PROJECT TITLE
SUB TITLE
Rooley Moor Wind Farm
Chapter 13: Socio-Economic Assessment
CPL
Rooley Moor Wind Farm Environmental Statement
Contents
13. Socio-economic Assessment ................................................................................................................................................................... 13-1
13.1 Introduction ................................................................................................................................................................................................ 13-1
13.2 Relevant Legislation and Policy ................................................................................................................................................................. 13-1
13.3 Study Area ................................................................................................................................................................................................. 13-1
13.4 Methodology .............................................................................................................................................................................................. 13-2
13.5 Socio-economic baseline ........................................................................................................................................................................... 13-5
13.6 Predicted Economic Impacts ................................................................................................................................................................... 13-11
13.7 Predicted Socio-economic Impacts .......................................................................................................................................................... 13-14
13.8 Wider Impacts .......................................................................................................................................................................................... 13-21
13.9 Mitigation .................................................................................................................................................................................................. 13-22
13.10 Cumulative Impacts ............................................................................................................................................................................... 13-24
13.11 Offsetting, Enhancement and Monitoring ............................................................................................................................................... 13-24
13.12 Conclusion and Statement of Significant Impacts .................................................................................................................................. 13-25
13.13 References ............................................................................................................................................................................................. 13-26
CPL PAGE 13-1
Rooley Moor Wind Farm Environmental Statement
13 Socio-Economic Assessment
13.1 Introduction
13.1. This chapter provides an assessment of the potential social and economic impacts, both beneficial
and adverse associated with the construction, operation and decommissioning phases of the
Development. In particular, it assesses impacts on local communities and the economy due to the
construction and operation of the Development.
13.2. The economic impacts cover issues in terms of businesses, direct and indirect employment and
direct and indirect spending that may arise as a consequence of the Development. Community
impacts refer to the consequences of the Development on human populations, relating to how
people live, work, play, relate to one another, organise to meet their needs and generally operate
as members of society. In this assessment these are assessed with regards to recreational
amenities, tourism and availability of local services.
13.3. The Proposed Development will also offer a range of wider socio-economic benefits associated
with the provision of renewable energy as set out within section 5.1 of Chapter 5: Planning Policy
Context.
13.2 Relevant Legislation and Policy
13.4. This section builds on Chapter 5: Planning Policy Context by reviewing local and national policy
relating to socio-economic development. There is no legislation of direct relevance to this
assessment.
13.3 Study Area
13.3.1 Location of the Development
13.5. The Development is located near Whitworth, within the administrative boundaries of Rochdale
Borough Council in the Greater Manchester area and Rossendale Borough Council in Lancashire,
approximately 25km north of Manchester. The Development includes 12 turbines and will generate
a total of 39.6MW.
13.3.2 Catchment Area
13.6. A catchment area of the Development has been identified for the socio-economic baseline
analysis. This area corresponds to a 10km catchment from the centre of the Development site and
it approximately represents the local economy that will be affected by the Development. A 10km
catchment has been chosen as it contains the town of Rochdale without including the North of
Manchester. This is presented in Figure 13.1.
CPL PAGE 13-2
Rooley Moor Wind Farm Environmental Statement
Figure 13.1 Catchment area for socio-economic baseline
13.4 Methodology
13.4.1 Introduction
13.7. The methodology of this assessment is based on a desk based analysis, comprising the collection
and review of a wide range of data and information from published material as well as through
consultation with key stakeholders. In order to predict the likely impact of a development, it is
important to have a clear understanding of the socio-economic conditions of the area. This can be
used as a baseline against which the significance of predicted changes can be assessed. In
addition, social impacts of similar developments have been reviewed in order to give a good
indication of the likely effect of the Development.
13.8. The assessment has been based on experience from other projects, analysis of the baseline
situation and analysis of consultation outcomes.
13.9. Following a review of the baseline socio-economics of the site, the following social and economic
indicators have been considered within this assessment:
Employment - the assessment will examine the level of construction activity and job creation and
the potential linkages with the wider local economy. This will include an assessment of potential
multiplier effects within the local economy.
Economic Activity - the degree to which local businesses could benefit from involvement with the
proposal’s development, use and eventual decommissioning will be examined. Business revenue
will be created as a result of the construction and operation of the Development including contracts
awarded to local business through the supply chain and spending by temporary and permanent
employees in the area.
CPL PAGE 13-3
Rooley Moor Wind Farm Environmental Statement
Community - potential community effects will also be considered with respect to availability of local
services.
Tourism and Recreation - potential for impacts on the tourism industry and also on areas of
recreation (including Public Rights of Way (PRoW)) during construction, operation and
decommissioning. Potential tourism and recreation impacts arising during the construction and
operation phases relate to:
o disruption to the normal use of resources within the site or on the proposed access routes
(addressed separately here for tourism / recreation amenities and access / rights of way);
o a reduction in the enjoyment gained from using these tourism and recreation resources
potentially resulting in a reluctance by individuals to visit the feature arising from, for
example, a negative perception of construction activities as a feature in the landscape or
from construction noise and traffic; and/or
o a reluctance by individuals to visit the feature or area arising from an adverse perception of
the wind turbines as a feature in the landscape.
13.10. As there is currently no established best practice EIA methodology for the assessment of socio-
economic impacts, professional judgement has been used when assessing the impacts of the
Development. The general principles of the most relevant guidance “Guidelines and Principles for
Social Impact Assessment” (Ref. 13-1)) have, however, been followed in this assessment, although
this has been tailored specifically for the assessment of impacts from wind farm development in the
context of the Borough of Rochdale. Reference has also been made to attitude surveys as the
best available indicators of the public’s perception of wind farms.
13.4.2 Consultation
13.11. This assessment has taken due regard to the Scoping Report and the formal Scoping Opinion.
The consultees highlighted a number of concerns with regards to socio-economic assessment as
summarised below, alongside the Applicant’s response to these concerns:
Table 13.1 Consultee Responses
Consultee Comment CPL Response
Approach lacks detail on positive and negative impacts
The positive and negative socio economic impacts are presented in this chapter.
Construction phase impacts should be included Construction phase impacts have been considered as part of the socio economic assessment.
Local economic Impact Report should be produced using LM3 analysis to explore spend.
This has been provided as part of the Socio economic assessment.
Specific approach to tendering for skills and materials should be provided
Information on this approach is not known at this stage of the development and therefore detail has not been provided.
ES should consider training and skill development opportunities. This should extend into schools activity and links with Post 16 training and local Training Compacts
Information on this approach is not known at this stage of the development and therefore detail has not been provided
Explore potential for promoting the site as a destination in its own right for recreational and educational users.
The opportunity for increased access to recreational users has been considered in Chapter 14: Land Use and within this chapter.
Wider opportunities to encourage tourism, recreation, understanding of cultural heritage and natural environment should be assessed, including impacts on tourism in Rossendale and Rochdale. Could include development of a visitor centre at the
Impacts on tourism in Rochdale and Rossendale have been considered in this chapter. The development of a tourist centre and wider opportunities to encourage tourism, recreation, understanding of cultural heritage and natural environment is not appropriate at this stage in the
CPL PAGE 13-4
Rooley Moor Wind Farm Environmental Statement
Consultee Comment CPL Response
Adrenaline Gateway. development and has not been included.
Chapter to be cross referenced to other chapters that deal with land management and access
This chapter cross references Chapter 14: Land Use and Chapter 12: Access, Traffic and Transport as appropriate.
Section on the Community Fund should be explicit including amount payable per MW, area eligible and rationale, how community needs will be identified, interface with other potential sources of funding and management of the fund.
Details of the Community Fund cannot be provided at this stage in the development.
Community Benefits should be addressed as a separate chapter.
Details of the Community Fund cannot be provided at this stage in the development.
Potential for negative impacts on farmers from restrictions on grazing should be cross referenced to benefits in land management chapter
The impact on grazing is considered in Chapter 14: Land Use.
Practical arrangements for grazing regimes and diversification should be explored
The impact on grazing is considered in Chapter 14: Land Use.
Include measures as to how the developer will work with the land ownership and management interests beyond the site to secure long term, sustainable and integrated land management, focusing on benefits to all users and pressures from anti-social or unauthorised vehicular use
The impacts on land use are considered in Chapter 14: Land Use.
Assessment should focus on impacts on the local economy and not solely rely on regional scale analysis
This chapter assesses impacts on the local economy.
