of 52
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
1/52
Tarbutton Road Interchange and I-20 Frontage Roads
Dr. N. Wasiuddin Instructor
Braden Smith Project Manager
Jared Taylor Transportation GroupJohn Harrison Geotechnical Group
Sarah Wells Water Group
Samantha Tatro Structural Group
Ryan Ross Estimating and Planning Group
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
2/52
Project Overview
Timeline
Current State
Transportation
Geotechnical
Water
Structural
Estimating and Planning
Questions
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
3/52
Working Period: September, 2012 May, 2013
Objectives: Add Exit 83 at Tarbutton Road
Construct a Wider Tarbutton Road Bridge
Relativeness: Under Review by LA DOTD
Preliminary Data:
Survey Data Waggoner Engineering
Boring Logs Copies Provided from DOTD Plans
Traffic Data Copies Provided from DOTD Plans
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
4/52
September
Teams Formed and Project Defined
October
Researching Manuals and Software
November Learning Software Packages
December
Calculations and ModifyingProcedures
January Design/Calculations
February
Design/Calculations
Transportation
Structures
Water
Estimatingand
Planning
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
5/52
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
6/52
Geometric Design
Followed AASHTO: Geometric Design of
Highways and Streets
AutoCad Civil3D Main Software
Horizontal Alignment
Vertical Alignment
Pavement Cross-Sections
Intersections Lane Widening
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
7/52
AutoCad Civil3D
Received *.dwg file
from Waggoner
Survey Data and
Topographic Maps
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
8/52
Tarbutton Road Alignment
Multiple problem areas to avoid
Main Roadway and all entrance
and exit ramps
Civil 3D uses Design Speed,
minimum radius of curvature, and
super elevation to govern curves
45 mph design for Tarbutton
35 mph design for ramps
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
9/52
Vertical Alignment
Tarbutton Road
East Bound Ramps
West Bound Ramps
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
10/52
Cut/Fill
Calculated from the corridor to the existing surface
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
11/52
Pavement Design AI Method
Initial AADT 3990 veh/day
Asphalt Institute SW-1 Input: Vehicle Type Percentage
Truck Factors
Minor Arterial System
Initial Year ESAL
Design Period ESAL
6.6 HMA over 8 Aggregate Base
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
12/52
Pavement Analysis
Mechanistic approach
Two main failure modes
Fatigue Cracking
Rutting
Causes Tensile Strain
Compressive Strain
Fatigue Cracking
18 Kip ESAL
Rutting
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
13/52
Pavement Analysis
Kenpave
Evaluates Durability and Life Expectancy
Based on Load Repetitions
Repetitions Cause Pavement Failure
Rutting and Fatigue Cracking
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
14/52
Tasks
Soil Investigation Fall Quarter
Soil Sampling
Soil Testing Soil Profile
Pile Design Winter Quarter
Ultimate Bearing Capacity
Pile Grouping Design
Slope Stability Spring Quarter
Slope Stability
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
15/52
Field Sampling
Disturbed soil sampling
1ft 4ft
Hand augers
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
16/52
Field Sampling
Initially brown clayey
soil.
Transitioned into
reddish sandy clay
material around 3 ftdepth.
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
17/52
Soil Tests
Moisture Content
Sieve Analysis
Specific Gravity
Plastic Limit
Liquid Limit
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
18/52
Soil Testing
Results correlated with
information provided inboring logs.
Provided hands on
experience withcollecting data and
performing tests.
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
19/52
Soil Profile
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
20/52
Bearing Capacities
Bearing Capacities
Driven - Software
LA DOTD Pile Capacity
Design Guide
Piles are being placed in
very dense gray clayey
sand layer.
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
21/52
Pile Grouping
3 or 4 Columns
16(18 piles)
Spacings
4.5ft center to center.
