+ All Categories
Home > Documents > RTN 950 V100R007C00 Commissioning Guide 02

RTN 950 V100R007C00 Commissioning Guide 02

Date post: 02-Nov-2015
Category:
Upload: nielsen-kaezer
View: 91 times
Download: 6 times
Share this document with a friend
Description:
RTN 950 V100R007C00 Commissioning Guide 02
213
 OptiX RTN 950 Radio Transmission System V100R007C00 Commissioning Guide Issue 02 Date 2014-09-15 HUAWEI TECHNOLOGIES CO., LTD.
Transcript
  • OptiX RTN 950 Radio Transmission SystemV100R007C00

    Commissioning Guide

    Issue 02Date 2014-09-15

    HUAWEI TECHNOLOGIES CO., LTD.

  • Copyright Huawei Technologies Co., Ltd. 2014. All rights reserved.No part of this document may be reproduced or transmitted in any form or by any means without prior writtenconsent of Huawei Technologies Co., Ltd. Trademarks and Permissions

    and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.All other trademarks and trade names mentioned in this document are the property of their respective holders. NoticeThe purchased products, services and features are stipulated by the contract made between Huawei and thecustomer. All or part of the products, services and features described in this document may not be within thepurchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,and recommendations in this document are provided "AS IS" without warranties, guarantees or representationsof any kind, either express or implied.

    The information in this document is subject to change without notice. Every effort has been made in thepreparation of this document to ensure accuracy of the contents, but all statements, information, andrecommendations in this document do not constitute a warranty of any kind, express or implied. Huawei Technologies Co., Ltd.Address: Huawei Industrial Base

    Bantian, LonggangShenzhen 518129People's Republic of China

    Website: http://www.huawei.comEmail: [email protected]

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    i

  • About This Document

    Related VersionsThe following table lists the product versions related to this document.

    Product Name VersionOptiX RTN 950 V100R007C00iManager U2000 V200R014C50

    Intended AudienceThis document describes how to commission the OptiX RTN 950, including preparations beforecommissioning, site commissioning, and system commissioning.The intended audience of this document are:Installation and commissioning engineers

    Symbol ConventionsThe symbols that may be found in this document are defined as follows.

    Symbol Description

    Indicates an imminently hazardous situationwhich, if not avoided, will result in death orserious injury.

    Indicates a potentially hazardous situationwhich, if not avoided, could result in death orserious injury.

    Indicates a potentially hazardous situationwhich, if not avoided, may result in minor ormoderate injury.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide About This Document

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    ii

  • Symbol DescriptionIndicates a potentially hazardous situationwhich, if not avoided, could result inequipment damage, data loss, performancedeterioration, or unanticipated results.NOTICE is used to address practices notrelated to personal injury.

    Calls attention to important information, bestpractices and tips.NOTE is used to address information notrelated to personal injury, equipment damage,and environment deterioration.

    General ConventionsThe general conventions that may be found in this document are defined as follows.

    Convention DescriptionTimes New Roman Normal paragraphs are in Times New Roman.Boldface Names of files, directories, folders, and users are in

    boldface. For example, log in as user root.Italic Book titles are in italics.Courier New Examples of information displayed on the screen are in

    Courier New.

    Command ConventionsThe command conventions that may be found in this document are defined as follows.

    Convention DescriptionBoldface The keywords of a command line are in boldface.Italic Command arguments are in italics.[ ] Items (keywords or arguments) in brackets [ ] are optional.{ x | y | ... } Optional items are grouped in braces and separated by

    vertical bars. One item is selected.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide About This Document

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    iii

  • Convention Description[ x | y | ... ] Optional items are grouped in brackets and separated by

    vertical bars. One item is selected or no item is selected.{ x | y | ... }* Optional items are grouped in braces and separated by

    vertical bars. A minimum of one item or a maximum of allitems can be selected.

    [ x | y | ... ]* Optional items are grouped in brackets and separated byvertical bars. Several items or no item can be selected.

    GUI ConventionsThe GUI conventions that may be found in this document are defined as follows.

    Convention DescriptionBoldface Buttons, menus, parameters, tabs, window, and dialog titles

    are in boldface. For example, click OK.> Multi-level menus are in boldface and separated by the ">"

    signs. For example, choose File > Create > Folder.

    Change HistoryUpdates between document issues are cumulative. Therefore, the latest document issue containsall updates made in previous issues.

    Updates in Issue 02 (2014-09-15) Based on Product Version V100R007C00This document is the second release of the V100R007C00 version.

    Change Description Fixed the known bugs.

    Updates in Issue 01 (2014-05-30) Based on Product Version V100R007C00This document is the first release of the V100R007C00 version.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide About This Document

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    iv

  • Contents

    About This Document.....................................................................................................................ii1 Safety Precautions.........................................................................................................................11.1 General Safety Precautions.............................................................................................................................................21.2 Warning and Safety Symbols.........................................................................................................................................31.3 Electrical Safety..............................................................................................................................................................41.4 Environment of Flammable Gas.....................................................................................................................................71.5 Storage Batteries.............................................................................................................................................................71.6 Radiation.........................................................................................................................................................................91.6.1 Safe Usage of Optical Fibers.......................................................................................................................................91.6.2 Electromagnetic Exposure.........................................................................................................................................111.6.3 Forbidden Areas........................................................................................................................................................111.6.4 Laser..........................................................................................................................................................................111.6.5 Microwave.................................................................................................................................................................121.7 Working at Heights.......................................................................................................................................................131.7.1 Hoisting Heavy Objects.............................................................................................................................................131.7.2 Using Ladders............................................................................................................................................................141.8 Mechanical Safety........................................................................................................................................................161.9 Other Precautions.........................................................................................................................................................172 Notices for High-Risk Operations...........................................................................................192.1 Operation Guide for the Toggle Lever Switch.............................................................................................................202.2 Operation Guide for the IF Jumper...............................................................................................................................222.3 Operation Guide for the IF Cables...............................................................................................................................232.4 Operation Guide for the IF Board.................................................................................................................................243 Commissioning Preparations....................................................................................................263.1 Preparing Documents and Tools...................................................................................................................................273.2 Preparing the Certificate File for NE Access from a USB Flash Drive.......................................................................293.3 Obtaining a USB Flash Drive.......................................................................................................................................313.4 Determining the Commissioning Method....................................................................................................................323.5 Checking Commissioning Conditions..........................................................................................................................333.5.1 Site Commissioning...................................................................................................................................................333.5.2 System Commissioning.............................................................................................................................................33

