1 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
First Wind Turbine of Mongolia
2 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Model: 1.6-82.5 Cold Weather Technical Data (General)
Rated Capacity: 1.6 MW
Cut in Wind Speed: 3.5 m/s
Cut out Wind Speed: 25 m/s
Rated Wind Speed: 10.65 m/s
Rotor Diameter: 82.5 m
Hub Height: 80 m
Certification: IEC TC IIb Ve50 = 56 m/s
Climate Conditions: Cold Weather option
Operation: -30 C to +40 C (-22 F to 104 F)
Survival: -40 C to +50 C (-40 F to 122 F)
Noise Level: 106 db (A) average
3 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Installed 1.6-82.5 WTGS (total 1,709 up to end of 2012 )
Total 19627 Installed 1.X WTGS up to end of 2012
4 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Slide Number 4 LJIIB Technical Review
Date:July 20, 2010
1.6-82.5 Machine Head / Hub /Blades
5 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
1.6-82.5 Machine Head / Hub /Blades
Pitch System
• Independent for each blade
• Planetary gearbox, DC Motor with Battery Backup
Drive Train
• Mechanical Power: 1660 kW
• Gear Ratio: 1:85.7
• Operations Speeds: 800 – 1600 rpm
• Operation Speed @ Rated power: 1440 rpm
Generator
• Rated Power: 1.6 MW
• Rated Voltage: 690 V
• Frequency: 50 Hz
• Rated Speed: 1440 rpm
• Power Factor Range: + .95
Yaw Drive
• Actuation:4 Electrical Drives
• Yaw Rate: .5 degree / sec
• Voltage: 690 V / 50 Hz
Brake System
• Primary System: Individual Blade Pitch
• Emergency Brake: Hydraulic Disc Brake
Blades
•GE/LM 40.3P
• Material: Fiberglass & Epoxy or Polyester resin
6 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
SCADA & WindCONTROL Comm. Network
SCADA
Rack
Wind Control
(WFMS)
OPC Server
Software
Server
SQL
Server
Customer
Server
Remote
Connection
(Customer)
Substation
Substation
or
O&M Building
CTs & VTs
Step up Transformer
Remote
Connection
(GE)
Local Viewer
Pad
Mount
Pad
Mount
Pad
Mount
Pad
Mount
Pad
Mount
Pad
Mount
T1 Line
SCADA Rack in O&M Building SCADA Rack in Substation
Electrical Power
Fiber Optic
Ethernet
7 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
WindCONTROL
8 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Down Tower Electronics assemble
9 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Tower lifting
10 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Machine Head lifting
11 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Rotor Assembly
12 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Rotor lifting
13 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Turbine internal M&E work
14 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Installation Quality Control Document Flow
IIP
ICL
BBCICL
1.5Serie_xxHz_ICL_all
Comp_IIP.EN
VERIFY CORRECTS
TORQUE VALUES –TOOL
CERTS etc.
VERIFY MEASURMENT
REPORT (CE) IF Appl.
Phase /INS. INTEGRITY
TESTING TESTING
GROUND RESISTANCE
TEST
Quality Control
VERIFY GEN
ALIGMENT
Values
VERIFY FOUNDATION
DELIVERABLES
Mechanical completion Certificate
Contract specific Exhibit
VERIFY UNDERGROUND
FIBER OPTIC
COMPLETION
PUNCH LIST
CLOSED
Enter
documents in
Job Site Book
IIP PRE-CONDITIONS
CUSTOMER/GE
Commissioning
takes ownership
15 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Installation Quality Control Document Flow
IIP
ICL
BBCICL
1.5Serie_xxHz_ICL_all
Comp_IIP.EN
VERIFY CORRECTS
TORQUE VALUES –TOOL
CERTS etc.
VERIFY MEASURMENT
REPORT (CE) IF Appl.
Phase /INS. INTEGRITY
TESTING TESTING
GROUND RESISTANCE
TEST
Quality Control
VERIFY GEN
ALIGMENT
Values
VERIFY FOUNDATION
DELIVERABLES
Mechanical completion Certificate
Contract specific Exhibit
VERIFY UNDERGROUND
FIBER OPTIC
COMPLETION
PUNCH LIST
CLOSED
Enter
documents in
Job Site Book
IIP PRE-CONDITIONS
CUSTOMER/GE
Commissioning
takes ownership
16 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
PCAT (Pre Commissioning Acceptance Test)
This Procedure is the de energized portion of the WTG commissioning.
FCAT (Field Commissioning Acceptance Test) The FCAT is the step by step process to
energize the turbine.
CCT (CONVERTER COMMISSIONING TEST) After CCT test, turbine begins to produce
power
Turbine completion Certificate
Contract specific Exhibit
Customer takes
ownership
contract specific
PRT SCADA/WFMS ATP
Enter
documents
in Job Site
Book
Commissioning Quality Control Document Flow
17 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Experienced GE project team
most Team member: Education background: Mechanical or Electric bachelor +10 years work experience + 5 years wind project experience +1000 turbines Built and maintain Oversea project experience
18 JRI GLM
01/23/2014 GE Proprietary Information Unauthorized Disclosure and Use are Prohibited
Thank You For Your Presence