13.4.3 Significance Criteria
13.12. The magnitude of a socio-economic effect can be difficult to define and while this is preferably
defined in quantitative terms (e.g. additional workforce); this is not always possible and a qualitative
assessment based on professional judgement is needed and used. As all socio-economic
receptors (e.g. households, workforce and tourists) are considered here to have the same level of
sensitivity, the identification of effect significance is based solely on the magnitude of the effect.
The terms major, moderate, minor and negligible have been adopted to describe effect significance
as described in Table 13.2. This is used as a guide for evaluating the significance of a change that
results from the Development. Effects can be either neutral (no change), beneficial or adverse.
However it should be noted that for the purposes of the impact assessment, a worse-case scenario
is always presented. For example, the introduction of turbines into a landscape will be considered
an adverse effect, when in reality only a proportion of the receptors will consider this to be the
case, with other being completely neutral to their introduction and others still considering them to
be a positive addition to the landscape and their enjoyment of it.
13.13. In addition, the assessment considers the temporal nature of the effect. Here the effect is
considered to be either temporary, which is defined as lasting for up to one year’s duration or
permanent, which is defined as lasting for the duration of the operational period.
CPL PAGE 13-5
Rooley Moor Wind Farm Environmental Statement
Table 13.2 Significance of Effects
Significance of impact (beneficial or adverse)
Criteria/Definition Description
Major
Results in major
change, causing a
major socio-economic
loss or gain in the
study area
A project is considered to have a
substantial change on e.g. local
resources, businesses, employment
and the local and visiting population
affecting more than 100 people or
leading to a substantial change in
employment opportunities. Project
activities affect a large number of
people in the study area.
Moderate
Results in a moderate
change, causing a
partial socio-economic
loss or gain in the
study area
A project is considered to have a
moderate change on e.g. local
resources, businesses, employment
and the local and visiting population
(e.g. affects less than 100 people or
leads to a moderate change in
employment opportunities). Project
activities affect a moderate number of
people in the study area.
Minor
Results in a small
change causing a
minor socio-economic
effect
A project is considered to have a small
change on e.g. local resources,
businesses, employment, and the local
and visiting population (e.g. affects
less than 20 people or leads to a few
changes in employment opportunities).
Project activities affect a small number
of people in the study area.
Negligible
Results in no change
causing a negligible
socio-economic effect
A project would have no discernible
effect e.g. local resources, businesses,
employment, and the local and visiting
population (e.g. affects less than 10
people; and / or effects would be
temporary (i.e. experienced for less
than one year).
13.14. Impacts that are major or moderate in magnitude are considered to be significant under the terms
of the EIA Regulations.
13.5 Socio-economic Baseline
13.15. The Lower Super Output Areas (LSOAs) that fall within the 10km radius from the approximate
centre of the Development have been identified. LSOAs are the lowest statistical geographical
level and therefore provide the highest level of accuracy when aggregating data in a small
catchment area. There is a total of 194 LSOAs in the defined catchment area.
13.16. Several socio-economic characteristics have been taken into consideration in the socio-economic
baseline. These include: population, age structure, economic activity indicators, sectoral split,
level of qualifications of the population and Gross Value Added (GVA). These have been
obtained from Census 2011 data (Ref. 13-2) and the Office of National Statistics (ONS) (Ref. 13-
3). The results are presented below.
CPL PAGE 13-6
Rooley Moor Wind Farm Environmental Statement
13.5.1 Population
13.17. There are approximately 310,000 people in the catchment area, with the majority of the
population located in Rochdale. Since 2001, the area has experienced a 5.8% increase in
population according to both Census 2001 (Ref. 13-4) and 2011 data, slightly below the overall
7.1% growth in population in England and Wales.
13.5.2 Age structure
13.18. The age structure of the population within the catchment area is very similar to the average age
structure in England and the North West, with a slightly lower proportion of residents over the age
of 60, approximately 2% less than England and Wales, and a slightly higher proportion of
residents under the age of 24 (+1.5%). This indicates that the population in the area is slightly
younger compared to the average for England and Wales.
13.5.3 Economic activity
13.19. In terms of economic activity, the catchment area scores slightly worse than the whole of England
and Wales and the North West. Table 13.3 shows that unemployment is higher in the catchment
area while the rate of economically active population is also slightly lower.
Table 13.3 Economic activity indicators
Economic activity indicators
(Census 2011)
Eco
nom
ical
ly A
ctiv
e;
Em
ploy
ee; P
art-
Tim
e
Eco
nom
ical
ly A
ctiv
e;
Em
ploy
ee; F
ull-T
ime
Eco
nom
ical
ly A
ctiv
e; S
elf-
Em
ploy
ed
Eco
nom
ical
ly A
ctiv
e;
Une
mpl
oyed
Eco
nom
ical
ly A
ctiv
e; F
ull-
Tim
e S
tude
nt
Eco
nom
ical
ly In
activ
e; R
etire
d
Eco
nom
ical
ly In
activ
e;
Stu
dent
(In
clud
ing
Ful
l-Tim
e
Stu
dent
s)
Eco
nom
ical
ly In
activ
e;
Look
ing
Afte
r H
ome
or F
amily
Eco
nom
ical
ly In
activ
e; L
ong-
Ter
m S
ick
or D
isab
led
Catchment area 13.5% 37.3% 8.8% 5.2% 2.7% 13.9% 5.0% 4.8% 6.1%
England and Wales 13.7% 38.5% 9.7% 4.4% 3.4% 13.8% 5.8% 4.3% 4.2%
North West 13.9% 37.5% 8.2% 4.7% 3.5% 14.8% 5.6% 3.9% 5.6%
13.5.4 Sectoral Split
13.20. The top five employment sectors for the catchment area correspond to wholesale and retail trade;
repair of motor vehicles and motor cycles (18%), human health and social work activities (15%),
manufacturing (12%), education (10%) and public administration (6%). These sectors employ a
slightly higher proportion of the residents in employment in the catchment area than on average in
England and Wales as well as the North West. Sectors such as professional, scientific and
technical activities (5%) and financial and insurance activities (3%) employ a slightly lower
proportion of the population in employment in the catchment area compared to England and Wales.
13.5.5 Level of Qualifications
13.21. The level of qualifications in the catchment area compared to the national average is presented in
Figure 13.2. This shows that the average level of qualification in the study area is to some extent
lower in comparison with England and Wales. The largest differences are found in the proportion of
residents with no qualifications, which is 3.5% larger in the catchment area, as well as in the
CPL PAGE 13-7
Rooley Moor Wind Farm Environmental Statement
proportion of residents with Level 4 qualification (university degree), which is 4.7% lower in the
catchment area.
Figure 13.2 Level of Qualifications – Residents aged 16 and over (Census 2011)
13.5.6 Local Gross Value Added
13.22. Statistics for local GVA show once again that the study area scores slightly worse than England in
terms of its socio-economic characteristics. While GVA per head for England is £21,349 (2011 at
current basic prices), GVA per head in the North West is £17,754 and £16,472 in Lancashire
County Council, where the borough of Rossendale is located.
13.5.7 Tourism and Recreation in the Catchment Area
13.23. In assessing the tourist, visitor and recreational facilities within the tourism study area, it is those
which appear most frequently within tourist or visitor websites, brochures, guidebooks, and other
media that are taken to represent the principal tourism resources in the area. This is a standard
approach taken as a proxy for tourists or other visitors assessing the potential attraction of an area.
13.24. According to the Rossendale Tourism Study published in 2010 (Ref. 13-5), current attractions and
events in the catchment area are heavily influenced by the Borough’s industrial heritage and
natural assets. The same applies to the Borough of Rochdale, in the south of the catchment area.
Heritage attractions include a number of museums and heritage centres, such as Helmshore Mills
Textile Museum. The East Lancashire Railway attracts the largest number of visitors (circa 105,000
per annum). In the See Gallery and Bamboo Theatre there are cultural venues of national and
international renown.
13.25. Tourist attractions near Whitworth, one of the closest towns to the Development, are mainly related
to natural assets and outdoor sports. Important attractions include Cowm Reservoir, Whitworth
Water Ski Centre, Lee Quarry Mountain Bike Trail, Pennine Bridleway and Healey Dell Nature
Reserve. Cowm Reservoir regularly hosts competitions for water sports, while the Pennine
Bridleway is a popular route amongst horse riders. Healy Dell Natural Reserve, located at the
southern end of Whitworth, on the Whitworth - Rochdale border, has a wide range of flora and
fauna, its own Fairy Chapel and a rich industrial past.
