    Fairfield Metro Center &

    Intersection Improvements

    Project Status Update

    Expenses and ProjectionsAs of April 30, 2011

  • 8/6/2019 RTM Metro Center Update June 27 2011

    2/43

    2

    Agenda

    Fairfield Metro Center & Intersection Improvements:

    Project Teams

    Schedule/Milestones Project Expenses

    Budget Status

    Revenues

    Summary and Action Items

  • 8/6/2019 RTM Metro Center Update June 27 2011

    3/43

    3

    Project Teams

  • 8/6/2019 RTM Metro Center Update June 27 2011

    4/43

    4

    Fairfield Metro Center

    Project Team General Contractor: Guerrera Construction

    Construction Inspection: STV

    Environmental Professional: Loureiro Engineering (LEA)

    Site Monitor: Redniss & Mead

  • 8/6/2019 RTM Metro Center Update June 27 2011

    5/43

    5

    Intersection Improvements

    Project TeamFairfield Intersection Improvements & Paving: General Contractor: Guerrera Construction

    Construction Inspection: VHB/STV

    Improvements @ Black Rock Turnpike & Access Road:

    General Contractor: Rizzo Electric

    Construction Inspection: Town

  • 8/6/2019 RTM Metro Center Update June 27 2011

    6/43

    6

    Schedule/Milestones

  • 8/6/2019 RTM Metro Center Update June 27 2011

    7/43

    7

    Fairfield Metro Center

    MilestonesWork Started: 7/21/10

    Contract Duration: 480 days

    Contract Completion: 11/13/11

    Tentative Station Opening: Late October

  • 8/6/2019 RTM Metro Center Update June 27 2011

    8/43

    8

    Intersection Improvements

    MilestonesWork Started: 4/19/10

    Planned Duration: 240 days

    Planned Completion: July 2011

  • 8/6/2019 RTM Metro Center Update June 27 2011

    9/43

    9

    Project Expenses- Fairfield Metro Center

    - Intersection Improvements

  • 8/6/2019 RTM Metro Center Update June 27 2011

    10/43

    10

    Fairfield Metro CenterProject Expenses

  • 8/6/2019 RTM Metro Center Update June 27 2011

    11/43

    11

    Fairfield Metro Center

    Major Cost Components

    Acquisition

    Pre-Development Construction

    Inspection and Engineering

    Excess Soil Disposal Other

  • 8/6/2019 RTM Metro Center Update June 27 2011

    12/43

    12

    Fairfield Metro CenterConstruction Components

    Parking Lot, Roadway & Site Infrastructure

    Wetland/Shoreline Restoration

    Environmental Remediation Site Walls

  • 8/6/2019 RTM Metro Center Update June 27 2011

    13/43

    13

    Fairfield Metro CenterConstruction Expense ($ millions)

    Expended toDate

    EstimatedCost to

    Complete

    ProjectedTotal Cost

    Parking Lot, Roadway

    & Site Infrastructure$ 7.1 $6.5-$7.0 $13.6-$14.1

    Wetland/ShorelineRestoration

    $ 1.0 $1.0 $2.0

    EnvironmentalRemediation

    $ 3.4 $2.4-$2.7 $5.8-$6.1

    Site Walls $ 3.8 $1.3 $5.1

    Total $15.3 $11.2-$12.0 $26.5-$27.3

  • 8/6/2019 RTM Metro Center Update June 27 2011

    14/43

    14

    Fairfield Metro CenterConstruction Components

    Parking Lot, Roadway & Site Infrastructure

    Wetland/Shoreline Restoration

    Environmental Remediation Site Walls

  • 8/6/2019 RTM Metro Center Update June 27 2011

    15/43

    15

    Parking Lot, Roadway & Site Infrastructure($ millions)

