Jigme Namgyel Engineering College Department of Civil Engineering & Surveying SURVEYING LABORATORY INSTRUCTION MANUAL SEMESTER- II Compiled By: Department of Civil Engineering & Surveying Royal University of Bhutan
Transcript
  • Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    SURVEYING

    LABORATORY INSTRUCTION MANUAL

    SEMESTER- II

    Compiled By: Department of Civil Engineering & Surveying

    Royal University of Bhutan

  • Prepared By: Phurba Tamang, Associate Lecturer Page 1 of 5

    INTRODUCTION TO LAB PROCEDURES

    Field book: Example of field book is given in the next page

    All the practical assigned for this module will be carried out in the field. A record of each field practical

    shall be kept in your respective field book. Your field book shall be kept neat and orderly as it will be

    collected and graded periodically throughout the semester. Your field book shall include your name

    and group information on the first single page.

    Pencil only, preferably 2H drafting pencil

    Essential guidelines:

    1. The left page is used for recording data, while the right page is used for sketches.

    2. Erasure should never be made in the field book. If a measured value is recorded incorrectly, it

    should be cut by a horizontal line and the correct value should be recorded above the cut value.

    3. At the end of the day’s work, the notes should be verified and signed by the tutor or lab in charge.

    Practical Report:

    After the verification of field data by the tutor, every students should produce an individual practical

    report. The guidelines of the report shall be as per the practical manual circulated by the tutor.

    Note:

    Left page should be solely used for sketches and calculations or data representation written with

    pencil. Any theoretical aspects/backgrounds or results can be written on the right page

    Field Crews:

    Each student will be assigned to a 7 or 8 people crew. A crew chief should be appointed for each

    practical session. The Crew Chief will be responsible for checking out and returning the equipment at

    the end of the lab session.

    Survey Equipment:

    Equipment for each lab assignment will be checked out at the beginning of the lab and checked

    back in when the assignment is finished. Some important things to remember about the use and

    care of the equipment are as follows:

    • Much of the equipment used are very expensive and quite sensitive whereby great care should be

    exercised to protect the equipment from damage.

    • Instruments should be transported in their cases when taken to and from the field. These

    instruments may be carried on the tripod from station to station as long as they are held

    vertically at all times.

    • Steel tapes should be straightened out prior to being wound onto their reels. Care should

    be taken so that the tapes do not kink, bend or snap.

    • Malfunctioning equipment should be reported to the lab in charge or tutor

  • Page 1 Page 2

    Lab. 1: Title of the experiment

    Equipment: Eg. Ranging rods, measuring tapes

    Weather: Eg. Sunny

    Ground Cover: Eg. Grass

    Scale:

    Date: Group No: Example, A-1 Group No: Example, A-1 Date:

    All the data recording has to be done on this page (left page). If additional information are not sufficient on this page, you may use the next left

    page.

    Note: Use only pencil

    Use this section for sketching purpose and result inter-

    pretation

    (Use only pencil)

    Show direction of meridian

    Prepared By: Phurba Tamang, Associate Lecturer Page 2 of 5

  • Prepared By: Phurba Tamang, Associate Lecturer Page 3 of 5

    Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    Soil Mechanics & Foundation Laboratory

    LAB-1: MEASUREMENT OF DISTANCE BY PACING AND DIRECT RANGING

    Aim:

    • To determine the average length of your own pace.

    • To measure the direct distance between two end stations by direct ranging.

    • To familiarize with using a steel tape to measure approximate horizontal distances.

    • To become familiar with keeping notes in a field book.

    Theory:

    Pacing consists of counting the number of steps or paces in a required distance. Distances obtained by

    pacing are sufficiently accurate for many purposes in surveying. Pacing is also used to validate survey

    work and eliminate any taping blunders. Measuring your pace length requires a measured 100-foot

    distance. You then walk this distance and count the number of steps. It is best to repeat the process

    four times and average the results.

    By the various methods of determining distance the most accurate and common method is the method

    of measuring distance with a chain or tape commonly known by the term chaining. For work of

    ordinary precision a chain is used. But where great accuracy is required a steel tape is invariably used.

    The term chaining was originally applied to measure distance with a chain. The term chaining is used

    to denote measuring distance with either chain or tape, in the process of chaining, The survey crew

    consists of a leader (the surveyor at the forward end of the chain) and a follower (the surveyor at the

    rare end of the chain and an assistant to establish intermediate points).

    Ranging helps in establishing intermediate point between two points. Direct ranging is usually

    employed when two end stations are inter visible.

    Figure. 1. Pacing

  • Prepared By: Phurba Tamang, Associate Lecturer Page 4 of 5

    Figure. 2. Method of Direct Ranging

    Equipment:

    1. Ranging rods

    2. Measuring tape

    Instructions:

    1. The location for this lab shall be determined by the instructor.

    2. Identify two inter-visible points ‘A’ and ‘B’ and fix the ranging rods at points ‘A’ and ‘B’.

    3. Stand about 2 m behind the ranging rod fixed at point ‘A’.

    4. Direct the person at ‘C’ to move the rod to right or left until the three ranging rods appear exactly

    in the straight line ‘AB’.

    5. Sight only the lower portion of rod in order to avoid error in non-vertically.

    6. After ascertaining that three rods are in a straight line, direct the person at ‘C’ to fix to fix

    the road to establish the intermediate point ‘C’.

