+ All Categories
Home > Documents > SAEP-351

SAEP-351

Date post: 12-Nov-2014
Category:
Upload: mbayou
View: 1,680 times
Download: 278 times
Share this document with a friend
Description:
SAEP-351
11
Previous Issue: 7 November 2006 Next Planned Update: 12 May 2017 Page 1 of 11 Primary contact: Nasri, Nadhir Ibrahim on 966-3-8809603 Copyright©Saudi Aramco 2012. All rights reserved. Engineering Procedure SAEP-351 12 May 2012 Bolted Flange Joints Assembly Document Responsibility: Piping Standards Committee Saudi Aramco DeskTop Standards Table of Contents 1 Scope............................................................. 2 2 References..................................................... 2 3 Responsibilities.............................................. 2 4 Pre-Assembly Inspection............................... 3 5 Torquing......................................................... 4 6 Torquing Tools............................................... 4 7 Stud Bolt Tightening Procedure..................... 4 8 Stud Bolt Additional Tightening Procedure where Leaks Occur During Pressure Testing................................ 5 Table-SAEP-351-01 Friction Factors for Different Lubricants.................................. 6 Table-SAEP-351-02 Torque Values for Low-Alloy Steel Bolting............................. 7 Table-SAEP-351-03 Torque Values for Isolating Gaskets (PIKOTEK) on ASME B16.5 and ASME B16.47 Series A & B, Class 150 Through Class 2500 Flanges....................................... 8 Figure SAEP-351-01 Stud Bolt Tightening Sequence (4 to 32 Bolts)............................... 9 Figure SAEP-351-02 Stud Bolt Numbering (36 to 68 Bolts)............................................. 10 Table-SAEP-351-04 Cross-Pattern Tightening Sequence (36 to 68 Bolts) Per (ASME PCC-1)...................................... 11
Transcript
Page 1: SAEP-351

Previous Issue: 7 November 2006 Next Planned Update: 12 May 2017

Page 1 of 11

Primary contact: Nasri, Nadhir Ibrahim on 966-3-8809603

Copyright©Saudi Aramco 2012. All rights reserved.

Engineering Procedure

SAEP-351 12 May 2012

Bolted Flange Joints Assembly

Document Responsibility: Piping Standards Committee

Saudi Aramco DeskTop Standards

Table of Contents

1 Scope............................................................. 2 2 References..................................................... 2 3 Responsibilities.............................................. 2 4 Pre-Assembly Inspection............................... 3 5 Torquing......................................................... 4 6 Torquing Tools............................................... 4 7 Stud Bolt Tightening Procedure..................... 4 8 Stud Bolt Additional Tightening Procedure where Leaks Occur During Pressure Testing................................ 5 Table-SAEP-351-01 – Friction Factors for Different Lubricants.................................. 6 Table-SAEP-351-02 – Torque Values for Low-Alloy Steel Bolting............................. 7 Table-SAEP-351-03 – Torque Values for Isolating Gaskets (PIKOTEK) on ASME B16.5 and ASME B16.47 Series A & B, Class 150 Through Class 2500 Flanges....................................... 8

Figure SAEP-351-01 – Stud Bolt Tightening Sequence (4 to 32 Bolts)............................... 9 Figure SAEP-351-02 – Stud Bolt Numbering (36 to 68 Bolts)............................................. 10

Table-SAEP-351-04 – Cross-Pattern Tightening Sequence (36 to 68 Bolts) Per (ASME PCC-1)...................................... 11

Page 2: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 2 of 11

1 Scope

This procedure defines minimum requirements to assemble bolted flanged joints in

pressure containing piping systems as defined in SAES-L-100. It is applicable for both

new and existing facilities.

2 References

2.1 Saudi Aramco References

Saudi Aramco Engineering Standards

SAES-L-100 Applicable Codes & Standards for Pressure Piping

Systems

SAES-L-109 Selection of Pipe Flanges, Bolts and Gaskets

SAES-L-350 Construction of Plant Piping

SAES-L-450 Construction of Pipelines

2.2 Industry Codes and Standards

American Petroleum Institute

API BULL 5A2 Bulletin on Thread Compounds for Casing, Tubing,

and Line Pipe

American Society of Mechanical Engineers

ASME B16.5 Pipe Flanges and Flanged Fittings NPS ½ through

NPS 24

ASME B16.47 Large Diameter Steel Flanges NPS 26 through NPS 60

ASME B31.3 Process Piping

ASME B31.4 Pipeline Transportation Systems for Liquid

Hydrocarbons and Other Liquids

ASME B31.8 Gas Transmission and Distribution Piping Systems

ASME PCC-1 Guidelines for Pressure Boundary Bolted Flange

Joint Assembly

3 Responsibilities

3.1 For existing facilities the following shall apply:

3.1.1 It is the responsibility of Operations Superintendent to ensure that this

Page 3: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 3 of 11

procedure is adhered to during the maintenance activities within the

facilities under his jurisdiction.

