    Configuration Document SAP PP-PI Page 1 of 75 Version 1.0

    Claris Lifesciences Ltd.

    mySAP ERP ECC 6.0 Implementation

    PP PI Configuration Documentation

  • 5/22/2018 SAP PP Configuration Document

    2/75

    Configuration Document SAP PP-PI Page 2 of 75 Version 1.0

    Table Of Contents

    1. PURPOSE OF THE DOCUMENT........... ............. ............. ............. .............. ............. ............ .............. ..... 5

    1.1 Purpose ................................................................................................................................................ 5

    2. PRODUCTION PLANNING..................... ............. ............. ............. .............. ............. ............ .............. ..... 6

    2.1 Define MRP Controller............. .............. ............. .............. ............ .............. ............. ............ .............. . 62.2 MRP Type ............ ............. .............. ............ .............. ............. ............ .............. ............. .............. ......... 7

    2.3 Lot Size.......... .............. ............. ............ .............. ............. .............. ............ ............. .............. ............. ... 8

    2.4 Defining MRP Groups ............. ............ .............. ............. .............. ............ ............. .............. .............. .. 9

    2.5 Defining Special Procurement Type .............. ............. ............ .............. ............. .............. ............ .......10

    2.6 Define Scope of Planning for Total Planning............. ............ .............. ............. .............. ............ .......11

    2.7 Scheduling Parameters ............ ............ .............. ............. .............. ............ ............. .............. ............. ..12

    2.9 Define Scheduling Margin key..... .............. ............. ............ .............. ............. .............. ............ ...........13

    2.10 Selection ID for BOM ........... .............. ............. ............. ............. .............. ............. ............ .............. ....14

    2.11 Defining BOM Explosion............. .............. ............. ............ .............. ............. ............ .............. ...........152.12 Define Number Ranges for Planned Independent Requirements ............. ............. ............ .............. ....16

    2.13 Define Version Numbers ........... .............. ............. .............. ............ .............. ............. ............ ..............16

    2.14 Defining Strategy for MRP ............. ............ .............. ............. ............ .............. ............. .............. ........18

    2.15 Define Strategy Group ............. ............ .............. ............. .............. ............ ............. .............. .............. .18

    2.16 Define Planning Horizon ............. .............. ............. ............ .............. ............. ............ .............. ...........19

    2.17 Defining Availability of Stock ............. ............. ............. ............. .............. ............. ............ .............. ....20

    2.18 Defining Rescheduling Check for Plant and MRP Group..................... ............. .............. ............ .......21

    2.19 Define Number ranges for Planning Run................ ............ .............. ............. ............ .............. ...........22

    2.20 Planning File Entry for Termination .......... .............. ............. ............ .............. ............. .............. ........23

    2.21 Maintain Rounding Profile ............. ............ .............. ............. ............ .............. ............. .............. ........24

    2.22 Define Storage location MRP per plant...... .............. ............. ............ .............. ............. .............. ........25

    2.23 Defining Parallel Processing for MRP .............. ............. .............. ............ ............. .............. .............. .26

    2.24 Assigning MRP Checking Rule ............ .............. ............. .............. ............ ............. .............. ............. ..27

    2.25 BOM Usage............. ............. ............ .............. ............. ............ .............. ............. .............. ............ .......28

    2.26 Defining Item Categories ............. .............. ............. ............ .............. ............. ............ .............. ...........29

    2.27 Define Reasons for Variances...... .............. ............. ............ .............. ............. ............ .............. ...........29

    2.28 Define Number ranges for Manual Processing................... .............. ............. ............ .............. ...........30

    2.29 Activating Requirements Planning............. ............. ............ .............. ............. .............. ............ ...........31

    2.30 Defining Item Numbers of Order Types........... ............. ............. .............. ............. ............ .............. ....32

    2.31 Defining Conversion Planned Order to Process Order...... .............. ............. .............. ............ ...........33

    3. PRODUCTION PLANNING FOR PROCESS INDUSTRIES...............................................................35

    3.1 Define Resource Category ............ .............. .............. ............. ............ .............. ............. .............. ........35

    3.2 Defining Person Responsible for Work Centre............. ............. .............. ............. ............ .............. ....36

    3.3 Standard Value Keys...........................................................................................................................37

    3.4 Defining Formula Parameters for Resources ............. ............ .............. ............. .............. ............ .......38

  • 5/22/2018 SAP PP Configuration Document

    3/75

    Configuration Document SAP PP-PI Page 3 of 75 Version 1.0

    3.5 Defining Formula for Resources............. ............. .............. ............ .............. ............. ............ ..............39

    3.6 Task List Usage...................................................................................................................................40

    3.7 Define Capacity Planner........... .............. ............. .............. ............ .............. ............. ............ ..............41

    3.8 Define Number Ranges for Master Recipe.............. ............ .............. ............. ............ .............. ...........42

    3.9 Recipe Status.... ............. ............ .............. ............. .............. ............ .............. ............. ............ ..............43

    3.10 Recipe Usages.... ............. ............. .............. ............. ............ .............. ............. .............. ............ ...........43

    3.11 Define Planner Groups............ ............ .............. ............. .............. ............ ............. .............. ............. ..44

    3.12 Control key for Master Recipe ............ ............. ............. ............. .............. ............. ............ .............. ....44

    3.13 Define Capacity Categories............ ............ .............. ............. ............ .............. ............. .............. ........45

    3.14 BOM Status ............. ............. ............ .............. ............. ............ .............. ............. .............. ............ .......46

    3.15 Process Order Type ............. ............ .............. ............. ............ .............. ............. .............. ............ .......47

    3.16 Number Ranges for Process Order............. ............. .............. ............ .............. ............. .............. ........47

    3.17 Define Production Scheduler.............. ............. ............. ............. .............. ............. ............ .............. ....48

    3.18 Define Production Scheduler Profile............. ............. ............ .............. ............. .............. ............ .......49

    3.19 Scope of Check....................................................................................................................................503.20 Define Checking Control ............. .............. ............. ............ .............. ............. ............ .............. ...........51

    3.21 Define Scheduling parameters for a process order............ ............ .............. ............. ............ ..............52

    3.22 Defining Parameters for Order Confirmation ............ ............ .............. ............. .............. ............ .......53

    3.23 Assigning Material Types to Task List............. ............. ............. .............. ............. ............ .............. ....54

    3.24 Define Material Types Allowed for BOM Header.................. ............ .............. ............. .............. ........55

    3.25 Defining Order Type-Dependent Parameters.... ............. .............. ............ ............. .............. ............. ..56

    3.26 Assigning Process Instructions to Control Recipe Destinations.... .............. ............. ............ ..............57

    4. BATCH MANAGEMENT.........................................................................................................................59

    4.1 Activate Document Management for Batches ............. ............ .............. ............. .............. ............ .......594.2 Defining Batch Level............. .............. ............. ............. ............. .............. ............. ............ .............. ....59

    4.3 Activating Automatic Batch Number Assignment .............. ............ .............. ............. ............ ..............59

    4.4 Maintain Internal Batch Number Assignment Range.................... ............ ............. .............. ............. ..60

    4.5 Define Batch Creation for Production Order / Process Order..... ............ ............. .............. ............. ..60

    4.6 Define Process Order Condition Tables............ ............. .............. ............ ............. .............. ............. ..61

    4.7 Define Process Order Access Sequences ............. .............. ............ .............. ............. ............ ..............61

    4.8 Assign Search Procedure to Process Order and Activate Check............. ............. ............ .............. ....62

    4.9 Activating batch-specific Unit of Measures .............. ............. ............ .............. ............. .............. ........63

    4.10 Edit Batch-Specific Material Unit of Measure......... .............. ............ .............. ............. .............. ........634.11 Define Calculation of Proportion Quantity from Base Quantity ............. ............. ............ .............. ....64

    4.12 Maintain Period Indicator ............ .............. .............. ............. ............ .............. ............. .............. ........64

    4.13 Activating Expiration Date View per Plant............. ............ .............. ............. .............. ............ ...........65

    4.14 Define Process Order Strategy Types.............. ............. ............. .............. ............. ............ .............. ....65

    4.15 Define Search Procedure to Process Order................ ............ .............. ............. .............. ............ .......66

    4.16 Activating Batch Derivation............. .............. ............. ............ .............. ............. .............. ............ .......67

  • 5/22/2018 SAP PP Configuration Document

    4/75

    Configuration Document SAP PP-PI Page 4 of 75 Version 1.0

    4.17 Define Derivation Events ............. .............. ............. ............ .............. ............. ............ .............. ...........67

    5. DOCUMENT MANAGEMENT ............ .............. ............. ............ .............. ............. .............. ............ .......68

