+ All Categories
Home > Documents > RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double...

RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double...

Date post: 08-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
6
1.5 (page 1 of 6) RESTORING MEANDERS TO STRAIGHTENED RIVERS M A N UA L O F R I V E R R E S TO R AT I O N T E C H N I Q U E S These techniques were developed to suit site specific criteria and may not apply to other locations 1.5 New meandering channel replacing concrete weirs RIVER MARDEN LOCATION - Town centre at Calne,Wiltshire ST 998710 DATE OF CONSTRUCTION - 1999 LENGTH – 100m COST - not available DESCRIPTION A town centre factory had been demolished leaving a reach of river flowing through the site in a straight, concrete channel. The channel bed dropped vertically in two places forming weirs that barred the passage of fish and were unsightly. Redevelopment of the site required that the river be diverted south of its existing course and that its character be improved to create an attractive public amenity. The site is prominently located in the heart of an ancient market town. The diversion was undertaken in the form of a double meander such that natural geomorphological features including shoals, riffles and pools could be incorporated, as well as good public access to the waterside and a variety of sustainable attractive habitats for flora and fauna. Earlier proposals to create an impounded, canal-like waterway were dropped in favour of the relatively free flowing river regime described. 1 River course prior to works Old culvert Existing Buildings Ramp Ramp Pool Pool Pool Pool New twin culverts Footbridge N e w s h o p p i n g d e v e l o p m e n t N e w p a r a d e E x i s t i n g Ro a d 0 10m B A A C C* X X 67.4m 67.5m B* 68.4m Key Flood wall 1m high Gravel Shoals on inner bends Stone Riffles in riverbed 2 No. (see 5.4) Vanes at culvert entry Stone foundations to river walls or stone revetment of bank Hinged flood gates 3 No. Stepped platforms (stone) give access to shoal – (see 8.5) Grassed areas at waterside For sections 'B-B' and 'C-C' see 8.5 For section 'X-X' see 5.4 * Figure 1.5.1 PLAN OF NEW MEANDERS
Transcript
Page 1: RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double ... Purbeck Limestone from quarries at Swanage was chosen because it occurred ...

1.5 (page 1 of 6)

RESTORING MEANDERS TOSTRAIGHTENED RIVERS

M A N U A L O F R I V E R R E S T O R A T I O N T E C H N I Q U E S

These techniques were developed to suit site specific criteria and may not apply to other locations

1.5 New meandering channel replacing concrete weirsRIVER MARDENLOCATION - Town centre at Calne,Wiltshire ST 998710DATE OF CONSTRUCTION - 1999LENGTH – 100mCOST - not available

DESCRIPTION

A town centre factory had been demolished leaving areach of river flowing through the site in a straight,concrete channel. The channel bed dropped verticallyin two places forming weirs that barred the passage offish and were unsightly.

Redevelopment of the site required that the riverbe diverted south of its existing course and that itscharacter be improved to create an attractive publicamenity. The site is prominently located in the heartof an ancient market town.

The diversion was undertaken in the form of a doublemeander such that natural geomorphological featuresincluding shoals, riffles and pools could be incorporated,as well as good public access to the watersideand a variety of sustainable attractive habitatsfor flora and fauna.

Earlier proposals to create an impounded, canal-likewaterway were dropped in favour of the relatively freeflowing river regime described.

1

River courseprior to works

Old culvert

ExistingBuildings

Ram

p

Ramp

Pool

Pool

Pool

Pool

New twinculverts

Footbridge

New shopping development

New parade

Existing Road

0 10m

B A

A

C

C*

X†

X

67.4m

67.5m

B*

68.4m

KeyFlood wall 1m high

Gravel Shoals on inner bends

Stone Riffles in riverbed 2 No. (see 5.4)

Vanes at culvert entry

Stone foundations to river wallsor stone revetment of bank

Hinged flood gates 3 No.

Stepped platforms (stone) give accessto shoal – (see 8.5)

Grassed areas at waterside

For sections 'B-B' and 'C-C' see 8.5

For section 'X-X' see 5.4

*

Figure 1.5.1PLAN OF NEW MEANDERS

Page 2: RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double ... Purbeck Limestone from quarries at Swanage was chosen because it occurred ...

1M A N U A L O F R I V E R R E S T O R A T I O N T E C H N I Q U E S

These techniques were developed to suit site specific criteria and may not apply to other locations

RESTORING MEANDERS TO

STRAIGHTENED RIVERS

DESIGN

The diversion necessitated the re-siting of theupstream part of twin box culverts that carry the riverunder the main road. Figure 1.5.1 shows the locationof old and new culverts. The double meander routebetween the existing channel and the new culvertswas optimised within the constraints of the existingand new buildings shown.

