+ All Categories
Home > Documents > Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge...

Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge...

Date post: 12-Mar-2020
Category:
Upload: others
View: 7 times
Download: 0 times
Share this document with a friend
165
ROUGHNESS AT THE PAVEMENT-BRIDGE INTERFACE by Y!-Chin Hu Tsu-Long Wu Clyde E. Lee Randy Machemehl Research Report/Number 213-1F Roughness at the Pavement-Bridge Interface Research Project 3-8-76-213 conducted for Texas State Department of Highways and Public Transportation in cooperaticn with the U. s. of Traosportation Federal Highway Administration by the CENTER FOR HIGHWAY RESEARCH THE UNIVERSITY OF TEXAS AT AUSTIN August 1979
Transcript
Page 1: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

ROUGHNESS AT THE PAVEMENT-BRIDGE INTERFACE

by

Y!-Chin Hu Tsu-Long Wu Clyde E. Lee

Randy Machemehl

Research Report/Number 213-1F

Roughness at the Pavement-Bridge Interface

Research Project 3-8-76-213

conducted for

Texas State Department of Highways and Public Transportation

in cooperaticn with the U. s. Departme~t of Traosportation

Federal Highway Administration

by the

CENTER FOR HIGHWAY RESEARCH

THE UNIVERSITY OF TEXAS AT AUSTIN

August 1979

Page 2: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement
Page 3: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

'.

PREFACE

This is the first and final published report on Research Project

3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-

maries of pertinent literature, methodologies for measurement and analyses of

surface roughness, and recommendations for precluding and minimizing approach

surface roughness.

Two unpublished theses based on various phases of the study have been

submitted to The University of Texas at Austin in partial fulfillment of the

requirements for the ~Bster of Science degree in Civil Engineering. These

are:

"A Study of Roughness at the Pavement-Bridge Interface," June 1977, by Y. C. Hu, and

"Roughness at the Bridge-Pavement Interface," August 1979, by T. S. Wu.

Copies of these are available for interlibrary loan from The University

of Texas at Austin, Austin, Texas 78712.

111

Page 4: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

ABSTRACT

Road surface roughness in the proximity of the pavement-bridge interface

may lower riding quality and induce excessive dynamic wheel loads on highway

structures. Twenty-one bridge sites in four Texas State Department of Hir,h­

ways and Public Transportation Districts, Lubbock, Houston, Austin, and San

Antonio, are selected for study. The Surface Dynamics Profilometer is uti­

lized to measure roadway profiles. Dynamic vehicular tire forces induced by

three types of vehicles at two specified speeds are estimated using a computer

simulation model. Possible causes and typical patterns of surface irregular­

ities are identified and classified and various treatment methods are exam­

ined. A dynamic load index is developed to assess ride quality and predict

subjective ratings.

iv

Page 5: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

SUMMARY

An extensive study of surface roughness along and adjacent to bridge _.

approaches is presented. A survey of literature indicates that various as­

pects of the generalized problem have been investigated by a number of re­

searchers. Most research efforts have recommended design and construction

methodologies which have been incorporated into current practice.

Field data collection efforts have consisted of gathering design, con­

struction, and maintenance histories and surface profile descriptions for

bridge approaches in four SDHPT Districts. Computer simulation of vehicular

tire forces for measured approach profiles indicates that dynamic tire forces

induced by typical approach roughness may reach as much as 4.5 times their

static values.

A large number of factors suspected of being related to approach rough­

ness could not be identified as causative. These include traffic volume,

bridge function, bridge type, bridge age or height of embankment fill. Rigid

pavements could not be identified as being generally superior to flexible

pavements; however. CRCP generally provided better performance than JRCP.

Type of material utilized in approach embankments was found to be the factor

best correlated with roughness problems. Timely performance of maintenance

activities was, likewise, identified as having a strong relationship to the

development and progression of approach problems.

v

Page 6: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

IMPLEMENTATION STATEMENT

A concise summary of courses and manifestations of pavement surface

roughness on bridge approaches is provided. Information presented may be

utilized as a guide to design, and construction techniques which may be

utilized to help preclude approach roughness problems. Data regarding sur­

face maintenance may, likewise, be utilized as a guide to practices which may

help alleviate roughness problems. Simulation based prediction of dynamic

vehicular tire forces induced by specific roughness types, can be used to pre­

dict magnitudes and locations of dynamic loading on bridge approaches and

bridge surfaces.

Page 7: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

.-TABLE OF CONTENTS

PREFACE

ABSTRACT

SUMMARY

IMPLEMENTATION STATEMENT •

CHAPTER 1. INTRODUCTION

Roughness Indicators Objectives Scope of the Report

CHAPTER 2. CAUSE EXAMINATION AND TREATMENT STUDY - A LITERATURE REVIEW

Traffic • Climate and Environment Material Design Construction Maintenance Summary •

CHAPTER 3. SITE INVESTIGATIONS

District 14 (Austin) Sites District 15 (San Antonio) Sites District 5 (Lubbock) Sites District 12 (Houston) Sites • Roughness Patterns

CHAPTER 4. ANALYSIS OF DYNAMIC WHEEL LOADING

Surface Dynamics Profilometer • DYMOL • Data Analysis and Result Presentation • Dynamic Loading Index •

CHAPTER 5. CONCLUSIONS AND RECOMMENDATIONS

Conclusions • Recommendations •

vii

iii

iv

v

vi

1 2 2

6 7 8

15 23 24 25

29 36 41 47 50

57 58 62 71

79 82

Page 8: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

APPENDIX. 84

REFERENCES 155

viii

Page 9: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

CHAPTER 1. INTRODUCTION

Road surface irregularities adjacent to highway bridges have long plagued

highway users and highway maintenance agencies.' These bumps, dips, and rolls

not only create an unpleasant ride when a vehicle passes onto and off the

bridge but also, in severe situations, may present a hazardous condition to

fast moving traffic. The deterioration of both pavement and bridge structures

is accelerated as a result of increased dynamic wheel loading caused by sur­

face irregularities. Moreover, in order to correct these surface faults,

costly repair work is often required. Under a heavy traffic flow situation,

this maintenance operation may seriously disrupt the normal flow of traffic

and thus significantly increase total user costs.

There is no general agreement on the specific longitudinal boundaries

of bridge approaches. Many parts of the roadway may contribute to poor rid­

ing quality, such as the bridge deck and abutment, pavement structure, sub­

grade, embankment, and foundation. Though the physical condition of the pave­

ment-bridge interface often provides an indication of the problem, the source

of the problem usually lies somewhere else. For instance, the local climate

could be a contributing source. In fact, the problem is so complicated that

almost all aspects of design, construction, and maintenance are involved.

These factors will be examined more closely later.

ROUGHNESS INDICATORS

Pavement distress is an obvious concern of this study. It includes at

least three modes: fracture, distortion, and disintegration. A summary of

1

Page 10: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

distress manifestations, with possible distress mechanisms, is shown in

Fig 1.1.,

2

One prevalent indicator of an unsatisfactory bridge approach is displace­

ment of the pavement. As depicted in Fig 1.2, this may be either settlement

or uplift of the pavement at the abutment or at the pavement end of an ap­

proach slab. Also shown in Fig 1.2, although not a frequent cause, is settle­

ment or rotation of the abutment.

OBJECTIVES

This study is a continuing effort to examine roughness problems at pave­

ment-bridge interfaces in the State of Texas. An number of representative

cases in four districts, Austin, San Antonio, Lubbock, and Houston, are se­

lected. The objectives are to locate and characterize the types of roughness,

to identify their possible causes, and to suggest possible solutions or treat­

ment techniques.

SCOPE OF THE REPORT

Chapter 2 includes a literature review in which causative factors and

common treatments are classified and examined. Results of investigations at

a number of selected field test sites are presented in Chapter 3. Data col­

lected through questionnaires and on site studies form the basis of this anal­

ysis. Typical roughness patterns are identified and schematically illustra­

ted.

Road surface profile measuring hardware and techniques are presented

in the first section of Chapter 4. The second section describes a simulation

model, which is used to predict dynamic vehicular tire forces which occur as

the result of surface profile irregularities. The measured profiles are com­

pared with rod-and-level elevations, and the applicability of profilometer

Page 11: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

'.

Distress Mode

Fracture

Distress Manifestation . 'Examples of DiStress Mechanism*

Cracking _____ ..

Spalling

Permanent deformatio~n-----I

Loading Fatigue Thermal changes Moisture changes Slippage (horizontal forces) Shrinkage

changes Moisture changes

Loading Time-dependent deformation

(e.g., creep) Densification (i.e., compaction) Consolidation Swelling

Distortion ---I

Disinte­gration

Faulting

Stripping

--0001 Raveling

Loading (pumping) Densification (i.e., compaction,

consolidation) Swelling Erosion

TAdhesion ----------I~emical reactivity

Abrasion by traffic Degradation of aggregate

----------~ Durability of binder Insufficient asphalt

Scaling ~emiCal reactivity

__________ ~ Abrasion by traffic Freeze-thaw action

* Not intended to be a complete listing of all possible distress mechanisms.

Fig 1.1. Categories of pavement distress (from Ref 1).

3

Page 12: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

"

Fig 1.2.

."Uft of Approach Sl.1> - Iz'panl1oll fl'. _Ubi Solb 01' ".""iDi

... Uill S .. ttl .. llt 111101 .. nulbl. rn •• ", or Ap,roach 3l. .. b .... t M.'1""tely Supported

at Al>ut:M1lt

AI>u~ .. t Sntl .. llt (1.f •• o ... "t)

t lotation or wteral ~_ftt o~ AII~t""t (l"fraqu.llt)

Typical bridge approach problems (from Ref 2).

4

Page 13: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

5

records to dynamic load prediction is analyzed. The vehicle simulation

. analysis is presented in the subsequent section. Dynamic wheel load diagrams

of simulation results are included in the appendix. A dynamic loading index

is developed to permit quantitative expression of the potential for creation

of dynamic vehicular loading by given surface profiles.

Page 14: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

CHAPTER 2. CAUSE EXAMINATION AND TREA'nIENT STUDY

- A LITERATURE REVIEW

In order to develop necessary understanding of previously completed

study efforts, a review of available literature was made. Factors affecting

the riding quality of bridge approaches were examined and treatment methods

that have been used were studied.

Factors which influence the performance of the pavement bridge inter­

face are very complex and are interrelated with one another. There is no

consensus about the causes and effective treatments of the problem. In this

study, related factors are assembled into the following six groups:

(1) traffic

(2) climate and environment

(3) materials

(4) design

(5) construction, and

(6) maintenance.

TRAFFIC

Among the important factors to be evaluated for damages by traffic to

highway pavements and bridge decks are the effects of vehicle characteristics,

traffic volume, and speed of vehicle operation.

Major vehicle characteristics include weight and weight distribution,

number of axles, axle arrangement, tire spacings, tire pressures, and elas­

tic suspension system. One means of expressing the effects of vehicle axle

weight upon pavement life is through the AASHTO equivalency factors (Ref 3).

--- ----- - - - .. --- -- -. ------- - -----" - -- -- - --- --~

Page 15: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

These relationships can be utilized to numerically express the relative

damage effects of any vehicle axle. The AASHTO equivalency factors indicate

that the damage per pass by light passenger car axles is very small as com­

pared with that by those of a heavy truck.

7

Most investigators agree that the magnitudes of dynamic loads increase

with increasing speeds (Refs 4 and 5). Higher speeds increase the excitation

of vehicle suspension systems when pavement roughness is present; however, the

variation of dynamic wheel forces with speed depends heavily on the type of

vehicle and the type of road roughess.

CLIMATE AND ENVIRONMENT

The most important factors under this category are temperature and mois­

ture. Freezing temperatures in the presence of moisture directly induce

frost action (Ref 6). In a broader sense, frost action means both frost

heave and loss of subgrade support during frost-melt periods. This phenom­

enon is one severe cause of pavement roughness. Sometimes, structural dam­

age during the spring thaw is so great that heavy loads are prohibited

(Ref 7). Economic loss to the public resulting from selective shutdown of

roads under such conditions may be very high.

For rigid pavements and bridge decks, temperature variations of the

slab may affect the condition of the interface. With a rising temperature,

the slab will expand and push against the abt:.tment, causing displacement of

the abutment if there are no well-maintained expansion joints and a properly

installed anchorage system (Ref 8).

The effect of precipitation on pavement performance has not received

the same attention as effect of frost action. However, since the load-bear­

ing capacity of a pavement is determined considerably by the strength of the

Page 16: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

8

subgrade, increases in water content due to rainfall or poor drainage

conditions may lead to pavement breadup. Rainfall also provides part of the

mechanism by which pumping of rigid pavements and shrinkage and swell of some

subgrades may occur (Ref 9).

The presence of a water source near bridge abutments affects the poten­

tial for approach roughness. A study made in Kentucky (Ref 10) shows that a

bridge over a river is more likely to have rough approaches than a bridge for

a grade separation. Embankments near water sources have a tendency to absorb

moisture, and the excess moisture often adversely affects material properties.

In general, the extent of damage at a bridge approach due to climate var­

iables depends on the type of pavement, the amount of traffic, and particular­

ly the type of embankment and foundation materials. For those areas with

swelling clay or frost-susceptible soil, frequent moisture changes and freeze­

thaw cycles will create roughness. Elaborate preventive measures are often

warranted for such cases.

MATERIAL

Materials considered here include (1) original foundation soil, (2) em­

bankment fill, (3) abutment backfill, and (4) swelling clay.

Foundation Material

It is believed that the post-construction settlement of foundation mater­

ial is a common cause of roughness at bridge approaches (Ref 2). Subsurface

exploration at the abutment site is utilized to predict the total amount of

consolidation that can be anticipated in the embankment foundation and the

time required for it to take place under imposed loads. Highly compressible

foundation material at the bridge approach can be treated using several com­

mon methods as discussed below.

Page 17: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

9

Removal by Excavation. This treatment can be adopted when soft material

is reasonably shallow, required borrow is readily available, and embankment

stability must be achieved in a relatively short period. Typical sections

for various cases of excavation are shown in Fig 2.1. The cost of excavation

is very high, and non-uniform post-construction settlement may occur if the

undesirable material is not completely removed.

Removal by Displacement. As an alternative to excavation, displacement

of soft materials by deliberate overstressing with the weight of the embank­

ment, perhaps combined with a temporary surcharge, is sometimes employed

(Ref 12). It is essential for this operation to have sufficient weight to

force out the underlying soil, and the mudwave created before the leading

fill front should be excavated to a sufficient depth, so that the displace­

ment direction can be controlled and pockets of displaced soil will not be

entrapped within the embankment. The method may result in the intrusion of

fill into the area outside the boundary of the roadway, requiring more fill

and more surcharge, thus adding to the cost of the project. In some cases,

removal of the subsoil may be excellent; however, pockets of soft soil some­

times remain to produce differential settlements, which are intolerable for

major highways. This method would therefore be more suited for secondary

roads with low traffic volume.

Surcharge. This may be the most commonly used methrod for accelerating

the rate of settlement. The embankment fill is placed to a height above the

required for final elevation so that more settlement will occur during a

given time period (Ref 13). The thicker surcharge will induce more and

faster consolidation, but this benefit is partially offset by the high cost

of placing the fill and subsequently removing the unneeded portion by the

need for berms if the heavier surcharge is used.

