Date post: | 22-Mar-2017 |
Category: |
Education |
Upload: | denish-makvana |
View: | 81 times |
Download: | 2 times |
A Detail Project Report Of
Rural Infrastructure Development Projects Under MGNREGA,
Clean Village : A Step Towards Clean India Campaign ,
Concept Sustainable Planning Of feasible Infrastructure Facilities And Tourism Site
Development.for
Bhagal Village, Valsad Institute: G.E.C. Valsad
Gujarat Technological University
Ahmedabad, Gujarat
A Detail Project Report Of
Rural Infrastructure Development Projects Under MGNREGA,
Clean Village : A Step Towards Clean India Campaign ,
Concept Sustainable Planning Of feasible Infrastructure Facilities And Tourism Site
Development.for
Bhagal Village, Valsad Institute: G.E.C. Valsad
Guided By (Nodal Officer) : Prof. D. J. Patel
Submitted By: Enrolment Nos.:
1. Harsh H. Mehta 110190106001
2. Harshiv U. Pandya 110190106015
3. Denish R. Makvana 110190106019
Content● Objective of project● Introduction about RIDP ● Methodology● Infrastructure projects under MGNREGA● Study area profile● Data collection & analysis● SWOT analysis● Design proposal for road & canal● Introduction about clean india campaign● Needs of study● Methodology● Waste types generated● Existing Condition ● Design proposal for waste management site● Introduction about planning of infrastructure facilities and tourism site
development● Layout and Zoning of Facilities for Bhagal● Conclusion
Existence of Work Investigation of executed work as per preplanning
To investigate about discrepancies
● To know if the works taken up under the MGNREGA physically exist.
● To ascertain if the works have been executed as per the approved plan and estimate.
● To find out the discrepancies if any between the measurements as per Measurement Book and physical verification of the completed works.
Objective of Project
Ensure execution as per guidelines
Objective of Project
Feedback of the people about the projectSurvey for maintenance
● To assess whether the execution of works have been carried out as per guidelines.
● To elicit public opinion on utility and durability of assets and the type and extent of benefits flow to the community from the assets created.
● To explore the arrangement for maintenance of assets created.
Remedial measures
Objective of Project
Provide technical guidelines Tourism development
● To recommend remedial measures for improved performance of the program
● To provide technical guidance for the works under MGNREGA.
● To develop appropriate site at the sea coast for tourism
Design proposal
Objective of Project
create awareness Clean environment
● To propose a design for bitumen road, canals, and waste management site so as to recycle/reuse the waste.
● To create awareness among the rural people to recycle/reuse the waste products.
● To provide a cleaner and healthier surroundings to the rural people.
● What is MGNREGA…?
Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) implemented by the Ministry of Rural Development (MoRD), is the flagship programme of the Government that directly touches lives of the poor and promotes inclusive growth.
Wage transaction through
banks/post offices
MOU with the postal dept.
Name changed to MGNREGA
Came into force in 200 districts
130 more districts included
Universalization Of the scheme NREGA legalized
Time line of MGNREGA……
August 2005
Introduction
Methodology
Site Visit
Problem Identification
Preliminary Survey
Data collection
On going/Completed Works
Upcoming Works
Methodology
Quality Audit
Technical Analysis of designs
Alternate Design Proposals
Design Suggestions
Conclusion
Infrastructure Projects Under MGNREGA
Rural connectivity
Irrigation Channel
Agriculture related works
Drought Proofing
Flood Control and Protection Works
Land Development
Works in coastal areas
Water Conservation and Water Harvesting
Rural Sanitation related works
Study area profile
District : ValsadBlock : ValsadVillages : Bhagal, Chharvada, Dandi, Dharasana, Kakwadi Danti, Malvan, VasanArea : Coastal Highway Vasan
Malvan
Dandi
Kakwadi DantiDharasana
BhagalChharavada
Study area profile
● Village location on the map
• Vasan
• Total Nos. of Work : 5• Type of Work : WBM• Work Status : Completed• Year : 2011-14• Total expenditure on work
Estimated : Rs. 2219412/-Actual : Rs. 1533234/-
• Malvan
• Total Nos. of Work : 2• Type of Work : WBM• Work Status : Completed• Year : 2012-14• Total expenditure on work
Estimated : Rs. 1000000/-Actual : Rs. 931749/-
• Kakwadi Danti
• Total Nos. of Work : 2• Type of Work : WBM• Work Status : Completed• Year : 2013-14• Total expenditure on work
Estimated : Rs. 1000000/-Actual : Rs. 769502/-
Data collection & analysis
• Dharasana
• Total Nos. of Work : 2• Type of Work : WBM• Work Status : Completed• Year : 2011-14• Total expenditure on work
Estimated : Rs. 749267/-Actual : Rs. 584115/-
• Dandi
• Total Nos. of Work : 4• Type of Work : WBM• Work Status : Completed• Year : 2011-14• Total expenditure on work
Estimated : Rs. 2000000/-Actual : Rs. 1596588/-
• Chharawada
• Total Nos. of Work : 4• Type of Work : WBM• Work Status : Completed• Year : 2011-14• Total expenditure on work
Estimated : Rs. 1907012/-Actual : Rs. 1187042/-
• Bhagal
• Total Nos. of Work : 2• Type of Work : WBM• Work Status : Completed• Year : 2011-14• Total expenditure on work
Estimated : Rs. 985384/-Actual : Rs. 853043/-
S WO T
SWOT Analysis
ThreatCorruption
Entry of big firms or MNC’sMaking of unrealistic NTB’s by foreign
country
OpportunityCreate export oriented units more
Adaptation of effective marketing strategies from relating MNC’s
WeaknessUnskilled labour
Lack of good infrastructureLack of new technology
StrengthGovernment SupportLow cost production
High employment rate
SWOT
Road section design
2 cm
Base course
Sub base
Road way
4.8 m
ShoulderShoulder
0.6 m0.6 m
Right of way
8 m
22.5 cm
43.5 cm
Road section estimate
Item No.
