CAL VERT CLIFFS NUCLEAR POWER PLANT UNITS I & 2 STEAM GENERATOR REPLACEMENT
REPLACEMENT STEAM GENERA TOR SAFETY EVAL UA TION REVIEW AND
PROJECT S TA TUS PRESENTATION TO THE NRC
NOVEMBER 1, 2000
Calvert Cliffs Nuclear Power Plant, Inc.Constellation Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Name A. R. Thornton --------------
T. L. Konerth ---------------
G. Tesfaye -----------------M. T. Finley ----------------W. C. Holston ---------------
M. Massoud ----------------
K. J. Connell ---------------M. D. Ceraldi ---------------
M. B. Baker ----------------
J. Millman ------------------
NRC Presentation November 1, 2000, Slide 2
NTitle
CCNPP Manager-Nuclear Project Management Department
CCNPP Project Engineer
CCNPP Senior Licensing Engineer CCNPP Principal Engineer
CCNPP Supervisor Eng. Assessment CCNPP Consulting Engineer
SGT RSG Engineering Manager SGT Lead Licensing Engineer
FTI Senior Licensing Engineer
BWC Senior Project Engineer
Constellation Nuclear
Calvert Cliffs Nuclear Power Plant Attendees
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N Meeting Objectives
Present to the N RC staff an Overview of Replacement SG Safety Evaluation
* h-..Update Licensing Status
* ;'6.Update Engineering Status *,'-'Update Fabrication Status
Constellation NRC Presentation November 1, 2000, Slide 3 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N.0bA
W,"
,we
0A.
"0A
IV419
Agenda
Introduction
RSG Safety Evaluation
Licensing Status
Engineering Status
Fabrication Status
Open Discussion
Closing Remarks Supplementary Presentation
"Gothic Application"
A. R. Thornton M. T. Finley
G. Tesfaye
T. L. Konerth
T. L. Konerth
All Attendees
A. R. Thornton
M. Massoud
Constellation NuclearNRC Presentation November 1, 2000, Slide 4
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Functional Relationships
Constellation NuclearNRC Presentation November 1, 2000, Slide 5
N
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
SG Replacement Events
Warehouse construction starts March 2001 W&V,. OSG storage facility construction starts
March 2001 .*6" Unit 1 RSGs arrive Oct-Nov 2001 * Unit 1 replacement outage starts March 2002 .*6% Unit 2 RSGs arrive Oct-Nov 2002 -*, Unit 2 replacement outage starts February
2003
Constellation NRC Presentation November 1, 2000, Slide 6 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
.,6" Background >--RSG designed similar to OSG >- Most significant design/operating changes:
4 RSG tubing Alloy 690 with reduced wall thickness 4, UA 4% above zero plugged tube UA for OSG 4 Secondary steam pressure increases 50 psi
(25 psi above current safety analysis assumption) 4, RCS flow increases (back to zero plugged tube
value) 4 Integral flow restrictor (1.9 ft2) installed
)- Primary and secondary inventory very similar by design
Constellation NRC Presentation November 1, 2000, Slide 7 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
NRSG Safety Evaluation
10CFR50.59 Scope
Constellation NuclearNRC Presentation November 1, 2000, Slide 8
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
NRC Presentat
RSG Safety Evaluation L: Review Process (Performed by FTI)
>Review each accident and identify: "4. the acceptance criteria "4, the critical parameters that affect the approach to the
acceptance criteria >-Compare the OSG and RSG characteristics >-Could use of the RSG adversely affect the
approach to an acceptance criterion? 4, No.. .UFSAR remains bounding 4 Yes.. .Additional evaluation or analysis required
>Are all acceptance criteria met? "4 Yes. .. Document evaluation or analysis in UFSAR "4 No.. .NRC prior approval required
>AII documents reviewed I approved by SGT & CCNPP
