+ All Categories
Home > Documents > Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress...

Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress...

Date post: 23-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
19
1 Savannah Harbor Expansion Project SHEP Progress Report April 1 st – April 30 th 2016 Task 1: SCDNR would acquire and insert 10 sonic transmitters per year into Atlantic sturgeon in the Savannah River Estuary and an additional 10 sonic transmitters into shortnose sturgeon. These fish should be collected and tagged with sonic transmitters within or as close as possible to the estuary. The goal would be a 50/50 split between adults/sub-adults and juvenile fish. All sturgeon collected will be weighed, measured, Passive Integrated Transponder (PIT) tagged, and have a fin clip taken for genetic analysis before being released. Overview 1: A total of 46 Atlantic and 47 shortnose sturgeon were captured and five adult/13 juvenile Atlantic and 13 adults/9 juvenile shortnose were transmitted in year 1 and 2 of the study (Table 1). In year three, 35 Atlantic and 26 shortnose have been captured with five adult/five juvenile Atlantic and five adult shortnose transmitted. (Table 2). Fish condition precludes some fish from receiving transmitters. Efforts will continue in order to catch juvenile shortnose sturgeon in year three of study. *Note: Differences in numbers of sturgeon captured from earlier progress reports are due to a corrupted excel database used to store the capture data. The current numbers of sturgeon captured in this April report have been validated and are correct. Task 2: SCDNR would acquire and insert 10 sonic transmitters per year into Atlantic sturgeon in the Savannah River, 10 sonic transmitters into shortnose sturgeon, and 20 transmitters into other species representative of the New Savannah Bluff Lock and Dam (NSBL&D) area fish community (Striped bass, Robust redhorse, and American shad). These fish should be collected and tagged with sonic transmitters within or as close as possible to the NSBL&D. If sufficient numbers of sturgeon are not available for capturing, tagging and tracking in the upper river, transmitters can be implanted in other species representative of the NSBL&D fish community, preferably American shad. Overview 2: Task 2 was not funded by the USACE Task 3: Acquisition, operation, and maintenance of 23 receivers per year are included in the statement of work. Receivers would be concentrated in the estuary, where the impacts of harbor deepening are anticipated (Figure 1). Overview 3: Twenty-five receivers have been deployed from the South Channel of Savannah River to Front River at river kilometer (rkm) 50, Middle, and Back River (Table 3). GPS locations of receivers and locations of tagged fish (residency master list) are also included as part of this progress report. All receivers were downloaded, and resulting telemetry data will continue to be shared with UGA with provided residency master list.
Transcript
Page 1: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

1  

Savannah Harbor Expansion Project

SHEP Progress Report April 1st – April 30th 2016

Task 1: SCDNR would acquire and insert 10 sonic transmitters per year into Atlantic sturgeon in the Savannah River Estuary and an additional 10 sonic transmitters into shortnose sturgeon. These fish should be collected and tagged with sonic transmitters within or as close as possible to the estuary. The goal would be a 50/50 split between adults/sub-adults and juvenile fish. All sturgeon collected will be weighed, measured, Passive Integrated Transponder (PIT) tagged, and have a fin clip taken for genetic analysis before being released. Overview 1: A total of 46 Atlantic and 47 shortnose sturgeon were captured and five adult/13 juvenile Atlantic and 13 adults/9 juvenile shortnose were transmitted in year 1 and 2 of the study (Table 1). In year three, 35 Atlantic and 26 shortnose have been captured with five adult/five juvenile Atlantic and five adult shortnose transmitted. (Table 2). Fish condition precludes some fish from receiving transmitters. Efforts will continue in order to catch juvenile shortnose sturgeon in year three of study. *Note: Differences in numbers of sturgeon captured from earlier progress reports are due to a corrupted excel database used to store the capture data. The current numbers of sturgeon captured in this April report have been validated and are correct. Task 2: SCDNR would acquire and insert 10 sonic transmitters per year into Atlantic sturgeon in the Savannah River, 10 sonic transmitters into shortnose sturgeon, and 20 transmitters into other species representative of the New Savannah Bluff Lock and Dam (NSBL&D) area fish community (Striped bass, Robust redhorse, and American shad). These fish should be collected and tagged with sonic transmitters within or as close as possible to the NSBL&D. If sufficient numbers of sturgeon are not available for capturing, tagging and tracking in the upper river, transmitters can be implanted in other species representative of the NSBL&D fish community, preferably American shad. Overview 2: Task 2 was not funded by the USACE Task 3: Acquisition, operation, and maintenance of 23 receivers per year are included in the statement of work. Receivers would be concentrated in the estuary, where the impacts of harbor deepening are anticipated (Figure 1). Overview 3: Twenty-five receivers have been deployed from the South Channel of Savannah River to Front River at river kilometer (rkm) 50, Middle, and Back River (Table 3). GPS locations of receivers and locations of tagged fish (residency master list) are also included as part of this progress report. All receivers were downloaded, and resulting telemetry data will continue to be shared with UGA with provided residency master list.

