of 81
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
1/81
Blacksburg High School
Repairs and Gym ReplacementSeptember 23, 2010
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
2/81
Team
OWPRArchitects and Engineers
Contractors
Dr. Barker Independent StructuralConsultant verifyingOWPRs methodology
Town ofBlacksburg
Montgomery County
Public Schools
Testing Agencies
MBPConstruction Manager
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
3/81
Investigation and Testingthat has occurred at Blacksburg High School
Investigation/Testing Findings
1. OWPR Facility Assessment
Visual inspection of building components and systems
Floor elevation survey (documenting floor level and flatness)
Repairs necessary - (Category 1 Items)
2. Wall Settlement
Electrical resistivity testing Used ground probes in a grid arrangement throughout the
building and site to profile subsurface conditions
Test Borings
Drilled test borings in several locations inside and outside ofbuilding to identify soils and subsurface conditions
Data indicated no large voids under building. Data
found four possible voids outside of the building. Testborings are recommended at these locations todetermine if open voids are present.
No unusual soil conditions and no unusual subsurfacefindings, other than those at three locations whereunderpinning can be installed.
3. Auditorium Structural System Repair Forensic Engineer investigation of the gym collapse (FORCON)
Auditorium structural steel roof framing members and welds
Used ultrasound to examine full-penetration welds
Repairs necessary to Auditorium steel construction(similar to gym)
4. Deficient Concrete Beams
Non-destructive testing to determine size, quantity, and location of
reinforcing steel in concrete beams (28% of beams tested)
Used ground penetrating radar (GPR) and R meter
Used destructive testing to verify the results
Reinforcing steel strength testing
Repairs necessary
100% of beams need to be tested
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
4/81
Ccr
Ccr
Geology of the Site
ATS InternationalAdvanced Technical Services
www.ats-intl.com
mCopper Ridge Formation (lower Knox Group): Interbedded medium-gray. fine- to medium-grained. locaJJyCcr crossbedded sandy dolomite and medium-gray. finegrained, rrKlssive dolomite. s. upper siliceous oolite and- " " quartzose sandstone; discontinuous sandstone and sili-_ (, ceous oolite near the middle; and basal {eldspathic':i sandstone. Tellerina (F-946), an indicator or Tremp-ealeau age. is found within one horizon. The uppersandstone marker bed consists of about 10-20 feet(3.1-6.1 m) of interbedded siliceous oolite andmedium-grained quartzose sandstone. The bm;al sandstone marker bed consists of about 10-20 feet (3.1-6.1 m) o f predominantly light-gray, fine- to mediumgrained feic/$pathic sandstone interbedded with lesseramounts of sandy dolomite. Total thickness is about1200 feet (366 m). The soil is characterized by a thick(10-20 feet; 3.1-6.1 m) colluvial mantle with abundantsiliceous oolite, sandstone, and chert detritus overlyinga thick brown subsoil and saprolite.
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
5/81
Summary of Karst Formation
Rainwater becomes slightlyacidic with dissolved CO2.
Water percolates intolimestone bedrock alongfractures, joints, bedding
planes
Limestone or dolomite
slowly dissolves away,forming cave passages andnatural conduits for waterflow
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
6/81
Sinkhole Formation- Cover Subsidence
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
7/81
Sinkhole Formation- Cover Collapse
ATS InternationalAdvanced Technical Services
www.ats-intl.com
Overburdenm o r y day)
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
8/81
Types of Karst Features
ATS InternationalAdvanced Technical Services
www.ats-intl.com
r
l( ~
.-"-E'08-
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
9/81
Resistivity Imaging for Identifying Karst
~46cm(18
in)
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
10/81
Factors Effecting Resistivity
Moisture
Grain Size
Mineral Content
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
11/81
Voids
Sinkholes
Voids
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
12/81
Potential Ledges or Float
Cutters and Pinnacles
Cutters and Pinnacles
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
13/81
Collected Data for 12 Resistivity Sections
ATS InternationalAdvanced Technical Services
www.ats-intl.com
Ii(
..
