Direct hoist operator to lift to proper position, use

hand signals and verbal direction.

Disconnect block hanging line from stored position.

JSA’s should be rig specific.

Rig manager is required on the

floor when using bosun’s chair.

Use fall protection, 100% tie off

and avoid pinch points.

Notify Rig Manager that

personnel will be lifted by air/

hydraulic hoist and that drill

line is ready to be cut.

Operational issues may

change position of drill string.

Keep hands clear while line is

spooling on drum.

Tools should be 100% tied off.

Use proper lifting device. Use

100% tie off (refer to JSA on

lifting personnel with air/

hydraulic hoist).

Attach directly to shackle.

Ensure tag line is manned by

qualified person.

Keep feet and hands clear of

catch points.

1

2

1

2

3

4

0

1

2

3

4

5

6

7

STEP SUB PROCEDURE REMARKS

Derrickman

DERRICKMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

2

Attach block-hanging line to top of blocks.

Direct hoist operator to lower to proper position, use

hand signals and verbal direction.

Remove harness / bosun’s chair and store for later

use.

Assist with proper removal of guards from front of

drawworks.

Assist with proper removal of automatic Driller/

weight indicator load cells off dead line.

Stand clear while blocks are lowered slowly (hang-

ing line takes full weight of blocks).

Use derrick climber assist to visually inspect the

blocks to ensure that blocks are hung properly.

Assist in securing tag line to drilling line, use tag line

to pull drilling line from drum.

Assist in taping drilling line area being cut.

Assist in placing drilling line in line cutter properly.

Assist in securing drilling line prior to cutting, to

avoid any recoil in line.

READY TO CUT DRILLING LINE

Assist in pulling drilling line off drum and guide line

out V-door/beaver slide.

Assist in attaching air/hydraulic hoist to drilling line

when there is three wraps left on drum.

Stand clear while remaining drilling line is pulled off

drum with air / hydraulic hoist.

Block hanging line should be

attached at the crown. Use

verbal communication. Do not

use stationary cable and

clamps on block hanging eye.

Keep feet and hands clear of

catch points.

Avoid pinch points and store

guards in safe position.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Ensure blocks slowly rest on

backside of derrick.

Ensure tie off line and shackle

is properly aligned and secure.

Use 100% tie off.

Avoid pinch points.

Watch for burs / wickers.

Watch for burs / wickers, cover

line cutter.

Watch for burs / wickers and

avoid pinch points. Do not let

drilling line slide through hands.

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers and

avoid pinch points.

1

2

1

2

1

2

8

9

10

11

12

13

14

15

16

17

18

Romfor International Ltd. Derrickman

STEP SUB PROCEDURE REMARKS

DERRICKMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

3

Inform Driller to stop drum when drilling line clamp is

accessible for removal.

Assist with proper removal of drilling line clamp and

inspect for wear.

Assist in pulling remainder of drilling line from drum

using air / hydraulic hoist.

Assist in slowly lowering cut off drilling line down

beaver-slide / V–door and store properly for disposal.

Assist in positioning drum for drilling line installation.

Assist in proper Installation of drilling line in drum.

Inform Driller to rotate drum forward to proper

position for installation of drilling line clamp.

Assist with proper installation of drilling line clamp.

Assist in keeping proper tension on drilling line while

drill line is spooled on drum (for tension attach

snatch block to fast line and raise with air/hydraulic

hoist until proper tension is on line).

Assist in proper removal of snatch block and air/

hydraulic hoist.

Inform Driller, when proper amount of drilling line is

on drum according to rig design.

Ensure brake handle is locked

down.

Watch for burs / wickers and

avoid pinch points. Use proper

hand tools to remove clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Use tag line.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Use tag line.

Ensure brake is locked down.

Watch for pinch points and

watch for burs / wickers.

Ensure brake handle is locked

down.

Watch for burs / wickers and

avoid pinch points. Use proper

hand tools to install clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Ensure

brake is locked down.

