1
The Republic of Rwanda (hereinafter
“Rwanda”) established a long-term development
plan called “VISION 2020” in 2000 to announce
its aim to develop the country to a middle-income
country by 2020. Regarding the water resource
development and water supply, the plan is aimed at
improving the water supply coverage of 52% as of
2000 (according to the definition provided by the
Rwanda Ministry of Infrastructure (hereinafter
“MININFRA”)) to 100% by 2020. The Economic
Development and Poverty Reduction Strategy 2
(EDPRS II) brought forward the goal to attain the
water supply coverage of 100% by 2018. The ratio
of people who use water resources that have been
treated for water supply is 87% in the urban area
and 72% in the rural area (WHO/UNICEF Joint
Monitoring Programme, hereinafter, “JMP,” 2015),
relatively higher in the former than in the latter. On
the other hand, advancing urbanization has resulted
in a rapid increase in the urbanization rate from
19.3% to 28.8% in the last ten years (JMP, 2015).
In Kigali City which is the capital city of Rwanda,
in particular, the urban population growth rate is
expected to reach 4.1% to 5.8% by 2025. The
water service has not caught up with this rapid
population growth. Furthermore, shortage of
amount of water resources and a great deal of
water leakage are causing water to be supplied
only for a short time, eight hours on the average,
and making constant restriction or stop of water
supply unavoidable. Therefore, the Water and
Sanitation Corporation (hereinafter “WASAC1”) in
1WASAC is an organization formed in 2014 under the supervision
of MININFRA by creating an independent entity of the water
supply and sanitary departments of the Energy, Water and
Sanitation Authority, which was established in 2012 as the
organization for implementation, planning, and monitoringof
JICA Project Brief Note
Rwanda
Project for Strengthening Non-revenue Water Control in Kigali City
Water Network June 2017
1. Project Background and Problems
Republic of Rwanda Project Location Map
2
charge of water service under the supervision of
MININFRA is pursuing a target of ensuring the
water supply quantity of Kigali and promoting a
plan to double the water supply quantity in Kigali
as of 2015 by the end of 2017 by implementing
plans for constructing a new purification plant and
expanding an existing purification plant through
public-private partnerships(PPP).
However, Kigali, despite its limited amount of
water resources, had a high Non-Revenue Water
(NRW)(the portion of the treated water that has
been produced at the water treatment plants and is
leaked, stolen, not measured, etc. Before it reaches
the customer, which is revenue loss) rate of 25% to
38% in 2015 (result of JICA Detailed Planning
Survey in January 2016). Therefore, WASAC
urgently needs to undertake improvement in
quantity of water supplied, and improvement in the
financial performance of WASAC as a whole,
through measures for NRW reduction. Under these
circumstances, a request was made for this Project
in June 2015 with the aim of the enhancement of
technical capacity regarding NRW reduction
measures and the construction of sustainable
systems. In the project, since Kigali has about half
the piping length of the urban water supply
network in the entire country (2,400 km), use of
this Project in Kigali as a model for NRW
reduction of Rwanda will allow WASAC to spread
the effect to other cities. Implementation period of
the project is from July 2016 to June 2019, and the
following is an outline of its progress as of June
2017 (at the end of Phase 1).
policy regarding energy, water supply, and sanitation.
2.1 Project objective and outputs
The objective of this project is to strengthen the
capability of WASAC to carry out measures to
reduce non-revenue water in Kigali City in a
planned manner, and the above 4 outputs were
adopted as indices for the achievement of the
objective.
2.2 Project implementation system
The implementing agencies of this project are
Urban Water and Sanitation Services (UWSS) and
Commercial Services (CS) of WASAC, with
MININFRA as the supervising ministry. CS has
jurisdiction over 20 branches of WASAC
throughout the country, but the branches directly
2. Approach to Problem Solving
【Overall Goal】
WASAC conducts NRW reduction
measures as planned for Kigali city.
【Project Purpose】
WASAC's capacity is enhanced to
conduct NRW reduction measures as
planned for Kigali city.
【Output 1】
Planning capacity of NRW reduction of
WASAC is enhanced.