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide Contents

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    v

  • 4 Commissioning Process.............................................................................................................354.1 Site Commissioning Process........................................................................................................................................364.2 System Commissioning Process...................................................................................................................................405 Site Commissioning (Using the Web LCT)............................................................................425.1 Powering On the Equipment.........................................................................................................................................435.2 Logging In to the Web LCT (Through a Mini USB Interface)....................................................................................465.3 Logging In to the Web LCT (Through NMS Interface)...............................................................................................505.4 Downloading a Commissioning Data Script to an NE Using the Web LCT...............................................................525.5 Configuring Site Commissioning Data by Using the Web LCT..................................................................................535.5.1 Creating NEs by Using the Search Method...............................................................................................................585.5.2 Logging In to an NE (Web LCT)..............................................................................................................................595.5.3 Changing the NE ID..................................................................................................................................................605.5.4 Changing the NE Name.............................................................................................................................................615.5.5 Changing the NE IP Address.....................................................................................................................................625.5.6 Enabling NE Automatic Reporting............................................................................................................................635.5.7 Configuring Logical Boards......................................................................................................................................645.5.8 Synchronizing NE Time............................................................................................................................................655.5.9 Changing the Modem Chip Mode.............................................................................................................................665.5.10 Changing the IF Service Type.................................................................................................................................665.5.11 Configuring a Hop of Radio Link............................................................................................................................675.5.12 Creating an IF 1+1 Protection Group......................................................................................................................715.5.13 Configuring the VLAN ID and Bandwidth Used by an Inband DCN.....................................................................735.5.14 Configuring Orderwire............................................................................................................................................745.6 Checking Alarms..........................................................................................................................................................755.7 Testing Connectivity of Cables....................................................................................................................................765.7.1 Testing Connectivity of E1 Cables............................................................................................................................765.7.2 Testing Connectivity of Network Cables..................................................................................................................785.7.3 Checking Fiber Jumper Connection..........................................................................................................................795.8 Aligning the Antennas..................................................................................................................................................815.8.1 Main Lobe and Side Lobes........................................................................................................................................815.8.2 Aligning Single-Polarized Antennas.........................................................................................................................845.8.3 Aligning Dual-Polarized Antennas............................................................................................................................875.9 Checking the Radio Link Status and the Receive Power.............................................................................................906 Site Commissioning (Using a USB Flash Drive)...................................................................926.1 Powering On the Equipment.........................................................................................................................................936.2 Loading Commissioning Data from a USB Flash Drive..............................................................................................966.3 Using the Web LCT to Complete Subsequent Commissioning Items.........................................................................987 System Commissioning............................................................................................................1007.1 Configuring Networkwide Service Data....................................................................................................................1027.2 Testing Connectivity of E1 Services..........................................................................................................................102

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide Contents

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    vi

  • 7.2.1 Testing E1 Services by Using a BER Tester...........................................................................................................1027.2.2 Testing E1 Services Using PRBS............................................................................................................................1047.3 Testing Connectivity of Ethernet Services.................................................................................................................1067.3.1 Testing Ethernet Services Configured on a Per-NE Basis.......................................................................................1067.3.2 Testing Ethernet Services Configured in an End-to-End Manner...........................................................................1117.4 Testing ATM Services................................................................................................................................................1147.5 Testing AM Shifts......................................................................................................................................................1177.5.1 Testing AM Shifts on IFU2/IFX2 Boards...............................................................................................................1177.5.2 Testing AM Shifts on the ISU2/ISX2/ISV3............................................................................................................1197.6 Testing Protection Switching......................................................................................................................................1207.6.1 Testing IF 1+1 Protection Switching.......................................................................................................................1207.6.2 Testing N+1 Protection Switching..........................................................................................................................1227.6.3 Testing SNCP Switching.........................................................................................................................................1257.6.4 Testing ERPS Switching.........................................................................................................................................1297.6.5 Testing MPLS APS Protection Switching...............................................................................................................1327.6.6 Testing Linear MSP Switching................................................................................................................................1347.6.7 Testing Switching of the Integrated System Control and Communication, Switching, and Timing Board............1387.7 Checking the Clock Status..........................................................................................................................................1417.8 Testing the FM over a Radio Link..............................................................................................................................1427.9 Testing E1 Service Performance................................................................................................................................1477.10 Testing Ethernet Service Performance.....................................................................................................................1497.10.1 Testing Latency, Throughput, and Packet Loss Ratio...........................................................................................1497.10.2 Testing the Long-term Packet Loss Ratio.............................................................................................................1538 Site Commissioning Data Script Generation Using the Offline Configuration Function..........................................................................................................................................................1568.1 Process of Generating a Commissioning Data Script.................................................................................................1578.1.1 Creating a Pre-configured NE.................................................................................................................................1578.1.2 Configuring Site Commissioning Data....................................................................................................................1628.1.3 Generating a Commissioning Data Script...............................................................................................................1669 ETH-OAM Operations on the EoS/EoPDH Plane...............................................................1689.1 Creating MDs.............................................................................................................................................................1699.2 Creating MAs.............................................................................................................................................................1709.3 Creating MPs..............................................................................................................................................................1719.4 Performing an LB Test...............................................................................................................................................1729.5 Parameter Description: Ethernet Service OAM_Creation of MDs............................................................................1739.6 Parameter Description: Ethernet Service OAM_Creation of MAs............................................................................1749.7 Parameter Description: Ethernet Service OAM_Creation of MPs.............................................................................1759.8 Parameter Description: Ethernet Service OAM_Enabling LB...................................................................................177A Glossary......................................................................................................................................179

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide Contents

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    vii

  • 1 Safety PrecautionsAbout This Chapter

    This topic describes the safety precautions that you must follow when installing, operating, andmaintaining Huawei devices.

    1.1 General Safety PrecautionsThis topic describes essential safety precautions that instruct you in the selection of measuringand testing instruments when you install, operate, and maintain Huawei devices.1.2 Warning and Safety SymbolsBefore using the equipment, note the following warning and safety symbols on the equipment.1.3 Electrical SafetyThis topic describes safety precautions for high voltage, lightning strikes, high leakage current,power cables, fuses, and ESD.1.4 Environment of Flammable GasThis topic describes safety precautions for the operating environment of a device.1.5 Storage BatteriesThis topic describes safety precautions for operations of storage batteries.1.6 RadiationThis topic describes safety precautions for electromagnetic exposure and lasers.1.7 Working at HeightsThis topic describes safety precautions for working at heights.1.8 Mechanical SafetyThis topic describes safety precautions for drilling holes, handling sharp objects, operating fans,and carrying heavy objects.1.9 Other PrecautionsThis topic describes safety precautions for removing and inserting boards, binding signal cables,and routing cables.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1

  • 1.1 General Safety PrecautionsThis topic describes essential safety precautions that instruct you in the selection of measuringand testing instruments when you install, operate, and maintain Huawei devices.

    All Safety PrecautionsTo ensure the safety of humans and a device, follow the marks on the device and all the safetyprecautions in this document when installing, operating, and maintaining a device.The "CAUTION", "WARNING", and "DANGER" marks in this document do not cover all thesafety precautions that must be followed. They are supplements to the safety precautions.

    Local Laws and RegulationsWhen operating a device, always comply with the local laws and regulations. The safetyprecautions provided in the documents are in addition/supplementary to the local laws andregulations.

    Basic Installation RequirementsThe installation and maintenance personnel of Huawei devices must receive strict training andbe familiar with the proper operation methods and safety precautions before any operation.l Only trained and qualified personnel are permitted to install, operate, and maintain a device.l Only certified professionals are permitted to remove the safety facilities, and to troubleshoot

    and maintain the device.l Only the personnel authenticated or authorized by Huawei are permitted to replace or

    change the device or parts of the device (including software).l The operating personnel must immediately report the faults or errors that may cause safety

    problems to the person in charge.

    Grounding RequirementsThe grounding requirements are applicable to the device that needs to be grounded.l When installing the device, always connect the grounding facilities first. When removing

    the device, always disconnect the grounding facilities last.l Ensure that the grounding conductor is intact.l Do not operate the device in the absence of a suitably installed grounding conductor.l The device must be connected to the PGND permanently. Before operating the device,

    check the electrical connections of the device, and ensure that the device is properlygrounded.

    Human Safetyl When there is a risk of a lightning strike, do not operate the fixed terminal or touch the

    cables.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    2

  • l When there is risk of a lightning strike, unplug the AC power connector. Do not use thefixed terminal or touch the terminal or antenna connector.

    NOTEThe preceding requirements apply to wireless fixed station terminals.

    l To avoid electric shocks, do not connect safety extra-low voltage (SELV) circuits totelephone-network voltage (TNV) circuits.

    l Do not look into optical ports without eye protection. Otherwise, human eyes may be hurtby laser beams.

    l Before operating the device, wear an ESD protective coat, ESD gloves, and an ESD wriststrap. In addition, you need to get off the conductive objects, such as jewelry and watches,to prevent electric shock and burn.

    l In case of fire, escape from the building or site where the device is located and press thefire alarm bell or dial the telephone number for fire alarms. Do not enter the burning buildingagain in any situation.

