PLANNING& BUILDING
AGENCY
SANTAANA
CITY OF
APPLICABLE BUILDING STANDARDS: 1. 2013 California Plumbing Code (CPC) 2. 2008 California Energy Code (Title24, Part 6) 3. 2013 California Building Code (CBC) 4. Santa Ana Municipal Code 5. City of Santa Ana Citywide Design Guidelines
RESIDENTIAL WATERHEATER INSTALLATION
Page 1 of 4Rev: 10/20/2014
PLB-02 CPC 2013
THE PERMIT APPLICANT SHOULD CHECK WITH THE PLANNING DIVISION FOR SHED CONSTRUCTION MATERIAL REQUIREMENTS AND SUBMIT A SITE PLAN SHOWING EXACT LOCATION OF THE SHED ON THE PROPERTY.THE PLANNING DIVISION’S APPROVAL IS REQUIRED PRIOR TO THE ISSUANCE OF BUILDING AND PLUMBINGPERMITS
WINDOW OR OTHER OPENINGINTO THE BLDG.
BUILDINGWALL "0-'4
MU
MINI
M
8'-0"MINIMUM
LC U.L. LISTEDVENT CAP
STORM COLLAR
SHEET METAL FLASHING
1" MINIMUM CLEARANCE BETWEEN VENTAND ANY COMBUSTIBLE MATERIAL
MINIMUM 3" DIA.U.L. LISTED B-VENT (DBL-WALL)
UPPER COMBUSTION-AIR MIN. 50 SQ. IN.
AN APPROVED PRESSURE AND TEMPE-RATURE RELIEF VALVE IS REQUIRED.TERMINATE THE DISCHARGE PIPE NO MORE THAN 24" OR LESS THAN 6" ABOVE THE GROUND. DO NOT REDUCE PIPE SIZE. TPR DRAINLINE SHALL BE METAL FOR INTERIOR WATER HEATER INS-TALLATION (IN-HOUSE OR GARAGE) DRAINLINE SHALL EXTEND TO EXTERIOR OF BUILDING. PROVIDE 1/4" PER FOOT FALL ON DRAIN LINE
MINIMUM 12"ABOVE ROOF
APPROVEDFULL OPENING
SHUT-OFF VALVE
COLD
HOT
UNIONS (TYP)H C
A LISTED APPLIANCE VALVE WITH
FLEX-CONNECTOR,MAX. LENGTH
36"
GASGAS PIPING MAY REQUIRE A10# AIR TEST. CHECK WITH FIELD INSPECTOR
LOWER COMBUSTION-AIR MIN. 50 SQ. IN.
UP
VENT CONNECTOR PIPE APPROVEDINSIDE THE ENCLOSURE ONLY
WATER HEATER SHALL BE ANCHORED OR STRAPPED TO RESIST HORIZONTAL DISPLACEMENT DUE TO EARTHQUAKE MOTION. REFER TO THE ILLUSTRATIONS ON PAGE 2. THE PERMIT APPLICANT SHALL BE RESPONSIBLE FOR THE ACTUAL DESIGN OF EARTHQUAKE RESTRAINTS.
LEVEL CONCRETE SLAB
MINIMUM 5'-0"
APPROVEDRIGID METAL
BRACKETUP
1" MINIMUM FROM COMBUSTIBLES
FLEXIBLE WATER CONNECTION
FLEXIBLE GASCONNECTION
9''+-
4''+
1 3/4''
1 3/4''
APPROVEDSTEEL STRAPS
Planning & Building AgencyBuilding Safety Division20 Civic Center PlazaP.O. Box 1988 (M-19)Santa Ana, CA 92702(714) 647-5800www.santa-ana.org
CONTROLS3" MINIMUM UNLESS LOCATED IN GARAGE THAN ALL BURNERS AND IGNITION DEVICES MUST BE AT LEAST 18" ABOVE THE FLOOR. REFER TO NOTES ON PAGE 4 OF 4.
Tankless water heater requirements on reverse side
Page 2 of 4
2X4 STUD
2X4
EXTRA SPACER OF WOOD NAILED TO 2X4 TO CREATESNUG FIT BETWEENTANK AND WALL
ALTERNATE SECTION A-A
IF TANK HAS AN INSULATIONBLANKET, LEAVE IN PLACE
A APPROVED STEEL STRAPSSNUGGLY WRAPPED AROUND TANK AND SNUG SPACERPROVIDED BETWEEN THE WATER HEATER AND WALL
THIS SYSTEM MAY BE USED TO ANCHOR A HOT WATERHEATER THAT IS ADJACENT TO A WALL. TANK FEET NEEDTO BE BOLTED TO THE FLOOR AND THE HEATER HOOKEDUP WITH A FLEXIBLE GAS CONNECTION.
A
2X4 ATTACHEDWITH 16D NAILS
APPROVED STEEL STRAPS ATTACHED WITH 16D NAILS TO 4X4 POST
ALTERNATE METHODOF BRACING FORFREE STANDING WATER HEATER
2X FRAMING MEMBER
STEEL ANGLEBRACKETS
4X4 POST
SNUG SPACER REQUIREDBETWEEN THE WATERHEATER AND THE WALL
2X4 STUD
1/4" X 4 1/4" LAGSCREW WITH WASHER(FOR CONCRETE WALLS,SUBSTITUTE 1/4" EXPANSION BOLTSFOR SCREWS)
SECTION A-A
TANKLESS WATER HEATERSTankless water heaters are becoming a popular, energy-efficient replacement for standard tank-type heater. When installing a tankless water heater there are many things to consider.
The following items will need to be provided to the inspector at the time of the initial water heater inspection:
Manufacturer’s installation instructions often require special venting materials and specific installation practices.
Most installations require larger combustion air openings/ducts to be installed.
Typical tankless water heater gas demands require gas pipe sizes to be significantlyincreased or additional dedicated piping, from the gas meter to the water heater, to be installed.
Water heater and venting material manufacturers’ installation instructions.Calculations/drawings for the increased gas demand.
CAUTION:
NOTE:
BEWARE:
1.
2.
Street Street
CITY OF SANTA ANA CITYWIDE DESIGN GUIDELINES
APPROPRIATE
APPROPRIATE
INAPPROPRIATE
INAPPROPRIATE
1. Mechanical equipment such as air-condition units, utility meters, transformers, water heaters, satellite dishes, etc. may not be located on the front elevation.
2. On new homes or when additions are proposed, water heaters should be located within a building's foot print.
3. Water heater enclosures are discouraged. When used, enclosures should be architecturally compatible with the primary structure and fully enclosed.
4. Solar panels should not directly face to the street and should be installed in recesses into the roof structure whenever possible. Solar panels should be fully integrated into the roof structure.
5. When possible, consider the installation of solar panels on accessory structures, patios or ground mounted in the rear yard, away from the public view.
Figure 6-49: Locate accessory structures to the rear of a property
Figure 6-50: Water heater enclosures should be architecturally compatible with the house.
Page 3 of 4
Page 4 of 4
(1) Gas utilization equipment in residential garages and in adjacent spaces that open to the garage and are not part of the living space of a dwelling unit shall be installed so that all burners and burner-ignition devices are located not than less 18 inches above the floor unless listed as flammable vapor ignition resistance.
(2) Such equipment shall be located or protected so it is not subject to physical damage by a moving vehicle.
NOTES: CPC Installation in Residential Garages
(3) When appliances are installed in a separate, enclosed space having access from only out-side of the garage, such equipment may be installed at floor level, providing the required combustion air is taken from the exterior of the garage.
Combustion and ventilation air shall be provided and installed in accordance with Section 506.0.