: 082 - 348199
: 082 - 334199
Name : Eu Hieng Mew
NRIC : 890218 - 13 - 6435
Matric Number : AB 080157
Contact Number : 016 - 8658275
Programme : 2 SBQ
Section : Section 1
Session : 2009 / 2010
Lecturer : Dr. Mohd. Saidin B. Misnan
Fax
E-Mail Address
ELEMENTAL COST ANALYSIS 1
SBQ 2732
LT JURUUKUR BAHAN SDN. BHD.
No. 42H, Lot 9750, 1st & 2nd Floor,
Section 64, Mendu Commercial Centre, Jalan Mendu,
93200 Kuching, Sarawak, Malaysia
Telephone
ii
TITLE PAGE
FORM 1 1
FORM 2 2
FORM 3 3
APPENDICES -
TABLE OF CONTENTS
1
Contract Particulars :
Yes
No
Basis of Tender : RM Int (Jv)/L
Bills of Quantities
Bills of Appr. Quant. - -
Sched. of Rates/
Spec. & Drawings RM 4,000,000.00
: RM -
: RM 3,000,000.00
: RM -
: RM 60,000,000.00
Accomodation and Design Features :
Areas :
Lower Ground Floor m2 Functional Unit : 968.40 m
2
Ground Floor 1,358.04 m2
Upper Floor 57.82 m2
GROSS FLOOR AREA 1,415.86 m2 External Wall Area 855.00 (a) %
Gross Floor Area 1,415.86
Usable Area 968.40 m2 = 0.604 (b) 95.92 %
Circulation Area 92.88 m2
Ancillary Area 345.73 m2 (c) 4.08 %
Internal Division 8.85 m2
GROSS FLOOR AREA 1,415.86 m2 Storey Heights : (d) %
Av. below Grd. Floor m
Floor Space NOT Enclosed 283.08 m2 At Ground Floor 3.00 m
Above Ground Floor 1.50 m
Roof Area
(Structural & Plant Rooms) 1,329.36 m2
Contract Sums RM
Provisional Sums RM (Tender : RM 2,135.80 per m² Usable Area)
Prime Cost Sums RM
Preliminaries RM Being 5.00 % of remainder
Contingencies RM Being 0.00 % Contract Sum
RM
Government
A block of dining hall located between male and female dormitory.
Water supply along main road. Capacity and pressure to be determined by Engineer. Electricity
/ Telephone not available.
Items for modular workstation, laboratory equipments, building sign board, landscape works and
capital contribution are included in Provisional Sum.
60 m road reserve on North Boundary. From Town, the road is going uphill up to approximately
1/3 of the site Frontage. The land is undulating. Mainly covered with secondary forest with some
rubber trees and cash crops at in pockets. Rocks usually detectable at the apex of road. Jungle
track accessible by motorcycle leading to the planted areas.
Period of Honouring of certificate :
30 days from the date of the architect
Number of Tenders Received
Private
Prime Cost Sum
Preliminaries
Contract Period Stipulated by Client
Contract Period Offered by Buliders
ANALYSIS OF SINGLE BUILDING - DINING HALL
Competitive Tender List
JOB TITLE : Sekolah Menengah Kebangsaan yang Mengandungi 36 Bilik Darjah &
JOB TITLE : Kemudahan Berkaitan Di Atas Lot 343, Block 8, Kayan Land District,
JOB TITLE : Tebedu, Daerah Serian Sarawak
Cost Fluctuation :
Period of Interim Certificates :
Monthly
Scope of the project's works are construction and completion of Administration and Academic
Blocks, Canteen, Dining Hall, 2 blocks Quarter Class "D", Quarter Class "C", 4 blocks Quarter
Class "F", Male Dormitory, Female Dormitory and Multi Purpose Hall; related Mechanical and
Electrical works; related External works.
Project Details and Site Conditon
The project comprising construction and completion of a secondary school consisting of 36
classrooms and able to be utilised by about 1080 students.