3.1.2 The maintenance personnel executing the flange assembly activities must

be aware of this procedure and ASME PCC-1 Guideline and have the

proper training to conduct the work.

3.2 For new capital program projects the following shall apply:

3.2.1 The Project Manager is responsible for ensuring that the Construction

Contractor is following this procedure or specific procedures that shall

be approved by Proponent, SAPMT, Inspection and the Piping Standards

Committee Chairman or his representative.

3.2.2 The contractor personnel executing the flange assembly shall adhere to

flange assembly procedure. They shall have proper training and skills to

conduct the job.

4 Pre-Assembly Inspection

4.1 The gasket shall be verified for correct type, rating, dimension and compatibility

with the flange facing. Also, it shall be free from any damage particularly in the

seating element. Ensure that spiral wound gaskets are stored flat especially for

large sizes, 24 inches and larger.

4.2 Bolts, nuts and washers shall be visually checked for proper size, grade,

dimension and for any physical damage to shanks or threads which would affect

the bolt assembly or performance. Also, check the suitability of the stud bolts

and nuts material for the service temperature and the compatibility with the

flange material.

4.3 The flange facing, particularly the seating area, shall be visually examined for

cleanliness and ensure that no damage, such as scratches exist.

For ring joint type flanges, the ring and the ring groove shall be free of damage

and dirt.

4.4 Proper lubricant for bolts and nuts shall be used. Lubricant for bolts and nuts shall

be Jet-Lube SS-30 or other acceptable lubricants listed in Table-SAEP-351-01.

4.5 Tightening tools shall be checked for adequacy, performance and calibration, if

required.

4.6 Lubricant shall not be used in the gasket and the gasket seating area.

4.7 Flange shielding shall be installed/reinstalled when required.

Page 4: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 4 of 11

Commentary Note:

Flange shielding is normally used for personnel protection against possible liquid splash or high temperature during operation.

5 Torquing

5.1 Torque values vary according to flange rating, bolt size, type of gasket, and

friction factor of the thread lubricant.

5.2 The torque values are specified in Table-SAEP-351-02 and Table-SAEP-351-03.

5.3 Table-SAEP-351-02 applies to all gaskets listed in SAES-L-109, except for

insulating gaskets.

5.4 Table-SAEP-351-03 applies to isolating gaskets (e.g., PIKOTEK), based on a

friction factor of 0.16.

6 Torquing Tools

6.1 There are various types of tools available to achieve the proper torque value.

Selection of the proper tool depends on the stud bolt size, physical location of

the flanged joint, and criticality of the flange. Identifying the proper tools shall

be resolved between Contractor, SAPMT, Proponent and Inspection prior to

commencing the erection of the piping.

6.2 The manufacturer's instructions shall be followed for the operation, limitation

and maintenance of all torque wrenches used to perform flange bolts tightening.

6.3 Torque wrench calibration shall be performed in accordance with manufacturer's

recommendations.

7 Stud Bolt Tightening Procedure

Step 1 Align flanges and gasket. Forced tightening is not allowed to overcome non

acceptable alignment tolerances. Clamp securely in place.

Step 2 Apply lubricants to stud threads over length and nut engagement and to face of

nut which contacts flange. Ensure that the nuts run freely down the thread of

the studs.

Step 3 Install all studs and nuts hand tight, ensure that studs pass freely through the

flange holes. Position the nut on one end of the stud such that only the crown

of the stud projects beyond the face of the nut. The excess stud length should

project beyond the nut on the other side.

Page 5: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 5 of 11

Commentary Note:

By doing this, the nut that is installed nearly flush with the end of the stud can be easily removed since the threads are not coated, and normally have not been subjected to corrosion. The side of the stud with the flush nut should be chosen by taking into consideration factors such as whether one side has better access for maintenance personnel and/or tightening tools, e.g., torque wrench or impact wrench, etc.

Step 4 Number each stud according to its position in the flange as shown on Figure 1:

Stud Bolt Tightening Sequence.