Constellation "ion November 1, 2000, Slide 9 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Calvert Cliffs RSG Safety Analysis Matrix Accident [UFSAR Chapter [ Effect of RSG I Disposition
CEA Withdrawal 14.2 . UA I beneficial Evaluation . RCS flow 1" beneficial . Core physics unaffected
Boron Dilution 14.3 . RCS inventory very similar Evaluation . Boron worth unaffected
Excessive Load 14.4 . Steam flow increase is less than 3% Evaluation . Steam flow remains less than analysis of record since
5% margin was available . RCS flow 1T beneficial
Loss of Load 14.5 . UA 1T beneficial for primary pressure, adverse for Analysis secondary pressure
. Analysis for peak secondary pressure performed
. RSG design pressure T 15 psi , Result is less than 110% of design pressure
Loss of Feedwater 14.6 . Secondary inventory very similar Evaluation Flow . Decay and sensible heat very similar
. Siqnificant margin in analysis of record low level trip Excess Feedwater 14.7 . Feedwater condition5" unaffected Evaluation Heat Removal . RCS flow 1T beneficial RCS 14.8 . PORV and pressurizer unaffected Evaluation Depressurization . RCS flow 1" beneficial Loss of Coolant 14.9 . RCP coastdown less rapid with fewer plugged tubes Evaluation Flow , RCS flow T beneficial
Loss of AC Power 14.10 . Decay and sensible heat very similar Evaluation . Secondary inventory very similar
CEA Drop 14.11 . Core physics unaffected Evaluation * RCS flow T beneficial
Asymmetric SG 14.12 o UA t has small effect on core temperature tilt Evaluation * RCS flow 1T beneficial
CEA Ejection 14.13 o Core physics unaffected Evaluation * RCS flow 1f beneficial
SLB - IC 14.14 * Integral flow restrictor beneficial (break area 1.) Evaluation SSecondary inventory very similar
SLB - OC 14.14 , UA T and secondary pressure increase adverse Analysis * Significant margin in break size in analysis of record • RCS flow 1T beneficial • Secondary inventory very similar - dose unaffected
SGTR 14.15 , Tube ID T is adverse Evaluation • Shortest tube length 1" is beneficial • Secondary pressure 1t is beneficial * Ruptured tube flow is bounded * Adequate overfill volume
Seized Rotor 14.16 , RCS flow distribution and step change unaffected Evaluation * RCS flow 1t beneficial * UA T beneficial
LOCA 14.17 , Primary inventory very similar Evaluation * UA T is beneficial * Decreased tube plugging is beneficial
Fuel Handling Inc. 14.18 , Unaffected Evaluation Turb. Overspeed 14.19 , Unaffected Evaluation Containment 14.20 * Primary inventory very similar Evaluation Resp. - LOCA * RCS flow 1T beneficial since Tave . Containment 14.20 o Smaller break with dry steam adverse Analysis Resp. - MSLB o Peak pressure less than design
, Temperature spike short with redundant spray Hydrogen Accum 14.21 o Unaffected Evaluation Waste Gas Inc. 14.22 , Primary inventory very similar Evaluation Waste Evan Inc. 14.23 o Unaffected Evaluation MHA 14.24 . Unaffected Evaluation Excess Charging 14.25 o Pressurizer and charging pumps unaffected Evaluation
. Primary inventory very similar Feedline Break 14.26 . Secondary inventory very similar Evaluation
. UA t is beneficial o Significant margin in break uncovery assumption in
analysis of record
NRC Presentation November 1, 2000, Slide 100 Constellation
Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N RSG Safety Evaluation CEA Withdrawal
>-Heatup event where increased UA is beneficial
>-Increased RCS flow is beneficial
>-Core physics unaffected
,. Boron Dilution >-Primary inventory is very similar
>-Boron worth is unaffected
Constellation NRC Presentation November 1, 2000, Slide 11 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
"re Excess Load >-Steam flow increase is less than 3% >-Steam flow remains less than analysis of record.
