© 2009 Wellesley Information Services. All rights reserved.
Implement SAP ERP Consumption-Based Planning Functionality for Your Non-Critical Production Materials
Isaac MazliachS.D.M. Consulting
3
In This Session ...
• The purpose of this session is to tackle Consumption-Based Planning (CBP) from its business perspective as it pertains to differing MRP methodologies. And then — go through its configuration settings.
4
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
5
General
• CBP is a branch of MRP dealing with all those materials whose planning is a function of their consumption, as opposed to how much is currently needed for production or to fulfill customer demand
• In accordance with the above, we will use CBP for less expensive, less critical components. That is, those less expensive components that we usually purchase from external vendors (e.g., nuts and bolts).
8
A Word About SAP Supply Chain Management (SCM-APO)
When should you use CBP and when should we use SCM-APO?
9
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
10
Categorization
• Categorization of products is about defining the delivery time and the delivery service for each of the products in the product program. Categorization of the products is made from a categorization of the customers and the products they buy.
• Subsequently the categories for the finished products are then linked to the semi-finished and the raw materials respectively, and later also to suppliers
• With categories at each level it is possible to create a very efficient supply chain
• Product Categorization gives a superb basis for implementing Lean Manufacturing, by clearly showing the product priority when it comes to flow, inventory, planning, etc.
11
ABC Approach
• One of the common practices for categorizing materials is the ABC approach
• In principal, the ABC approach says: Categorize your materials according to the following simple rule: A – “A” materials are the most expensive and critical materials
in your organization B – “B” materials are the less expensive, less critical materials
in your organization C – “C” materials are the non-expensive, non-critical materials
in your organization
12
When to Use CBP
• CBP deals primarily with the “C” materials that we purchase• One of the purposes of CBP is to create Purchase Orders as
automatically as possible in order to reduce manual intervention in the purchase process
• It is possible to use transaction MIBC (ABC Analysis for Cycle Counting) as a basis for ABC categorization. However, it does not take into account the criticality of the material, and therefore manual work must still be performed.
13
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
14
General
• Reorder point planning should be used with relatively constant consumption materials
• If the material’s consumption is not constant over time, this method might result in excess stock (the need to keep high safety stock) or stock shortage (fluctuations)
15
Methodology
Reorder point quantity includes safety stock. The PO quantity depends on the lot size (e.g., fixed).
16
Calculation
MRP compares the quantity in stock + PRs + POs to the reorder point. There is a shortage if the total quantity is lower than the reorder point.
18
Forward Scheduling
CBP calculates the availability date depending on lead times from today’s date
20
Planning Based on Past Consumption
• Planning based on past consumption should be used for materials whose future behavior can be predicted by their past consumption
• Materials with short life cycle would therefore probably not be a good choice for planning using this method
• Good candidates for planning using this method might be materials with relatively many consumption periods
21
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
22
General
• Time-phased planning should be used for materials that are delivered on specific dates
• This method works similarly to reorder point planning — the difference is that specific delivery dates are taken as parameter
• To run this method, a specific calendar must be created and maintained
Methodology
Time-phased planning works almost the same way as reorder point planning, only with specific GR dates
25
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
26
General
• Forecasting can be used to: Predict future consumption values from old ones Calculate safety stock Calculate reorder points
32
Backward Scheduling
Forecasting calculates the date when we should start purchasing according to the requirement date
34
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
40
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
42
Configure CBP Forecast Views:Start by Activating the Material Master MRP (cont.)
• There are other IMG activities for all that is on the screen, but all can be configured in a one-stop shop
43
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
50
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
53
What We’ll Cover …
• Main differences between MRP and CBP• Materials categorization — the ABC approach• Reorder point planning; planning based on past consumption• Time-phased planning• Forecasting• Plant MRP and MRP areas• Illustration: Customizing plant parameters • Illustration: Customizing MRP types and lot sizes• Illustration: Customizing MRP areas• Wrap-up
54
Resources
• SAP courses – www.sap.com/usa/services/education/index.epx SAPSCM - Supply Chain Management Solution Overview SCM525 - Consumption-Based Planning and Forecasting
• http://help.sap.com Consumption-Based Planning (MM-CBP)
http://help.sap.com/saphelp_erp60_sp/helpdata/en/7d/c2821c454011d182b40000e829fbfe/frameset.htm
• Product Categorization (ABC categorization) www.flexinfonet.com/setprice.asp?page=34
55
7 Key Points to Take Home
• Categorize your materials• Use CBP for your “C” components• Materials with relatively constant consumption should be planned
with reorder point planning• Materials with numerous consumption histories may make use of
forecasting to predict their future consumption• Materials with specified delivery dates may use time-phased
planning• Forecasting may be used also to calculate safety stock and
reorder points according to past consumption figures• Creating a new MRP type can be useful to control customized
planning methodology as combination of “standard” methods
57
Disclaimer
SAP, R/3, mySAP, mySAP.com, xApps, xApp, SAP NetWeaver®, Duet™, PartnerEdge, and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and in several other countries all over the world. All other product and service names mentioned are the trademarks of their respective companies. Wellesley Information Services is neither owned nor controlled by SAP.