    Device Safetyl Before any operation, install the device firmly on the ground or other rigid objects, such as

    on a wall or in a rack.l When the system is working, ensure that the ventilation hole is not blocked.l When installing the front panel, use a tool to tighten the screws firmly, if required.l After installing the device, clean up the packing materials.

    1.2 Warning and Safety SymbolsBefore using the equipment, note the following warning and safety symbols on the equipment.Table 1-1 lists the warning and safety symbols of the OptiX RTN 950 and their meanings.

    Table 1-1 Warning and safety symbols of the OptiX RTN 950Symbol Indication

    This symbol is for ESD protection.A notice with this symbol indicates that you should wearan ES wrist strap or glove when you touch a board.Otherwise, you may cause damage to the board.

    CLASS 1LASER

    PRODUCT

    LASERRADIATION

    DO NOT VIEW DIRECTLYWITH OPTICALINSTRUMENTS

    CLASS 1M LASERPRODUCT

    This symbol is for the laser class.A notice with this symbol indicates the class of the laser.Avoid direct exposure to the laser beams. Otherwise, it maydamage you eyes or skin.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3

  • Symbol IndicationA notice with this symbol indicates where the subrack isgrounded.

    ATTENTION CLEAN PERIODICALLY

    A notice with this symbol indicates that the air filter shouldbe cleaned periodically.

    DON'T TOUCH THEFAN LEAVES BEFORETHEY SLOW DOWN !

    This symbol is for fan safety.A notice with this symbol indicates that the fan leavesshould not be touched when the fan is rotating.

    1.3 Electrical SafetyThis topic describes safety precautions for high voltage, lightning strikes, high leakage current,power cables, fuses, and ESD.

    High Voltage

    DANGERl A high-voltage power supply provides power for device operations. Direct human contact

    with the high voltage power supply or human contact through damp objects can be fatal.l Unspecified or unauthorized high voltage operations could result in fire or electric shock, or

    both.

    ThunderstormThe requirements apply only to wireless base stations or devices with antennas and feeders.

    DANGERDo not perform operations on high voltage, AC power, towers, or backstays in stormy weatherconditions.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    4

  • High Leakage Current

    CAUTIONBefore powering on a device, ground the device. Otherwise, the safety of humans and the devicecannot be ensured.

    If a high leakage current mark is labeled near the power connector of the device, you mustconnect the PGND terminal on the shell to the ground before connecting the device to an A/Cinput power supply. This is to prevent the electric shock caused by leakage current of the device.

    Power Cables

    DANGERDo not install or remove the power cable with a live line. Transient contact between the core ofthe power cable and the conductor may generate electric arc or spark, which may cause fire oreye injury.

    l Before installing or removing power cables, you must power off the device.l Before connecting a power cable, you must ensure that the label on the power cable is

    correct.

    Device with Power On

    DANGERInstalling or removing a device is prohibited if the device is on.

    DANGERDo not install or remove the power cables of the equipment when it is powered on.

    Short CircuitsWhen installing and maintaining devices, place and use the associated tools and instruments inaccordance with regulations to avoid short-circuits caused by metal objects.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    5

  • NOTICETo avoid short-circuits when using a tool (such as a screwdriver), do not place the tool on theventilation plate of the subrack.

    NOTICEPrevent any screws from dropping into the subrack or chassis to avoid short-circuits.

    Fuse

    CAUTIONIf the fuse on a device blows, replace the fuse with a fuse of the same type and specifications toensure safe operation of the device.

    Electrostatic Discharge

    NOTICEThe static electricity generated by the human body may damage the electrostatic sensitivecomponents on the board, such as the large-scale integrated circuit (LSI).

    l The human body can generate static electromagnetic fields in the following situations:physical movement, clothing friction, friction between shoes and the ground, plastics inthe hand. Such static electromagnetic effects can remain for an appreciable time.

    l Before operating a device, circuit boards, or ASICs, wear an ESD wrist strap that is properlygrounded. The ESD wrist strap can prevent the electrostatic-sensitive components frombeing damaged by the static electricity in the human body.

    Figure 1-1 shows the method of wearing an ESD wrist strap.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    6

  • Figure 1-1 Wearing an ESD wrist strap

    1.4 Environment of Flammable GasThis topic describes safety precautions for the operating environment of a device.

    DANGERDo not place or operate devices in an environment of flammable or explosive air or gas.

    Operating an electronic device in an environment of flammable gas causes a severe hazard.

    1.5 Storage BatteriesThis topic describes safety precautions for operations of storage batteries.

    DANGERBefore operating a storage battery, you must read the safety precautions carefully and be familiarwith the method of connecting a storage battery.

    l Incorrect operations of storage batteries cause hazards. During operation, prevent any short-circuit, and prevent the electrolyte from overflowing or leakage.

    l If the electrolyte overflows, it causes potential hazards to the device. The electrolyte maycorrode metal parts and the circuit boards, and ultimately damage the circuit boards.

    l A storage battery contains a great deal of energy. Misoperations may cause a short-circuit,which leads to human injuries.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    7

  • Basic PrecautionsTo ensure safety, note the following points before installing or maintaining the storage battery:l Use special insulation tools.l Wear an eye protector and take effective protection measures.l Wear rubber gloves and a protection coat to prevent the hazard caused by the overflowing

    electrolyte.l When handling the storage battery, ensure that its electrodes are upward. Leaning or

    reversing the storage battery is prohibited.l Before installing or maintaining the storage battery, ensure that the storage battery is

    disconnected from the power supply that charges the storage battery.

    Short-Circuit

    DANGERA battery short-circuit may cause human injuries. Although the voltage of an ordinary batteryis low, the instantaneous high current caused by a short-circuit emits a great deal of energy.

    Avoid any short-circuit of batteries caused by metal objects. If possible, disconnect the workingbattery before performing other operations.

    Hazardous Gas

    NOTICEDo not use any unsealed lead-acid storage battery. Lay a storage battery horizontally and fix itproperly to prevent the battery from emitting flammable gas, which may cause fire or deviceerosion.

    Working lead-acid storage batteries emit flammable gas. Therefore, ventilation and fireproofingmeasures must be taken at the sites where lead-acid storage batteries are placed.

    Battery Temperature

    NOTICEIf a battery overheats, the battery may be deformed or damaged, and the electrolyte mayoverflow.

    When the temperature of the battery is higher than 60C, you need to check whether theelectrolyte overflows. If the electrolyte overflows, take appropriate measures immediately.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    8

  • Battery Leakage

    NOTICEIn the event of acid overflow or spillage, neutralize the acid and clean it up appropriately.

    When handling a leaky battery, protect against the possible damage caused by the acid. Whenyou find the electrolyte leaks, you can use the following substances to counteract and absorb theleaking electrolyte:l Sodium bicarbonate (NaHCO3)l Sodium carbonate (Na2CO3)In the event of acid overflow or spillage, neutralize the acid and clean it up as recommended bythe battery manufacturer and any local regulations for acid disposal.If a person contacts battery electrolyte, clean the skin that contacts the battery electrolyteimmediately by using water. In case of a severe situation, the person must be sent to a hospitalimmediately.

    1.6 RadiationThis topic describes safety precautions for electromagnetic exposure and lasers.

    1.6.1 Safe Usage of Optical FibersThe laser beam can cause damage to your eyes. Hence, you must exercise caution when usingoptical fibers.

    DANGERWhen installing or maintaining an optical interface board or optical fibers, avoid direct eyeexposure to the laser beams launched from the optical interface board or fiber connectors. Thelaser beam can cause damage to your eyes.