【Output 2】
Basic knowledge, skills and technique on
NRW control are acquired by WASAC.
【Output 3】
WASAC learned how to conduct NRW
reduction measures through the
implementation of the Pilot Project.
【Output 4】
4 branches in Kigali establish the system to
measure NRW rates accurately.
3
involved in this project are 4 branches in Kigali
city: Kacyiru, Gikondo, New Nyarugenge, and
Nyamirambo. The Counterparts (hereafter, “C/P”)
that are the implementing organizations of
WASAC that are the subject of the technology
transfer in this project are the staff of UWSS and
CS. The head of UWSS was appointed as the
Project Director, the Section Head of the
Non-revenue Water Section of UWSS was
appointed as Manager.
Fig. 1: WASAC organization chart
In addition, immediately after commencement of
the project, the Management Team was organized
to produce the 5-year Strategic Action Plan for
Non-revenue Water Reduction, with the head of
the Urban Water and Sanitation Services as the
leader. Furthermore, an Action Team was
organized including mainly technical staff
members that will carry out the actual non-revenue
water reduction measures in pilot project.
Fig. 2: Project implementation system
2.3 Project outputs and approaches
(1) Activities regarding Output 1
Despite the fact that non-revenue water is the
major issue in WASAC, WASAC does not have a
specific strategy to deal with non-revenue water.
Therefore, by formulating the 5-year Strategic
Action Plan for Non-revenue Water Reduction in
this project, the activities will become specific, and
it will be required that the WASAC plan
formulation capabilities be improved in the process
of formulating this plan. The following work will
be carried out jointly by the JICA Experts and the
Counterparts.
1) Evaluation of the details of the non-revenue
water reduction measures currently being
implemented by WASAC, and identification of
issues.
In order to determine the status of water supply
MININFRA
Rural Water Services(RWS)
Board of Directors
WASAC
Water and Sanitation
Development Services (WSDS)
Director Urban Water and
Sanitation Services(UWSS)Commercial Services(CS) Financial Sservices(CFO) Support Services(SS)
Water Operation
Services(WOS)
Sewerage Operation
Services(SOS)
Non-Revenue Water(NRW)
Quality Assurance Services
Utility Planning Services
Revenue Management
Services
Customer Services
Management
Branch Management
Services
Nationwide branch offices
(20 branchs)
Corporation Secretary
Executive Assistant
Internal Audit Officers
Legal Advisory Services
Head Public Relations
Steering Committee (SC)Chairman: WASAC-CEO
[Rwandan Side] [Japanese Side]Project Board JICA Experts
Project Director JICA Rwanda Office
Project Manager Embassy of Japan (Observer)
NRW Management Team MembersOfficials from MININFRA
JICA Experts Team
Project Director (PD) : Director of UWSS
Project Manager (PM): Manager of NRW, UWSS
NRW Management TeamLeader: Director of UWSSCo-leader: Director of CS
Director of CFOMember: Manager of NRW, UWSS
Manager of Water Operation Services(WOS), UWSSManager of Utility Planning Services, UWSSManager of Revenue Management Services (RMS), CSManager of Customer Service Management (CSM), CS
NRW Action TeamLeader: Head of leak detection and pressure management,
NRW, UWSSCo-leader: Kachiru Branch Manager (CS)
Gikondo Branch Manager (CS)Nyarugenge Branch Manager (CS)Nyamirambo Branch Manager (CS)Kanonbe Branch Manager (CS)
Remera Branch Manager (CS)Member: Head of zoning and mapping services, NRW, UWSS
Head of water distribution services, WOS, UMSS
Head of Leak Detection and Pressure Management (NRW,UWSS)
Inspection and Enforcement Officer (NRW,UWSS)
Mapping Officer (NRW,UWSS)
Head of Meter Management Services (CSM,CS)
Water Distribution Officer of each Branch
Customer Service Officer of each BranchBilling Officer of each Branch
4
and the status of implementation of non-revenue
water countermeasures in each branch, information
was obtained through a questionnaire survey for
the Non-revenue Water Section of UWSS of
WASAC and the 20 branches, site visits to each of
the branches, and from the Geographical
Information System (GIS) and customer database.