    7. Measure the chainage distance between ‘AC’ and ‘AB’. Add the distance to calculate the total

    distance ‘AB’.

    8. Use your normal walk to pace of each distance ( i.e.: 0 to 20 m ) for three consecutive trials.

    9. Record the number of paces for each trial in your field book.

    10. Calculate the average number of paces for each trial distance ( Refer the example given in Table. 1.)

    11. Count the number of paces between point ‘A’ and ‘B’ and calculate the total distance.

    12. Draw a detailed sketch of the measurement to a reduced scale in the field book.

    13. Replicate all the data and sketches in your respective practical notebooks.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 5 of 5

    Table 1. Sample calculation for determining Average Pace

    Trial 1 2 3

    Distance 0-20 m 0-20 m 0-20 m

    No. of paces 30 30 31

    Average no. of paces 30.33

    Average pace = 20/30.33 = 0.66 m/pace

    Observation and Calculation Sheet:

    Determination of Average Pace

    S. No.

    Trial

    1

    2

    3

    1

    Distance

    0-20 m

    0-20 m

    0-20 m

    2

    No. of paces

    3

    Average no of paces

    Average pace = ________

    Measurement of Distance by Direct Ranging

    S. No. Chainage Line No. of paces Distance measured by

    Pace (m) Distance measured by

    Tape (m)

    1 AC

    2 CB

    3 AB

    Result:

    By ranging and chaining the total distance between station ‘A’ and station ‘B’ is ____________

    By pacing the distance between station ‘A’ and Statin ‘B’ is ____________

    Precautions:

    • The ranging rod should be established correctly at all points.

    • The judgment of line should be taking correctly during the establishment of intermediate points.

    • Distance between surveyor’s eye and ranging rods (e.g. A, B and C) should be kept at minimum

    distance of 1 m.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 1 of 2

    Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    Soil Mechanics & Foundation Laboratory

    LAB-2: MEASUREMENT OF DISTANCE BY RECIPROCAL RANGING

    Aim: To measure the direct distance between two end stations by indirect or reciprocal ranging.

    Theory:

    When the end stations are not inter visible due to rising ground between them, or due to long distances

    between the end stations, ranging is carried out in indirect manner. Indirect ranging is generally used

    to lay out a line with inaccessible points or across a mountain.

    Figure. 1. Reciprocal Ranging

    Equipment:

    1. Ranging rods

    2. Measuring tape

    A

    C D

    B

    A B C D

    C1 D1

    C2

    D2

    D3 C3

  • Prepared By: Phurba Tamang, Associate Lecturer Page 2 of 2

    Instructions:

    1. The location for this lab shall be determined by the instructor.

    2. Identify two non-visible points ‘A’ and ‘B’ and fix the ranging rods at points ‘A’ and ‘B’.

    3. Choose two temporary intermediate points ‘C1’ and ‘D1’ between ‘A’ and ‘B’, such that the person

    standing at ‘C1’ can see both the ranging rods at ‘D1’ and ‘B’. Similarly, the person standing at ‘D1’

    can see the both the ranging rods at ‘C1’ and ‘A’.

    4. Stand about 2 m behind the ranging rod fixed at point ‘D1’ to direct the person standing at ‘C1’

    5. Direct the person at ‘C1’ to move the rod to ‘C2’ so as to be line with ‘A’.

    6. Now the person standing at ‘C2‘ directs the person at ‘D1’ to move to new position ‘D2’ so as to be

    line with ‘B’.

    7. Continue the direction until the points are in line with ‘AB’. Fix the ranging rods to establish the

    intermediate points ‘C’ and ‘D’.

    8. Measure the chainage distance between ‘AC’ ,‘CD’ and ‘DB’. Add the distances to calculate the total

    distance ‘AB’.

    9. Draw a detailed sketch of the measurement to a reduced scale in the field book.

    10. Replicate all the data and sketches from the filed book into your respective practical notebooks.

    Observation and Calculation Sheet:

    Measurement of distance by Reciprocal Ranging

    S. No.

    Chainage Line

    Distance Measured by Tape (m)

    1 AC

    2 CD

    3 DB

    4 AB

    Result:

    By ranging and chaining the total distance between station ‘A’ and station ‘B’ is ____________

    Precautions:

    • The ranging rod should be established correctly at all points.

    • The judgment of line should be taking correctly during the establishment of intermediate points.

    • Distance between surveyor’s eye and ranging rods (eg. A, B and C) should be kept at minimum

    distance of 1 m.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 1 of 7

    Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    Soil Mechanics & Foundation Laboratory

    LAB-3: CHAINING ACROSS OBSTACLES

    Aim: To perform chaining across obstacles and to calculate the obstructed length using different

    methods.

    Theory:

    The measurement of distances consist of chaining and making offsets. During measurements, it is

    practically impossible to set out all the chain lines in a straight forward method because of a variety of

    obstructions to chaining and raining in the field. The difficulties can be overcome by running

    perpendicular and parallel lines or by running a few additional lines and measuring angles by some

    instrument. The obstacles may be divided into two classes. Those which do not obstruct ranging (view)

    but obstructs chaining (measurement) fall in the category of ‘ obstacles to measurement ’, e.g. ponds,

    rivers, etc. The others are those which cannot be seen across i.e. both the chaining and ranging are

    obstructed, e.g. houses, stacks, etc., and are know as ‘ obstacles to alignment ’.