    Expended toDate

    Estimated Costto Complete

    Total ProjectedCost

    Mobilization & Site Prep $2.2 $0.1 $2.3

    Excavation $2.3 $0.4-$0.6 $2.7-$2.9

    Clean Fill & Stone $0.5 $0.7-$0.9 $1.2-$1.4

    Curbing/Sidewalks $0.1 $0.3 $0.4

    Asphalt $0.1 $1.2 $1.3

    Drainage Structures $0.6 $0.5 $1.1

    Fencing/Landscaping $0.1 $0.5 $0.6

    Project Coordination $0.2 $0.2 $0.4

    Lighting & Utilities $0.8 $2.0-$2.1 $2.8-$2.9

    Other $0.2 $0.6 $0.8

    Total $7.1 $6.5-$7.0 $13.6-$14.1

  • 8/6/2019 RTM Metro Center Update June 27 2011

    16/43

    16

    Fairfield Metro CenterConstruction Components

    Parking Lot, Roadway & Site Infrastructure

    Wetland/Shoreline Restoration

    Environmental Remediation Site Walls

  • 8/6/2019 RTM Metro Center Update June 27 2011

    17/43

    17

    Wetland/Shoreline Restoration($ millions)

    Expended toDate

    Estimated Costto Complete

    Total ProjectedCost

    Elevated Walkways $0.3 $0 $0.3

    Maintenance Road &

    Access Trail

    $0.1 $0.1 $0.2

    Field Stone Wall $0 $0.2 $0.2

    Topsoil Mixes $0.2 $0.3 $0.5

    Landscaping $0 $0.2 $0.2

    Sedimentation/Erosion

    Controls$0.1 $0.1 $0.2

    Drainage Structures $0.1 $0 $0.1

    Other $0.2 $0.1 $0.3

    Total $1.0 $1.0 $2.0

  • 8/6/2019 RTM Metro Center Update June 27 2011

    18/43

    18

    Fairfield Metro CenterConstruction Components

    Parking Lot, Roadway & Site Infrastructure

    Wetland/Shoreline Restoration

    Environmental Remediation Site Walls

  • 8/6/2019 RTM Metro Center Update June 27 2011

    19/43

    19

    Environmental Remediation($ millions)

    Expendedto Date

    Estimated Costto Complete

    Total ProjectedCost

    Disposal of ControlledMaterials (PCBs)

    $0.6 $0.3-$0.4 $0.9-$1.0

    Treatment Contaminated

    Groundwater $1.3 $0

    .6-$0

    .7$1

    .9-$2

    .0

    Stabilization ofUnsuitable Soils

    $0.2 $0.2-$0.3 $0.4-$0.5

    Installation of Geo-Membrane Liner

    $0.8 $0.7 $1.5

    Granular Base (Liner) $0.1 $0.1 $0.2Cofferdam $0.3 $0.5 $0.8

    Other $0.1 $0 $0.1

    Total $3.4 $2.4-$2.7 $5.8-$6.1

  • 8/6/2019 RTM Metro Center Update June 27 2011

    20/43

    20

    Remediation Requirements

    In sediment and below mean high water:

    Excavate casting sands for placement under geo-membraneliner; back-fill with clean material.

    Excavate all PCB-impacted soils above 1ppm but less than10ppm for placement under liner; backfill with clean material.

    Excavate and remove all PCB-impacted soils greaterthan10ppm for off-site disposal at an approved landfill.

  • 8/6/2019 RTM Metro Center Update June 27 2011

    21/43

    21

    Remediation Requirements Above mean high water:

    In areas without liner: excavate casting sands and PCB-impacted soils with concentrations less than 10ppm to adepth of4 feet or the water table, whichever is greater, forplacement under liner; backfill with clean material.

    Casting sands and PCB-impacted soils with concentrationsless than 10ppm may remain in place provided that they areunderneath a liner, a building foundation or have at least 4feet of clean material over them rendering them inaccessible

    and/or environmentally isolated.

    Excavate and remove all PCB-impacted soils greaterthan10ppm for off-site disposal at an approved landfill.

  • 8/6/2019 RTM Metro Center Update June 27 2011

    22/43

    22

    Remediation Requirements

    Groundwater encountered during excavation work and incontact with impacted soils:

    Presumed contaminated.

    Must be treated in accordance with permitrequirements prior to being discharged to the

    sanitary sewer.