    5.1 Define Number Ranges for Document Numbers............. .............. ............ ............. .............. ............. ..68

    5.2 Define Document Types ............ .............. ............. .............. ............ .............. ............. ............ ..............69

    5.3 Define Data Carrier........ ............. .............. ............. ............ .............. ............. ............ .............. ...........70

    6. CLASSIFICATION SYSTEM ............ .............. .............. ............. ............ .............. ............. .............. ........72

    6.1 Define Characteristics Groups ............ .............. ............. .............. ............ ............. .............. ............. ..72

    6.2 Define Characteristics Status.............. ............. ............. ............. .............. ............. ............ .............. ....73

    7. OTHER SETTINGS...................................................................................................................................74

    7.1 Check Units of Measurement .............. ............. ............. ............. .............. ............. ............ .............. ....74

  • 5/22/2018 SAP PP Configuration Document

    5/75

    Configuration Document SAP PP-PI Page 5 of 75 Version 1.0

    1. PURPOSE OF THE DOCUMENT

    1.1 PurposeThis document captures the required configurations details in SAP system to meet the business

    requirements as envisaged in the Design Stage (Business Blue Print Stage) for Project, Claris SAPImplementation Production Planning Module. The configuration steps have mappings to

    corresponding menu path to where the configuration has been done in the IMG (Implementation

    Guide).

    The documentation provides visibility to all project teams members on the proposed system settingsand changes. It is an important document for all future references in terms of system configuration. All

    future changes or updates to the system should be done based on this and the documentation updatedaccordingly.

    This volume contains details on the configuration requirements for the Production Planning module

    for Claris Life Sciences pertaining to Master Data

    This document should be read in conjunction with:

    1. Process definition document

    2. Key Data Structures

  • 5/22/2018 SAP PP Configuration Document

    6/75

    Configuration Document SAP PP-PI Page 6 of 75 Version 1.0

    2. PRODUCTION PLANNING

    2.1 Define MRP Controller

    Menu PathImplementation Guide for R/3 Customizing (IMG)ProductionMaterial

    Requirements Planning PlanningCheck MRP Types Out Overall

    Maintenance of Plant ParametersMRP Controller

    Transaction Code OPPQ

    Configuration

    Description

    The MRP controller is a person or a group of persons responsible for monitoringmaterial availability. MRP controller can be used to select the planning results

    per MRP controller.Every material that is relevant to the planning run must be assigned to an MRP

    controller in the material master record.

    For all the C&Fs and CAs agents treated as Plants, the MRP Controller

    would be Z01. For Manufacturing Plants, it is detailed below. For all other

    plants, 001 MRP controller is named as General

    Plant MRP Controller Description

    101 RM Injectables

    102 PPM Injectables

    103 SPM Injectables

    104 TPM Injectables

    105 Production Inj.

    106 Packing Inj.

    107 Engineering Inj.

    108 Lab Mat.Injectable

    109 HK & Admin

    1001

    110 Captive Consumptn

    101 RM Infusion

    102 PPM Infusion

    103 SPM Infusion

    104 TPM Infusion

    105 Production Inf.

    106 Packing Inf.

    107 Engineering Inf.

    108 Lab Mat.Infusion

    109 HK & Admin

    1002

    110 Captive Consumptn

    101 RM API102 PPM API

    103 SPM API

    104 TPM API

    105 Production API

    106 Packing API

    107 Engineering API

    108 Lab Mat. API

    1003

    109 HK & Admin

    1004 101 Utility for Clarion

  • 5/22/2018 SAP PP Configuration Document

    7/75

    Configuration Document SAP PP-PI Page 7 of 75 Version 1.0

    2.2 MRP Type

    Menu PathImplementation Guide for R/3 Customizing (IMG)ProductionMaterial

    Requirements PlanningMaster Data Check MRP Types

    Transaction Code SPRO

    Configuration

    Description

    MRP type to assign the procedure to be used to plan a material and to control,which MRP parameters can be, maintained for the material in the material

    master record. MRP type is assigned in the material master record

    The following MRP Types are used for Claris

    MRP type Description

    PD Normal MRP

    VB Manual Reorder Level Planning

    ND No Planning

    V1 Manual Reorder Level with External Requirements.

    M0 Master Production Scheduling

  • 5/22/2018 SAP PP Configuration Document

    8/75

    Configuration Document SAP PP-PI Page 8 of 75 Version 1.0

    2.3 Lot Size

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirements Planning Planning Lot-Size CalculationCheck Lot-

    Sizing procedure

    Transaction Code OMI4

    Configuration

    Description

    Lot-sizing procedures serve to calculate the procurement quantities, that is, the

    purchase order and production quantitiesWith the lot-sizing procedure we define how the order quantities are determined.

    A lot size defining the lot-sizing procedure is assigned to every material masterrecord applicable to materials planning. The lot size is defined in Customizing

    by the combination of the lot-sizing procedure and the lot-sizing indicator.

    Lot Size Key Description

    EX Lot for Lot Order Quantity

    FX Fixed Order Quantity

    WB Weekly Lot Size

    MB Montly Lot Size

  • 5/22/2018 SAP PP Configuration Document

    9/75

    Configuration Document SAP PP-PI Page 9 of 75 Version 1.0

    2.4 Defining MRP Groups

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production

    Materials Requirements Planning MRP Groups Carry Out Overall

    Maintenance of MRP Groups

    Transaction Code OPPRConfiguration

    Description

    In this step, we determine the MRP groups and we maintain the control

    parameters from a particular point of view. The MRP group groups certain

    materials together from the material requirements planning point of view toallocate them special control parameters for planning. These control

    parameters include the strategy group, the planning horizon and thecreation indicator for the planning run selection of the Process Order type

    automatically.

    PlantMRP

    GroupDescription

    1001 Demand for Domestic in

    Injectable

    1002 Demand for Exports in

    Injectable

    1003 In-house Production in

    Injectable

    1004 In-house Packing in Injectable

    1001

    1005 External Procurement

    1001 Demand for Domestic in

    Infusion

    1002

    1002 Demand for Exports in Infusion

  • 5/22/2018 SAP PP Configuration Document

    10/75

    Configuration Document SAP PP-PI Page 10 of 75 Version 1.0

    1003 In-house Production in Infusion

    1004 In-house Packing in Infusion

    1005 External Procurement

    2000 2001 Traded Products

    2002 Loan Licence

    2.5 Defining Special Procurement Type

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirements Planning Master Data Define Special Procurement Type

    Transaction Code SPRO

    Configuration

    Description

    In this step, we define the special procurement keys which as well as theprocurement type control the procurement and storage of a material.

    The special procurement type always refers to a procurement type.

    We can , also define how the system treats the material as a component duringthe BOM explosion using control indicators.

    Example 1 (special procurement keys without other indicators)

    The procurement type "external procurement" is defined for raw materials. If amaterial is to be procured via a consignment order, you assign the special

    procurement type "consignment" to the material in the material master record.

    Example 2 (special procurement keys with other indicators)

    A material appears in several BOMs as a component because it is assembled in

    finished products in in-house production. It is procured from an alternative plantif no dependent requirements exist for the material.

    The Special Procurement Keys are defined for the Manufacturing Plants

    and it has to be extended to the C&Fs, which are defined as plants

    Plant Special Procurement Key Description

    1001 ZB Stock transfer (Proc from 1002)

    1001 ZC Stock transfer (Proc from 1003)

    1002 ZA Stock transfer (Proc from 1001)

    1002 ZC Stock transfer (Proc from 1003)

    1003 ZA Stock transfer (Proc from 1001)

    1003 ZB Stock transfer (Proc from 1002)

    4500 ZD Stock transfer (Proc. From 4500)

    2000WA

    Stock transfer (Proc. From 2000)

  • 5/22/2018 SAP PP Configuration Document

    11/75

    Configuration Document SAP PP-PI Page 11 of 75 Version 1.0

    2.6 Define Scope of Planning for Total Planning

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionMaterials

    Requirement PlanningPlanningDefine Scope of Planning for total

    planning

    Transaction Code OM0E

    Configuration

    Description

    In this IMG activity, we define the scope of planning and the sequence of the

    organizational units to be planned. These are either plants or, if we have

    converted MRP to MRP at MRP area level, the MRP areas that we plan togetherin a total planning run.

    We enter the key for the planning run in the initial screen of the total planning

    run. The total planning run then carries out MRP for the plants or MRP areasdefined in the scope of planning. we can enter as many plants or MRP areas as

    we like in the scope of planning. We can also only enter one MRP area. MRP is

    then only carried out for one MRP area. If we have activated MRP for MRPareas, when we enter a plant, this includes all MRP areas of this plant.