Step 5 For insulting gaskets like PIKOTEK, enough gap (½" of gap is recommended)

should be available between flange faces to avoid any damage to seals during

inserting the gaskets, if due to any reasons, seals are damaged, change the seal

before installing PIKOTEK.

Step 6 Matting flange faces and the gaskets should be dry and free from grease, oil or

water.

Step 7 Tighten studs per the Stud Bolt Tightening Sequence, for 4 to 32 bolts use

Figure SAEP-351-01 and for 36 to 68 bolts see Figure SAEP-351-02 for bolts

numbering and then follow the tightening sequence of Table SAEP-351-04.

An appropriate tool should be used such as an air impact wrench or equivalent.

Step 8 For joints containing RTJ or Spiral Wound Gaskets, repeat step 7.

Step 9 Tighten the stud bolts in stages to obtain the final required torque from the

appropriate torque Table-SAEP-351-02. The first stage should not be more

than 30% of the final torque. The final torque shall be within ±5% of the

required torque value.

Apply the torque evenly to each stud following the stud bolt tightening

sequence. The final torque must be within ±5% of the required values per

Section 7 above.

8 Stud Bolt Additional Tightening Procedure where Leaks Occur During Pressure Testing

Step 1 Depressurize the piping system and re-torque stud bolts to maximum torque

value shown on Table-SAEP-351.

Step 2 If leak does not stop after re-torquing has been performed, disassemble the

flange joint and inspect as follows:

a. Inspect stud bolts and nuts for defects or damage to threads or improper

cleaning of threads.

Page 6: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 6 of 11

b. Inspect flange faces for damage, misalignment.

c. Inspect gasket for damage or defects.

Step 3 After all defective and damaged items have been repaired or replaced,

reassemble the flange joint using a new gasket and tighten the bolts using the

maximum torque values.

Table-SAEP-351-01 – Friction Factors for Different Lubricants

Lubricants Friction Factors Torque

Correction Factor

Moly Graphite .06 0.67

Tool Joint Compound .08 0.8

Graphite and Oil (used as the base line for torque values in Table-SAEP-351-02)

.10

1.0

Aerocote #4 .11 1.1

KOPR-KOTE .11 1.1

EL-PRO C5A .11 1.1

FEL-PRO C100 .11 1.1

FEL-PRO C102 (commonly called Anti-Seize)

.11 1.1

Jet Lube SS-30 .12 1.2

API BULL 5A2 Thread Compound

.125 1.3

Light Machine Oil as shipped .15 1.5

Dry Bolts .2 2

Page 7: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 7 of 11

Table-SAEP-351-02 – Torque Values for Low-Alloy Steel Bolting

Stud Bolt Size inch

Torque Ft-Lb

Noncoated Bolts Coated Bolts

1/2 60 45

5/8 120 90

3/4 210 160

7/8 350 250

1 500 400

1-1/8 750 550

1-1/4 1050 800

1-3/8 1400 1050

1-1/2 1800 1400

1-5/8 2350 1800

1-3/4 2950 2300

1-7/8 3650 2800

2 4500 3400

2-1/4 6500 4900

2-1/2 9000 6800

2-3/4 12000 9100

3 15700 11900

3-1/4 20100 15300

3-1/2 25300 19100

3-3/4 31200 23600

4 38000 28800

Notes:

1) Torque values are based on 50,000 psi prestress on stud bolts and Friction Factor of 0.16 for noncoated surfaces and 0.12 for new coated surfaces. A combination of various elements such as the conditions of the threads, the condition of the flange to the nut bearing surface and the type of lubricant used, makes up the friction factor which can vary from .04 to .20 or as much as 500%.

2) Torque values for stainless steel or other alloy stud bolts can be obtained by multiplying the ratio of the specified minimum yield strength (SMYS) of stainless steel stud bolts to A193 B7 stud bolts, to the torque values in the Table-SAEP-351-02. The SMYS values for all bolting materials are listed in ASME B31.3 code (Note: SMYS depends on grade, class and size).