since 5% margin is available >-Increased RCS flow is beneficial
"-,-s Loss of Load • Increased UA beneficial for primary pressure, adverse for
secondary pressure
>--Analysis required for maximum secondary pressure case > RSG design pressure is 15 psi greater >) Result of analysis is peak secondary pressure is less
than 110% of design pressure
Constellation NRC Presentation November 1, 2000, Slide 12 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N RSG Safety Evaluation "r:." Loss of Feed
>-Secondary inventory very similar >-Decay and sensible heat very similar >-Significant margin in analysis of record Low Level
Trip set-point (-116" analysis trip vs. -50" actual trip set-point)
•:1 Excess FW Heat Removal >-FW temperatures are not affected >-Increased RCS flow is beneficial
Constellation NRC Presentation November 1, 2000, Slide 13 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
"&,. RCS Depressurization >-PORV and pressurizer are not affected >Increased RCS flow is beneficial
Igh.,. Loss of Flow >-RCP coastdown less rapid with fewer plugged
tubes >Increased UA is beneficial
Constellation NuclearNRC Presentation November 1, 2000, Slide 14
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
'61 Loss of AC Power >-Decay and sensible heat are very similar >-SG secondary inventory very similar
W960 CEA Drop >-Core physics unaffected
>-Increased RCS flow is beneficial
Constellation esentation November 1. 2000 Slide 15 NuclearNRC Pr
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
o,: Asymmetric SG >Increased UA has a small effect on RCS cold leg
temperatures >-Increased RCS flow is beneficial
o,- CEA Eject >-Core physics unaffected >-Increased RCS flow is beneficial since Thot and fuel
enthalpy are reduced
Constellation NuclearNRC Presentation November 1, 2000, Slide 16
N
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
MSLB-IC (Post-trip) >- Integral flow restrictor beneficial (smaller break size) >- Secondary inventory is very similar
- MSLB-OC (Pre-trip) >- Increased UA and higher secondary pressure are more adverse >- Increased RCS flow is beneficial >- Comparative analysis of peak power was performed >- Peak power increases slightly for same break )- Break size for RSG is decreased as compared to analysis of record >- Peak power for RSG is less than analysis of record >- Secondary inventory is similar so dose is unaffected
Constellation NRC Presentation November 1, 2000, Slide 17 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
SGT R > -Tube ID is slightly increased - adverse >- Shortest tube length is increased - beneficial >-Secondary pressure is increased - beneficial (reduced
tube delta-P) >- Detailed ruptured tube flow rate analysis shows RSG tube
flow bounded by analysis of record ">-Adequate dome volume available for overfill
Constellation NRC Presentation November 1, 2000, Slide 18 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
. Seized Rotor >- RCS flow distribution and step change not affected >- Increased RCS flow is beneficial >) Increased UA .is beneficial
LOCA Core Response >- Primary inventory very similar >- Decreased tube plugging benefits steam vent during reflood
(large break) >- Increased UA is beneficial (small break)
o,. LOCA Containment Response >- Primary inventory very similar >- Increased RCS flow with decreased Tave is beneficial
Constellation NRC Presentation November 1, 2000, Slide 19 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
SRSG Safety Evaluation
MSLB Containment Response >-Integral flow restrictor reduces break size and causes
dry steam blowdown
>-Current licensing basis is 20% moisture carryover
>-Reanalysis performed with zero moisture carryover
>-Methodologies have been approved for PWR use
>-Peak pressure less than design-Structural integrity maintained
>-Temperature spike short with redundant spray
>-Currently evaluating effect of temperature spike on EQ
>-No issues for NRC prior approval identified
Constellation NRC Presentation November 1, 2000, Slide 20 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Safety Evaluation
Waste Evaporator and Waste Gas Incident
SPrim a ry in v e n to ry v e ry s im ila r
Excess Charging >- Pressurizer and charging flow are unaffected
>- Primary inventory very similar
: Feed Line Break )-Secondary inventory very similar >- Increased UA is beneficial
>-Significant margin in break uncovery assumption in analysis of record
Constellation NRC Presentation November 1, 2000, Slide 21 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Licensing Status
Draft Licensing Report (complete)
Interim Licensing Report
RSG 50.90 Submittal
RSG 50.59 Evaluation
Updated Licensing Report (Unit 1)
Updated Licensing Report (Unit 2)
July 1999
May 2000
Dec 2000
Mar 2001
April 2002
April 2003
Constellation Nuclear
NRC Presentation November 1, 2000, Slide 22
e'Ya
We''
O's
.0A.