Page 18: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

'.

~~~~ __ ~ ________ ~L-~ ____ ~~~~~~~ __ _

Ortof\lt "01f'lol ,.'M 101.,.".1 Pey"""t 41ft. •••• cl •• lIIouow

UNSUITABLE MATERIAL EXCAVATION SHALLOW OEPTHS (0 TO 5 FT.)

t

U"t ..... 1IIe O'90fti C •

~I-,.,m l-"o ••• iOl

l I

... ' ..... ,1 Ii". MleCI ....... .

UNSUITABLE MATERIAL EXCAVATION DEPTHS GREATER THAN ~FT.

IIIOIS.d .,ee 10 IN i ... I"d.d ill .,cOYIIlio" .... boeU,1t Quonhti., to .rOWlf. tOt _,bl. tlo,,;hi,,; of •••••• Iio" slOp .. . PG' .... "I 10 IN bo •• d ... a.,,,.1 .... . IIOtto! ... " .... il"i~ Ihi .110 •• II ... "

UNSUITABLE MATERIAL EXCAVATION CASE OF SURFACE FILL OVER ORGANIC SOIL

Fig 2.1. Typical sections for excavation of unsuitable material (from Ref 11).

10

Page 19: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

11

Vertical Sand Drains. Layers of soft soils 10 to 15 feet (3 to 4.5 m)

thick can often be stabilized by consolidation under surcharge only. For

thick deposits of soft materials, however, stabilization can be attained more

economically through installation of vertical sand drains, combined with pre­

load fills (see Fig 2.2). Sand drains are pervious sand columns and are usu­

ally installed in a grid pattern. A blanket of pervious sand is placed on the

tops of the drains to allow the water moving out of the drains to flow later­

ally from under the embankment. Sand drains can reduce the length of the

water drainage path and, thus, the required surcharge thickness, the surcharge

time, and the size of the berms, if any. There are many successful field

experiences with this design (Ref 14), but the closed-end displacement-type

installation may induce too much soil disturbance and reduce soil stability.

Hence, nondisplacement types of drains, for which the hollow shaft flight

auger is used, are often preferred to displacement types (Ref 15).

Embankment Material

The volume change of a roadway embankment is generally assumed to be

less serious than that occurring in foundation material. It should be noted,

however, that this assumption is valid only when good materials and good con­

struction procedures are used (Ref 16). Since vertical stress beneath the

centerline of the embankment decreases slowly with the depth (see Fig 2.3),

high pressure, especially that associated with large fills, may induce severe

settlement in the foundation and the embankment itself. Special select mater­

ials and increased density for the bridge approach embankment are specified by

some agencies to ensure good performance (Ref 2).

Several experiments using lightweight material, instead of common borrow,

for the embankment have been reported to be successful (Refs 18-20). Light­

weight fill will reduce the embankment weight and the foundation stress

Page 20: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

SETTLEMENT PROBES

WATER DRAINAGE ~TTERN

J~S'ND DFtAIN

Fig 2.2. Design information for sand drain installation (from Ref 12).

12

Page 21: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

--.. ... ~ D. .~

.. ~. , .. " ,." .. ' .. :,

EMBANKMENT -Foundation Contact Pressures:

h· 20', w· 200'; q. 2.5 ksf h • 40', w· 280'; q. 5.0 ksf

BRIDGE PIER -Footing Contact Pressure

q • 4 ksf (Total load· 4000 kips)

VERTICAL STRESS (kips/ft2 )·

o O~----~~--~~~~--~~-----.

2 3 4 5

20

Earth Embankment

40

60

80

l00~--~--~~----~----~--~

Fig 2.3. Comparison of vertical stresses beneath center lines of bridge pier and earth embankments.

13

Page 22: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

14

considerably. As a result, the settlement is reduced and the berms are either

reduced accordingly or eliminated completely.

So-called lightweight material includes sawdust, sewage ash, and fuel

ash. Although costs for such materials are low, their properties differ

greatly, and care must be exercised when they are used in the field. In some

cases, frost susceptibility and deterioration in air of such materials may

cause trouble. Precautionary actions should be taken, such as lime or cement

stabilization to reduce frost heave and asphalt sealing to minimize air de­

terioration.

Abutment Backfill Material

Good condition of the abutment backfill is vital in bridge approach con­

struction. Use of unsuitable backfill material, combined with poor compac­

tion, has been a serious cause of roughness at bridge approaches.

In many instances specially graded granular material, such as sandy

gravel, is specified for abutment backfill. It is not practical, however,

to specify use of such high-quality material in all locations. The Road Re­

search Laboratory (RRL) in England has experimentally compared the performance

of sandy gravel and other materials (Refs 21-25). In the RRL experiments,

well-graded sandy gravel was used as the abutment backfill at one side of a

bridge, and another material was used at the other side. This arrangement

eliminated the complicated variations of environment and traffic, and hence

the performances of these two materials could be easily compared. It was

found that (1) lightweight pulverized fuel ash, (2) a medium clay, (3) a

uniformly-graded fine to medium sand, and (4) a stony-clay fill were very

good or quite satisfactory as a substitute for sandy gravel. On the other

hand, a silty clay turned out to be unacceptable and therefore should be

avoided as abutment backfill.

Page 23: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

15

Swelling Clay

Most highway agencies are concerned with settlement problems at bridge

approaches, but those agencies located in areas of expansive clay are also

concerned with swell. In these areas, special backfill is used on some occa­

sions as a buffer to protect the bridge abutment and the approach slabs

(Ref 2). Other treatments include removal of swelling clay, lime stabiliza­

tion, and preswelling of the soil before construction through ponding. Plas­

tic sheets and bituminous membranes have also been used to form moisture bar­

riers above expansive clay (Ref 26).

DESIGN

Design factors discussed include (1) type of pavement, (2) type of

abutment, (3) type of abutment support, (4) embankment slope stability, and

(5) approach slabs.

Type of Pavement

Pavement is usually classified as either rigid or flexible. The major

difference between them is the manner in which tire forces are distributed

upon the subgrade. The load-carrying capacity of flexible pavements develops

from the load distributing characteristics of the layered system. Such pave­

ments consist ~f a series of layers, generally with an asphalt concrete sur­

face at the top. The thickness design of the pavement is influenced appre­

ciably by the behavior of the subgrade. Rigid pavements, including both

JRCP and CRCP, because of their rigidity and high modulus of elasticity,

tend to act as rigid plates; thus certain weak spots in the subgrade can be

bridged over by the pavement. For this reason, a rigid pavement, at least

for a short period of time, may allow better performance at bridge approaches

(Ref 10).

Page 24: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

TYpe of Abutment

A pointed out in Chapter 1, the condition of the bridge abutment is

sometimes a factor in causing irregular approach surfaces. Such conditions

include rotation of abutments on ~ile groups and settlement of abutments on

spread footings.

There are three general types of abutments which are frequently used.

(a) Closed, or retaining wall, type abutments (Fig 2.4) usually con­

sist of a central pier to support the bridge deck and two wing

16

walls to retain the backfill. This type of abutment is treated as

a retaining wall in structural design. One objectionable feature

is the inherent difficulty in placing and compacting material

against the wall and betweeL wing walls. Vertical alignment of the

abutment may be disturbed if heavy equipment is permitted to work

near the wall. In addition, placement of the embankment after con­

struction of the abutment may cause excessive foundation settlement.

To overcome these problems, backfilling is not started until the

first bridge span is in place and as much of the adjacent embankment

as is practical is placed before abutment construction.

(b) Stub, or shelf, type abutments (Fig 2.5) are constructed after the

embankment has settled to ,the final elevation. It can be supported

on spread footings, drilled shafts, or piles. Since the difficulty

of compaction is eliminated, many engineers believe that this type

of abutment provides the best bridge approach performance.

(c) Spill-through, or open, type abutments (Fig 2.6) consist of two or

more vertical columns extending from the natural ground to carry

a beam that supports the bridge seat. Proper compaction of the fill

around the columns and under the abutment cap is nearly impossible

Page 25: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

17

Fig 2.4. Typical closed or retaining wall abutment (from Ref 2).

Fig 2.5. Typical stub or shelf abutment (from Ref 2).

/-~'" - . , . .

, ,

Fig 2.6. Typical spill-through or open abutment (from Ref 2).

Page 26: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

to attain. It is believed, therefore, that this type of abutment

may be highly susceptible to bridge approach problems.

Type of Abutment Support

18

Regardless of the abutment type adopted, there are only two principal

types of abutment support. These include spread footings (shallow foundation)

and piles or drilled shafts (deep foundation).

Abutments on spread footings may have less differential settlement be­

tween abutment and approach slab than abutments on deep foundations (Ref 2).

The total settlemtns of abutments on shallow foundations may, however, be

intolerably large. Many agencies, therefore, strongly recommend use of deep

foundations at all abutments in embankment fills (e.g., Ref 27). Moreover,

drainage for abutments on shallow foundations can be very critical. Some

special granular material has to be used to offset possible settlement or

erosion (Ref 2).

Embankment Slope Stability

Approach embankment slope failure is a serious cause of surface roughness

near the interface area. Several methods used to maintain slope stability

are summarized here.

Drainage System._ Along with paved surface drains, provision for the re­

moval of subsurface water is an essential part of the abutment design. Infor­

mation concerning area ground water conditions in association with abutment

type and backfill materials is utilized to choose among the several alterna­

tive drainage schemes shown in Fig 2.7 (Ref 2).

Membrane. Various types of asphaltic membranes are often used to reduce

changes in moisture content for sites with highly plastic or expansive soils.

Three types commonly referred to as surface, buried, and envelope membranes

are shown in Fig 2.8. Envelope type membranes used on the Gulf Freeway in

Page 27: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

;

Cranular Kateriel

fabanlallllnt

DraiDAg. Carried to Either Side or ThrouRh Abut .. nt We.phol.a

I'l'D'II 011. sm., ASU"l'HEIITS

Embanbent

Drainage Carried to lither Side or Through Abut .. nt Weephol ••

Fig 2.7. Typical methods used to provide abutment drainage (from Ref 2).

1

Fig 2.8. Functional types of membranes (from Ref 28) •

• -: HAV SECTION AT FILL

LONG. SECTION AT ,P,'DGE. END

lig 2.9. Typical embankment sections with envelope-type membranes, Gulf Freeway (from Ref 28).

19

Page 28: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

,

20

Houston (see Fie 2.9) provided excellent stabilization of the plastic abutment

fills and the strength of the fill did not decrease significantly during a

l4-year monitoring period.

Stabilizing Berm. When the weight of the embankment causes shear stress­

es greater than the shearing strength of the foundation soil, the underlying

soil may be displaced laterally. The purpose of a berm placed against the

outer embankment slope is to offer some counterweight to resist the overturn­

ing moment on the failure arc (see Fig 2.10). It can also be used to correct

failures which occur during or after construction.

Benching. Because even small movements of the embankment may create

problems at bridge approaches, benching of the natural ground is sometimes

employed to provide a stable horizontal foundation with a larger contact

plane. A typical section is depicted in Fig 2.11.

Approach Slab

Many agencies consider the use of reinforced portland cement concrete ap­

proach slabs to be the most satisfactory means for controlling surface irreg­

ularities at bridge approaches. However, in regions of serious swelling clay

problems, approach slabs sometimes become so troublesome that they have to be

removed.

Approach slabs are designed in a wide range of shapes, lengths, widths,

and depths. Some frequently used types are shown in Fig 2.12.

In many cases, the use of approach slabs may shift the bump to the pave­

ment end of the slab (see Fig 1.1). This shifting, in fact, does not solve

the roughness problem. Therefore, special joints for use between roadway

pavement and approach slabs have been developed to correct the condition.

Figure 2.13 illustrates five examples.

Page 29: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

21

Z' ABOVE PROFILE GRADE

" .:. FIRST CONSTRUCTION STAGE

r' .. ' .. ..'

r~~~.~~iJJ,~T~:~ '. , . ,"

Fig 2.10. Typical half-section of stabilizing berm (from Ref 12).

. .

Fig 2.11. Abutment end section with natural ground benched (from Ref 2).

Page 30: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

20' 0" ----~I

........ u'o ... ,,_3 1111.10

/1--------- 24' 0" ab.--------ll

·····Fj ] lrid," _

20' o·

fl

~r~'_'_'_'_' __ ' _'_'_'_, ________ i_2 __ , ___ , __________ ..JI~· .... b Co.oU ...

Fig 2.12. Commonly used bridge approach slabs (from Ref 2).

20'0" ,. tr.foraed J017

20'0"

1/2" 'r.foraeel J01Dt rU1.r

Wada. (Ml ..... ) ,. JoLDt (La.) r Joint

Cr ...... teel 'U.

c.) (11110010)

10'

") ~t" Carol1u)

{""""""'r I------"I"-------r--'I J LJ- ~. JJ L )' (La.L.J ea.pactad Aa.re.at. r,. QIiu---=>I st11 010.)

C-nta 1111

(c)

(d)

T , G rith Dovel

, CoDtractlota \Jolt

(a)

Fig 2.13. Joints used between roadway pavement and approach slabs (from Ref 2).

22

Page 31: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

23

CONSTRUCTION

Two construction techniques which are sometimes helpful in precluding

roughness are discussed here: (1) slow rate construction and (2) compaction.

Slow Rate Construction

This is probably the most economical construction technique because it

involves no additional construction material. The only requirement is suf­

ficient time.

Slow rate construction is employed where the foundation soil would under­

go shear failure if the embankment were constructed under normal procedures.

However, due to its relatively rapid consolidation characteristics, such a

soil might become strong enough during a controlled or partially delayed con­

struction period to prevent such a possibility.

In case of slow rate construction, an elapsed time of three to six months

between embankment construction and paving operations is common. A ~aiting

time so:·long that it extends into the next construction season is common for

major structures (Ref 2).

COmpaction

Improper placement and compaction of material in approach embankments is

one primary source of surface roughness. Therefore. stringent specifications

and inspection of soil compaction are extremely important. Some state high­

way agencies require the compactive density be as high as 102 percent of the

maximum density specified in the ASSHTO T-99 test (Ref 27). On the whole.

most agencies believe that their current specifications for embankment con­

struction are satisfactory (Ref 17). However, as noted earlier. special

difficulties may be associated with the abutment backfill. Thus. a special

quality control program may be required for this critical area.

Page 32: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

24

MAINTENANCE

Timely and proper maintenance of bridge approaches can smooth the road-

way surface, decrease dynamic wheel loads, and reduce the deterioration rate.

Depending on the problem and its cause, maintenance may be simple and inex-

pensive, such as slab jacking or heater planing, or it may entail complete

rehabilitation through an overlay (Ref 1). Illustrated in Fig 2.14 are the

routine bituminous leveling techniques. Settlement is corrected by adding

additional asphalt to the approach pavement; however, when swelling has

lifted the approach, additional asphalt is added to the first span of the

bridge.

Correction

f ~ J ~ J Settlment

Correetion

f @j 1 f . .... 11~1II

Fig 2.14. Use of bituminous leveling to correct settlement or swelling (From Ref 2).

i

Page 33: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

25

SUMMARY

The above review indicates that there are many causative factors which

can create roughness in the p'roximity of the bridge-pavement interface. A

study sponsored by the Ohio Department of Transp'ortation concluded that the

correlation between bridge approach performance and design/construction param-

eters was very poor and that differential approach settlement had no general

correlation with the embankment height (Ref 27). However, it seems appro-

priate to emphasize four major causes:

(1) excessive settlement of the embankment and its foundation,

(2) embankment slope failure over a soft foundation,

(3) volume chan~e of the expansive chay due to moisture variations, and

(4) horizontal movement of a concrete slab due to temperature or mois­ture variations in the slab.

These four major factors, together with various treatment methods, are

summarized in Table 2.1. Remedial treatments should be considered in design

and appropriately implemented in construction processes. Heavy trucks may

worsen the problem, while maintenance can help alleviate the problem. The

environment may have either positive or negative effects on' the overall

situation.

Page 34: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

26

TABLE 2.l. SUMMARY OF BRIDGE APPROACH PROBLEMS AND TREATMENTS

Excessive Slope Swelling Slab Treatments Settlement Failure Clay Movement

Drainage X :x :x

Membrane X X X

Berm X

Benching :x

Approach slab X

Anchorage system X

Lightweight fill X X

Lime stabilization X ·X X

Good subbase X X material

Granular fill X X X

Removal of bad X X X foundation material

Surcharge X X X

Sand drain X X :x

Compaction X X X

Water ponding X

Page 35: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

CHAPTER 3. SITE INVESTIGATIONS

In order to characterize surface roughness in the proximity of the

pavement-bridge interface site, investigations were conducted in four SDHPT

Districts. The conditions of District 14 (Austin), District 15 (San Antonio),

District 5 (Lubbock), and District 12 (Houston) were sampled. Engineers in

those areas were asked to select about a dozen representative bridge sites

in their districts and provide general information by filling out specially

developed questionnaires. Personal opinions and experiences with the pave­

ment-bridge interface problems were exchanged through informal discussions

between engineers and researchers.

The overall riding quality of each site was evaluated subjectively by

SDHPT engineers and was categorized into either "good" or "bad" subgroups.

Based on such information, several locations of interest; i.e., those with

either typical or special design features or those in quite good or quite

bad condition, were chosen in each district for road surface profile meas­

urements. Roughness p~tterns were identified for further analysis of their

potential for inducing dynamic vehicular tire forces.

QUESTIONNAIRE

Based on the literature review of roughness problems at bridge approach­

es, two questionnaires were designed to obtain data which might enable objec­

tive analysis of approach problems. Questionnaire A (Fig 3.l), which was a

form listing general information about site conditions and history of bridge

and pavement performance, was developed and used in District 14. Initial

27

Page 36: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

28

BRIOOE "BUMP" CHECK LIST A

Dist. No. __________ _ Highway ___________ _

Location _____________________________________________________ __

lnservice Date: ________________________________________________ ___

Traffic Description:: % Trucks _________________ _

No. of Bents ---------- Span Lengths __________ _

Type of Footing: ______________________ _

Bridge Deck Description: ______________________________________ _

App,roach Slab: ______________________________ _

Joint Connection Type: _________________________________________ ___

Fill: _____________________________ _

Height of Fill: ___________________________ _

Fill or Cut Soil, Description: ________________________________ _

Soil Borings Available __________________________ _

Roadway Pavement Type __ ..=J..:,:R=:CP::..J!'-=C::.R:.,:C;:..PL..:,!FP:....:..L!..=O..=t:.:,he::..::r==--____________ _

Maintenance Performed.

Date ________________ _ Description _______________ _

Date ________________ _ Description __________________ _

Date ____________ _ Description __________ _

Resident Engr. During Construction ________________ _

Comments ___ --------________________________________ _

Ma1nt. Engr./Foreman _______________________ _

Comments ______________________________________________ __

Fig 3.1. Questionnaire A

Page 37: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

29

experience with this format indicated the need for more detailed information,

and Questionnaire B (Fig 3.2) was thus developed for use in Districts 15,

5, and 12. Information on representative bridge sites was hence collected so

that both successful and unsuccessful practices ,could be evaluated.

DISTRICT 14 (AUSTIN) SITES

Table 3.1 summarizes basic information about selected bridges in Dis­

trict 14. All the bridges have asphaltic concrete pavements on the adjacent

roadways. Settlement in the fill material on the bridge approaches appeared

to be the most prevalent cause of roughness problems. Drilled shafts were

commonly adopted to support bridges; spread footings were used only with low

fills (e.g., 5 feet). Approach slabs are seldom used in this area because

of the difficulties in maintenance, especially where swelling clay is in­

volved. Heavy and light traffic are observed in both subgroups.

The following observations seem to indicate that many problems are re­

lated to bridge age, depth of fill, and quality of backfill materials:

(1) All the problem sites have been in service less than 10 years while

all the sites in good condition have been in service for more than

10 years. Two of the four sites in good condition have been under

traffic for more than 20 years.

(2)

(3)

Four out of five problem sites have fill heights of more than 15

feet (4.5 m) while only one out of four in the good subgroup has a

fill above that height.

Clayey fill material was used for all the problem sites while three

out of four sites in good condition were built on rock or certain

other stable material. The only site with high PI fill in the good

subgroup had very goo~ backfill material. The relatively low fill

Page 38: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

30

I :.

BRIroE "BUMP" CHECKLIST B

Dist. No. __________ _ Highway __________ _

Location ------------------------------------1 • Bridge Approach Condition: good bad - -2. Roadway Pavement Type. _JRCP _CRCP _ACP _Other _____ _

J. Bridge:

Function. _for grade separation _for crossing major river

_other ________________________ _

Type of Footing: ____________________ _

Bridge Deck Description : ______________________ _

Joint Connection Type : ____________________________ _

4. Climatic Condition: ------------------------------------s. Traffic Description. Artr

% Truck

Speed Limit ______________ _

6. Abutment Types retaining wall abutment (closed type)

_stub or shelf type

_open column or spill-through type

_other ______________________________ _

7. Embankment Slope Stability Experience and Treatment

Slide :---.Jes _no Description;....: _________________ _

Sufficient Drainage :-yes _no

Asphaltic Membrane for Stabilization :-yes _no

if yes. ~envelope type _buried type _surface type

(Cont:inued~

Fig 3.2. Questionnaire B.

Page 39: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Stabilization Berm: --yes _no

Benching of Sloping Ground:--yes _no

Other Treatment: ____________________________________________ __

8. Embankment Material:

Fill or Cut Soil, Description: _______________________________ _

Soil Boring Available: ______________________________________ _

Height of Fill: _____________________ _

Swelling Clay: ---yes _no. treatment: ________________________ _

9. Backfill Material:

Description: ________________________________________________ _

Lime or Cement Stabilization: _______________________________ _

Other Treatment: ___________________________________________ __

10. Foundation Material:

Description: _______________________________________________ _

Boring Available: __________________________ _

Vertical Sand Drain: --yes _no

if yes, spacing ________________ _

method of installation ____________________________ _

Removal of Bad Material:_none _dredging _displacement

Other Treatment: ____________________________________________ _

11. Construction History:

Date of Start of Emabnkment Constructlon: ____________ _

Date of End of Embankment Construction: -------------------------Waiting Period: Inservice Date: -------------

(Continued)

Fig 3.2. Continued

31

Page 40: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

32

12. Compaction:

Specification Used: __________________________________________ _

Moisture Content Controls ___________________________________ __

Lift Thickness Controls ___________________ _

Type of Equipment Used: ____________________ _

Dry Density Requirement: __________________________ ___

Comment: ----------------------------------13. Special Design:

Approach Slab ~es ___ no

Other:~ _______________________________ ___

Comment: _______________________________________ ___

14. Maintenance Performed:

Date

Date

Date

Date

Description ___________ _

Description _________ _

Description ___________ _

Description ________________ _

Difficulties Encountered: ________________________________ __

Comment: ________________________________________________ ___

Resident Engineer During Construction _________________ __

Comments _________________________________ _

Maintenance Englneer/Foreman ________________________ __

Comments ___ ----------------------------____________________ _

District Contact Man _________________________ _

Fig 3.2. Continued

Page 41: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

TABLE 3.1. BRIDGE INFORMATION, DISTRICT 14

AUSTIN, TEXAS

Condition

Location

Pavement Type

Bridge Type

Bridge Function

Type of Support

Joint Type

ADT (1973)

% Truck

Height of Fill (ft.}

F11l Matedal

Backfill Material

lad

US 290 over !!KT RR

AC1'

PC

Grade separation

Drilled shafts

11%

8,33Q

6.7

20

Yellow clay

Years in Service (to 19J5} 8

Maintenance Performed Patching and leveling

Approach Slab Yes

Bote Premix patch over approach. slabs

lad

Loop 427 over Mustang Creek

AC1'

Simple P..C

River crossing

Drilled shafts

F1%

10

Righ PI yellolo1 clay

Highly plastic material

3

Leveling up

No

Lime 6" sub grade

\.

Bad

US 1835 over Loop 343

ACP

PC

Grade separation

Drilled shafts

Open

15,680

17.5

15

Yellow clay

9

Leveling \Jp bridge ends

No

Settle1!lent observed

33

Page 42: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

34

TABLE 3.1. (Continued)

Condition lad lad Bad

tDcat1011 US 183S aver 11S 290 over IB 35 over lollY Creek. Loop 360S Chandler Creek

Pa~t Type AtP ACP ACP

.ridge Type PC PC Si1llPle RC

addge Function liver Grade lUver croning .eparation crossing

Type of Support Drilled Drilled Spread ahafts .hAfts footings

Joint Type 71:z 71Jr. F1Jr.

.AM (1913) 16,010 24,45<1 19.,350

:: Truck 16.1 5.3 11.6.

Hdght of Fill (ft.) 24 1.5 .5

Fill Katerial tellow Clay Rock. clay

Backfill Material Granular sate-rial

tears in Service (to 19]51 9 6 40

Kaintenance Pe-rformed Patching Bot m1Jr. flddse ends overlay

Approach. Slab 110 .0 Mo

Iote Settlement Settlement oll.ened ob.e~d

Page 43: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

35

TABLE 3.1. (Continued)

Condition Good Good Good

Location S'B 29 over San US 290 over SH 71 over Cabrid liver MPRR Bie Creek..

:rave_nt Type ACP ACP ACP

Bridge Type Continuous PC Simple RC I-bUlll

Bridge 1!"UIlct:l.on f..1ver Grade liver crossing separation crossing

Type of Support Drilled Drilled Drilled shafts shafts shafts & spread footing

Joint Type Open Fix Fix

AM' (1973) 1,390 35,600 2,690

% Truck 9.0 3.4 6,8

Height of Fill 10 20 8.:t

Fill Material I1gh PI Stable lock ... terial _terial

Backfill Haterial Base .. terial

Year. in Service {to 19]5} 16 14 28

Maintenance Performed !fo patching in No patching la.t 3 years a1nce 1970

AppToach Slab 110 110 110

lote

Page 44: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

and light traffic of that section might also have helped decrease

the potential for creating surface irregularities.

DISTRICT 15 (SAN ANTONIO) SITES

36

Generally speaking, the sites in District 15 exhibit problems which are

different from those in District 14. Since the soil containing montmorillo­

nite and illite of high swelling potential is dominant in this district, the

roughness problems generally result from large volume changes in the expan­

sive soils, rather than settlements as encountered in District 14.

From informal discussions with engineering personnel and from an on-site

inspection of the sites in San Antonio, it was revealed that the joint be­

tween adjacent rigid pavements and one bridge approach slab had opened as

much as 4 inches (Fig 3.3). The gap enabled water on the pavement surface

to penetrate into the fill material and increase the potential for swelling.

At another site, pressure of the expansive soil had moved the abutment and

caused the rocker supporting the bridge to tilt (Fig 3.4). The curb near this

bridge end was also lifted about 3 inches (Fig 3.5). The vertical curvature

in the pavement surface can be easily seen by referencing the lane markers

and the curb to the guardrail shown in the background.

Engineers in District 15 feel that approach slabs are necessary, but

that special designs which keep moisture on the roadway surface from pene­

trating into the fill material are needed. Finger joints with a lateral

drain have been effective at several sites (Fig 3.6) and the expansion joint

has been eliminated between the pavement and the approach slab with good re­

sults at other locations (Fig 3.7). Granular backfill materials have been

used for drainage at some sites.

Page 45: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Fig 3.3. Gap between the approach slab and the pavement, IH 37 over Fair Ave., San Antonio. Texas.