  • 8/6/2019 RTM Metro Center Update June 27 2011

    23/43

    23

    Fairfield Metro CenterConstruction Elements

    Parking Lot, Roadway & Site Infrastructure

    Wetland/Shoreline Restoration

    Environmental RemediationSite Walls

  • 8/6/2019 RTM Metro Center Update June 27 2011

    24/43

    24

    Site Walls($ millions)

    Expended toDate

    Estimated Costto Complete

    Total ProjectedCost

    Excavation $0.2 $0 $0.2

    Site/Retaining Walls $2.2 $0.4 $2.6

    Steel Bars $0.2 $0 $0.2Concrete $0.6 $0.5 $1.1

    Granular Fill/Stone $0.2 $0.1 $0.3

    Steel Piles $0.4 $0 $0.4

    Tunnel $0 $0.2 $0

    .2

    Other $0 $0.1 $0.1

    Total $3.8 $1.3 $5.1

  • 8/6/2019 RTM Metro Center Update June 27 2011

    25/43

    25

    Fairfield Metro CenterExpense Summary ($ Millions)

    Expended toDate

    Estimated Costto Complete

    Projected TotalCost

    Acquisition $3.8 $ 0 $3.8

    Pre-Development $1.4 $ 0 $1.4

    Construction $15.3 $11.2-$12.0 $26.5-$27.3

    Inspection &Engineering

    $1.7 $1.6-$1.8 $3.3-$3.5

    Excess SoilDisposal $0 $0-$2.0 $0-$2.0

    Other $0.5 $0.6 $1.1

    Total $22.7 $13.4-$16.4 $36.1-$39.1

  • 8/6/2019 RTM Metro Center Update June 27 2011

    26/43

    26

    Intersection ImprovementsProject Expenses

  • 8/6/2019 RTM Metro Center Update June 27 2011

    27/43

    27

    Intersection Improvements

    Design

    Construction

    Inspection

    Other

  • 8/6/2019 RTM Metro Center Update June 27 2011

    28/43

    28

    Intersection ImprovementsConstruction Expense

    Expended toDate

    Estimated Costto Complete

    Total ProjectedCost

    MultipleIntersections &Paving

    $2.2 $1.0-$1.2 $3.2-$3.4

    Black RockTurnpike &

    Access Road$0.1 $0.1 $0.2

    Total $2.3 $1.1-$1.3 $3.4-$3.6

  • 8/6/2019 RTM Metro Center Update June 27 2011

    29/43

    29

    Intersection ImprovementsInspection Expense

    Expended toDate

    Estimated Costto Complete

    Total ProjectedCost

    Inspection $0.2 $0.3-$0.4 $0.5-$0.6

  • 8/6/2019 RTM Metro Center Update June 27 2011

    30/43

    30

    Intersection ImprovementsExpense Summary

    Expended toDate

    Estimated Costto Complete

    Total ProjectedCost

    Design $0.3 $0 $0.3

    Construction $2.3 $1.1-$1.3 $3.4-$3.6

    Inspection $0.2 $0.3-$0.4 $0.5-$0.6

    Other $0.1 $0 $0

    .1

    Total $2.9 $1.4-$1.7 $4.3-$4.6

  • 8/6/2019 RTM Metro Center Update June 27 2011

    31/43

    31

    Combined Expenses

  • 8/6/2019 RTM Metro Center Update June 27 2011

    32/43

    32

    Combined Expense Summary($ millions)

    Expended toDate

    Estimated Costto Complete

    Total ProjectedCost

    Fairfield MetroCenter

    $22.7 $13.4 - $16.4 $36.1 - $39.1

    IntersectionImprovements

    $ 2.9 $ 1.4 - $1.7 $ 4.3 - $4.6

    Total $25.6 $14.8 - $18.1 $40.4 - $43.7

  • 8/6/2019 RTM Metro Center Update June 27 2011

    33/43

    33

    Budget Comparison

  • 8/6/2019 RTM Metro Center Update June 27 2011

    34/43

    34

    Fairfield Metro CenterProjected to Budget ($ Millions)