13.26. Rossendale has more public footpaths within its boundary than any other borough in the country.
The 47 mile long Rossendale Way crosses over the summit of Brown Wardle Hill. Mountain bike
magazines class the South Pennines as having some of the best riding in the country.
26.1%
14.1%
16.4%
3.7%
12.1%
22.5%
5.1%
22.7%
13.3%
15.3%
3.6%
12.3%
27.2%
5.7%
0%
5%
10%
15%
20%
25%
30%
No Qualifications Highest Level ofQualification;
Level 1Qualifications
Highest Level ofQualification;
Level 2Qualifications
Highest Level ofQualification;
Apprenticeship
Highest Level ofQualification;
Level 3Qualifications
Highest Level ofQualification;
Level 4Qualifications
and Above
Highest Level ofQualification;
OtherQualifications
Catchmentarea
Englandand Wales
CPL PAGE 13-8
Rooley Moor Wind Farm Environmental Statement
13.27. Brown Wardle is also popular with hang gliders and paragliders and the Pennine Bridleway
(including the 42 mile long Mary Townley Loop) attracts many horse riders.
13.28. Table 13.4 describes the criteria used in assessing the sensitivity of tourism and recreational
facilities to the Development.
Table 13.4 Sensitivity of Resource
Sensitivity of Receptor Description
High
Where the receptor or resource (visitors to activities, resources, attractions or
businesses) is defined as being of International or National status and
generates high visitor numbers.
Medium Where the receptor or resource is defined as being of regional status and
generates medium visitor numbers.
Low Where the receptor or resource is defined as being of local status and
generates low visitor numbers.
13.29. The receptors falling within the 10km catchment area are shown in Figure 13.1. Table 13.5
describes each of the facilities and its sensitivity to impact from the Development.
Table 13.5 Tourism and recreational facilities and their sensitivity to wind farm development
Site Description Sensitivity
Helmshore Mills Textile
Museum
Open afternoons April to September. The museum
demonstrates nationally important textile machinery in
the mill, and tells the stories of wool, cotton and the
Industrial Revolution.
Low.
East Lancashire Railway
Runs every weekend throughout the year and every
Wednesday, Thursday and Friday April to September.
Features a restored railway with running steam
locomotives including vintage vehicles from the early
1900s. Carries more than 100,000 passengers per year
on the 12 mile route from Heywood to Rawenstall.
Medium.
Horse + Bamboo Theatre
Performing arts and theatre centre located at The Boo,
and with many shows touring locally and
regionally. Shows use masks, puppets, music and
story-telling, as well as film and animation.
Low.
Cowm Reservoir
The Whitworth Waterski Centre is located at Cown
reservoir and offers water activities and accommodation
7 days a week from April to October and week-ends
through the off season.
The 1.5 mile surfaced path round the reservoir is also
popular with locals. Facilities include picnic area, toilets,
car parking and a sculpture trail.
Medium.
Cown Leisure
150 Acre disused stone quarry featuring natural terrain
for Trials Bikes, Road Legal 4 x 4's, Pit Bikes, Enduro
Bikes, Remote Controlled Cars and Cyclo Trials Bikes.
Opening Hours: 9:30am - Dusk every weekend and
Bank Holiday.
Low.
CPL PAGE 13-9
Rooley Moor Wind Farm Environmental Statement
Site Description Sensitivity
Lee Quarry Mountain
Bike Trail
Over 8km of technical mountain bike trails in Lee
Quarry, Bacup. The trail is open all year round.
Low.
Pennine Bridleway
The Pennine Bridleway is a 330km National Trail
running through the Pennine hills from Derbyshire to
Cumbria. It has been specially designed for horse
riders, and is also great for mountain bikers and
walkers.
The Trail includes 2 large loops. The first is the Mary
Towneley Loop in the South Pennines; this is 47 miles
long and makes a great weekend’s walk or ride. The
2nd Loop is the 10 mile Settle Loop in the Yorkshire
Dales. This makes an excellent days walk or horse ride
and can be extended by using the bridleway network to
take in the village of Malham too.
High.
Healey Dell Nature
Reserve
A disused 1800s railway line is now a nature trail with
magnificent views from a 100-foot high viaduct.
The visitor centre and tea room is open Friday to
Sunday and all Bank Holidays and has a permanent
exhibition on the industrial heritage of the reserve and
details of guided walks and trails. The disused railway line
through the centre of Healey Dell is part of the National
Cycle Network, Regional Network Route 92 which joins
National Route 66.
Healey Dell is on the Rochdale Way and the Pennine
Bridleway passes the northern end.
Low.
Healey Dell and Syke
Angling
Healey Dell Fishery is a water of approximately 1 acre
and is owned by the Rochdale Walton Angling
Society. Syke’s main water is approximately 1 acre and
also has a small pond. The Society has approximately
150 members and day ticket anglers are welcome.
Low.
Trows Lane Angling Rochdale and District Angling Society has 6 waters at
Trow’s Lane strictly for use by Society members.
Low.
Rossendale Way
66km circular walk passing through Haslingden,
Whitworth, Stubbins and Healey. The walk also goes
through Healey Dell Nature Reserve.
Medium.
Brown Wardle Paragliding training courses running Tuesday to
Sunday from the training base at Brown Wardle Hill.
Low.
Greenbooth and Naden
Reservoirs Circular walk round edge of reservoirs.
Low.
Springmill Reservoir Low.
CPL PAGE 13-10
Rooley Moor Wind Farm Environmental Statement
Site Description Sensitivity
Watergrove Reservoir
Open all day every day. The first route 'The Watergrove
Trail', around the reservoir follows the perimeter of the
reservoir and goes past the sailing club. The second
route 'Hades Trail', going up to the ruins of Higher Slack
Brook Farm. The Long Causeway, an old packhorse
route to Ramsden branches off at the northerly point of
this route. Site facilities include toilets, picnic area and
free car parking.
The West Pennine Sailboard Club is a windsurfing club
based at Watergrove reservoir providing facilities for
members and non-members throughout the year.
Low.
Cowpe Reservoir
Cowpe Reservoir is a 16.5 acre trout water offering fly
fishing to club members and the general public through
day tickets. There is also a circular walk around the
escarpment above Cowpe Reservoir.
Low.
Hollingsworth Lake
The Water Activity Centre on Lake Bank provides
instruction in windsurfing, dinghy sailing and other
water-based sports, and arranges training for groups in
mountain biking and climbing. The Lake is also a base
for a sailing club and a rowing club. The wider Country
Park has plenty of walking routes, from easy strolls
around the lake shore to sturdier treks in the
surrounding hills. The Country Park is open every day
of the year and the Visitor Centre on Saturday, Sunday,
and Monday during the winter. The lake is well served
by a selection of cafes, pubs, and restaurants, as well
as B&Bs and a caravan and camping site for overnight
stays.
Medium.
Tandle Hill Country Park
Consists of approximately 110 acres, a combination of
beech woodland and open grassland. The park
contains a countryside centre, picnic areas, children's
play area and numerous trails and paths into the
surrounding area.
Low.
Mandale Park Features recently renovated BMX track and playground. Low.
Springfield Park
The Borough's largest park with landscaped and
wooded slopes down to the Roch Valley. Attractions
include the lake, children's play area and, on summer
weekends, a miniature steam railway. Sports include
football, cricket, tennis and athletics track, a permanent
orienteering course and an 18 hole golf course
(Marland Golf Course).
Low.
Broadfield Park
Venue for various outdoor events, the park has been
extensively refurbished and contains a Victorian-style
bandtstand, bowling greens, and a play area for
children.
Low.
Falinge Park
Park with children's play area, facilities, a brand new
Victorian style bandstand, conservatories plus formal
'Sun Gardens' and bowling greens.
Low.
CPL PAGE 13-11
Rooley Moor Wind Farm Environmental Statement
Site Description Sensitivity
Jubilee Park Park with elegant bandstand and scented rose beds.
Band concerts are performed during the summer.
Low.
Lobden Golf Club 9 hole moorland course open to non-members.
Low.
Rochdale Golf Club 18 hole golf course and clubhouse offering golf and
venue facilities to members and non-members.
Low.
Marland Golf Course Public 18 hole parkland course located in Springfield
Park. Also home to Springfield Golf Club.
Low.
Bacup Golf Club 9 hole course open to non-members. Low.
Rossendale Golf Club 18 hole golf course and clubhouse open to non-
members for golf and venue hire.
