Business Process Master List (BPML) Management Guide Version 1.0 • December 2003
Transcript
Page 1: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 • December 2003

Page 2: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

2

Document Information

Abstract The Business Process Master List (BPML) is a key tool for use in implementations to capture the scope of the project, drive the planning and managing of configuration and testing. This document is an overview of what a BPML is and how to use and manage it in an implementation. The following pages were provided by a large COTS user and reflect their process for using the BPML.See also the sample BPML included in the EI Toolkit.

File Name bpml_mgmt_guise.ppt

Document Name Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Date Last Validated

September 2004

About this Document

Use Policy

This document was created to be used as a reference, sample or template. Contents of the EI Toolkit should not be repurposed for publication in copyrighted material. This policy applies to all contents unless otherwise specified in a particular document.

Document Change History

Version Reason for Change Date

0.0 Created for use by commercial industry customer #2 March 2001

1.0 Submitted for use in EI Toolkit December 2003

Page 3: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Table of Contents

Overview Objectives Utilization File Explanation Organization, Roles and

Responsibilities Updates Management

Page 4: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Overview

Business Process Master List (BPML) is An excel worksheet containing Latin America Business Processes configured in SAP R/3

The BPML was originally created in the ASAP tool through the utilization of the Project Scooping module, and adapted to Colgate business practices by the Jaguar team

Since then, the BPML is the Back-Bone of Jaguar Project as it is used in all project phases

Page 5: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Overview

BPML is enriched after each implementation with the new functionality delivered to the subsidiary

Page 6: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Objectives

Repository of Colgate Latin America Business Processes, Practices and Variants

Repository of Country Specific Functionality

Configuration and Test Management

Support other Key Project Activities, such as, Change Management and Security

Page 7: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Utilization

The BPML is used through out the implementation phases to support key project activities, such as: Implementation Team Training Business Workshops Business Variants Documentation Configuration Management GAP Analysis Integration and Day in the Life Tests Security Roles & Responsibilities.

Page 8: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationImplementati

on Team Training

Implementation Team is trained to execute all business processes supported by the Latin America Application Framework

As well as the business logic behind each piece of configuration

Therefore, the BPML is used as training program

Page 9: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationBusiness

Workshops

Implementation team presents to Subsidiary Management all the Business Processes configured in the Latin America Application Framework

The BPML is used to build up the BW-Agendas and therefore a business cycle sequence

Page 10: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationBusiness Variants

Implementation team has to identify and document all the Business Variants that occurs in their Subsidiary Processes

These Business Variants are documented in the BPML and Used: By the Core Team to track Configuration By the Implementation team to duplicate Subsidiary

Business Process in SAP R/3With this approach both Configuration and

Testing activities are efficiently managed and implementation progress objectively measured

Page 11: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationBusiness Variants

All Business Variants are documented in the MASTER LIST section of the BPML in RED

The Core Team MARKS the functionality and business variants that will be available for a giving configuration Cycle

Implementation team generates the test cycle from MASTER LIST

Implementation team prints out the cycle n from C n section

Implementation team assign testers in Cycle n

Page 12: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Utilization Business Variants

Implementation team documents test results in Cycle n section If Variant is successfully tested and approved by end

users, it is marked in Blue in both Master List & Cycle n Sections And the OK Word in TESTING DATE / Column ACTUAL

Page 13: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationBusiness Variants

Implementation team document test results in Cycle n section If Variant or Business Process Procedure-BPP are not

successfully tested, error is documented in Integration Test Tracking Sheet-ITTS and BPP or Variant will remain in RED

And the ERROR ID in TESTING DATE / Column ACTUAL

Page 14: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Utilization Configuration

Management

The Core Team delivers subsidiary configuration in a specific dates along the implementation calendar, these dates are identified as Configuration Cycles in the High Level Plan

The MASTER LIST sheet has a FINAL CONFIGURATION CYCLES section with Four C columns that represents Configuration Cycles

Core Team Leaders marks with an X the configuration / variants that will be delivered in each configuration cycle

Page 15: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationGAP

Analysis

Once the Configuration available for each cycle is identified the implementation team documents the corresponding business variants

During GAP Analysis implementation team develops the necessaries business conditions to replicate their business processes in SAP R/3, AND

Evaluate the FIT of the Latin America Application Framework in their business

Page 16: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationIntegration

Tests

After GAP Analysis, there will be several integration test, each of them with specific objectives

IT-Agendas will be based in functionality / business variants available for a giving cycle

BPML will be used to keep teams focus to achieve test objectives

Page 17: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

UtilizationSecurity

In the Area of Security the BPML is used to document all the transactions that are used for a specific profile.