    Equipment:

    1. Ranging rods

    2. Measuring tape

    3. Pegs and

    4. Plumb bob

    Procedure:

    1. Obstacles to Measurement ( Obstacles to chaining but not ranging)

    A) First Method: When an obstacle interrupts the chain line yet chaining is possible around the

    obstacle. Such obstacles are chained using a Rectangular or a Triangular Method. E.g. Chaining

    across a pond.

    A.1. Chaining by Rectangular Method

    Figure. 1. Chaining by Rectangular Method

  • Prepared By: Phurba Tamang, Associate Lecturer Page 2 of 7

    Procedure:

    1. Assuming a pond. Where vision is free but chaining is obstructed.

    2. On both side of pond, place the ranging rods at a certain distance, marking point A and B.

    3. From both the station A and B, fix another two ranging rods at certain distance away from it by

    proper ranging and marking point as C and D.

    4. From point C and D, draw perpendicular line with base line AB by using 3- 4 - 5 method.

    5. Take equal offset distance from point C and D and mark the point as E and F respectively.

    6. Connect the points E and F.

    7. Distance EF is equal to CD.

    8. Measure distance AC, EF and DB and add the distance AC, EF and DB

    9. Draw the diagram of measured distances in reduced scale.

    A.2. Chaining by Triangular Method

    Figure. 2. Chaining by Triangular Method

    Procedure:

    1. Assuming a pond. Where vision is free but chaining is obstructed.

    2. On both side of pond, place the ranging rods at a certain distance, marking point A and B.

    3. From both the station A and B, fix another two ranging rods at certain distance away from it by

    proper ranging and marking point as C and D.

    4. From point C, draw perpendicular line with base line AB by using 3- 4 - 5 method.

    5. Take certain offset distance from point C and mark the point as E.

    6. Connect the points E and D.

    7. Measure the distance ED.

    8. By using Pythagoras theorem we get distance CD, giving length of the pond.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 3 of 7

    9. Measure distance CE and ED.

    10. Draw the diagram of measured distances in reduced scale.

    B) Second Method: When an obstacle interrupts the chain line but chaining is not possible around

    the obstacle. E.g. Chaining across a river.

    B.1. Chaining across a small width river

    Figure. 3. Chaining across small width river

    Procedure:

    1. Assume a small width of river, where vision is free and chaining is obstructed.

    2. On both sides of river, take two points as A and B.

    3. Take another two points C and D along the base line A and B by performing proper ranging.

    4. From point C, erect perpendicular line and locate a point E.

    5. Determine the mid-point of line CE and name this point as F.

    6. From point E, erect perpendicular line and locate a point G in such a way that by moving the rod

    in EG direction, until line DFG comes in straight line.

    7. Measure distance EG which is equal to CD.

    8. Draw the diagram of measured distances in reduced scale.

    E F

  • Prepared By: Phurba Tamang, Associate Lecturer Page 4 of 7

    B.1. Chaining across a large width river

    Figure 4. Chaining across a large width river

    Procedure:

    1. Assume a large width of river, where vision is free and chaining is obstructed.

    2. On both sides of river, take two points as P and Q.

    3. Take another three points A,C and R along the base line P and Q by performing proper ranging.

    4. From point C and A, erect perpendicular line and locate a points D and F. Distance AD = CF.

    5. Connect point FD.

    6. Extend line FE in such a way that line EDR comes in straight line.

    7. Determine the mid-point of line CE and name this point as F.

    8. We get two similar triangle i.e. ∆ ADR and ∆EFD . By using similar triangle rule, we can determine

    the distance AR.

    9. Calculate the distance AR using the relation, FE/AD = FD/AR

    10. Draw the diagram of measured distances in reduced scale.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 5 of 7

    2. Obstacles to Alignment ( Obstacles to both Chaining and Ranging)

    Such a problem arises when a building comes across the chain line. Following is one of the methods

    used when chain line is obstructed in which both ranging and chainage are obstructed.

    A. First Method:

    Procedure:

    1. Let AB be the obstructed length across the building.

    2. A point C is assumed arbitrarily.

    3. B and C are joined such that BC = CD.

    4. Now A and C are also joined such that AC = CE.

    5. Connect the points D and E.

    6. Triangles CAB and CDE are similar triangles. Therefore, obstructed length DE = AB

    7. Draw the diagram of measured distances in reduced scale.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 6 of 7

    B. Second Method:

    1. Assume AB is the chain line.

    2. Two points C and D are selected on it at one side of the building.

    3. Erect two equal perpendiculars CC1 and DD1 from C and D.

    4. Extend the line C1D1 until the building is crossed.

    5. On the extended line, select two points E1 and F1.

    6. Erect the perpendiculars E1E and F2E such that E1E=F1E=D1D=C1C.

    7. The points C, D, E and F will lie on the same straight line AB.

    8. Measure the distance D1E1 to get the required chainage of DE.

    9. Draw the diagram of measured distances in reduced scale.

    Observation and Calculation:

    Note:

    Scaled drawings and calculations of obstructed length for all methods should be shown here.