    Cleaning Fiber Connectors and Optical Interfaces

    NOTICEIf fiber connectors or flanges are contaminated, optical power commissioning is seriouslyaffected. Therefore, the two endfaces and flange of every external fiber must be cleaned beforethe fiber is led into the equipment through the ODF for being inserted into an optical interfaceon the equipment.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    9

  • The fiber connectors and optical interfaces of the lasers must be cleaned with the followingspecial cleaning tools and materials:l Special cleaning solvent: It is preferred to use isoamylol. Propyl alcohol, however, can also

    be used. It is prohibited that you use alcohol and formalin.l Non-woven lens tissuel Special compressed gasl Cotton stick (medical cotton or long fiber cotton)l Special cleaning roll, used with the recommended cleaning solventl Special magnifier for fiber connectorsFor cleaning steps, see Task Collection "Cleaning Fiber Connectors and Adapters" in the OptiXRTN 950 Radio Transmission System Maintenance and Troubleshooting.

    Replacing Optical FibersWhen replacing an optical fiber, cover the fiber connector of the unused optical fiber with aprotective cap.

    Connecting Optical Fibersl Use an attenuator if the optical power is excessively high. A high received optical power

    damages the optical interface.l Directly connect an attenuator to a slanting optical interface. Install the attenuator on the

    IN port instead of the OUT port.l Do not directly connect an attenuator to the level optical interface. Use the optical

    distribution frame (ODF) to connect an attenuator to a level optical interface.Figure 1-2 shows a slanting optical interface, and Figure 1-3 shows a level optical interface.

    Figure 1-2 Slanting optical interface

    Slanting opticalinterface

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    10

  • Figure 1-3 Level optical interface

    Level opticalinterface

    1.6.2 Electromagnetic ExposureThis topic describes safety precautions for electromagnetic exposure.If multiple transmit antennas are installed on a tower or backstay, keep away from the transmitdirections of the antennas when you install or maintain an antenna locally.

    NOTICEEnsure that all personnel are beyond the transmit direction of a working antenna.

    1.6.3 Forbidden AreasThe topic describes requirements for a forbidden area.l Before entering an area where the electromagnetic radiation is beyond the specified range,

    the associated personnel must shut down the electromagnetic radiator or stay at least 10meters away from the electromagnetic radiator, if in the transmit direction.

    l A physical barrier and an eye-catching warning flag should be available in each forbiddenarea.

    1.6.4 LaserThis topic describes safety precautions for lasers.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    11

  • CAUTIONWhen handling optical fibers, do not stand close to, or look into the optical fiber outlet directlywithout eye protection.

    Laser transceivers are used in the optical transmission system and associated test tools. The lasertransmitted through the bare optical fiber produces a small beam of light, and therefore it hasvery high power density and is invisible to human eyes. When a beam of light enters eyes, theeyes may be damaged.In normal cases, viewing an un-terminated optical fiber or a damaged optical fiber without eyeprotection at a distance greater than 150 mm does not cause eye injury. Eye injury may occur,however, if an optical tool such as a microscope, magnifying glass, or eye loupe is used to viewan un-terminated optical fiber.

    Safety Instructions Regarding LasersTo avoid laser radiation, obey the following instructions:l All operations should be performed by authorized personnel who have completed the

    required training courses.l Wear a pair of eye-protective glasses when you are handling lasers or fibers.l Ensure that the optical source is switched off before disconnecting optical fiber connectors.l Do not look into the end of an exposed fiber or an open connector when you are not sure

    whether the optical source is switched off.l Use an optical power meter to measure the optical power and ensure that the optical source

    is switched off.l Before opening the front door of an optical transmission device, ensure that you are not

    exposed to laser radiation.l Do not use an optical tool such as a microscope, a magnifying glass, or an eye loupe to

    view the optical connector or fiber that is transmitting optical signals.

    Instructions Regarding Fiber HandlingRead and abide by the following instructions before handling fibers:l Only trained personnel are permitted to cut and splice fibers.l Before cutting or splicing a fiber, ensure that the fiber is disconnected from the optical

    source. After disconnecting the fiber, cap to the fiber connectors.

    1.6.5 MicrowaveWhen installing and maintaining the equipment of Huawei, follow the safety precautions ofmicrowave to ensure the safety of the human body and the equipment.

    CAUTIONStrong radio frequency can harm the human body.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    12

  • When installing or maintaining an aerial on the tower or mast that is installed with multipleaerials, switch off the transmitter in advance.

    1.7 Working at HeightsThis topic describes safety precautions for working at heights.

    CAUTIONWhen working at heights, be cautious to prevent objects from falling down.

    The requirements for working at heights are as follows:l The personnel who work at heights must be trained.l Carry and handle the operating machines and tools with caution to prevent them from falling

    down.l Safety measures, such as wearing a helmet and a safety belt, must be taken.l Wear cold-proof clothes when working at heights in cold areas.l Check all lifting appliances thoroughly before starting the work, and ensure that they are

    intact.

    1.7.1 Hoisting Heavy ObjectsThis topic describes the safety precautions for hoisting heavy objects that you must follow wheninstalling, operating, and maintaining Huawei devices.

    CAUTIONWhen heavy objects are being hoisted, do not walk below the cantilever or hoisted objects.

    l Only trained and qualified personnel can perform hoisting operations.l Before hoisting heavy objects, check that the hoisting tools are complete and in good

    condition.l Before hoisting heavy objects, ensure that the hoisting tools are fixed to a secure object or

    wall with good weight-bearing capacity.l Issue orders with short and explicit words to ensure correct operations.l Ensure that the angle between the two cables is less than or equal to 90 degrees during the

    lifting, as shown in Figure 1-4.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    13

  • Figure 1-4 Hoisting heavy objects

    1.7.2 Using LaddersThis topic describes safety precautions for using ladders.

    Checking Laddersl Before using a ladder, check whether the ladder is damaged. After checking that the ladder

    is in good condition, you can use the ladder.l Before using a ladder, you should know the maximum weight capacity of the ladder. Avoid

    overweighing the ladder.

    Placing LaddersThe proper slant angle of the ladder is 75 degrees. You can measure the slant angle of the ladderwith an angle square or your arms, as shown in Figure 1-5. When using a ladder, to prevent theladder from sliding, ensure that the wider feet of the ladder are downward, or take protectionmeasures for the ladder feet. Ensure that the ladder is placed securely.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    14

  • Figure 1-5 Slanting a ladder

    Climbing Up a LadderWhen climbing up a ladder, pay attention to the following points:l Ensure that the center of gravity of your body does not deviate from the edges of the two

    long sides.l Before operations, ensure that your body is stable to reduce risks.l Do not climb higher than the fourth rung of the ladder (counted from up to down).If you want to climb up a roof, ensure that the ladder top is at least one meter higher than theroof, as shown in Figure 1-6.

    Figure 1-6 Ladder top being one meter higher than the roof

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    15

  • 1.8 Mechanical SafetyThis topic describes safety precautions for drilling holes, handling sharp objects, operating fans,and carrying heavy objects.

    Drilling Holes

    CAUTIONDo not drill holes on the cabinet without prior permission. Drilling holes without complyingwith the requirements affects the electromagnetic shielding performance of the cabinet anddamages the cables inside the cabinet. In addition, if the scraps caused by drilling enter thecabinet, the printed circuit boards (PCBs) may be short-circuited.

    l Before drilling a hole on the cabinet, remove the cables inside the cabinet.l Wear an eye protector when drilling holes. This is to prevent eyes from being injured by

    the splashing metal scraps.l Wear protection gloves when drilling holes.l Take measures to prevent the metallic scraps from falling into the cabinet. After the drilling,

    clean up the metallic scraps.