11h,1%h,
NS
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
NRC Pr
Licensing Status
W.4.Activities Requiring Prior NRC Review and Approval
>-Technical Specification Revisions >-ASME Code Relief Requests >-No other items requiring NRC review are anticipated >-AlI Submittals are planned for December 2000
Constellation esentation November 1, 2000, Slide 23 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Licensing Status
&,&Technical Specification Revision >-SG Level References
4 Current SG levels are referenced with respect to the feed ring elevation
4 SG level set points are not expected to change relative to % span
4 Since feed ring elevation is lower, editorial change is needed
>-SG Repair Options
>-increase RCS Minimum Required Flow
Constellation
NRC Presentation November 1, 2000, Slide 24 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Licensing Status
"ASME
>-Code >-Code
>-Code
>-Code
NRC Presentation November
Code Relief Requests Case N-20-4 (approved)
Case 2142-1 (approved) Case 2143-1 (approved)
Case N-619 (will be submitted 12/00)
Constellation 1, 2000, Slide 25 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Engineering Status
oFN Replacement Steam Generator >-Two piece replacement with new moisture
separation equipment >Lower Assemblies designed to ASME III 1989
Edition No Addendum- NPT stamped >-Primary side hydrostatic test at BWC >-No secondary side hydrostatic Test at BWC >Pre-service Inspection at BWC in accordance with
ASME Section XI 1998 Edition No Addendum
Constellation NRC Presentation November 1, 2000, Slide 26 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Engineering Status
*4% Replacement Steam Generator >-Installation will be in accordance with ASME
Section XI 1998 Edition No Addendum >-Post installation primary and secondary side
Pressure test will be performed in accordance with Code Case N-416-1
.No post installation primary or secondary side hydrostatic test will be performed
Constellation NRC Presentation November 1, 2000, Slide 27 N lear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Engineering Status
*,"Structural Analysis ),Re-created 3-D Dynamic Structural beam Model of RCS
Loop in ANSYS SBenchmarked to Original CE STRUDL Loop Analysis with
excellent agreement SReplaced the portion of the Model representing the
Original Steam Generator with detailed Model of Replacement SG and recalculated seismic response.
>All loads and primary side attached piping anchor point motions bounded by original analysis loads/motions.
Constellation NRC Presentation November 1, 2000, Slide 28 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Engineering Status
"4 'Engineering Packages >6 Packages Common to both Units >o28 Packages specific to Unit 1 >-28 Packages specific to Unit 2
Constellation NuclearNRC Presentation November 1, 2000, Slide 29
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
NRC Pr•NR Pr,
Engineering Status
W, Engineering Packages Common to Both Units >-Replacement Steam Generator
>--Steam Generator Offload >-RSG Transport >-Site Facilities
>OSG Storage Facility
SKConstellation
esentation Novemhber I hn .i1 in 0Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Engineering Status
"WO Unit Specific Engineering Packages >-Hatch Transfer System >-Steam Generator Insulation >RCS Support
>-Steam Generator Supports
>-Contingency Elbows >Temporary Power >-Various packages for interference removal and
reinstallation
Constellation NRC Presentation November 1, 2000, Slide 31 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Engineering Status
W,'%Status of Engineering Packages >14 Packages approved for installation >-AlI Common and Unit 1 packages scheduled to be
complete by June 2001 >-All Unit 2 packages scheduled to be complete by
February 2002
Constellation =sentation November 1, 2000, Slide 32 NuclearNRC Pri
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Fabrication Schedule1 1999 1 2000 2001
InA I I I J N D]III MJaSI N InJIFumI MI A] M I J I n1" 8 1mna0u
Sshell can #2
732
cone
732
S1shell can #1
732
Sattach lugs lubesheet N blowdown nozzle assembly =-;
procurement of primary head
overlay
cone/shell •an assembly
732
gundnill & dabun-
731
pdrimary head/no7zZe divider plate assembly
+ 733
, divider plate 733
NGI
NG2
NG3
NG4
primary head/tubesheet IHelium secondary shell assembly pwht Ishlroud g d'stubas seal weld final ex
79 739 769,
shroud cans
749
lattice bars & gnds
795
procure tubes
779
1,4 t799 7 9
799
am I hydro ECT final prepshipping Unit NG1
999 999 999 Unit NG2
02
z
Unit NG3
Unit NG4
NRC PesenttionNovemer 1,2000 S~id33IClontlatio
1998
, n ....