The information was shared at the meetings and
workshops held afterwards and issues of
non-revenue water countermeasures were
identified.
From the WASAC side, many issues were
identified, such as (1) Organization (low priority
for NRW reduction within WASAC, insufficient
personnel and budget, insufficient coordination
between departments), (2) Systems (NRW
reduction procedures, regulations for new water
supply connections (existing pipe connections,
material selection), insufficient sharing of
information between branches), (3) Equipment
(insufficient pipe materials, heavy machinery,
vehicles, tools, etc.), (4) Knowledge/awareness of
the personnel (insufficient expertise, insufficient
ownership), (5) Asset management (maintenance,
renewal of pipelines and valves). From the JICA
Experts side the issues were, a: Design/ standards/
records (long-term renewal plans, various types of
design, material standards, criteria for new
connections, drawings, insufficient control
documents), b: Management of outsourced
construction (insufficient inspection after
appointment of contractor), c: Accuracy of basic
data (GIS, customer data, details of various types
of facility, drawings). Also, issues regarding
facilities that were recognized in common included
lack of a system for measurement of non-revenue
water percentage,high water distribution pressures,
water leakage surveys, repair of distribution pipe,
management of water meters, management of
public water hydrants, management of water theft,
etc.
2) Based on the issues identified, the policies and
procedures to be implemented by WASAC in the
future as non-revenue water reduction measures
were proposed.
After identification of the issues, workshops were
held continuously, to determine the status of the
activities being implemented by WASAC, and
summary of the policies for non-revenue water
reduction measures being implemented with
respect to these issues is being carried out.
Regarding these issues, 105 items have been
proposed as methods to deal with them. These
were broadly classified into the basic
countermeasure items: water supply system input
metering accuracy, apparent losses (commercial
losses), actual losses (water leakage), unbilled
authorized water (water that is not billed such as
water for facility management, firefighting, etc.),
based on the water balance table of the
International Water Association (IWA). By further
classifying them into 18 main component items of
the 5-year Strategic Action Plan for Non-revenue
Water Reduction, the countermeasure actions were
clarified. Also, the order of priority, the schedule
for year of implementation, and the department
within WASAC responsible for implementation
were clarified for these 105 countermeasure items.
Table 1 shows an overview (framework) of some
of the Action Plan.
Table 1: Overview of Part of the Action Plan
5
From this table it can be seen that there are many
departments in WASAC involved in the
non-revenue water countermeasure activities, such
as formulation of the plan at Headquarters, 11
sections (Non-revenue Water Section, Facility
Maintenance Section, Quality Control Section,
Planning Section, Revenue Management,
Customer Services, Branches, Financial Services,
Personnel Services, Information Technology,
Procurement Services) of 4 departments carrying
out executive management (Urban Water and
Sanitation Services, Commercial Services,
Financial Services, Support Services), and the 20
branches carrying out activities on site, etc. The
non-revenue reduction countermeasure activities
must be implemented as a unit through cooperation
between these multiple departments. Therefore, in
order to create a consensus among these relevant
departments regarding the 5-year Strategic Action
Plan for Non-revenue Water Reduction, a joint
workshop with the Management Team and the
Action Team was held on the May 29, 2017 at
which the framework was confirmed.
It is necessary in the future to formulate each of
these countermeasure items as more detailed and
specific actual work, clarify the quantities of work,
set schedules, and carry out budget preparation
measures for these activities.
(2) Activities regarding Output 2
Basic knowledge, technologies, and skills
regarding non-revenue water management were
acquired by the WASAC Counterparts through
indoor training and OJT.
i) Management of non-revenue water
A “Non-revenue Water Reduction Measures
Overview Manual (Draft)” was prepared, and
distributed to the Management Team. Also,
training was carried out based on seminars to
identify the problems in terms of formulating basic
countermeasures in non-revenue water
management, so that knowledge was acquired
relating to non-revenue water management.