    The Following Scope of planning has been defined for Claris

    Planning Scope Description

    CFWH C & Fs and Wareshouse

    MFG Mfg plants

    MRP Material Requirement Planning

  • 5/22/2018 SAP PP Configuration Document

    12/75

    Configuration Document SAP PP-PI Page 12 of 75 Version 1.0

    2.7 Scheduling Parameters

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionCapacity

    Requirements Planning Operations Scheduling Define scheduling

    parameters for planned ordersTransaction Code OPU5

    Configuration

    Description

    In this step we define the parameters for scheduling planned orders for eachplant, order type and production scheduler. This comprises the followingsettings:

    Scheduling levels (detailed-, production-rate and rough-cut scheduling)

    Date adjustment when deadlines are exceeded

    Scheduling control for detailed schedulingReduction

    Scheduling parameters for planning scenarios for long-term planning/simulation

    Scheduling Parameters for the Planned Orders are same for all the Plants

    as defined below:

    Parameters Values

    Detailed Scheduling

    Horizon

    90

    Rough Cut

    Scheduling Horizon

    90

    Scheduling Levels Via Detailed Scheduling

    Adjust Dates Adjust basic dates, adjust dep reqmts to operation date

    For Capacity

    Scheduling

    Always basic dates, dep reqmts to operation dates

    Scheduling type Backwards

  • 5/22/2018 SAP PP Configuration Document

    13/75

    Configuration Document SAP PP-PI Page 13 of 75 Version 1.0

    2.9 Define Scheduling Margin key

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Shop Floor

    control Operations Scheduling Define Scheduling Margin key

    Transaction Code SPRO

    Configuration

    Description

    Scheduling margin key specify time floats for scheduling as well as the release

    period for order release.The following floats are defined:

    Float before production: This is the time between the order start date and thescheduled start date.Float after production: This is the time between the order finish date and the

    scheduled finish date.

    The release date is calculated by adding the release period. The order release is

    carried out on this date.

    The opening period represents the number of workdays that are subtracted from

    the order start date in order to determine the order creation date. The MRPcontroller uses this time as a float for converting planned orders into process

    orders.

    The release period represents the number of workdays that are subtracted fromthe order start date in order to determine the process order release. The release

    period is only relevant for process order management.

  • 5/22/2018 SAP PP Configuration Document

    14/75

    Configuration Document SAP PP-PI Page 14 of 75 Version 1.0

    The following SMK are maintained for plants 1001, 1002 and 2000. For

    C&Fs, C&As treated as plants, the SMK are 000

    Plant SMK Opening per Float Before Prd Float After Prd Relea

    1001 Z00 000 000 000 Z01 001 000 000

    Z02 000 001 001

    Z03 000 001 002

    Z04 000 001 003

    Z05 000 001 004

    1002 Z00 000 000 000

    Z01 001 000 000

    Z02 000 001 001

    Z03 000 001 002

    Z04 000 001 003

    Z05 000 001 0042000 Z01 003 000 000

    2.10 Selection ID for BOM

    Menu PathImplementation Guide for R/3 Customizing (IMG)Production Material

    Requirements PlanningPlanning BOM Explosion Define BOM

    Selection

    Transaction Code SPRO

    Configuration In this step, we specify the priority with which a BOM usage or routing usage is

  • 5/22/2018 SAP PP Configuration Document

    15/75

    Configuration Document SAP PP-PI Page 15 of 75 Version 1.0

    Description selected during the planning run. Here, a sequence is usually determined which

    is used to select a valid BOM via the criterion "Usage".

    For all the plants the selection id is set as 01

    2.11 Defining BOM Explosion

    Menu PathImplementation Guide for R/3 Customizing (IMG)Production Material

    Requirements PlanningPlanning BOM Explosion Define BOM

    Explosion Control

    Transaction Code OMIW

    Configuration

    Description

    In this step, we specify the priority with which a BOM usage or routing usage is

    selected during the planning run. Here, a sequence is usually determined whichis used to select a valid BOM via the criterion "Usage".

    For all the plants the Control Parameters for BOM Explosion has been

    set as (BOM explosion number/order start date)

  • 5/22/2018 SAP PP Configuration Document

    16/75

    Configuration Document SAP PP-PI Page 16 of 75 Version 1.0

    2.12 Define Number Ranges for Planned Independent Requirements

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Production

    Planning Demand Management Define number ranges for planned

    independent requirements

    Transaction Code OMID

    Configuration

    Description

    In demand management, number ranges are only used internally within the

    system for counting per planned independent requirements item. The number of

    the planned independent requirements is not displayed.

    The Number Range is preset: 000000000001 to 9999999999999

    2.13 Define Version Numbers

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionProduction

    PlanningDemand ManagementPlanned Independent requirements

    Define Version Numbers

  • 5/22/2018 SAP PP Configuration Document

    17/75

    Configuration Document SAP PP-PI Page 17 of 75 Version 1.0

    Transaction Code OMP2

    Configuration

    Description

    In this step, we define versions to be able to:

    differentiate between different planned independent requirements

    indicate the transfer of requirements from previous planning levels (forexample, the sales plan from SOP)

    simulate requirements planning in long-term planning

    We have maintained versions for all the twelve months of the year and for

    requirement plan

    Requirement Plan Description

    01 January version

    02 February version

    03 March version

    04 April version

    05 May version

    06 June version

    07 July version

    08 August version

    09 September version

    10 October version

    11 November version

    12 December version

  • 5/22/2018 SAP PP Configuration Document

    18/75

    Configuration Document SAP PP-PI Page 18 of 75 Version 1.0

    2.14 Defining Strategy for MRP

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirements PlanningMaster Data Independents Requirements

    Parameters Planning Strategy Define Strategy

    Transaction Code SPRO

    Configuration

    Description

    The planning strategy represents a procedure to be used for planning a material.

    It is defined by:a requirements type from demand management, or

    a requirements type from sales order maintenance, or

    a combination of both that makes sense

    The following strategy is being used

    Strategy Description

    10 Make to stock, used for Domestic Requirement PIR

    11 Gross demand from C&F

    40 Planning with final Assembly, used for InternationalSales order

    2.15 Define Strategy Group

    Menu Path

    Implementation Guide for R/3 Customizing (IMG) Production Material

    Requirements PlanningMaster Data Independents RequirementsParameters Planning Strategy Define Strategy Group

    Transaction Code SPRO

    ConfigurationDescription

    The planning strategy represents an appropriate procedure to be used for

    planning and produced a material.

    The Strategy Group available in standard SAP system will be used. To be

    Specific the below mentioned strategy will be used in CLARISFor all the Non-repeat export products and domestic products with unique

    Secondary packing material requirements, PM requirements the Strategy

  • 5/22/2018 SAP PP Configuration Document

    19/75

    Configuration Document SAP PP-PI Page 19 of 75 Version 1.0

    group will be maintained as 40, for other materials at Manufacturing plants

    the strategy group will be maintained as 10, warehouse & at C&Fs

    strategy group is 11

    Strategy Description

    10 Make to stock, used for Domestic Requirement PIR

    11 Gross demand from C&F40 Planning with final Assembly, used for International

    Sales order

    2.16 Define Planning Horizon

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirements PlanningPlanning MRP CalculationDefine Planning

    Horizon

    Transaction Code OMDX

    Configuration

    Description

    The planning horizon is the period that is set for the "net change planning in the

    planning horizon." For this type of net change planning, only those materials are

    planned in the planning run that have a change relevant to MRP within theperiod (in work days).

    The length of the planning horizon should at least include the following:Period in which customer orders enter

    Delivery timesComplete material processing time

    The Planning Horizon for all the Plants, C&Fs, C&As defined as Plants are

    maintained as 135 Work Days (Current Month 45 days + 3 Months - 90

  • 5/22/2018 SAP PP Configuration Document

    20/75

    Configuration Document SAP PP-PI Page 20 of 75 Version 1.0

    Working days)

    2.17 Defining Availability of Stock

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production MaterialRequirements Planning Planning MRP Calculation Stocks Define

    Availability of Stock in Transfer/Blocked Stock/Restricted Stock

    Transaction Code SPRO

    Configuration

    Description

    In this step, we define whether stock in transfer (plant to plant) and/or blocked

    stock are included as well as restricted-use stock as available stock in the netrequirements calculation.

    Stock in transfer is the quantity that has already been withdrawn from the issuingplant (movement type, remove from storage - plant) but that has not yet beenreceived by the receiving plant (movement type, place in storage - plant)

    The system treats this stock as stock in transfer (plant to plant) for the receiving

    plant until the material is actually received and posted.