    Students are required to draw all the diagrams of all methods to scale with all dimensions on the left

    pages of lab record

  • Prepared By: Phurba Tamang, Associate Lecturer Page 7 of 7

    Result:

    1. Obstacle to Measurement

    • Obstructed length from First Method (Rectangular Method): _________ m

    • Obstructed length from First Method (Triangulation Method): _________ m

    • Obstructed length from Second Method (For small width river): _________ m

    • Obstructed length from Second Method (For large width river): _________ m

    2. Obstacles to Alignment ( Obstacle to both Chaining and Ranging)

    • Obstructed length from First Method: _________ m

    • Obstructed length from Second Method: ______ m

    Precautions:

    • The ranging rod should be established correctly at all points.

    • The judgment of line should be taking correctly during the establishment of intermediate points.

    • Perpendicular offsets should be erected accurately.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 1 of 5

    Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    Soil Mechanics & Foundation Laboratory

    LAB-4: DIFFERNTIAL LEVELLING

    Reducing Levels by Rise and Fall Method and Height of Instrument Method

    Aim: To determine the elevation of various points with Dumpy Level by Rise and Fall method and

    Height of Instrument (Collimation) method.

    Theory:

    The art of determining and representing the relative height or elevation of different object/points on

    the surface of earth is called leveling. It deals with measurement in vertical plane. By leveling operation,

    the relative position of two points is known whether the points are near or far off. Similarly, the point

    at different elevation with respect to a given datum can be established by levelling.

    Dumpy level is the most widely used direct instrument. It consists of a telescope which is rigidly fixed

    to its support. It can be neither be rotated about its longitudinal axis nor can it be removed from its

    support. It is very advantages when several observations are to be made with one set up of instrument.

    Rise and Fall method: While in rise and fall method, the difference of level between consecutives point

    is determined by comparing the reading of each point after the first with immediately preceding. The

    difference between their staff readings indicates a rise or fall according to the staff reading at the point

    is smaller or greater than that at the preceding point. The reduced level of each point is then calculated

    by adding the rise or subtracting the fall from the reduced level of the preceding point.

    Arithmetic check in Rise and Fall method: B.S. - F.S. = Rise - Fall = Last R.L. - First R.L.

    Height of Instrument (Collimation) method: The reduced level of the points from the staff reading

    taken in the field are also calculated by using collimation method (HI). In collimation method, the height

    of the instrument is found. For every set up of the instrument, height of the instrument is obtained by

    adding the back sight to the reduced level of the bench mark. The RL of the intermediate points and the

    first change point are then obtained by subtracting the staff reading taken on those points (I.S and F.S)

    from the elevation of plane of collimation.

    Arithmetic check in Height of Instrument method: B.S. - F.S. = Last R.L. - First R.L.

    Equipment:

    1. Dumpy Level

    2. Levelling Staff

    3. Tripod stand

    4. Plumb bob

  • Prepared By: Phurba Tamang, Associate Lecturer Page 2 of 5

    Procedure:

    The following adjustments are made to the level before the commencement of the survey

    A) Setting up the Dumpy Level

    Procedure:

    • Release the clamp screw of the instrument

    • Hold the instrument in the right hand and fix it on the tripod by turning round only the lower part

    with the left hand.

    • Screw the instrument firmly and bring all the foot screws to the center of its run.

    • Spread the tripod legs well apart and fix any two legs firmly into the ground by pressing them

    with the hand.

    • Move the third leg to up or down until the main bubble is approximately in the center.

    Objective Focus

    Horizontal fine

    motion knob

    Bottom plate Levelling screw

    Eye piece lens

    Optical Sight

    Circular Level

    Figure. 1. Dumpy Level

    Figure. 2. Measuring Tape

    Figure. 3. Levelling Staff

  • Prepared By: Phurba Tamang, Associate Lecturer Page 3 of 5

    • Then move the third leg in or out until the bubbles of the cross-level is approximately in the

    center.

    • Fix the third leg firmly when the bubbles are approximately in the centers of their run

    B) Levelling up

    Procedure:

    • Place the telescope parallel to a pair of foot screws.

    • Bring the bubble to the center of its run by turning the foot screws equally either both inwards

    and both outwards.

    • Turn the telescope through 90º, so that it lies over the third foot screw.

    • Turn this third foot screw so that the bubble comes to the center of its run.

    • Turn the telescope through and check whether the bubble remains central

    C) Elimination of Parallax:

    Procedure:

    • Remove the lid from the object glass.

    • Hold a sheet of white paper in front of the object glass.

    • Move the eyepiece right or left until the cross hairs are distinctly visible.

    • Direct the telescope towards the staff.

    • Turn the focusing screw until a clear and sharp image is formed in the plane of the cross hairs.

    Procedure for Rise and Fall Method:

    • Select a suitable area to conduct levelling.

    • Fix the tripod on the level ground by moderately spreading its legs. Try to level the tripod head

    approximately at suitable height.

    • Fix the dumpy level on the tripod and level its base with help of foot screw and air bubble.

    • To make the object clear and distinct, the eye piece is made to focus on cross hair by pointing the

    telescope towards the sky and moving the eye piece in or out till the cross hair seen sharp and

    distinct.

    • Place the staff over a bench mark (B.M), whose reduced level is known, and set up the instrument

    in convenient and safe location where the B.M (point A) is visible. Take a sight on the staff, that

    reading is called Back Sight (B.S).

    • Direct the telescope towards the levelling staff and take readings at position B, C, D etc. which will

    be the Intermediate Sights (I.S) and Fore Sights (F.S) for the Change Points.

