+ All Categories
Home > Documents > Sanitary Sewer Examplesewervue.com/case_studies/SewerVUE_Sanitary_Sewer_Sample_Report_V5.pdf · V5C...

Sanitary Sewer Examplesewervue.com/case_studies/SewerVUE_Sanitary_Sewer_Sample_Report_V5.pdf · V5C...

Date post: 26-Mar-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
9
Sanitary Sewer Example Reported Lines: MH1 – MH2 March, 2013
Transcript

Sanitary Sewer Example

Reported Lines:

MH1 – MH2

March, 2013

i

TABLE OF CONTENTS

PROJECT OVERVIEW .................................................................................... 1

OVERVIEW: MH1 – MH2 .............................................................................. 2

OBSERVATION REPORT MH1 – MH2 ............................................................... 3

OBSERVATION REPORT MH1 – MH2 ............................................................... 4

OBSERVATION REPORT MH1 – MH2 ............................................................... 5

DEBRIS GRAPH MH1 – MH2 ........................................................................... 6

CONTACT DETAILS ....................................................................................... 7

Tables Table 1: Project Overview ............................................................................................................... 1

Table 2: Project Summary ............................................................................................................... 1

Table 3: Overview: MH1 – MH2..................................................................................................... 2 Table 4: Summary: MH1 – MH2 ..................................................................................................... 2

1

PROJECT OVERVIEW

Table 1: Project Overview

PROJECT OVERVIEW

Project Name Storm Drain Example

Profiler System FlySwatter System – LiDAR, Sonar, HDCam

Client Example City

Contractor Cues Inc.

Data Processing SewerVUE Technology Corp.

Date Profiled February 2013

Date Reported March 2013

Table 2: Project Summary

PROJECT SUMMARY

Asset No. Distance

Profiled Debris ft

3 Diameter

MH1 – MH2 543.3 ft 1074.60 66x69”

Totals 543.3 ft 1074.60 -

2

OVERVIEW: MH1 – MH2

Table 3: Overview: MH1 – MH2

OVERVIEW: MH1 – MH2

Asset No MH1 – MH2 Date Installed –

Survey Start MH1 Material Concrete

Survey End MH2 Size 66x69”

Survey Direction Downstream Location Example City

Table 4: Summary: MH1 – MH2

SUMMARY: MH1 – MH2

Distance Observation Comment

8.7 ft Survey Start MH1

8.7-15.0 ft Deep sediment Calculated from Sonar data

176.7 ft Visible pipe loss Verified by LiDAR

270.0 ft Deep sediment Calculated from Sonar data

327.0 ft Varied pipe loss Calculated from LiDAR data

458.5 ft Significant pipe loss Calculated from LiDAR data

464.1 Visible anomaly at 12 o’clock Verified by LiDAR

552.0 ft Survey End MH2

3

OBSERVATION REPORT MH1 – MH2

MH1 – MH2

Clo

ck p

ositi

on

Pipe location [ft]

Visible pipe loss

Pipe loss with a visible “island”

Fluid level

Debris

Original pipe wall

Pipe wall

Pipe loss [in]

-10 -8 -6 -4 -2 0 2

20 40 60 80 100 120 140 160 180 200

3

69

12

Deep sediment

6

-40 0 40

-40

0

40

4

OBSERVATION REPORT MH1 – MH2

MH1 – MH2

Deep sediment

Varied pipe lossC

lock

pos

ition

Pipe location [ft]

200 220 240 260 280 300 320 340 360 380 400

3

9

Fluid level

Debris

Original pipe wall

Pipe wall

Pipe loss [in]

-10 -8 -6 -4 -2 0 2

6

12

6

-40 0 40

-40

0

40

5

OBSERVATION REPORT MH1 – MH2

MH1 – MH2

Clo

ck p

ositi

on

Pipe location [ft]400 420 440 460 480 500 520 540

3

9

Significant pipe loss

Visible anomaly at 12 o’clock

Fluid level

Debris

Original pipe wall

Pipe wall

Pipe loss [in]

-10 -8 -6 -4 -2 0 2

6

12

6

-40 0 40

-40

0

40

6

DEBRIS GRAPH MH1 – MH2

Clo

ck p

ositi

on

MH1 – MH2

Variation of fluid level

Variation of debris depthmaximum

Pipe diameter

Pipe location [ft]

50 100 150 200 250 300 350 400 450 500 550

3

9

Pipe loss [in]

-10 -8 -6 -4 -2 0 2

Variation of maximum pipe loss

6

12

6

0 40 80 120 160 200 240 280 320 360 400 440 480 520 560

0

20

40

60

80

7

CONTACT DETAILS

Csaba Ekes [email protected]

4650A Dawson St Burnaby

British Columbia V5C 4C3 Canada

888-973-9378

The information contained in this Report is provided for interpretation by suitably qualified civil engineering professionals engaged by the Client. This Report is not intended and must not be taken to be professional civil engineering advice, nor shall it be relied upon as a substitute for professional civil engineering advice.

Interpretation of this Report, evaluation of the pipelines, and any rehabilitation, investigative, cleaning or other decisions are the sole responsibility of the Client.

Certain information contained in this report such as distances and dimensions may incorporate information provided by others. This information may not always be accurate and complete. The Engineer should make their own assessments with regards to such information.


Recommended