    The Stocks, which will participate in the Net requirement Calculation, areUnrestricted Stock and Stock in Transit for all the plants and C&F defined

    as plants

    For all the plants excepting clarion campus, Nourish, PKD, ICD and Head

    Office, blocked stocks are not included in the MRP calculation for Stocks.

  • 5/22/2018 SAP PP Configuration Document

    21/75

    Configuration Document SAP PP-PI Page 21 of 75 Version 1.0

    2.18 Defining Rescheduling Check for Plant and MRP Group

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirements Planning Planning MRP CalculationDefine

    Rescheduling Check

    Transaction Code OMDW

    Configuration

    Description

    The rescheduling period represents the period in which the system checks

    whether the existing dates of the receipt elements that are no longer allowed tobe changed automatically still suit the requirements situation. If the dates ofthese elements are no longer suitable, the system creates the following exception

    messages depending on the requirements situation

    The Rescheduling checks for all the Plants and depot are identical as

    detailed below:

    Parameters Value

    Rescheduling horizon 100

    Firm Planned Order Indicator Set

    Production Order Indicator Set

    Firm Purchase requisition Indicator SetOrder item/Sch line Indicator Set

    QM inspection lot Indicator Set

    Shipping notification Indicator Set

  • 5/22/2018 SAP PP Configuration Document

    22/75

    Configuration Document SAP PP-PI Page 22 of 75 Version 1.0

    2.19 Define Number ranges for Planning Run

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionMaterial

    Requirements Planning Number Ranges Maintain Number Ranges for

    Planning Run

    Transaction Code OMI2

    ConfigurationDescription

    In this step, we specify number ranges and intervals for the documents createdduring the planning run. These documents include:

    Planned orders for operative planningPlanned orders for long-term planning (simulative planning)

    Dependent requirements and reservationsPurchase requisitions

    MRP lists

    The standard Number ranges would be used

  • 5/22/2018 SAP PP Configuration Document

    23/75

    Configuration Document SAP PP-PI Page 23 of 75 Version 1.0

    2.20 Planning File Entry for Termination

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirement Planning Planning MRP Calculation Define Error

    Processing in the Planning

    Transaction Code OMDY

    Configuration

    Description

    In this step, we specify how the system is to proceed if errors occur during the

    planning run.Maximum number of purchase order proposals per date. If we have selected a

    fixed or maximum lot size, the number of purchase order proposals createdduring the planning run is determined in lot sizing. If more purchase order

    proposals are created during the planning run than the upper limit specified here,the planning run is terminated for the material in question and a termination

    message appears

    For Plant 1001 & 1002 The maximum Number of proposals have been

    defined as 999 and Sub MRP controller is 105. For all other plants this

    value is to set for 50 and sub MRP controller is 001

  • 5/22/2018 SAP PP Configuration Document

    24/75

    Configuration Document SAP PP-PI Page 24 of 75 Version 1.0

    2.21 Maintain Rounding Profile

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionMaterials

    Requirement PlanningPlanningLot-Size CalculationMaintain

    Rounding profilesTransaction Code OWD1

    Configuration

    Description

    In this IMG activity, we define the rounding profile in order to adaptthe units of measure in material requirements planning to the delivery and

    transport units, for example, if purchase orders can only be delivered in bundles

    of 10 pieces.With the rounding profile, we can define settings for rounding up/down orderproposal quantities to deliverable quantities. There are two different types of

    rounding profiles; one for the core application and a rounding profile for Retailapplication:

    Statistical rounding profile for MRP in the standard system Dynamic rounding profile and quantity to beadded/subtracted profile for Retail functions

    The statistical rounding profile for MRP is made up of: Level

    Threshold value Rounding value

    We can define several combinations of threshold and rounding values for arounding profile. The individual combinations are then assigned a level.

    The threshold value is the value from which the system rounds up to the next

    deliverable quantity. If the threshold value is not reached, the system rounds thequantity according to the next lower level. If the lowest level is not reached, then

    the system rounds up to a multiple of the rounding value, if the requirements

    quantity is larger than the threshold quantity. Otherwise, the requirementsquantity remains unchanged. The rounding value is the value to which the

    system rounds the quantity if the threshold value is exceeded

    The following Rounding profiles are maintained for Claris

    Rounding Profile

  • 5/22/2018 SAP PP Configuration Document

    25/75

    Configuration Document SAP PP-PI Page 25 of 75 Version 1.0

    2.22 Define Storage location MRP per plant

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionMaterials

    Requirement PlanningPlanningDefine Storage location MRP per plant

    Transaction Code SPRO

    Configuration

    Description

    In this step, we define the default values for storage location MRP (multi-plant).The indicator that we set here is proposed when creating a material master record

    for the storage locations maintained. If we have created a material for a storage

    location in the material master, for which we have maintained a proposal value.

    The following data is maintained for Claris

  • 5/22/2018 SAP PP Configuration Document

    26/75

    Configuration Document SAP PP-PI Page 26 of 75 Version 1.0

    2.23 Defining Parallel Processing for MRP

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionMaterials

    Requirement PlanningDefine Parallel Processing n MRP

    Transaction Code SPRO

    ConfigurationDescription

    With the help of parallel processing procedures, we can significantly improve theruntime of the total planning run. To process in parallel, we can either selectvarious sessions on the application server or various servers. The work package,

    with a fixed number of materials that are internally defined in the program, isdistributed over the individual servers/sessions. Once a server/session has

    finished processing a package, it starts processing the next package. If a low-

    level code is being planned, the servers/sessions that have finished must wait

    until the last server/session has finished its package to avoid inconsistencies.Then the next low-level code is processed per packages. The parallel processing

    procedure is switched on in the initial screen of total planning.

    The destination of parallel processing is maintained as

    CLSERDEV-CO_CDV_00

  • 5/22/2018 SAP PP Configuration Document

    27/75

    Configuration Document SAP PP-PI Page 27 of 75 Version 1.0

    2.24 Assigning MRP Checking Rule

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirements Planning Procurement Proposals Planned Orders Define

    Availability Check for ComponentsTransaction Code OPPJ

    Configuration

    Description

    We control the availability check for requirements planning by defining thechecking group and the checking rule at plant level or per MRP group.The availability check can be carried out in MRP for the dependent

    requirements. This means that the availability check can directly check whether

    sufficient material is available for the production of the assembly. The

    availability check is initiated from planned order processing. It is not carried outautomatically in the planning run for each requirement of an assembly.

    In the checking group, several checking rules are grouped together. Therefore,

    we can define different checking rules for different business application areas

    (sales and distribution, MRP, production orders, inventory management) or for

    different business operations. If we require different checking rules for differentbusiness operations, we can create several checking groups with the appropriate

    checking rules or we can assign another checking rule using the MRP group. Thechecking group is assigned to the material in the material master record, MRP 2

    screen, in field "Availability check".

    For all the manufacturing plant, the Check on the Material will be done

    during the Creation and Release of the Process Order. If there is material

    short falls No release will be carried outThe following checking rules are defined

    Checking Rule Order Type

    Z1 Checking Rule for Order Type C001

    Z2 Checking Rule for Order Type C002

    Z3 Checking Rule for Order Type C003

    Z4 Checking Rule for Order Type C004

    Z5 Checking Rule for Order Type C005

  • 5/22/2018 SAP PP Configuration Document

    28/75

    Configuration Document SAP PP-PI Page 28 of 75 Version 1.0

    2.25 BOM Usage

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Basic Data

    Bill of Material General data Bill of Material Usage

    Transaction Code OS20

    Configuration

    DescriptionFor one material separate bills of material for the individual organisational

    areas involved can be created. For example, you create separate BOMs for

    R&D, production, and costing. In this way, each area is dealing only with the

    specific data it requires.

    Example:

    The R&D BOM includes all the components of the product and their technical

    data from the design point of view. This BOM is generally not linked to anyorder.

    The production BOM contains all the items required from the production and

    process point of view. Only items relevant to production, for which process

    data (such as the issue storage location) can be entered, are required. A

    production BOM does not contain any packaging materials required in the

    shipping department.

    While defining a BOM usage, the configuration of the item status is defined.

    The item status is made up of a number of indicators in the BOM item (for

    example, "relevant to production", "relevant to engineering/design", and so

    on).

    The item status controls how the BOM item is processed in related application

    areas.

    For example, the production department requires a BOM with all the items

    that are relevant to production. These items are first copied to the planned

    order. When the planned order is converted to a process order, the items are

    copied to the process order. The process order tells the production department

    which materials and intermediates it has to produce.