ii) GIS
OJT was carried out on updating GIS data, using
the GIS database owned by WASAC. Specifically,
pipeline network and customer data that is being
prepared by ESRI (a company commissioned by
WASAC to prepare GIS applications) was
used,and training was carried out in the techniques
necessary for organized and efficient flow of
updating.In addition, specifically trainings were
carried out to promote the sharing and use of GIS
data, such as introduction of examples of
utilization of GIS in seminars, distribution of GIS
data using free software such as QGIS, etc.,
introduction of applied layout techniques using
GIS, and data analysis techniques, etc.
iii) Hydraulic Analysis
To date there are few personnel and departments
within WASAC with experience of hydraulic
analysis of water pipe distribution networks, and
there has been absolutely no hydraulic analysis
carried out to determine the properties of the water
distribution pipe networks of WASAC by hydraulic
calculation. The introduction of hydraulic analysis
systems has been delayed, associated with the
delay in development of the GIS data. However
first it was necessary to start with understanding
hydraulic calculation, so training was provided in
hydraulic calculation using the general purpose
software EPANET and Excel.
iv) Water leak detection
Instruction on water leak detection was carried
out by indoor training and OJT with the following
components as the framework, taking into
consideration that control of the flow rate is the
basis for achieving an effect.
6
1 Measurement of flow rates in the WASAC
network
2 Water leak detection techniques
3 Data monitoring and data analysis
4 Method of analysis of NRW composition
5 Flow rate measurement by WASAC and repair
of instruments for water leak detection
v) Pipe Repair
As a result of a survey of the status of water pipe
repair in WASAC, issues were identified and a
training plan was formulated, based on discussions
with the C/P. The items for training were not
simply confined to the work of pipe repair on site,
but also included items on countermeasures against
water leakage and maintenance management
systems, that are necessary for continuous
improvement in the future. There were a total of 5
items: safety management, earthworks construction,
technical specifications and records, repair of pipe
connections, and inspection of structures and
materials. Those receiving the training included
pipeline engineers from the 6 branches in Kigali
City, and those responsible for construction on site.
(3) Activities regarding Output 3
1) Pilot area project overview
Two locations were selected as pilot areas from
among 11 candidate locations within the city based
on the conditions shown below, and preparation
work was carried out in Phase 1 for the
implementation of non-revenue water reduction
measures.
- It had to be possible to hydraulically isolate the
area. As a result of isolation, there must be no
reduction in water pressure or water quality.
- There shall be about 1,000 water supply
hydrants.
- There is 24 hour 7day continuous water
supply.
- There must be drawings of the pipe network.
- Meters must be installed at all households.
- The pipes must be old, and the pressure high.
- It must be an environment in which water leak
detection can be carried out.
Table 2: The 2 selected pilot areas
No. Area name Branch name
Area 1 Kadobogo Kacyiru
Area 2 Ruyanzi New Nyarugenge
2) Pilot area activities and plan
The non-revenue water reduction activities in
the pilot areas are broadly divided into preparation
work and non-revenue water reduction activities.
a) Installation of valves, flow rate meters, and
chambers for pilot DMA2 configuration
Pipes flow into the pilot areas at a total of 4
locations, namely, 3 locations in Kadobogo pilot
area and 1 location in Ruyenzi pilot area.
Fig. 3: Kadobogo pilot area (Area 1)
Fig. 4: Ruyenzi pilot area (Area 2)
2Abbreviation of District Meter Areas, areas partitioned for control
of water supply with water meters
7
Table 3: Main indices for the pilot areas
b)The baseline of non-revenue water percentage is
calculated based on the records of the installed
flow rate meters and the customer invoice data.
c) Implementation of the reduction measures
i) Survey of meter accuracy:
- The accuracy of all the household water meters is
carried out using a test meter, and meters with an
error of greater than ±5% over the range of flow
rates in use are replaced (preparation of test meter
survey report).
ii) Survey of water theft, and quantity of
acknowledged uninvoiced water:
- A water theft countermeasure team is organized,
which carried out a survey of households using
water even though a water meter is not installed,
and households where a water meter is installed
but the quantity of water used is extremely low
(preparation of a water theft report (including
reasons for the water theft)).
- If water theft is discovered, the illegal connection
pipe is immediately removed, and official
subscription is recommended. If they do not
respond, then a fine is applied, in addition to
removal of the illegal connection pipe.