37

Page 46: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

49 62

Fig 3.4. Tilted rocker, Southcross St. over IH 37, San Antonio, Texas.

.38

Page 47: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Fig 3.5. Lifted curb, Southcross St. over IH 37) San Antonio) Texas.

Fig 3.6. Finger joint and drain, IH 10 over H. to1. lilhite Blvd., San Antonio, Texas.

39

Page 48: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Fig 3.7. Joint deletion between the pavement and the approach slab, IH 37 over Durango St., San Antonio, Texas.

40

Page 49: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Information about bridge sites in the rural areas of District 15 is

summarized in Table 3.2. The sites are all on IH 10 east of San Antonio

and have asphaltic concrete pavements on the approach roadways.

The following observations are made based upon on-site visits and col­

lected data (see Table 3.2):

41

(1) All sites are located within 30 miles of each other on the same

highway. The concentration of the sampled sites makes the traffic

volume, several design factors, and, sometimes, geological condi­

tions considerably uniform. No bridges have been in service more

than 10 years; most of them are only 4 years old. Little mainte­

nance work has been applied up to this point.

(2) Washed river gravel was used as the backfill at all locations.

Though swelling clay is common, the riprapped embankment slopes

generally exhibit good stability. At one site, the approach slabs

were removed due to excessive heaving.

(3) The use of stub-type abutments, deep foundations, approach slabs,

and Hyster compactors are common practice in this district. All

three sites in the bad subgroup incorporate lime stabilized fill

to a depth of 6 inches. The original foundation materials in the

bad subgroup are all clays while those in the good classification

are sand or sandy clay.

DISTRICT 5 (LUBBOCK) SITES

Information about selected bridre sites in District 5 is summarized in

Table 3.3 In this area, four sections were designated as having good ride

quality and two as having bad. Some observations can be made as follows:

Page 50: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

TABLE 3.2. BRIDGE INFORMATION, DISTRICT 15

SAN ANTONIO, TEXAS

Condition lad lad

Location 11£ 10E over IE 10E over 1M 725 Gu.ada11.1pe River

Milepost 604.4 605.1

Pavement Type ACP ACP

Iridge Type ItC

Bridge Function Grade :aiver Separation CrOSSing

Type of Support Drilled shafts Drilled s~afts with bells vith bells

Joint 'type Open Open & Hn~e.r

ADT (1974) 9.000 8.610

% Truck 15 15

Abutment Type Stub Stub

Embankment Slope Good Good Stability Stability Stability

. Height of Fill (ft.) 10 13-17

Fill Material Clay cliche Black sandy 11' ave 1 clay

. Backfill Material Washed river W .. shed river Iravel lrave!

Foundation ~Aterial Yellov & Itlue shaley lray clay clay

Svelling Clay Yes

Years 10 Service 9 9 (to 1976)

Compaction Equipment Ryster By.ter

Malotenance Performed Hone lIone

Approach Sla& Yea (VBL ret'lOVt!d) Yes

1I0te time 6" .ubarade L1IIe 6" subgrade

42

lad

III 10 over PlUIII Creek

631.8

ACP

River Crossine

Open

6,770

15

Stub

Good Stability

22-28

Gray sandy clay

Washed river gravel

Blue clay

4

Ilys"er

1I0ne

Yes

Lime 6" sub grade

Page 51: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

TABLE 3.2. (Continued)

Condition

Location

Milepost

Pavement Type

Bridge Type

Bridge Function

Type of Support

Joint Type

AD! (1974)

ZTruck

Abutment Type

Embankment Slope Stability

Beight of Fill (ft)

Fill Material

Backfill ~~teria1

Foundation Material

Swelling Clay

Years in Service (to 1916}

Compaction Equipment

Maintenance Performed

Approach Slab

Bote

Good

IB. 10E over Allen Creek

623.2

ACP

ac

River crossing

Drilled shafts with. bells

Open

7,750

15

Stub

Good Stability

10

Cray landy clay

Washed river gravel

Bllle sandy clay

110

4

IIyster

ICone

Y ..

Good

m 10E over lash Creek

619 .• 2

ACP

ItC

River crossing

Cene:rete piles

Open

7,670

15

Stub

Good Stability

15-20

Red undy clay " gravel

lI'ashed river gravel

Cray & brown sand

10

4

Ilyater

Bone

Yas

Good

m lOll' Over San Marces River

626.9

ACP

River crossing

Steel B piles

Open

6,770

15

Stub

Good Stability

20

Gray sandy clay

lo.'ashed river gravel

Brown " gray sandy clay

4

lyater

Rone

Yas

43

Page 52: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

TABLE 3.3. BRIDGE INFORMATION, DISTRICT 5

LUBBOCK, TEXAS

Condition

Pavement type

Bridge type

Bridge function

Type of Support

Bridge deck condition

ADT (1977)

% truck

Speed limit (mph)

Abutment type

Embankment slope stability

Beight of fill (ft)

Swelling clay

Backfill material

Years in service (to 1978)

Compaction Equipment

Kaintenance performed

Approach slab

IIcte

Spur 326 over AT & SF RR

Good

ACP

Continuous steel I beam

Grade separation

Drilled shafts

Linseed 011 treatment

8080

10

30

Stub

Good stability

25

No

Sandy loam

23

Pneuma tic and sheepsfoot

Bole patching

tes

Nev overlay on approacb slabs

US 87 at 98th St.

Good

Simple PC girder

Grade separation

Drilled shafts

Linseed 011 treatment

9960

10

55

Stub

Riprap moved

18

Yes

Sandy 10a.'11

8

Hyster and pueumatic

Rone

tes

Approach slabs rnaoved

US 84 at Brazos River (Southbound)

Good

Concrete box girder

River crossing

Drilled shafts

Asphalt overlay

1860

13

55

Stub

Good stability

No

Sandy loam

so

No special equipment

Overlay

tes

Old bridge over Brazos

44

Page 53: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Condition

Pavement type

Bridge typ~

Bridge function

Type of support

Bridge deck condition

AM' (1977)

% truck

Speed limit (mph)

Abutment type

Embankment slope stability

Beight of fill (ft)

Swelling clay

Backfill material

Years in service (to 1978)

Compaction equipment

Maintenance perfo~d

Approach dab

Ilote

TABLE 3.3. (Continued)

US B4 at Brazos River (northbound)

Good

ACP

Concrete slab (pan form)

River crossing

Drilled shafts

Asphalt overlay

1860

13

55

Stub

Cood stabili ty

No

Sandy loam

20

Overlay

Yes

Rev bridge over Brazos

FH 1065 at Los Linguish Creek

Bad

Tvo-course sur­face treatment

Concrete slab (simple span)

River crossing

Concrete piles

Rough

150

9.7

55

Stub

Good stabi~ity

9

Yes

Sandy gravel

27

Sheepsfoot and pneumatic

Approach slabs removed

Loop 289 at US 87 South

Bad

ACP

Concrete slab (arch shape)

Grade separation

Drilled 'shafts

Epoxy overlay

21020

10.9

55

5.tub

Good stability

19

No

Sandy loam

13

Byster and pnewnatic

Epoxy overlay and asphalt patching

Yes

Epoxy is _arin~ off

45

Page 54: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

46

(1) It is interesting to note that the bridge surface condition has a

definite correlation with the subjective ride quality assessment.

Pavement surface distress has been corrected to some exte~t through

various types of surface treatment. The decks of good bridges were

virtually all treated either by linseed oil or asphalt. One bad

bridge had no surface treatment at all, while the other had one

epoxy overlay, which was wearing rapidly.

(2) Average daily traffic counts on the two bad sections were both the

highest (21,020) and the lowest (150), indicating that traffic

cannot be identified as a critical factor. A similar conclusion

can be drawn for bridge function, bridge type, and bridge age.

That is, the number of bridges examined in this analysis is too

small to imply, for example, that approach sufrace conditions for

bridges at grade separation are less troublesome than for those at

river crossingB.

(3) Use of the stub-type abutment, which is believed to be the least

likely to cause roughness problems, is common practice in Lubbock.

Sandy loam or sandy gravel, with no special stabilization, was gen­

erally used as the backfill material for both good and bad sub­

groups.

(4) The predominant soil in this area is windblown cover sand. Swell­

ing clay is encountered in some locations but has not been identi­

fied as a predominant problem. Approach slabs are commonly used

and serve well in general, although in some sections of swelling

clay they have been removed because of excessive movement.

(5) Deep foundations, either piles or drilled shafts, are utilized

for all bridges considered. Embankment slopes, protected by

Page 55: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

47

concrete riprap, are quite stable for most cases. Asphalt concrete

pavement is used on all sampled roadways with the exception of one

farm-to-market road which has a two-course surface treatment.

(6) The approach performance has no general relationship with height

of fill. A 25-foot high embankme,nt falls into the good subgroup,

while a bad case has a fill of only 9 feet.

(1) Lubbock is located in northwestern Texas and has an elevation of

above 3000 feet. The average temperature during the winter months

is about 40°F. Extended periods of subfreezing temperatures are

rare over the whole State of Texas, and therefore, the problem

of frost action is not critical.

DISTRICT 12 (HOUSTON) SITES

Basic information about the bridge sites in this district is tabulated

in Table 3.4. Due to insufficiency of data, this table is not so detailed

as Tables 3.2 and 3.3. Nevertheless, based on the summary table and on-site

inspection, overall observations can be made as follows:

Page 56: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

TABLE 3.4. BRIDGE INFOPY~TION, DISTRICT 12

HOUS TON, TEXAS

Condition

Pavement type

Bridge type

Bridge function

Type of support

AD! (1977)

Abutment type

Approach slab

Condition

Pavement type

Bridge type

Bridge function

Type of support

ADT (1977)

Abutment type

Approach slab

Condition

Pavement type

Bridge type

Bridge function

Type of support

ADT (1977)

Abutment type

Approach slab

lH 610 (S. Loop) at Calais St.

Good

CRCP

Continuous concrete slab

Grade separation

Drilled shafts

129,180

Stub

Yes

IH 45 at S. Belt

Bad

JPCP

Simple PC

Grade separation

Piles

81,390

Stub

Yes

IH 10 at W. Belt

Bad

JRCP

Simple PC

Grade separation

Piles

132,210

Stub

Yes

IH 610 (S. Loop) at SH 288

Good

eReP

Continuous con­crete slab

Grade separation

Drilled shaf ts

129,180

Stub

Yes

sa 225 at Shell over;,ass

Bad

JRCP

Simple PC

Grade separation

Piles

35,810

Stub

Yes

IH 610 (N. Loop) at HB & ! RR

Bad

JRCP

Sblple PC

Grade separation

Drilled shafts

73,550

Stub

Yes

IH 610 (N. Loop) at McCarty Rd.

Good

JRCP

Simple PC

Grade separation

Drilled shafts

73,550

Stub

Yes

SH 225 at Scar-borough Lane

Bad

JRCP

Simple PC

Grade separation

Piles

74,790

Stub

Yes

48

Page 57: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

49

(1) Eight bridge sites were selected and five of those were categorized

as bad. The pavement type is rigid on all sections (either CRCP or

JRCP). Data suggest that CRCP provides better riding quality,

because the two sections with CRCP ar~ in the "good" classification.

(2) The use of approach slabs, stub-type abutments, and deep foundations

(piles or drilled shafts) is common to all. All bridges under

study wer~ constructed for grade separations. The common height of

fill ranges from 15 to 20 feet. Traffic is heavy for both subgroups.

Since Houston is a port, a higher percentage of trucks (17 percent)

is present. The speed limit is 55 mph, and in some sites there is

a posted minimum speed of 40 mph.

(3) The predominant soil in this area is Beaumont clay. Hence found a-

tion and embankment materials are generally not good. High PI

fills are sometimes used because only small quantities of sandy

material are available and the quality is not remarkably better

than the clay.

(4) The normal annual rainfall here is about 46 inches. A large por-

tion of the rainfall occurs within short periods of time, providing

an important source of moisture variations in subsoils. The rather

frequent wetting-drying cycle, together with the Beaumont clay,

easily induces soil volume changes. This is likely one critical

reason why movement of the approach slab was observed in almost

every case. Virtually all approach slabs, though designed in

different ways, have translated up or down relative to the bridge

abutments. Envelope-type asphaltic membranes used with success ,

for stabilization on the Gulf Freeway (Ref 28) were not applied

to bridge sites under examination in this study.

Page 58: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

50

(5) All the bridges were constructed during the 1960s. Modern compac­

tion equipment, such as the sheepsfoot and pneumatic-tired rollers,

were extensively employed during construction. Sandy material,

stabilized by lime/cement, was used in abutment backfilling.

Presumably such procedures would improve bridge approach perform-

ance.

ROUGHNESS PATTERNS

The road profile of each section in the four districts was measured

using the Surface Dynamics Profilometer. Profile data thus obtained include

the whole bridge and extend on both ends about 200 feet from the structure.

After examining all the in-hand road profiles, some typical roughness

patterns were identified and are schematically illustrated in Figs 3.8 through

3.12. These patterns include the following components:

(1) roughness on the bridge -

(a) camber or sag formed by bridge span (Fig 3.8),

(b) opening at the bridge joints (Figs 3.9,3.12), and

(c) discontinuity between the bridge and the pavement/

approach slab (Figs 3.8, 3.10, 3.11, 3.12);

(2) roughness in the bridge approach area -

(a) long wave profile (Fig 3.8),

(b) tilted or distorted approach slab (Figs 3.10,

3.11, 3.12),

(c) gap between the approach slab and the pavement

(Figs 3.10, 3.11),

(d) hump or sag near bridge end (FifS 3.8, 3.9), and

(e) gap at pavement joint (Figs 3.10, 3.12).

Page 59: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

1.00 -. c: -..4 -'" ,t:: r...

-..4 Q) 0.00 :I: Q)

.-4 -..4 \w 0

"" ~ -1.00

0 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285300 t Horizontal Distance (ft.)

TRAFFI~ I ( BRIDGE .. I.. PAVEMRNT

A. Sag formed by each span C. Hump near bridge end

B. Discontinuity' at bridp.e-pavement interface D. Long waves on bridp.e approach

Fig 3.ff. Bridge profile, ~ 1065 over Los l.inruish Creek (Lubbock), end of brid~e. . VI

'""'

Page 60: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

2.00i~--------------------------------------------------------------~

-c: ...t -u

1.00

~ 0.001 .. ...t I ' ~ J = ' u-N ".,-.,. r

U

~ .. 1.00 ...t ~ o J.I

Po. .. 2.00

o 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240255 270285 300 Horizontal Distance (ft.)

TRAFFIC

I.. BRIDGE

A. Discontinuity between approach slab and bridp.e

B. Open joint between bridge decks

C. Sag near bridge end

....

Fig 3.9. Bridge profile, Loop 289 over US 87 South (Lubbock), start of bridge. VI NI

Page 61: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

-t: '" -.u ..c C(j

"r'4

3.00 ..

... A

2.00

~ cu

.-I .... 1M o ~ o,oo'~~~~~~~===:~;f~~--~--=-~~~~~~~~==~~::~~~~:)~~~~ \:X-? " V'I } ::"'t ~ ft <- ~ ~I

1.00

c

C ...-1.,1

• "I -1.00 b 15 3'0 4'5 90 105 120 135 150 165 180 195 210 225 240 255 270285 300

Horizontal Distance (ft.)

TRAFFIC --, -- BRIDGE ................

A. Gap at pavement joint

B. Tilted or distorted approach slab

C. Joint between approach slab and brid~e

D. Joint between approach slab and pavement

Fig 3.10. Bridge Profile, SH 225 over Scarborough Lane (Houston). VI W

Page 62: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

1.00

-• c: ~ -..., .c: 00

~ 0.00 tr: III

..-4 ~ loW 0 ... p..

-1.00 0 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225240 255 270 285 300

Horizontal Distance (ft.)

TRAFFIC ~ W~ WJ1J SLAB I.. BRIDGE ... 1 SLAB

A.

B.

C.

Discontinuity between approach slab and pavement

Distorted approach slab

Discontinuity bet,.,een approach slab and bridy.e

Fig 3.11, Brid~e profile, South Loop over Calais Street (Houston). VI 4:'-

Page 63: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

- 1.00 . c:I

'" -.u ,J: bO .~

G.I ::r: G.I 0.00 ..... '" "-t 0 ~

Po.

-1.00 t-I --r--~---r-"""T""-~-r-----r---r--~-~---r---r---r----r-------r---r---r---.....------'r------4 o 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270285300

TRAFFIC If Horizontal Distance (ft.)

-I WA BRIDGE .. I SLAB

A. Openinr, between bridge decks

B. Tilted approach slab

c. Discontinuity between approach slab and bridge

D. Gap at pavement joint

Fig 3.12. Bridge profile, IH 10 over West Belt (Houston), end of bridre. \I' \I'

Page 64: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

56

The potential for those patterns to produce dynamic vehicular tire forces is

assessed in later sections.

Page 65: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

57

CHAPTER 4. ANALYSIS OF DYNAMIC WHEEL LOADING

As noted earlier, roughness in the vicinity of the pavement-bridge

interface may lower the riding quality of the roadway and induce excessively

large dynamic loads. In this study, the Surface Dynamics Profi1ometer was

the fundamental tool used to measure and record longitudinal road profiles

in each wheel path and thus provide the basic data for assessing riding

quality. A computer simulation model called DYMOL was used to predict the

magnitude of dynamic vehicular tire forces created by specific types of

vehicles moving at specified velocities over the defined profile. Critical

types of roughness encountered in Austin, Houston, San Antonio, and Lubbock

were identified in each section and the interaction of vehicles with these

roughness patterns was analysed. However, certain inherent characteristics

of the profilometer may distort road profile measurements. Therefore the

effect of this distortion was analyzed before using the profilometer measured

profile records for DYMOL simulations.

SURFACE DYNAMICS PROFILOMETER

The profilometer (Fig 4.1) is a specially instrumented two-axle van-type

vehicle which measures variations in the elevation of each wheel path along

the roadway. The profile is detected by two small sensor (feeler) wheels

at the center of the test vehicle. The relative vertical movement between

the sensor wheel and the vehicle body is measured by a linear potentiometer.

An accelerometer, mounted above each potentiometer, senses the vertical

acceleration of the vehicle body at these locations. An analog computer in

the vehicle immediately double integrates the acceleration to produce

vertical displacements. These displacements, combined with the movement

Page 66: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

measured by the potentiometers, yield an estimation of the roadway profile

in each whee1path. The results are written onto a 4-track analog tape, and

a strip chart depicting the profile is produced. Interested readers are

ANALOG COMPUTATION

r-'---=---;::J.--ACCELEROMETER

w

Fig 4.1. Principle of the high speed Surface Dynamics Profi1ometer (from Ref 9).

referred to the related reports for details and some inherent problems

(Ref 29-3]).

DYMOL

58

DYMOL is a FORTRAN program developed at the Center for Highway Research

at The University of Texas at Austin (Ref 32). It simulates the behavior of

vehicles interacting with a road profile in each wheel path and can be used

to predict the magnitude, duration, and location of the induced dynamic wheel

loads.

The DYMOL program can be used to simulate five typical types of vehicles,

as shown in Fig 4.2. Specific vehicle configurations, including weights and

axle spacings, can be selected by the user. Each vehicle model consists of a

series of masses, springs, and dashpots which are connected with one another • •

In a statistically designed validation program, the simulation model predic-

ted maximum dynamic wheel forces within about + 10 percent of measured

values (Ref 32).

Page 67: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

59

Closs DesiO notion

J 2-0

II 2S-1

III 3-A

IV 2S-2

V 3S-2

Fig 4.2. Five representative types of vehicles (from Ref 32).

_.---. --- -.-• 0- ~ _. __ •

Page 68: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

60

In this study, the vehicle was assumed to be initially at rest on a

level surface with elevation equal to that of the start of the pavement

section under analysis. Vehicles were "driven" at specified velocities over

the section profile. Output included listings and plots of dynamic loads

applied to the surface by the moving wheels of the modeled vehicle.

Analyses of Profilometer Measurement Capability

The Profilometer-measured road profile data are sometimes distorted

due to slight phase shifting characteristics. In order to examine the

effect of this distortion, rod-and-level measurements of the roadway surface

profile at three bridge sites were made to compare with those measured by

the profilometer. These sites were (1) Loop 427 over Mustang Creek, Taylor,

(2) IH 10 over Plum Creek, San Antonio, and (3) Test Section No.8, Austin.

Emphasis was placed on the bridge and areas where more intensive readings

were made.

The measurements were plotted to scale, and after examining the general

trend of the whole section, the grade was corrected to a straight, sloping

line. This slope was subtracted from the measured elevations and the

results were compared with the profilometer-measured profiles.

Observations and Explanations

Though the rod-and-level measurements and the profilometer measured

profile did not agree exactly, it was found that the high-frequency (short

wavelength) bumps and dips were represented quite consistently in both

profiles. The phenomenon can be explained by the following facts:

(1) Vertical curves in an actual profile cannot be adequately

approximated by a straight line.

Page 69: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

61

(2) The dynamic response of the profilometer filtering cannot be

corrected exactly by a simple slope adjustment technique.

(3) Most importantly, distortion of the profilometer measurements is

more apparent in long wavelength than in short wavelength rough-

ness, due to the inherent characteristics of the instrumentation.

As a result, the profilometer can measure high frequency roughness on

the roadway with acceptable accuracy and with great consistency.

Vehicular Response to Long-Wave Profile Roughness

It is understandable that a vehicle will respond differently to road

profile waves of the same amplitude but of different wavelength. The

dynamic loads produced by a wave 10 feet long and of I-inch amplitude will

be much greater than those loads resulting from a lOO-foot wave of the same

amplitude. Since the profilometer is able to record short wavelength rough-

ness fairly accurately but distorts the long waves, it is important to inves-

tigate the relative effects of different wavelengths on dynamic wheel loads

which result from a wheel interacting with a rough road profile. If the

effects of the profilometer distortion are not significant, the profilometer

records can be used as input to DYMOL, and an adequate analysis of dynamic

loading by traffic at the pavement-bridge interface can be made.

Filtering and Phase-Shift Correction

Several techniques for obtaining a corrected profile record that repre-

sents the actual roadway section have been used. None of these has yet been

wholly successful. However a profile analysis program was utilized to correct

the phase shift by moving long waves various distances computed on the basis

of the frequency response curve of the profilometer.

Page 70: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

62

Comparison of the Dynamic Loads

The original profilometer profile of a test section and a phase-shift

corrected profile are plotted in Fig 4.3. It can be observed that the short

wavelength bumps and dips agree while the long waves disagree greatly. For

predicting dynamic wheel loads, a simulated two-axle dump truck was "driven"

at 55 mph on both the measured and the adjusted profile. In Fig 4.4, the

light solid line represents the dynamic loads produced by the measured

profile, and the dark dotted line, those produced by the adjusted profile.

Most of the time, discrepancies between the predicted dynamic loads from the

two profiles are less than 10 percent of the static weight. The maximum

discrepancies do not exceed 15 percent of the static weight. Considering

that the simulation model was found to predict dynamic wheel forces within

about 10 percent in the validation experiments of the DYMOL program, errors

of this range are quite acceptable.

It is concluded, therefore, that the errors created by the distorted

long waves are within a tolerable range. And the DYMOL program can be a

satisfactory tool for predicting dynamic wheel loads that result from profiles

containing long-wave roughness even though the profilometer distorts these

waves somewhat.

DATA ANALYSIS AND RESULT PRESENTATION

In this study, three representative types of vehicles. a two-axle dump

truck (2-D). a three-axle concrete mixer (3-A), and a five-axle tractor

trailer (3S-2). were modeled at speeds of 40 and 55 mph. Two general types

of dynamic loading oscillations were observed. These include high frequency

oscillations. with frequencies from 8 to 12 Hz due to movements of the

unsprung mass of the vehicle undercarriage, and low frequency oscillations,

Page 71: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

{

z

... C') II:

'.50

I.eo

o.!oO

~-..... ~~-

.t.!or.

1--3.1 Hz I

Uncorrected

• BRIDGE

r

' ........ ~./ " " 1 J :

, •• lof t " -.,. "LO' Nt'. o 205 ,do !ido eoo ______ u IO,:i. _ u ___ I~Q::L. 140::' ,do:! Ido!l

Fig 4.3. Phase-shift corrected and uncorrected profile,l SH 71 over Bee Creek, Slf. of Austin.

CI'\ W

Page 72: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

-• ~ '-'"

~ 0

...:I

('

\2000 r 8000

·000

I"'ILI 2

11000

.000

~('cr r

_:J I VLM:l. .. f .• .(1.,; ar", Ut.JIU""' JU" ~ _

R~ll ~US~ S'I~ SUSP 8R"P . liRE 5TI' I 535 LBS 5.0 4000 LBS

.,2~OINT3~8~lbeSAVERaCpoO' PRO'?~PO LSS

_ • ;',;).00 MetH I IRE. DR"P

2·00 2.00

Uncorrected 3.1 Hr-J ~ ~~~ "'----'corrected

IAy,.1 . c~:---------~.~i~~:l----------~.rn~~e----------'"rl'----------'~;o"'ii;;r;~~iS"","CE-'~r.~;-----;i,,---------,t.,1!C~~'-~~~'-600 e~ d HORlll'NTR~ ott. .d j~\lo \40t J 29"l1li"76 ~lC'·NO.1 1600 I !lOll .

Fig 4.4. Dynamic wheel loads resulting from phase-sh1ft corrected and uncorrected profile, SH 71 over Bee Creek, SW. of Aust1n.

0\ ~ ...

Page 73: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

with frequencies from about 1.5 to 3 Hz associated with movements of the

sprung mass of the vehicle. Dynamic wheel loads exercised on the road

surface are the combination of these two types of oscillations.

65

To examine the dynamic wheel loads which result from vehicles traversing

the bridge-pavement interface areas, high and low frequency oscillations are

treated separately. The amplitudes of the wheel force curves for both

frequencies are measured and expressed as percentages of the static weight of

the axle considered. A graphical presentation is designed to show the load

variations by the thickness of a line. Class limits for categories of wheel

force amplitude are set at 0-20, 20-40, 40-60, 60-80, and more than 80

percent of the static weight. If amplitudes of wheel force curves vary less

than 20 percent from the static weight, no line is plotted. A line of

one-unit thickness is used for 20-40 percent, two-unit for 40-60 percent,

three-unit for 60-80 percent, and four-unit for 80 percent or more. The

profile of the roadway over which the vehicle travels is attached at the top

of the graph. The seriousness of the dynamic loading over each section can

be judged by the overall "blackness" of the graph.

Graphical analysis of simulation results is presented in Figs A4.1

through A4.35, in the appendix. Twenty-one bridge sites including three in

Austin, four in San Antonio, six in Lubbock, and eight in Houston, are

presented. The length of profile for each case is' approximately 300 feet.

If the bridge is long enough, the start of the bridge and the end of the

bridge are shown separately. Otherwise the entire bridge is presented in

one figure. As mentioned earlier, the high and low frequency load variations

of each section are shown in two graphs, noted as A and B. The types of

vehicles are shown on the left. "V" is used to designate velocity in mph,

Page 74: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

66

and "An indicates the axle number of the simulated vehicle. The location of

the peak loading, as directly read from the DYMOL output, is identified with

a small triangle, and its magnitude is recorded as a percentage of the

static weight on the far right end. The shaded area on each graph represents

the range appreciably affected by dynamic vehicular loading. Significance

of the shaded area is discussed later.

Table 4.1 provides an overview of roughness patterns and induced dynamic

loads for the selected sites. High and low-frequency dynamic loads are again

separated. An X indicates the load classification when the dynamic variations

of the specified amplitude are induced anywhere in the section. The maximum

peak load and the mean peak load for each site are also tabulated as a

percentage of the static weight. The standard deviation is calculated by

where

N I: (X

i-X)2

C1" i-I ---------

X .. i

X ..

N ..

N - 1

the peak load induced by each axle in the section (%),

the mean peak load of the sampled axles (%), and

total number of axles, equal to 20 in this study.·

The next two rows give the values of ~-1C1 and ~-2C1. Assuming the peak loads

induced by different axles are normally distributed, these two numbers are

the approximate values that 84 percent and 98 percent of the induced peak

loads will exceed. For instance, the mean peak load created by the roughness

of the section of PM 1065 over Los Linguish Creek (Lubbock), start of bridge

.(see Fig A4.l3), is 203 percent. The standard deviation is 35 percent. With

Page 75: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Subjective Rating

Site

(Lubbock)

Referenced Figure

Main Roughnesa Pattern

Class --

Amplitudes, o - 20 % of Static 20 - 40 Weight

40 - 60

60 - 80

80+

Haximum P('ak Load, %

~ean !'eak Load ..

I.

Standard Deviation, %

u - la, %

Il - 20, %

TABLE 4.1. ROUGHNESS PATTERNS AND DYNAMIC LOADS

Dad Dad Good Good Dl1d

PH 1065 over PH 1065 over Spur 326 over Spur 326 over Loop 289 over Los Linguiah Los Lingubh AT & SF RR, AT & SF RR, US 87 South, Creek, start Creek, end of start of end of brid~e Rtart of of bridge bridge bridge bridge

A4.13 M.14 M.15 M.16 All. 11

Sag formed SAr. formed by Ipen joints witl Tlltf"d ;01': approach by each sf'lIn ('ach span approach "lab approach "lab "lab and brtdg('

Frequency

Ilil!:h Low IIlph Low III r.h I.ow IIlAiI Low 1111''' J.ow

X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X

294 312 280 211 214

203 210 204 171 181

)'; 44 40 19 18

168 1(,6 164 15R 1('9

In 122 124 139 151

Dad