The BPML assures no T-Code is missing for a specific role

Page 18: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Utilization Roles &

Responsibilities

End user procedures and business procedures defined and linked

Job roles assignedMay be linked to Security profiles

Page 19: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Area:This column is used to identify the Functional Area of the Business ProcessesExample: Finance

Sample BPML

Page 20: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Scenario: This column is used to identify the Scenario in which The Business Processes are Involved.Example: Contract Manufacturing

Sample BPML

Page 21: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Group: This column is a sublevelOf the scenario, used to Classify several process with the Same objective.

Sample BPML

Page 22: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Process: This column is a sublevelOf the Group, used to identify Business processes.

Sample BPML

Page 23: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Business Process Procedure: This column, used to identify the specific tasks within a processThat have a particular T-Code on The System.

All business variants have to be documented in the Master ListSection of the BPML that are involved in the Process.

Initial variants in color RED

Variants tested and approved in color BLUE in the Master List Section

Sample BPML

Page 24: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Code: This column, used to document the T-Codes of SAP for their own BPP

These are not to be modified

Sample BPML

Page 25: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Consultant: This column, used to assign aConsultant that is responsible For the specific Business process

These column is to be updated By the core team.

Sample BPML

Page 26: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Owner: This column, used to assign aCP Person that is responsible For the specific Business process

These column is to be updated By the implementation team.

Sample BPML

Page 27: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

C1: This column, used by the core teamto mark which business processes are in scope to be tested on the specific cycle C”n”.This will be used to generate the Cycle “n” Worksheet.

Sample BPML

Page 28: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

C1 worksheet: After identifying the scope of The testing cycle and you Generate the worksheet, here Is were you find the worksheet

Sample BPML

Page 29: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

C1 Worksheet: This is how the testing scope Worksheet looks like, you have the same process structure (area, scenario group, process,BPP & T-Codes this are to be generated Automatically.

The Testing Dates column should be updated after each process or variant is tested and signed off.

Sample BPML

Page 30: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

C1 Worksheet:

The Tester column is the Person responsible to test the specific Process

This is updated by theImplementation team

Business Variants tested OKWill be Marked “OK”inTESTING DATES / Column ACTUAL in Section C1 of the BPML

Variants with error will remain in RED in bothMaster List and C1

Sample BPML

Page 31: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Organisation, Roles and Responsibilities

Page 32: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Organisation

FunctionalTeams

Technical &Security Team

Change Team

FunctionalTeams

Technical &Security

Core Team

Subsidiary Team

Core TeamLeader

BPML Coordinator

Subsidiary Team Leaders

Change Team

Page 33: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Organisation : Roles and Responsibilities

BPMLCoordinator

Receive changes from all teamsEnsure BPML structure integrityEnsure teams complete only their area of

responsibility Publish & ensure all teams work with the

latest version of the BPML

Page 34: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Organisation : Roles and Responsibilities

Core Team Leaders

Responsible to document system configuration in a Business Process format in the BPML document

Maintain up-to-date the BPML with all new developments and configuration status

Report new configuration / documentation to BPML coordinator

Page 35: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Organisation : Roles and Responsibilities

Subsidiary Team Leaders

Ensure team members : Maintain Business Variants Update business variants after Integration or

Day in the Life Tests Maintain file structure Work with the latest version

Page 36: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Organisation : Roles and Responsibilities