    • Set up the instrument in new position and continue taking the readings.

    • The last sighting will be the Fore Sight (F.S) after which the data would be tabulated.

    • Staff stations are established at the uniform distances. Taking approximately 5 to 10 m of interval.

    • Note down readings of back sights, intermediate sights and fore sights for tabulation.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 4 of 5

    Tabulation for Rise and Fall method

    Staff Station

    Chainage

    READINGS

    Rise Fall Reduced Level Remarks B.S I.S F.S

    A B.M

    B

    C

    D

    E

    F

    G

    H

    I

    J

    K F.S

    Arithmetical Check:

    B.S. - F.S. = Rise - Fall = Last R.L. - First R.L.

    Procedure for Height of Instrument Method:

    The field procedure and booking of staff reading is done in the same way as explained in the

    Rise and Fall method. However the data booking is performed as shown in the Table below.

    Tabulation for Height of Instrument (Collimation Method)

    Staff Station

    Chainage READINGS Height of

    Instrument Reduced Level Remarks

    B.S I.S F.S

    A B.M

    B

    C

    D

    E

    F

    G

    H

    I

    J

    K F.S

  • Prepared By: Phurba Tamang, Associate Lecturer Page 5 of 5

    Arithmetical Check:

    B.S. - F.S. = Last R.L. - First R.L.

    Result:

    1. Rise and Fall method

    • B.S - F.S =

    • Rise - Fall =

    • Last R.L. – First R.L. =

    2. Height of Collimation method

    • B.S - F.S =

    • Last R.L. – First R.L. =

    Precautions:

    • The staff should be held vertical while taking the reading;

    • The bubble in the level tube is to be brought to central before taking any reading;

    • Readings should be taken in the proper direction depending on the type of staff;

    • Balancing of sight is to be maintained as far as possible;

    • Reading and recording of observation correctly.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 1 of 5

    Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    Soil Mechanics & Foundation Laboratory

    LAB-5: PROFILE LEVELLING & CROSS SECTIONAL LEVELLING

    Aim: To determine the configuration of ground surface by conducting Profile and Cross

    Sectional levelling

    Theory:

    Profile Levelling: The process of determining elevations at points at short measured intervals along

    a fixed line is called Longitudinal or profile leveling. Profile leveling is one of the most common

    applications of running levels and vertical distance measurement for the surveyor. The results are

    plotted in the form of a profile, which is a drawing that shows a vertical cross section. Profiles are

    required for the design and construction of roads, curbs, sidewalks, pipelines etc. In short, profile

    leveling refers to the process of determining the elevation of points on the ground at mostly uniform

    intervals along continuous line.

    Figure. 1. Profile Levelling

    Cross Sectional Levelling: The term cross-section generally refers to a relatively short profile view of

    the ground, which is drawn perpendicular to the route centerline of a highway or other types of linear

    projects. Cross-sectional drawings are particularly important for estimating the earthwork volumes

    needed to construct a roadway; they show the existing ground elevations, the proposed cut

    or fill side slopes, and the grade elevation for the road base.

    Figure. 2. Cross Sectional Levelling

  • Prepared By: Phurba Tamang, Associate Lecturer Page 2 of 5

    Any of the following checks are opted based on the method chosen for reducing the Levels.

    • Arithmetic check in Rise and Fall method:

    B.S. - F.S. = Rise - Fall = Last R.L. - First R.L.

    • Arithmetic check in Height of Instrument method:

    B.S. - F.S. = Last R.L. - First R.L.

    Equipment:

    1. Dumpy Level

    2. Levelling Staff

    3. Tripod stand

    4. Plumb bob

    5. Measuring Tape

    6. Pegs

    Instructions for Profile Levelling:

    1. Suppose AB is the direction chosen for the construction of road, drain, etc.

    2. After reconnaissance survey establish several staff stations between A and B at regular interval.

    3. The levelling instruments is placed at suitable position (say L1, L2, L3 …) and after temporary

    adjustments, the readings are taken from staff stations.

    4. The first staff reading of any set up is taken from bench mark and entered in the back sight

    column, and the last reading in the foresight column.

    5. The other readings are entered in the intermediate sighting column.

    6. Similarly, change points are also established measuring its foresight and back sight

    7. At the end of the day, a temporary bench mark must be placed at suitable points for future

    reference. This temporary benchmark can also be used to continue the levelling and align the

    direction of levelling work with the previous alignment. 8.

    9. All the recordings are entered into the level book and the profile is being plotted.

    A) Plotting the Profile and Cross Sections ( Refer Fig. 3 and Fig. 4 )

    • The profile drawing is basically a graph of elevations, plotted on the vertical axis, as a

    function of stations, plotted on horizontal axis.

    • A gridded sheet called profile paper is used to plot the profile data from the field book.

    • All profile drawings must have a proper title block, and both axes must be fully labeled with

    stations and elevations.

    • The elevation or elevation scale is typically exaggerated; that is, it is ' stretched ' in comparison

    to the horizontal scale. For example the vertical scale might be 10 times larger. The horizontal

    line at the bottom of the profile does not necessary have to start at zero elevation

  • Prepared By: Phurba Tamang, Associate Lecturer Page 3 of 5

    Tabulation for Profile Levelling

    All the readings are recorded in meters.