The gradient of the new river bed became ‘fixed’between the culvert invert and the existing upstreamlevel. Figure 1.5.2 shows the resultant longitudinalprofile with a mean bed gradient of 1 in 140. Thisgradient is much steeper than arises naturally on this part of the river with consequent high watervelocities when the river is in flood.

Hydraulic modelling indicated velocities of up to 2 metres per second and flood levels up to 80cmabove adjoining roads and property. These hydraulic parameters meant that flood walls would be neededto contain the river and that erosion of the river bed and banks would need to be rigidly controlled.

A design concept was needed that was sufficientlyrobust to meet these demanding hydraulic conditionsbut equally to meet the need for an attractive andsustainable environment.

The concept adopted was based on the premise that the gradient and alignment of the river were

more typical of upland river locations where rock outcrops and gravel and cobble river bed substratesmight be expected. Design of the many elements of the project began by developing a method of simulating stratified bedrock underneath the wholeriver diversion that would ‘outcrop’ to form riverbank revetments, retaining wall foundations and river bed control cills.

Research was undertaken to select quarried rock that could be re-constructed on-site to simulate itsnatural characteristics. Purbeck Limestone fromquarries at Swanage was chosen because it occurredin large, flat slabs of thickness between 10cm and90cm. Slabs of rock could be laid securely, oneabove another, at consistent angles to recreate the‘dip and strike’ of natural outcrops. The stone wassufficiently durable to withstand frost and could alsobe provided in cut building blocks for use in walls.Its colour and texture is similar to locally availableCotswold stone but its durability was much greater,an important factor in riverside locations.

The following lists the key locations where stone slabswere incorporated:

Within the foundations of all vertical riversideretaining wallsSlabs were laid at a consistent angle to project intoand above the water creating the appearance of thewalls being built on natural rock. Contrasting faceson opposite sides of the river were achieved by

(page 2 of 6) 1.5

1

2

3

4

Key

Original bed level – concrete channelwith two drop weirs

New mean bed gradient at 1 in 140

2 stone riffles built to stabilise river bed;pools upstream and downstream of each

Actual bed profile of gravel andcobble susbstrates

0 20 40 60 80 100 120

Chainage (m)

64

65

66

67

69

68

1 3

2

4

Footbridge68.2 Floodwall

67.4 Road

Diversion Existing

RoadCulverts

m.O

.D.

Figure 1.5.2LONGITUDINAL PROFILE

Page 3: RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double ... Purbeck Limestone from quarries at Swanage was chosen because it occurred ...

maintaining the ‘dip’ in the same direction i.e. smoothdip slopes one side and jagged escarpment faces onthe other. As the river alignment approaches the culverts in the same direction as the selected dip-slopes, slabs were laid with the dip parallel to theretaining wall. This enabled a series of ‘craggy’ current deflectors to be incorporated into the foot ofthe wall.

At the bottom of earth slopes on outer bends liable to erosionSlabs were laid exactly as above with consistentdirection of dip and strike to revet these banks with

varying faces depending upon the channel alignmentof each location. See section A–A, figure 1.5.3 foraspects of both wall foundations and bank revetments.

Outcrops in the riverbed to create low cillsThe steepness of the river bed gradient needed to bechecked by introducing two low barriers of rock toresist any tendency of the bed to scour downwards.These are shown as feature 3 on figure 1.5.2. Theyare located just downstream of each meander bendwhere underwater bars of river bed substrate e.g.gravels would naturally accumulate in the form ofriffles. The stonework on adjacent walls and river

1.5 (page 3 of 6)

RESTORING MEANDERS TO

STRAIGHTENED RIVERS

M A N U A L O F R I V E R R E S T O R A T I O N T E C H N I Q U E S

These techniques were developed to suit site specific criteria and may not apply to other locations

1

Before:View downstreamtowards culvert

Completion:View of the newriver course

Page 4: RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double ... Purbeck Limestone from quarries at Swanage was chosen because it occurred ...

bank was linked across the bed with stone laid at the same dip slope. Technique 5.4 shows details of these. They incorporate a gently sloping down-stream face, much like a riffle. This enables the easypassage of migratory fish to be achieved and createsa ‘tumbling’ water feature rather than a sharp fall.

Building stone in walls and for amenity surfacesDressed stone was used to face and cap all retainingwalls and flood walls as well as the head walls on thenew road culvert. These head walls were designedwith curving arched soffits to give the appearance ofan older stone bridge, hiding the unsightly concreteboxes that carry the water under the road. On theinner bend fronting the new development, largestone slabs were laid to create stepped platformsdown to the waterside shoal (see 8.5 for details).