19

20

21

22

23

24

25

26

27

28

29

STEP SUB PROCEDURE REMARKS

Derrickman

DERRICKMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

4

30

31

32

33

34

35

36

37

38

39

Assist with proper installation of drawworks guards,

load cells, drilling line anchor clamp and secondary

anchor safety clamp.

Stand clear while blocks are raised to proper height

for removal of block hanging line.

Inspect and put on proper size lifting harness /

bosun’s chair.

Attach harness / bosun’s chair to air/hydraulic hoist.

Ensure tag line is attached to bosun’s chair.

Direct hoist operator to lift to proper position, use

hand signals and verbal direction.

Disconnect block hanging line from top of blocks.

Secure block-hanging line in proper position.

Direct hoist operator to lower to proper position, use

hand signals and verbal direction.

Remove harness / bosun’s chair and store properly.

Prepare to finish trip.

END OF PROCEDURE

Inspect all clamping devices on

anchor (brass inserts, anchor

bolts and nuts) tighten to

proper torque in sequence (use

torque wrench). After initial trip

in re-torque anchor clamping

device.

Use proper lifting device. Use

100% tie off (refer to JSA on

lifting personnel with air /

hydraulic hoist).

Attach directly to shackle.

Ensure tag line is manned by

qualified personnel.

Keep feet and hands clear of

catch points.

Keep feet and hands clear of

catch points.

Store under Rig Managers

control.

Review JSA on 100% tie off.

Verbally confirm 100% tied off

with Driller (use radio).

1

2

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

CU

T A

ND

SL

IP

DR

IL

LIN

G L

IN

E

DrillerDriller

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

DrillerDriller

Romfor International Ltd. Driller

DRILLER DRILLING LINE

CUT AND SLIP DRILLING LINE

STEP SUB PROCEDURE REMARKS

1

1

2

1

2

0

1

2

3

4

5

6

7

8

PPE Requirements - Hardhat, Safety Glasses, Full

Face Shield, Work Gloves, Steel Toe Shoes, Back

Support and Fall Protection.

Review rig specific JSA’s on cutting and slipping drilling

line and hoisting personnel. Notify Rig Manager that

bosun’s chair is needed for lifting employees.

Inspect Equipment:

Anti-Fall equipment, block hanging line, bosun’s

chair, shackles, block slings, line cutter and hand

tools used for the job.

READY TO HANG BLOCKS

(Assuming drill pipe is in rotary table)

Drill String should be positioned at bottom of last

casing string and well secured.

Ensure that well bore is static.

Ensure slips are set (with drill string at proper height).

Lower blocks for unlatching elevators.

Ensure that elevators are unlatched using proper

handles.

Raise blocks to proper position for installing safety

valve in drill pipe, using low drum clutch.

Install safety valve using air/hydraulic lifting hoist.

Ensure drill pipe safety valve is tightened to proper

make up torque.

Raise blocks slowly while inspecting drilling line on

drum for bad spots in the line.

JSA’s should be rig specific.

Rig manager is required on the

floor when using bosun’s chair.

Use fall protection, 100% tie off

and avoid pinch points.

Notify Rig Manager that

personnel will be lifted by air/

hydraulic hoist and that drill

line is ready to be cut.

Operational issues may

change position of drill string.

Ensure that proper lifting

techniques are used

Avoid pinch points.

Use full open lifting eye for

hoisting safety valve.

Avoid pinch points and ensure

floor is clear of trip hazards.

Ensure safety valve is in the

open position.

If line damage is found, slip

extra line (as required) before

cutting.

Driller

DRILLER DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

STEP SUB PROCEDURE REMARKS

2

Move blocks to proper position for installation of

block hanging line.

Ensure that Derrickman is raised to the top of the

blocks.

Ensure block-hanging line is properly attached to top

of blocks.

Ensure Derrickman is lowered to floor and is discon-

nected from hoist line.

Ensure proper removal of guards from front of

drawworks.

Ensure proper removal of automatic driller / weight

indicator load cells off dead line.