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
14/81
9
Line 9
possible fracturezones
Results of Line 9
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
15/81
1
5
Southwest Northeast
Line 5
bedrockwall
likely fractureand/or solutional
zones
Line 1
gymnasiumTennis courts
likelyfracture
zone
possiblesolutional zones
possiblesolutional zone
Results of Lines 1 and 5
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
16/81
Lines of Evidence That the Problem is Not
From Ongoing Geologic Processes
The Copper Ridge Formation is not a
Strong Karst Former
There are no Sinkholes, Springs, or
Disappearing Streams on or Near the Site Water is the Engine to Ongoing Karst
Formation- Hardscape Prevents Infiltration There is no Evidence in the Geophysical
Data of Voids Beneath the Building
ATS InternationalAdvanced Technical Services
www.ats-intl.com
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
17/81
Questions about Testing and Investigations
//
ARCHITECTS AND ENGINEERS
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
18/81
1. Category 1 items from OWPR Facility Assessment
2. Wall settlement in three locations
3. Auditorium roof structural steel
4. Deficient concrete beams
Items to be Repaired
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
19/81
Repair of Category I Items from OWPR FacilityAssessment
Issue Solution Spalling concrete on columns and beams Epoxy mortar repair
Cracks Epoxy injection
Collateral damage from gym collapse Repair as required
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
20/81
Estimate for Cost of Category 1Repairs
Description Budget Estimate BidorProposal
1.Category1ItemsfromOWPRFacilityAssessment $ 141,000.00 General&Mech.Services(GMS)
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
21/81
Questions about the Repair of Category 1 Itemsfrom the OWPR Facility Assessment
//
M BOLYARDPECKBP McDONOUGH
ARCHITECTS AND ENGINEERS
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
22/81
Wall Settlement in Three Locations
Issue Solution
Wall settlement in Boiler Room, Auto Shop, and Wood Working Shop Install foundation underpinning (helical piers)
Description Budget Estimate BidorProposal
WallSettlementRepairsinthreelocations $ 66,000.00 RACConstructionCompany
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
23/81
Questions about Wall Settlement Repairs
//
M BOLYARDPECKBP McDONOUGH
ARCHITECTS AND ENGINEERS
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
24/81
Auditorium Roof Structural Steel
Issue Solution
Defective full-penetration welds at various locations
Various under-sized steel truss members
Reinforce welds with additional steel plates
Reinforce with additional steel members
Note: A 30 length of the west wall of the auditorium exceeds the
maximum allowable height for its construction and will require steelbracing to the roof framing. This work will be done when theauditorium trusses are repaired and will be concealed above theceiling.
Description Budget Estimate BidorProposal
AuditoriumRoofStructuralSystem $ 170,000.00 CSESteelErection&GMS
Cross Section of Failed Weld from Gym Truss Seat Auditorium Truss Seat
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
25/81
Questions about Auditorium Repairs
, /
/
M B ~ ~ H ARCHITECTS AND ENGINEERS
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
26/81
Deficient Concrete Beams
Issue Solution
Inadequate reinforcing steel within concrete beams Carbon fiber reinforcement or additional steeland concrete
Area of Destructive Testing to Verify Reinforcing Steel
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
27/81
Concrete is artificial stone
Steel reinforcing is placed in the tension zone
The two materials are combined, each material utilizing its bestproperties
Reinforced Concrete 101
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
28/81
Water flows down hill
You cannot push rope
Bodies in motion produce forces
Basic Civil Engineering Principles
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
29/81
Bending moments must balance; externally and internally
Bending Moment a force times a distance
G
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
30/81
Beam a horizontal structural member supporting vertical loads by bending
Glossary
Gl
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
31/81
Cantilevered Beam a beam that projects beyond a supportingcolumn or wall
Glossary
Gl
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
32/81
Column A vertical structural member supporting vertical loads bycompression
Glossary
C
C ti R i f d C t B
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
33/81
Continuous Reinforced Concrete Beam
I ,I. ITI
,I. ,I I J J JTI
" ,l I,
Where is the tension?
TIT T TTIT T TTIT// Where does the steel g07IT IT IT
What happens i f new supports are added between columns?