x
r
NRC Presentation November 1, 2000, Slide33 SConstellation
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Insertion of Shroud into NG2 in Clean Room •- • i• •i•_i~i! ,• •• •.•~i•,•4-
NRC Presentation November 1, 2000, Slide34 Conste�I;]iIon
Calvedt Cliffs Nuclear Power Plant Steam Generator Replacement Project
Lattice Grid Assembly on Alignment Test Table
SJ... ..4
NRC Rresentation November 1, 2000, .SIide35 ConstellauunNRC Presentation November 1, 2000, Slide35 1"Constellafiun
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Primary SeDarator
NRC Presentation November 1, 2000, Slide36 Constellation
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Lower Assembly #3 without Base Support
ConstellationNRC Presentation November 1, 2000, Slide38
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Lower Assembly #4 without Primary Head
NRC Presentation November 1, 2000, Slide38 ; Constellation
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N,
/AIt/'' I-)•
Ivi-I r-lesenialton November 1, 2000,
CCNPP-NRC Meeting Schedule
Project overview meeting (July 29,1998),Z
SG Fabrication QA/QC review and project status meeting (April 28, 1999) /
'41,0 Replacement SG safety evaluation review meeting (November 15, 1999) if
,*0 Replacement SG safety evaluation review meeting (November 1, 2000) if
.'10 Pre-installation meeting Unit 1 (Spring 2002)
ft'. Post installation meeting Unit 1(Fall 2002)
1610 Pre-installation meeting Unit 2 (Spring 2003)
W". Post Installation meeting Unit 2 (Fall 2003)
.,.8 Other meetings as needed
0 Constellation Nuclear
CALVERT CLIFFS NUCLEAR POWER PLANT UNITS I & 2 STEAM GENERA TOR REPLA CEMENT
SUMMARY OF CCNPPI EXPERIENCE IN
APPLICATION OF THE GOTHIC COMPUTER CODE
PRESENTATION TO THENOVEMBER
Calvert Cliffs Nuclear Power Plant, Inc.
1,1NRC
2000
Constellation Nuclear
C)
0 bJ2
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
BACKGROUND
o:o CCNPPI Has Been Using GOTHIC Since 1994 o. A Total Of 17 Design Calculations (Formally Quality
Assured & Documented) Using The GOTHIC Code Are Prepared
o* Extensive Benchmark Is Made With The COPATTA Code On Containment Response
4, Cold-leg LOCA, Maximum Safety Injection 4& Cold-leg LOCA, Minimum Safety Injection .& Hot-leg LOCA, Minimum Safety Injection 4. Main Steam Line Break
Constellation S.. . .a . -, -. A_ _ a n .. .. ... .. . .N u c le a r
AIt~lf •iVI-, ri"sdIUIIu ivNovembrer i, 20UU, .. ilae z
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
BACKGROUND (Cont'd)
**oCCNPPI Has Also Gained Experience In Non-containment Related Applications
o**CCNPPI Has Made 5 Presentations To GOTHIC Advisory Group Meetings
Constellation esentation November 1, 2000. Slide 3 NuclearNRC Pro
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Containment Related Applications
*** Developing Containment Response Model For Benchmark With COPATTA
*** Developing Break Flow Model To Calculate Long Term Mass & Energy Transfer Rates
****Performing Sensitivity Study Regarding Time Step Size Effects On Containment Peak Pressure And Temperature
Constellation esentation November 1. 2000 Slide 4 NuclearNRC Pro
Y . .I . . .
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Containment Related 1 Applications (Cont'd)
** Developing Models For Containment Electrical Penetrations
***Analyzing Containment Response To Various Heat Sink Coating (Paint/primer) Systems
Constellation Nuclearlvi \k'J I-Ih!•IILQIUII IvUVembefl I I, 2L00, Iu, U allAI•f'( Dr,.
