+ All Categories
Home > Documents > SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

Date post: 08-Apr-2018
Category:
Upload: buildbhs
View: 212 times
Download: 0 times
Share this document with a friend

of 81

Transcript
  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    1/81

    Blacksburg High School

    Repairs and Gym ReplacementSeptember 23, 2010

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    2/81

    Team

    OWPRArchitects and Engineers

    Contractors

    Dr. Barker Independent StructuralConsultant verifyingOWPRs methodology

    Town ofBlacksburg

    Montgomery County

    Public Schools

    Testing Agencies

    MBPConstruction Manager

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    3/81

    Investigation and Testingthat has occurred at Blacksburg High School

    Investigation/Testing Findings

    1. OWPR Facility Assessment

    Visual inspection of building components and systems

    Floor elevation survey (documenting floor level and flatness)

    Repairs necessary - (Category 1 Items)

    2. Wall Settlement

    Electrical resistivity testing Used ground probes in a grid arrangement throughout the

    building and site to profile subsurface conditions

    Test Borings

    Drilled test borings in several locations inside and outside ofbuilding to identify soils and subsurface conditions

    Data indicated no large voids under building. Data

    found four possible voids outside of the building. Testborings are recommended at these locations todetermine if open voids are present.

    No unusual soil conditions and no unusual subsurfacefindings, other than those at three locations whereunderpinning can be installed.

    3. Auditorium Structural System Repair Forensic Engineer investigation of the gym collapse (FORCON)

    Auditorium structural steel roof framing members and welds

    Used ultrasound to examine full-penetration welds

    Repairs necessary to Auditorium steel construction(similar to gym)

    4. Deficient Concrete Beams

    Non-destructive testing to determine size, quantity, and location of

    reinforcing steel in concrete beams (28% of beams tested)

    Used ground penetrating radar (GPR) and R meter

    Used destructive testing to verify the results

    Reinforcing steel strength testing

    Repairs necessary

    100% of beams need to be tested

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    4/81

    Ccr

    Ccr

    Geology of the Site

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

    mCopper Ridge Formation (lower Knox Group): Interbedded medium-gray. fine- to medium-grained. locaJJyCcr crossbedded sandy dolomite and medium-gray. finegrained, rrKlssive dolomite. s. upper siliceous oolite and- " " quartzose sandstone; discontinuous sandstone and sili-_ (, ceous oolite near the middle; and basal {eldspathic':i sandstone. Tellerina (F-946), an indicator or Tremp-ealeau age. is found within one horizon. The uppersandstone marker bed consists of about 10-20 feet(3.1-6.1 m) of interbedded siliceous oolite andmedium-grained quartzose sandstone. The bm;al sandstone marker bed consists of about 10-20 feet (3.1-6.1 m) o f predominantly light-gray, fine- to mediumgrained feic/$pathic sandstone interbedded with lesseramounts of sandy dolomite. Total thickness is about1200 feet (366 m). The soil is characterized by a thick(10-20 feet; 3.1-6.1 m) colluvial mantle with abundantsiliceous oolite, sandstone, and chert detritus overlyinga thick brown subsoil and saprolite.

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    5/81

    Summary of Karst Formation

    Rainwater becomes slightlyacidic with dissolved CO2.

    Water percolates intolimestone bedrock alongfractures, joints, bedding

    planes

    Limestone or dolomite

    slowly dissolves away,forming cave passages andnatural conduits for waterflow

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    6/81

    Sinkhole Formation- Cover Subsidence

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    7/81

    Sinkhole Formation- Cover Collapse

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

    Overburdenm o r y day)

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    8/81

    Types of Karst Features

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

    r

    l( ~

    .-"-E'08-

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    9/81

    Resistivity Imaging for Identifying Karst

    ~46cm(18

    in)

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    10/81

    Factors Effecting Resistivity

    Moisture

    Grain Size

    Mineral Content

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    11/81

    Voids

    Sinkholes

    Voids

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    12/81

    Potential Ledges or Float

    Cutters and Pinnacles

    Cutters and Pinnacles

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    13/81

    Collected Data for 12 Resistivity Sections

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

    Ii(

    ..