Low.
Walmersley Golf Club 18 hole moorland golf course open to non-members. Low.
Lowes Park Golf Club 9 hole moorland course open to non-members. Low.
SkiRossendale Dry ski slope offering ski and snowboard lessons and
tubing Tuesday to Sunday.
Low.
13.30. In terms of the economic contribution of tourism to the local economy in Rossendale, tourism
employs 7.1% of the workforce, similar to the regional average of 7.2% (Rossendale Tourism Study
2010 (Ref. 13-5)). The area lacks a strong accommodation offer which is reflected in the average
visitor spend, which is lower than the average for the region.
13.31. The borough of Rochdale has good access to the South Pennines and Manchester city centre,
attractive countryside and a rich heritage. Currently the borough attracts mainly day visitors, with
the greatest percentage visiting the Hollingworth Lake area. The current visitor economy in the
borough includes both facilities and attractions within the urban area and outside the urban area in
more rural locations such as Hollingworth Lake and the South Pennines Moors (Ref. 13-6),
Rochdale Core Strategy).
13.32. Visitors to Rochdale have grown from 6 million per year in 2003 to 8 million per year in 2008 and by
2009 had received 11% more visitors than in 2005. Tourism expenditure increased between 2005
and 2007, fell slightly in 2008, but by 2009 was 11% higher than the 2005 baseline. In 2008 tourism
expenditure in the borough of Rochdale totalled £376 million. The growth of tourism between 2005
and 2009 was accompanied by a 6.5% rise in tourism supported employment in Rochdale Borough
(Ref. 13-7).
13.33. The borough of Rossendale attracted 2.17 million visitors in 2008, generating a total of 2.34 million
visitor days. There is an underlying trend of a small annual incremental rise in the length of the
average stay – due especially to growth in the non-serviced accommodation sector.
13.6 Predicted Economic Impacts
13.6.1 Introduction
13.34. The lifecycle of a wind farm involves four main stages: development, construction, operation and
maintenance and decommissioning. The present economic impact assessment focuses on the
construction and operation phases, which will approximately last for one year and 25 years
respectively. During these phases, employment and GVA will be generated directly at the site,
which will in turn create opportunities for local businesses to provide services to the people
CPL PAGE 13-12
Rooley Moor Wind Farm Environmental Statement
employed in the wind farm and to those providing those services. The methodology to measure the
total economic activity that will originate from the wind farm is outlined below.
13.6.2 Methodology
13.35. The process of estimating total employment and GVA arising from the construction and operation
of Rooley Moor wind farm is undertaken in two steps:
Estimation of direct and indirect employment and GVA
Estimation of induced employment and GVA
Reference to actual case studies of wind farms built in the local area
13.36. Direct impacts refer to employment and GVA directly generated from the construction or operation
of the wind farm, which only includes people working at the wind farm directly. Supply chain or
indirect impacts consist of expenditures generated down the supply chain as a result of the
expenditure of the income that is directly generated by the development. This typically includes
expenditures in suppliers.
13.37. Direct and supply chain impacts have been calculated using benchmarking data from a report
published by Renewable UK in 2012 called “Onshore Wind, Direct and Wider Economic Impacts”
(Ref. 13-8). The data in the report has been analysed to obtain the average number of jobs per
MW and the average GVA per MW at different geographical levels that is obtained directly from
wind farms in the UK. The results of the analysis are presented in Table 13.6.
Table 13.6 Benchmarking data - Direct and supply chain impacts in 2011 across the UK
Benchmarking data
from Renewable UK
Construction Operation
GVA per MW (£
million) Jobs per MW
GVA per MW (£
million) Jobs per MW
Local 0.02 0.25 0.01 0.07
Regional 0.06 1.10 0.01 0.17
National 0.1 1.69 0.02 0.24
13.38. Direct and indirect impacts do not include however a third type of economic impacts called induced
impacts. Induced impacts refer to employment and GVA arising from the re-expenditure of income
generated as a result of direct and indirect impacts. Induced impacts are calculated here using
Type II and Type I multipliers from the Scottish government statistics agency, who have undertaken
extensive and reliable research on the economic impact of different industries. Type I multipliers
are factors used to convert direct into direct and indirect economic impacts, while Type II multipliers
also include induced impacts. The difference between the two factors has been used to convert the
direct and supply chain impacts obtained from benchmarking data into total impacts including
induced economic impacts. These are shown in Table 13.7.
CPL PAGE 13-13
Rooley Moor Wind Farm Environmental Statement
Table 13.7 Multipliers to obtain total economic impacts from direct and indirect impacts
Multipliers – induced impacts1 GVA Employment
Construction - specialised 1.3 1.3
Electricity production and distribution 1.3 2.2
13.6.3 Results
13.39. Total employment and GVA generated directly from the construction and operation of the wind farm
is shown in Table 13.8. This has been estimated based on benchmarking data by MW presented in
Table 13.6 and applying it to 39.6MW, the expected generating capacity of the wind farm. For the
construction phase, results are given as a total instead of on a per year basis.
Table 13.8 Direct and supply chain impacts
Direct Impacts – Rooley Moor
Wind Farm
Construction (total) Operation (per year)
GVA (£ million) Jobs GVA (£ million) Jobs
Local 0.61 10 0.31 3
Regional 2.56 43 0.50 7
National 3.93 67 0.78 10
13.40. The results are shown in Table 13.9. These results include direct, indirect and induced impacts and
show that the employment and income generated by Rooley Moor Wind farm could be 6 jobs and
around £0.4 million per year at a local level during its operation phase. Even though the numbers
may seem small, they are significant in the context of a low densely populated area. During the
short phase of construction, the estimated number of jobs and GVA generated could be more than
twice the annual employment and GVA generated in the operation phase.
Table 13.9 Direct, indirect and induced economic impacts
Direct, indirect and induced
economic impacts
Construction Operation
GVA (£ million) Jobs GVA (£ million) Jobs
Local 0.8 13 0.41 6
Regional 3.4 56 0.66 15
National 5.3 86 1.04 21
13.41. The economic impacts estimated are approximations and are based on a conservative one size
fits all approach. They should therefore be used with caution. The size and geographical
1 These multipliers have been obtained by subtracting Type II minus Type I multipliers (2009) obtained from the Scottish
government and adding 1. This factor is then multiplied by the direct and indirect impacts to obtain total economic
impacts.
CPL PAGE 13-14
Rooley Moor Wind Farm Environmental Statement
distribution of the impacts could vary depending on multiple factors such as the possibility to
obtain supplies locally or the disposable income of employees. However, the comparison of these
estimations with other case studies reveals that both the direct and the total employment and
GVA calculated are reasonable compared to the economic impacts calculated for other wind
farms.
13.6.4 Case Studies
13.42. It is therefore much better to refer to actual case studies of contract work undertaken on wind
farms in the local vicinity of the Development
Table 13.10: Case studies and projection for the Development
Name of Wind farm Number of
Turbines
Percentage of
contract kept in
local Area
Value of contract
kept in local Area
(£)
Hameldon Hill (West Yorkshire and
Lancashire)
3 44% 1,690,000
Hampole (Lincolnshire and
Yorkshire)
4 68% 963,000
Todmorden (West Yorkshire and
Lancashire)
5 52% 1,535,000
Crook Hill (West Yorkshire and
Lancashire)(Projected)
11 55% 3,100,000
Proposed Rooley Moor 12 55% 3,440,000
All figures provided by the contract who worked is working on these projects except the Rooley
Moor figures. The Rooley Moor figures are based on predictions using the case studies as a
baseline.
13.43. Thus it can be seen that actual case studies demonstrate that the figure of spend for that is kept in
the local area for construction is far higher than the general statistics imply and demonstrate what
can be achieved if developers work with their contractors to ensure high levels of local spend. It is
therefore considered that the figures for the Development as set out in Table 13.10 are accurate
for construction.
13.44. There is no statistics for jobs on the case studies currently due to the logistical exercise of
determining exactly where each employee lived. However, discussions with the contractor who
supplied these statistics indicated that at least 30% of the work force was employed locally. Figures
for operation will have to rely on the figures at Table 13.10 as it has not been possible to obtain
data for case studies.
13.7 Predicted Socio-economic Impacts
13.45. Further socio-economic impacts are evaluated in a qualitative manner in this section. In particular,
the following categories have been considered: employment opportunities, economic activity,
availability of services and quality of life.
