R3 MRP LogicR3 MRP Logic
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 2
The purpose of MRP is to guarantee material availability by planning for procurement or production of required quantities.
Convert
Planned Order
Dependent Reqmts
Reservations
Purchase Requisition
Warehouse
ProductionOrder
Planned IndRequirements
Purchase Order
ScheduleLine
Material ReqmtsPlanning
SalesOrders
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 3
R
Sales order /Planned Ind Requirement
Planned order
Purchase requisition
Dependent requirement
Planned order
Dependent requirement
FinishedFinishedproductproduct
Assembly 2Assembly 1
Raw material 3
Raw material 1
Raw material 2
R/3’s MRP is for unconstraint-based planning, APO is for the constraint-based planning
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 4
How the Planning Run Works
Net Requirements Calculation1. Determine Available Warehouse Stock 2. Determine Planned Receipts (after considering existing issues and receipts)3. Calculate the Shortage Quantity
Lot Size CalculationDetermine the lot size of each plan order. R3 Lot Sizing falls into 3categories : Static Lot Size, Optimum Lot Size or Period Lot Size
Procurement Type & SchedulingIn-house Production or External Procurement & Backward Scheduling orForward Scheduling
BOM ExplosionDetermine the valid BOM for explosion
Quota ArrangementA lot can further be split by quota arrangements (MM will cover this)
Net Requirements Calculation ---> Lot Size Calculation ---->-------> Scheduling --------> BOM Explosion ----->-------> Quota Arrangement
Net Requirements Calculation ---> Lot Size Calculation ---->-------> Scheduling --------> BOM Explosion ----->-------> Quota Arrangement
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 5
Firmed receipts: production order, purchase order, firmed planned order
Reschedule in Reschedule out
Tolerance
In-house production time+
Goods receiptprocessing time
+Rescheduling horizon
Receipts
Reqmts
Time
Rescheduling Check for Firmed Receipts
* *Tolerance Tolerance
Exceptionmessage
Exceptionmessage
The planning run will not automatically displace firmed receipts.
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 6
BOM Explosion
Scheduling
Procurement type
Lot-size calculation
Net Reqmts CalculationNet Reqmts Calculation
Overview: Net Requirements Calculation
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 7
MRP: Net Requirements Calculation
ShortageShortage
SalesSales Orders Orders
Planned Ind ReqmtsPlanned Ind Reqmts
Dependent ReqmtsDependent Reqmts
ReservationsReservations
Planned Orders
Production Orders
Purchase Requisitions
Purchase orders
Warehouse Stock
Lot Size
SafetySafety Stock Stock
CompareCompare
DemandSupply
MRP will compare the requirement and supply to get a shortage gap. A comparison is made between warehouse stock and the appropriate receipts and issue. In the net requirements calculation, a difference is made between reorder point planning, forecast-based planning, and MRP. In each procedure, the system calculates available stock differently.
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 8
MRP Procedures
based on consumption in the past
MRPMRP Procedures Procedures
controlled byMRP type in
material master(MRP 1 view)
MRPConsumption-based
Reorder pointplanning
Forecast-basedplanning
Time-phasedplanning
W/ or W/O Requirements
Deterministic Planning
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 9
Master Data
Material Master (Important Ones) MRP Group (MRP1) - Group common MRP materials together MRP Type (MRP1) - Planning Method. Reorder Point (MRP1) - For Reorder Point Planning Methods Planning Time Fence (MRP1) - Restrict Planning Activities within the TimeFence Planning Cycle (MRP1) - Only for Time Phased Planning MRP Controller (MRP1) - Planner for the material Lot Sizing (MRP1) - Lot Size determination Storage Cost Indicators (MRP1) - For Optimum Lot sizing Only Ordering Costs (MRP1)- For Optimum Lot Sizing Only Assembly Scrap (MRP1) - For Assembly Scrap Only Procurement Type (MRP2) - Make or Buy Indicator. Special Procurement (MRP2) - For stock transfers, phantoms etc. Quota Arrangement (MRP2) - Splitting of Quota for internal and/or external
procurement (MM will handle this)
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 10
Master Data (Cont’d)
Material Master (Important Ones) Lead Times (GR and Planned Delivery Time) (MRP2) - Receiving and Purchasing
Lead Times Scheduling Margin Key (MRP2) - How external or internal procurement is
scheduled Safety Stock (MRP2) - Safety Stock Forecast (MRP3 and Forecasting) - Mainly for Forecast Based Planning, ReOrder
Point Planning and Time Phased Planning Planning Strategy (MRP3) - Mainly for Finished Goods - to be decided by APO Availability Check (MRP3) - ATP logic for components - to be decided by ZL. For
Finished Goods - to be decided by APO. Discontinuation (MRP4) - Discontinuation by material across all BOMs Component Scrap (MRP4) - Component Scrap Requirements Grouping (MRP4) - Group requirements for planning or display Storage Location MRP (MRP4) - Only if storage MRP is required
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 11
How the Planning Run Works Per MRP Type
Reorder Point Planning (REORDER) (MRP Type VB, Reorder Level)
When Available Stock falls below reorder level, planned orders are
generated in the planning run to order up to reorder level. Safety Stock
requirement is just for information
Available Stock = Plant Stock + ReceiptsAvailable Stock = Plant Stock + Receipts
Reorder Point Planning + Requirements (REORDERREQS) (MRP Type V1,
Reorder Level)
When Available stock falls below reorder level, planned orders are generated in the planning run to order up to reorder level. Safety stock requirement is just for information. The difference here is that sales orders and reservations are also taken into account.