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    14/81

    9

    Line 9

    possible fracturezones

    Results of Line 9

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    15/81

    1

    5

    Southwest Northeast

    Line 5

    bedrockwall

    likely fractureand/or solutional

    zones

    Line 1

    gymnasiumTennis courts

    likelyfracture

    zone

    possiblesolutional zones

    possiblesolutional zone

    Results of Lines 1 and 5

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    16/81

    Lines of Evidence That the Problem is Not

    From Ongoing Geologic Processes

    The Copper Ridge Formation is not a

    Strong Karst Former

    There are no Sinkholes, Springs, or

    Disappearing Streams on or Near the Site Water is the Engine to Ongoing Karst

    Formation- Hardscape Prevents Infiltration There is no Evidence in the Geophysical

    Data of Voids Beneath the Building

    ATS InternationalAdvanced Technical Services

    www.ats-intl.com

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    17/81

    Questions about Testing and Investigations

    //

    ARCHITECTS AND ENGINEERS

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    18/81

    1. Category 1 items from OWPR Facility Assessment

    2. Wall settlement in three locations

    3. Auditorium roof structural steel

    4. Deficient concrete beams

    Items to be Repaired

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    19/81

    Repair of Category I Items from OWPR FacilityAssessment

    Issue Solution Spalling concrete on columns and beams Epoxy mortar repair

    Cracks Epoxy injection

    Collateral damage from gym collapse Repair as required

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    20/81

    Estimate for Cost of Category 1Repairs

    Description Budget Estimate BidorProposal

    1.Category1ItemsfromOWPRFacilityAssessment $ 141,000.00 General&Mech.Services(GMS)

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    21/81

    Questions about the Repair of Category 1 Itemsfrom the OWPR Facility Assessment

    //

    M BOLYARDPECKBP McDONOUGH

    ARCHITECTS AND ENGINEERS

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    22/81

    Wall Settlement in Three Locations

    Issue Solution

    Wall settlement in Boiler Room, Auto Shop, and Wood Working Shop Install foundation underpinning (helical piers)

    Description Budget Estimate BidorProposal

    WallSettlementRepairsinthreelocations $ 66,000.00 RACConstructionCompany

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    23/81

    Questions about Wall Settlement Repairs

    //

    M BOLYARDPECKBP McDONOUGH

    ARCHITECTS AND ENGINEERS

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    24/81

    Auditorium Roof Structural Steel

    Issue Solution

    Defective full-penetration welds at various locations

    Various under-sized steel truss members

    Reinforce welds with additional steel plates

    Reinforce with additional steel members

    Note: A 30 length of the west wall of the auditorium exceeds the

    maximum allowable height for its construction and will require steelbracing to the roof framing. This work will be done when theauditorium trusses are repaired and will be concealed above theceiling.

    Description Budget Estimate BidorProposal

    AuditoriumRoofStructuralSystem $ 170,000.00 CSESteelErection&GMS

    Cross Section of Failed Weld from Gym Truss Seat Auditorium Truss Seat

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    25/81

    Questions about Auditorium Repairs

    , /

    /

    M B ~ ~ H ARCHITECTS AND ENGINEERS

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    26/81

    Deficient Concrete Beams

    Issue Solution

    Inadequate reinforcing steel within concrete beams Carbon fiber reinforcement or additional steeland concrete

    Area of Destructive Testing to Verify Reinforcing Steel

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    27/81

    Concrete is artificial stone

    Steel reinforcing is placed in the tension zone

    The two materials are combined, each material utilizing its bestproperties

    Reinforced Concrete 101

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    28/81

    Water flows down hill

    You cannot push rope

    Bodies in motion produce forces

    Basic Civil Engineering Principles

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    29/81

    Bending moments must balance; externally and internally

    Bending Moment a force times a distance

    G

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    30/81

    Beam a horizontal structural member supporting vertical loads by bending

    Glossary

    Gl

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    31/81

    Cantilevered Beam a beam that projects beyond a supportingcolumn or wall

    Glossary

    Gl

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    32/81

    Column A vertical structural member supporting vertical loads bycompression

    Glossary

    C

    C ti R i f d C t B

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    33/81

    Continuous Reinforced Concrete Beam

    I ,I. ITI

    ,I. ,I I J J JTI

    " ,l I,

    Where is the tension?

    TIT T TTIT T TTIT// Where does the steel g07IT IT IT

    What happens i f new supports are added between columns?