13.46. The methodology described in section 13.4 has been followed. This methodology tries to establish
the direction and magnitude of the potential socio-economic impacts of the Development during the
construction and operation phases. As there is currently no established best practice EIA
methodology for the assessment of socio-economic impacts, professional judgement has been
used when assessing the impacts for the Development.
13.47. In relation to tourism and recreational facilities, those identified to be of medium or high sensitivity
to wind farm development have been further assessed. The proximity of the facility to the
CPL PAGE 13-15
Rooley Moor Wind Farm Environmental Statement
Development Area and the visibility of the Development from the facility have been considered,
therefore establishing which require further assessment.
13.7.1 Potential Impacts – Construction Phase
Employment
13.48. Various construction activities will take place onsite, including civil engineering, turbine installation,
electrical and commissioning studies. A detailed construction workforce schedule i.e. employee
numbers throughout the construction programme and likely shift patterns would not be known until
the contract for building the wind farm has been granted, however the temporary workforce is
anticipated to be around 70 people (based on project experience of a similar nature), with
approximately 30% of these construction jobs being sourced locally (see paragraph 13.44 above).
The potential direct and indirect employment associated with construction of the Development is
provided in Table 13.9. In accordance with the socio-economic assessment criteria outlined in
Table 13.2, this is considered to be a beneficial but minor impact when compared to employment
rates in the Rochdale and Rossendale area.
Economic Activity
13.49. The construction of the wind farm will lead to significant new investment into the Rochdale and
Rossendale area, and the wider economy. Published information on installed costs for UK wind
farms can be found in a report prepared on behalf of the RenewableUK and Department of Energy
and Climate Change (Onshore Wind Direct & Wider Economic Impacts, BiGGAR 2012 (Ref. 13-9)
(the BiGGAR report).
13.50. The nature of wind farm projects means that engineering / technical components of the build are
unlikely to be delivered from the local area or region; however, construction, engineering and
technical contractors can be sourced locally. Expenditure in the local economy therefore varies
from project to project as a function of various factors, including project size, duration and
availability of local suppliers. The applicant estimates for Rooley Moor Wind Farm a local spend of
approximately £3.44 million in the local area during construction. The types of local businesses
that might benefit from this could include fencing contractors, local civil engineering contractors,
timber and aggregate suppliers, hoteliers, caterers and haulage companies.
13.51. The additional profits generated in businesses as a result of the project plus the additional salaries
that are paid to the employees of these businesses can be expressed in project terms as the Gross
Value Added (GVA). GVA has been calculated using data from the BiGGAR report, which shows
the average GVA per employee in wind farms in the UK for the construction phase is £57,981.
This is considerably higher than the GVA per resident head in Lancashire i.e. £16,472 (see
paragraph 13.22).
13.52. Based on the socio-economic assessment criteria in Table 13.2, the overall impact on the local and
wider economy is expected to be moderate, beneficial and therefore significant but only
temporarily.
Availability of Local Services
13.53. During construction it is not considered that the numbers of personnel required will place any strain
on local services (GPs, schools etc). There is good room availability within the Lancashire region
at a variety of levels of quality which should be sufficient to suit requirements. At this time it is not
known what the principal contractor’s accommodation requirements will be2, however, it is
assumed that this will not impact on availability for tourists.
2 Websites such as http://www.bedsforbuilders.co.uk have been established to ensure contractors are able to find the
required level of accommodation.
CPL PAGE 13-16
Rooley Moor Wind Farm Environmental Statement
13.54. The impact of the Development on the demand for local services and therefore the availability of
these for existing users is expected to be negligible.
Tourism and Recreation
13.55. Potential tourism and recreation impacts arising during the construction phase relate to:
disruption to the normal use of resources within the site or on the proposed access routes
(addressed separately here for tourism / recreation amenities and access / rights of way); and also
a reduction in the enjoyment gained from using these tourism and recreation resources potentially
resulting in a reluctance by individuals to visit the feature arising from, for example, a negative
perception of construction activities as a feature in the landscape or from construction noise and
traffic.
Section x above identified the following resources as potentially impacted by the construction of the
Development.
Pennine Bridleway
13.56. The Pennine Bridleway is a 330km National Trail running through the Pennine hills from Derbyshire
to Cumbria. It has been specially designed for horse riders, and is also great for mountain bikers
and walkers.
13.57. The Trail includes 2 large loops. The Mary Towneley Loop in the South Pennines crosses the
Development Area, entering the Development Area at Knack’s Lane and following the Rooley Moor
Road to the Top of Leach where it leaves the Development Area headed west. Tracks associated
with the Development cross the Bridleway at four points along the route and Bridleway itself
provides the construction access from the Bottom of Rooley Moor to approximately Top of Pike.
Whilst effects are temporary without mitigation this would be a major and adverse effect and
therefore a significant impact.
Rossendale Way
13.58. The Rossendale Way is a 66km circular walk passing through Haslingden, Whitworth, Stubbins
and Healey. The walk also goes through Healey Dell Nature Reserve and shares a portion of its
route across the Development Area with the Pennine Bridleway as shown on Figure 13.1. Tracks
associated with the Development cross the Rossendale Way at four points along the route. The
construction of these tracks would disrupt the normal use of this route. Without mitigation this
would be a major and adverse effect and therefore a significant impact.
13.7.2 Potential Impacts - Operational Phase
Employment
13.59. Wind farms typically result in only a few opportunities for long-term employment, as projects of the
size of the Development are largely unmanned. One to two part time maintenance engineers will
be required, as will a small number of staff to occasionally service the wind turbines. It is, however,
likely that major maintenance events will occur from time to time when additional staff and
contractors will be required for short periods only. It is anticipated that this would equate to one
FTE job.
13.60. Again there is the potential for indirect and induced employment to occur due to the Development,
as shown in Table 13.9. Based on the socio-economic assessment criteria outlined in Table 13.2,
this is considered to be a permanent, beneficial, negligible, impact. The main economic benefits to
the local community through the lifetime of the project are not through long-term employment, but
instead through the introduction of community funds (see paragraph 13.82).
CPL PAGE 13-17
Rooley Moor Wind Farm Environmental Statement
Economic Activity
13.61. There are various sources of information which give details of the impact and boost to the local
economy from operational wind farms. The most recent research is available in the BiGGAR report
(Ref. 13-9). Onshore wind brings substantial new economic benefits and job opportunities to the
country as a whole and at a local level. The BiGGAR economics report shows that in 2011 onshore
wind was worth £548 million to the UK economy. Whilst this project is small in the context of these
numbers, it will nonetheless contribute to investment and opportunities for the local supply chain,
albeit, as highlighted, at low levels. Supplies of maintenance products, such as oil and paint, will be
needed during the operation of the Project. During maintenance work, it is likely that plant hire will
be required and it is expected that this will be sourced locally.
13.62. Expenditure in the local community continues throughout the operational phase of the project. The
GVA for the operational phase is shown in Table 13.9.
13.63. The Development is also expected to provide an annual payment in business rates based on
requirements for non-domestic properties. This payment will be made to RMBC and RBC which in
turn could have an indirect benefit on ability of RMBC and RBC to provide services to the local
community. That said, this will be minor, beneficial and permanent impact but is not expected to
have a significant impact on the area
13.64. Based on the socio-economic assessment criteria in Table 13.2, the impact on the wider supply
chain is expected to be permanent, beneficial and minor.
Availability of Local Services
13.65. The limited number of personnel on site during operation means there is not expected to be any
noticeable change in the demand for local services. It is therefore anticipated that there will be no
impacts on the on the availability of these for existing users.
Tourism and Recreation
13.66. A number of public surveys focused on the public perceptions of wind farms as well as studies
researching the impact of wind farms on tourism have been undertaken in the UK since wind farms
were first developed in the early 1990s. A study by BWEA (now RenewableUK) (Ref. 13-10) into
public attitudes found that there were over 60 separate public surveys conducted over a 15 year
period. The study concluded that, on average, there was a 70-80% level of support for wind farm
development, both in principle and also in practice among residents living near to developed wind
farms.
13.7.3 Literature Review
13.67. A review of recent relevant studies on public perception of wind farms and the impacts of wind
farms on tourism is presented in Table 13.11. A common conclusion of the surveys undertaken is
that once wind farms are built and operational, the predicted adverse effects that people
considered may occur either did not materialise or the wind farm was not necessarily considered to
be unacceptable to the majority of the public.