Vertical vanes in the river upstream of the newroad culvertsThe twin culverts create an artificially wide riverchannel at entry with the consequential risk of theculvert on the inside of the bend attracting excessivesilt accumulations. Four upright slabs of stone wereconcreted into the river bed to induce a sustainedflow of water towards the inner culvert without barring the natural tendency of flow towards theouter culvert. The slabs project a nominal 15cmabove normal water levels and serve as ‘vanes’ thateffectively modify the water currents at all stages ofriver flow, including flood flows.

All of the stone features described, effectively define a precise and stable course to the river which wasessential in this tightly developed urban location. The creation of the river bed and waterside shoals was

an equally important aspect of design since both hadto be similarly stable as well as being able to sustainflora and fauna.

Geomorphological calculations were undertaken todetermine size, shape and distribution of the river bedsubstrates that were to be introduced in the differinghydraulic conditions generated by the double meanderchannel configuration. Two sources of material wereselected for use either singly or in combination.

Stone rejects from nearby limestone gravel pits wereused on the river bed upstream of chainage 40m (the lower riffle) where water velocities were highest.Sizes ranged from 40mm to 200mm and shape variedbetween rounded gravels and cobbles to flat pieces ofstone. Elsewhere 40mm graded and washed gravelswere used where water velocities were less severe. This included the inner bend shoals where the publicwould have easy access. A mixture of both was usedin intermediate locations simulating the natural ‘grading’ of bed substrates that would arise had theybeen carried and deposited by the river.

The design was completed to accommodate floodwalls and floodgates and a range of public accessand amenity features as well as a comprehensive landscape planting scheme sympathetic to the riverineenvironment. The introduction of marginal aquaticplants, etc. along soft edges and within the numerousinterstices of the rock outcrops was deferred untilfloodwaters has passed through the newly createdreach of the river. This enables the river to modifyand soften the engineered work thereby revealing themost appropriate plant species for the multitude ofdifferent habitat niches expected.

1

(page 4 of 6) 1.5

M A N U A L O F R I V E R R E S T O R A T I O N T E C H N I Q U E S

These techniques are developed to suit site specific criteria and may not apply to other locations

RESTORING MEANDERS TO

STRAIGHTENED RIVERS

0 5 10 15 20Chainage (m)

65

70

Parade

Floodwall

Floodlevel

Stone slabsStone slabs Gravel/cobblesubstrate

m.O

.D.

Figure 1.5.3SECTION A THROUGH RIVER AND STONE SLABS

Page 5: RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double ... Purbeck Limestone from quarries at Swanage was chosen because it occurred ...

1.5 (page 5 of 6)

RESTORING MEANDERS TO

STRAIGHTENED RIVERS

M A N U A L O F R I V E R R E S T O R A T I O N T E C H N I Q U E S

1

These techniques are developed to suit site specific criteria and may not apply to other locations

View of Section A in November 2001

View of Section A (fig 1.5.3) on completion

Page 6: RRC MANUAL 4/12/02of an ancient market town. The diversion was undertaken in the form of a double ... Purbeck Limestone from quarries at Swanage was chosen because it occurred ...

1

(page 6 of 6) 1.5

M A N U A L O F R I V E R R E S T O R A T I O N T E C H N I Q U E S

These techniques are developed to suit site specific criteria and may not apply to other locations

RESTORING MEANDERS TO

STRAIGHTENED RIVERS

SUBSEQUENT PERFORMANCE 1999 – SPRING 2001

Landscaping and planting have yet to be completedbut the new riverworks have meanwhile been subjectedto several flood events.

The works have all remained remarkably stable bearing in mind that river bed substrates and shoalmaterials were all kept to minimum sizes, rather than‘over-sizing’ to ensure stability.

The river has re-distributed some of the stone placedbetween the two riffles. This has created an additionalriffle within the reach and the shoal at the front ofthe stepped platform has built up into an attractive,accessible beach.

The edge of the river channel between the two stone‘riffles’ has slightly eroded along the un-revetted side.The latter can be easily controlled using pre-plantedfibre rolls as part of the landscaping work and the former simply requires some gravel reject stone to beintroduced into the soil that will then be grassed.

The four vanes at the culvert entry appear to beworking well and sustain interesting current variationsat low flows although some flood debris is attached tothem. This debris is easily removed and is less prob-lematic than it would be if it had entered the culverts.

The overall appearance of the riverworks is excellentand once the contractor finally clears the site andlandscaping is completed it should naturalise well.Wildlife has occupied the site despite the intensebuilding work with wagtails, duck and fish beingmost obvious. The underwater rock and the sustainedpools and faster flowing runs of water all promise todevelop into valuable habitats.

Local comments are of young people enjoying ‘messing about in the river’ with no serious vandalism, partly due to the robustness of the design concept.

Contacts:RRC, Silsoe, Beds. MK45 4DT, Tel: 01525 863341.

After:The new town centre in November 2001


Recommended