    I-210 InterchangeImprovements

    Making Every Day Count

    Timothy Nickel, P.E.

    (225) 379-1110

    [email protected]

    Post Office Box 94245

    Baton Rouge, LA 70804-9245

    mailto:[email protected]:[email protected]
  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    2/19

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    3/19

    Project Details

    Project Acceleration

    What made it work

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    4/19

    Future Development

    Opening July 2014

    Existing Congested

    Nelson Interchange

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    5/19

    Based on a 2007 Corridor Study DOTD had an existing need for improvements on I-

    210, with current budget, improvements would be years down the road.

    Developer approached DOTD with the request for an interchange and to provide $17

    Million toward the project. (June 2011) DOTD teamed with the developer who paid for

    all engineering & a portion of construction. This allowed an accelerated schedule

    An Interchange Justification Report (IJR) is required to be completed and accepted by

    FHWA, alternatives vetted through the NEPA process, and designed in accordance withDOTD and FHWA guidelines.

    Developer requested if we could expedite project process to limit impacts to their

    initial opening in July 2014.

    This would consolidate a typical 10 year process into 3 years.

    THIS MADE EVERY DAY COUNT

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    6/19

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    7/19

    Early MOU Schedule

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    8/19

    Environmental Process

    For the EA, the team worked with FHWA and DOTD

    to issue the FONSI within a condensed schedule.

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    9/19

    STAKEHOLDER/PUBLIC MEETING

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    10/19

    Design Process

    DOTD allowed condensed reviews and used real-time

    working meetings to resolve comments and questions.

    Early coordination of utility relocations and ROW

    acquisition accelerated the schedule

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    11/19

    Project was given high Priority in the Department

    All reviews were given priority by all DOTD Sections

    DOTD staff would work overtime to meet timelines.

    Interchange Justification Report and NEPA Process was done concurrently.

    At the Developer's own risk, Preliminary Design began during NEPA process

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    12/19

    For the IJR, after investigating over 30

    concepts, a full interchange at Cove along

    with improvements to Nelson was selected as

    the preferred alternative.

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    13/19

    Obstacles Along The Way

    1. Interchange Justification Report

    1. Memorandum of Understanding

    2. Alternatives, Alternatives, Alternatives

    2. NEPA Process

    1. Timing

    2. What moves forward from IJR?

    3. Design1. Critical Items first

    2. Avoid late notices

    3. Value Engineering

    4. Real Estate

    1. Limit impacts to community

    2. Begin as early as possible5. Utilities

    6. Construction

    1. Consider Incentives

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    14/19

    Estimated Project Cost = $80 Million

    Three Phases

    Private Investment $20 Million

    State Capital Outlay $20 Million

    DOTD Program $20 Million Parish, City, MPO Locals $20 Million

    Total $80 Million

    Initial Estimated Project Cost = $50 Million

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    15/19

    A good plan is just a good plan without the motivated

    people to make it happen.

    Team was creative with solutions and motivated others.

    We held many meetings at the Consultants office and ours with very littlenotice.

    Specialty specific meetings and conference calls were held to discussplan development with Consultant in-between submittals.

    Stovepiping was limited by having multiple specialties work together

    periodically.

    A lot of team trust.

    Support of the Executive and Administrative staff of DOTD and theConsultant.

    PROJECT TEAM

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    16/19

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    17/19

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    18/19

    Private interest willing to provide resources

    Executive Staff (encouragement and priority)

    Local entities working with us

    Excellent Plan Development Teamwork and individual effort FHWA

    DOTD

    Consultant

    City/MPO Locals

  • 7/29/2019 S63_I-210 Interchange Improvements Making Every Day Count_LTC2013

    19/19

    Questions or Comments?

    Post Office Box 94245

    Baton Rouge, LA 70804-9245

    Timothy Nickel, P.E.

    (225) 379-1110

    [email protected]

    THANK YOU!