Unlock brake handle and lower blocks slowly until

hanging line takes full weight of blocks.

Instruct Derrickman to use derrick assist to visually

inspect blocks and ensure that blocks are hung

properly.

Visually inspect brake linkages and brake bands.

Ensure proper removal of secondary safety clamp

and drilling line anchor clamp.

Ensure tag line is secured to drilling line, use tag line

to pull initial drilling line from drum.

Slowly reverse proper amount of drilling line off the

drawworks drum according to ton mileage program.

Ensure brake handle is locked

down after positioning blocks.

Use proper lifting device. Use

100% tie off. (Refer to JSA on

lifting personnel with air/

hydraulic hoist).

Block hanging line should be

attached at the crown. Use

verbal communication with the

Derrickman. Do not use

stationary cable and clamps on

block hanging eye.

Avoid pinch points and store

guards in safe position.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Ensure blocks slowly rest on

backside of derrick.

Ensure 100% tie off.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Avoid pinch points.

Avoid pinch points. If using

drawworks to reverse drilling

line, ensure that drawworks is

in reverse before clutching.

1

2

1

2

1

2

3

4

1

2

9

10

11

12

13

14

Romfor International Ltd. Driller

DRILLER DRILLING LINE

CUT AND SLIP DRILLING LINE

STEP SUB PROCEDURE REMARKS

3

Tape drilling line area being cut.

Ensure drilling line is placed in line cutter properly.

Secure drilling line prior to cutting to avoid any recoil

in line.

READY TO CUT DRILLING LINE

Instruct motorman to cut drilling line, operating from

the proper side (closed/pump side) of the cutter.

Ensure line cutter is released and stored properly.

Reverse drilling line off drum and guide line out V-

door / beaver slide.

Ensure air/hydraulic hoist is attached to drilling line

when there is three wraps left on drum.

Using air/hydraulic hoist pull remaining drilling line

off drum.

Stop drum when drilling line clamp is accessible for

removal. Lock down brake handle.

Ensure proper removal of drilling line clamp and

inspect for wear.

Ensure that remainder of drilling line is pulled from

drum using air / hydraulic hoist.

Slowly lower cut off drilling line down beaver-slide /

V–door and store properly for disposal.

Unlock brake handle and position drum for drilling

line installation.

Ensure proper Installation of drilling line in drum.

Rotate drum forward to proper position for installa-

tion of drilling line clamp. Lock down brake handle.

Watch for burs / wicker’s.

Watch for burs / wicker’s.

Ensure proper PPE, Full-face

shield and avoid pinch points.

Cover line cutter.

Avoid pinch points.

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers and

avoid pinch points.

Ensure brake handle is locked

down.

Watch for burs / wickers and

avoid pinch points. Use proper

hand tools to remove clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watches for burs / wickers and

avoid pinch points. Use tag line.

1

2

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Driller

DRILLER DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

STEP SUB PROCEDURE REMARKS

4

1

2

3

29

30

31

32

33

34

35

36

Ensure proper installation of drilling line clamp.

Unlock brake handle. Ensure proper tension is kept on

drilling line while spooling drilling line on drum (for

tension attach snatch block to fast line and raise with

air/hydraulic hoist until proper tension is on line).

Ensure proper removal of snatch block and air/

hydraulic hoist.

Spool proper amount of drilling line on drum accord-

ing to rig design (use mechanical assist to feed line

off of drilling line spool). Drilling line spool should be

equipped with brake.

Lock brake handle and ensure proper installation of

drawworks guards, load cells, drilling line anchor

clamp and secondary anchor safety clamp.

Unlock brake handle and raise blocks to proper

height for removal of block hanging line.

Lock brake handle down. Raise Derrickman to top of

blocks.

Ensure block-hanging line is properly removed and

secured to derrick.

Ensure Derrickman is lowered to floor and is discon-

nected from hoist line.

Unlock brake handle and raise blocks to proper

position for removal of drill pipe safety valve.