Loop 289 over US 81 South, end of bridp;e

M.18

Open joint: bddge decks

IItS!:h Low

X X X

X

X X

271

215

34

181

141

\

0---..J

Page 76: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Subjective I.tln~

Site (Lubbock)

Referenced Figure

Main Roughness Pattern

£lass

~ .. "'.d •• '\0 -20 % of Static 20 - 40 Weip,ht 40 _ 60

60 - 80

80+

~Inx imuftl Peak Load, %

~lean resk toad. %

Standard Deviation, %

IJ - la, %

J' - 20, %

Good

US 81 South over 98_t!! St.

M.19

Long wave ."ro­fUe neor brillg.. end

TABLE 4.1.

Good

US 84 oveT 8raz08, old stTucture. staTt of bridge

M.20

Open in/,:, lIt brldgE' . joint

CONTINUED

Good

us fI4 over 8razos, old structure, end of hridge

114. 21

Tilted 81"I"rooch IIlab

Good

US 84 oveT IIT8zos. new structure. start of bridge

AI,. 22

Tilted first 81'"n

FreqlJt'llcy

Good

US 84 over Brazos, new structul'e. end of bridge

114.23

!Ii11conttnul ty: hridj:!e and sp­

lProach slnb

• Utgh Low 1_~'.!~. __ I.()V_I_"~'_~ l--1I1,:'!.. I.ow I IUJ!h Low I X X X X X

X :It X X

X X X

X X X

X X X

264 11,6

180 132

38 R

142 121,

104 116

X X

X X

X

256

161

34

127

93

172

145

110

131

117

x X

X

X

165

145

11

134

123

x X

.1.

0'\ CO

Page 77: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Subjective Rating

Site (Houston)

Referenced Figure

Haln Roullhne88 Pattern

Claaa

Bad

1H 45 over S. Belt, start of bridge

A4.24

TABLE 4.1.

Bad

IH 45 over S. Belt, end of brtdRe

11.4.25

Discontinuity: hrtdlte and lopenlng at approach slab pave_'lt joint

CONTINUED

Bad Bad Bnd Good

SH 225 Shell SH 225 Shell overpass., startloverpas!I, end of bridge of bridge

SH 225 over Scarboroulth J,ane

South Loop over Calais St.

11.4. 26

TUted approach Illab

FreqlJen('y

1\4.21 11.4. 28 A4.29

I.on~ wave on lopenfng at I DiscontinuIty hridge approtl(~h pavement joint approach slab &

pavement

.,..!!.~h I,ow IIlfl;h T,o~_J!.!.~-,~I~_ tow .. ~I.!!'.!~ _. _~lW _I!~.&!, 1.01/ IIlfgh Low I Amplitudes,

% of Statie Weight

o - 20

20 - 40

40 - 60

X

X

X

"0 - 801 X

80+ ( X

tlax illlUm Peak Load, %

tlean Peak Lo.ttl. %

Standard Deviation, %

lJ - la, %

IJ - 2a, %

434

254

91

If,J

12

X

X

X

X

X

X

X

X

X

X

358

233

51,

179

125

X

X

X

X

X

X

X

X

X

X

314

201

32

169

131

X

X

X

X

X

X

X

X

X

351

222

42

lRO

DR

X

X

X

X

X

X

X

X

X

X

449

310

55

255

200

x X

X

X

X

X

X

X

X

X

256

196

30

166

136

x X

X

X

(7\

""

Page 78: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Subje~tive Rating Good

S. Loop over

Site SH 288

(Roullton)

Reference~ Figure /1.4.30

01scont inlli ty: Main Roughness approach slab

Pattern and pavement

ClaS8 IIlgh Low

Amplitudes, % of o - 20 X X

Static 20 - 40 X X Weight

40 - flO X X

60 - 80 X X

80+ X

tlaxilllUIII Peak Load, % 303

Mean Peak 232 Load X

Standard 34 Deviation, %

U-la,% 198

U-Zo,% 164

TABLE 4.1. CONTINUED

Gond Bad Bad

N. Loop over 1M 10 over W. 1M 10 over W. tlcCarty Pod. Belt, start Belt, end of

of brldy.e bridy.e

.M.31 11.4.32 .M.33

Upen1ng betweel upen1n~ betweel Tilted approach slab approach slab

~pproach sll1b nnd b ridj;tC nnd brfdp.E' Freq.uenry

lItr.h 1.0101 II t,'h t.nw Hir.h I.ow

. X X X X X X

X X X X X X X X X X X X

X X X X

X

213 203 239

181 165 192

III 21 25

163 144 161

145 123 1/.2

Bnd

N. Loop over RR, !!tllrt of bridl!;e

11.4.34

TUted approach slab

IUgh Low

X X

X X

X X

X X

X

297

217

39

178

139

Bad

N. Loop over RR, end of brid~e

A4.3S

Tilted apprO<!ch !!lab

IIIgh Low

X X

X X

X X

X X X X

301

180

46

134

Ill!

t. ... /

....., o

Page 79: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

71

the assumption of a normal distribution, 84 percent of the induced peak loads

will be higher than 168 percent of the static axle weight, and 98 percent of

those loads will be higher than 133 percent of the static axle weight.

The section of SH 225 over Scarborough Lane (Houston) is another example.

The major roughness is due to a large opening at a pavement joint. The

induced maximum dynamic peak load for one axle is almost 4.5 times its

static weight. The mean peak load is 310 percent and the standard deviation

is 55 percent. As a result, 84 percent of the dynamic loads are higher than

2.55 times the static weight and about 98 percent of those loads are twice

their static weights.

At this point, it seems worthwhile to emphasize the significance of

approach slabs. There are thirty-five sections, presented in Figs A4.l

through A4.35 respectively, and twenty-eight sections have approach slabs.

Among those twenty-eight about 80 percent (twenty-two sections) have primary

roughness problems related to approach slabs, which are tilted or distorted

or have a gap between the approach slab and the bridge/pavement. As noted

already, the use of approach slabs is common in San Antonio, Lubbock, and

Houston. Great care in choice of design and construction processes may

improve performance in the vicinity of the bridge-pavement interface.

DYNAMIC LOADING INDEX

Though Table 4.1 provides useful information, it is not adequate for

identifying the most critical types of roughness inducing dynamic loads.

For example, the X shows the induced load class, but it does not show where

and by how many axles the loads were created. Therefore, in order to better

quantify the dynamic loading problem, a dynamic load index was developed.

It is the sum of the products of the mean of each load classification and

Page 80: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

72

the number of axles which induce the dynamic load in that classification.

The index includes all dynamic loads within the influence range of the

roughness under consideration. If, for a total of 20 axles, the roughness

creates oscillations with amplitudes less than 20 percent of the static

weight, this index is 10% X 20 = 2.0 (10 percent is the mean of that class­

ification). On the other extreme, if all axles are excited and large loading

oscillations with amplitudes greater than 80 percent are induced, the index

will be 100% X 20 = 20.0, where 100 percent is the assumed mean value of

that classification since the upper bound is not set. The index is bounded

by these two limits.

The proper choice of the length of influence range is vital for devel­

opment of the index. The area of most severe roughness itself must be

included. It was found, however, that the range must extend beyond the

end of the most severe roughness a distance of at least one dynamic load

cycle. The cycle length varies with vehicle speeds and loading frequencies.

The lowest frequency in each load category was selected for use so that the

longest cycle length could be included. When the speed is 40 mph, the

rounded cycle length is 8 feet for high-frequency oscillations, and 40 feet

for low-frequency oscillations. When the speed is 55 mph, the rounded cycle

lengths are 10 and 50 feet for high and low-frequency oscillations respec­

tively. The ranges thus developed are marked on the graphs (Figs A4.l

through A4.35 with light shading.

A combination of several types of roughness, not an isolated discontin­

uity, normally creates maximum dynamic loading. The section of Scarborough

Lane (Houston) exemplifies this statement. A detailed analysis of that

site is shown in Fig 3.10. Besides the previously mentioned gap at the

pavement joint, there are at least three other types of roughness present.

Page 81: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

73

These include (1) a tilted or distorted approach slab, (2) a discontinuity

between the approach slab and the bridge, and (3) a discontinuity between

the approach slab and the pavement. The dynamic loads induced by one rough­

ness pattern will often influence the loads by another. Therefore, dynamic

wheel loads are, quite often, the composite result of several types of

roughness.

Numbers of axles in each load classification for major roughness

patterns, with references to analysis figures, and derived dynamic load

indices are summarized in Table 4.2. These indices are useful for identify­

ing the potential for creating large magnitude dynamic loads. Small index

values indicate little tendency to produce excessive dynamic tire forces.

The smaller the indices, the smoother the roadway. It is interesting that

these indices may be correlated with subjective ratings and can be therefore

useful for indicating a measure of ride quality. For the cases examined in

San Antonio, Lubbock, and Houston, an index value of 9.0 is an appropriate

division between good and bad riding quality. If one of the indices for a

site is greater than 9.0, the overall rating for that site is almost certainly

bad. This is true for 16 out of 18 sites in those three districts, with

only two exceptions. The site of Spur 326 over the AT & SF Railroad

(Lubbock) has an index equal to 13.8 for high-frequency oscillations but is

rated as good. Another exception is the site of South Loop (IH 610) over

SH 288 (Houston) which is rated as good although the largest index value

for that section is 9.5. However, in general, the index seems to be well

correlated with subjective ride quality ratings for those three districts.

In Austin only three sites (two bad and one good) are considered and all

the index values are lower than 9;0. The Austin data is simply too limited

in quantity to make significant statements about the correlation between

Page 82: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

TABLE 4.2. DYNAMIC WHEEL LOAD INDICES

Subjective Rating Bad Bad Good Bad Good

Mustang Creek Boggy Creek Bee Creek Hackberry St. Durango St. Site Location (Au!! tin) (Austin) (Austin) (S.A.) (S .A.)

Hump near Dropoff at Sharp rise GAp between Distorted Description of bridge ends. bridge end. at bridge slab & pVIAt. approach slob.

Roughness Patterns end.

Predicted Dynamlc Vehicular Loading

End of Bridge Start ~:nd Enrl Start Stllrt End Start End

Referenced Figures A4.1 M"2 M.) fIIl.4 fil,. S fII •• 6 114.7 M.8

Dyllomic Numher of Ob",ervattons Tire Forces

(%) : o - 20 8 1 1 2 0 0 IS 16 lIigh 20 - 40 11 15 12 14 8 10 J 2

Frequ.,~

OsciI llitlon 40 - 60 I 3 6 2 8 6 2 0

60 - 80 0 1 1 1 2 3 0 2

80+ 0.· 0 0 1 2 1 0 0

I.oading Index 4.6 6.8 7.4 7.1 9.8 9.1 3.4 3.6

o - 20 11 7 12 9 1 4 4 4 Low 20 - 40 9 11 6 9 IS IS 13 11

Frequen.£I. Oscillation 40 - 60 0 2 2 2 J 1 3 3

60 - 80 0 0 0 0 1 0 0 2

81}!· 0 0 0 0 0 0 0 0 Loading Index 5.0 4.0 1,.6 6.8 5.4 5.8 6.6

Good

W. W. White Blvd. (S .A.)

Finger joint with drain between PVOIt. & slab.

Start End

114.9 A4.10

5 6

14 14

1 0

0 0

0 0

5.2 4.8

9 3

7 12

4 4

0 1

0 0 5.0 6.6

Bad

Plum Creek (S .A.)

Tilted slab and hump near bridge ends.

Start End

M.l1 A4.12

2 0

15 14

2 2

1 1

0 3

6.4 8.9

0 0

11 8

2 6

4 4

3 2 to.l 10.2

:

I

i ,

!

....., ~

Page 83: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

~lIhjective R"t In" &ad Cood

~tte '-ocation .os Un~u"h I<T (. SF RR (I.llhhn .. k) Creek

Description of So. forl!ll!d by Poor jolntR RouRhness Pattern each lipan with

apr roach slab

End of Brld~e Start t:nd Start End

(S) (N) (S) (N)

('(erenced Figure M.13 "".14 A4·15A4.16

Dyna .. i.: rire rorce o - 7.0 1 4 e 10

(%) : 20 - 40 5 HI 1 7

Hieh Frequenc,!

60 - 60 B 1 '! 1

!!.8dlla- 60 - 110 5 1 5 2 tion 80+ 1 4 (, 0

LOl1dinr. Ind .. x 10.1 Ii. (, U.B 5.0

Dynamic Ire Forcp., o - 20 5 1 ](I 4

(%) : 20 - 40 0 8 ; I,

Low 40 - 60 5 2 1 5

!~e~~I.!.I!S~ oscillA· 60 - /10 4 2 ~ 7 --t-l~;--

!I(l+ 6 7 n f'

LOlldlnr. Index 11. II 11.9 5.'0 9.0

TABLE 4.2. (!ONTlNUED

B .. d r.OClli Good

US 117 S 9~t! St. BrnEo" Ct,ld)

Gap betveen Open joint Lonp, \lave Open In" at rilted .. pproach appro .. ch 81ab betveen bridge pr"fllp. brld"e joint lIl .. b

on" hridr.e deck .. near brld!,:" . end

rre-tllr.tl'd D)'no1mic \'chit'.'];'!r I.Il:u!~""

~tart End rnd Start End (E) (II) (N) (NIl) (SF.)

A 4.17 AI,.18 ,,~. 19 "4. 20 M.21

- Numb"r 01 l'bsl'tvatin,,:,

4 0 10 16 8

5 2 6 4 8

8 (, 0 0 2

2 5 3 0 0

1 7 1 0 2

8.3 14.1 5.9 2.11 6.~

13 20 7 20 11

5 0 4 0 i

0 0 3 0 2

0 0 4 0 (I

0 0 " n II

l.O 2.0 ~.:! :'.0 4 . .!

Coo"

Bra .. o. (n"v)

Til ted I)(sc"ntlnult~·

Hut bet ..... en lipan "prro .. ch .lab

.. nd brld!!e

~tart En.1 (SE) (NIl)

AI,.22 A 4. 23

13 15

7 5 . 0 0

0 0

0 0

3.4 J.O

II 11

12 OJ

0 0

0 0

0 0

4.4 l.1I

I

I I

I

I

i

!

...... VI

Page 84: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

SubJective Ratin~

Site Location (Houston)

Oesct'iption of Roughness Pattet'n

£nd of Bdefl'll!

Referenced Fif{\lt'p

\J~'l1al:1ic

ire Forces o - 20 (X) :

20 - 40 Higb

40 - 60 FreguencI OscUla- 60 - 80

tion 80+

Loadinf{ Yndex

Dyna1llic Tire Forces o - 2(

(%) : 20 - l,(

Low 40 - 6f Frequency

Osci11a- 1)0 - 8( tlon

80+

loading Index

TABLE 4.2. CONTINUED

Bad Sad

S. Belt Shell Overpass

Discontinuity Opening at TUted Long \lave on between bddf{e pavel!!ent joint appt'oacb slnb brld!!:e 1'Ipproacb and approach

slab

Predicted Dynamic Vehlr.ular Loadin!!:

Stat't End Start End (NW) (SE) (W) (F.)

A4.24 M.25 AI,. 26 A4.21

Number of OhservntJons

3 0 '2 10

7 6 10 2

3 11 5 5

4 0 1 2

3 3 2 1

9.7 10.3 8.4 6.5

8 5 3 5

2 8 4 1

2 3 10 2

5 3 3 5

3 1 0 7

8.9 7.5 8.6 12.3

Bad

~cat'bornUJll.h Lane

Opening at pavel!!ent

joint

Stat't (W)

A4. '28

3

0

1

3

13

15.9

6

4

5

2

3

8.7

I

I

..... 0\

Page 85: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

Subj.ctive R3tln~

Site Locat Ion (Houaton)

Dese drt 1(1" of Rou~hness Pattern

End of l!Irid,e

Referenced F1 ~l1n~

DynamIc rire Forces o - 20

(%): 20 - 40 High 40 - 61) Freguenc)!

08c111a- 60 - BO tion

80+ --

Loading Index

Dynamic: Tire Forces o - 20

(%): 20 - 4( Low

40 - 61 Frequency Oscilia- 60 - 811

tion 80+

loading Index

TABLE 4.2. CONTINUED

Good Good Good Rod

Galais St. SH 288 HcCarty Rd. W. !lelt

IHscontin- .Jlscon t In- Of>eninR be- 0rcning betweel tllty uity tween op- aprroacb slab Tilted arrroacl

between ap between ap- proach slal> and bridge slab pro.,ch proach slah Ilnd hridge and pvt. and pvt.

Pn.dlcted lJyn:tmlc Vehl culor I.oadl"~

End Start End gtart End (W) (W) (51':) ( F.) (W) -14.29 II 4. 31) 114.31 11.4.32 A4·33

Numher of Ob""l'vatlonl'l

J 0 2 0 0

8 11 <) 12 6

S S 7 7 9

1 1 2 1 3

3 3 0 II 2

A.9 9.S 7.8 7.8 10.4

4 4 9 6 4

8 Ie <) <) 6

4 3 2 S 8

4 3 0 0 2

0 0 0 0 0 -7.6 7.0 4.6 S.8 7.6

Bad

R.R.

Tilted approach

slab

Start End (NIl) (5E)

114.34 114.35

3 IS

10 3

6 0

1 0

0 2

7.0 4.4

4 4

4 10

6 3

4 2

2 1

9.4 7.3

" "

Page 86: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

78

ride quality and loading index.

\ \

Page 87: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

79

CHAPTER 5. CONCLUSIONS AND RECOMMENDATIONS

In this study, roughness problems in the vicinity of the bridge-pavement

interface are examined. Information on representative bridge sites in the

Austin, San Antonio, Lubbock, and Houston districts of the State Department

of Highways and Public Transportation was obtained through a special survey

questionnaire. With the aid of on-site inspections, twenty-one locations

were selected for road surface profile measurements. A vehicle computer

simulation program was used to analyze the interaction of vehicles with

roadway profiles. The following conclusions and recommendations are based

upon study and analysis of these data.

CONCLUSIONS

(1) Based upon observations of this study, the magnitude of traffic

volume cannot be identified as a causative factor of surface

roughness at bridge approaches. Since the temperature in Texas

is neither extremely cold nor extremely hot, frost action and

slab movement due to temperature variations are not serious. No

significant correlation was consistently found between the

performance of bridge approaches with bridge function, bridge

type, bridge age, or the height of embankment fill.

(2) While flexible pavement is dominant in Austin, San Antonio, and

Lubbock, rigid pavement is primarily used in the Houston area.

No obvious superiority of one type over another was found.

However, compared with JRCP, CRCP provides better performance.

Page 88: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

80

(3) Stub-type abutments, generally recognized as most desirable, were

utilized at all sites investigated. Deep foundations are used

almost exclusively as supports for bridges and appear to be very

effective in minimizing total settlement. No special treatments

for slope stability have been applied; that is, membranes, berms,

or benching has not been utilized. There are no special treatments

for soft foundations. Though light-weight material offers promise

for use in fills, no such material is used in these four districts.

(4) The type of material utilized in the approach roadway structure is

related to the pavement-bridge interface roughness problem.

Highway compressible clayey material was used as embankment fill

for all problem sites in District 14. Expansive soil appeared

to be the major cause of roughness in District 15. Heavy rainfall

in conjunction with expansive Beaumont clay induced severe surface

irregularities in Houston. No similar cause can be identified

for the Lubbock area. However, based on those sites studied,

Lubbock seems to have a less serious situation than the others.

(5) Penetration of water through pavement joints or cracks, especially

when expansive soils are involved, may become a major creator of

roughness. Elimination of expansion joints and use of finger

joints with transverse drains has been effective measures for

reduction of the water intrusion problem.

(6) Timely maintenance and slow rate construction techniques certainly

offer promise for reduction of surface irregularities. Modern

compaction equipment, which has been extensively used since the

1960s, also offers promise for problem minimization. Stringent

Page 89: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

specifications and inspections of soil compaction are essential

to obtaining satisfactory bridge approaches.

(7) Roughness at bridge approaches can occur either on the bridge or

81

on the roadway. A number of typical roughness patterns have been

identified. Except in Austin, the use of approach slabs as the

transition between the bridge and the pavement is a common practice.

However, for those sections having approach slabs, about 80 percent

of the identified roughness problems are related to the existence

of approach slabs. In San Antonio and Lubbock, approach slabs have

been removed in some locations, and the road profile has remained

relatively smooth following this modification.

(8) The Surface Dynamics Profi10meter provides a safe, convenient

means of obtaining the road profile information that is needed for

locating and identifying critical patterns of roughness at the

pavement-bridge interface. Rod-and-1eve1 measurements at three

sites in Texas have revealed that short wavelength roughness is

represented adequately by the Surface Dynamics Profi10meter but

that long waves in the profile are somewhat distorted. Dynamic

wheel loads can, however, be predicted satisfactorily by simula­

tion from the profi1ometer records since vehicular response to

long-wave roughness is relatively insignificant.

(9) The DYMOL vehicle simulation program is a power tool for pre­

diction of the relative effect of roughness in creating dynamic

wheel loads. The analysis process developed for DYMOL output

seems to be acceptable. The derivation of a dynamic load index

is useful for quantitative evaluation of roughness conditions.

The index is also useful for prediction of riding quality.

Page 90: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

(10) The most serious case encountered in this study is SH 225 over

Scarborough Lane (Houston). The primary roughness pattern,

consisting of a wide gap at the pavement joint, induced peak

dynamic axle loads of 4.5 times static weight. If a normal

distribution is assumed for dynamic loading, about 98 percent of

the dynamic axle loads will be twice their static weights. The

importance of joint sealing or repair cannot be overlooked.

RECOMMENDATIONS

(1) To avoid or alleviate interface roughness problems, generally

recognized good design and construction practices offer the most

promise. Stub-type abutments, deep foundations for bridges,

adequate investigations of the foundation site, appropriate

specifications and inspections of soil compaction, and sometimes

a slow-rate construction schedule should be considered. Benching

the natural ground to support the approach embankment is also

recommended.

82

(2) High-volume-change materials should be used with caution in embank­

ment construction, and special attention should be given to the

drainage system. On the one hand, the surface water should be

prevented as much as possible from penetrating into the underlying

layers. On the other hand, water having intruded into the soil

should be removed quickly and completely. Select granular-type

material, probably with additives for stabilization, is always

desirable as the abutment backfill.

Page 91: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

83

(3) Though in many cases bridge approach roughness is associated with

approach slabs, the banning of approach slab use is not considered

to be proper. The decision to use the specially designed reinforced

approach slabs should be based on traffic volume, soil condition,

construction cost, and an estimate of the possible problems if they

are not used. It is impractical, however, to specify any particular

design for approach slabs as being better than any other; local

past experience will provide valuable guidance.

(4) When undesirable surface roughness adjacent to the bridge-pavement

interface does occur, maintenance should be performed immediately.

Scheduled preventive maintenance may prove to be a more effective

and economical solution. Points of major concern include pavement

joints, bridge joints, and the joints between the approach slab

and the bridge-pavement.

(5) Even though the effect of a distorted profile from the Surface

Dynamics Profilometer is not critical in the simulation analysis

made by DYMOL, a good representation of the real profile is highly

desirable. More study should be devoted to defining the capability

of the Surface Dynamics Profilometer to measure long-wave roughness.

(6) Extensive soil exploration, along with detailed and accurate

information on the design, construction, and maintenance history

of the bridge site, is essential for determining the extent and

the specific causes of one particular interface roughness. Analyses

of this depth are beyond the scope of this study. Further in-depth

research efforts are surely warranted in the investigation of rough­

ness problems in the proximity of the bridge-pavement interface.

Page 92: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

84

APPENDIX

Dynamic Wheel Load Diagrams

Page 93: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i L1

~ B

HORIZONTAL DISTANCE (FT) o 15 30 45 60 15 90 105 120 135 150 165 180 19!5 210 22!5 240 255 270

z

~ 1.001-C!

-.-- I T

= ~. -veu_ ~ O.ooE== '- ...... w ~ <:07.

6 I i -1.00 _4

Do

VIA

I

4°1~ 55 2

40rl

3

I

5512 3

I I--

2

40~ 5

M~ 5

~BRIDGE

, l

1 __ A

~I!i iJtl.-

i]!i!!i

, ,

I

~rl~l. ....

,

. 1'1" Fig A4.lA. Dynamic wheel load diL:l:;ram, high frequency oscillation,

Loop 427 over Mustane Creek (Austin). start of bridge.

, ';1

1

MAX. LOAD (%) -,~

122

118

131

133

121

137

130

132

143

149

119

117

126

124

136

138

133

139

130 135 -----0

00 VI

Page 94: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

- o 15 30 45 60 15 90 HORIZONTAL DISTANCE (FT) 105 120 135 150 165 180 195 210 225 240 255 210

z ... 1:

1.001-

, I I I I I"

~ O.OOt== i-'OO -- -,~- ~'~I "V" •

VEHICLE V I A I ~BRIDGE

I :: t Ill!lliiililill!I!!lllllillillllljill!I!~ill!I~!,:::::::::::: _ 11

d I

55~ 3

~~ 5 r1

B ~~ 5

l

II ~l~za mltl ~Laru

,

Fig A4.1B. Dynamic wheel load diar:ram, 10\-1 frequency oscillation, Loop 427 over Hush.np; Crel.1k (Austin), start of bridge.

j.

1 , ,

J

MAX. LOA 0 (0/0) --.,

122

118

131

Jll 121

137

130

132

143

149

119

117

126

124

136

138

133

139 130 135 ----'

(X) a-

Page 95: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

o z ... 2: 1.001-. C!)

I~ HORIZONTAL DISTANCE (FT)

30 4~ 60 75 90 105 120 135 150 165 180 19~ 210 225 240 ~5 270 I

~ Ooot'- -e ~ eA.. ~.~. ~ -.. .. ~""""-- ........ ~~ l&J • .... ""'- .... ~$l 1~. *V ...J ii: ~ -1.001-a.

VEHICLE I V I A BRIDGE ~ LOAD(%)

d I

55~ 3

r1 ~~ 5

lJ ~~ 5

/

-~::::::~::i:::i:::i:C:':':':':':

Fig A4. 2A. Dynamic wheel load diaera.:n, hir;h frequellcy osc illation, Loop 427 over Nustang Creek (Austin) t end of bridge.

L

137

132

142

'~

125

158

186

131

148

148 -148

j 130

133

165

185

149

146 171

156 169

00 .....

Page 96: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i d r1

~

- o z ~ a 1.001-· iii

IS HORIZONTAL DISTANCE eFT)

30 4S 60 7S 90 105 120 135 150 165 180 195 210 22S 240 255 270 I

l&I. ,....",.,..,.. A cn....- L.......... ......... -~ ~ L -' 0.00- • "-~'- -"..... .~ -1 ii: ~ ...... -

i Q. -1.00

IvTA BRIDGE lMAX. LOAD(%)

I

40\ ~ , 55 2

I

40n=

3

I

5S~ 3

~~ 5

M~ 5

Fig A4. 2B. Dynamic l-lheel load di3{';rrun, low frequency oGcillation, Loop 427 over Mustang. Creek (Austin), end of bridge.

,7 I~

I~ ,2

2

,5

125 158

186

131

148

148

148

130

133

165

185

154

146

171 156 169

00 00

Page 97: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

0 15 z I

~ I.ool w -::r::: 0.001 w ~

ii: ~ -1.001-Il.

VEHICLE V A

I I

40 2

I 55

2

[I. 40 2

3

I

55 2

31 I

2

r1 40 3

4

5

1,-

U 2

55 3

4

5

HORIZONTAL DISTANCE (FT) 30 45 60 75 90 105 120 135 150 165 180 195 ·210 225 240 255 270

~ ~ ..... -- ~ ~

~

BRIDGE

~

,

Fig A4.3A. Dynnmic wheel load diacr31ll, hlc:h frequency oscillation, US 18) over Bogey Creck (Austin), end of bridge.

/

A

MAX. LOAD (G/,,) ---,

133

136

153

148

130 147 163

144

·175

. 183

137

128

156

141

166

159

155 172 154

15L

00 \C

Page 98: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

- 0 IS Z I i

... 1.00 :r <=)

w :r 000 w . ...J Li: i-tOO Q.

VEHICLE VIA -i

I 40~

I 557-I

40~ 3 I

SSn= 3'

L1 I

~~ 5 ~ -I

B ~~ 5

HORllONTAL DISTANCE (FT) 30 4S 60 15 90 105 120 135 150 165 IBO 19S 210 22S 240 255 270

i i I I I I I I I I I I I

l .. ,- :....r...;?

BRIDGE-==:!i

Fig A4 .3B. Dynn.m:lc wheel load d1:Jo~am, ION' frequency oscillation, US 1IJJ over DoG[';y CI·eeJ.~ (Aus tin), end of bridge.

/ j'tAX.

LOAD(%) .......,' 133

136

153

14B

129 147

163 , 144

175

IB3

137

128

156

141

166

159

165 172

154 , 162

---I

\0 0

Page 99: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

o IS z ~ x 1.001-~ LLI X

~O.OO~

1£ -I.OO~ Do

VEHICLE I V I A

i L1

ri .3

I

4°1~ 55 2

III 40~

3

I

55~ 3

I I--

2

40

1 : 5

M~ 5

HORIZONTAL DISTANCE eFT) 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270

.-. "-" --- 7' -... -c;r' ~

~BRIDGE

icrL !

• jWI £~~L ,

jl~!l~~t : A • ·Al*'4~ ----.a::::::::::::: ~ t:·;.:·:··, n;,'wna,we HatE _

- f#4Allltlt* ;Z ;<.' lPW_ A t·::, ..... " ~ ; 0 ;'=:::;;aW'Cb r:=: ::r«t.fIwt_VW .: ..... !.~.:.:. B%I '';''('~I'" ~ ';'m,ZHi'tt:_._ _____ :.~: ........ '

n - " ;. , It:.:i::c:;;:...~ .. ~7':::L ________ IiiiiI~~~ & atiM: _ IM!Z!kSEct&6!Z*'"* '~: ..

J

-

.J t-j ::::::::::: 1 ~.-

IE Fig A4.4A. Dynamic wheel load diagram, high frequency oscillation,

SH 71 over Bee Creek (Austin), start of bridge.

j

MAX. LOAD(%) ---,

137 138

139

140

137

156

174

148

192

193

152

131

145

133

147

152 156 160

166 175 ----I.

\0 I-'

Page 100: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

0 I~ Z i

~ 1.00 z: C!)

l&J z: l&J ~

iL ~ 1.00 Q.

VEHICLE VIA

i I

4°1~ 55 2

L1 .&

40m

3

11 55~

3 -I --2 i

----< 40

1 ~ 1

5 -fi I u Mff 5

30 i

j

HORIZONTAL DISTANCE (FT) 4~ 60 75 90 105 120 135 150 165 180 195 210 225 240 255

i i i , i I I i • I i I I •

"---

I--BRIDGE

_______ .. 1 _______ I 111111111111111111 f

&

1

-------------ll~I!I!!!!I'!I!~II:

270

MAX. LOAD(%) - I 137

138

139

140

137 156

174

148

192

193

152

131

145

133

147 152

156

160

.66 175

------I

--------..... ---- ~ll!llilll: ;WD

Fig A4.4B. Dynamic wheel load. dia3ram, low frequency oscillation, SH 71 over Bee Creek (Austin), start of bridge.

\0 N

Page 101: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT)

~ O.ooy I~ 3f' 4~ 6.0 TIS ~ 1~5 I~O '~5 '10 'f5 I?O 210~ I I I I I

-.... a-tOO \ iii :t: I.IJ -2.

S-300 Q.

VEHICLE I V I A PAVEMENT SLAB -,7 rzzz

BRIDGE

ti

r1 ~

~o I 2

2 1 I

55 1 2 1

I I--

~

40~ 5

I

Mff 5

4

2

2

2

2 1

1

1 2 3

3

m=

7Y.!~!"

,~;;:~bM'+ tl~~

Fig A4.SA. Dynamic "Theel load diagram, hir;h frequency oscillation, IH 37 over Hackberry :Jt., (S·.A.), start of bridge.

MAX. LOAD (%) --, 165

188

192

..lliL 161

192

195

142

233

~45

149

201

203

192

179

181 193

200

183

~

\0 W

Page 102: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

fi C1

.... o z l-%: -1.001-. (!'

iii %: ~-2.00[J,

~-3.00[ n.

VIA

I

4°1 ~ 55 2

, 40ttj

3

55~ 3

~~ 5

M~ 5

15 30 45 60 15 I I

90 HORIZONTAL DISTANCE eFT) 105 120 135 150 165

I

1\ ..... /

.-IBO ~'O 225

PAVEMENT SLAB

#

Fig A4 .5B. Dynamic Hhee1 load dia,'jrrun, 10.-1 frequency osc111ation, IH 37 over Hackberry st .. , (S.A.) ,_start of bridge.

~ I

MAX . LOAD (0/0) ...........,

165

IBB

192

179

161

192

195

142

233

245

149

201

203

192

179

IBI

193 200

IB3 I~

\0 ,c..

Page 103: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i d ~

It

B

o I~

ZI.OO~ ... .

~ 0.00 lIJ %: lIJ -I.OO~ ...J

ii: ~-2.001-~

VIA

I

4°1~ 55 2

I

40~ 3

55~ 3

I I----

2

40

1 ! 5

~~ 5

30 45 60 15 T

~

-

HORIZONTAL DISTANCE (FT) 90 105 120 135 150 165 180 195 210 225 240 255 210 285 300

I 1

--..r'

BRIDGE ::::::t'!rJ.LI1::zr.rr------~ MAX.

SLAB LOAD(%) :·:·:·:·:·:·:·:·:·:·:··<:1::·:

,l;',~i·:.r .. :J"';.;;"i: ... i: __ _ 44.t))~. - -

189

183

168

185

I~j%~\~\~~ .. :~..,·: .. i~..,~~ .. ~ ........ ___ _ ::::~;::~::·:;:·::(:t:?::-S;;:

___ "'F~.;;::. :;:.~~.~.' ... ~ .. ~ .. '!l?~"";!"!. ;!'!o~."''' ___ '''''IIiIi_'' - 153

208

183

'$tz,W"M HM%" £SMS ~%%I{%)?!/~\~ 176

211 ~ "~~~~::.::".)7:~7:C~{:~::·_.I=_II' ___ -1. ___ .. ~ ...... ' ....... ~ : cew _ .. ~~~-;;.:;~:.:~~~J.~ .. ~:. __ .. _ ........... . 212

-

-:44.:~:~:~:\:~::::::::::: :::~~:~::~:~:~~::~:~:::~:~. ::~:.:':i:~::::::~:i:i:i:i:i

__________ :IIi:: .. :::,;,.i:.Or:i!::$i;:~J::::::::::;:.

.,:-ft.:~.~~:

162

203

213

204

169

191

181 205

184 210 -----'

Fig A4 .6A. DynaJT\ic wheel lna'i dla.,:ra.m, hiGh rrcqu!~ncy o::;cillutiJn, IH 37 over Hackberry st., (S ~A.), end of bridge.

\D U1

Page 104: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i

r1 B

HORIZONTAL DISTANCE (FT) o IS 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

T :I z

-~ i~OO : ~ ~-IOO ~ ~-2.00~

.--.....

Q.

VIA BRIDGE

:~:~:~:! :!i!:!i !i~:!j!j!i~::t! i~:ljlj!:!j!i !:! ~;~; ~;~; ~;~;~ ;~;~; : : ~ I

4°1: ! ~! ~! j i j j i ~ i ~! ~ i i ~ ~ i I I ;st;:; i ~ ~ ~ ~ ~ i:; ~; ~ i ~ ~; ~! ~~ ~!! i i ill I! I! Iii! i ~ i i ~ 55 2

40~ 3

55~ 3

~~ 5

I

2