Table 13.11 Literature review - public perceptions and tourism impacts of wind farms
Study Key Findings
Research by Ipsos MORI (2012)
(Ref. 13-11)
66% of the 1009 16 to 64 year olds surveyed in favour of wind power
with the majority of individuals (59%) seeing the use of wind power as
a good way to reduce carbon emissions and to reduce dependence
of the UK on energy sources from overseas
CPL PAGE 13-18
Rooley Moor Wind Farm Environmental Statement
Study Key Findings
‘Wind Power in the UK’ (2005),
Sustainable Development
Commission (Ref. 13-12)
Wind farm benefits are shared by the whole of the UK, but the
communities that are local to the development are most directly
benefited;
Public attitudes to wind farms are generally beneficial and are
evolving as more are constructed and as the realisation of the need
for renewable energy sources increases; and
Local community involvement at all stages in the development is key
to the success of a wind farm.
Survey by YouGov on behalf of
Scottish Renewables (2010)
(Ref. 13-13)
77% (41%-strongly agree, 36% agree) agree that ‘wind farms are
necessary so that we can produce renewable energy to help us meet
current and future energy needs in Scotland’.
Only 23% agree or strongly agree that ‘wind farms are, or would be,
ugly and a blot on the landscape’, compared with 52% disagree or
strongly disagree with it.
59% agree or strongly agree that ‘wind farms are necessary so that
we can produce renewable energy, what they look like is
unimportant’, compared with 23% who disagree or strongly disagree.
The Economic Impacts of Wind
Farms on Scottish Tourism,
Glasgow Caledonian University,
Moffat Centre, and Cogentsi,
(2008) (Ref. 13-14)
Three-quarters of tourists felt wind farms had a beneficial or neutral
impact on the landscape. Overseas visitors seem to be more
accepting about wind farms than domestic tourists.
Importantly, respondents that had seen a wind farm were less hostile
than those who had not. The vast majority (93-99%) of tourists that
had seen a wind farm in the local area suggested that the experience
would not have any effect on their decision to return to that area, or to
Scotland as a whole.
Research by the University of
the West of England in North
Devon (2004) (Ref. 13-15)
The study demonstrated that the overwhelming majority of tourists
would be unaffected by such developments and indeed that such
developments were regarded by a narrow majority of respondents as
having a positive effect.
13.68. As summarised in the literature review, according to research studies on the public perceptions of
wind farms, there is generally a positive opinion of wind farms overall in the UK, both in terms of
residents and tourists. For this reason and due to the distance of most identified tourism and
recreation amenities, which are the tourism spots attracting the largest number of visitors, it is likely
that the Development will have overall a negligible impact on tourism in the catchment area.
13.69. With respect to the Development, impacts on the use of the tourism and recreational facilities may
be linked to landscape and visual impact (Chapter 6: Landscape and Visual Impact
Assessmnet), noise (Chapter 10: Noise) and traffic and transport (Chapter 12: Access, Traffic
and Transport). A summary of the risk of impacts on the enjoyment of tourism and recreation
amenities as a result of the Development’s operation with respect to these is as follows:
The operational noise assessment has demonstrated that the ETSU-R-97 criterion limits (including
daytime amenity) can be satisfied at all properties across all wind speeds. The operational noise
levels are acceptable in terms of the guidance recommended by planning policy for the
assessment of wind farm noise and therefore are considered not significant in EIA terms. Being at
a greater distance than the residential properties considered, and based on the socio-economic
impact assessment criteria in Table 13.2, it is considered that there would be no impact in terms of
noise on the identified tourism and recreation facilities described in Table 13.4;
Vehicle movements during the operational phase are expected to be minimal (see Chapter 12:
Access, Transport and Traffic). No impact is therefore anticipated with respect to tourism and
recreation amenities due to operational traffic impacts being insignificant.
CPL PAGE 13-19
Rooley Moor Wind Farm Environmental Statement
A review of the Zone of Theoretical Visibility mapping indicates that there will be visibility of the
wind farm at the following medium and high sensitivity visitor locations:
o East Lancashire Railway
o Pennine Bridleway and Rossendale Way
o Cowm Reservoir
o Hollingsworth Lake
There will also be some visibility for recreational viewers using footpaths on and in the vicinity of
the site. These views are likely to be transitory and will be experienced as people move through
the landscape. In socio economic terms, although the wind turbines may be seen, on the basis of
the survey evidence presented above it is reasonable to conclude that there will be no significant
adverse impact on the use and enjoyment of amenities, and thereby no resulting reluctance by
individuals to visit the feature or area. As a result the socio-economic impact is considered to be
negligible.
13.70. Impacts on the tourism in the area are therefore predicted to be negligible.
13.71. The routes of the right of way in relation to the proposed turbine locations were considered during
the optimisation of the site layout, with the turbines being located so as not to oversail these routes,
in accordance with available guidance (Ref.13-16). No impact on the use of these is therefore
anticipated due to health and safety issues arising from proximity to the turbines.
13.72. Two turbines (T5 and T6) are slightly within the British Horse Society’s (BHS) recommended
buffers of a minimum of 200m of the Pennine Bridleway (Ref. 13-17) (although it must be noted
that these hold limited weight as planning criteria). The separations distances to these turbines at
174m and 186m respectively, are well in excess of the 50m oversail and The Highways Agency
setback from the highway boundary recommendation of height plus 50 metres for commercial
turbines. BHS guidance acknowledges the 200m separation “may not be appropriate in all
situations. Every site should be considered independently because there are likely to be many
interdependent factors involved.”
13.73. The proposed access track will use the Pennine Bridleway from the Bottom of Rooley Moor to
approximately the Top of Pike and cross footpaths and bridleways in six locations but will not
obstruct its use. During operation of the Development, no major disruption to the footpath is
expected, as, on a day to day basis, minimal maintenance and thereby associated vehicles is
anticipated (see Chapter 4: Development Description). Major maintenance is likely to occur only
occasionally. Any temporary disruption due to vehicles accessing turbines at such times will be
over a much shorter period (days rather than weeks) than during construction. There is however a
potential for minor health and safety impacts at these times and mitigation is proposed in Section
13.9.
13.74. While the wind turbines may be visible when using the PROW onsite and in the area, the impact of
this on an individual’s enjoyment of and continued use of Rooley Moor for leisure activities is very
much personal and subjective. Again, although the wind turbines may be seen, on the basis of the
survey evidence presented above it is reasonable to conclude that there will be no significant
adverse impact on the enjoyment of the PRoW.
13.75. A summary of the results are presented in Table 13.12 and Table 13.13. The tables show the
expected potential impact as well as whether there is a need for socio-economic mitigation.
Overall, the assessment shows that there is a need for mitigation measures and additionally there
is an opportunity to maximise the positive impacts of the Development by using local resources
where possible.
13.76. Table 13.12 presents the potential impacts for the construction phase.
CPL PAGE 13-20
Rooley Moor Wind Farm Environmental Statement
Table 13.12 Social Impacts - Construction Phase
Aspect/activity Potential impact Assessment of
potential impact
Need for socio –
economic mitigation
Employment
Direct and indirect
temporary employment
Increased
employment with the
potential for indirect
jobs associated with
services to those
employed during the
construction period
(e.g. service
industry)
Temporary,
beneficial, minor
No – beneficial impact,
however, opportunity to
maximise by commitment
to use local resources
where practicable
Economic Activity
Economic Investment
Expenditure in the
local area, regionally
and nationally with
associated GVA.
Temporary,
beneficial, moderate
No – beneficial impact,
however, opportunity to
maximise by commitment
to use local resources
where practicable
Availability of Services
Influx of workers Strain on local
services
Temporary, neutral,
negligible
No – however commitment
to use local resources
where practicable
Tourism and Recreation
Footpaths, bridleways and
bike tracks
Disruption to access
due to health and
safety during
construction activities
Temporary, adverse,
major Yes
13.77. Table 13.13 presents the potential impacts for the operation phase.
Table 13.13 Social Impacts - Operation phase
Aspect/activity Potential impact Assessment of
potential impact Need for mitigation
Employment
Direct and indirect permanent
employment
Creation of
employment
opportunities
Permanent,
beneficial, minor
No – beneficial impact,
however, opportunity to
maximise by commitment to
use local resources where
practicable
Economic Activity
Economic Investment
Applicant and
employee spend in
the local area,
regionally and
nationally,
associated GVA and
also business rates
Permanent,
beneficial, minor
No – beneficial impact,
however, opportunity to
maximise by commitment to
use local resources where
practicable where
practicable
CPL PAGE 13-21
Rooley Moor Wind Farm Environmental Statement
Aspect/activity Potential impact Assessment of
potential impact Need for mitigation
Availability of Local Services
Influx of workers Strain on local
services No impact
No – however commitment
to use local resources where
practicable
Tourism and Recreation
Footpaths, bridleways and
bike tracks Changes to routes
Permanent,
adverse, major Yes
Tourist and visitor attractions Negative perception
of wind farms
Permanent,
adverse, minor No
13.8 Wider Impacts
13.78. Apart from employment and GVA impacts, wider socio-economic impacts may be realised as a
result of the Development. These could be for instance an increase in local skills through local
employment or the promotion of new local businesses. This can be especially relevant in the
context of an area that lags behind the regional average in terms of its socio-economic
performance.