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
NRC Pr F
>Non-Containment Related Applications
*. Natural Circulation In The Vessel And The Refueling Pool After Loss Of Shutdown Cooling With Upper Guide Structure (UGS) Installed Or Removed
o. Analysis Of Issues On "Independent Spent Fuel Storage Installation (ISFSI)"
4, Calculation Of Maximum Flow Rate To Flood "Dry Storage Cask (DSC)" In Support Of Unload Procedure
4• Design Optimization Of Pump & Bypass Loop Orifice To Flood DSC
., Determination Of The Critical Helium Mass And Temperature In Blowdown, Dry Up, And Fill Phases
Constellation esentation November 1 200( S•liide 0 Nuclear
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Non-Containment Related Applications (Cont'd)
***Analysis Of Once-through Core Cooling (OTCC)
*o.RCS Response To SIT Nitrogen Ingress In A SB-LOCA
***Determination Of NPSH For HPSI Pumps In A Loss Of CCW To The Reactor Coolant Pump Seals
Constellation esentation November 1, 2000, Slide 7 NuclearNRC Pr(
o o
0 ................................. ........ S0 9 . .... .... .... ..... 0 : : : : : : : : :: : : : : • : :: ']
S0 >• ..... ..... ..... ....................... 0 . . ... . I, •.. .. .. .. .... .. .. .. .%. . ..... ... . . . .. .. . .• .-- .
o 000 C 0.0
: • - ......... ,..............%............ . . . . -0 . . . . . . . . . . . . . . . . . .. . . . . . .... .: : :. . . . . . . . .
LQ 4 a ......... .......... .
%&ft c• ::: * ............................ = = = = = = == = == = =i.~~ . .. . . . . . . . . . . • . . . . .. ..°
C ) 4 a ... .......... ....
-4C-4
oo
co 0 S.. .: .. . . :.. .: . .... :.... :.... : .........
. .. .. .. . .
.............. . ..... .......................................
......... ......... ..... ............... ..... ..... - 0.
.. . . . ..
..........
• ::::.::::,:::. .. .. . . . ............... 0 0 0• 0.......
S. . .. .a. . . . . . . .. . . . . .. . . . .. . . . .• . .. . . . . . . . . . . . . . .
LL .. . . .. . .. ....... . . : : ::..................... :
(0o to o o
-• (D, sl d . Jn ss ad1J ~u a u ,1~ u oO. -\
- 0
o
FF
<(
0
O() .
CO
Lwl <
r -4
0
WQ)
-o C
0 E)
LL. _
0 E 00 (9 --J
n0 -F- -o
0
O/u 0o
(9?
r
C..
ft• O
a,.
C,.,.
C'
0 1:: (j) @jnlojadwG1 4uawuOIuo 0
I....i .' !... .... ... : 2 : ::: . :. -.. ; .'. ... :
00 o........ :
..... ................... .......... ..
. .... .. ............................
. . . .. .. .g
. - -. --- ... .- . . . . .- . . .- . . .. . ... .... . .. '. . % . ... .. ..
.:: : : : : : : : : : : : :: :: ::' ... ... ** .,,.. ; , . ,,,.._.....
. . . . . . ... . .. . .. . . . . .
°~~ . . . . .i, . . . . . . %
S. ... . ... . . . . . ~~~~~~. .. . . . . . . . . .. . . .. . . . .: , , . . . . . .
°~~ ~~~ ~~ .° ° ° .* ° .° .° * °•.. . .° ..° . .o . • . . '
• . . .* . . . . . . . . . . . . . . . .
(D
0
0
0
V-
C.)
(NJ
0
0
U
0)
E
0 0 0 0 0 0 CO (0 D It C M) (N (N (N CN
b O
CD
0
0
0 0
0
C,"
@.
¢0
a)
0 co
0 o 0 '4- CN r- t-
0 0
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
GOTHIC Nodalization of Quadrant Vessel & RFP UGS (Installed)
UOI8 - - -
F--i
I I I- I
• I I I I
4
6' __-r- •
M A91 do±I
s -eAo' -
NRC Presentation November 1, 2000, Slide 10 0 ConstIOI1
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Stage 6: DSC In Reflood Mode
PRESSURE GAUGE 0-100 (MINIMUM)
ATTACHED
ATTACHED
TO VENT PORT
TO SIPHON PORTSFP WATEf
NR rsnaio oebr1 200 Slide 1 ofa rwLd
PSI
NRC Presentation November 1, 2000 Slide 11
-1 -
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
DSC Temperature & Pressure in Stage 6
Li
Lii
I�tL F- -
- -
GOTHIC; S• (ilOAt1.,r- (i9'0107 CC 5'A
Time (sec)
DIRECT HTC OPTION
SPLIT: 0 - 1
I. 2.
4. 5. 6.