~~~~~~;;;;~~~~~;;;;;;;;;~;;i;;~;;;~;;;~;;:i:;:;:;:~:i~W

rrmffmrlr}rrrtWmt~ !~!!!!~i!i~i~I!!!i!i~t!lt~~~ili!ill~ili!~!lll!i!i!1!1!l)it~·

168

185

153

208

183

176 211

212

162

203

213

204

169

191

181 205

184 55 : - ;;~~;;;;;<.::;.j.1):h':Zi~i!!!~!:i!!!!!!!!i!i!!i

5 :::::::::::::::::::::~>'j.i,:E~j:::::::::::::::}:::;: ,~ -I~ Fig A4.6B. Dynamic wheel load. rii.;.{T.11::, Jow fn'(IL:!ollCY o:;r:;llJo..tior"

IH 37 over Hackberry ~;t., (S.A.), end of hridge. \0 0\

Page 105: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i d fi

B

HORIZONTAL DISTANCE (FT) 0 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270

Z 1.00(: --. •

... ::z: (.!)

l&.I 0.00 ::z: l&.I

~ -I.OOl Q.

~ --/\. /

~~ MAX,

V A ] LjAO(%) ==-=F-=+-------------------_,."".O ........... ~.~.~~.:.:.:::;:.:.:::.\;:BRIOGE 1 -; I

40 2

I 55

2

40~ 3

I

55P=

3

~~ 5

I

~~ 5

134

128

135

ill 124

.1 139

147 1 140

-1 ;;,..1 179 '. ---j

A , j

j 1

1

Fig A4. 7A. Dynamic wheel load dlD/rD.':J, h:lC:h frequency o:3cillation, IH 37 over Duranco ~t., (S.A.), start of bridge.

j

... :_.16 ..... _~ •. .M. ~~9 145

133

152

142

150

153

132

167 174 17~

\0

"""

Page 106: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

0 15 Z I.OO~ l-X C> i&i 0.00 x

'" ..J

~-1.00L Q.

VEHICLE V A

11 I

40 2

55 2

L1 40 2 ,

:5

I

55 2

:5

2

r1 40 :5

4

5

I

~ 2

55 :5 4

5

HORIZONTAL DISTANCE (FT) 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 2S5 270

• ,

./--' ~ ,.,-'"

~ 1LLA

SLAB -r--BRIDGE

j

.. Fig A4.7B. Dynamic wheel load diC4~17url' low frequency oscillation,

III 37 over DUr.J.nr:;o st., (S.A.), start of bridge.

1

• 1

...,.

!

""

LOAD(%) I~AX. 134

128 135

131

124

1 1139 147 140

179

189

145

133

152

142

150

153

132 167 174 179 --

\0 !XI

Page 107: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

o 15 z

i IDO~. % 0.00 1&.1 -' iL ~ -1.001-Q.

VEHICLE rvrA -i 40~ 2

I 551--

2

I

40~ 3

1

55P=

[j 3

I

~~ 5 ~ I

~I ! r4 ~ r--

5

HORIZONTAL DISTANCE (FT) 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270

~ ~

v

BRIDGE' J222Z!7ll~7J777777771~~~(%)

- , .a

.A

'- r::! :;:;;::::'::1$'. fh*9¥€

--..A--. .'363>1,+'9, s:C" ...... 4·i i'%iN .. ..

.a

- j

j ,

A

-Ci7iTI'" • J.

Fig A4.8A. Dyn;unic wheel ].~):l'; dl~'l~I~'r.;, hie;h frequency oscillation, IH 37 over Durar1[;o :;t., (S.A.), end of bridge.

128 135

139

n.e.. 126 175

182

142 175

169

159

138

150 140

147

186

160 178

166 178

----'

\0 \0

Page 108: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i Ll

o z

... 1.00 :r <:)

lIJ :r .... ...J

~ -1.00 Q..

I

40~ , ,

55rt '3

~ 2 r'1 140

I--

~ S5~ t±

5

IS I

HORIZONTAL DISTANCE (FT) 30 4S 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270

I T

B~£" it-r!.:~ ~~X~!O{O) 12 •

Iliiiiii/111_ j

a

j

1

1

&

1

" :E:i:[~i£~:i:::i:i:::r:::::J

-~,,;,u;·:·;·:-:l: j

.I:,:,:,~:,,:,:,I, r:::::::::<~i.t:::::::::::i:;:i:i:i:i:~

.-~~ il= • 1 --f<i~;~;~;;Jjf;i~

...•.................. ::::::::::::;;.::.:.;.:.;;.:~ ,::t:'_~ffJ • ..b. ..... .,J~ .......

Fig A4. 8B. Dynamic wheel load. d.ia,-:;r.:un, 1m-I freq ucncy oscillation, IH 37 over Duraneo st., (S.A.). end of bridge.

135

139

138

126

175

182

142

175

169

159

138

150

140

147 186

160 178 166 178

--'

,.... 0 0

Page 109: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT) .... o 15 30 45 60 15 90 105 120 135 150 165 180 195 210 225 240 255 210 z ~

1.001-~

~ 0.00=-~- ~~ ~ t ~ ... OO ~ "'V7 0.

VEHICLE VIA 14=="BRIDGE

i 1

40

1: 55 2

1

Li 40~

:3

1

55~ j

:3

r1 I ~;I!;I~i;~~i ~ 2 -'o.k., .... ,.,.,., ........ ,.,.,.

55 3 .. ~'~~'~:,"",' .~. __ {:trltt~~(:lttt~

, j

Fig A4.9A. Dynamic wheel load diaGram, high frequency oscillation IH 10 overtf. W. \·lhiteBlvd., (S.A.), start of bridge.