13.79. The economic impacts estimated in section 13.6 can be actively maximised if the wind farm
developer is committed to:
Encourage local employment and provides training for local employees
Encourages local sourcing of goods
Works with the local community and schools to increase awareness on renewable energy
13.80. All these actions will not only increase the employment and GVA estimated but will also ensure that
there is a positive impact on the community in the long term.
13.8.1 Community Fund
13.81. In the UK, wind farm developers usually create a community fund associated to the wind farm in
order to benefit the local community. This is not included in any regulation regarding wind farms
and it is an entirely voluntary decision. The developers of Rooley Moor Wind Farm are currently
exploring a number of Community Benefit options, such as a fund to provide financial support to
local groups/projects, energy efficiency schemes and environmental educational programmes.
They are liaising with local groups in order to determine the best alternative for providing such fund.
13.82. Community funds can be managed by different agents or organisations, such as a local trust, local
community projects or the local council, amongst other options. Its size is generally based on an
agreed amount per MW, although it may take the form of a lump sum. These funds can be used for
a variety of purposes including:
Investment3 in business support and skills linked to the wind farm supply chain
3 Investments could be done both as a donation and as a loan scheme.
CPL PAGE 13-22
Rooley Moor Wind Farm Environmental Statement
Investment in local leisure facilities
Investment in the local road network
Support businesses in investing in green technologies and energy efficiency improvement
strategies
Investment in encouraging tourism
13.83. As a result, this fund will bring additional benefits to the region that should be taken into account in
conjunction with the benefits presented in section 5.
13.9 Mitigation
13.84. Table 13.11 and Table 13.12 indicate that no significant adverse socio-economic impacts are
anticipated for the construction, operation and decommissioning phases of the Development save
in relation to the health and safety of the public when using PROW during the construction and
decommissioning phases where mitigation measures are required. This section outlines these
mitigation measures and also the measures proposed to offset the remaining adverse potential
impacts.
13.9.1 Construction
13.85. The mitigation required for the construction phase with respect to the use of onsite PROW has
been developed to protect the health and safety of recreational users while keeping any disruption
to PROW to the minimum.
13.86. The main Pennine Bridleway will be segregated from users and construction traffic. Users will also
be able to use alternative bridleways that take them away from the main Pennine Bridleway for the
construction period if they wish to take these alternative routes. At all times when users of the
PROWs are in the construction site they will have priority over construction traffic (see paragraph
13.92) below.
13.87. The construction compound, laydown area, substation and substation compound and turbine
foundations when being actively worked will be fenced, as will any open excavations where
required. All plant, equipment and welfare units will be shuttered up, locked and parked within the
construction compound when not in use.
13.88. Appropriate signage/information boards will be used at entry points (i.e. at points where the rights
of way enter the application boundary) to inform visitors of the construction activities. Signage will
request that visitors do not stray from the defined rights of way and will also show the location of
the construction activities and the access tracks.
13.89. The location of the crossing points will be fully signed in accordance with “Safety at Street Works
and Road Works A code of practice ISBN 0 11 551958” (Ref. 13-18) and Chapter 8 of the “Traffic
Signs Manual and Guidance for Safer Temporary Traffic Management” (Ref. 13-19). All
approaches to the crossing points will be signed to warn path users and construction vehicles of
the approaching hazard.
13.90. Careful attention will be paid to the surfacing of the access track as it crosses the right of way and
the condition of the footpath at this point.
13.91. All construction staff will be required to undertake an induction to alert them to the potential for
recreational users and to the environmental, health and safety measures that need to be taken. All
delivery drivers and plant operators will be briefed during tool box talks (i.e. a presentation to the
workforce) as to the location of crossing points and the safety procedure to be adopted for them.
13.92. All operatives and delivery drivers will be informed to advise site management of any deterioration
of crossing point safety. All drivers will be required to keep within an onsite speed limit of 15mph
and to reduce this speed further when passing recreational users using crossing points. The speed
limit will be rigorously enforced.
CPL PAGE 13-23
Rooley Moor Wind Farm Environmental Statement
13.93. A Health and Safety risk assessment will be undertaken. If this identifies that additional mitigation is
required to ensure the safety of the public, then further measures will be considered, which may
include the use of banksmen, for example when plant is operating during the construction of new
tracks or at the site entrance. The role of the banksmen will be to ensure that anyone exercising
their right to use the rights of way is able to do so in safety away from any active or dangerous
works. Alternatively, it may be preferable to close the PRoW for longer periods (for example up to
6 months), should discussions with RMBC Rights of Way team indicate that this is necessary.
Should this be the case then a contribution towards maintenance/improvements to the local PRoW
network affected by the Development may be considered appropriate mitigation and a Rights of
Way Improvement Plan would be developed. Again this would be agreed with the Rights of Way
team.
13.94. Proposed mitigation measures to address adverse impacts during the construction phase also
include the continued engagement with the community to listen to, and respond to, their concerns
as the Development develops. An ongoing communication strategy will be implemented by the
applicant to ensure that the local community and interested stakeholders are engaged with respect
to any issues of concern and provided information regarding the proposed mitigation. The
construction programme and details will also be communicated to the local community in order to
reduce any inconvenience or disturbance.
13.9.2 Operation
13.95. The access track will cross footpaths and bridleways at six locations in addition to sharing the
Pennine Bridleway to access the turbines and, therefore, permanent signage will be added to
facilitate the use of the right of way. Drainage will be designed to ensure that runoff is away from
the footpath and any deterioration in the surface of the footpath due to the wind farm activities will
be rectified. Again all staff will be required to undertake an induction to alert them to the potential
for recreational users. All operatives and delivery drivers will be informed to advise site
management of any deterioration of crossing point safety. All drivers will be required to keep within
an onsite speed limit of 15mph and to reduce this speed further when passing recreational users
using the crossing points. The speed limit will be rigorously enforced.
13.96. Continued engagement with the local community will be undertaken by the applicant to keep the
public and stakeholders informed as to activities relating to the operational phase.
13.9.3 Decommissioning
13.97. Health and safety will again be of paramount importance and a range of measures will be
employed in a similar manner to those described in paragraphs 13.84-93 for the construction phase
and in accordance with a risk assessment which will be prepared prior to the start of this phase.
13.98. Consultations with local residents and stakeholders will be undertaken prior to the
decommissioning phase beginning in order to inform them of the proposed schedule and activities
to be undertaken during this phase. This will enable the applicant to communicate the expected
impacts of this phase, and allow consultees to feedback their concerns and queries. The applicant
will respond to and address as far as practicable these queries prior to the decommissioning phase
beginning.
13.9.4 Residual Impacts
13.99. With the proposed mitigation measures in place, the major potential impacts with respect to health
and safety during the construction and decommissioning phases will be minimised and the residual
effect is anticipated to be temporary, adverse and of minor significance. In addition, residual
impacts with respect to tourism and recreational amenities in the area are anticipated to be adverse
(assuming a worst-case scenario where all users and visitors consider the presence of turbines to
be detrimental to their enjoyment) and permanent, but of negligible significance.
CPL PAGE 13-24
Rooley Moor Wind Farm Environmental Statement
13.100. There are a range of beneficial residual effects associated directly with the Development, although
these are considered, due to the size of the project, to be minor to moderate in magnitude, when
the project is considered in isolation. However, when combined with other wind farm development
in the region and across the UK, it will contribute to the economic stimulus they are reported to
provide. According to the BiGGAR report (Ref 13-9) the onshore wind industry supported more
than 8,600 jobs and was worth £548 million to the UK economy in 2011; of which around 1,100
jobs and £84 million investment occur at the local authority level in which onshore wind turbines are
located. This represents approximately £700,000 for every MW of onshore wind installed in the UK,
with over £100,000 staying within the host local authority area.