- Publicity activities regarding subscription to the
water supply and prevention of water theft are
carried out using churches and schools.
iii) Water leakage survey:
- A survey of the minimum flow rate at night time
is carried out to determine the total quantity of
water leakage. In addition, flow rates are measured
in each small area to select areas with large water
leakage, then using the water leak detectors the
location of the water leaks are identified. After
identification of the water leak location, repairs are
carried out immediately. When carrying out the
repairs, the quantity of leakage is measured.
- Patrols are carried out twice per day to detect
water leaks above ground, and inspection for water
leakage from water storage tanks and overflows is
carried out once per week, and if a leak is detected
immediately repairs and countermeasures are
investigated. In this case the quantity of water
leakage is measured or estimated (preparation of
patrol records).
iv) Other surveys:
- In case of the causes of water leakage are likely
to be high water pressure, aged pipes, and pipe
materials, so investigation is carried out into
sustainable high water pressure measures.
- Regulations for subscribers are prepared so that
water meters can be installed in locations where
they are easy to read.
d) The non-revenue water percentage is calculated
after implementation of this work
- The non-revenue water percentage is calculated
based on the records of the installed flow rate
meters and the customer invoice data.
e) Preparation of non-revenue water analysis table
(water distribution rate analysis table)
After carrying out the above work, the results
are summarized on a table as an analysis of the
water distribution rate, the non-revenue water
reduction effect in the pilot areas is analyzed, and
the effectiveness of each action is reflected in the
5-year Strategic Action Plan.
f) Analysis of cost-effectiveness
Pilot AreaArea1
Kadobogo (Kiyovu)
Area 2
Ruyenzi (Runda)
Area 100.4ha 648.2ha
Population 15,329 32,467
Served Population (=Number of connections x 5) 4,940 5,925
Service Coverage Ratio (%) 32 18
Number of Connections 938 885
Domestic 906 854
Public taps 1 6
Collectivity 2 3
Commercial 27 18
Industry 0 0
Government 2 4
Monthly Water Consumption (m3/month) 13,157 12,259
Average Consumption per Capita (L/day) 86 67
Number of Illegal Connections 19 14
Number of Meter Problems 98 50
(including screen and index status problems)
Percentage of Illegal and Meter Problems 12% 7%
8
- The increase in revenue due to reduction of the
non-revenue water percentage and the cost of the
non-revenue water reduction countermeasures are
compared, to calculate the cost effectiveness
(benefits and costs B/C).
g) Formulation of future non-revenue water
reduction measures
・From analysis of the results of the work in a) to g),
non-revenue water reduction measure manuals will
be formulated.
The following shows the implementation
procedure flow within the pilot areas.
Fig. 5: Flow of procedures for implementation of
non-revenue water reduction measures
(4) Activities regarding Output 4
In order to calculate the non-revenue water
percentage, it was planned to hydraulically isolate
water pipe distribution networks of the 4 branches
in Kigali City by installing electromagneticflow
meters and construct the flow rate monitoring
system.The boundaries for hydraulic isolation of
water networks of the branches were determined
by coordination of opinions between the GIS team
and the branches and on-site observation, while
advice was provided by the JICA Experts.
Thereafter the positions for installation of the flow
rate meters for isolation of water networks of the
branches was investigated on GIS maps, and after
joint confirmation with the WASAC side, it was
decided to install chambers for flow rate
measurement at 23 locations. Detailed design of
each chamber main structure and their ancillary
equipment was carried out,contracts were placed
with local contractors, and chamber construction
was commenced.
At present construction of chambers has been
completed at 11 locations, and construction will be
continued in Phase 2. Also tender procedures for
the equipment such as electromagnetic flowmeters,
etc., were carried out in May 2017.