A

.J-

l

&

j

MAX. LOAD(%) --,

130

132

126

131

127

146

148

124

157

148

142

135

133

154

ISS

146 137 165

136

158 ----'

I-' 0 I-'

Page 110: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT) .... o 15 !O 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 z I I I I r

... 1.001--::t: C)

iii ::t: 0.00 LLI

~ ~ -- ........

~ ,.J

~ -1.001-

a. MAX.

VEHICLE V A SLAB i---BRIDGE LOAD(%) ----,. .

ti I

40 2

55 2

130 132

126

131

127

1111111111111~!liil!ill!i!I!llIil---~---------------------------------------------------------------------------------------4 .. ~ ... ~ .. ~ .. B'."~~.~~~~:~~~~:~, ...•. :~~~~~------------~------~

d 40 2

3

I

55 2

3

2

r1 40 3

4

5

~155 4

5

• j

Fig A4. 9B. DynamiC wheel load. dia.;-rtlJ,l, low frcq uency oscillation, IH 10 over \;. \-1. \·lhite Blvd., (S.A.), start of bridge.

";',

;~l\....­fj .;'I:

146

148

124

151

148

142

135

133

154

165

146

131 165

136

158 ---'

\ .... 0 N

Page 111: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

11

c1

r1 U

HORIZONTAL DISTANCE (FT) ..... o 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 z I

~IOO~ ~ 0.00 ~ __ --......,... ~-=-

~ V Id ...J

~ -LOOt-

a..

V A

I 40 2

I 55

2

40 2

3

I

55 2

3

2

40 3 4

5

I

2

55 3

4

5

-BRIDGE ... , SLAB

...

&

,

j , j

• A

" , Fig A4.10A. Dynamic wheel load di3tiraJll, hie;h i"r:cquency o5cillatlon,

111 10 over W. W. Whi te Blvd., (S .A.), end of bridge.

--MAX. LOAD (0/0) --,

127

138

132

148

137

133

140

153

143

142

142

135

131

131

129

171

153

156 164

170 ~

.... 0 w

Page 112: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

o z

~ 1.00 ~

LIJ J: &&.I ..J

~ -1.00 Q.

VEHICLE I V I A

ti I

4

°1 ~ 55 2

I

L1 40~

3

I

5Sn=

3

~ ~~ 5

B ~~ !5

HORIZONTAL DISTANCE (FT) IS 30 45 60 1~ 90 lOS 120 135 150 165 180 195 210 225 240 255 210

I -I

MAX. BRIDGE SLAB LOAD (0/0)

Ir~;;"~··ri··';''''''.'!i.',;:.;i:,"~,"·~':.' ______ .

----, 127

138

132

148

137

133

140

153

141

142

142

135

131

131

129 171

153

------... ::~:i$irJr:(~:~~~4;F::::::::? 5_ 156

164 :::::::::::::::::::X:::::::::::::::::>:::' ..... _--.:"'.,.. .. :-'-" .. ~, .. _- 170

F'ig A4.10B. Dynamic uhcel load d::';:{;r::1I:'.. 10:1 ~.r-qU(,II'-;'y v:.;..:.Hla.tlO:1. IH 10 over W. W. White Blvd., (S.A.). end of bridge.

--~ 0

"""

Page 113: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

- 0r-__ ~ __ ~ __ ~~~~~T-~~~~ __ ~~~~~~~~ __ =r Z

f0-X ~ au x au

1.00

= -1.00

~ 0.-2.00

195 "T

210 T

225 240 255 270 I I I I

-~

I VEHICLE I V I A I SLAB i--BRIDGE ! _.* .... •. ~_!!,:,,;:o.~.~.,;:~t.~.·*· .... ~· ••

i L1

.

I

~ I

557

40 2

3

.o~ 5

~~ 5

FI~ A4.llA.

j

J , .I

Dynar.:ic ·.i; l(;c1 l:}.:l!i. i~ i,J,;;ra;n, hlr;h frQq u0ney o.:;cillation. IH 10 o'/or Flu.'n C:::-cd., (S.A.), start of bridge.

A. --

MAX. LOAD (0/0) --..,

r45

143

169

200

160

ISO

160

198

170

186

147

132

165

141

170

238

215 189

189

203

..... 0 \JI

Page 114: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

z ... 2: c.!)

o I~ 30 4~ 60 75 90 HORIZONTAL DISTANCE (FT)

105 120 135 150 165 180 I

~

195 210 225 240 255 270 I I 1

~ ~

I VEHICLE I V I A I ,.,.,.,.,.,;,!,~.~",~,!,,!,:t;;:;:;~~~'~i .. ,.,., :~"~.,;------I

11 4°1~ 55 2

,

d 40~

3

L

. ..- ... : ... ::;::-------------..• _- ----...---

'Ott , 55~

3

_____ ~I,:.jo: :.:.>:. ~.-: ', .. .: . ~: ,', ,'., ...... ' .... ,' .. ,', ,',

f{(f]i\r?:t:r}:>f:~~~:~~:~:~~~~~:~;:;~;:

____ rd[ .. igi'.:.;:;:,~~;;;;:;~':·!i~~.~ F'~g A4 lIB DV":\oric "hf;f'1 IC"'(l G.l<1."'Y'l·l '1"'1' 1 . ···t' '''c'' r,.-c·il-l·,tl'OIl • • oJ • , . - ~..... t. ,.J ... \. .... , .......... j " " '\. ..... _ .... 1 -..... .... ~ •

III 10 over PIU!'1 Creek, (S.A.), start of bridge.

~ ~~ 5 A

~~ 5

__ : : .... :: ;:::=::, ::;:;:;iE':cm:w

~ .":1

MAX. LOAD(%) -145

143

169

200

160

150

159

198

170

186

147

132

165

141

170

238

215

189 189

203 ---"

.... 0 (7\

Page 115: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

o IS 60 75 HORIZONTAL DISTANCE eFT)

10!5 120 135 150 165 180 1\ 22!5 240 2!5!5 270 28!5 30 4!5 90 z I I I

2.00.-

'\ ~ \ ~ COl- ~ OJ I. '" i OCOL "'-~-I.OO

MAX. lOAD (O!c~)

-,. I VEHICLE I V I A I BRIDGE =+!.J.S~.t ........... s..e........ '» 1--140

147

160

166

~ 5512=1 - .{:::~:~~::~j~:::::::::::::::~}?~{:~:~:~:::~. 55 2 i

j 138

165

198

186

228 [J 40 2 _ -:'~::::::::::.:::.:::::{\::::::.:... .:.:;;:~ 2 _

227

151

133

157

170

173 F1 ~~ !5

l

~

l

183 137

224

175 - ~~ • B --

:5 211 -----'

~ 0 -...J

Fig A4.12A. Dyn~ic h"heel 10<:'.d. di;:.--;ra.r:J, htr;h fr(:(PJct·,,~y o:c;cll1otion, . IH 10 over PIUl'1 Cx-cck, (S.A.), end of bridge.

Page 116: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

2! 3.00C:= If 30 45 j j

~ :z:: 2.001-C!)

'" :z:: 1001-

'" ...J i&: ~O.OO~ ~

VEHICLE V A

i I

40 2

55 2

d 40 2

3

I

55 2

3

2

r1 40 3

4

5

I

~ 155 2

3

4

5

Fig A4.12B.

60 75 , I

HORIZONTAL DISTANCE (FT) 90 105 120 135 150 165 180A210 225 240 255 270 I iii I I J \ I I I I

~ ,-BRIDGE SLAB I ~

~ .. ~:::'I'j~~I.1r:

.................

~I¥.~.~ll~~~\\jiliillJ~lliT· ~Z£B235rQ,;::;·,.;;

-:-:-:·:-:·:-:·:-:-:·:-:-:-:-:-:-:··v·:-:·:::··:·· .. ~"!;;~:':':~ ... '~.a;. :~.' "" _.

;~::~~:::~:~~~~~~illi2~l~ .. ~.~._. :::::::::::::::::::::::~::':::::::::;~::i~:):~:::~ .,.,.~:. ".::.--:::::;~~~.~.~ ...

~Ti:~:~~::27:::"~~~~:~~:ir~1r~:~~ ";'.~ .... .,~~.t ............... ......,...Ai!.~ :::~:~:;~:~.~., '.:..:~:~ .. "~'~"':::::::::::::::::::: t~'f""t""",," ,., ........ ,.~.. I ...... .

DynaMic loTheel load. diac;rarn, low frequency oscillation, IH 10 over Plum Creek, (S.A.), end of bridge.

3

3 4

4

3

3'

MAX. LOAD(%J .......,

140

147 160

166

138

165

198 186

228

227

151

133

157

169

173

183

137 224

175

~ I-' 0 en

Page 117: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) 30 4~ 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300 1-----' ,- ~-----. .----.--,--

j

~ lill!!i!!I::ll~~I~!,:: A A :I~ , . [A~ ~ r:=BR,JGE L'A'\;(%l

I

1!!~!,!!:!:!!!!]1~!l:I!~~;, A ~~; ,

-----------....... -----.J,~:~~:~:~:~:~:~:;~;:~::~~:~~~~~~~~~~~~~~~~~~~~~~~~_t~~~~~1iij 185 Ll , I £~~:j:~:~:~:~!::~}Gliitt~lbm::~::im;:~ 187 I

e~H~tt;f{l~~~~~~f~~~~~~ff~~~r~~rll~ . , 281

1.~~~::~~~:~0;;:~:!1:1:1:1. A A ~:~ ~~:~:;::::/~:~:~~:::::;::~:::~~~:~::::::::.>;::~::~:;~:J j 199 r1 Ejt!,!:I~;;~i~~IIII.: A A

.~(~::i::: L~::: ~ ~ ~ ~: ~: ~:: ~ ~:::::: ~::::::: j: ~: ~ ~: ~ ~ ~ ~: ~: ~: ~:: ~ ~ ~ ~ ~ I LJ

L-----L-----IL-....I...-______________________ .Jisll:·:Bi:~~:;~;:j;;:::;:;;;:;:;:;:;:;:;;;;;;:;:;:;:;:;:;:i:;:;:;

197 177

206

239 294

Fig A4.13A. DynaMic wheel ~_oCld diar,rC'll". hirh frc'1l1(>ney oseU b tj on. I'M 1065 over Los Linpuish Creek (Lubbock), Rtart of bridrc.

..... o \0

Page 118: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.)

-- 0 ;i

30 90 105 120 135 150 165 180 45 60 15

I- 2.00 ::z::: C!)

1&1 1.00 ::z:::

~ 0.00 .... 0 g: -1.00

VEHICLErV I A BRIDGE -t ~ 55 ~ ,

I

Li 40 2

3

I

55 2

, ,

3

2

40~ 4

5 -I -2

55~ j

4 -5 L _____ ...I __ L:...L __________________________________ , _______ ;;l;L __ .... • .. b.;,· ... h ........... , ... ~ ........ h'. hn. ,9 ;,. hr' . .hie.o+',. 'b'

. .: ... -: ..... ~ .. ~:::.:-~. ::-::~::-::~~::.:>~ .. <~-::'o::::: :::: :':::'7~:':~ .

rip. A4.13D. Dynamic wheel loact diarrnrn, low freqt1ency osci Ilntion, Fr' ] 065 over Los J.in!!uish Creek (I.uhhock), stnrt of bridre.

MAX. LOAD(%)

====, 171

184

166

168

187

208

213

167

185

187

281

212

217

211

199

197

177

206

239

294 - .... ...... 0

Page 119: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

if Li A

)

- B

HORIZONTAL DISTANCE (FT.) I!S 30 4!S 60 75 90 105 120 135 150 165 ISO 195 210 225 240 255 270 2S5 300

I I z o

.... x C)

w x W ..J

I.L. ~-0.50 Q.

MAX. BRIDGE ----l LOAD(%l

====, 169

174

152

'"'4

209

: I =-~'ll:l-i~:~;;:,~:~;~;~;:;~~~~ 217

It+- ~""""·."'.'''·'''·._.·I~:':'''' ............... , ... _ ... ~ ........... y.lj,.:..I ~

211

229

155 206

217

Fi~ A4.14A •.

j

j

j

j j

Dynamic wheel load diarxam, hiph frc(jIlCTlcy oscillation, I'M 1065 over Los Linguish Creek (Lllbhock), enl\ of hridrc •

312

219

21B

IB9

199

274

166

lSI

245

295 -~ ~ ~

Page 120: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

t Ll

i o~~~~~~r-~F-~F-~F-~~~r-~~~r-~r-~r-~r-~r-~~~~~~-=~-=~-=; .... I­::r (!)

iii 0.50 ::r ~ 0.001~~~~~7'~~--+-~--~~---.~~--~----------------------------~----------

u.. 0-0.50 a:: Q.

V A

40 I

2

55 Z

I

40 2

:5

I

55 2 -:5

,

, . -"" ,l._ ..

BRIDGE~

.. _ ............ '!'II

• zw:;;atar MSMWj@i$l'iR'xG== -;~::::::::::::::::::::::::::::~::::::2:::~:~?:::::::::::::::::::::~:::::~;~:~~::::::::;:~~jlj~I~?\4* ; s;;;:!~ ~.

Fig A4.14B •. Dynamic wheel load diagram, 1m" frequency oscillation, FH 1065 over Los Linguish Creek (Lubbock), end of bridge.

.~-.~ ---... --..,: ....J....'_.liIIIIoI.I..

MAX. lOAO(%l

====t 169

174

152

174

209

211

229 155

206

217

312

219

218

189

199

274

166

181

245 29L

......

...... N

Page 121: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) ~ 0 ,~ 30 4~ 60 75 90 105 120 135 150 165 180 _._ _ __ % 1.00. I 1 1

IQ~ ?ll"I ??~ ?4l"1 255 270 285 300

... :t:

~O.OOt· ~"Y

\.IJ -1.00C- • -J

I.L. o 0:-2.00 t­o..

......A ~,.~.

rrTT VEHICLE V A SLABF4= BRIDGE

~

I :;::~J:::::::::':::':;::::;';':::::::::::;;';':;:::::: 1i 40 r- -e~,,·~~,"~ ~ ___ _

~ ~.

MAX. LOAD (0/0)

==, 180

163

191 ______ a-__________________________________________________ ~

8

1:3 ~.;.;.. • ± .... __ , e,; ,.:.::;j,01I:l:!b

~ LJ3 I" ~ ~::::::::-::~;i~~~3:::~ .. -:=:=~Z:::~::~::,.::::::::::::!:: .. ::!~!..*H------------I

I 5 ::::;:11.0... ""-"""-"w;l~.-.-. __ .,' .

Fir. A4.lSA. Dynamic wheel load diagram, high frequency oscillation, Spur 326 over AT & SF Railroad (Lubbock), start of bridge.

134

207

214

152

251

263

166

166

204

208

220

205

216

260

238 280 - I--'

I--' IoN

Page 122: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.)

i 1.000 I~ 30 4~ 60 15 90 105 120 135 150 165 180 195 210 225 240 255 210 285 300

I I I I I I I

~ ~ ..".-" ~O,OO~.,/\, 'V

w :r ~ I.&J -1.00 -' I.L.

~-2.00 a.

VEHICLE I V I A

i L1

I

'Ol~ 55 2

I

40~ 3

I

55~ 3

I '--

2

Ai~ I

LJ 55ff 5

Fir: A4.l5B.

SLAB~BRIOGE

ilf;!j'!I!t~=- - ·

Dynamic wheel lond diar-ram. low frequency oscillation. Spur 326 over AT & SF Railroad (Lubbock), start of bri.dge.

MAX. LOAD (°/0)

====, 180

163

191

168

134

201

214

152

251

~ 166

166

204

208

220

205

216

260

238 2§.£L

..... ..... J:oo

Page 123: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

,... z o 15 30 45

I- 1.00 l­x CJ w

I I I

~O.OO~~V ...J

~

~ ·'.00 l-n.

60 ,- 75 ,- 90 I

~

HORIZONTAL DISTANCE (FT.l 105 120 135 150 165 180 195 210 225 240 255 270 285 300

I I I I I

1

~~~~r:lr;1======================================;;~~=;~~~----------------------------~MAX. I , A LOAD (0/01

i :: : 1!!!;lli~ll:t!ii!I;II~i!llli~ L1 I::! ' I -1!1;!;!I~li;III!!!!~!illiilt·IJt[r;II;.·, ~-.Ji.Ji ••••• :~ •. -----I

3

r'-1 A

.o~ 5

A

I A

~i ! 5

A

j

Fig A4.l6A. Dynamic wheel load diagram, hir,h frequency oscillation. Spur 326 over AT & SF Railroad (Lubbock), end of bTjd~e.

A I

15Z

164

165

171

154

156

174

169

211

205

IB9

17B

163

156

167

Z03 174

203

196 19L

.... ..... VI

Page 124: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

""': 0 IS 30 4S 60 7S 90 z

I- 1.00 ::t: CI W ::t: 0.00 W ..J iA: fi -1.00 a. I I I Villi' IMAX.

• U J\ ....... , ~~ ...~, A ~ LOAD (O/o) VEHIC~

40 ~

J

J

I 152

164

165

171

154

156

174

169

211

205

189 im:~f~}I))~~~~@j~~;;ijt~~:~ijt:~:~::~~::}}~:,t::\1:~:{2'-

401 ~ __ .__ ~!!~liillt~lllt::~~.~" •.. ":::".;..A:::.i.:"----I ~~;

551 ~ - ,- 1'j~iE~~ iii Fig A4.16B. Dynamic wheel load diapram, low frequency oscillation, Spur 326 over At & SF

Railroad (Lubbock), end of bridge.

,... ,... 0'\

Page 125: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

~

Li 1

~

o I~ T

Fip. ft.4.l7A.

HORIZONTAL DISTANCE (FT.) 30 ,. 4!5 ,.- 60

T 1!5 T

90 T

105 120 135 150 165 ISO 195 210 225 240 255 210 285 300 I I I I

.~ ~

''".1;1

I .4-::;.:;td~; go--?;;;; ;"-i'~iJmiil

I

Dynamic wheel load diagram, high frequency oscillation, Loop 289 over US 87 South (Lubbock), start of bridge.

MAX. LOAD(%)

===t 206

157

213

ISS

161

IS4

194

lSI

177

179

IS8

208

208

158

169

214

202

178

197 lSI -

'""" '""" "

Page 126: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) - 0 ,~ 30 4~ 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300 Z I I I

~ 1.00 C)

~ O~O~------~~~------------------------~--~~----------------------------~--~------I

w ...J -1.00 LI.. o :i-2.00

I VEHICLE I V I A I ~f.~~~.~~} DGE

i :1t ~ ,

A

40~ 3 L1 I

55~ 3 ,

r'i .o~ 5 I

LB 155~ 5

Fie A4.17B. Dynamic wheel load dia~ram, low frequency oscillation, Loop 289 over US 87 South (Lubbock), start of bridge.

MAX. LOAD(%) .,

206

157

213

188

161

184

194

181

177

179

188

208

208

158

169

214

202

178

197 181 ----'I

..... ..... co

Page 127: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.l

; 2.000 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

I I I

!~::~~ ..... ..,.,.." '-..::---------:;:0 .,..

o cr CI.

VEHICLE I V I A UIUIA

BRIDGE :::::;:'SLAB

~ 40:;:1i351 e; ,.i"n,.m·: " I------+--+-..,. ..... :!:"!'- .,.::.tI~·······

:~~~:~~~;;~;;~:J.)~~~l~t~ _ 40 .:::;~:::f::::)~;::::8::::::::::.~.~::::: :::Z:::J"e, AiM. UQi:I:&:JjtW ••

. ::. ::::8:::!f:~:~:~:~:::::~rtrt t * t n. M'M''';;:'.:>' .. ',. ".'rle"~:aJIiCtl

::.::.:.~.:::.·~.::~ .. :i.%.~~.:~.:.,.~.:rPi~; ::.;;.::: :=:t,:= :=~;::a M +ggeu , Ie :::::::::::::::::::::::::::::::::::::::::::;::8 :_: :': ... :: J .:: : .,,'" ::-;. " ·~_·It·;;·:~;';~: *.1+.'.-' " *1t .. ,. Os,t;;MI·iWHH8Acw;aaw:i! i-I

,;'~~I" d

~:)\.:.,!::.~.!,~.~:~~

!~.l!':'-... _____ _ tr.-~' -

____ -L __ -J~ __ .·~~~·~·:~~~:~&~~~~::~~~:.~~~\~lIItmal~:.:.~:::.~~:~a.~(~~tJ~::~l~a ...................................... ...

Fir. A4.l8A. Dynamic wheel load diap.ram, hi~h frequency oscillation, Loop 289 over US 87 South (Lubbock), end of hridge.

Page 128: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEH. __ _

HORIZONTAL DISTANCE (FT.)

i 2.000 I~ 30 4~ 60 75 90 105 120 135 ISO 165 180 195 210 225 240 255 270 285 300

I I I I I

~~~ :z: C) 100

;0.00 .. ,~ .. LL. o IX: D..

~ ~~--~-------::o .,.

,g 213

159

200

169

I m 'ZWIn IMAX 'r' < : V ::;...................... BRIDGE---ISLABLOAD(%1

40 ~~i~II:~'ll:1 I

I •

L1 , j

~, 1-'

8

fi~ A4.l8B. Dynamic wheel load diarram, low frequency oscillation, Loop 289 over US 87 South (Lubbock), end of bridp,e.

178

266

277

173

195

203

193

228

229

191

259

215 224

223

244 259

,... N o

Page 129: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.1 """: 1000 15 30 45 60 15 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

~ . r, I ; 0.50 1

~ l&J ~~00~---r~~~~------------------~~~~~r.----z~~~--~--__ ~-7~-----------r-­l&J ..J

~-0.50 o a: Q.

r,:;:~~r:lr;1----------------l===;;~~===============================;;;;;~~--------------~MAX. A BRiDGE BRIDGE LOAD (%1

i LJ A

>'

I 40

12

I 55. 2

1

40~ 3

I

5512

3

40~ 5

j ItZla~i£k7Eitl

l~iljL'll~. j

_________________________________ .. _ .. e ••• ;lll~;~fi~~i~~

•••••••• '.·.;i$ ... a:.·- - -=f4'~!iilii:iii!~1 • fi~~;ii;

.~. ~.:.:-........ .

,

UIM~ .................. .a .................. ~ .......................... ~.: ... :~:~:

................... ----.... ----.......... ~ 5 .... == ..... 1= .__ •• awWlllWWliJl.;VI

Fir A4.l9A. Dynamic wheel load diar:ram, hir-h frequency oscillr!tion, lTS 87 South over 98th street (Lubbock).