Ensure drawworks is shut

down completely. Watch for

burs / wickers and avoid pinch

points. Use proper hand tools

to install clamp.

Watch for overhead loads.

Watches for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watches for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watches for burs / wickers and

avoid pinch points.

Inspect all clamping devices on

anchor (brass inserts Anchor

bolts and nuts) tighten to

proper torque in sequence (use

torque wrench). After initial trip

in re-torque anchor clamping

device.

Use proper lifting device. Use

100% tie off (refer to JSA on

lifting personnel with air /

hydraulic hoist).

Watch for overhead loads.

Watches for burs / wickers and

avoid pinch points.

Ensure weight indicator is

working properly.

Romfor International Ltd. Driller

DRILLER DRILLING LINE

CUT AND SLIP DRILLING LINE

STEP SUB PROCEDURE REMARKS

5

37

38

39

Ensure proper removal of drill pipe safety valve.

Ensure Derrickman is 100% tied off before raising

blocks, to run first stand of tubulars.

Check crown-o-matic for proper setting on first stand

of tubulars.

END OF PROCEDURE

Watch pinch points. Use full

opening lifting eye and air /

hydraulic hoist (store in proper

position).

Verbally confirm (with radio)

that Derrickman is 100% tied

off.

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

CU

T A

ND

SL

IP

DR

IL

LIN

G L

IN

E

Lead TongLead Tong

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

Lead Tong

Hand

Lead Tong

Hand

Romfor International Ltd. Lead Tong Hand

STEP SUB PROCEDURE REMARKS

LEAD TONG HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

1

PPE Requirements - Hardhat, Safety Glasses, Full

Face Shield, Work Gloves, Steel Toe Shoes, Back

Support and Fall Protection.

Review rig specific JSA’s on cutting and slipping

drilling line and hoisting personnel.

Inspect Equipment:

Anti-Fall equipment, block hanging line, bosun’s

chair, shackles ,block slings, line cutter and hand

tools used for the job.

READY TO HANG BLOCKS

(Assuming drill pipe is in rotary table)

Drill String should be positioned at bottom of last

casing string and well secured.

Ensure that well bore is static.

Assist in setting slips (with drill string at proper

height).

After blocks are lowered, stand clear while elevators

are unlatched.

Assist as directed in inspecting drilling line, while

Driller is raising blocks.

After blocks are raised to proper position, assist in

using air / hydraulic hoist for installing safety valve.

Assist as directed in tightening drill pipe safety valve

to the proper make up torque.

Stand clear while blocks are moved to the proper

position for installation of block hanging line.

Assist Derrickman, in attaching harness / bosun’s

chair to air/hydraulic hoist.

JSA’s should be rig specific.

Rig manager is required on the

floor when using bosun’s chair.

Use fall protection, 100% tie off

and avoid pinch points.

Operational issues may

change position of drill string.

Ensure that proper lifting

techniques are used.

Avoid pinch points and stay out

of Drillers view.

Keep hands clear while line is

spooling on drum.

Use full open lifting eye for

hoisting safety valve.

Avoid pinch points and ensure

floor is clear of trip hazards.

Ensure safety valve is in the

open position. Stay out of the

red zone (between rig tongs).

Ensure brake handle is locked

down after positioning blocks.

Attach directly to shackle.

1

2

0

1

2

3

4

5

6

7

8

9

STEP SUB PROCEDURE REMARKS

Lead Tong Hand

LEAD TONG HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

2

Ensure tag line is attached to bosun’s chair.

While Derrickman is lifted, use tag line to position

Derrickman properly.

While Derrickman is lowered, use tag line to position

Derrickman properly.

Assist in removing air / hydraulic winch from harness

/ bosun’s chair and store for later use.

Assist with removal of guards from front of

drawworks.

Assist with removal of automatic driller / weight

indicator load cells off dead line.

Assist with removal of secondary safety clamp and

drilling line anchor clamp.

Assist in securing tag line to drilling line, use tag line

to pull initial drilling line from drum.

Assist in taping drilling line area being cut.