  • 5/22/2018 SAP PP Configuration Document

    29/75

    Configuration Document SAP PP-PI Page 29 of 75 Version 1.0

    For Claris we have used the standard Usage as1 for Production

    Usage Description

    1 Production

    2.26 Defining Item Categories

    Menu Path

    Implementation Guide for R/3 Customizing (IMG) Production Basic Data

    Bill of MaterialItem Data Define item categories

    Transaction Code OS13

    Configuration

    Description

    When we enter a new BOM item, we must assign an item category to the item.The item category defines the attributes and functions of a BOM item. It controls

    field and screen selection for detail screens in BOM maintenance

    The Following item categories are being used

    Item category Description

    N Non Stock Item

    L Stock Item

    K Class Item

    D Document Item

    M Intra Material

    2.27 Define Reasons for Variances

    Menu PathImplementation Guide for R/3 Customizing (IMG)ProductionShop Floor

    Control Operations Confirmation Define Reasons for Variances

    Transaction Code OPK5

    Configuration The reasons for variances are maintained at the plant level.

  • 5/22/2018 SAP PP Configuration Document

    30/75

    Configuration Document SAP PP-PI Page 30 of 75 Version 1.0

    Description The Reasons mentioned below are currently maintained at manufacturing

    plants 1001, 1002 (Injectable and infusion)

    Variances

    2.28 Define Number ranges for Manual Processing

    Menu PathImplementation Guide for R/3 Customizing (IMG)Production Materials

    Requirement Planning Number rangesDefine Number Ranges for Manual

    ProcessingTransaction Code OMI3

    Configuration

    Description

    In this step we maintain number ranges for Planned orders and Purchase

    requisitions

    The SAP default values are used in our configuration

    for Planned orders

    internal number range 1 with interval from 1 to 19999999

    external number range 2 with interval from 20000000 to 29999999

    for Purchase requisitions

    internal number range 1 with interval from 10000000 to 19999999

    external number range 2 with interval from 900000000 to 99999999

  • 5/22/2018 SAP PP Configuration Document

    31/75

    Configuration Document SAP PP-PI Page 31 of 75 Version 1.0

    2.29 Activating Requirements Planning

    Menu PathImplementation Guide for R/3 Customizing (IMG)ProductionMaterial

    Requirements PlanningPlanning File Entries Activate MRP and Set Up

    Planning File

    Transaction Code OMDU

    ConfigurationDescription

    We define the plants for which we want to carry out MRP here. Entries are onlyto be made in the planning file once this indicator has been set. This means:

    When creating a material, the material number is entered in the planning file andthe system sets the total change indicator as well as the net change planningindicator

    Every time the material undergoes a change relevant to the planning run, the

    system sets the total change indicator and/or the net change planning indicator(depending on the planning horizon).

    All the plants at Claris Life sciences have been activated for MRP

  • 5/22/2018 SAP PP Configuration Document

    32/75

    Configuration Document SAP PP-PI Page 32 of 75 Version 1.0

    2.30 Defining Item Numbers of Order Types

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Material

    Requirements Planning Procurement Proposals Conversion of

    Procurement Proposals Define Conversion of Planned Orders into

    Purchase Requisitions

    Transaction Code OMDV

    ConfigurationDescription

    In this step, We define the following:Number of planned orders, that are to be proposed for the collective conversionof planned orders into purchase requisitions

    Item number of the item that is transferred to the purchase requisition during theconversion. Thus, it is possible to differentiate the purchase requisitions that

    were created in the planning run from the ones that were created manually by thepurchasing department

    For all the plants 500 has been proposed for the collective conversion of

    planned orders into purchase requisitions

  • 5/22/2018 SAP PP Configuration Document

    33/75

    Configuration Document SAP PP-PI Page 33 of 75 Version 1.0

    2.31 Defining Conversion Planned Order to Process Order

    Menu PathImplementation Guide for R/3 Customizing (IMG)ProductionMaterial

    Requirements Planning Procurement Proposals Conversion of

    Procurement Proposals Define Order Type for Conversion to

    Production/Process OrderTransaction Code OPPE

    Configuration

    Description

    We define the order type that is automatically set when converting plannedorders into production orders or process orders

    For Plants 1001, 1002, Production order PP01 Standard production order &

    Process order PI01 Process order (internal number assignment) have been

    set for conversions

  • 5/22/2018 SAP PP Configuration Document

    34/75

    Configuration Document SAP PP-PI Page 34 of 75 Version 1.0

  • 5/22/2018 SAP PP Configuration Document

    35/75

    Configuration Document SAP PP-PI Page 35 of 75 Version 1.0

    3. PRODUCTION PLANNING FOR PROCESS INDUSTRIES

    3.1 Define Resource Category

    Menu Path

    Implementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Resource General Data DefineResource Category

    Transaction Code OP40

    Configuration

    Description

    The resource category determines the data that can be maintained in a resourceand, therefore, the functions (for example, costing or scheduling) for which theresource can be used.

    Each resource category is assigned to the applications (for example, production,

    and plant maintenance or quality management) whose menus allow us tomaintain resource with this category.

    Each resource category has a number of screens assigned to it which the system

    displays when resource of this category are displayed. The screens contain

    groups of fields (for example, scheduling data). Depending on the resourcecategory, we can make field selections on these screens (for example, definingrequired entry fields).

    We specify whether change documents are written for each resource category.

    LineProcessing unit

    Team

    Labor

    Standard settings available in the system are used. The Resource Category

    used are 0008(Processing Unit)

  • 5/22/2018 SAP PP Configuration Document

    36/75

    Configuration Document SAP PP-PI Page 36 of 75 Version 1.0

    3.2 Defining Person Responsible for Work Centre

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Resource General Determine

    Person Responsible

    Transaction Code SPRO

    Configuration

    Description

    With this key, we can identify a person or group of people responsible for

    maintaining the master data in certain work centers.These employees are not responsible for planning tasks but only for the

    maintenance of the work center parameters

    The following persons are responsible for maintaining work centre at Claris

    Person Responsible

  • 5/22/2018 SAP PP Configuration Document

    37/75

    Configuration Document SAP PP-PI Page 37 of 75 Version 1.0

    3.3 Standard Value Keys

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Resource General Data Standard

    Value

    DefineStandard Value keyTransaction Code OP19

    Configuration

    Description

    In this step we define standard value keys. The standard value key determines

    the meaning of the six standard values in the operation. The SAP System assignsa parameter ID to the standard values of the operation and the work in network

    activities.The parameter ID in turn determines:the key word displayed for the standard value on the screen, for example, setup,

    machine, labor, teardown etc.

    the dimension (for example, time, quantity, volume) of the standard value

    For Claris SAP Implementation we have defined Z001 as Standard Value

    key

    Key Description

    Z001 Fixed+Var+Labor+Power+Steam

  • 5/22/2018 SAP PP Configuration Document

    38/75

    Configuration Document SAP PP-PI Page 38 of 75 Version 1.0

    3.4 Defining Formula Parameters for Resources

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Resource Capacity Requirements

    Planning Formulas for Resources (Work Centers) Define Formula

    Parameters for Resources (Work Center)

    Transaction Code OP17Configuration

    Description

    A formula is identified by its formula key. It is composed of formula parameters

    that are identified by parameter Ids.

    The following parameters are maintained for Claris Life Sciences

    Parameter Description

    SAPC04 Fixed Duration

    SAPC05 Lot Size dep. Duration

    SAP_03 Labour

    SAP_09 Operation Quantity

    SAP_08 Base Quantity

    SAP_17 No. of Employees

    ZCL_01 PowerZCL_02 Steam

  • 5/22/2018 SAP PP Configuration Document

    39/75

    Configuration Document SAP PP-PI Page 39 of 75 Version 1.0

    3.5 Defining Formula for Resources

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process IndustriesMaster Data Resource Capacity Requirements

    Planning Formulas for Resources (Work Centers)Define Formula for

    Resources (Work Center)

    Transaction Code OP17

    Configuration

    Description

    We define the formulas that you want to use in the following areas:

    Capacity planningScheduling

    Costing

    You can use the formula parameters to which values have been previously

    assigned. The formula parameters can be linked mathematically using the

    following operators:Addition => +

    Subtraction => -Multiplication => *

    Division => /

    Formula ZCL001 will be used in Machine dependent resources for

    scheduling and costing. Formula ZCL002 will be used in Labor dependent

    resources for costing. Formula ZCL003 will be used in Labor dependentresources for scheduling.