Fig. 6: Chamber construction location map (23
locations)
Fig. 7: Overview of the monitoring system
Calculation of non-revenue water percentage prior to non-revenue
water countermeasures
Non-revenue water countermeasures
(1) Meter accuracy
measures
(2) Measures against water theft,
and quantity of acknowledged
uninvoiced water
Calculation of non-revenue water percentage after
implementation of this work
(3) Leak detection and
repair measures
Analysis of cost-effectiveness
Formulation of future non-revenue water reduction measures
Hydraulic isolation of water networks of the pilot areas
Analysis of current situation
(4) Other surveys
Preparation of non-revenue water analysis
table
9
(1) Results for Output 1
An objective of the technical cooperation project
is to strengthen the capabilities of the Recipient
side, so it is essential that the cooperation is not
imposed by the Japanese side, and that the training
is conducted so as to nurture the self-help efforts
and independence of the Recipient side. The
WASAC side may have the wrong idea that a
technical cooperation project is work outsourced to
the JICA Experts, which continued in this project
from the start of the project. However, eventually
at the Management Meeting held in March 2017,
when the JICA Experts presented the summary of
the results of the analysis of the causes of
non-revenue water and the framework that is the
basis of the planned countermeasures, the
agreement of the Management Team was obtained.
In the meeting, it was decided that investigations
would be carried out through workshops by a
WASAC select team. In this way, WASAC itself
was enabled to carry out the work of formulating
the 5-year Strategic Plan, so the workshops were
held led by WASAC and preparation of the Action
Plan proceeded, with advice from the JICA
Experts.
Photo 1: Workshop led by WASAC
Photo 2: Grouping of countermeasures
(2) Results for Output 2
i) Management of non-revenue water
Training materials were prepared in order to
raise problems in terms of formulation of basic
measures for non-revenue water management.
Seminars were held in the regular weekly meetings.
This training document will be used as a basic
document for the studies for formulation of the
5-year plan for NRW Reduction. A questionnaire
survey was carried out to identify the priority items
of WASAC.
The items that were judged should be promptly
implemented were as follows.
1. Formulate a long-term basic concept for the
water supply system
2. Update the customer data and pipe maps
3. Replace defective customer meters
4. Continuously replace aged pipes based on
evaluation of the degree of aging of the pipes
5. Separate water supply pipes from water
delivery pipes
The other priority items were, 1. Considerations
for areas where water is not supplied, 2. Carry out
customer surveys and check the accuracy of water
meters on site, 3. Water distribution piping as-built
drawings, sketches of water supply pipes, etc., to
be added to GIS information, 4. Survey of the
status of operation of public water hydrants and
updating the positions of public water hydrants on
3. Practical Results of the Approach
10
GIS, 5. Survey of the status of use of water by
large-scale customers to determine the future
demand for water, 6. PVC pipe replacement as
pointed out by the FS report, 7. Proper design work
(in particular thrust blocks 3 , measures against
water hammer, elimination of large diameter hard
vinyl chloride PVC pipes, etc.), 8. Clarification of
the distinction between water delivery pipes and
water distribution pipes, and 9. Continuous surveys
for illegal connections.
ii) GIS
A seminar was held with the GIS team in
connection with updating, utilization, and sharing
of GIS data. At the seminar there were lively
discussions regarding the updating of GIS data and
other issues, and many of the participants
expressed the opinion that sharing and utilization
of GIS data was very interesting. As a result of
holding the seminar the overall understanding of
updating, sharing, and utilization of GIS data was
deepened. At the start of the project the team
members were unable to go around carrying out
the field reconnaissances carrying maps and
drawings, but when the instruction was completed
they are seen carrying out the field reconnaissances
with maps and drawings prepared by the members
of the GIS team.
Also, an environment that enables sharing of
GIS data among the 6 branches of WASAC in
Kigali City and that enables the GIS data
possessed by WASAC to be freely viewed was
constructed using QGIS.
3At pipe fittings with a deformed shape such as bends, etc., a
non-uniform force (force acting to the outside on the pipe bend:
thrust) due to the water pressure within the pipe acts so as to move
the pipe. A thrust block is a concrete block that prevents movement
of the pipe due to this non-uniform force, which would otherwise
push the pipe bend to the outside, possibly causing it to separate
from the pipe joint.
Photo 3: (Left) Commencement of field
reconnaissance (Right) Field reconnaissance
several months later
Fig. 8: Kigali City pipeline network map viewed
with QGIS, developed so that it can be viewed in
the 6 branches in Kigali City
iii) Hydraulic Analysis
As a result of separate concentrated instruction,
the basic theory of hydraulic analysis was
understood, and, the importance of hydraulic data
quality was understood by the GIS team.