    Sharp Objects

    CAUTIONWear protection gloves when carrying the device. This is to prevent hands from being injuredby the sharp edges of the device.

    Fansl When replacing parts, place the objects such as the parts, screws, and tools properly. This

    is to prevent them from falling into the operating fans, which damages the fans or device.l When replacing the parts near fans, keep your fingers or boards from touching operating

    fans before the fans are powered off and stop running. Otherwise, the hands or the boardsare damaged.

    Carrying Heavy ObjectsWear protection gloves when carrying heavy objects. This is to prevent hands from being hurt.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    16

  • CAUTIONl The carrier must be prepared for load bearing before carrying heavy objects. This is to prevent

    the carrier from being strained or pressed by the heavy objects.l When you pull a chassis out of the cabinet, pay attention to the unstable or heavy objects on

    the cabinet. This is to prevent the heavy objects on the cabinet top from falling down, whichmay hurt you.

    l Generally, two persons are needed to carry a chassis. It is prohibited that only one personcarries a heavy chassis. When carrying a chassis, the carriers should stretch their backs andmove stably to avoid being strained.

    l When moving or lifting a chassis, hold the handles or bottom of the chassis. Do not holdthe handles of the modules installed in the chassis, such as the power modules, fan modules,and boards.

    1.9 Other PrecautionsThis topic describes safety precautions for removing and inserting boards, binding signal cables,and routing cables.

    Removing and Inserting a Board

    NOTICEWhen inserting a board, wear an ESD wrist strap or ESD gloves, and handle the board gently toavoid distorting pins on the backplane.

    l Slide the board along the guide rails.l Do not contact one board with another to avoid short-circuits or damage.l When holding a board in hand, do not touch the board circuits, components, connectors,

    or connection slots of the board to prevent damage caused by ESD of the human body tothe electrostatic-sensitive components.

    Binding Signal Cables

    NOTICEBind the signal cables separately from the high-current or high-voltage cables.

    Routing CablesIn the case of extremely low temperature, heavy shock or vibration may damage the plastic skinof the cables. To ensure the construction safety, comply with the following requirements:

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    17

  • l When installing cables, ensure that the environment temperature is above 0C.l If the cables are stored in a place where the ambient temperature is below 0C, transfer

    them to a place at room temperature and store the cables for more than 24 hours beforeinstallation.

    l Handle the cables gently, especially in a low-temperature environment. Do not performany improper operations, for example, pushing the cables down directly from a truck.

    High Temperature

    CAUTIONIf the ambient temperature exceeds 55C, the temperature of the front panel surface marked the

    flag may exceed 70C. When touching the front panel of the board in such an environment,you must wear the protection gloves.

    IF Cables

    CAUTIONBefore installing or removing an IF cable, you must turn off the power switch of the IF board.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 1 Safety Precautions

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    18

  • 2 Notices for High-Risk OperationsAbout This Chapter

    This topic provides notices for the operations that may cause bodily injury or equipment damageif they are not performed properly during the commissioning and maintenance of microwaveequipment.

    2.1 Operation Guide for the Toggle Lever SwitchThe ODU-PWR switch on the IF board is a toggle lever switch which must be turned on and offas per the following instructions to avoid damaging the IF board.2.2 Operation Guide for the IF JumperBefore installing or removing IF jumpers, shut down the ODU power supply to prevent personalinjuries and damaged to the IF boards or ODU.2.3 Operation Guide for the IF CablesBefore installing or removing IF cables, shut down the ODU power supply to prevent personalinjuries and damaged to the IF boards or ODU.2.4 Operation Guide for the IF BoardBefore removing or installing an IF board, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 2 Notices for High-Risk Operations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    19

  • 2.1 Operation Guide for the Toggle Lever SwitchThe ODU-PWR switch on the IF board is a toggle lever switch which must be turned on and offas per the following instructions to avoid damaging the IF board.

    Position and Description of the Toggle Lever SwitchThe toggle lever switch is located on the IF board and controls the power that is fed to the ODU,as shown in Figure 2-1.

    Figure 2-1 Toggle lever switch

    Turning On the Toggle Lever Switch1. Gently pull on the toggle lever switch out.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 2 Notices for High-Risk Operations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    20

  • 2. Turn it to the left.

    3. Release the toggle lever switch.

    Turning Off the Toggle Lever Switch1. Gently pull on the toggle lever switch out.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 2 Notices for High-Risk Operations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    21

  • 2. Turn it to the right.

    3. Release the toggle lever switch.

    2.2 Operation Guide for the IF JumperBefore installing or removing IF jumpers, shut down the ODU power supply to prevent personalinjuries and damaged to the IF boards or ODU.

    ProcedureStep 1 Follow instructions in 2.1 Operation Guide for the Toggle Lever Switch to power off the

    ODU.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 2 Notices for High-Risk Operations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    22

  • 21

    DANGEREnsure that the ODU is completely powered off before removing or installing the IF jumper.

    Step 2 Remove or install the IF jumper.----End

    2.3 Operation Guide for the IF CablesBefore installing or removing IF cables, shut down the ODU power supply to prevent personalinjuries and damaged to the IF boards or ODU.

    ProcedureStep 1 Follow instructions in 2.1 Operation Guide for the Toggle Lever Switch to power off the

    ODU.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 2 Notices for High-Risk Operations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    23

  • DANGEREnsure that the ODU is completely powered off before removing or installing the IF cable.

    Step 2 Install or remove the IF cables.----End

    2.4 Operation Guide for the IF BoardBefore removing or installing an IF board, turn off the ODU-PWR switch to avoid bodily injuryor damage to the IF board and ODU.

    ProcedureStep 1 Turn off the ODU-PWR switch on the IF board. For details, see 2.1 Operation Guide for the

    Toggle Lever Switch.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 2 Notices for High-Risk Operations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    24

  • 321

    3

    DANGEREnsure that the ODU is completely powered off before removing or installing the IF board.

    Step 2 Disconnect the IF jumper or IF cable.Step 3 Remove or install the IF board.

    ----End

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 2 Notices for High-Risk Operations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    25

  • 3 Commissioning PreparationsAbout This Chapter

    This chapter describes the preparations that need to be made prior to commissioning equipment.

    3.1 Preparing Documents and ToolsThis section lists the document and tools that should be prepared prior to commissioning theequipment.3.2 Preparing the Certificate File for NE Access from a USB Flash DriveThis section describes how to prepare an RTN.CER file used for certification of NE access froma USB flash drive. The file allows you to perform site commissioning, database backup/restoration, and software upgrades using a USB flash drive.3.3 Obtaining a USB Flash DriveObtain a proper USB flash drive before you commission a site by using a USB flash drive.3.4 Determining the Commissioning MethodBy using the U2000 for commissioning, engineers can adopt the single-hop commissioningmethod or network commissioning method based on the network size.3.5 Checking Commissioning ConditionsEnsure that the equipment meets the commissioning requirements for the site or system prior toperforming such tasks. The following sections provide a non-exhaustive checklist for bothscenarios.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    26

  • 3.1 Preparing Documents and ToolsThis section lists the document and tools that should be prepared prior to commissioning theequipment.

    DocumentsThe following document should be available before commissioning the equipment:l Engineering design documents, including:

    Network plan Engineering design

    l Commissioning guides, including: OptiX RTN 950 Radio Transmission System Commissioning Guide OptiX RTN 950 Radio Transmission System Configuration Guide

    ToolsTable 3-1 lists the tools required for the commissioning task.