    Staff Station

    Chainage

    READINGS

    Rise Fall Reduced Level Remarks B.S I.S F.S

    A B.M

    B

    C

    D

    E

    F

    G

    H

    I

    J

    K F.S

    Arithmetical Check:

    B.S. - F.S. = Rise - Fall = Last R.L. - First R.L.

    Figure. 34. Longitudinal Cross Section

    0

    50

    100

    150

    0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160

    R.L

    . in

    Me

    ters

    Distance in Meters

    Profile Levelling

    Datum 100 m

    A

    B

  • Prepared By: Phurba Tamang, Associate Lecturer Page 4 of 5

    Instructions for Cross Sectional Levelling:

    1. Let ABC be line of section set out on the ground and mark with pegs at equal interval (say 10 to 20

    m).

    2. Set up the level at side of profile to avoid too short sight on the point near instruments and care

    must be taken to set up level approximately midway between two change point.

    3. Start levelling from bench mark of known value.

    4. From each set up, staff reading are taken on pegs already fixed at desired interval and also at

    significant points.

    5. All readings are recorded as intermediate sight against the respective chainages along the line is in

    level book.

    6. When the length of sight is beyond the power of telescope, the foresight on change point is taken.

    The level is then shifted and back sight is taken on change point.

    7. Continue chaining and reading as before, till whole line of section is completed.

    8. The fore bearing and back bearing of section line should be taken and recorded.

    Tabulation for Cross Sectional Levelling

    All the readings recorded in meters.

    Staff Station

    Chainage READINGS

    Rise Fall R.L Remarks Left Center Right B.S I.S F.S

    1.415 105.405 B.M

    A 0 1.875 0.460 104.945 C.S.-1

    5 1.795 0.080 105.025

    10 1.625 0.170 105.195

    15 1.540 0.085 105.280

    5 1.535 0.005 105.285

    10 1.685 0.150 105.135

    15 1.805 0.120 105.015

    B C.S.-2

    Arithmetical Check:

    B.S. - F.S. = Rise - Fall = Last R.L. - First R.L.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 5 of 5

    Figure. 4. Transverse Cross Section

    Result:

    Plot the Longitudinal and Transverse cross sections of the survey area.

    Precautions:

    • The staff should be held vertical while taking the reading;

    • The bubble in the level tube is to be brought to central before taking any reading;

    • Readings should be taken in the proper direction depending on the type of staff;

    • Balancing of sight is to be maintained as far as possible;

    • Reading and recording of observation correctly.

    0

    50

    100

    150

    200

    -15 -10 -5 0 5 10 15

    R.L

    . in

    Me

    ters

    Distance in Meters

    Cross Sectional Levelling

    Point of Center Line

    Left Side Right Side

    10 L 5 L 5 R 10 R 15 R15 R

    Datum 100 m

  • Prepared By: Phurba Tamang, Associate Lecturer Page 1 of 5

    Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    Surveying Laboratory

    LAB-6: THEODOLITE TRAVERSING

    Aim: To adjust and balance a closed traverse using Gale’s Traverse Table.

    Theory:

    Traversing is that type of survey in which member of connected survey line from the frame work and

    the direction and lengths of the survey lines are measured with help of an angle measuring instrument.

    Theodolite traversing is a method of establishing control points and their position being determined

    by measuring distance between the traverse station and angle subtended at the various station by their

    adjacent stations. After measuring angle, length and direction, Gales table is prepared to calculate final

    traversing. Gales table helps in calculating errors and getting accurate bearings, angles and lengths.

    Equipment:

    1. Theodolite

    2. Ranging rod

    3. Tripod stand

    4. Plumb bob

    5. Measuring Tape

    6. Pegs

    Objective Lens

    Handle

    LCD Display

    Tri-pod Base Plate

    Focusing Ring

    Optical Plummet

    Telescope clamp

    Telescope fine motion

    Horizontal Clamp Horizontal fine motion

    Targeting Sight

    Operating Keys

  • Prepared By: Phurba Tamang, Associate Lecturer Page 2 of 5

    Instructions:

    The following adjustments are made to the theodolite before traversing.

    A) Setting, Levelling and Centering Theodolite

    • Release the clamp screw of the instrument

    • Hold the instrument in the right hand and fix it on the tripod by turning round only the lower

    part with the left hand.

    • Screw the instrument firmly and bring all the foot screws to the center of its run.

    • Spread the tripod legs well apart and fix any two legs firmly into the ground by pressing them

    with the hand.

    • Move the third leg to up or down until the main bubble is approximately in the center.

    • Then move the third leg in or out until the bubbles of the cross-level is approximately in the

    center.

    • Fix the third leg firmly when the bubbles are approximately in the centers of their run.

    • Place the telescope parallel to a pair of foot screws.

    • Bring the bubble to the center of its run by turning the foot screws equally either both inwards

    and both outwards.

    • Turn the telescope through 900 , so that it lies over the third foot screw.

    • Turn this third foot screw so that the bubble comes to the center of its run.

    • Turn the telescope through and check whether the bubble remains central

    • Looking through the optical plummet, focus the centering index mark. Slide the theodolite on

    the tripod head until the reference mark is centered in the optical plummet.

    • Fully tighten the centering screw. Look through the optical plummet again and adjust the

    theodolite foot screws for alignment with the reference mark.