,I. ,I. ,lTI
I ,I. I,
T TTIT
IT
I, 1 1
T
IT
TIT
IT
MBP McDONOUGHBOLYARDPECK
ARCHITECTS AND ENGINEERS
I d d t R i f OWPR M th d l
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
34/81
Used original engineering drawings, specifications, schedules andbuilding codes
Verified OWPRs computations and methodology
Verified computer output all computer results are wrong unlessproven otherwise
Independent Review of OWPRs Methodology
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
35/81
Strengthening and Repairof Reinforced Concrete
Structures
Ian Wienholt
Business Development Manager
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
36/81
34 years of Concrete Repair and
Strengthening Experience Over 15,000 Repair Project
Over 25,000 PT Projects
1,500 Employees
22 Offices- International
UAE, UK, Saudi, China
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
37/81
General Repair Group:
Strengthening Division
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
38/81
Carbon Fiber Reinforced PolymerStrengthening
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
39/81
Externally Bonded FRP Sheet
550,000 psi Tensile
10x that of steel
Lightweight
Does NOT corrode
FRP Design Guidelines
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
40/81
FRP Design Guidelines
440.2R-02 440.2R-08
To Date:
Nationwide 15-18M sqft installedSPS 7M sqft installed on over 700 + projects
ACI 4 40.2R-08
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
41/81
Tension Steel
Yield
FRP carries
TENSION
What Is FRP Flexural Strengthened R/C?
Positive Moment
Wh I FRP Fl l S h d R/C?
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
42/81
CompressionConcrete carries
COMPRESSION
TOP
BOTTOM
SteelTension
Yield
FRP carries
TENSION
What Is FRP Flexural Strengthened R/C?
Column
Negative Moment
What Is FRP Shear Strengthened R/C?
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
43/81
SHEAR
What Is FRP Shear Strengthened R/C?
Installation Step 1:
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
44/81
Installation Step 1:
Surface Grinding/Shot Blastingto Open Pores
I ll i S
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
45/81
Installation Step 2:
Remove Dust from Surface
Before After
I ll i S 3
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
46/81
Installation Step 3:
Epoxy Primer Application
I ll i S 4
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
47/81
Installation Step 4:
Epoxy Putty Trowel Applied
I ll i S 5
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
48/81
Installation Step 5:
Saturation Coat and CFRP
I t ll ti St 6
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
49/81
Installation Step 6:
Rib Roll & Final Saturation Coat
I t ll ti St 7
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
50/81
Installation Step 7:
Intumescent Topcoat
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
51/81
External Post TensioningStrengthening
E t l P t T i i
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
52/81
External Post Tensioning
F
F
NEW LOAD
Upliftat Deviator
Dead end
Live end
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
53/81
Flexural Strengthening Case Study
Environmental Overload
Tension Tension
YIELD
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
54/81
Flexural Strengthening Case Study
Environmental Overload
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
55/81
Flexural Strengthening Case Study
Environmental Overload
Form & Pump
Amplitude
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
56/81
Flexural Strengthening Case Study
Environmental Overload
Dowel Hole Drilling
High Pressure Water Blasting
Dowel Insertion
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
57/81
Flexural Strengthening Case Study
Environmental Overload
Fl l S h i C S d
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
58/81
Flexural Strengthening Case Study
Environmental Overload
Fl l S h i C S d
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
59/81
Flexural Strengthening Case Study
Environmental Overload
Fl l St th i C St d
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
60/81
Flexural Strengthening Case Study
Environmental Overload
Fl l St th i C St d
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
61/81
Flexural Strengthening Case Study
Environmental Overload
Fl l St th i C St d
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
62/81
Flexural Strengthening Case Study
Environmental Overload
43
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
63/81
SCC Section EnlargementStrengthening
Transfer Slab Cracking
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
64/81
Transfer Slab Cracking
/ I
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
65/81
Demo and Prep
PAM Machine in Action
Supplemental Beam Column
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
66/81
Supplemental Beam-Column
Connection
Mechanical Anchoring and
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
67/81
Mechanical Anchoring and
Reinforcement Cage
2000
UndercutAnchors
3000 HiltiStuds
SCC Pumping Anyone???
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
68/81
SCC Pumping Anyone???