    ,I. ,I. ,lTI

    I ,I. I,

    T TTIT

    IT

    I, 1 1

    T

    IT

    TIT

    IT

    MBP McDONOUGHBOLYARDPECK

    ARCHITECTS AND ENGINEERS

    I d d t R i f OWPR M th d l

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    34/81

    Used original engineering drawings, specifications, schedules andbuilding codes

    Verified OWPRs computations and methodology

    Verified computer output all computer results are wrong unlessproven otherwise

    Independent Review of OWPRs Methodology

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    35/81

    Strengthening and Repairof Reinforced Concrete

    Structures

    Ian Wienholt

    Business Development Manager

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    36/81

    34 years of Concrete Repair and

    Strengthening Experience Over 15,000 Repair Project

    Over 25,000 PT Projects

    1,500 Employees

    22 Offices- International

    UAE, UK, Saudi, China

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    37/81

    General Repair Group:

    Strengthening Division

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    38/81

    Carbon Fiber Reinforced PolymerStrengthening

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    39/81

    Externally Bonded FRP Sheet

    550,000 psi Tensile

    10x that of steel

    Lightweight

    Does NOT corrode

    FRP Design Guidelines

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    40/81

    FRP Design Guidelines

    440.2R-02 440.2R-08

    To Date:

    Nationwide 15-18M sqft installedSPS 7M sqft installed on over 700 + projects

    ACI 4 40.2R-08

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    41/81

    Tension Steel

    Yield

    FRP carries

    TENSION

    What Is FRP Flexural Strengthened R/C?

    Positive Moment

    Wh I FRP Fl l S h d R/C?

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    42/81

    CompressionConcrete carries

    COMPRESSION

    TOP

    BOTTOM

    SteelTension

    Yield

    FRP carries

    TENSION

    What Is FRP Flexural Strengthened R/C?

    Column

    Negative Moment

    What Is FRP Shear Strengthened R/C?

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    43/81

    SHEAR

    What Is FRP Shear Strengthened R/C?

    Installation Step 1:

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    44/81

    Installation Step 1:

    Surface Grinding/Shot Blastingto Open Pores

    I ll i S

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    45/81

    Installation Step 2:

    Remove Dust from Surface

    Before After

    I ll i S 3

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    46/81

    Installation Step 3:

    Epoxy Primer Application

    I ll i S 4

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    47/81

    Installation Step 4:

    Epoxy Putty Trowel Applied

    I ll i S 5

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    48/81

    Installation Step 5:

    Saturation Coat and CFRP

    I t ll ti St 6

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    49/81

    Installation Step 6:

    Rib Roll & Final Saturation Coat

    I t ll ti St 7

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    50/81

    Installation Step 7:

    Intumescent Topcoat

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    51/81

    External Post TensioningStrengthening

    E t l P t T i i

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    52/81

    External Post Tensioning

    F

    F

    NEW LOAD

    Upliftat Deviator

    Dead end

    Live end

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    53/81

    Flexural Strengthening Case Study

    Environmental Overload

    Tension Tension

    YIELD

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    54/81

    Flexural Strengthening Case Study

    Environmental Overload

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    55/81

    Flexural Strengthening Case Study

    Environmental Overload

    Form & Pump

    Amplitude

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    56/81

    Flexural Strengthening Case Study

    Environmental Overload

    Dowel Hole Drilling

    High Pressure Water Blasting

    Dowel Insertion

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    57/81

    Flexural Strengthening Case Study

    Environmental Overload

    Fl l S h i C S d

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    58/81

    Flexural Strengthening Case Study

    Environmental Overload

    Fl l S h i C S d

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    59/81

    Flexural Strengthening Case Study

    Environmental Overload

    Fl l St th i C St d

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    60/81

    Flexural Strengthening Case Study

    Environmental Overload

    Fl l St th i C St d

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    61/81

    Flexural Strengthening Case Study

    Environmental Overload

    Fl l St th i C St d

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    62/81

    Flexural Strengthening Case Study

    Environmental Overload

    43

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    63/81

    SCC Section EnlargementStrengthening

    Transfer Slab Cracking

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    64/81

    Transfer Slab Cracking

    / I

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    65/81

    Demo and Prep

    PAM Machine in Action

    Supplemental Beam Column

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    66/81

    Supplemental Beam-Column

    Connection

    Mechanical Anchoring and

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    67/81

    Mechanical Anchoring and

    Reinforcement Cage

    2000

    UndercutAnchors

    3000 HiltiStuds

    SCC Pumping Anyone???

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    68/81

    SCC Pumping Anyone???