    B) Instructions for Theodolite Traversing

    • The area to be surveyed is first thoroughly examined to decide the best possible way of starting

    the work.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 3 of 5

    • Consider a closed traverse with stations namely ABCDEFA. The traverse stations are marked

    on the ground by wooden pegs with nails on top.

    • Set up the instrument at A. Complete the adjustments (levelling and centering) before sighting

    the station B.

    • Once levelling and centering have been achieved, turn on the theodolite by pressing the power

    key.

    • Place the compass over the theodolite and rotate to find the direction of meridian (North).

    • Once the direction has be set, press the HOLD key twice to lock the reference direction.

    • Press the L/R key for horizontal angle options. R mode is used when the traversing is carried

    out in clockwise direction and L mode in counter-clockwise direction.

    • Press V/% key to see the inclination angle of optical telescope. The angle has to be in 000’0’’

    (zero inclination) to maintain the line of collimation throughout the process of traversing.

    • After zero-inclination has been maintained, use the vertical clamp screw to restrict the rotation

    of telescope.

    • Now, sight the levelling staff or ranging rod placed at B and record the fore bearing.

    • Station the instrument at Station B and sight at Station A and record its back bearing.

    • Similarly, complete the process for entire traverse stations.

    • Find the included angles ∠A, ∠B, ∠C, ∠D, ∠E, and ∠F. Measure the length of traverse legs

    connecting all the stations.

    • Plot the traverse and find the closing error graphically ( Draft in AutoCAD )

    • Check the adjustment of interior angles using the condition, i.e. the sum of the included angles

    should be (2n±4) x 900 , where n is the number of sides of closed traverse.

    • Perform all essential checks using the Gale’s Traverse Table.

    • Re-plot the corrected traverse.

    1. Tabulation for Traversing

    Station Line Fore

    Bearing (DMS)

    Line Back

    Bearing (DMS)

    Traverse Line Traverse

    Length (m) Included

    Angles (DMS)

    A 78085’20’

    AB 6000’0’’ BA 24000’0’’ AB 10

    B 78085’20’

    BC 6000’0’’ CB 24000’0’’ BC 12

    C 78085’20’

    CD 6000’0’’ DC 24000’0’’ CD 9

    D 78085’20’

    DE 6000’0’’ ED 24000’0’’ DE 11

    E 78085’20’

    EF 6000’0’’ FE 24000’0’’ EF 12

    F 78085’20’

    FA 6000’0’’ AF 24000’0’’ FA 9

    Instruction: Plot the traverse to check the closing error. ( Draft in AutoCAD)

  • Prepared By: Phurba Tamang, Associate Lecturer Page 4 of 5

    2. Tabulation for Gale’s Traverse Table

    Instruction: Find the closing error using, CE = 2 2( ) ( )Latitude Departure +

    Sta

    tio

    n

    Lin

    e

    Le

    ng

    th

    Inte

    rio

    r a

    ng

    les

    Co

    rre

    ctio

    ns

    Co

    rre

    cte

    d A

    ng

    les

    WC

    B

    RB

    Qu

    ad

    ran

    ts

    Consecutive coordinates

    Correction (Bowditch Rule

    Corrected Consecutive Coordinates

    Independent Coordinates

    Lat. Dep. Lat. Dep. Lat. Dep. N (+) S (-) E (+) W (-)

    N (+)

    S (-)

    E (+)

    W (-)

    N (+)

    S (-)

    E (+)

    W (-)

    N (+) S (-) E (+) W (-)

    A

    AB

    B

    BC

    C

    CD

    D

    DE

    E

    EF

    F

    FA

    A

    Ʃ

  • Prepared By: Phurba Tamang, Associate Lecturer Page 5 of 5

    Result:

    • The graphical closing error of the traverse was found to be ……………..

    • Plot the traverse ABCDEFA before and after correction

    Precautions:

    • The staff should be held vertical while taking the reading.

    • The bubble in the level tube is to be brought to central before taking any reading.

    • Readings should be taken in the proper direction depending on the type of staff.

    • Balancing of sight is to be maintained as far as possible;

    • Reading and recording of observations should be done correctly.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 1 of 5

    Jigme Namgyel Engineering College

    Department of Civil Engineering & Surveying

    Surveying Laboratory

    Aim: To determine the tacheometric constant and elevation difference between two given points

    using the principle of tacheometry.

    Theory:

    Tacheometeric surveying is a method of angular surveying in which the horizontal distance from the

    instrument to the staff station and the elevation of the staff station concerning the line of collimation

    of the instrument are determined from instrument observation only. Thus, chaining operation are

    eliminated. There are two method in tacheometric surveying. These are stadia system and tangential

    system. In this method stadia system is used to determine the difference in elevation between two

    given points.

    The principle of tacheometry is based on the property of isosceles triangles, where the ratio of the

    distance of the base from the apex and length of the base is always constant.

    ∆ O1a1a2, ∆ O1b1b2 and ∆ O1c1c2 are isosceles triangles. D1, D2 and D3 are the distances of the bases from

    the apices and S1, S2 and S3 are the lengths of the bases. According to this principle

    31 2

    1 2 3

    (constant)DD D f

    S S S i= = =

    sin 2( )sin

    2

    f SV f d

    i

    = + +

    is known as multiplying constant, D S ( )f

    f de

    = + +

    is the focal

    length of the objective lens and i is the stadia intercept.