40 Tons ofSteel
1100LF
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
69/81
Finished Product
185 CU YDS /
375 Tons of
Concrete
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
70/81
Finished Product
Estimated Cost of Beam Testing and Repairs
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
71/81
Description Budget Estimate BidorProposal
TestingofConcreteBeams $ 95,000.00 RadarView
Demolition/RepairWallsforTesting $ 325,000.00 EstimatebyGMS&MBP
Tearoff/PatchRoofforTesting $ 259,000.00 BakerRoofing
SubtotalTestingofConcreteBeams $ 679,000.00DeficientConcreteBeams $ 3,400,000.00 StructuralPreservationSystems
SubtotalofStructuralRepairs $ 3,400,000.00ReplaceRoofafterRepairs $ 715,000.00 BakerRoofingkerRoofing
SubtotalofStructuralRepairs&Testing $ 4,079,000.00
Contingency $ 1,423,680.00
Total $ 5,502,680.00
Questions about Concrete Beam Repairs
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
72/81
//
M BOLYARDPECKBP McDONOUGH
ARCHITECTS AND ENGINEERS
Estimated Cost of Gym Replacement
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
73/81
Description Budget Estimate
GeneralConditionsareincludedineachoftheitemsbelow $
Sitework&Demo $ 615,257.00
Concrete $ 1,020,386.00
Masonry $ 548,958.00
Metals $ 448,002.00
Wood&Plastics $ 9,042.00
Thermal&MoistureProtection $ 236,398.00
Doors&Windows $ 112,361.00
Finishes $ 295,720.00
Equipment $ 1,271,599.00
Elevator $ 50,000.00
Plumbing,Heat,Ventilation&AirConditioning $ 1,460,794.00
Electrical $ 876,003.00
SubTotalConstruction $ 6,944,520.00
Permits $ 12,900.00
A/EFees $ 1,041,700.00
CostEstimating $ 14,000.00
Geotechnical&StructuralTests $ 100,000.00
Engineering&SpecialTesting $ 40,000.00
QualityAssurance&TestingFees $ 17,200.00
ConstructionManagement $ 300,000.00
SubTotalFees&SoftCost $ 1,525,800.00
Total $ 8,470,320.0010%Contingentlyincludedinallitemsabove
Thisestimateincudes costto rebuildtheentirelowerlevelfoundation,structure,exteriorandinteriorwalls
Questions about Gym Replacement Estimate
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
74/81
, //
M B ~ ~ H ARCHITECTS AND ENGINEERS
Estimated Total Cost Repairs and
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
75/81
Gym Replacement
Description Budget Estimate Bid
or
Proposal
TestingofConcreteBeams $ 95,000.00 RadarView
Demolition/RepairWallsforTesting $ 325,000.00 EstimatebyGMS&MBP
Tearoff/PatchRoofforTesting $ 259,000.00 BakerRoofing
SubtotalTestingofConcreteBeams $ 679,000.001.Category1ItemsfromOWPRFacilityAssessment $ 141,000.00
General&Mech.Services
(GMS)
2.WallSettlementRepairsinthreelocations $ 66,000.00 RACConstructionCompany
3.AuditoriumRoofStructuralSystem $ 170,000.00 CSESteelErection&GMS
4.DeficientConcreteBeams $ 3,400,000.00
StructuralPreservation
Systems
CM/DesignDocuments $ 250,000.00 OWPR&MBP
SubtotalofStructuralRepairs $ 4,027,000.00ReplaceRoofafterRepairs $ 715,000.00 BakerRoofingkerRoofing
SubtotalofStructuralRepairs&Testing $ 4,706,000.00CM/DesignDocuments $ 250,000.00 OWPR&MBP
Contingency $1,423,680
GymReplacementEstimatedCost $ 8,470,320Testing,Repairs,andGymReplacement $ 14,850,000
Schedule
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
76/81
/
o".. .oN
".. ." . . .oN
N".. .