Assemblies Spacer Support Sleeves DSC Wall TC Wall
6
Time (sec)
iF
-J 10
Xl0e3
NRC Presentation November 1, 2000, Slide 12SConstellation
E
Stage 6. DSC tnj.: 2 GPM at 1805 s. Ann Flooded. Ti = 650
GOTHIC 5 010A11 -C 02!20197 11,10:38 C GOTHIC 5 0 OA - 02!20197 1 110 ý?
2
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Effect Of Time Step Size On Peak Pressure CLx.rcs, Dt(min): 1 E-6 sec, Graph Int.: U sec
.. ... . . ..... ......... .
.............................. . ............. ........... ..........
........... . ....... ... .. .... . . ......... . . .. .
. . .. "...- . -.... ..... ..... ........ . ........... . .... .... .............. ..... .. .........
........................ . .... .................
.... ........ ...............
.... ..... .. . .. .. . .. .. ...........
.. . .. . . .. . .......... ........ ..... ....
.......... .. . . . . . . . .. . . . . . . . .
.............. .. . . . . .
............ . ................ .. . . . . . . ...... ..... ..... ................... .. .
. ..... .' . .......-...... .... .. :.... ....... ". .. . . . . . . . . . . ...... . .'"°;""°"•" , , °,, ''°•,o,. °,•• °• °.. . . . . . . ........
.. . . ................. .. ......... ..... :•. .: .' ....... .................. :
S....~~~~...... .. . . ............. ,° o*o • ,•° . .... .... ...
° ", . .. • •° °¢ ° ; °.o. ° ° o . ...... o ... o.. . . . . . . .. . . . . . . . ... .... . . . . . . . . . . . .o. .o.. . . . . . . . .,,.
3 4 5 6 7 10-1 2 3 4 5 6
Time Step Size (sec)
NRC Presentation November 1, 2000. Slide 13 f% co�.tou�
49.3
49.2
49.1
49.0
48.9
48.8
48.7
48.6
48.5
48.4
0.)
C
0) 0©
48.3
10-2 2
NRC Presentation November 1, 2000 Slide 13 r% P-t-0.0
,A-: ; : i j - - ! - - , :;::,1+0.I°Z
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Nodalization of RCS and Steam Generator
I • . -.I I -.
C
-J
•, II_ <= Ir")I .. "-r • P O
- L .... ........ ... I.... I..... •
I~ L
I I L J Im - I
L -_
NRC ~ ~ ~ ~ ~ ~ ~ ~ ~~~( PrsnainNvme , 00 ld 4OCntollatioSNRC Presentation November 1, 2000, Slide 14
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Calvert Cliffs OTTCC Matrix
PORVs
___________ Chaging::, rump:: _ _ _ _ _ ______
X
3. I I I . 2X X
c c
X X
X X X
rr 2!I I2401
CU 13: 101
flTJ [3: 251 C1I 15: 51 CU 12: 451 CU 13: 301'', CU 2 CU (2: 401 CU [3: 251x
X
CU 13: 501
X CU 13: 301 CC+ I t -
x CU 13: 451 CC+ I 1 1
CU 15: 151 CC CC- _______________ . . I i
CU 13: 151
X CU 15: 101 CCI i .
x CU 15: 101 CC" ..... X c u - : .0 .
CU 141 CU [5: 401 CC
. . . . . . . . . . .............................,....:.:..:..........~...
OConstelnationNRC Presentation November 1, 2000, Slide 15
a ______________________ .
x
.. ......
........... ........... ........... ........... .......... ............ ............ ...........
A .. s . .....:.0 .. 1~~
x
X
X
3
CC
3iiiiiiiiiil ] :::0 : x
CCCCCCCC
CCCC
C.1 .....
............... E::::::::::::
ccCC
ccCC"
".................... .............. ..... .v.. .v........ ... ... ... ... ... .... ".b:.:•:.:,:.:q•:q.
I:
'X
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Nodalization of Integrated RCS and ContainmentI
L
L-- YI
NRC Presentation November 1, 2000, Slide 16w
I
i
l
co
ConsteNation KI-L..,