    LAB-7: TACHEOMETRIC SURVEYING

  • Prepared By: Phurba Tamang, Associate Lecturer Page 2 of 5

    From the theory of stadia tacheometry, the following equation is used to relate the distance, stadia

    intercept and the constants i.e.

    D S ( )f

    f di

    = + +

    Where, ( )f d+ is the additive constant

    S is the stadia intercept and d is the distance between the vertical axis and centre of objective.

    Equipment:

    1. Theodolite

    2. Levelling staff

    3. Tripod stand

    4. Plumb bob

    5. Measuring Tape

    Instructions:

    A) Determination of Tacheometric constant

    • Choose a fairly level ground. Set up the theodolite at O and fix the pegs at A1, A2 and A3

    • The staff intercepts (stadia hair readings) are noted at each of the pegs. The intercepts are taken

    as S1, S2 and S3

    • The horizontal distances of the pegs from O are accurately measured. The distances are

    recorded as D1, D2 and D3

    • The values of stadia intercepts and distances are substituted in the general equation.

    • The equations are then solved to obtain several values of multiplying constant (f

    i) and

    additive constant ( )f d+ .

    • The mean of these values are taken for the required constant.

  • Prepared By: Phurba Tamang, Associate Lecturer Page 3 of 5

    B) Instructions for Theodolite Traversing

    • Select the site, which has got certain differences in elevation between two points.

    • Fix the tripod on the level ground by moderately spreading its legs. Try to level the tripod head

    approximately at suitable height.

    • Fix the tacheometer on the tripod and level its base with help of foot screw and air bubble.

    • To make the object clear and distinct, the eye piece is made to focus on cross hair by pointing

    the telescope towards the sky and moving the eye piece in or out till the cross hair seen sharp

    and distinct.

    • Direct the telescope towards the staff and the images are made to appear clear and sharp by

    adjusting the focusing screw.

    • Hold the staff on the bench mark and take the bearing. Take all the readings like top, bottom

    and central.

    • After measuring the bench mark reading, rotate the instrument and take the forward reading

    on chosen points.

    • If the given point is at higher elevation, the following case is considered.

    Figure. 1. Considering the angle of elevation

    2cos ( )cosf

    D S f di

    = + +

    sin 2( )sin

    2

    f SV f d

    i

    = + +

    R.L of the staff station = Height of Instrument + V- h

    Where, h = central hair reading

    S = Staff Intercept (stadia interval)

    D = Horizontal distance between instrument and staff

    V = Vertical distance between instrument axis and central hair

    Θ = angle of elevation

  • Prepared By: Phurba Tamang, Associate Lecturer Page 4 of 5

    Figure. 2. Considering the angle of depression

    2cos ( )cosf

    D S f di

    = + +

    sin 2( )sin

    2

    f SV f d

    i

    = + +

    R.L of the staff station = Height of Instrument - V- h

    Where, h = central hair reading

    S = Staff Intercept (stadia interval)

    D = Horizontal distance between instrument and staff

    V = Vertical distance between instrument axis and central hair

    Θ = angle of depression

    1. Tabulation for Tacheometric Constants

    Instrument Station

    Staff Station

    Distance (m)

    Stadia Readings f

    i

    ( )f d+

    Lower Upper

    O

    A

    B

    C

    Average

  • Prepared By: Phurba Tamang, Associate Lecturer Page 5 of 5

    2. Tabulation for Tacheometric Data Entry

    Instrument Station

    Staff Station HI Vertical

    Angle (θ)

    Staff Reading in meters

    Upper Stadia Cross Hair

    Lower Stadia

    O

    A

    B

    Instrument Station

    Staff Station

    Distance (m)

    Vertical Distance (m)

    Stadia Intercept

    (m)

    Central Hair

    Reading (m)

    R.L (m) Remark

    O

    A Point O is assumed to be

    a B.M (R.L.=100 m) B

    Result:

    • The R.L. of points A is …………. and that of B is …………

    • The multiplying and additive constants are ………….. and ……………

    Precautions:

    • The staff should be held vertical while taking the reading.

    • The bubble in the level tube is to be brought to central before taking any reading.

    • Readings should be taken in the proper direction depending on the type of staff.

    • Reading and recording of observations should be done correctly.

    Manual for Soil Mechanics & Foundation Engineering for DAAPractical_1Introduction to lab procedures with practial no.1Publication1Introduction to lab procedures with practial no. 1Jigme Namgyel Engineering CollegeDepartment of Civil Engineering & SurveyingSoil Mechanics & Foundation Laboratory

    Introduction to lab procedures with practial no. 1Jigme Namgyel Engineering CollegeDepartment of Civil Engineering & SurveyingSoil Mechanics & Foundation Laboratory

    Practical_2Jigme Namgyel Engineering CollegeDepartment of Civil Engineering & SurveyingSoil Mechanics & Foundation Laboratory

    Practical_3Jigme Namgyel Engineering CollegeDepartment of Civil Engineering & SurveyingSoil Mechanics & Foundation Laboratory

    Practical_4Jigme Namgyel Engineering CollegeDepartment of Civil Engineering & SurveyingSoil Mechanics & Foundation Laboratory

    Practical_5Jigme Namgyel Engineering CollegeDepartment of Civil Engineering & SurveyingSoil Mechanics & Foundation Laboratory