The C/P were members of the GIS team, and so
were proficient in the use of PCs, so they quickly
understood the hydraulic analysis application
(EPANET), and became proficient in the basics of
hydraulic analysis. A manual for use was provided,
so the members were instructed on how to proceed
while checking by themselves, in future examples
of application.
Trial hydraulic analysis was carried out using
the pilot area as a model. It was possible to
understand general tendencies that were commonly
known, such as in areas where there is a large
difference in level the pressures are extremely high
in some parts, and WASAC uses pipes that are on
the large side, so the reduction in quantity of water
is small.
11
Fig. 9: Results of trial analysis of Ruyenzi area
iv) Water leak detection
Instruction was repeatedly given on the method
of use of ultrasonic flow rate meters on the four
existing main water delivery pipes and water
distribution pipes. As a result the trainees could
experience that it is possible to measure the
quantity of water leakage from the flow rate
measurements. Also, the trainees gradually
understood the necessity of paying attention to
differences in accuracy of the measured values that
can occur due to the conditions.
Instruction was given on the methods and
principles of water leak detection within the pilot
areas. The sound of water leaking and its
transmission was explained, and there are
differences in the water leakage sound and
transmission between water supply pipes, water
distribution pipes, metal pipes, and nonmetal pipes,
so the trainees understood the necessity for a
certain amount of skill and experience.
Photo 4: Carrying out water leak detection
In addition, a seminar on water leak detection
was held, and instruction was given to many
people in how to use leak detection equipment, etc.,
thereby disseminating the understanding of the
importance of water leak detection.
Photo 5: Water leak detection training
In addition testing was carried out on the
functional state of water leak detection equipment
possessed by WASAC but that is not used, with a
view to restoring their function. By checking
whether it can be used by expert, and what part
must be repaired so that it can be used, the
equipment was restored to a usable state.
12
Fig. 10: List of equipment on which repairs and
checks were carried out
v) Pipe Repair
Training materials (safety management,
earthworks, technical specifications and records,
repair of pipe joints, inspection of structures and
materials) were prepared with reference to
Rwandan technical standards and specifications,
manufacturers’ procedures, technical specifications
of Japanese water supply organizations, and the
specifications of international organizations.
During the training there was lively exchange of
opinions regarding document control and
earthwork methods, so it is clear that these were
weak points in the day-to-day work of the trainees.
Photo 6: Explanation of how to use machinery by
the trainees
Also instruction was given on how to
appropriately repair pipes using the equipment
provided. In this way the awareness and
knowledge regarding pipe repair in WASAC was
strengthened, and this will be useful in future pipe
repairs.
Photo 7: Training in pipe repair
(3) Results for Output 3
Construction of the chambers (for installation of
the flow rate meters, pressure gauges, valves) for
measurement of the non-revenue water percentage
that will be the baseline in the pilot areas has been
completed. With these chambers it is possible to
hydraulically isolate the pilot area DMA, so a
system has been prepared that enables the quantity
of water distributed to the DMA to be measured.
Equipment
nameUse Photo
Details of
repair/check
Seba KMT
Hydrolux
Leak
Locator
HLE 5000
(Water leak
detector)
Detector that
identifies water leak
locations by
detecting the
location of the
sound of water
leaking
Battery holder
and battery snap
were replaced.
Seba KMT
Digital
Correlator :
Correlux P1
(Leak
sound
correlator)
Water leak detector
in which 2 sensors
are installed on a
wastewater pipe, to
detect the location
of a water leak
between the
sensors
After initializing
everything and
recharging the
battery, it could
be used.
COSMOS
DATA
LOGGER
(CDL-2U )
SENSUS
(Data
logger)
Device that stores
various types of
data measured and
collected by flow
rate meters and
pressure gauges
It was found that
it could be used
after re-
assembling the
sensors.
Ultrasonic
Flow Meter
( FLUXUS
F601 )
FLEXIM
(Ultrasonic
flow rate
meter)
Flow rate meter that
measures the flow
rate of a liquid
flowing within a
pipe using
ultrasonic waves
It was found that
it could be used
after the battery
was charged.
