1 Route 146 over the Mohawk River Design – Build Project Public Information Meeting October 14, 2015
Transcript
Page 1: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

1

Route 146 over the Mohawk River Design – Build Project Public Information Meeting

October 14, 2015

Page 2: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

2

Introductions Project History Purpose of Meeting Major Work Elements Project Schedule Construction Details Design Approval Considerations Questions and Answers Contact Information

AGENDA

October 14, 2015

Page 3: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

3

Introductions NYSDOT Local Officials

Town of Clifton Park Town of Niskayuna

Design Build Team Tioga Construction AECOM MJ Engineering and Land Surveying Atlantic Testing Laboratories Ravi Engineering & Land Surveying Fitzgerald & Halliday

October 14, 2015

Page 4: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

4

Project History Transportation Needs Identified in Early 1990’s Expanded Project Proposal Approved in 1998 3 Public Meetings Held Coordination with Agencies

• Federal Highway Administration • NY State Historic Preservation Office • NYS Thruway and Canal Corporation • US Coast Guard • NYS Department of Environmental Conservation • US Army Corps of Engineers

October 14, 2015

Page 5: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

5

Project History Project Design Considerations

• Maintain Traffic During Construction • Limit impacts o Roadway footprint o River navigation o Pedestrian access o Visual impacts o Noise during construction o Historic properties

• Balance Cost against Safety and Impacts Design Approval Granted August 22, 2014 “Design-Build” RFP issued January 23, 2015

October 14, 2015

Page 6: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

6

Purpose of the Meeting 1) Describe the project, which will improve travel along the Route 146

corridor for all travelers.

2) Hear and respond to questions and concerns.

October 14, 2015

Page 7: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

7

Major Elements of Work 1) Replace the Route 146 Bridge. 2) Build a Roundabout at Route 146/Aqueduct

Road. 3) Widen Route 146 from Aqueduct Road to

Riverview Road and Intersection Improvements made at Route 146/Riverview Road.

4) Construct a Bike/Pedestrian Trail from the Mohawk-Hudson Bike/Hike Trail to the Town of Clifton Park Bike Route at Riverview Road.

October 14, 2015

Page 8: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

8

Schedule 2015 July-December

Design, subsurface investigations (borings), utility relocations and associated clearing

2016 April-December Bridge construction, foundations, roundabout construction using staged construction & temporary signals, bike trail, roadway widening, traffic signals, drainage, steel erection

2017 April – November Concrete deck placement, guiderail, bridge lighting, final paving, traffic shift onto new roadway, demolition and removal of existing bridge and foundations

October 14, 2015

Page 9: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

9

Bridge Aerial View

Replace the Bridge

Bridge Cross Section

• Avoid Conflict with Existing Foundations • Keep Piers Outside River Channel • Do Not Restrict River Flow

October 14, 2015

Page 10: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

10 Replace the Bridge

Existing Bridge

Proposed Bridge

October 14, 2015

Page 11: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

11 Construct the Roundabout – Stage 1 • Maintain Traffic During Construction

• Provide Pedestrian Access

October 14, 2015

Page 12: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

12 Construct the Roundabout – Stage 2

October 14, 2015

Page 13: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

13 Construct the Roundabout – Stage 3

October 14, 2015

Page 14: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

14 Construct the Roundabout – Final

October 14, 2015

Page 15: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

15 Construct the Roundabout – Final

Roundabout Typical Section

October 14, 2015

Raised Center for Trucks Two Lane

Roundabout Two Lane

Roundabout

Page 16: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

16 Widen Route 146

October 14, 2015

Left Turn Lane

11’ min. Median

4 – 12’ Wide Travel Lanes

Page 17: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

17 Widen Route 146

October 14, 2015

11’ min. Median

Pedestrian Activated Signal

Page 18: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

18

Roadway Typical Section

Widen Route 146

October 14, 2015

Page 19: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

19 Bike/Pedestrian Trail Connect Mohawk-Hudson Bike/Hike Trail with Town of Clifton Park Bike Route

October 14, 2015

Page 20: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

20 Bike/Pedestrian Trail

Connect Mohawk-Hudson Bike/Hike Trail with Town of Clifton Park Bike Route

October 14, 2015

Page 21: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

21

Traffic The Rexford Bridge and Route 146 will remain open to vehicles, bicycles and pedestrians during construction, with only minor disruptions. River navigation will be maintained during all phases of construction, except for limited, temporary restrictions during steel erection/bridge demolition.

Construction Noise/Dust Jack hammering, hoe-ramming, pile driving, blasting, bridge demolition and other noise producing activities (70 db max) limited to: 6am – 10pm & dust control measures must be in place.

Design Approval Considerations

October 14, 2015

Page 22: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

22

Tree Clearing Limit number of trees impacted

Design Approval Considerations

October 14, 2015

Page 23: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

23

Tree Clearing

Design Approval Considerations

October 14, 2015

Page 24: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

24

Tree Clearing

Design Approval Considerations

October 14, 2015

Page 25: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

25

Turning Lanes Center auxiliary lanes were added where possible.

Pedestrian Safety Measures Sidewalk was added from Main Street North to Riverview Road to allow crossing at activated signal.

Lighting on bridge and bike/hike trail Lighting for bridge, roadway and bike/pedestrian trail is being negotiated with Towns.

Screening/Berms/Barriers Existing berm at 1671 Balltown Road will be replaced in kind. Trees/plantings impacted by the project will be replaced.

Design Approval Considerations

October 14, 2015

Page 26: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

26

State Historic Preservation Office Coordination

Design Approval Considerations

Programmatic Agreement Reached on July 28, 2014

October 14, 2015

Page 27: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

27

Rowing activities No Impacts Anticipated

Design Approval Considerations

October 14, 2015

Page 28: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

28

T H AN K Y O U

October 14, 2015

Page 29: Route 146 over the Mohawk River Design – Build Project ... · 10/14/2015  · 1 Route 146 over the Mohawk River . Design – Build Project . Public Information Meeting . October

29

Contact Information NYSDOT has a website:

www.dot.ny.gov/rexfordbridge

Tom Hoffman, P.E. NYSDOT Project Manager (518) 485-9538 Email: [email protected] Bruce Samson NYSDOT On-Site Quality Assurance Engineer (518) 344-6137 Email: [email protected]

October 14, 2015