133

145

135

185

154

198

197

150

209

200

133

140

163

181

179 169

187

264

224 253

i

------ I-' N I-'

Page 130: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) 105 120 135 150 165 180 195

l-X 0 LIJ X 0.00 LIJ -' i:i:-0.50 0 IX

~T7.Ir~--------------,------------------------------------------.------------~IMAX. LOADt%)

Q..

VEHICLE I V I A

ti 140

12

155

j

j

Ll'40 1

55 r-

3 -I -2

40Q

j

4 -5 -I

2

55n 4 -5

Fig A4.19B. Dynamic wheel load diar:ram, low frequency oscillation, tlS 87 South over 98th Street (Lubbock).

133

145

135 185

154

198

191

150 209

200

133

140

163

181

119

169

181

264

224 253

I

..... '" '"

Page 131: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

i

HORIZONTAL DISTANCE (FT.) ~ 0 I~ 30 4~ 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300 z 2.00. I

.... J: 1.00 C)

~O.OO -~~ u. -1.00 o a: 0...

Fig A4.20A.

, ,

,

,

, ,

Ili!li!~iil!!illlltllltl

Dynamic wheel lo~d diagram, hip,h frequency oscillation, US 84 over Brazos River (Luhbock), old structure, start of bridge.

123

128

122

125

114

137

141 123

140

139

131

146

139

128

132

131 127

143

130 132

-----A

l-I\.)

W

Page 132: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i L1 ~

3

HORIZONTAL DISTANCE (FT.' . ~ 2000 IS 30 4S 60 7~ 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

- • I 1 I I I I I

LIJ ..J

i:i: -1.00 o a: 0.

V A

40

55

40ttj 3 -I

55~ 3

I

40~ 5 -I

tI 5513

E 5

SLAB

A

BRIDGE

A A

A A

A

A

A A

rl!III~llllririlil A

Fig A4. 20B. Dynamic wheel load diagram, low frequency oscillation, US 84 over Brazos River (Lubbock), old structure, start of bridre.

MAX. LOAD (0/0)

i 123

128

122

125

114

137

141

123

140

139

131

146

139

126

132

131

127 143 130 132

.... N' ~

Page 133: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

30 T

45 T

60 I

----- -T

15 T

90 T

HORIZONTAL DISTANCE (FT.) 105 120 135 I~O 165 180 195 210 225 240 255 270 285 300

1 I :;;c 9 ~ I

"" r7777/J MAX. ,_nAO (%)

'=f -t=*"" ______ .... ______ ...... _ ..... ==B==R=I~D=G'='=E=~~l,.-A B -_.

128

127

165

157 -121

170

178 :~)~:h:;;::::;:::::::)::::::::{?::)\>:(:~:;)}; :.:-: ...... " .. ~ ...... , ........... , ..... ' ... ' ... ,~.t~)to:r:.::f'*':,=I!:ou'!""-----_----------___4 :::::;::::::;:J:::;:::::;:::::;:;::::;::::::;:;:;:;:;:;:;:;:;:;::;::;:::::::::;:: ~:t~:·~:~:·.·:: .. ~ ...... ' ~.~;:) .~.:~ ):::::::::::::::::::::::::::::~::::: 149

' .. :~ 236

t1256

~C::)-IrI ____________________ "·· .. ··.··.II_II ..... ii~I-I.I"a:·i£i~::,;·p;~i:>;:;:::::::::::>::::::::::::::::::::::::::::::::::~:::::::f::?:-""''''''';'!"' ..... ~.:~ ..... "' .... ~-....... -.......... -."" ..... ~; .. -· .. " .. ·f!'" .. i .. ~5 '"' 4 d

A

Fir A4.2lA. Dynamic wheel load dia~ram, high frequency oscillation, l1S 134 over Brazos River (Lubbock), old structure, end of bridre .

A 131

137

172

160

138

171

150

153

156 160 -- ~

N V1

Page 134: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

· 0 IS ~ S.OO~ I-

~ 4.00L~ w 3.00 I

~ 2.00t ~ 1.00

~ 0.00 a.

30 I

4S 60 I I

~ .......

HORIZONTAL DISTANCE (FT.) 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

I I I~ I I I I I

'" MAX. VEHICLE V A

g. 40 I , 2 i.

I 55 2

BRIDGE~LAB _.

- I _1~!~I]~~:I;111!!jl: " , I LOAD (0/0)

i 128

127

165 157 -

I

~ 40;

lJ3 55 2

3

I

2

r140

:' I

U3 55 ~ 4

5

A

Fir. A4.2lB. Dynamic wheel load diar,ram, low frequency oscillation, US 84 over Brazos River (Lubbock), old structure, end of bridge.

,

121

170

178

149

236

256

131

137

172

160

138

171

150

153

156 160 -----I

'""' t.,)

0\

Page 135: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

tE

Ll 4 Ll3

HORIZONTAL DISTANCE (FT.' -; 2000 15 30 45 60 75 90 105 120 135 150 165 180 195

I 210 225 240 255 270 285 300

=. I~ ... l: C) 1.00t-w ::r w 0.00 ~ ..J

"""" Ia.. 0 a:: -1.00 J- . ~-

.... n.

ffi 40 ~ I

557

I

40~ 3 j -

ct: 55 2: j

3 , I

.o~ 5 -I

55ff 5

Fig A4.22A. Dynamic wheel loa~ diR~ram. high frequencY o~cillation, US 84 over Brazos River (Lubbock), new structure, start of bridge.

I I

MAX. LOAD(%)

==, 123

131

141

142

127 j I 141

145 135 154

160

139

128

141

134

167

157 144

172

151 162 - ....

N .......

Page 136: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

i 2000 15 30 - . p::; .-:r CI 1.00 I-w :r w 0.00 ..J

Lt.. 0 a: -1.00 I-a..

IVl"A . 40~

2

I 551--

2 i I

40~ 3

I

55~ c1 3

I

40~ 5

A )

-1 ........, 2

B 05

1 : 5

Fig A4.22B.

HORIZONTAL DISTANCE (FT.) 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

~ I I I

~.~ --....

lTTTll -.J

j

j

Dynamic wheel load diagram, low fre<luency oscillation, US 84 ever Brazos River (Lubbock), new structure, start of hridpe.

, I

MAX. LOAD(%)

====, 123

131

141

142

127

141

145

135

154

160

139

128

141

134

167

157

144

172

151 162 ----'

..... N 00

Page 137: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.)

i o 15 30 45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

.... 1.00 l­x (!)

. I I I I I I 1

I&J 0.50

; 0.00 ~ ~~ ~

LL 0·0.50 a:: Q.

MAX.

VEHICLE V A BR1DGE~SL.~_~. 1--

~ ::! 111!lliii!!!i!i!I!I,:.:;..:[ __________ +-_

IOAO(%) ...,

LJ

r1

I t--

40 2

3

I

55m

:3

I -2

4013,

4 -5' A

lJ 55[ oO""-_----'----''---I _______________ j~jjl~::~:~ll::~:~::~l:i:::::::j:~::~·~:-:·:~~::l~l::~l~:l::::::::jl::l~ll A 5

Fi~ A4.23A. Dynamic wheel load diarram, hirh freqllency oscillation, US 84 over Brazos River (Lbbbock), new structure, end of bridge.

132

133

138

135 -

122

156

165

137

157

157

133

143

158

140

143

154

138 151

151 155 ------I

..... N \0

Page 138: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

~ ~

o z

~ 1.001-C!)

1!5 T

30 "T

4!5 T

60 T

75 T

~O"O~A ~ 0.00 1.1.. 0-0.50 a:: Q.

90 T

HORIZONTAL DISTANCE (FT.) 105 120 135 150 165 180 195

I I

~~L~ ~ I

'II

210 225 240 255 270 285 300 . I , iii ii' I I I I

,

Fig A4.:3B. Dynamic lo1heel load diagraM, low frequ<.>ncy oscillation, US 84 over Brazos River (Lubbock), new structure, end of bridge.

Page 139: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.)

i 2.00° . 15 :-T

30 .- 45 T

60 -. 75 T

90 .- 105 120 135 150 165 180 195 210 225 240 255 270 285 300 I I I I I I I I I I I I I

~ 1.00 C)

w O.OO~----------------------------~----------------~~--------------------------------~ ::J: w -1.00 ~

u: -2.00 o g: -3.00

VEHICLE I V I A

~ ..

~

Li ~

~ 5i. I

40~ 3

SlAB~8RIDGE

MAX. LOAD(%)

====, 155

160

192

188

137

219

226

167

264

284

354

332

427

182

188

m..:::' 356 340

434

213 "'55 -

.,.J'hlCM'W A

A

j'.> I I m _'N •• _'= ,',','~', , ., LB 155~" "---"2 ... .zc.x, • 4 :~:/:L",_ .. ~4 __ ..... _ ... _ ...... _ ....... 5

Fig A4. 24A. Dynamic wheel load diilgra!1l, hip,1I frefluency oscillation, IH 45 over South Belt (Houston), start ofbridre.

~ w ~

Page 140: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) 4S 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

I I I

~B~8RmGE ~~----------------~~~

I T 2 r' ' -~;;::'i;;§mG=:= M •

: .. ',',' .. "';':-~::8~: 4013 r:~: :;;;:;::;::: :::::::::;.._ ..... . ~

B 4

I--5

2 L.B 1551 3 i--t---

~ 5

Fi~ A4. 24B. Dynamic wheel load diarram, low frequency oscillation, 1H 45 over South Belt (Houston), start of hridge.

,~:

MAX. LOAD(%) =j 155

160

192

I§.8

137

219

226

167

264

284

354

332

427

182

188

356 340

434

213 255 -

""" IN N

Page 141: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

o 15 z

2.00 l-X C)

L&J 1.00 x

30 I

HORIZONTAL DISTANCE (FT.l 45 60 15 90 105 120 135 150 165 180 195 210 225 240 255 210 285 300

I

~O.OO~--------~~~~~~~~----~~~~~~~~~~~~~~--------------------~ La.. o g: -1.00

~~~~r:lr~================================~~~==~~~~----------------~------------------------------~MAX. I, A BRIDGE LOAD(%l

:: li:~!I~!~~!~~!!li:J;~----------------t i 214

194

172

186

40 ~ r~: •• ·.~~ •••• ~.!;~~;;~~l~t~"'---------------I 185

171

239

183

315 Li 358

221

55 i _iii:~I·e"i3i'~~: .. "_a:IIIi:I.:;_ ..•. _e._--------

242

332

245

259

233

268

249

~

I I 1- .. _ .,- · ·~:iJ,10.Jtlr~~f:;3t.1rJ~1;;_idf%$3&fBt'MCgd MWPtkA I ~ 189 16 -

~ Fir A4. 25A. Dynamic wheel load diC1pr:lm, high freqllency oscillation, IH 4.'>

over South Belt (Houston), end of bridge.

~ w w

Page 142: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

..... 0 z r-~r-~r---~--~--~--~--~~~--~~~~-T~~~~~~r-~~~~~~--~~~~~

;2.00 :r: C)

W 1.00 :r:

~O.OO~----------~~~~~~~----~~~=:~~~------~~~~~--------------------~~I I.&. o g: -1.00

UlIlllA BRIOGE--tSLAB l~t:O(%l

jt(!1l~2~~(r~1~f!~~illi; ______ _ :.:««<-:-:.:-:.:.:.:.;.:.:.:.:.:.:. :':'~-:'>""» ..... .

j

j

j

::::::::::{::::::::;r::~:];:?r::::::: _~i",,,,,,,,,~,,,,,,,~'.J.,;'\,,,,,,,,., ,,;:;#;~

. __ :1 ~;~~~i·;-:~l·!~';-!j;l ........ ~_. ____ ~~ F" :C;::,.::g:,gg*etn::v:, ::::;z::t:::: :t' :~ ft.:; :~.;; ..... ~~~:;.'~:Jj\.::~>:.: .. :~:.:.'(':::::'::::~':::':'):~."" .......... '=' _ ~~+:4 •• t'd ':.".'.

- ;:;:;:':;'::::;:':;;;::::;:::::::{::::;:;:::::::::-:::.:::::::

'~;""'IIC1jI*&.i!ifF '*".; V'" . .. .••.... ;. ",. j - ~::::::::::::8~~::::r;:::::~::{\:~:;~::::t::: -*, : i!t@et'*::!u:;::::;u;;¢z;;ueX;tU'lt\d:;;;;:·z;m i •• J ':~i1~~~~:~~·~::;';:~~;:j;f·;:;:.:i~;~~] :: :::

-_._.., '~"IT __ ~l:;:::::::::::;:::::::::;::::::::::::::::::::::::

Dynamic wheel load diagram, 10H frequency oscillation. IH 45 over South Belt (Houston), end of brld~e.

I

214

194

172

186

185

17\

239

183

315

358

221

242

332

245

259

233

268 249

189 196 - ....

I..J .c--

Page 143: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) 30 4!5 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 28~ 300

I T ~ I 1

_~rJ .........- '-l

MAX. LOAD (0/0 )

lE ===, 174

197

194

190

163

219

314

189

194

192

--U~:8::::··:::<::::::::··'-:::::-:::::-::-· ..... " .... :.:.:.;.: :::::::~~ • • ____________________ .. _._IIl"Ir. ... ~, : ... " : ... :,:::=t: ?r,<.~:;:r;t t::;:,t:c~.=:;; ~J

- .. ·~~.::~I~«::.~~."':' .• ~>· .. -:I .. _;,.I;.;'I .•. f •• : ..... ':' ..... 1" •• :.~ •••• I.::f~':_;·..., ..... ~-- - - _._-- - .. _- - •• - •. - --LlI

ill.II.I .. d 190

Ai 177

189

169

228

203

194

228

198

.,

~~,~];;:~{i;i1;~~~iil~t!li _k~ft~n~:@~:.r:t~~/~~[iilfi[[ffffff~f~~~~~f~fff~ff~·

~ , B

:::::::i::::::::::::::::::;:::;::::::::::::::::::::::::::::::::::::::::::::::::: "14 -.... -----.... --..... -..L..----_________________________ ....Il_l:ll;io::il...i::~:-:~.;..Kri:;:;:;:-..:.:i·,,~,,:-:'_'-:_'-:·..:.;·.:..:·,,:·::.J·; ... · ____________________ ..... _.;:..;...

rig A4.26A. Dynamic wheel load diarrClm, hir,h frequency oscillation, SH 225 Shell Overpass (Houston), start of brjdre.

.... w V1

Page 144: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

Li ~

HORIZONTAL DISTANCE (FT.) 30 T

45 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

~ _ _ /\J

I I I

~~ ~ ~

'.LlL SLAU~BR10GE

!) e ,II jlgo:¢i .. :: ............. ~ ... ": .. .,.~.'.~:.:.~::-:::::-:::::::~:::::: J . ltt:.·}.gW:~%r~~t ----------1

.:-:.

~( :-:: ,- :;·:!:r.":rathi:ig ... w. :~~~:::;::::~.... ,

FiF A4.26B.

~nj=])"~Z

-'-

-'-

Dynamic wheel load dinrrnm, 10\0' frc(1t1ency oscillation. Sit 225 Shell Overpass (Houston), start of bridre.

MAX. LOAD(%)

====, 174

197

194

190

163

219

314

189

194

192

190

177

189

169

228

203 194

228

198 214 - ....

W 0\

Page 145: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

g

Ll ~

B

HORIZONTAL DISTANCE (FT.' 4~ 60 75 90 105 120 1:35 150 165 180 195 210 225 240 255 270 285 300

I

__ f..ZZZZZZZ~ BRTDGt: ~SLAB

IMAX. LOAD(%)

'~.:.

195

220

196

219

202

204

251

208 j

... ~.:IOI:1:::l~~ ..... 189

~~.w...~" ~ . ., 194

245

183

209 187

237

218

181

263

288 • I HI' =_:.=." ':-:-:,:-:,:-:;:-:·:-:·:-:-:-;;:-:-:i:-:-:·:-:-:-:-:-:::-:·:,:-:,:-:;:::::::':::-:-:':-:-:1 ~.-' • "751 -Fig A4.27A. Dynnmic wheel lo"d uiaprnm, hir-h frequency oscillation, SH 225

Shell Overpnss (Hotlston), end of bridf!c.

, .... \..oJ '-J

Page 146: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE CFT.)

i 2.000 IS 30 ,- 4S 60 75 90 I

105 120 135 150 165 180 195 210 225 240 255 270 285 300

~ 1.00r (.l)

w 0.00 J:

~ -tOOt-iA: o-2.00~ a:: Q.

I I I I I

~- _A --"-~ -

\/ VEHICLE rvrA BRI DGE---a--I SLAB ...

I 40t-;-

1551 ~ I

40~ 3

I -55~

Ii ::::::::::::::~::~:::~i::~~·:.···r-·~~~:~~~~::~:,:~~~::0~

.----.. rft:::~ ~:-..... ~ ...... f""~.'rrl"!'"".,.l

I ' I ---"~~=;"

A Ll 3 , -2

40~ 5 -~

"'I .... r'I".y.~.:.:.'" .... ~~.N'.,.: ::t'~"" •. ..:.;.:::.;.:~ ~.t QFC.;;!&~22~2L~:::t:~:2E:~g:~:±~

')mG3ml&@ Wi 9*_.j __ # .. =!~~1,;;~~~1~;;!11t~ A II l) II V ~ w~~~"...,..;;.; .• ".=~ .. ~""" LD 55:; ~=:==:'==~~~f2:2~~:;ifi~"'~':~~;d

Fig A4.27B. flynamic wheel load diagram, low fr£'qu('ncy oscillation, SH 225 Shell Overpass (Houston), end 0:0 hridre.

MAX. LOAD (0/0 )

===, 195

220

196

219

202

204

251 208

189

194

245

183

209 187 237

218

181

263

288 351 - ....

w co

Page 147: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

j

LJ ~ lJ

. 0 15 30 45 60 75 90

§ 3.00 l= , I I I ... ::r ~ 2.00 ::r

~

HORIZONTAL DISTANCE (FT.) 10~ 120 135 150 165 180 19~ 210 22~ 240 25~ 270 28~ 300 I I I I I I I I I

UJ 1.00 oJ

LL. o O.OOl-----------"'or-...,-..-­a: Q.

VIA SLAB~- BRIDGt: ~~t:';(%l - uIL

BRIDGE---.-.fSLAB

:: ~·lS~=· ~:rx:L'"

, 40~

3

I

55~ 3

+ ' .. :1£'11

~::~~:~~;.~~:~::;::t~~~~~] .' . f.-.... ...-. _.............. ..~ ... ::;!:qg:N4§4+i2i );BiJilllifti'!Uimll :.:.:-:.:-:.:.:.:.:.:.:.:.:.:.).:.:.:.:.:. ; ...

c=-------,. r-"I ~; .... ~~.' •. '"""",;,~~ dl .... « •• ' :c .. :w:&tcZC .... ZOiItlt .. :.i!':tJ:cIilU'l3!CW

E:· ~S:~:s=S:: .. .' .. ' -:.;.: ............ :: .. : ... :-.<: ... <-:.:.:-----------.... -- • pO.".; .4F,4 W;;;;; 7'! <f,ue;:." F -.~ .. - .... -~ :oJ

'" I , ,.,~ ... _.. * .... ~ 'rl 'ft '*1 MH ~~··, .... 1!ttt'8*,..··4. M ... ·i>ihtLQ "*+"" 'P' ...... _...... r» ee eril

1--~5;....j b .. ,,:. ,'.' :,.:, ..... ~:.:= , 551 ~

.~~

I': &lli:t::'...L.._, _~~,:",~~~"'".'!"'j~

~::Il

Fig A4.28A. Dynamic wheel lond diagram, hip-,h frequency oscillation, SlI 225 over

Scarborough Lane (lIflllS ton) .

, 307

245

305

257

217

322

302

230

324

321

271

449

348

337

300

294

351 410

305 295 -

~ I..J \0

Page 148: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

~

~ 0 15 30 45 60 75 90 z l- I , I :; 3.00 t-:t ~ 2.00 LtJ

HORIZONTAL DISTANCE (FT.) 105 120 135 150 165 180

I I I I , 195 T

210 225 240 255 270 285 300 I I I I I

~1.00 ~ ~ ~ ~O.OO V .Jo.

SLABJ--- BRIDGE

~ ~MAX ~OAD(%)

I BRIDGE=---4 SLAB

307

245

305

257

217

!!jlj~~~:lll.:I~lll·il·l·:::I~·:I··ll:!~lll·!l.:·j·~::1'1:111 322

302

230 :~:~:~~jJj;~~~~i:~t~i~.S~}Jt~~tk.l..~!Ii:::"" _________ ---------------1 .;1~~··.~.· ... 1·1~1~:~·1;::1:"'1:.:.;.~:~""~~1:.:.~1------------------------4---::::..:::...:...-1

-:.:.:.:-:.~'.:-:::::::::::::::::::::::::.:.:.:.:-:-:-:.:-:.

324

321

2 b-.A . . . ;i.wr.. :{nr:?::::):::?}??/=??~ 401 3 ~:=:~~::~::::'~!:==~:_'::_::.;::':':::.:".::::.;.':::;:: .... :: .. :;.:"~':~=~::1IKII ... ::iIIai= ....... ___ -Ij

4 I--

5 A -an' 'S'.' d: ; .. ~~~::':~~:l~:~3:::~~::~:::~:~:.:::~·-~~::~:·~~::~~· .... ~D A &:iEL~~;:t::~::~::::::~:::~·::::-::~::::::~~::::~::::::·::~:~~~~C~lCRCSc:t +wi a:;:.::-=:;;:;-;:-~~~

271

449

348

337

300

lJ 55 ~ L ,,~~~~~]~~i~r;i~~,,:~~riii!?~~~~~=~::: , ,5 j """",,,"",.4< ... ~~ M,. ,,_.~ ",' .. ..,....E;~~~

294

351 410

305

Fig A4. 28B. Dynamic wheel load diapram, low frequency oscillAtion, SH 225 over Scarboroup,h Lane (Houston).

~95 - f-I ~ 0

Page 149: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

t Li

i 1.000 ..... ... ~ 0.50 w %0.00 w -' ~-0.50 IX 0..

V A

40 I

2

155

12

I

40 2

3

I

55 2

SLAB

HORIZONTAL DISTANCE (FT.) 105 120 135 150 165 180

BRIDGE BRIDGE

:?f:'J.'::~::::::_::;~:~}::~~:?~:\\

•• IiI ••••• Wi; ••• IIII·.s::I·I#IIl-II .. Ei;iI~aC;"l:IfwlZl.I'il'III-.;65&, •• _ ...... IIIH.III'.IIIIWS.iIII'lell-II:I-.III-···I1:"I::::~ili~~:'!'f~!~~!-:r~:~j~m~tam~~t~%:

---------~----------'.' •• <

MAX, LOAD (0/01

=====, 175

1!!i7

174

ill 154

195

233

193

237 . ) \~:~:::::::(:::::::::::::~:«~:~t-:

I - Hi"WEE i"'F&¥*Cw., ,. 5 "'! •• 'SIMi '18'1 ~J'l+r-Pl-t,...,,~.,.,~.fo1.~

A 1111 I":"! ?38

2

40t! 4

5 1

2

55n 4 5

~~~#~J.#:~:~:?~rf

______ tffi~l~~~~ll~jjll~~i~~jl

1~;I~~!~~im :.~~" ... ~ ................... ~ .• ~" ......... l :~w~:~:~::~:~#~:·::::;;:~:~:~:·::::

FigA4. 29A. Dynamic wheel load diar.r:11", h1"h f"e'1ut:!ncy oscillation, South Loop over Calais Street (Hotlston).