Standard Form of Contract :
PWD Form 203A (Rev. 10/83)
Contract :
4
Market Conditions : Negotiated
4,000,000.00
-
3,000,000.00
-
60,000,000.00 Contract Sums Less Contingencies
3
PWD Form 203A (Rev. 10/83)
Open/Selected
Negotiated
Serials
2
Contingencies
Contract Sum
Brief Cost Information
A - 2 - 1416
9 - Building, Spaces in General
Number of Tenders Issued
ELEMENTAL COST ANALYSIS - Form 1
JOB TITLE : Cadangan Pembangunan Projek Pendidikan Sebuah
LOCATION : SERIAN, SARAWAK
1
120 weeks
30 months
1
CLIENT : GOVERNMENT
TENDER DATE : 27th JULY 2007
60,000,000.00
INFORMATION TOTAL PROJECT
Project and Contract Information
Provisional Sum
Single Storey Construction
Double Storey Construction
3 Storey Construction
Design/Shape Information
=
Design/Shapes
Percentage of Gross Floor Area
Type of Contract :
Functional Unit Costs excluding external works :
Below Ground Floor
1
√ √
√
√√
√
√
2
GROSS FLOOR AREA : 1,415.86 m²
Total Cost Cost Element Element Ratio Reinforced
of Element per m² GFA Unit Rate per m² GFA Concrete
RM RM RM m3 kg
1
1A -
1B 404,990.00 286.04 1,358.04 m² 298.22 0.96 383.35 41,297.00
404,990.00 286.04 383.35 41,297.00
2
2A 142,692.00 100.78 57.82 m² 2,467.87 0.04 116.00 12,193.00
2B 39,573.20 27.95 294.00 m² 134.60 0.21 38.22 3,326.00
2C 381,523.30 269.46 1,386.00 m² 275.27 0.98
2D -
2E 22,522.40 15.91 524.00 m² 42.98 0.37
2F 43,927.45 31.03 92.33 m² 475.77 0.07
2G 11,551.20 8.16 206.00 m² 56.07 0.15
2H 4,092.30 2.89 12.72 m² 321.72 0.01
645,881.85 456.18 154.22 15,519.00
3
3A 25,087.00 17.72 1,387.00 m² 18.09 0.98
3B 31,010.00 21.90 1,680.00 m² 18.46 1.19
3C 23,598.00 16.67 1,680.00 m² 14.05 1.19
3D 174,936.00 123.55 0.00
254,631.00 179.84
4 -
5
5A 15,548.00 10.98 70 nos 222.11 0.073
5B 98,055.45 69.26
5C -
5D 84,335.20 59.56 31.92 Tm3
5E 369,237.71 260.79
5F 27,262.80 19.26
5G -
5H 31,142.96 22.00
5J -
5K -
5L 3,480.30 2.46
629,062.42 444.30
6
6A 478,716.38 338.11
6B 170,594.67 120.49
6C 52,373.22 36.99
6D 8,382.06 5.92
6E 30,181.30 21.32
740,247.63 522.83
133,740.65 94.46
2,808,553.55 1,983.64
1,934,565.27 1,366.35
Group Element Total
Preliminaries
TOTAL (Less Contingencies)
Group Element Total
SUB-TOTAL exclude External Works,
Preliminaries and Contingencies
Builder's Work in Connection with Services
Site Work
Drainage
External Services
Ancillary Buildings
Recreational Facilities
Group Element Total
Electrical Installation
Fire Protection Installation
Lift & Conveyor Installation
Communication Installation
Special Installation
Builder's Profit & Attendance on Services
Sanitary Appliances
Plumbing Installation
Refuse Disposal
Air-conditioning & Ventilation System
Substructure
Piling
Superstructure
Finishes
Fittings and Furnishings
Services
Work Below Lowest Floor Finish
Frame
Upper Floors
Roof
Group Element Total
Internal Ceiling Finishes
External Finishes
External Walls
Windows & External Doors
Internal Walls & Partitions
Internal Doors
Internal Wall Finishes
Internal Floor Finishes
Group Element Total
1,773.50
1,304.00
312.75