Assist in placing drilling line in line cutter properly.

Ensure drilling line is secured prior to cutting, to

avoid any recoil in line.

READY TO CUT DRILLING LINE

Assist in cutting drilling line, operate cutter from the

proper side (closed/pump side).

Assist in storing cutter properly.

Assist in pulling drilling line off drum and guide line

out V-door / beaver slide.

Ensure tag line is manned by

qualified person.

Ensure Derrickman’s feet and

hands are clear of catch points.

Ensure Derrickman’s feet and

hands are clear of catch points.

Avoid pinch points and store

guards in safe position.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Avoid pinch points.

Watch for burs / wickers.

Watch for burs / wickers, cover

line cutter.

Use proper PPE, Full-face

shield and avoid pinch points.

Avoid pinch points.

Watch for burs / wickers and

avoid pinch points. Do not let

drilling line slide through hands.

1

2

10

11

12

13

14

15

16

17

18

19

20

21

22

Romfor International Ltd. Lead Tong Hand

STEP SUB PROCEDURE REMARKS

LEAD TONG HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

3

Assist in attaching air/hydraulic hoist to drilling line

when there is three wraps left on drum.

Assist in pulling remaining drilling line off drum with

air / hydraulic hoist.

Assist with proper removal of drilling line clamp and

inspect for wear.

Assist in removing the remainder of drilling line from

drum using air/hydraulic hoist.

Assist in lowering cut off drilling line down beaver-

slide / V–door and store properly for disposal.

Assist in Installation of drilling line in drum.

Stand clear while drum rotates forward to proper

position for installation of drilling line clamp.

Assist in installation of drilling line clamp.

Assist in attaching snatch block to fast line and raise

with air / hydraulic hoist to keep proper tension on

drilling line while spooling drilling line on drum.

Assist with removal of snatch block and air / hydraulic

hoist.

Ensure line is slipping through anchor properly.

Have adequate communications from rig floor to

drilling line stand / anchor area (use mechanical

assist to feed line off of drilling line spool).

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers and

avoid pinch points. Use proper

hand tools to remove clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Use tag line.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Use tag line.

Avoid pinch points and use

proper tools.

Ensure brake handle is locked

down. Watch for burs / wickers

and avoid pinch points. Use

proper hand tools to install

clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

1

2

23

24

25

26

27

28

29

30

31

32

STEP SUB PROCEDURE REMARKS

Lead Tong Hand

LEAD TONG HAND DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor

4

33

34

35

36

37

38

39

40

41

42

Assist in installing drilling line anchor clamp and

secondary anchor safety clamp.

Stand clear while blocks are raised to proper height

for removal of block hanging line.

Assist Derrickman, in attaching harness / bosun’s

chair to air/hydraulic hoist.

Ensure tag line is attached to bosun’s chair.

While Derrickman is being lifted to proper position,

pay attention to hand signals and verbal direction

from the Derrickman.

Ensure block hanging line is disconnected from top

of the blocks and placed in stored position.

Assist in lowering Derrickman to proper position,

paying attention to hand signals and verbal direction.

Assist in removing air / hydraulic winch from harness

/ bosun’s chair and store properly.

Assist with removal of drill pipe safety valve (do not

put tongs on open / close area of drill pipe safety

valve). Lift drill pipe safety valve with air / hydraulic

hoist.

Assist Driller in checking crown-o-matic for proper

setting on first stand of tubulars.

END OF PROCEDURE

Inspect all clamping devices on

anchor (brass inserts, anchor

bolts and nuts) tighten to

proper torque in sequence (use

torque wrench). After initial trip

in re-torque anchor clamping

device.

Attach directly to shackle.

Ensure tag line is manned by

qualified personnel.

Ensure Derrickmans feet and

hands are clear of catch points.

Spool line on air / hydraulic

winch properly to prevent

fouling.

Use verbal communication.

Ensure Derrickman’s feet and

hands are clear of catch points.

Store under Rig Managers

control.

Avoid pinch points and ensure

floor is clear of trip hazards.