Available Stock = Plant Stock + Receipts - (Sales Orders + ReservationsAvailable Stock = Plant Stock + Receipts - (Sales Orders + Reservations))
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 12
How the Planning Run Works Per MRP Type
Forecast Based Planning (FORECAST) (MRP Type VV, Create Forecast)System only considers forecast requirements (any other requirements are not considered). Planned orders are proposed when available stock is less than forecast requirements.Available Stock = Plant stock - Safety Stock + Receipts - Forecast RequirementsAvailable Stock = Plant stock - Safety Stock + Receipts - Forecast Requirements
Time Phased Planning (TIMEPLAN) (MRP Type R1, Planning Cycle, CreateForecast)
Material is planned according to same cycle in which it is delivered ie the material is not planned during the normal MRP run. The material have to be planned using a separate MRP run. Available Stock = (Plant stock - Safety Stock + Receipts - Forecast Requirements) Available Stock = (Plant stock - Safety Stock + Receipts - Forecast Requirements) within the planning cyclewithin the planning cycle.
MRP Planned (PDFORECAST) (MRP Type PD, Optional Create Forecast)System checks every requirement to determine whether they are covered by available warehouse stock and/or receipts.Available Stock = Plant stock - Safety Stock + Receipts - All RequirementsAvailable Stock = Plant stock - Safety Stock + Receipts - All Requirements
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 13
Safety stock
Safety stock partially available
Dynamic safety stock
Safety time
Quantity and Time Floats
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 14
Reqmt Receipt
Stock
TimeSafety stock(not availablefor planning)
Availablequantity
for planning
Safety stock: To be set in materialmaster (MRP 2) or in the MRP areasegment
Safety Stock
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 15
Reqmt Receipt
Time
StockAvailablequantity
for planning
Portion of safety stocknot available for planning
Safety stock partially available: set inMRP group
Statisticalsafety stockfrommaterialmasterPortion of
safety stockavailable
Safety
Safety Stock Partially Available
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 16
Minimum stock
Target stock
Maximum stock
Replenish to target stock Exception message
if falls below minimumstock
for firmed order proposals,otherwise adjustment
"dynamicsafety stock“
Dynamic Safety Stock (1)
Stock
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 17
Reqmts
Period 1 Period 2 Period 3 Period 4
Minimum stock
Target stock
Maximum stock
Time
Time
Average daily requirements
Average daily requirements
Average daily requirements
Days
Dynamic Safety Stock and Range of CoverageProfile
Dynamic Safety Stock (2)
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 18
Interval 1 Interval 2 Interval 3
Minimum stock
Target stock
Maximum stock
Reqmts
Time
Time
Definition of range of coverage profile inCustomizing, assignment in material master
Range of Coverage Profile: Intervals (1)
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 19
Interval 1 Interval 2 Interval 3
ReqmtsTime
Time
10.12.200020.12.2000
Periods with deviating range of coverage
Maximum stock
Target stock
Minimum stock
Range of Coverage Profile: Intervals (2)
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 20
Time
Safety time
30.03.28.03.