Page 8: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 8 of 11

Table-SAEP-351-03 – Torque Values for Isolating Gaskets (PIKOTEK) on ASME B16.5 and ASME B16.47 Series A & B,

Class 150 Through Class 2500 Flanges

Stud Bolt Size inch

Torque Value Ft-Lb

1/2 30

9/16 45

5/8 60

3/4 100

7/8 160

1 245

1-1/8 355

1-1/4 500

1-3/8 680

1-1/2 800

1-5/8 1100

1-3/4 1500

1-7/8 2000

2 2200

2-1/4 3180

2-1/2 4400

2-3/4 5920

3 7720

3-1/4 8400

3-1/2 9000

3-3/4 9600

4 10000

Note: Torque values based on 30,000 psi tension load and 0.16 Friction Factor from API BULL 5A2 thread compound. See Table-SAEP-351-02 Note (1) for other factors.

Commentary Notes:

a) For ASME Class 900 through Class 2500, API-6B and API-6BX Class 2000 through Class 15000, and RTJ Flanges, the maximum compressive stresses induced during installation should not exceed 25,000 psi. Design to 12,500 psi when possible.

b) Calculations for compressive stresses applied during torque-up procedures must account for ring joint grooves, gasket seal grooves, raised face diameters, and gasket inside diameter. (See PIKOTEK Gasket User's manual).

c) Bolt tensioning equipment such as HYDRATIGHT may be used for class 900 and above resulting in a minimum residual bolt stress of 30000 psi and a maximum of 50,000 psi. Refer to PIKOTEK Gasket User's manual for specific bolting instructions.

Page 9: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 9 of 11

Figure SAEP-351-01 – Stud Bolt Tightening Sequence (4 to 32 Bolts)

Page 10: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 10 of 11

Figure SAEP-351-02 – Stud Bolt Numbering (36 to 68 Bolts)

3

1

2

4

5

6

8

7

14

13 12

11

10

9

Page 11: SAEP-351

Document Responsibility: Piping Standards Committee SAEP-351

Issue Date: 12 May 2012

Next Planned Update: 12 May 2017 Bolted Flange Joints Assembly

Page 11 of 11

Table-SAEP-351-04 – Cross-Pattern Tightening Sequence (36 to 68 Bolts) per (ASME PCC-1)

No. of bolts

Sequence

36 1-2-3 19-20-21 10-11-12 28-29-30 4-5-6 22-23-24 13-14-15

31-32-33 7-8-9 25-26-27 16-17-18 34-35-36

40 1-2-3-4 21-22-23-24 13-14-15-16 33-34-35-36 5-6-7-8 25-26-27-28

17-18-19-20 37-38-39-40 9-10-11-12 29-30-31-32

44 1-2-3-4 25-26-27-28 13-14-15-16 37-38-39-40 5-6-7-8 29-30-31-32

17-18-19-20 41-42-43-44 9-10-11-12 33-34-35-36 21-22-23-24

48 1-2-3-4 25-26-27-28 13-14-15-16 37-38-39-40 5-6-7-8 29-30-31-32

17-18-19-20 41-42-43-44 9-10-11-12 33-34-35-36 21-22-23-24 45-46-47-48

52 1-2-3-4 29-30-31-32 13-14-15-16 41-42-43-44 5-6-7-8 33-34-35-36

17-18-19-20 45-46-47-48 21-22-23-24 49-50-51-52 25-26-27-29

9-10-11-12 37-38-39-40

56 1-2-3-4 29-30-31-32 13-14-15-16 41-42-43-44 21-22-23-24 49-50-51-52

9-10-11-12 37-38-39-40 25-26-27-28 53-54-55-56 17-18-19-20

45-46-47-48 5-6-7-8 33-34-35-36

60 1-2-3-4 29-30-31-32 45-46-47-48 13-14-15-16 5-6-7-8 37-38-39-40

21-22-23-24 53-54-55-56 9-10-11-12 33-34-35-36 49-50-51-52

17-18-19-20 41-42-43-44 57-58-59-60 25-26-27-28

64 1-2-3-4 33-34-35-36 17-18-19-20 49-50-51-52 9-10-11-12 41-42-43-44

25-26-27-28 57-58-59-60 5-6-7-8 37-38-39-40 21-22-23-24

53-54-55-56 13-14-15-16 45-50-51-52 29-30-31-32 61-62-63-64

68 1-2-3-4 37-38-39-40 21-22-23-24 53-54-55-56 9-10-11-12 45-46-47-49

29-30-31-32 61-62-63-64 17-18-19-20 57-58-59-60 33-34-35-36 5-6-7-8

41-42-43-44 13-14-15-16 49-50-51-52 25-26-27-28 65-66-67-68

Revision Summary 12 May 2012 Revised the "Next Planned Update". Reaffirmed the contents of the document, and reissued

with no other changes.


Recommended