Ensure safety valve is in the

open position. Stay out of the

red zone (between rig tongs).

Use full open lifting eye for

hoisting safety valve.

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

CU

T A

ND

SL

IP

DR

IL

LIN

G L

IN

E

MotormanMotorman

Romfor International Ltd.

CUT AND SLIP

DRILLING LINE

CUT AND SLIP

DRILLING LINE

MotormanMotorman

Romfor International Ltd. Motorman

STEP SUB PROCEDURE REMARKS

MOTORMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

PPE Requirements - Hardhat, Safety Glasses, Full

Face Shield, Work Gloves, Steel Toe Shoes, Back

Support and Fall Protection.

Review rig specific JSA’s on cutting and slipping

drilling line and hoisting personnel.

Inspect Equipment:

Anti-Fall equipment, block hanging line, bosun’s

chair, shackles ,block slings, line cutter and hand

tools used for the job.

READY TO HANG BLOCKS

(Assuming drill pipe is in rotary table)

Drill String should be positioned at bottom of last

casing string and well secured.

Ensure that well bore is static.

Assist in setting slips (with drill string at proper

height).

After blocks are lowered, unlatch elevators using

proper handles.

After blocks are raised to proper position, use air /

hydraulic hoist for installing safety valve.

Assist as directed in tightening drill pipe safety valve

to the proper make up torque.

Assist as directed in inspecting drilling line, while

Driller is raising blocks.

Assist Derrickman, in attaching harness / bosun’s

chair to air/hydraulic hoist.

Ensure tag line is attached to bosun’s chair.

JSA’s should be rig specific.

Rig manager is required on the

floor when using bosun’s chair.

Use fall protection, 100% tie off

and avoid pinch points.

Operational issues may

change position of drill string.

Ensure that proper lifting

techniques are used.

Avoid pinch points.

Use full open lifting eye for

hoisting safety valve.

Avoid pinch points and ensure

floor is clear of trip hazards.

Ensure safety valve is in the

open position. Stay out of the

red zone (between rig tongs).

Keep hands clear while line is

spooling on drum.

Attach directly to shackle.

Ensure tag line is manned by

qualified person.

1

2

0

1

2

3

4

5

6

7

8

9

STEP SUB PROCEDURE REMARKS

Motorman

MOTORMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

2

Operate hoist to lift Derrickman to proper position,

pay attention to hand signals and verbal direction

from the Derrickman.

Ensure block hanging line is disconnected from

stored position.

Ensure block-hanging line is attached to top of the

blocks.

Lower Derrickman to proper position, pay attention

to hand signals and verbal direction.

Assist in removing air / hydraulic winch from harness

/ bosun’s chair and store for later use.

Assist with removal of guards from front of

drawworks.

Assist Driller in visually inspecting brake linkages

and brake bands.

Assist with removal of automatic driller / weight

indicator load cells off dead line.

Assist with removal of secondary safety clamp and

drilling line anchor clamp.

Assist in securing tag line to drilling line, use tag line

to pull initial drilling line from drum.

Tape drilling line area being cut.

Assist in placing drilling line in line cutter properly.

Ensure drilling line is secured prior to cutting, to

avoid any recoil in line.

Ensure Derrickmans feet and

hands are clear of catch points.

Spool line on air / hydraulic

winch properly to prevent

fouling.

Block hanging line should be

attached at the crown. Use

verbal communication. Do not

use stationary cable and

clamps on block hanging eye.

Ensure Derrickman’s feet and

hands are clear of catch points.

Avoid pinch points and store

guards in safe position.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Avoid pinch points; ensure

100% tie off. Use proper hand

tools.

Avoid pinch points.

Watch for burs / wickers.

Watch for burs / wickers, cover

line cutter.

1

2

3

10

11

12

13

14

15

16

17

18

19

20

Romfmor International Ltd. Motorman

STEP SUB PROCEDURE REMARKS

MOTORMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

3

READY TO CUT DRILLING LINE

Cut drilling line, operating from the proper side

(closed/pump side) of the cutter.