Page 2: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

2  

Task 4: To allow identification of fish movement upstream of the NSBL&D, the contractor should locate 5 receivers between NSBL&D and the Augusta Shoals. Overview 4: Task 4 was not funded by the USACE Task 5: Manual tracking of instrumented fish will occur monthly July – September and at least quarterly for the remainder of the year. Overview 5: Manual tracking efforts were completed on April 8th with an emphasis on locating transmitted fish in Front, Middle, and Back Rivers. Temperature, salinity, dissolved oxygen, and conductivity were recorded at 1-meter water depth intervals at the location of each detected sturgeon. Planned downloads of estuarine receivers should provide information for missing fish with subsequent manual tracking efforts based on those locations. Manual tracking data is updated and available in the provided manual tracking database.

Page 3: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

3  

Table 1. Sturgeon, Striped Bass, and American Shad Capture Data for the Savannah River

SHEP - Project Year 1 and 2

Page 4: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

4  

Table 1. Sturgeon, Striped Bass, and American Shad Capture Data for the Savannah River

SHEP - Project Year 1 and 2 (continued)

Page 5: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

5  

Table 2. Sturgeon Capture Data for the Savannah River SHEP - Project Year 3

 

  

Page 6: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

6  

Table 3. GPS Coordinates of Savannah River Receiver Locations

Receiver # Station Name Latitude Longitude

111318 Savannah Jetty 32⁰02.074'N 80⁰51.064'W

111321 RM 0 32⁰02.248'N 80⁰53.990'W

111717 RM 3 32⁰04.274'N 80⁰57.289'W

111316 RM 6 32⁰04.616'N 80⁰57.394'W

111293 RM 9 32⁰05.390'N 81⁰01.173'W

111292 RM 15 32⁰04.972'N 81⁰05.615'W

108392 RM 17 32°07.596'N 81°08.058'W

108385 RM 17.5 32°08.188'N 81°08.383'W

111654 RM 18.5 32⁰08.699'N 81⁰08.416'W

111652 RM 21.5 32⁰09.647'N 81⁰09.256'W

111648 RM 22.5 32⁰10.971'N 81⁰09.368'W

111655 RM 24 32⁰11.816'N 81⁰09.259'W

111659 RM 27.5 32⁰14.164'N 81⁰09.012'W

111333 MR RM 0 32⁰08.794'N 81⁰07.974'W

111326 MR RM 1.5 32⁰09.523'N 81⁰08.253'W

111650 MR RM 2.5 32⁰10.342'N 81⁰08.150'W

111653 MR RM 4 32⁰11.602'N 81⁰08.252'W

111647 MR RM 5 32⁰12.613'N 81⁰08.289'W

111305 BR RM 4 32⁰06.673'N 81⁰06.471'W

111325 BR RM 7 32⁰08.704'N 81⁰07.236'W

111657 BR RM 9.5 32⁰10.068'N 81⁰07.790'W

111651 BR RM 13.5 32⁰11.574'N 81⁰07.096'W

111658 BR RM 16.5 32⁰13.280'N 81⁰08.598'W

111766 RM 31.5 32⁰16.141'N 81⁰08.052'W

111755 Abercorn RM 0 32⁰14.952'N 81⁰09.191'W

111754 Abercorn RM 1 32⁰15.127'N 81⁰10.057'W

111753 RM 39 32⁰20.490'N 81⁰07.932'W