    40 Tons ofSteel

    1100LF

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    69/81

    Finished Product

    185 CU YDS /

    375 Tons of

    Concrete

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    70/81

    Finished Product

    Estimated Cost of Beam Testing and Repairs

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    71/81

    Description Budget Estimate BidorProposal

    TestingofConcreteBeams $ 95,000.00 RadarView

    Demolition/RepairWallsforTesting $ 325,000.00 EstimatebyGMS&MBP

    Tearoff/PatchRoofforTesting $ 259,000.00 BakerRoofing

    SubtotalTestingofConcreteBeams $ 679,000.00DeficientConcreteBeams $ 3,400,000.00 StructuralPreservationSystems

    SubtotalofStructuralRepairs $ 3,400,000.00ReplaceRoofafterRepairs $ 715,000.00 BakerRoofingkerRoofing

    SubtotalofStructuralRepairs&Testing $ 4,079,000.00

    Contingency $ 1,423,680.00

    Total $ 5,502,680.00

    Questions about Concrete Beam Repairs

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    72/81

    //

    M BOLYARDPECKBP McDONOUGH

    ARCHITECTS AND ENGINEERS

    Estimated Cost of Gym Replacement

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    73/81

    Description Budget Estimate

    GeneralConditionsareincludedineachoftheitemsbelow $

    Sitework&Demo $ 615,257.00

    Concrete $ 1,020,386.00

    Masonry $ 548,958.00

    Metals $ 448,002.00

    Wood&Plastics $ 9,042.00

    Thermal&MoistureProtection $ 236,398.00

    Doors&Windows $ 112,361.00

    Finishes $ 295,720.00

    Equipment $ 1,271,599.00

    Elevator $ 50,000.00

    Plumbing,Heat,Ventilation&AirConditioning $ 1,460,794.00

    Electrical $ 876,003.00

    SubTotalConstruction $ 6,944,520.00

    Permits $ 12,900.00

    A/EFees $ 1,041,700.00

    CostEstimating $ 14,000.00

    Geotechnical&StructuralTests $ 100,000.00

    Engineering&SpecialTesting $ 40,000.00

    QualityAssurance&TestingFees $ 17,200.00

    ConstructionManagement $ 300,000.00

    SubTotalFees&SoftCost $ 1,525,800.00

    Total $ 8,470,320.0010%Contingentlyincludedinallitemsabove

    Thisestimateincudes costto rebuildtheentirelowerlevelfoundation,structure,exteriorandinteriorwalls

    Questions about Gym Replacement Estimate

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    74/81

    , //

    M B ~ ~ H ARCHITECTS AND ENGINEERS

    Estimated Total Cost Repairs and

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    75/81

    Gym Replacement

    Description Budget Estimate Bid

    or

    Proposal

    TestingofConcreteBeams $ 95,000.00 RadarView

    Demolition/RepairWallsforTesting $ 325,000.00 EstimatebyGMS&MBP

    Tearoff/PatchRoofforTesting $ 259,000.00 BakerRoofing

    SubtotalTestingofConcreteBeams $ 679,000.001.Category1ItemsfromOWPRFacilityAssessment $ 141,000.00

    General&Mech.Services

    (GMS)

    2.WallSettlementRepairsinthreelocations $ 66,000.00 RACConstructionCompany

    3.AuditoriumRoofStructuralSystem $ 170,000.00 CSESteelErection&GMS

    4.DeficientConcreteBeams $ 3,400,000.00

    StructuralPreservation

    Systems

    CM/DesignDocuments $ 250,000.00 OWPR&MBP

    SubtotalofStructuralRepairs $ 4,027,000.00ReplaceRoofafterRepairs $ 715,000.00 BakerRoofingkerRoofing

    SubtotalofStructuralRepairs&Testing $ 4,706,000.00CM/DesignDocuments $ 250,000.00 OWPR&MBP

    Contingency $1,423,680

    GymReplacementEstimatedCost $ 8,470,320Testing,Repairs,andGymReplacement $ 14,850,000

    Schedule

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    76/81

    /

    o".. .oN

    ".. ." . . .oN

    N".. .