Functional Team

Document Business Variant Update Business Variants Test Status

after Integration and Day in the Life Test Report BPML changes to functional team

leader

Page 37: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Maintenance Process Since the BPML is used & updated by different people a

central coordination is mandatory to ensure file integrity, AND

Set of rules to maintain its utilization synchronizationEvent Responsible

New BPP in BPML File Core Functional Team Configuration in Cycle n Core Team Leader Documentation of Business Variants Implementation

Team Testing Activities and Status Implementation Team Users Profiles Security Team Training Classes/Roles Change Team Communication of updated BPML BPML Coordinator

Page 38: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Management : Updating Approach

BPML update conditions and responsibilities : Core Configuration Team

Translate new functionality into BPML Business Processes Update configuration status Communicate updates to Core Team Leaders

Core Team Leaders

It is controlled centrally by the BPML Manager : The Core Team might update the BPML in this events

Include a new process New Transaction Identify process to be tested in specific cycles

The subsidiary might update the BPML in this events: Include new Business Variants Assign Owner of the Process Update the Tested Variants

Page 39: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Maintenance Flow - Core Team

Page 40: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Manage Control

Core Team: Configure or Modifies a Process

1.- CT Configure or Modifies a process

2.- CT fills up anUpdate form

3.- CT sends form to Team Leader

for authorization

4.- CT Leader Authorize update

5.- CT Leader Emails form to

BPML coordinator

6.- Updates BPML According to form

7.- Emails notification of New BPML

version on DB

Consultants

Subsidiary

Teams

Core Team

Leaders

Project Managers

Core Team Core TeamLeader

BPML Coordinator

Page 41: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Manage Control

Core Team: Identifies or Modifies a T-Code

1.- CT Identifies or Modifies a T-Code

2.- CT fills up anUpdate form

3.- CT sends form to BPML coordinator

with copy to CT Leader

6.- Updates BPML According to form

7.- Emails notification of New BPML

version on DB

Consultants

Subsidiary

Teams

Core Team

Leaders

Project Managers

Core Team

Core TeamLeader

BPML Coordinator

Page 42: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Manage Control

Core Team: Identifies Cycle ”N” for IT.

1.- CT Identifies processes for

cycle “n” in BPML

2.- CT sends BPML to Team Leader

for Review

3.- CT Leader Reviews BPML

5.- CT Leader Emails form toBPML manager

6.- Updates OfficialBPML

7.- Emails notification of updated BPML version on DB

Consultants

Subsidiary

Teams

Core Team

Leaders

Project Managers

Core Team Core TeamLeader

BPML Coordinator

Page 43: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Maintenance Flow - Implementation Team

Page 44: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Manage Control

Subsidiary Team: Identifies Business Variant.

1.- Sub Identifies a Business Variant

for a process 7.- Emails notification

of updated BPML version on DB

Consultants

Subsidiary

Teams

Core Team

Leaders

Project Managers

Subsidiary Subsidiary Team Leader

BPML Coordinator

3.- Sub sends form to Sub Team Leader for authorization

2.- Subsidiary fills up an Update form

4.- Sub Leader Authorize update

5.- Sub Leader Emails form toBPML manager

6.- Updates BPML According to form

Page 45: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Manage Control

Subsidiary: Identifies an Owner of a Process

1.- Subsidiary Identifies or

Modifies a T-Code

2.- Subsidiary fills up aBPML

3.- Subsidiary sends File to BPML

manager with copy to Sub Leader

4.- Updates OfficialBPML

5.- Emails notification of updated BPML version on DB

Consultants

Subsidiary

Teams

Core Team

Leaders

Project Managers

Subsidiary

SubsidiaryLeader

BPML Coordinator

Page 46: SAP BPML

Business Process Master List (BPML) Management Guide

Version 1.0 December 2003

Manage Control

Subsidiary Team: Indicate Tested B. Variants

1.- After IT, results of BVariants test will be in the BPML colored

accordingly.

2.- Subsidiary sends file, to BPML

Manager with copy to IT coordinator

4.- Updates OfficialBPML

5.- Emails notification of updated BPML version on DB

Consultants

Subsidiary

Teams

Core Team

Leaders

Project Managers

Subsidiary

IT Coordinator

BPML Coordinator


Recommended