13
Photo 8: Flow rate meter and valve installed
within constructed chamber
In Area 1, water leak detection expert and the
NRW team conducted sonic testing at each house.
Meter data at 36 locations was identified within
Pilot Area 1 from the customer data, each house
was visited, and testing was carried out to
determine whether or not there was the sound of
leaking water, the status of operation of the meters
was checked, etc. There were many meters that
were not on the GIS data, so the importance of
improving the accuracy of the GIS data was again
recognized.
Photo 9: Sonic testing at houses
In Pilot Area 2, 14 locations having different
elevations within the same water distribution
system were selected, and a water pressure survey
was carried out by the pipe fitters of New
Nyarugenge. From the survey results it was found
that the high-pressure area is at an elevation of
close to 1,400 m. From this training the trainees
understood that by preparing pipe drawings
showing contours, it is possible to identify the high
water pressure areas, and judge the locations with
high water pressure.
Fig. 11: Map of Ruyenzi high water pressure area
Photo 10: Measurement of water pressure
14
(4) Results for Output 4
The locations of installation of the flow rate
meters to be used for calculating non-revenue
water percentage of the 4 branches in Kigali City
have been decided, and construction of the
chambers for installation of the flow rate meters is
in progress.
(1) Initiatives adopted for project
implementation
The C/P WASAC is participating in this project
while also carrying out their normal work, so the
work of this project is also a part of their normal
work. The objective of this project is to make the
non-revenue water reduction activities of WASAC
more clear, efficient, and sustainable, and it is an
extension of their normal activities.
The C/P tends to want rapid results (outputs)
from the JICA Experts (for example: detection of
water leaks, preparation of plans). However, the
objective of this project is not directly to produce
the outputs that WASAC wants, the objective is to
enable WASAC to produce these outputs by
themselves. It is important to patiently but strongly
get across the point that above all this project is
about capacity building. Therefore regular
meetings are held every week on Fridays at which
WASAC and the JICA Experts share the status of
their activities and problem points, etc., so that the
project can proceed smoothly. By ensuring daily
close communication, a state is created in which
both sides always understand the details of
activities.
Photo 11: Weekly meeting
Also, when seminars are held, the main C/P of
WASAC takes the lead as facilitator, thereby
encouraging their independence, and a sense of
pride. The knowledge of the C/P themselves and
the knowledge obtained from the instruction of the
JICA Experts is expressed in the seminars. In this
way an environment is formed in which many
discussions are exchanged with high awareness of
the participants, with the WASAC staff sharing the
situation on site so that issues can be raised that
they are closer to, and not just lectures delivered
one-sidedly from the Experts.
Photo 12: View at seminar
(2) Lessons learned during project
implementation
Gradually the understanding evolved that the
project must be undertaken together cooperatively,
and not by the WASAC side and the JICA Experts
4. Initiatives adopted and lessons
learned during project implementation
15
each leaving the other side to get on with their own
work. By holding hands and stepping forward
together, a relationship of trust was built, leading
to a good quality project. This took time, but it is
believed firmly that it is of major significance.
○ Project implementation period
This project extends from July 2016 to June
2019, in 2 phases. The time period of each phase is
as follows.
- Phase 1: July 2016 to June 2017
- Phase 2: July 2017 to June 2019
References:
- Japan International Cooperation Agency (2016)
“Project for Strengthening Non-revenue Water
Control in Kigali City Water Network - Survey
Report for Detailed Plan Formulation”
- Japan International Cooperation Agency /
Kokusai Kogyo Co., Ltd., Kyowa Engineering
Consultants Co., Ltd., Yokohama Water Co., Ltd.
(2017) “Republic of Rwanda Urban Water Supply
Survey to Collect and Check Basic Information -
Final Report”
- SusWas (2014) “PPP for increased access to
Sustainable Water Services in Rwanda Monitoring
NRW in Kanombe”
- SusWas (2014) “PPP for increased access to
Sustainable Water Services in Rwanda Monitoring
NRW in Remera”