    FormulaKey

    Description Formula

    ZCL001MACHINE

    DEPENDENT

    SAPC04 + ( SAPC05 * SAP_09/ SAP_08 )

    ZCL002LABOR

    DEPENDENT SAP_03 * SAP_09 / SAP_08

    ZCL003LABOR

    DEPENDENT(SCH)

    (SAP_03 * SAP_09 / SAP_08) /

    SAP_07

  • 5/22/2018 SAP PP Configuration Document

    40/75

    Configuration Document SAP PP-PI Page 40 of 75 Version 1.0

    3.6 Task List Usage

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Resource General Data Define

    Task List UsageTransaction Code OP45

    Configuration

    Description

    Task List Usage key controls, that a resource can be used in which task lists like

    master recipe or PM task list. For example, we can categorize resource into

    maintenance resource or inspection resource according to their relevance andtheir usage in general task lists or inspection plans. We can also allow resource

    to be used in any combination of task lists types

    Standard settings available in the system are used.

    The following table lists the entries which are used for Claris

    Task list type Description

    002 Only inspection plans

    008 Master recipe + process order

    009 All task list types

  • 5/22/2018 SAP PP Configuration Document

    41/75

    Configuration Document SAP PP-PI Page 41 of 75 Version 1.0

    3.7 Define Capacity Planner

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Resource Capacity Requirement

    Planning

    Determine Capacity PlannerTransaction Code SPRO

    Configuration

    Description

    Key for a group of employees who are responsible for capacity planning. We can

    use this key to select specific capacities. This is maintained at the client level.

    The Following capacity Planners are maintained

    Plant MRP Controller Description

    A01 INJ PRD LINE-1

    A02 INJ PRD LINE-2

    A03 INJ PRD LINE-3

    A04 INJ PRD LINE-4

    A05 INJ PRD LINE-5A06 INJ PAC BELT-1

    A07 INJ PAC BELT-2

    A08 INJ PAC BELT-3

    A09 INJ PAC BELT-4

    A10 INJ PAC BELT-5

    A11 INJ SPM PRINTING

    A12 INJ STERILIZATION

    A13 INJ DISP PM STORE

    1001

    B01 INF PRD LINE-1

    B02 INF PRD LINE-2

    B03 INF PRD LINE-3B04 INF PRD LINE-4

    B05 INF PRD LINE-5

    B06 INF PRD LINE-6

    B07 INF PRD LINE-7

    B08 INF PAC BELT-1,2

    B09 INF PAC BELT-3,4

    B10 INF PAC BELT-5,6

    B11 INF PAC BELT-7,8

    B12 INF PAC BELT-9,10

    B13 INF PAC BELT-11,12

    B14 INF PAC BELT-13

    B15 INF DISPENSING

    B16 INF SPM PRINTING

    B17 INF STERILIZATION

    1002

    B18 INF DISP PM STORE

  • 5/22/2018 SAP PP Configuration Document

    42/75

    Configuration Document SAP PP-PI Page 42 of 75 Version 1.0

    3.8 Define Number Ranges for Master Recipe

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning forProcess Industries Master Data Master Recipe Setting for Task List

    Type Define Number Ranges for Master Recipe

    Transaction Code C2N2

    Configuration

    Description

    In this step we define number ranges for recipe groups.When a master recipe is created, it must be assigned to a recipe group, which is

    identified using a group key

    The Number Range is preset to:A0000001 to ZZZZZZZZ

  • 5/22/2018 SAP PP Configuration Document

    43/75

    Configuration Document SAP PP-PI Page 43 of 75 Version 1.0

    3.9 Recipe Status

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Master Recipe Data for Recipe Header

    Define Recipe StatusTransaction Code OP46

    Configuration

    Description

    The recipe status determines:

    Whether a recipe is released for use in process orders

    Whether a recipe is released for costingWhether a consistency check is carried out before the recipe is posted

    When a master recipe is created, a status must be assigned to it. This status canlater be changed according to the processing stage of the recipe. Together with

    the recipe usage, the recipe status is used to create priority sequences that serve

    as a basis for the automatic selection of recipes during order creation, capacity

    planning and costing.The following status are being maintained for Recipe

    Plant Description

    1 Created

    4 Released (general)

    3.10 Recipe Usages

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Master Recipe Data for Recipe Header

    Define Recipe Usage

    Transaction Code SPRO

    Configuration

    Description

    The recipe usage determines:

    The purpose or area, for which a recipe is created (for example, the chemical, the

    pharmaceutical or the food industry) The dynamic modification criteria to beused in the corresponding orders for adjusting the inspection scope if inspection

    points have not been defined When we create a master recipe, we must assign arecipe usage to it. We can create several recipes with different recipe usages for

    one material.

    The standard usage available will be used

    Usage Description

    1 Production

  • 5/22/2018 SAP PP Configuration Document

    44/75

    Configuration Document SAP PP-PI Page 44 of 75 Version 1.0

    3.11 Define Planner Groups

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Master Recipe Data for Recipe Header

    Define Planner Group

    Transaction Code SPRO

    Configuration

    Description

    A planner group identifies one or several planners who are responsible for

    Maintaining certain recipes in a plant. When we create or change a master

    recipe, we can assign a planner group to it.The following planner group are being maintained for Claris

    Plant Planner Group Description

    1001 A01 IPQA Manager - Injectable

    1001 A02 Production ManagerInjectable

    1002 B01 IPQA Manager Infusion

    1002 B02 Production Manager - Infusion

    3.12 Control key for Master Recipe

    Menu Path

    Implementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Master Recipe Data for Operationsand Phases Define Control Keys

    Transaction Code OP67

    Configuration

    Description

    Control keys are assigned to operation and phases, and secondary resources.

    In the control key, we set a number of flags and keys that specify the businessfunctions to be carried out for an operation, a phase or a secondary resource.

    Control key determines how an operation, phase, or secondary resource ishandled in order processing and in product costing.

  • 5/22/2018 SAP PP Configuration Document

    45/75

    Configuration Document SAP PP-PI Page 45 of 75 Version 1.0

    Control keys can be used as follows:In resources:

    The control key we enter here is referenced or copied to the corresponding

    operations, phases and secondary resources of the master recipe.In the master recipe

    When creating operations and phases as well as when allocating secondary

    resources:In the process order when maintaining operations, phases and secondary

    resources:

    When we create a process order, the system copies the control keys we havemaintained in the master recipe to the order. They can still be changed in the

    order if there is no reference to the resource.

    For Claris we are maintaining the following control keys

    Control Key Control key Description

    ZP01 Process manufacturing

    ZP02 QC : Scheduling and MIC

    ZP03 Process mfg., Inspection, AutoGR

    ZP04 QC : MIC only

    ZP05 Process manufacturing with AutoGR

    ZP06 Process manufacturing-Bulk Preparation

    ZP07 QA : Scheduling

    3.13 Define Capacity Categories

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process IndustriesMaster DataResourceCapacity requirement planning

    Define Capacity Categories

    Transaction Code SPRO

    Configuration

    Description

    In this step we define the capacity category that we want to assign to the

    resource. With capacity category we determine,which capacity type a capacity category belongs to, for example:

    - "available capacity in volumes/quantity" for storage resources

    - "available capacity in time units" for processing unitswhether a capacity category can be assigned to people as single capacities

    We have used the Capacity category 008

  • 5/22/2018 SAP PP Configuration Document

    46/75

    Configuration Document SAP PP-PI Page 46 of 75 Version 1.0

    3.14 BOM Status

    Menu PathImplementation Guide for R/3 Customizing (IMG) ProductionPlanning for

    process Industries Master Recipe Material List General Data Define

    BOM Status

    Transaction Code OS23

    Configuration

    Description

    Via the BOM status, we define which other application areas can use a bill ofmaterial with this status.

    In the different areas in a company (such as costing), the BOM is exploded

    according to the application. When we define an application for a certain area inthe company, we select the status indicators in the Minimum requirements of

    BOM status dataset that the BOM status must have before the BOM is read for

    the BOM explosion.In MRP, the following indicators are checked directly from the definition of theBOM status:

    Explosion in MRP

    Released for ordersMRP only reads BOMs whose BOM status has at least one of these indicators.

  • 5/22/2018 SAP PP Configuration Document

    47/75

    Configuration Document SAP PP-PI Page 47 of 75 Version 1.0

    3.15 Process Order Type

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Process Order Master Data Order Define Order

    Types

    Transaction Code CORN

    Configuration

    Description

    Process order type covers control information that is needed for managing the

    order.The order type defines the following:

    We have to assign an order category to each order type. The order categorieshave fixed assignments in the SAP System and show the technical characteristics

    of the orders. The order category defines, for example, the transactions we can

    use to process an order.