    Table 3-1 Tools and metersTool and Meter Application Scenariol Adjustable wrenchl Screwdriverl Telescopel Interphonel Hex keyl Multimeter that has a test cable with a

    BNC connector at one endl North-stabilized indicator

    Aligning antennas

    l Laptop on which the Web LCT is installedl Mini USB cable

    l Connecting the Web LCT to the MiniUSB port of the CSHU/CSHUA board

    l Configuring site commissioning data byusing the Web LCT, or download acommissioning data script to an NE usingthe Web LCT

    l Testing connectivity of E1 cablesl Checking the radio link status and the

    receive powerl Checking alarms

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    27

  • Tool and Meter Application Scenariol Laptop on which the Web LCT is installedl Network cable

    l Connecting the Web LCT to the NMS portl Configuring site commissioning data by

    using the Web LCT, or download acommissioning data script to an NE usingthe Web LCT

    l Testing connectivity of E1 cablesl Checking the radio link status and the

    receive powerl Checking alarms

    USB flash drive where desired sitecommissioning data has been storedNOTEl The recommended USB flash drive type for

    the OptiX RTN 950 is Netac U208 (4 Gbytes).Not all USB flash drives are supported by theOptiX RTN 950. If a USB flash drive ofanother model or capacity is required, confirmwith the local Huawei representative officethat the USB flash drive is supported by theOptiX RTN 950.

    l If you want to upgrade the NE software whenperforming the per-NE commissioning, put thelatest NE software package in the pkg folderof the USB flash drive.

    Loading commissioning data from a USBflash drive

    BER tester l Testing connectivity of E1 cablesl Testing E1 servicesl Testing IF 1+1 switchingl Testing N+1 protection switchingl Testing SNCP switchingl Testing linear MSP switchingl Testing E1 service performance

    Network cable tester Testing connectivity of network cablesl Optical power meterl Short fiber jumper

    Checking connectivity of optical fibers

    PC on which the U2000 is installed Centralized U2000 commissioningE1 jumper Testing E1 service performance

    NOTE

    For details about the requirements and methods for installing the Web LCT, see the iManager U2000 WebLCT User Guide.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    28

  • 3.2 Preparing the Certificate File for NE Access from a USBFlash Drive

    This section describes how to prepare an RTN.CER file used for certification of NE access froma USB flash drive. The file allows you to perform site commissioning, database backup/restoration, and software upgrades using a USB flash drive.

    PrerequisitesThe NMS is available.

    Tools, Equipment, and MaterialsU2000

    NOTE

    Web LCT also supports this operation and the steps are the similar to those on the U2000.

    ProcedureStep 1 Optional: Query the encryption algorithm used for the NE password and set related parameters

    accordingly.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    29

  • NOTEThe supported encryption types are MD5, SHA256, and PBKDF2. The default encryption type is PBKDF2.

    Step 2 Access the directory for saving the USB file generation tool.NOTE

    l On the U2000, the tool is stored under D:\oss\client\client\tools\usbtool (an example).l On the Web LCT, the tool is stored under D:\WebLCT\weblct\tools\usbtool (an example).

    Step 3 Run startup_usbTool.bat.

    The USB File Generation Tool dialog box is displayed.Step 4 Generate a certification file for NE access from a USB flash drive.

    1. Enter the user name and password for logging in to the NE to be commissioned.NOTE

    l Default user name: szhwl Default password: nesoft

    2. Select an encryption type according to the encryption algorithm used by the NE.NOTE

    l The supported encryption types are MD5, SHA256, and PBKDF2. The default encryption type isPBKDF2.

    l If you do not know the encryption algorithm used by the NE, select All. In this case, the certificationfile generated by the USB file generation tool includes three segments of ciphertexts for the password.Each segment corresponds to one algorithm from MD5, SHA256, and PBKDF2. The NE decrypts theciphertexts according to the used encryption algorithm.

    l If PBKDF2 or All is selected, set SSL Certificate and Certificate File Path. SSL Certificate includestwo types: Default and Custom.l If you want to use the default certificate file of the U2000, select Default. The default certificate

    file server.p12 is saved in the U2000 server path (such as D:\oss\server\etc\ssl\nemanager\default\keyStore\PFX\), and the default key is Changeme_123, so this file can be used only when theUSB file generation tool is run on the U2000 server. If you want to use another certificate file,select Custom.

    l Customized certificates include two types: *.crt and *.p12. A *.p12 certificate is encrypted, so akey is required.

    l Both *.crt and *.p12 certificates need to be synchronized with the NE. For details, see the U2000Administrator Guide.

    3. Click Generate File.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    30

  • Step 5 Click OK in the displayed confirmation dialog box.

    Step 6 Go to the directory where the RTN.CER file is stored, and copy it to the root directory of theUSB flash drive.

    NOTE

    l On the U2000, the RTN.CER file is stored under D:\oss\client\client\tools\usbtool\output (an example).l On the Web LCT, the RTN.CER file is stored under D:\WebLCT\weblct\tools\usbtool\output (an

    example).l Save the RTN.CER file before closing the USB file generation tool. Otherwise, the file will be automatically

    deleted when you close the tool.

    Step 7 Click Close.----End

    3.3 Obtaining a USB Flash DriveObtain a proper USB flash drive before you commission a site by using a USB flash drive.

    Supported ModelThe recommended USB flash drive for the OptiX RTN 950 is Netac U208 with a 4 GB capacity.A USB flash drive of another model or capacity may cause incompatibility issues. If a USB flashdrive of another model or capacity is required, contact the local Huawei office for confirmation.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    31

  • Data and Storage Locations on a USB Flash DriveData Storage LocationRTN.CER Root directory

    NOTEThe RTN.CER file contains the administrator-level accounts and the mapping passwords that areencrypted. This file can be generated by using adedicated tool.

    NE software \pkgNOTE

    Data is saved in the \pkg folder only when the NEsoftware is upgraded. Otherwise, keep the folderempty.

    License \licenseScripts \script

    3.4 Determining the Commissioning MethodBy using the U2000 for commissioning, engineers can adopt the single-hop commissioningmethod or network commissioning method based on the network size.

    ContextNOTE

    In the following instructions for both types of commissioning methods, site commissioning and systemcommissioning are defined as follows:l Site commissioning refers to commissioning that is performed on a hop and sites at both ends of the

    radio link by connecting the commissioning tool to the NE at a single site.l System commissioning refers to commissioning that is performed on all the NEs in the network by

    connecting the commissioning tool to a gateway NE where it configures the commissioning data foreach site.

    Single-hop CommissioningThe single-hop commissioning method is preferred for small-scale microwave transmissionnetworks (for example, a network with only one or two radio link hops). By performing single-hop commissioning, you can complete all site and system commissioning items at a time. Themajor commissioning steps are as follows:1. On both ends of a radio link, power on the NEs.2. Use the Web LCT to configure site commissioning data or copying site commissioning

    data from the USB flash drive.NOTE

    The commissioning data is all NE data including service data and clock data.3. Use the Web LCT to complete the site commissioning items.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    32

  • 4. Use the Web LCT to complete the system commissioning items.NOTE

    The Web LCT is used for single-hop commissioning, and therefore this document does not detail how to usethe Web LCT. For details about how to use the Web LCT, see the Commissioning Guide in the documentationpackage of the Web LCT version.

    Network CommissioningThe network commissioning method is usually used for large-scale microwave transmissionnetworks. The major commissioning steps are as follows:1. On both ends of a radio link, power on the NEs.2. Use the Web LCT to configure site commissioning data, or copying site commissioning

    data from the USB flash drive.NOTE

    The commissioning data may contain only data that is required for DCN and link availability.3. Use the Web LCT to complete the site commissioning items.4. Use the U2000 to complete the system commissioning items at sites where services

    converge.

    3.5 Checking Commissioning ConditionsEnsure that the equipment meets the commissioning requirements for the site or system prior toperforming such tasks. The following sections provide a non-exhaustive checklist for bothscenarios.