    TotalProjected

    CostBudget Variance

    Acquisition $3.8 $3.8 $0

    Pre-Development $1.4 $1.4 $0

    Construction $26.5-$27.3 $25.5 $1.0-1.8

    Inspection &Engineering

    $3.3-$3.5 $2.5 $0.8-$1.0

    Excess Soil Disposal $0-$2.0 $0 $0-$2.0

    Other $1.1 $0.8 $0.3

    Total $36.1-$39.1 $34.0 $2.1-$5.1

  • 8/6/2019 RTM Metro Center Update June 27 2011

    35/43

    35

    Intersection ImprovementsProjected to Budget

    ($ millions)Total Projected

    CostBudget Variance

    Design $0.3 $0.3 $0

    Construction $3.4-$3.6 $3.2 $0.2-$0.4

    Inspection $0.5-$0.6 $0.3 $0.2-$0.3

    Other $0.

    1 $0.

    2 ($0.

    1)

    Total $4.3-$4.6 $4.0 $0.3-$0.6

  • 8/6/2019 RTM Metro Center Update June 27 2011

    36/43

    36

    Combined Project ExpensesProjected to Budget

    ($ millions)

    Total ProjectedCost

    Budget Variance

    Fairfield MetroCenter

    $36.1-$39.1 $34.0 $2.1-$5.1

    IntersectionImprovements

    $4.3-$4.6 $4.0 $0.3-$0.6

    Total $40.4-$43.7 $38.0 $2.4-$5.7

  • 8/6/2019 RTM Metro Center Update June 27 2011

    37/43

    37

    Combined Project Revenues($ millions)

    Planned Total Anticipated

    Federal $6.9 $6.3-$6.9

    State $19.9 $19.8-$19.9

    Town $6.0 $6.0

    BRR $5.2 $5.2

    Total $38.0 $37.3-$38.0

  • 8/6/2019 RTM Metro Center Update June 27 2011

    38/43

    38

    Summary

    S f E

  • 8/6/2019 RTM Metro Center Update June 27 2011

    39/43

    39

    Summary of Expenses toRevenues

    ($ millions)

    Best Case Worst Case

    Total Expenses $40.4 $43.7

    Total Revenues $38.0 $37.3

    Net $2.4 $6.4

    Based on Projections as of April 30, 2011

  • 8/6/2019 RTM Metro Center Update June 27 2011

    40/43

    40

    Fairfield Metro CenterMajor Cost Variance

    Budgeted Projected Max

    Groundwater Treatment $0.1 $2.0

    Excess Soil Disposal $0.0 $2.0

    PCB Disposal $0.4 $1.0

    Processed Stone $0.1 $0.7

    Clean Fill $0.1 $0.6

    Stabilization of Soils (CKD)$0

    .0 $0

    .5

    Earth Excavation $0.7 $1.2

    Utilities $1.2 $1.7

    Total $2.6 $9.7

  • 8/6/2019 RTM Metro Center Update June 27 2011

    41/43

    41

    Summary and Action Items

    Critical Factor This project was bid as unit cost notlump sum. State required the Unit Cost Bid.

    Bid Quantities were significantly underestimated.

    With new agreement, Town assumed responsibility forcleaning up the project site. This agreement alsochanged the revenue stream to the Town.

    More Contamination means more Testing, moreExcavation, more Removal, more Clean Fill.

  • 8/6/2019 RTM Metro Center Update June 27 2011

    42/43

    42

    Summary and Action Items - 2

    To minimize project cost through completion add Construction Manager.

    Keep pressure on to achieve lower range of

    projections. Allows for Economic Development effort to restart.

    Work with BRR to find suitable onsite location for

    Excess Soil. This could avoid $1-$2 Million inproject costs.

  • 8/6/2019 RTM Metro Center Update June 27 2011

    43/43

    43

    Summary and Action Items - 3

    Work with State DOT to find additional FundingSources.

    Confirm Funding Needs and come back forfurther approval next month.


Recommended