189

164

216

192

234

171 193 256

180 201 - ....

,t-. I-'"

Page 150: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) 105 120 135 ISO 165 IBO

SLAB BRIDGE BRIDGE SLAB ___ I1:11 _____________________ ... ______ Jtt::!);~M~:~in

175

----------------------------~r(ti~~~t~;;~~~~~~:I!l~l~I 157

174

-4----~--~---------------------------J----.............. --------~~-.. --.... ----.. --~-.. - .. --.. ~II..~;~.Ii;1!~Jlj:;:;it~~~1:~.:~------~ 171

154

. I~~t~~!~~];~~~:f.i.~ -+-_______________________ -.;l~jl!ll~~:ll~\!~![l!!!~.·.· .. II! i..

______________ .. ___ "" ... _______________ I01· __ ...,,:;~:j~:~:::::::::,::::::::\~::t::£}:&:

:::~~(:~:~:::::~:~:::t::~\~~::\}::~~:::~:~:::·' -------___________ :~.::.!: ':,;: .•.. _~ .. :: .. ~~.:.:::~~~:.~tl

::::::::::::::::~::t::::::::::::::::::::::::::::::::::::::::

------_-·----·N·IUIEl---r.l----==----.. ---..,!S;:~;~:;:::.>:,~,::;~,.<::>~::~:':;;::;,; ... • SUA we' .1i&&IJ&iZf::~:::~.:;::::~:::::::::?:·~:::::::~::j::::;:8}:;.:

MiiW:;;;"ljL:;;"~ .. ~JC::_::M!II.~';: ~L, ...t~~ =~~-:;,,;~~"::'::::~':':':"'~:~'.::~.::'~"~ ~·::~·:~J .. ~~1 .:.:.:-:.:.:.;.:.:.:-:-:-, .... :-:.:-:.:.:-:.:.:.:.:-:.;.:-:.:.

ussww: ••.• _;:::::: .. ,';.;'; ~~ . .' ~~~~:.~.~.~';;'.'-\',: .. :;..J _em__ _ ill':-~::_:: .. ~·:·:·;·:-:.;·:·;:::··:· .. :·:·:::·:·:·~···:·:·;·:;;::-;.;.;~'

-..~-...... .............. ~~~ ~,,,,,,,,,,',,~.

195

233

193

237

238

189

164

216 192

234

171

193

256

180

.?QL 'IL~~~:~~~~:~:~~ .' t_:S;tPII

_________________________________ ................. + ............. .........-.._~4._ .... H .... ~~:x:: .. i.· ....... a:::L3i .. ~.......,...; ............. ..:..._...{~_~;..~:~~~

Dynamic wheel load di;)tr;1M, low frequency osci ll;)tion, South Loop over Calais Street (lloustlm).

..... ,s:,.. N

Page 151: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

i 2.00°

~ 1.00 C!)

W 0.00 :r ~ -1.00 LL. ~-2.00 Cl.

HORIZONTAL DISTANCE (FT.) 10!S 120 135 150 165 180 300 --,

I I I r77"I"q'W~ ~J/77177ZZ2i IMAX.

"",:,:":::,,:,:,:,:,,,:;:;S":;%= 8RIDG~ BIiIDGE%~",.,.,:,:.,:~~ LOAD CYo1 VEHICLE 1 V 1 A

i 140

12

1 !S~

Ll,40 13

15!S~ 3

=B~r I~~~~;~;,~:~;:~~ !~~

Fi~ A4. 30ft.. Dynamic wheel lO<ld diagram, hip.h frequency oscillation, South toap over SH 288 (Houston).

204

169

273

303

17!S

242

270

J--I ~ w

Page 152: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

i 2.000 .5 30 45 60

T 75 T

90 T

HORIZONTAL DISTANCE (FT.) 105 120 135 150 165 180 195 210 225 240 255 270 285 300

I • I 1 I I

~ IDO <:)

w~OOI-------------------------------'~----------------------------------~~--~------~ ::J:

~-I.00 ~ I&. 0-2.00 IX 0.

VEHICLE I V I A SLAB I--- BRIDGE BRIDGE----I SLAB MAX. LOAD (°/01 ====, 222

191

213

- D4

169

Ii ::t! 111illl~, j I" J....: ....... ----------------... ~tJf.;;~.~: ,l ... :: . ...,· ... ,'!.)::·,.:~~~:· .. ~; . .:·~~u

d ~

B

-j

":'j 401~

4 La 5 I

j

j

, 121,

55 3 ~~~i;f:~[i~;·~:E};::~i·~!~~~~~jfj:i~~ri~~~!t.L -:---- :/;.:~~;}=:~~ ~;: ~ i~ ;~;::~:;;':: ::~F>:':":'d:': ::-::-':::-.:::: ~ :-:a_ ,,- '-,

;... - ....... *b ... ~ ...... ____ ......... )...r.~ .... .a....;.--........"", ............................... ~f .... _.1M.d'MM u ,k ....

j 1

Fir, 1\4.3013. nynamic wheel load diaf!ram, 10\-1 frequency oscillation, South Loop over SH 288 (Hollston).

j 273

j 303

175

242

270

205

232

222

247

231

229 254

262

259 233

r-o J:'­.t'-

Page 153: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

VEHICLE

i LJ r'-1

B

HORIZONTAL DISTANCE (FT.) ..... o 15

T 30 T

45 ,- 60 T

75 T

90 T

105 120 135 150 165 180 195 210 225 240 255 270 285 300 z I I I

I-~ 0.50 LtJ ::J: 0.00 I-_~L-_____ ~

LtJ ...J

~-0.50 0: Q.

VIA = I

407-

-I

55~

I

40~ 3

2

40 3

4

5 I

~5m 5

SLA8 lOGE BRIDGE ---I SLAB

A

A A

Fir, /\4. 31A. Dynamic wheel load diagram, high frequency oscillation, North Loop over ~cCarty Road (Houston).

'MAX. LOAD (O/ol ----.,

167

164

163

178

146

180

201

179

165

174

159

171

179

207

195

191

177

194

211 213

~ .to­\J1

Page 154: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORllONTAL DISTANCE eFT.} .... o IS 30 4S 60 7S 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

VEHICLE

iE c1 fB

z I I I I I I

io.sot ~ft :x: 0.00 .... ~~~------~~~--~--~~~~~~--~~~~----------~~----,r----~~~~---------w -' ~ -0.501-a: Q.

V

40

55

3

I -2

.o~ I

SLAB 1-4-- BRI DGE

j

===-f1l1l1/J BRIDGS:;~SlAIi

lilillll'illllil !Ilii;il;illlllll~~ill f~lj·!:~·Ii1il:

...... '>."':".~ .. " •• ,,:.;.:.;.:.:.:.:-:.:.: i:~i:ili.Y1;~·:·

~ ~ ~~~~~~~ ~~~~~;: ~~;~~~

~f:EDt~; ~ 150~j

5 .i_oi:iIi ••

Fig A4. 3IB. Dynamic whee] load dia~r<1m, low frequency oscillation, North Loop over t-fcCarty I{oad (Houston).

MAX. LOAD<%} =t 167

164

163

!1§.

146

180

201

179

165

174

159

171

179 207

195

191 177

194

211 21L

I-' l:'-CI'

Page 155: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FTJ _ ' 0 30 4S 60 15 90 105 120 135 150 165 180 195 210 225 240 255 270 28S 300 Z O.SO I ,j i r 'I r I j , I I f 1

.... :r ~ 0.00 w :r w ~-0.50 lI. o a: 11.

MAX. T VEHICLE V A - sCAollIIIE3RIDGE . . , __ n

I nAO (%)

=. 154

151

136

,2

g I

4°1~ 55 2

:::::;:::::{:::::::{:::::::::;:t I~

U

0

18

0

,2 [j

I

40~ 3

I

55P=

3 0

il:I!!!~!II';l~ ::

,4

143

, 1

11

16

,3

18

~ ~

40~

~ 5

L ____ L---I'--....L. ____________________ --I.'* __ ...... _~·!I~!;li; 1~ 14

9 )3 --

LJ 155~ 5

Fig A4.32A. Dynamic wheel load diagrnm, high frequency oscillation, IH 10 over West Belt (Houston), stnrt of brldre.

I-' ,s:,.. .....

Page 156: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL OISTANCE (FT.)

- 0 Z 0.50 90 105 120 135 150 165 180 195

-I-:l: ~ 0.00 LrJ :l: LrJ

=-0.50 1.1.. 0 0:: 0-

MAX. VEHICLE V A

40 I

t! 2 .. , , ~ .".'

55 2

IOAO(O/o) '9

154

151

136

152

SLAB 8RIDtb. ,--==--- ;"."';r;.;" •• ; •. ,.r;.":"':" • ...-.:f'.l':':":r:r.J'.:::r ••••. ~.:'.~t:.,.

A

141

L140 · 155~

180

198

130 IG2 J

3 170 I - 164 2

40~ 143

171 4 - 157 5 186 I 163 2 - 158

55~ 4 -5 --I-

194

179

20L ___________________________ .l:;~,_t .. :!.,;,-_~~~i;;~;iji;It·;:~2tD,;~;;;;S~: LVv I

Fi~ A4.32'B. Dynamic wheel load di<lgra!11. low frequency oscillation, 111 10 over l\l'est Belt (Houston), st.1rl of hridp.c.

I-' .t"-eo

Page 157: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) - o I~ 30 4~ 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300 z I i I I I Iii iii iii iii i i

~ 1.00f-C)

~ 0.5°F __ _ ~ 0.00 "-

LL. 0-0.501-a: a.

. ~ • J\ .~ -~~v

VE HIClE V A B R I DG E ---I SL A ~''''':'====-==.::===='''''''''====='''''"''===-==-==I=='''''

, i :: t ~:lli~]I;!lli1ji!;J ,.

ri

40 ~ ~;~: •••••• • ••• ;.·.·· ••• ·.·'!.·.i~ __ ~~:::.."i:l::iI:!I!l~[Di:J,'Z5i2ilEJt'!ll __ .. __ .... __ ....j

~~~~;.~~~.1~;~:0~:-:.~: ____ :::.:::~t:.,r.:.......:..v ... :::~::l.~~'~~' :::t:imICI!IIZISal .. _______ -I

I

2

40 3

fig A4. 3:!A. Dynamic '~heel load diarr<lnl, hlf",h fn.'ollL'ncy oscillation, IH 10 over West Belt (Houston), end of bridge.

Page 158: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) -::i o 15 30 45 60 75 90 10~ 120 135 I~O 165 160 195 210 225 240 255 270 285 300

~ 1.00 t!)

j I Iii I I I I I r I I I I J 1 i I

~ Q50~::::~~~~~~~==~ ____ ~~~~~~~~~~ ______ ~~~~~~~~~~~~~~~=-______ ~ ~ O.OO~ LL 0-0.50 a: 0.

VEHICLE I V I A SRI DGE "IS~AB

I ~ :: t : I 11illl!I]llif~fl!:·~tjt,:---------------I Li ~

~ ...J~SiEili .. ,,:waz:ao;: ...... , .. , .•.. " ." .................... ".. -11

.o~ A -r:;!~:!:~~·!~.~~!~.~j!.~!I~"==--"----I!!1--"------1 A ~~~~f~~~~W~r~~!~ _ ..• --al:...c .. ·-----2<:.:.::>.::~:· E~_.~,~.~~:~~.; .. :·.·.;.:~.:·:.

::::::::::::::::::::. U31553

Fig A4. 33B.

",-"-, .. ~,,~,,," .. :~l~i:~E

Dynamic wheel load dia~ra~, low frequency oscillation, IH 10 over West Belt (Houston), end of bridge.

MAX. LOAD(%)

===, 186

152

191

164

155

194

228

158

206

'.)~I

192

179

187

184

181

187 214

228

203 239 - I-

VI 0

Page 159: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.l ; OF I 5

30 45 60 15

T 90 -,. 105 120 135 150 165 180 195 210 225 240 255 210 285 300

1.00

~ 0.00

~ -1.00

~-2.00""

~-3.001-a: Q. -4.00 .....

1 I

~ I I

I ~

MAX. I -

I nAD (0/0) ..., VEHICLE V A SL48E]~tDGE 1--';;;

40 ~ 11'tt~';j,!~i),'i:;ilit~,~~ -= \1 I ~:f?;:::::::::::::;::;::;:;:::;::{:::::::r;{:t~:::: j 55 2

Li ~

I

40~ 3

I

5512

3

U ~5~ Fi~ A4. 34A.

, A

,

I

, ~

Dynamic wheel load diagram, hiRh frequency oscillation, North Loop over Railroad (Hollston), start of hridge.

116

113

164

119

IBB

213

213

115

191

211

225

291

2B6

191 216

256 210

200 23B

251 --- ..... VI .....

Page 160: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.) 30 ..,.

; O~15 45 60 15 T

90 .- 105 120 135 150 165 180 195 210 225 240 255 210 285 300

1.00

~ 0.00

I&J -1.00 x ~-2.001-

~ -3.00 I-0: Q. -4.00 t-

I I I I I I I I ~I _ t

I

~

A

A

, ~ c. M'3 !','~:;':;!:~0i::~~~~-=::::::- ~

______________________ ...;·IIl,~~·~~·~.l~:J"'~~~ ......... ' .. .... c· &m,." ..... , ',.')\"0 ' .....

Dynamic wheel load dlagram, lov, frequency oscillation, North Loop over Railroad (Houston), start of brid~e.

MAX. LOAD (0/0)

==-, 176

173

164

179

188

213

273

175

197

211

225

297

286

197

216

256

210

200

238

257 - ..... V1 N

Page 161: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

i 1.000 " T

~ O.OOr.:!

x -lOO~ ILl .J

li:-2.00 r o 0: Q.

HORIZONTAL DISTANCE (FT.) 30 4~ 60 75 90 105 120 135 150 165 180 195 210 225 240 255 270 285 300

I~III ~ -~ ~~-\ --

MAX. , I.

VEHICLE V A BRI DG~'":'"~"?_Lc.A~9_ -'7~. •• ,-

LOAD (°/0) =-,

, Ll '4012 I I"

155 tt

3

I

~ 40~ -I

B 155m A 4 -5

Fir. A4. 3SA.

.. ~-......... ~.--~ .....

A

.. i q, •. .1 ..... f •. ~ ... ~ .............. _.-..... ..... l-.:JW...-l-:. .....

.. .::-·~:H-~-::-~:;:,==~;.-:::;1m

l l

Dynamic wheel load diAtram, high frequency oscillation, North Loop over Rail road (Houston), end of hrldt;c.

145

168

162

174

133

151

163

166

271

301

160

155

172

136

148

183

165

176

209

2~ ..... I.n W

Page 162: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

HORIZONTAL DISTANCE (FT.)

i 1.000 15

T 30 45 60 15 90 10~ 120 135 I~O 165 180 19~ 210 225 240 255 210 285 300

~:f " ,

LJ Ai

B

.... l-

X O.OOp ~. w x .1.00 w ..J

ii: -2.001-o 0: Go

1 -5512 --3

1

2 I ----.

4013 i

] 5

i I I I

~I.~ ~

~~( .....,.

fl11l7/A

j

.&

LB 155E§~-:=:=~.d;~~;'::~~~,c. __ .=.: "':: :~;~::._;_::-::;~.::=-=::~~ 5: . ?OML~ WI

Fig A4.3SB. Dynamic wheel load din~rn~. low, frequency oscillation, North loop over Railrond (Houston), end of brlclre.

MAX. 1040 (0/0)

=-r 145

168

162

114

133

151

163

166

271

301

160

155

172

136

148

183

165

176

209 265 - I-'

\J1 J::-

Page 163: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

-.~ ....

REFERENCES

, . 1: "Pavement Rehabi.1itation-Materials and Techniques," National Coopera­

tive Highway Research Program Synthesis of Highway Practice (NCHRP SYN) No.9, Highway Research Board, 1972.

2. "Bridge Approach Design and Construction Practices," NCHRP SYN No.2, Highway Research Board, 1969.

155

,3. "AASHTO Interim Guide for Design of Pavement Structures - 1972," Ameri­can Association of State Highway and Transportation Officials, Wash­ington, DC, 1972.

4. "Dynamic Studies of Bridges on the AASHTO Road Test," Special Report 71, Highway Research Board, 1962.

s. General 1'1otors Corporation, "Dynamic Pavement Loads of Heavy Highway Vehicles, '.' NCHRP Report 105, Highway Research Board, 1970.

6. Kaplar, C. W., "Phenomenon and Hechanism of Frost Heaving," Highway Research Record No. 304, Highway Research Board, 1970, pp. 1-13.

7. Jessberger, H. L., and D. 1. Carbee, "Influence of Frost Action on the Bearing Capacity of Soils," High\.;ay Research Record No. 304, High~.]8y Research Board, 1970, pp. 14-26.

8.

9.

10.

11.

12.

• " ,,!

McCullough, B. F., and T. F. Sewell, "An Evaluation of Terminal Anchor­age Installation on Rigid Pavements," Departmental Research Report No. 39-4F, Texas High\.;ay Department, 1966.

Yoder, E. J., and M. W. Witczak, "Principles of Pavement .Design," Second Edition, John Wiley & Sons, 1975.

Hopkins, T. C., and R. C. Deen, "The Bump at the End of the Bridge," Highway Research Record No. 302, Highway Research Board, 1970, pp. 72-75.

Moore, L. H., "Summary of Treatments for Highway Embankments on Soft Foundations," Highway Research Record No. 133, Highway Research Board, 1966, pp. 45-59.

"Treatment of Soft Foundations for Highway Embankments," NCHRP SYN No. 29, Tran~portation Research Board, 1975 •

Page 164: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

13. Johnson, S. J., "Precompression for Improving Foundation Soils," Jour­nal of the Soil Mechanics and Foundations Division, Proceedings of the American Society of Civil Engineers, Vol. 96, No. SMl, January 1970, pp. 111-144.

14 • .Johnson, S. J., "Foundation Precompression with Vertical Sand Drains,1I Journal of the Soil Mechanics and Foundations Divisions, ASCE, Vol. 96. No. SMl, January 1970, pp. 145-175.

156

15. Landau, R.E., "Method of Installation as a Factor in Sand Drain Stabil­ization Design," Highway Research Record No. 133, Highway Research Board, 1966, pp. 75-97.

16. Hopkins, T.C., and G.D. Scott, "Estimated and Observed Settlements of Bridge Approaches," Highway Research Record No. 302, Highway Re­search Board, 1970, pp. 76-86.

17. "Construction of Embankments," NCHRP SYN No.8, Highway Research Board, 1971.

18. Nelson, D. S., and l-1. L. Allen Jr., "Sawdust as Lightwe:f ght Fill Mat­erial," Public Roads 39-2, Federal Highway Administration, September 1975, pp. 63-67.

19, Lea, N.D., "Highway Design and Construction over Peat Deposits in Lower British Columbia," Highway Research Record No.7, Highway Research Board, 1963, pp. 1-31.

20. Gray, D.H., "Properties of Compacted Sewage Ash," Journal of the Soil Hechanics and Foundations Division, ASCE, Vol. 96, No. SM2, Narch 1970, pp. 439-451.

21. ~!argason, G., and J. E. Cross, IISettlement Behind Bridge Abutments, The use of pulverised fuel ash in constructing the approach embank­ments to bridges on the Staines By-pass," RRL Report No. 48, Road Research Laboratory, Eneland, 1966.

22. McLaren, D., "Settlement Behind Bridge Abutments, The performance of a medium-clay fill used to form the approach embankment to a bridge on the M.1 Motorway," RRL Report LR 76, Road Research Laboratory, England, 1967.

23. McLaren, D., "Settlement Behind Bridge Abutments, The performance of a silty clay fill in an approach embankment on the M4 Motorway," RRL Report LR309, Road Research Laboratory, England, 1970.

24. Cross, J.E., "Settlement Behind Bridge Abutments, The performance of a uniformly-graded sand fill in an approach embankment on the M4 Motorway," RRL Report LR3l0, Road Research Laboratory, England, 1970.

Page 165: Roughness at the Pavement-Bridge Interface · 3-8-76-213, "Roughness at the Pavement-Bridge Interface." It includes sum-maries of pertinent literature, methodologies for measurement

..

25. Margason, G., "Settlement Behind Bridge Abutments, The performance of a stony-clay fill in an approach embankment to an overbridge on the M4 Motorway," RRL Report LR31l, Road Research Laboratory, England, 1970.

157

26. Wise, J.R., and W. R., Hudson, "An Examination of Expansive Clay Prob­lems in Texas,lI Research Report 118-5, Center for Highway Research, The University of Texas at Austin, 1971.

27. Grover, R., "Bridge and Approach Settlements Cured by Major Design Revisions," Rural and Urban Roads, July 1978, pp. 63-65.

28. Harris, F .A., "Asphalt Membranes in Expressway Construction," High1vay Research Record No.7, Highway Research Board, 1963, pp. 34-46:

29. Hu, Y. C., "A Study of Roughness at the Pavement-Bridge rnterface~" M.S.E. Thesis, The University of Texas at Austin, 1977.

30. Spangler, E.B., and W. J. Kelley, "GMR Profilometer - A Nethod for Measuring Road Profile," Highway Research Record No. 121, Highway Research Board, 1966, pp. 27-54.

31. Hudson, W.R., "High-Speed Road Profile Equipment Evaluation," Research Report 73~1, Center for Highway Research, The University of Texas at Austin, 1966.

32. l-lalker, R.S., F.L. Roberts, and W.R. Hudson, "A Profile Neasuring, Re­cording, and Processing System," Research Report 73-2, Center for Highway Research, The University of Texas at Austin, 1970.

33. AI-Rashid, N.r., C.E. Lee, and W.P. Dawkins, "A Theoretical and Experi­mental Study of Dynamic Highway Loading," Research Report 108-lF, Center for Highway Research, The University of Texas at Austin, 1972.

34. Wu, Tsu-Long, "Roughness at the Bridge-Pavement Interface," M.S. Thesis, The University of Texas at Austin, 1979.


Recommended