111825 RM 45 32⁰22.882'N 81⁰10.856'W

111818 RM 53 32⁰27.582'N 81⁰11.424'W

111824 RM 61.5 32⁰31.723'N 81⁰16.084'W

111764 RM 68 32⁰33.678'N 81⁰18.593'W

111826 RM 74 32⁰35.544'N 81⁰22.437'W

111813 RM 79.5 32⁰38.516'N 81⁰24.591'W

111759 RM 85.5 32⁰41.699'N 81⁰24.622'W  

Page 7: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

7  

Table 3. GPS Coordinates of Savannah River Receiver Locations (continued)

Receiver # Station Name Latitude Longitude 111756 RM 89.5 32⁰43.956'N 81⁰24.958'W

111758 RM 94.5 32⁰46.322'N 81⁰25.766'W

111814 RM 100.5 32⁰48.034'N 81⁰25.761'W

111757 RM 105 32⁰50.435'N 81⁰26.475'W

111763 RM 110.5 32⁰52.905'N 81⁰27.962'W

111762 RM 115.5 32⁰54.521'N 81⁰28.952'W

111752 RM 119 32⁰56.234'N 81⁰30.159'W

111815 RM 123 32⁰58.508'N 81⁰29.767'W

111820 RM 125.5 33° 0.3180'N 81° 29.688'W

111819 RM 133 33° 2.6160'N 81° 33.402'W

111821 RM 137  33° 4.3680'N 81° 35.502'W

111823 RM 147  33° 6.9420'N 81° 41.910'W

111812 RM 153  33° 10.578'N 81° 46.152'W

111716 RM 157  33° 13.044'N 81° 46.080'W

111817 RM 161.5  33° 13.542'N 81° 49.014'W

111715 RM 168  33° 15.810'N 81° 50.166'W

111721 RM 173  33° 17.946'N 81° 51.054'W

111718 RM 177.5  33° 19.656'N 81° 54.594'W

111816 RM 182  33° 19.656'N 81° 54.594'W

111720 RM 186  33° 21.540'N 81° 56.298'W

111719 RM 187  33° 22.302'N 81° 56.670'W

111822 RM 187.5  33° 22.308'N 81° 56.232'W

123576 RM 190 (Jason's Dock) 33° 23.052'N 81° 55.864'W

123593 Rm 199.7 (Marina) 33° 28.613'N 81° 57.591'W

123597 Lower Shoals 33° 30.751'N 82° 00.096'W

123601 Upper Shoals 33° 32.889'N 82° 02.157'W

123591 I20 Downstream 33° 31.458'N 82° 00.674'W  

Page 8: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

8  

Figure 1. Vemco receiver locations within proximity to the King Island Turn Basin.

Page 9: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

9  

Appendix 1

Pictures of Project

Page 10: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

10  

Page 11: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

11  

Page 12: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

12  

Page 13: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

13  

Page 14: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

14  

Page 15: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

15  

Page 16: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

16  

Page 17: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

17  

Page 18: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

18  

Page 19: Savannah Harbor Expansion Project Sturgeon...1 Savannah Harbor Expansion Project SHEP Progress Report April 1st – April 30th 2016 Task 1: SCDNR would acquire and insert 10 sonic

19  


Recommended