    3.5.1 Site CommissioningEnsure that the equipment and weather meet the requirements for site commissioning.

    ContextDetails about these requirements are as follows:l Hardware installation has been completed and has passed the installation check.l Power is available to the equipment.l The service signal cables that are connected to other equipment have been properly routed.l The appropriate risk control measures to arrest falling objects and ensure personnel safety

    are in place.l There is no adverse weather (such as wind, rain, snow, or fog) that could hinder or impact

    the commissioning.

    3.5.2 System CommissioningEnsure that the equipment and weather meet the requirements for system commissioning.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    33

  • ContextDetails about these requirements are as follows:l Site commissioning at both ends of a radio link has been completed.l DCN communication on the radio network is normal.l There is no adverse weather (such as wind, rain, snow, or fog) that could hinder or impact

    the commissioning.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 3 Commissioning Preparations

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    34

  • 4 Commissioning ProcessAbout This Chapter

    Based on the objects to be commissioned, the process can be divided into two stages: sitecommissioning and system commissioning.

    4.1 Site Commissioning ProcessSite commissioning refers to commissioning that is performed on a hop and sites at both endsof a radio link. Site commissioning ensures that the sites and the radio link between the siteswork properly, and is also performed in preparation of system commissioning.4.2 System Commissioning ProcessSystem commissioning refers to commissioning for the entire microwave transmission network.System commissioning ensures that various services are transmitted properly and protectionfunctions are implemented over the microwave transmission network.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 4 Commissioning Process

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    35

  • 4.1 Site Commissioning ProcessSite commissioning refers to commissioning that is performed on a hop and sites at both endsof a radio link. Site commissioning ensures that the sites and the radio link between the siteswork properly, and is also performed in preparation of system commissioning.

    ContextYou can use the following methods to configure site commissioning data for the OptiX RTN950 on site:l Web LCTl USB flash drive

    Site Commissioning Flowchart (Configuring Site Commissioning Data by Usingthe Web LCT)

    Commissioning engineers can configure site commissioning data by using the Web LCT on sitewhen they are:l Familiar with how to configure radio link data on the OptiX RTN 950 or ready with the

    commissioning data scripts.l Aware of the radio link data plan for the site.l Equipped with a laptop on which the Web LCT is installed.l Equipped with a network cable when the Web LCT needs to be connected to the NE through

    the NMS port.l Equipment with a Mini USB cable when the Web LCT needs to be connected to the NE

    through the Mini USB port.Figure 4-1 shows the site commissioning flowchart.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 4 Commissioning Process

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    36

  • Figure 4-1 Commissioning flowchart

    Start

    Power on the equipment

    Connect the Web LCT to the IDU

    Run commissioning data scripts on the Web

    LCT

    Check alarms

    Test connectivity of cables

    Align antennas

    Query the status and receive power of a

    radio link

    Test connectivity of fibers

    Test connectivity of Ethernet cables

    Test connectivity of E1 cables

    Required (parent item)Required (subitem)End

    Align single-polarized antennas

    Align dual-polarized antennas

    Start

    Power on the equipment

    Connect the Web LCT to the IDU

    Manually configure commissioning data

    Check alarms

    Test connectivity of cables

    Align antennas

    Query the status and receive power of a radio

    link

    Test connectivity of fibers

    Test connectivity of Ethernet cables

    Test connectivity of E1 cables

    End

    Align single-polarized antennas

    Align dual-polarized antennas

    Manually configuring commissioning dataRunning commissioning data scripts on the Web LCT

    Through Mini USB Interface

    Through NMS Interface

    Through Mini USB Interface

    Through NMS Interface

    Table 4-1 Configuring site commissioning data by running commissioning data scripts on theWeb LCT

    Commissioning Item Remarks5.1 Powering On the Equipment Required5.3 Logging In to the Web LCT (Through NMS Interface) Required5.4 Downloading a Commissioning Data Script to an NEUsing the Web LCT

    Required

    5.6 Checking Alarms Required5.7 Testing Connectivity ofCables

    5.7.1 Testing Connectivityof E1 Cables

    Required when E1 cables areused on the site

    5.7.2 Testing Connectivityof Network Cables

    Required when Ethernetcables are used on the site

    5.7.3 Checking FiberJumper Connection

    Required when optical fibersare used on the site

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 4 Commissioning Process

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    37

  • Commissioning Item Remarks5.8 Aligning the Antennasa 5.8.2 Aligning Single-

    Polarized AntennasRequired when microwaveservices are transmitted bysingle-polarized antennas

    5.8.3 Aligning Dual-Polarized Antennas

    Required when microwaveservices are transmitted bydual-polarized antennas

    5.9 Checking the Radio Link Status and the ReceivePower

    Required

    Table 4-2 Manually configuring site commissioning data on the Web LCTCommissioning Item Remarks5.1 Powering On the Equipment Required5.3 Logging In to the Web LCT (Through NMS Interface) Required5.5 Configuring Site Commissioning Data by Using theWeb LCT

    Required

    5.6 Checking Alarms Required5.7 Testing Connectivity ofCables

    5.7.1 Testing Connectivityof E1 Cables

    Required when E1 cables areused on the site

    5.7.2 Testing Connectivityof Network Cables

    Required when Ethernetcables are used on the site

    5.7.3 Checking FiberJumper Connection

    Required when optical fibersare used on the site

    5.8 Aligning the Antennasa 5.8.2 Aligning Single-Polarized Antennas

    Required when microwaveservices are transmitted bysingle-polarized antennas

    5.8.3 Aligning Dual-Polarized Antennas

    Required when microwaveservices are transmitted bydual-polarized antennas

    5.9 Checking the Radio Link Status and the ReceivePower

    Required

    NOTE

    a: Before aligning antennas, power on the equipment and configure site commissioning data on both ends of theradio link.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 4 Commissioning Process

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    38

  • Site Commissioning Flowchart (Configuring Site Commissioning Data by Usinga USB Flash Drive)

    Commissioning engineers can configure site commissioning data by using a USB flash drive onsite when they are:l Familiar with the radio link data plan for the target sites.l Equipped with a USB flash drive that stores the NE commissioning data scripts.l Equipped with a laptop on which the Web LCT is installed.Figure 4-2 shows the site commissioning flowchart.

    Figure 4-2 Commissioning flowchart

    Start

    Powering on the equipment

    Loading commissioning data from a USB flash drive

    Completing subsequent commissioning items

    Required (parent item)End

    Required (subitem)

    Using the Web LCT to complete subsequent commissioning Items

    Table 4-3 Configuring site commissioning data by using a USB flash driveCommissioning Item Remarks5.1 Powering On the Equipment Required6.2 Loading Commissioning Data from a USB Flash Drive RequiredCompleting SubsequentCommissioning Items

    6.3 Using the Web LCT toComplete SubsequentCommissioning Items

    Required when subsequentactions need to be performedon the Web LCT

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 4 Commissioning Process

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    39

  • 4.2 System Commissioning ProcessSystem commissioning refers to commissioning for the entire microwave transmission network.System commissioning ensures that various services are transmitted properly and protectionfunctions are implemented over the microwave transmission network.