2 workdaysReceipts
Reqmts
Safety time: To be set inmaterial master (MRP 2) or in
the MRP area segment
Safety Time
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 21
Dep . reqmts
ComponentsTime
Ind reqmt
Finished productTime
+
-
+
-
Safetytime
Reqmtstime
Ind reqmt
Defined using the safety time indicator in the material master (MRP 2) or inthe MRP area segment
Safety Time in Multi-Level Production
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 22
Time
Rec
eip
tsR
eqm
ts
2 workdays
Safety time
4 workdays
2 workdays
12.12.2000 20.12.2000
Safety timeSafety time
Definition of period profile in Customizing,assignment in material master
Period Profile for the Safety Time
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 23
BOM Explosion
Scheduling
Procurement type
Lot-Lot-size calculationsize calculation
Net RequirementsCalculation
Overview: Lot-Size Calculation
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 24
Staticprocedures
Staticprocedures
Lot-for-lot order quantity
Replenishment up tomaximum stock level
Fixed lot size
Periodprocedures
Periodprocedures
Daily lot size
Monthly lot size
Weekly lot size
Flexible periods according to
planning calendar
OptimumproceduresOptimum
procedures
Dynamic lot sizecreation
Least unit costprocedure
Part period procedure
Groff reorder procedure
Lot-Lot- sizing proceduressizing procedures
Overview of Lot-Sizing Procedures
Entered inMaterial master
Definition inCustomizing
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 25
Quantity
Time
Lot-for-lot order quantity (exact to the day)
Replenish up to maximumstock level
Fixed lot size
Receipts
Reqmts
EX
FX
HB
Static Lot-Sizing Procedures
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 26
Time
Period 1 Period 2 Period 3
Period length Period length Period length
Receipts
Reqmts
TB Daily lot size WB Weekly lot size
MB Monthly lot size
Period Lot-Sizing Procedures
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 27
Time
Period 1 Period 2 Period 3
Mon Tue Wed Thu Fri Sat Sun
18
1522
29
1623
3101724
4111825
5121926
6132027
7142128
July 2000
Wed, 3.7.2000
Wed, 1
0.7.2000
Wed
, 17.
7.20
00
Wed
, 24.7.2000PC Period Lot Size Acc. to
Planning Calendar
Lot Size According to Planning Calendar
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 28
Many deliveries/High order costs
Minimal stockkeeping/Minimal storage costs
Few deliveries /Low order costs
More extensive stockkeeping/Higher storage costs
Optimum Lot-Sizing Procedures
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 29
Lot-for-lotorder quantity Monthly lot size
Reqmts previewLong-term
Exact analysisShort-term
Reqmt Receipt
Long-Term Lot Size
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 30
2 months ago
11
Today
22
For 2 months, no eventsrequired a change in
planning, so not plannedduring NETCH + NETPL!
Problem
Maximum MRP period (MRP group)Possible Solution:
Planning Run Executed Regularly
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 31
Additional Restrictions
You can use these additional restrictions to further define lot sizes : Short Term and Long Term Lot Size
(SHORTLONGTERMLOT) (Lot Size Key LL) Minimum Lot Size Maximum Lot Size Rounding Value Rounding Profile
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 32
BOM Explosion
SchedulingScheduling
Procurement typeProcurement type
Lot-size calculation
Net Requirements Calculation
Overview: Scheduling
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 33
External procurementStockStock transfer transfer
Procurement TypesProcurement Types
In-In-house house productionproduction
SubcontractingSubcontracting VendorProductionProduction in in
ownown plant plantProductionProduction in in anotheranother plant plant
Reservation inReservation in anotheranother plant plant ComponentsComponentsComponents
Procurement typesSpecial procurement types
Procurement Types
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 34
Scheduling
The following times are taken into account : processing time required by purchasing
department (workdays) planned delivery time of the material (calendar
days) goods receipt processing time (workdays)
These times will be used to determine the
release date of the planned order or purchase
requisition.
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 35
Planned orderPlanned order
Availabilitydate
Openingdate
Order startdate
Order finishdate
Time
Goods receiptprocessing timeIn-house production timeOpening period
Scheduling marginkey (MRP 2)
Lot-size dependent: MRP 2Lot-size independent: work scheduling
MRP 2
Backward Scheduling for In-House Production
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 36
Availabilitydate
Order startdate
Order finishdate
Time
Goods receiptprocessing time
In-house production time
TodayPlanned orderPlanned order
Automatic, if order start date is in thepast during backward scheduling
Forward Scheduling for In-House Production
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 37
In-house production time
Plnd delivery timeProcessing timefor Purchasing
Order startdate
Order finishdate
CustomizingPlant parameters
Non-vendor-specific:Material masterVendor-specific: Outlineagreement or info record
Deliverydate
Releasedate
Time
... ...