Repair offrom OWPR
FacilityAssessment
Repair of WallSettlement inBoiler Room,Auto Shop, and
Wood Working
Pro ctRepair
Auditorium RoofStructural Steel
Repair Deficientncrete(including
testing)GymReplacement
MB BOLYARDPECKP McDONOUGH
ARCHITECTS AND ENGINEERS
Work that can be Done to Improve InteriorEnvironment and Building Operations
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
77/81
Environment and Building Operations
Description EstimateReplaceHeating,Ventilation,AirConditioning $ 3,300,000.00
ReplaceFireAlarm $ 265,000.00
Upgrade
Plumbing
Fixtures
to
ADA
Requirements $
200,000.00
SubTotalBuildingInfrastructureUpgrades $ 3,765,000.00ReplaceVinylFloorTile $ 256,000.00
ReplaceCarpet $ 91,000.00
PaintInteriorWalls $ 418,000.00
ReplaceCeilingGridandTiles $ 418,000.00
ReplaceAuditoriumSeating $ 210,000.00
SubTotalFinishesReplacement $ 1,393,000.00ReplaceFurnitureandUpgradeTechnology $ 1,500,000.00
AddSprinklerSystem $ 838,000.00
SubTotalUpgrades $ 7,496,000.00
BHS Existing Mechanical
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
78/81
Heating Plant Two 250 BHP, dual fuel, Scotch Marine 2-pass fire tube boilers,original
Heating Distribution Primary pumps, 20 HP centrifugal. Secondary pumps: severalinline pumps.
Cooling Plant Two 325 Ton variable speed Centrifugal Chillers with forced draftcooling towers, new.
Cooling Distribution Primary pumps, 50 HP centrifugal. Secondary pumps: severalinline pumps.
Auditorium Four pipe with Air Handling Units.
Classrooms Four Pipe unit ventilators in exterior Classrooms. Variable Air VolumeBoxes with hot water heat in interior classrooms
Administration - Variable Air Volume Boxes with hot water heat.
Library Four pipe with Air Handling Units.
Vo. Tech Four Pipe air handling units with hot water reheat.
Band/Coral Four Pipe air handling units with hot water reheat.
Cafeteria / Kitchen - Four pipe with Air Handling Units and unit ventilators.
BHS is basically a Four Pipe Fan Coil Unit system.
Proposed Mechanical
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
79/81
Systems Cost
Heating
Plant
Leave
as
is.HeatingDistribution Leaveasis.
CoolingPlant Leaveasis.
CoolingDistribution Leaveasis.
Auditorium ReplaceairhandlersandprovideCO2controls. $138,400
Stage ReplaceairhandlersandprovideCO2controls. $48,100
Commons ReplaceairhandlerandprovideCO2controls. $65,000
Library ReplaceairhandlerandprovideCO2controls. $48,000
Aud.Lobby Replaceairhandler. $21,000
Vo.Tech Replaceairhandlersandprovidefancoilunitsinsmallspaces. $263,000
Band/Coral Replaceairhandlersandprovidefancoilunitsinsmallspaces. $72,000
Administration ReplacewithDOAUw/activechilledbeamsorfancoilunits. $126,000
Classrooms ReplacewithDOAUw/activechilledbeamsorunitventilators. $520,000
Ductwork Cleansupplyandreturnductsthataretoremain $200,000
Controls Provide
new
DDC
control
system $700,000Total $2,201,500
OH&PandContingencyx1.5 $3,300,000
DOAU DedicatedOutdoorAirUnit
Work that can be Done to Improve InteriorEnvironment and Building Operations
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
80/81
Environment and Building Operations
Description EstimateReplaceHeating,Ventilation,AirConditioning $ 3,300,000.00
ReplaceFireAlarm $ 265,000.00
Upgrade
Plumbing
Fixtures
to
ADA
Requirments $
200,000.00
SubTotalBuildingInfrastructureUpgrades $ 3,765,000.00ReplaceVinylFloorTile $ 256,000.00
ReplaceCarpet $ 91,000.00
PaintInteriorWalls $ 418,000.00
ReplaceCeilingGridandTiles $ 418,000.00
ReplaceAuditoriumSeating $ 210,000.00
SubTotalFinishesReplacement $ 1,393,000.00ReplaceFurnitureandUpgradeTechnology $ 1,500,000.00
AddSprinklerSystem $ 838,000.00
SubTotalUpgrades $ 7,496,000.00
Questions/Discussions
8/7/2019 SB BHS Repair and Replacement (OWPR) Power Point) September 23 2010 (2)
81/81
//