    Context

    Table 4-4 System commissioning processCommissioning Item Remarks7.1 Configuring Networkwide Service Data Required7.2 TestingConnectivity of E1Services

    7.2.1 Testing E1Services by Using aBER Tester

    Required when E1 service are available anda BER tester is available on site

    7.2.2 Testing E1Services UsingPRBS

    Required when E1 services are available andno BER tester is available on site

    7.3 TestingConnectivity ofEthernet Services

    7.3.1 TestingEthernet ServicesConfigured on aPer-NE Basis

    Required when Ethernet services areavailable

    7.3.2 TestingEthernet ServicesConfigured in anEnd-to-EndManner

    Required when Ethernet services areavailable

    7.4 Testing ATM Services Required when ATM services are available7.5 Testing AMShifts

    7.5.1 Testing AMShifts on IFU2/IFX2 Boards

    Required when the AM function is enabledand a BER tester is available on site

    7.5.2 Testing AMShifts on the ISU2/ISX2/ISV3

    Required when the AM function is enabledand no BER tester is available on site

    7.6 TestingProtectionSwitching

    7.6.1 Testing IF 1+1ProtectionSwitching

    Required when the radio links are configuredwith the 1+1 HSB/FD/SD

    7.6.2 Testing N+1ProtectionSwitching

    Required when the N+1 protection isconfigured

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 4 Commissioning Process

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    40

  • Commissioning Item Remarks7.6.3 Testing SNCPSwitching

    Required when the SNCP is configured

    7.6.4 Testing ERPSSwitching

    Required when ERPS is configured

    7.6.5 Testing MPLSAPS ProtectionSwitching

    Required when MPLS APS protection isconfigured

    7.6.6 Testing LinearMSP Switching

    Required when 1+1/1:N linear MSP isconfigured

    7.7 Checking the Clock Status Required7.8 Testing the FM over a Radio Link Optional7.9 Testing E1 Service Performance Required when E1 services are available7.10 TestingEthernet ServicePerformance

    7.10.1 TestingLatency,Throughput, andPacket Loss Ratio

    Required when Ethernet services areavailable

    7.10.2 Testing theLong-term PacketLoss Ratio

    Required when Ethernet services areavailable

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 4 Commissioning Process

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    41

  • 5 Site Commissioning (Using the Web LCT)About This Chapter

    In most cases, site commissioning are performed using the Web LCT.

    5.1 Powering On the EquipmentBy checking the power-on process of equipment, you can verify whether the hardware systemof the equipment and the power system are functioning properly.5.2 Logging In to the Web LCT (Through a Mini USB Interface)When the Mini USB interface is used, users do not need to set the IP address of the computeron which the Web LCT is installed, which facilitates site commissioning.5.3 Logging In to the Web LCT (Through NMS Interface)When the NMS interface is used, users need to set the IP address of a computer on which theWeb LCT is installed and the IP address of an NE to be in one network segment.5.4 Downloading a Commissioning Data Script to an NE Using the Web LCTThis section describes how to download a commissioning data script to an NE using the WebLCT. The function applies to the scenario in which a site commissioning data script has beenprepared. With this function available, on-site configuration is not required.5.5 Configuring Site Commissioning Data by Using the Web LCTThis section describes how to configure site commissioning data when using the Web LCT toperform site commissioning.5.7 Testing Connectivity of CablesDuring the installation of the OptiX RTN 950, the cables may be connected to service interfacesincorrectly, or the hardware may malfunction. To ensure that the services run properly, testconnectivity of the cables.5.8 Aligning the AntennasAligning the antennas is the most important activity in HOP commissioning. The alignment hasa direct effect on the performance of the radio links.5.9 Checking the Radio Link Status and the Receive PowerAfter antenna alignment, check whether the status of a radio link is normal and the receive powermeets requirements.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 5 Site Commissioning (Using the Web LCT)

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    42

  • 5.1 Powering On the EquipmentBy checking the power-on process of equipment, you can verify whether the hardware systemof the equipment and the power system are functioning properly.

    Prerequisitesl Hardware installation has been completed and has passed the installation check.l The power system is available. The voltage, pole connection, and fuse current of the power

    system have been checked in the process of connecting power cables.l The power supply (for example, the power distribution box of the cabinet) has been turned

    off.

    Tools, Equipment, and MaterialsNone.

    Contextl For the OptiX RTN 950, the recommended fuse currents are listed in Table 5-1.

    Table 5-1 Fuse currentsChassis Recommended Fuse CapacityOptiX RTN 950 20 A

    NOTEThe recommended fuse capacity of 20 A can meet requirements under the maximum powerconsumption. Customers can compute the fuse capacity according to the actual power consumption.The fuse capacity should be larger than or equal to (total power consumption x 1.5)/(rated voltage x87.5%). For example, when the rated power supply is -48 V and the total power consumption of theIDU is less than or equal to 420 W, the fuse capacity can be set to 15 A (= [420 x 1.5]/[48 x 87.5%]).

    l The OptiX RTN 950 supports the following system control, switching, and timing board:Chassis Board TypeOptiX RTN 950 CSH/CST

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 5 Site Commissioning (Using the Web LCT)

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    43

  • Precautions

    NOTICEl If the equipment is configured with two PIU boards, the nominal voltage for the input power

    of each PIU board must be the same.l The ODU-PWR switch on the front panel of the IF board is designed with a locking device.

    Hence, you must pull out the switches lightly before you turn it. If the switch points to "O",the switch is turned off. If the switch points to "I", the switch is turned on.

    l If the output voltage of the power supply does not meet test requirements, do not power onthe cabinet. First, reconstruct the power supply and then test the output voltage again.

    ProcedureStep 1 Verify that the power cables of the chassis are correctly connected. Then, power on the equipment

    and check the status of the indicators. In normal conditions, the PIU/FAN indicators are steadygreen, as shown in Figure 5-1. Table 5-2 provides the descriptions for the different states of theindicators.

    Table 5-2 Status of indicatorsIndicator State DescriptionPWR Steady green Indicates that the power supply is in

    the normal state.Off Indicates a power failure.

    FAN Steady green Indicates that the fan is runningproperly.

    Steady red Indicates that the fan is faulty.Off Indicates that the fan is powered off.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 5 Site Commissioning (Using the Web LCT)

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    44

  • Figure 5-1 Normal statePIU indicator FAN indicator

    Step 2 Check the status of the indicators on the system control, switching, and timing board and ensure

    that the equipment is powered on. The board indicators should conform to the following statesand sequences.1. The PROG indicator should blink green, turn off, and then become steady green.2. The STAT indicators should be green.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 5 Site Commissioning (Using the Web LCT)

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    45

  • Figure 5-2 Normal state

    STAT PROG SYNC ACTX ACTC

    NOTE

    l For detailed meanings of the indicators, see the IDU hardware description.l For a board other than the system control, switching, and timing board on the IDU, the STAT indicator is

    on only after the corresponding logical board is added.

    Step 3 Turn the ODU-PWR switch on an IF board to the "I" position.NOTE

    l The ODU indicator on an IF board is green only after the logical board of the IF board connected tothe ODU and the logical board of the ODU are created.

    l In the event of indicator abnormalities, contact Huawei technical support.

    ----End

    5.2 Logging In to the Web LCT (Through a Mini USBInterface)

    When the Mini USB interface is used, users do not need to set the IP address of the computeron which the Web LCT is installed, which facilitates site commissioning.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 5 Site Commissioning (Using the Web LCT)

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    46

  • PrerequisitesThe NE has been powered on.

    Tools, Equipment, and MaterialsWeb LCT

    NOTE

    The U2000 does not support this operation.

    ProcedureStep 1 Start a laptop and log in to the operating system.Step 2 Use a Mini USB cable to connect a USB interface of the laptop and the OAM interface of CSHU/

    CSHUA board.

    NOTEIf the NE is configured with the active and standby CSHU/CSHUA boards, connect a USB interface of the laptopand the OAM interface of the active CSHU/CSHUA board.

    Step 3 On the desktop, double-click the Start Web LCT icon.The system displays the USER LOGIN window of the Web LCT.

    OptiX RTN 950 Radio Transmission SystemCommissioning Guide 5 Site Commissioning (Using the Web LCT)

    Issue 02 (2014-09-15) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    47

  • NOTEIf the USER LOGIN window is not d


Recommended