13.101. Overall residual effects are shown in Table 13.14.
Table 13.14 Residual Effects
Aspect/activity Assessment of potential impact Project Phase When Most
Apparent
Employment
Direct and indirect employment Permanent, beneficial, minor Construction, operation and
decommissioning
Economic Activity
Economic investment Permanent, beneficial, moderate Construction
Availability of Local Services
Influx of workers putting strain on
services
Temporary, adverse, negligible Construction
Tourism and recreation
Disruption to local amenities. Temporary, adverse, negligible Construction
Reduction of enjoyment of
amenities
Permanent, adverse, negligible Construction, operation and
decommissioning
Access and rights of way Temporary, adverse, minor Construction
13.10 Cumulative Impacts
13.102. The cumulative effects with wind farms in the 10km study area have been considered on the basis
of the negligible/minor adverse socio-economic effects associated with wind energy development
and the Development in particular. It is anticipated that there will be no significant adverse
cumulative effects likely to result from the Development in relation to socio-economic effects in the
local area. However as reported, this Development will contribute to the local economy and when
considered with other wind farm projects which may occur in the area, additional benefits on
employment, indirect employment and supply chain economic activity will accrue. These are
anticipated to be beneficial and permanent and moderate in magnitude and significance.
13.103. It is possible that over the lifetime of the Development, the local supply chain could develop in
response to the cumulative opportunities that these projects bring. Recent work by DECC (the
BiGGAR report) has shown that wind farms do have a very real beneficial effect on the local
economies in which they are located
13.11 Offsetting, Enhancement and Monitoring
13.104. The applicant is offering a community benefits package that will enhance and create further
benefits associated with the Development.
CPL PAGE 13-25
Rooley Moor Wind Farm Environmental Statement
13.11.1 Construction
13.105. During the construction phase, commitments to enhance the beneficial aspects of the Development
are as follows:
The applicant aims to ensure that, wherever reasonably practicable, local contractors and
employees are used in all aspects of wind farm development. The major opportunity lies during the
construction phase when suitably qualified local firms are identified and invited to bid for different
aspects of construction, such as foundation laying and electrical works. Construction materials are
normally sourced locally and local transport and plant hire companies used wherever possible.
The applicant will have in place supplier engagement processes to encourage opportunities to be
advertised locally so promoting selection of the most able suppliers and making it easier for small
and medium-sized enterprises to work on the Proposed Development during the construction
phase;
The applicant will aim to recruit from within the local area through targeted methods including
building relationships with local employment agencies and unemployment programmes. The
applicant will encourage contractors and sub-contractors to prioritise local recruitment. The socio-
economic baseline assessment identified construction skills as being present within the locality.
13.11.2 Operation
13.106. The applicant is proposing to establish a community benefit fund which will allow local people to
benefit from the wind farm. The community fund will be administered by local trustees who will
decide how the fund is managed and spent.
13.107. It is not however suggested that any weight should be given in the decision-making process to the
presence of this fund, but note does need to be made of the recent announcement by the
Government of the desire to see more community involvement in the decision-making process for
onshore wind turbines as well as the community receiving more in the way of benefits from such
developments.
13.11.3 Decommissioning
13.108. During the decommissioning phase, the applicant is committing to the following enhancement
measures:
the applicant will encourage contractors and sub-contractors to prioritise local recruitment;
the applicant will have in place supplier engagement processes to encourage opportunities to be
advertised locally so promoting selection of the most able suppliers and making it easier for Small
and Medium-sized Enterprises to work on the proposed development during the decommissioning
phase; and
the applicant will aim to recruit from within the local area through targeted methods including
building relationships with local employment agencies and unemployment programmes
the applicant will help those who have been in long term employment on the Proposed
Development find alternative work. This could be on another the applicant project or another wind
farm in the locality.
13.12 Conclusion and Statement of Significant Impacts
13.109. This chapter has presented the socio-economic assessment of the Rooley Moor Wind Farm
Development. More specifically, the economic, social, tourism and wider impacts have been
evaluated.
13.110. Overall, the Development is expected to give rise to temporary minor adverse effects on the use of
the Pennine Bridleway during construction and a temporary minor beneficial effect on the local
CPL PAGE 13-26
Rooley Moor Wind Farm Environmental Statement
economy, bringing an estimated £3.440,000 and 21 full time equivalent jobs during the construction
period, and so therefore a negligible socio economic effect in the local area.
13.111. During operation the Development will have a permanent, adverse but negligible effect on the use
of Pennine Bridleway and a permanent beneficial and minor effect on the local economy,
generating approximately £400,000 per year and providing 6 full time equivalent jobs. Overall there
is a negligible socio economic effect on the local area during operation of the Development.
13.112. The Developer will work with the relevant local groups to introduce relevant mitigation measures
where this is required.
13.13 References
13-1 The Interorganizational Committee on Guidelines and Principles for Social Impact
Assessment (2003). U.S. principles and guidelines: principles and guidelines for social
impact assessment in the USA, Impact Assessment and Project Appraisal, 21(3). 231-250.
13-2 Office for National Statistics, 2011 Census. [online] Available at
http://www.ons.gov.uk/ons/guide-method/census/2011/census-data/index.html [Accessed
30 June 2014]
13-3 Office for National Statistics. 2014. [online] Available at
http://www.ons.gov.uk/ons/index.html [Accessed 30 June 2014]
13-4 Office for National Statistics, 2001 Census. Available at http://www.ons.gov.uk/ons/guide-
method/census/census-2001/data-and-products/about-the-tables-and-products/types-of-
table/index.html [Accessed 30 June 2014]
13-5 BE Group (2010) Rossendale Tourism Study, Rossendale Borough Council. 2010
13-6 Rochdale Borough Council, (2013). Rochdale Publication Core Strategy, Rochdale Borough
Council
13-7 Rochdale Borough Council. Stats and Maps [online] Available at
http://www.statsandmaps.org.uk/metadata/view/dataview?id=134&norefer=true [Accessed
30 June 2014] The Scarborough Tourism Economic Activity Monitor (STEAM)
13-8 RenewableUK (2012).Onshore Wind, Direct and Wider Economic Impacts.
13-9 BiGGAR (2012) Onshore Wind Direct & Wider Economic Impacts, RenewableUK and
Department of Energy and Climate Change
13-10 RenewableUK Briefing Sheet (2005) Public Attitudes to Wind Energy in the UK
13-11 Ipsos MORI (2012) Publications [online] Available at http://www.ipsos-mori.com/Assets/Docs/Polls/renewable-uk-wind-power-topline-april.pdf [Accessed 17/10/12]
13-12 Sustainable Development Commission (2005) Wind Power in the UK
13-13 YouGov plc (2010) Public Attitudes to Wind Farms. Scottish Renewables
13-14 Glasgow Caledonian University, Moffat Centre, and Cogentsi (2008) The Economic Impacts of Wind Farms on Scottish Tourism
13-15 Aitchison, C. (2004) The Potential Impact of Fullabrook Wind Farm Proposal, North Devon: Evidence Gathering of the Impact of Wind Farms on Visitor Numbers and Tourist Experience, Bristol: University of the West of England/Devon Wind Power
CPL PAGE 13-27
Rooley Moor Wind Farm Environmental Statement
13-16 British Horse Society Advice on Wind Turbines and Horses to Riders and Carriage Drivers, [online] Available at http://www.bhs.org.uk/~/media/BHS/Files/PDF%20Documents/Access%20leaflets/BHS%20Advice%20on%20Wind%20Turbines%20for%20Riders%20and%20Carriage%20Drivers.ashx [Accessed 30/06/14]
13-17 British Horse Society Advice on Wind Turbines and Horses – Guidance for Planners and Developers [online] Available at http://www.bhs.org.uk/~/media/BHS/Files/PDF%20Documents/Access%20leaflets/BHS%20Wind%20Turbine%20Guidance%20for%20Planners%20and%20Developers.ashx [Accessed 30/06/14]
13-18 A Code of Practice issued by the Secretary of State for Transport, Local Government and the Regions, The Scottish Executive and the National Assembly for Wales (2001) Safety at Street Works and Road Works A code of practice, HMSO: 2001
13-19 Department for Transport (2009) Traffic Signs Manual and Guidance for Safer Temporary Traffic Management Chapter 8, HMSO: 2009