    Plant Order Type Description

    1001 C001 Production

    C002 Packing

    C002 Validation

    C004 Performance Qualification

    C005 Repacking

    1002 C001 Production

    C002 Packing

    C003 Validation

    C004 Performance Qualification

    C005 Repacking

    3.16 Number Ranges for Process Order

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process IndustriesProcess Order Master Data OrderNumber Ranges

    Define Number Ranges for orders

  • 5/22/2018 SAP PP Configuration Document

    48/75

    Configuration Document SAP PP-PI Page 48 of 75 Version 1.0

    Transaction Code CO82

    Configuration

    Description

    In this menu option, we define the number ranges for orders.

    Each order is uniquely identified by an order number within one client.

    We allocate each order to a number range group via the order type. We can

    allocate several order types to the same number range and thus the same interval.

    Internal number assignment

    When we create an order, the SAP System automatically assigns a

    consecutive number from the number range that we have defined.

    The number range defined are mentioned below

    Order Type Number Range

    C001 1000000000-1099999999

    C002 110000000- 1199999999

    C003 120000000- 1299999999

    C004 130000000- 139999999

    C005 140000000- 1499999999

    3.17 Define Production Scheduler

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Process Order Master Data Order Bill of

    MaterialDefine Production Scheduler

    Transaction Code CORU

    Configuration

    Description

    Production scheduler is the entity who controls how process orders are managed.

    For every production scheduler, a production scheduler profile is attached. By

    assigning production schedulers to materials, we can define responsibilities for

  • 5/22/2018 SAP PP Configuration Document

    49/75

    Configuration Document SAP PP-PI Page 49 of 75 Version 1.0

    materials within production activity control.

    In a production scheduling profile, we can Specify that in a process order

    particular business transactions be carried out in parallel.

    Automatic batch creation on order creation.Batch creation on order release

    For Claris we are marinating the following Production Scheduler

    Plant Production Scheduler Description

    1001 101 Production

    102 Packing

    1002 101 Production

    102 Packing

    3.18 Define Production Scheduler Profile

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning forProcess Industries Process Order Master Data Order Bill of Material

    Define Production Scheduler Profiles

    Transaction Code CORY

    Configuration

    Description

    Production scheduling profile is linked to the Production Scheduler and one can: Specify automatic functions like order release on order creation

    Printing of Order Scheduling on release

    We can assign a production scheduler profile to a material (MMR) and

    production Scheduler (Customizing)

    Scheduler profiles C001, C002, C003, C004 are maintained for plants 1001

    and 1002

    PlantProduction Scheduler

    profileDescription

    1001 C001 Production

    C002 Packing

    1002 C001 Production

    C002 Packing

  • 5/22/2018 SAP PP Configuration Document

    50/75

    Configuration Document SAP PP-PI Page 50 of 75 Version 1.0

    3.19 Scope of Check

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process IndustriesProcess Order OperationsAvailability Check

    Define Scope of Check

    Transaction Code OPJJ

    Configuration

    Description

    To check the availability of material components in the process order, the

    material components have to be assigned to checking group. Through checking

    group and checking rule the scope of check is defined. Through scope of checkwe can specify which MRP element to include and which stock categories to beincluded.

    Define Scope of Check Yes / No (Include / Not Include)

    Include safety stock Yes

    Stock in transfer No

    Include QI Stock No

    Include Blocked Stock No

  • 5/22/2018 SAP PP Configuration Document

    51/75

    Configuration Document SAP PP-PI Page 51 of 75 Version 1.0

    W/o Subcontracting No

    Check without RLT Yes

    No Stor. Location Inspection No

    Checking period No

    Include Purchase orders No

    Include Purchase Indents No

    Include dependent reqmts NoInclude reservations No

    Include Sales Reqmts No

    Include deliveries No

    Include shipping notification No

    Include Dependent reservations No

    Include released Orders No

    Include Planned Orders No

    Include Production Orders No

    Include receipts in Past and future No

    3.20 Define Checking Control

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Process Order Operations Availability Check

    Define Checking Control

    Transaction Code OPJK

  • 5/22/2018 SAP PP Configuration Document

    52/75

    Configuration Document SAP PP-PI Page 52 of 75 Version 1.0

    Configuration

    Description

    In this step we define the following:

    Whether an availability check is to be carried out when we create or release anorder

    Whether an availability check is to be carried out when we save an order that has

    been created or releasedWhich checking rule is to be used

    What effect a material shortfall is to have on the creation or release of an order

    For all the manufacturing plant, the Check on the Material will be done

    during the Creation and Release of the Process Order. If there is material

    short falls No release will be carried out

    3.21 Define Scheduling parameters for a process order

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Capacity

    Requirements Planning Operations Scheduling Define scheduling

    parameters for planned orders

    Transaction Code OPUZ

    Configuration

    Description

    The purpose of this activity is to define levels and control parameters forschedulingIt comprises maintenance of

    scheduling levels (detailed-, production-rate and rough-cut scheduling)

    date adjustment when deadlines are exceededscheduling control for detailed scheduling

    reduction

    For all the Plants and Order types the scheduling has been defined as

    forwards

  • 5/22/2018 SAP PP Configuration Document

    53/75

    Configuration Document SAP PP-PI Page 53 of 75 Version 1.0

    3.22 Defining Parameters for Order Confirmation

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Process Order Operations Confirmation Define

    Confirmation Parameters

    Transaction Code OPK4Configuration

    DescriptionUsing the Confirmation Parameters, you can proceed as follows:

    Confirmation function: Whether system proposes a partial confirmation, a final confirmation or

    final confirmation with withdrawal posting of the open reservations for

    the confirmation.

    Propose time unit Confirmation control: if the sequence is not adhered, you can issue a message

    Whether total confirmed qty of a operation checked for under delivery or

  • 5/22/2018 SAP PP Configuration Document

    54/75

    Configuration Document SAP PP-PI Page 54 of 75 Version 1.0

    over delivery tolerance in the order header

    Check on the dates Logs Goods Movement Propose confirmed data

    For all the Process Order types to the respective plants, all the indicatorswill be on and check on over delivery / under delivery will also be notchecked.

    3.23 Assigning Material Types to Task List

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Master Recipe Settings for the TaskList Type Assign Material Types

    Transaction Code SPRO

  • 5/22/2018 SAP PP Configuration Document

    55/75

    Configuration Document SAP PP-PI Page 55 of 75 Version 1.0

    Configuration

    Description

    Only materials of the material types allocated in this step can be allocated to a

    master recipe at the header level, that is, as the material to be produced.For task list type 2 Master recipe the following types have been assigned

    Task ListType Material type

    2 FERT

    2 HALB

    2 HAWA

    2 HIBE

    2 ROH

    2 ZERT

    3.24 Define Material Types Allowed for BOM Header

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Master Data Master Recipe Material list

    General Data Define Allowed Material Types for BOM Header

    Transaction Code OS24

    ConfigurationDescription

    In this step, we specify which material types in conjunction with BOM usages

    are allowed for the BOM header material.When we make these settings, we can make a generic entry in the fields for the

    BOM usage and the material type. This means, for example, that we can enter an

    "*" instead of a specific BOM usage. This stands for all possible BOM usages.When we create a new bill of material, the system checks the material type as

    follows:

    The fully qualified (non-generic) entries are checked first. The generic entriesare checked afterwards. We can define that the use of the material type in

    combination with the BOM usage is "allowed/not allowed" by setting the

    indicator.

  • 5/22/2018 SAP PP Configuration Document

    56/75

    Configuration Document SAP PP-PI Page 56 of 75 Version 1.0

    The Following data is maintained for Claris

    BOM Usage Material type

    1 All material Types

    3.25 Defining Order Type-Dependent Parameters

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Process Order Master Data Order Define Order

    Type-Dependent Parameters

    Transaction Code COR4Configuration

    Description

    In this step, we define the parameters that are valid for each order type andplant. The parameters are split up as follows:

    Master dataCost accounting

    PlanningImplementation

    For order type C001 and C002 production version and Master Recipe are

    automatically selected whereas for C003, C004, C005 they are Manual

    Selection

  • 5/22/2018 SAP PP Configuration Document

    57/75

    Configuration Document SAP PP-PI Page 57 of 75 Version 1.0

    3.26 Assigning Process Instructions to Control Recipe Destinations

    Menu PathImplementation Guide for R/3 Customizing (IMG) Production Planning for

    Process Industries Process ManagementControl Recipes / PI Sheets

    Define and Set Up Control Recipe Destinations

    Transaction Code O10C

    Configuration

    Description

    Control recipe destinations are assigned to the phases of the master recipe and

    the process order. In the process order, one control recipe is created and sent foreach control recipe destination assigned to the order. We specify the process

    instructions that are to be generated in the process order when a control recipe is

    created for a control recipe destination

    The following destinations are created in addition to the standard SAP

    destinations

    CRD CRD Destination Destination Address

    DC Dispensing Chemist Dispensing Chemist

    MC Mixing Chemist Mixing Chemist

    PS Packing Supervisor Packing Supervisor

  • 5/22/2018 SAP PP Configuration Document

    58/75

    Configuration Document SAP PP-PI Page 58 of 75 Version 1.0

    QA Quality Assurance Quality Assurance

    QC Quality Control Quality Control

    SC Sterlizer Chemist Sterlizer Chemist

  • 5/22/2018 SAP PP Configuration Document

    59/75

    Configuration Document SAP PP-PI Page 59 of 75 Version 1.0

    4. BATCH MANAGEMENT

    4.1 Activate Document Management for Batches

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Batch MasterActivate Document Management For

    BatchesTransaction Code ODOC

    Configuration

    Description

    In this step we activated the Document Managementfunction for batches.