Scheduling for External Procurement
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 38
Lead Time SchedulingLead Time Scheduling Order headerOrder header
Arbeitsvorgänge
Materialkomponenten
Fertigungshilfsmittel
Kosten Plan
Soll
Ist
2050
100
Used for production orders and routings Based on basic dates: MRP manual Target dates calculated (scheduled dates)
Basis for in-house production or operations Capacity requirements calculated Exact to the second
Target start dateTarget finish date
Separate scheduling for planned orders
Order finish dateOrder start dateOpening date
Basic SchedulingBasic Scheduling
tPeriods
Exact to the day Basic dates calculated
Basis for in-house production or replenishment lead time Improved performance No calculation of capacity requirements
Scheduling in Production Planning
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 39
OS Order start date
OF Order finish date
OD Opening date
Time
OD
Product
OS
OF
OD
OS
OF
Raw material
OD
Assembly
OS
OF
Goods receiptprocessing time
Opening period
Reqmts dateProduct
Reqmts dateProductBackward scheduling
Scheduling ind . =1, no capacity requirements
Order Dates for Basic Scheduling
Available
Available
Available
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 40
OS OF
Orderfinish date
Production finish date
Production finish date
Productionstart date
Productionstart date
Order start date
Operations(from routing)Operations
(from routing)
Float before productionScheduling margin key
Float after productionScheduling margin key
10 3020
Planned order
OS OF
11
22
Scheduling ind . = 2, capacity requirements are calculated
Lead Time Scheduling
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 41
OS OF
10 20 30 40 50
Float beforeproduction
Lead time schedulingusing routing
In-house production time shorter
In-house prod. time greater than scheduling in routing
In-house production time from material master
Float afterproduction
Requirements date
CalculationCalculation of of order dates order dates
CalculationCalculation of of planned dates planned dates
Scheduling: Significance of In-house ProductionTime
Wrong in-house production time inmaterial master?
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 42
Time
OS OFOD
10 3020
PS PF
10 3020
10 3020
OS Order start date
OF Order finish date
OD Opening date Opening period
Goods receiptprocessing time
PS Production start date
PF Production finish date
Assembly 1
Product
Assembly 2
Backward scheduling
Order Dates for Lead Time Scheduling
Assembly 2in routingassignedoperation 30
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 43
Finished product
Component 1
Component 2
Determining components
Lead-time offsetLead time
+-Time
Order startdate
Planned order
Dep . reqmts -Lead-time offsetDep . reqmts -
Lead-time offsetDep . reqmts -Lead time
Dep . reqmts -Lead time
BOM maintenance
Changing Dependent Requirement Dates
Note: the lead time and lead-time offset are not taken intoaccount in the lead time scheduling!
Dependent reqmts w/o lead time/lead-time offset
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 44
Scheduling
Procurement type
Lot-size calculation
Net Requirements Calculation
BOM ExplosionBOM Explosion
Overview: BOM Explosion
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 45
Usage quantity/dates
Target
Selection of BOM usage
Selection of Alternative BOM
Change status ofalternative BOM
Component selection
Dependent reqmtsquantities and dates
Usage
Lot size
Explosion date
Items relevant to production
BOM Explosion
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 46
Production versionExplosion date
Lot size
BOM explosion numberOrder finishOrder start
‘1’‘2,3’
Customizing for BOMexplosion
BOM explosion numberOrder finishOrder start
Customizing for BOMexplosion
BOM usage by selection ID
Selection method indicator
Alternative BOM selected
Change status of alternativeBOM determined
Summary: BOM Selection
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 47
Planned orderPriority
1
2
Usage
Production
Engineering
BOM Selection ID
Production BOM
CostingBOM
Engineering BOM
Used if no valid productionBOM exists
Selection of BOM usage
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 48
Order quantity(Lot size)
Order quantity(Lot size)
Explosion dateExplosion date
Production versionProduction version
Alternativeselectionindicator
in
materialmaster
2, 3
1
for multiple BOMs
Selection of Alternative BOM
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 49
Alternative 1
Alternative 2
Lot-size range 0 -10 pieces
Lot-size range 11 - 10,000 pieces
A B
A C
Multiple BOM
Small lot
Large lot
<= 10
pieces
> 10 pieces
( Selection method indicator = blank)
Selection by Order Quantity (Lot Size)
Plannedorder
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 50
Order start dateof a
planned order
BOM explosion number
(gross date)
Order finish dateof a
planned order
BOM explosion using
Planned order
Customizing
Selection by Explosion Date
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 51
Time
AlternativeBOM 1
AlternativeBOM 2
AlternativeBOM 3
Valid from(relevant to
planning from)
Valid from(relevant to
planning from)
Valid from(relevant to
planning from)
Order 1 Order 2
Order startOrder start
( Selection method indicator = 1)
Selection by Order Start
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 52
Time
AlternativeBOM 1
AlternativeBOM 2
AlternativeBOM 3
Valid from(relevant to
planning from)