Group dimensions areB= 10.5ft and Z= 37.5ft
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
22/52
Objectives
Calculate Runoff
Ditch Analysis
Existing Culvert Analysis
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
23/52
CATCHMENT 3
AREA = 28.627 ACRE
GRADE: 2%
HYDRAULIC LENGTH: 2410FT
CATCHMENT 2
AREA = 11.485 ACRE
GRADE: 1%
HYDRAULIC LENGTH: 1733FT
CATCHMENT 4
AREA = 15.443 ACRE
GRADE: 4%
HYDRAULIC LENGTH: 1687FT
CATCHMENT 1
AREA = 11.577 ACRE
GRADE: 2%
HYDRAULIC LENGTH: 1733FT
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
24/52
Introduction Existing Conditions Catchment Areas Analysis Conclusion
College of Engineering and Science
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
25/52
Introduction Existing Conditions Catchment Areas Analysis Conclusion
College of Engineering and Science
Project Classification
Design type
Rural
Open ditch facilities
Frequency
50 year storm
DRAINAGE CLASSIFICATION FREQUENCY
Interstates 50 years
Roadway Grade, Bridges, Cross Drains, or Side Drains under
important side roads25 or 50 years
Side Drains under private drives & average conditions 5 years
Median Drains 10 years
Storm Drains and Inlets 10 years
Roadside Channel 5 years
Detour Road Structures 1 year minimum
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
26/52
Introduction Existing Conditions Catchment Areas Analysis Conclusion
College of Engineering and Science
Rational Method
Catchment Areas
Rainfall Region
Runoff Coefficient Time of Concentration
Intensity
Final Peak Runoff Data
Q= CiAQ= peak runoff rate (ft^3/sec)
C= runoff coefficienti= average rainfall intensity at time of
concentration
A= drainage area
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
27/52
Introduction Existing Conditions Catchment Areas Analysis Conclusion
Runoff
Coefficient
Hydraulics Manual
Industrial Light
Areas
Lincoln
Parish
C = 0.50
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
28/52
Introduction Existing Conditions Catchment Areas Analysis Conclusion
Results of Runoff
Catchment Area (acre)Hydraulic
Length (ft)Slope
Time of
Concentration
(hr)
Intensity
(in/hr)
Peak Runoff
(ft3
/sec)
1 11.6 1733 2% 1.04 0.234 1.363
2 11.5 1733 1% 1.19 0.215 1.243
3 28.6 2410 2% 1.18 0.216 3.114
4 15.4 1687 4% 0.89 0.255 1.986
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
29/52
Drainage
Side Ditch Cross Drain Culvert
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
30/52
Side Drainage Calculations
Side Drainage Calculations
Hydraulic Radius
Manning's Formula
Critical Depth
Ifd dc
then the flow is tranquil
Ifd dc
then the flow is turbulen
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
31/52
Side Ditch Results
Side DitchFlow Rate(ft^3/sec)
Slope(%)
Depth(ft)
Critical Depth(ft)
New Slope(%)
New Depth(ft)
1 1.363 3.12 0.179 0.285 0.112 0.439
2 1.243 3.12 0.17 0.269 0.112 0.42
3 3.114 2.37 0.304 0.4517 0.37 0.494
4 1.986 2.25 0.242 0.352 0.25 0.434
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
32/52
Design Approach
Manual Calculations using Excel Spreadsheets
Verifying design through use of softwares
Two main softwares used: QConBridge
STAAD Pro
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
33/52
QConBridge
Check maximum moment and shear
Manual calculations varied by less than 1%
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
34/52
STAAD Pro Finite element analysis and design software
Creates 3D model of bridge
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
35/52
Project Overview
Bridge length: 300 ft.
4 lanes
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
36/52
SideView
Span 1: Span 2: Span 3: Span 4:
50 ft. 80 ft. 80 ft. 90 ft.
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
37/52
Maximum Span Length: 100 ft
Girder Selection:
AASHTO
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
38/52
Bridge Cross-Section Girder spacing: 8ft.
Overhang spacing: 3ft. - 11in
Lane width: 12ft. Shoulder width: 10 ft.- 8 in
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
39/52
Slab Design Maximum Design Span: 6.667 ft
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
40/52
Slab Reinforcement
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
41/52
F- Shape (PL-2)
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
42/52
Initial Substructure Design
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
43/52
Resources
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
44/52
Calculating Estimate
Unit Price * Quantity = Total Cost per Bid Item
(7200 sy)*($38.43/sy) = $276,696.00
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
45/52
Construction Cost Estimate Summary
Project Estimated Cost
Earthwork 3,001,674.15
Tarbutton Road 797,136.00
Interchange Ramps 1,217,707.00
Drainage 142,268.63
Bridge (Partial Estimate) 950,459.62Traffic Engineering 80,204.68
Roadside Development 33,653.37
$ 6,223,103.45
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
46/52
Earthwork Roadway excavation
Embankment Borrow
$3,001,674.15
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
47/52
Asphalt Pavement Superpave asphaltic concrete
Class II Base Course (varying thicknesses)
$2,014,843.00
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
48/52
Drainage Storm drain pipe (18 RCP)
Class A concrete
Trenching
$142,268.63
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
49/52
Bridge Construction Class A & AA concrete
Precast concrete test piles
Reinforcing steel
Expansion joint seal
$950,459.62
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
50/52
Traffic Engineering Traffic signals
Signage
Pavement markings
$80,204.68
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
51/52
Roadside Development
Topsoil Seeding
$33,653.37
7/29/2019 S19_Louisiana Tech University_LTC2013 (1)
52/52
Questions