    4.2 Defining Batch Level

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Specify Batch Level and Activate Status Management

    Transaction Code OMCT

    ConfigurationDescription

    In this activity we specify the following:

    The level at which batch numbers are uniqueWhether batch status management is active in the client

    The plants in which batch status management is activeThe initial status of new batches

    If we choose plant level, the batch number is unique in conjunction with therespective material and the plant. If you choose material level, the batch number

    is unique together with the material. At client level, the batch number is uniquein the whole client

    For Claris Batch level is maintained unique at Material Level

    4.3 Activating Automatic Batch Number Assignment

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Batch Number Assignment Activate Internal Batch

    Number Assignment

  • 5/22/2018 SAP PP Configuration Document

    60/75

    Configuration Document SAP PP-PI Page 60 of 75 Version 1.0

    Transaction Code OMCZ

    Configuration

    Description

    In this activity we activate internal batch number assignment. We define whether

    internal batch number assignment is allowed for goods receipts that have an

    account assignment

    The internal batch number assignment is activated

    4.4 Maintain Internal Batch Number Assignment Range

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Batch Number Assignment Maintain Internal

    Batch Number Assignment Range

    Transaction Code OMAD

    Configuration

    Description

    In this activity, we maintain number ranges for internal batch number assignment

    The SAP standard number range are used at Claris

    The number range is defined from 0000000001 to 9999999999

    4.5 Define Batch Creation for Production Order / Process Order

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Creation of New Batches Define Batch Creation for

    Production Order / Process Order

    Transaction Code CORW

    Configuration

    Description

    In this step we made the following settings in batch management for the existing

    production control profiles

  • 5/22/2018 SAP PP Configuration Document

    61/75

    Configuration Document SAP PP-PI Page 61 of 75 Version 1.0

    For plants 1001 and 1002 for order types C001 to C004 we have defined

    Automatic batch creation on order release and classification carried out in

    the background

    4.6 Define Process Order Condition Tables

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Condition Tables Define Process Order Condition

    Tables

    Transaction Code OPLD

    Configuration

    Description

    In this IMG activity, we define condition tables for batch determination in

    process orders.

    We have used the condition table 501 which determines Batch for each

    Material Type

    4.7 Define Process Order Access Sequences

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Access Sequences Define Process Order Access

    Sequences

    Transaction Code SPRO

    Configuration In this IMG activity, we define access sequences for batch determination in

  • 5/22/2018 SAP PP Configuration Document

    62/75

    Configuration Document SAP PP-PI Page 62 of 75 Version 1.0

    Description process orders.

    We have Defined the Order Sequence C003 which determines Batch for

    each Material Type

    4.8 Assign Search Procedure to Process Order and Activate Check

    Menu Path Logistics - General

    Batch Management

    Batch Determination and BatchCheck Batch Search Procedure Allocation and Check ActivationAssign

    Search Procedure to Process Order and Activate Check

    Transaction Code CORC

    Configuration

    Description

    In this IMG activity, we allocate batch search procedures to those combinations

    of process order and plant for which batch determination is to be carried out, and

    activate batch checking.

    For Order type C001, C002, C003, C004, C005 the search procedure is

    defined as CO0001

    Plant Order Type Search procedure

    1001 C001 CO0001

    1001 C002 CO0001

    1001 C003 CO0001

    1001 C004 CO0001

    1001 C005 CO0001

    1002 C001 CO0001

    1002 C002 CO0001

    1002 C003 CO0001

    1002 C004 CO0001

    1002 C005 CO0001

    1005 C005 CO0001

  • 5/22/2018 SAP PP Configuration Document

    63/75

    Configuration Document SAP PP-PI Page 63 of 75 Version 1.0

    4.9 Activating batch-specific Unit of Measures

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Batch-Specific Material Unit of Measure Activate

    Batch-Specific Material Unit of Measure

    Transaction Code OMWS

    Configuration

    Description

    If we want to use batch-specific material units of measure, set the Batch-specific

    material units ofmeasure active indicator

    The Batch Specific units of measure is activated

    4.10 Edit Batch-Specific Material Unit of Measure

    Menu Path

    Implementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Batch-Specific Material Unit of Measure Edit Batch-Specific Material Unit of Measure

    Transaction Code BMA1

    Configuration

    Description

    In this step, we define which units of measurement we want to use as batch-

    specific material units of measure.

    We have maintained the following unit of measure

    Unit Batch Specific UOM UOM

    KIK kg act.ingrd. / kg KG

  • 5/22/2018 SAP PP Configuration Document

    64/75

    Configuration Document SAP PP-PI Page 64 of 75 Version 1.0

    4.11 Define Calculation of Proportion Quantity from Base Quantity

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Batch-Specific Material Unit of Measure Define

    Calculation of Proportion Quantity from Base QuantityTransaction Code BMA3

    Configuration

    Description

    In this step, we define the ratio of the proportion unit to the base unit. This ratio

    is needed to convert base units to proportion units of measure.

    Unit Description Technical Format

    EML Endotoxin Units / Mililiter EU/ml

    G/L gram act.ingrd / liter gai/l

    KIK kg act.ingrd. / kg kai/kg

    4.12 Maintain Period Indicator

    Menu Path Implementation Guide for R/3 Customizing (IMG)Logistics - General

    Batch Management Shelf Life Expiration DateMaintain Period Indicator

    Transaction Code O02K

    Configuration

    Description

    In this step we specify which unit of measurement are used for the total shelf life

    and minimum remaining shelf life.

    We have used SAP defined Period indicators as day, week, month and year

  • 5/22/2018 SAP PP Configuration Document

    65/75

    Configuration Document SAP PP-PI Page 65 of 75 Version 1.0

    4.13 Activating Expiration Date View per Plant

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Shelf Life Expiration Date (SLED) Set Expiration

    Date Check

    Transaction Code OMJ5

    Configuration

    Description

    We have defined the time unit the system uses in the storage data of the material

    master record in the Period indicator field.

    The shelf life expiration date check is active for all the plants, except1004,1005,1006 and the shelf life expiration date check is active for all the

    movement types

    4.14 Define Process Order Strategy Types

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Batch Determination and Batch Check Batch Search

    Procedure Allocation and Check Activation Define Process Order Strategy

    Types

    Transaction Code SPRO

    Configuration

    Description

    In this step, we define a strategy type for batch determination in process orders.We use different batch search strategies for different combinations of plant and

    order type. For this purpose, we have created the following strategy types:

    A strategy type with a selection class that uses the shelf life expiration date as

  • 5/22/2018 SAP PP Configuration Document

    66/75

    Configuration Document SAP PP-PI Page 66 of 75 Version 1.0

    search criterion during batch determination

    Strategy

    TypeDescription Class Type

    ZC01 Mat.Type/Mvt/Plant 023 Batch

    4.15 Define Search Procedure to Process Order

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch ManagementBatch Determination and Batch CheckBatch Search

    Procedure DefinitionDefine Search Procedure to Process Order

    Transaction Code SPRO

    ConfigurationDescription

    In this step, we define batch search procedures for batch determination inprocess orders. A batch search procedure comprises all strategy types that can beused for a particular combination of plant and order type

    Search

    procedureDescription Condition Type

    ZO0001 Claris Batch Search Procedure CO03, CO01

  • 5/22/2018 SAP PP Configuration Document

    67/75

    Configuration Document SAP PP-PI Page 67 of 75 Version 1.0

    4.16 Activating Batch Derivation

    Menu PathImplementation Guide for R/3 Customizing (IMG) Logistics - General

    Batch Management Derivation of batch DataActivate batch Derivation

    Transaction Code DVSPConfiguration

    Description

    In this step, we activate Batch derivation

    The Batch Derivation is set as Active


Recommended