Valid from(relevant to
planning from)
Valid from(relevant to
planning from)
Order 1 Order 2
Order finishOrder finish
Explosion Date Using the Order Finish Date
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 53
BOM explosion no. xxx
BOM explosion no. xxx
Order for assembly 1
BOM explosion no. xxx
Order for assembly 2
BOMBOM explosion no explosion no.. xxx xxx
Alternative finished products
1.2.2000
Alternatives for assembly 2
Alternatives for assembly 1
Order for product
Explosion Using the BOM Explosion Number
Gross date
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 54
MaterialMaterialmastermaster
Production version 1
Production version 2
Describes production procedure
Routing
BOM Work center(Line
production)
( Selection method indicator = 2 or 3)
Selection by Production Version
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 55
Change status 1 Change status 2 Change status 3
Technical change
Order startOrder start
Order 2Time
Time
Technical change
Same alternative BOM
Order 1
Defining the Change Status Using the Order StartDate
Explosiondate
Explosiondate
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 56
Explosiondate
Change status 1 Change status 2 Change status 3
Order 1
Explosiondate
Order finishOrder finish
Order 2
Technical change
Technical change
Time
Time
Same alternative BOM
Defining Change Status Using the Order FinishDate
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 57
BOM explosion no. xxx
BOM explosion no. xxx
Order for assembly 1BOM explosion no. xxx
Order for assembly 2
BOMBOM explosion no explosion no.. xxx xxxChange status for product
Change status for assembly 2
Change status for assembly 1
Order for product
1.2.2000
Defining Change Status Using BOM ExplosionNumbers
Gross date
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 58
Other MRP Functions
• Planning Time Fence
• Discontinued Parts
• Alternative Parts
• Single and Multi Level Pegging
• Multi-Plant Planning
• Storage Location/MRP Area
• Blocked Storage Location
• Other Special Procurement
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 59
Planning Time Fence
Plan is protected from changes within the planning time fence.
End date of time fence determined from planning date.
You can configure system as to how you want the orders to react within the time fence.
Outside the time fence, system creates order proposal as usual.
When new orders move into the time fence, they may be firmed automatically depending on how the system is configured.
Firming Types for MRP Planned Materials :
Firming TypesOrders Moving Into TimeFence
New Order Proposals Creation
New Order Status
Type 1 Firmed Outside Time Fence Not FirmedType 2 Firmed No Orders Created NAType 3 Not Firmed Outside Time Fence Not FirmedType 4 Not Firmed No Orders Created NA
Firming TypesOrders Moving Into TimeFence
New Order Proposals Creation
New Order Status
Type 1 Firmed Outside Time Fence Not FirmedType 2 Firmed No Orders Created NAType 3 Not Firmed Outside Time Fence Not FirmedType 4 Not Firmed No Orders Created NA
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 60
Carrying Out the Planning Run
Planning File
Types of Planning Run
Regenerative (NEUPL)
Net Change Planning (NETCH)
Net Change Planning in planning horizon (NETPL)
Planning Mode
Creation Indicator
MRP Group vs Plant Parameters
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 61
Evaluating the Planning Run
• MRP List By Material
• MRP List Collective Display
• Stock Requirements List By Material
• Stock Requirements List Collective Display
• Compare MRP List against Stock Requirement List
• Planning situation for Material - (same as stock requirement list ie latest situation for a material)
• Planning result for material - (the last MRP run for the material) - you can compare your current plan against long term planning scenarios or stock requirements list here.
• Situation (all plants) - Review planning situation (ie stock requirement list) for material for all plants
• Order Report - Review your orders in the order report
• Pegged Requirements - Review Pegging
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 62
Important Configurations
• Plant Parameters• MRP Groups• MRP Types• Special Procurement Types• Stock Availability• Lot Size Calculation• Define Floats• Define External Procurement• BOM Explosion / Determine Routing• Define Storage Location/MRP area per Plant• Procurement Proposals
Most Important : Production-->MRP-->Planning File Entries-->Activate MRP and set up planning file
This Configuration should be done before materials are mass created in a new plant
Most Important : Production-->MRP-->Planning File Entries-->Activate MRP and set up planning file
This Configuration should be done before materials are mass created in a new plant
SAP AG 2001, A Business View of mySAP Financials, GBU FIN - 63
Implementation Decisions
• Group materials with common planning profile together.• Decide an MRP Type for each group of materials.• Decide what the lot sizing should be for each material/group of
materials.• Decide for each material, whether you require safety stock and if
safety stock is required, what method of planning the safety stock ?
• Which material require quota arrangements ?• What are the materials that have to be procured from another
plant ? • Are there any storage locations to be blocked from planning ?• Are there storage locations/MRP area needed to be planned
separately ?