Particulars of items of work Quantity Unit Rate Rs Per Amount Rs
Cost of materials
1. Black Trap Metal 288 Cu.m. 850/- Cu.m. 2,44,800/-
2. 40 mm gauge Stone Ballast
1350 Cu.m. 1800/- Cu.m. 24,30,000/-
Total 26,74,800/-
Cost of labour & machines
1. Balder for cleaning road, heating and spraying
asphalt, rolling
30 Nos. 200/- Nos. 6,000/-
2. Hire of Tar Boiler 1/6 day 600/- hr. 2,400/-
3. Roller(including driver and cleaner)
1/6 day 400/- hr. 1,600/-
4. Fuel for heating Asphalt 0.88 quintal 150/- quintal 132/-
5. Sundries, T&P, Brushers, etc.
Lump sum - 100/- - 100/-
Total 10,232/-
Canal section design
1
0.58
2.4m
2.85m2.086m
0.764m
5.7m
Introduction
Clean India Mission is a national campaign by the Government of India, covering 4041 statutory towns, to clean the streets, roads and infrastructure of the country.
The mission was started by Prime Minister Modi, who nominated nine famous personalities for the campaign, and they took up the challenge and nominated nine more people and so on.
The components of the programme are: • Construction of individual sanitary latrines Conversion of dry latrines into
low-cost sanitary latrines. • Construction of exclusive village sanitary complexes for women
providing facilities for hand pumping, bathing, sanitation and washing on a selective basis.
• Setting up of sanitary marts. • Total sanitation of villages through the construction of drains, soakage
pits, solid and liquid waste disposal. • Intensive campaign for awareness generation and health education.
Needs of study
• Absence of proper disposal of solid and liquid waste• In rural area waste is a severe threat to the public health concern
and cleanliness • 1.8 million people die every year from diarrhoeal diseases, 90% of
them are children under 5, mostly in developing countries. 1.3 million people die of malaria each year, 90% of them are children under 5.
Methodology
Site Visit
Data Collection
Design suggestions
Solid Waste Liquid waste
Existing Condition
Preliminary Survey
Conclusion
Waste types generated
Types of Waste
Solid waste Liquid Waste
Biodegradable Non-biodegradable
Recyclable Non-recyclable
Existing Condition
Solid Waste:
• In Bhagal village, solid waste management is a very serious issue.• The existing solid waste management is carried out at household
level. The waste generated from the houses is collected individually by householders themselves and then after some time period they burn it near their houses.
• Thus, we can conclude that there is no solid waste management planning in the study location, leading to a non-hygienic environment and thus sustainable solid waste planning becomes inevitable
Liquid Waste:
• In Bhagal, liquid waste generated at present is mostly at domestic level.
• Every individual house has been facilitated with soak pits which are proving to be efficient enough for controlling liquid waste.
• So for liquid waste management, further drainage facilitation would prove unnecessary and uneconomical.
Design proposal
• The values of the factors considered in the design of such a site are as follows:i. Population – 2500 (round off value)ii. Illiteracy – 21.5%iii. GDP – 6%iv. Population growth rate of Valsad district – 21%v. Total biodegradable waste generated – 70% of total waste generated
(assumed value)
For,population = 2500 , GDP per capita = 6.00% Illiteracy rate = 21.5%
Total waste generated by one person is 1.2576 kg/capita/day So, for bhagal village total waste is 441.8106 tonnes
Introduction
Bhagal is a village panchayat located in the Valsad district of Gujarat state,India. The latitude 20.6842015 and longitude 72.8766554 are the geocoordinate of the Bhagal. It is at a distance of 8 km from Valsad city. The surrounding nearby villages and its distance from Bhagal are Dandi 1.9 KM, Kakwadi 3.5 KM, Danti 4.7 KM, Chharvada 4.7 KM, Dharasna 5.7 KM, Malvan 7.5 KM, Kundi10.4 KM Tithal 11.1 KM Vasan 11.9 KM
Layout and Zoning of Facilities for Bhagal
Waste disposal site• Size : 50m x 50m
Commercial zone• Total area covered by this
zone is about 5185 sq.m.• Facility under this zone :
i. Panchayat buildingii. Police Chowkiiii. Bank & ATMiv. Health centrev. STD Booth
Shopping center• Numbers of shops : 10• Size of shop : 10ft. X 12ft.• Facility under this zone :
i. Marketii. Milk shopiii. General store
Educational zone• Total area covered by this
zone is about 18000 sq.m.• Facility under this zone :
i. Secondary & Higher Secondary school
ii. Training centreiii. Stationary store
Recreational zone• Total area covered by this
zone is about 7000 sq.m.• Facility under this zone :
i. Community hallii. Open play groundiii. Garden
Conclusion
● The alternate design proposal for road and canal mentioned here would prove to be more sustainable and cost effective for the government. This design would definitely improve the efficiency of rural transport system and water conveyance efficiency.
● If the proposed design for solid and liquid waste management should be implemented, so that cleanliness would be maintained in the village
● We can conclude that if the village is developed and planned as per the sustainable planning provided here, and if the coast line is developed as a tourist spot, the standard of the villagers could be increased and the village could reach newer heights of development.
THANK YOU…