    Repair offrom OWPR

    FacilityAssessment

    Repair of WallSettlement inBoiler Room,Auto Shop, and

    Wood Working

    Pro ctRepair

    Auditorium RoofStructural Steel

    Repair Deficientncrete(including

    testing)GymReplacement

    MB BOLYARDPECKP McDONOUGH

    ARCHITECTS AND ENGINEERS

    Work that can be Done to Improve InteriorEnvironment and Building Operations

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    77/81

    Environment and Building Operations

    Description EstimateReplaceHeating,Ventilation,AirConditioning $ 3,300,000.00

    ReplaceFireAlarm $ 265,000.00

    Upgrade

    Plumbing

    Fixtures

    to

    ADA

    Requirements $

    200,000.00

    SubTotalBuildingInfrastructureUpgrades $ 3,765,000.00ReplaceVinylFloorTile $ 256,000.00

    ReplaceCarpet $ 91,000.00

    PaintInteriorWalls $ 418,000.00

    ReplaceCeilingGridandTiles $ 418,000.00

    ReplaceAuditoriumSeating $ 210,000.00

    SubTotalFinishesReplacement $ 1,393,000.00ReplaceFurnitureandUpgradeTechnology $ 1,500,000.00

    AddSprinklerSystem $ 838,000.00

    SubTotalUpgrades $ 7,496,000.00

    BHS Existing Mechanical

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    78/81

    Heating Plant Two 250 BHP, dual fuel, Scotch Marine 2-pass fire tube boilers,original

    Heating Distribution Primary pumps, 20 HP centrifugal. Secondary pumps: severalinline pumps.

    Cooling Plant Two 325 Ton variable speed Centrifugal Chillers with forced draftcooling towers, new.

    Cooling Distribution Primary pumps, 50 HP centrifugal. Secondary pumps: severalinline pumps.

    Auditorium Four pipe with Air Handling Units.

    Classrooms Four Pipe unit ventilators in exterior Classrooms. Variable Air VolumeBoxes with hot water heat in interior classrooms

    Administration - Variable Air Volume Boxes with hot water heat.

    Library Four pipe with Air Handling Units.

    Vo. Tech Four Pipe air handling units with hot water reheat.

    Band/Coral Four Pipe air handling units with hot water reheat.

    Cafeteria / Kitchen - Four pipe with Air Handling Units and unit ventilators.

    BHS is basically a Four Pipe Fan Coil Unit system.

    Proposed Mechanical

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    79/81

    Systems Cost

    Heating

    Plant

    Leave

    as

    is.HeatingDistribution Leaveasis.

    CoolingPlant Leaveasis.

    CoolingDistribution Leaveasis.

    Auditorium ReplaceairhandlersandprovideCO2controls. $138,400

    Stage ReplaceairhandlersandprovideCO2controls. $48,100

    Commons ReplaceairhandlerandprovideCO2controls. $65,000

    Library ReplaceairhandlerandprovideCO2controls. $48,000

    Aud.Lobby Replaceairhandler. $21,000

    Vo.Tech Replaceairhandlersandprovidefancoilunitsinsmallspaces. $263,000

    Band/Coral Replaceairhandlersandprovidefancoilunitsinsmallspaces. $72,000

    Administration ReplacewithDOAUw/activechilledbeamsorfancoilunits. $126,000

    Classrooms ReplacewithDOAUw/activechilledbeamsorunitventilators. $520,000

    Ductwork Cleansupplyandreturnductsthataretoremain $200,000

    Controls Provide

    new

    DDC

    control

    system $700,000Total $2,201,500

    OH&PandContingencyx1.5 $3,300,000

    DOAU DedicatedOutdoorAirUnit

    Work that can be Done to Improve InteriorEnvironment and Building Operations

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    80/81

    Environment and Building Operations

    Description EstimateReplaceHeating,Ventilation,AirConditioning $ 3,300,000.00

    ReplaceFireAlarm $ 265,000.00

    Upgrade

    Plumbing

    Fixtures

    to

    ADA

    Requirments $

    200,000.00

    SubTotalBuildingInfrastructureUpgrades $ 3,765,000.00ReplaceVinylFloorTile $ 256,000.00

    ReplaceCarpet $ 91,000.00

    PaintInteriorWalls $ 418,000.00

    ReplaceCeilingGridandTiles $ 418,000.00

    ReplaceAuditoriumSeating $ 210,000.00

    SubTotalFinishesReplacement $ 1,393,000.00ReplaceFurnitureandUpgradeTechnology $ 1,500,000.00

    AddSprinklerSystem $ 838,000.00

    SubTotalUpgrades $ 7,496,000.00

    Questions/Discussions

  • 8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)

    81/81

    //


Recommended