Release line cutter and store properly.

Assist in pulling drilling line off drum and guide line

out V-door / beaver slide.

Assist in attaching air/hydraulic hoist to drilling line

when there is three wraps left on drum.

Operate air / hydraulic hoist to pull remaining drilling

line off drum.

Assist with proper removal of drilling line clamp and

inspect for wear.

Remove the remainder of drilling line from drum

using air/hydraulic hoist.

Slowly lower cut off drilling line down beaver-slide /

V–door and store properly for disposal.

Assist in Installation of drilling line in drum.

Stand clear while drum rotates forward to proper

position for installation of drilling line clamp.

Assist in installation of drilling line clamp.

Attach snatch block to fast line and raise with air /

hydraulic hoist to keep proper tension on drilling line

while spooling drilling line on drum.

Use proper PPE, Full-face

shield and avoid pinch points.

Avoid pinch points.

Watch for burs / wickers avoid

pinch points. Do not let drilling

line slide through hands.

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers avoid

pinch points.

Watch for burs / wickers and

avoid pinch points. Use proper

hand tools to remove clamp.

Watch for overhead loads.

Watch for burs / wicker’s and

avoid pinch points. Use tag line.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points. Use tag line.

Avoid pinch points and use

proper tools.

Ensure brake handle is locked

down. Watch for burs / wickers

and avoid pinch points. Use

proper hand tools to install

clamp.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

1

2

21

22

23

24

25

26

27

28

29

30

31

STEP SUB PROCEDURE REMARKS

Motorman

MOTORMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

Romfor International Ltd.

4

32

33

34

35

36

37

38

39

40

41

42

Assist with removal of snatch block and air / hydraulic

hoist.

Have enough excess drill line available for slipping

onto drum according to JSA and rig design.

Ensure line is slipping through anchor properly.

Have adequate communications from rig floor to

drilling line stand / anchor area (use mechanical

assist to feed line off of drilling line spool).

Install drilling line anchor clamp and secondary

anchor safety clamp.

Stand clear while blocks are raised to proper height

for removal of block hanging line.

Assist Derrickman, in attaching harness / bosun’s

chair to air/hydraulic hoist.

Ensure tag line is attached to back “D” ring of

harness / bosun’s chair.

Operate hoist to lift Derrickman to proper position,

pay attention to hand signals and verbal direction

from the Derrickman.

Ensure block hanging line is disconnected from top

of the blocks and placed in stored position.

Lower Derrickman to proper position, pay attention

to hand signals and verbal direction.

Assist in removing air / hydraulic winch from harness

/ bosun’s chair and store properly.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Watch for burs / wickers and

avoid pinch points.

Watch for overhead loads.

Watch for burs / wickers and

avoid pinch points.

Inspect all clamping devices on

anchor (brass inserts, anchor

bolts and nuts) tighten to

proper torque in sequence (use

torque wrench). After initial trip

in re-torque anchor clamping

device.

Attach directly to shackle.

Ensure tag line is manned by

qualified personnel.

Ensure Derrickmans feet and

hands are clear of catch points.

Spool line on air / hydraulic

winch properly to prevent

fouling.

Use verbal communication. Do

not use stationary cable and

clamps on block hanging eye.

Ensure Derrickman’s feet and

hands are clear of catch points.

Store under Rig Managers

control.

Romfor International Ltd. Motorman

STEP SUB PROCEDURE REMARKS

MOTORMAN DRILLING LINE

CUT AND SLIP DRILLING LINE

5

43

44

Assist with removal of drill pipe safety valve. Lift drill

pipe safety valve with air / hydraulic hoist.

Assist Driller in checking crown-o-matic for proper

setting on first stand of tubulars.

END OF PROCEDURE

Avoid pinch points and ensure

floor is clear of trip hazards.

Ensure safety valve is in the

open position. Stay out of the

red zone (between rig tongs).

Use full open lifting eye for

hoisting safety valve.


Recommended