Tendered Sum
1,616.75
External Works
Stairs
ELEMENTAL COST ANALYSIS - Form 29 - Building, Spaces in General
A - 2 - 1416
SUMMARY OF ELEMENT COSTS ( DINING HALL )
Reinforcement
1,773.50
TENDER DATE : 27th
JULY 2007
Preliminaries Shown Separately
Formwork
m²
Unit Quantity
Element
P.C Sums Allowed
3
9 - Building, Spaces in General
A - 2 - 1416
1 Substructure
1A Piling -
1B Work Below Lowest Floor Finish
2 Superstructure
2A Frame
2B Upper Floors
2C Roof
2D Stairs -
2E External Walls Well burnt clay bricks
2F Windows & External Doors
2G Internal Walls & Partitions Well burnt clay bricks; stainless steel queuing handrail
2H Internal Doors UPVC door; hollow core plywood flush door
3 Finishes
3A Internal Wall Finishes
3B Internal Floor Finishes
3C Internal Ceiling Finishes
3D External Finishes
4 Fittings and Furnishing -
5 Services
5A Sanitary Appliances
5B Plumbing Installation
5C Refuse Disposal
5D Air-conditioning & Ventilation System
5E Electrical Installation
5F Fire Protection Installation
5G Life & Conveyor Installation
5H Communication Installation
5I Special Installation
5J Builder's Profit & Attendance on Services
5K Builder's Work in Connection with Services Squatting pan base
6 External Works
6A Site Work
6B Drainage
6C External Services
6D Ancillary Buildings Pump house; guard house; rubbish bin; ruang cuci kaki; bus shed
6E Recreational Facilities Games court; football field; flagpost
Windows : Adjustable louvres winbdow c/w built in security grills
External Doors : Hard wood door; solid hard wood flush door; hollow core plywood flush door
Reinforced concrete drain; concrete sump; reinforced concrete box culvert; reinforced concrete detention pond; manhole;
polypass 1300; control room
External water reticulation; suction tank; high water tank
Site clearance; earthworks; road & carparks; fencing around development site, female dormitory & boundary; brickwall
fencing; footpath; external staircases; turfing
Sanitary Plumbing ( Soil, Waste & Vent Pipe ) : B.S.4514/5255 UPVC pipe above ground; B.S.4660 UPVC pipe below
ground
Telecommunication : 10 lbs PEUTTE tel. cable run in duct link; 10 pairs direct & extension line tel. DP; tel. point c/w socket
outlet in 9 nos
-
-
Bell : Alarm bell
PA Sound : 12W column speaker
MATV : VHF antenna c/w lightning arrestor & mounting bracket, UHF antenna c/w lightning arrestor, multi-band amplifier,
IF amplifier, TV wall outlet, UBB 2 way tap off
Stainless steel kitchen Hood ( 8 m x 2.5 m ) c/w grease filter inclusive of 2 nos. 12,000 cfm bifurcated fan at 400 pa, 960 rpm
Internal plastering; 200 mm x 200mm x 7 mm glazed ceramic wall tiling; 300 mm x 300mm x 7.5 mm glazed ceramic wall
tiling; skirting; alkali resisting primer & emulsion painting
Cold Water Supply : B.S.1387 G.S. pipe; B.S.1740 fitting for G.S. pipe; B.S.3505 UPVC pipe; B.S.2871 copper pipe; SUS
304 stainless steel pipe; PN 10 - M.S.1058 HDPE pipe; PN 9 - M.S.1419 ABS pipe; 50 gals HDPE tank in 2 nos
-
BRIEF SPECIFICATION
SPECIFICATION
ELEMENTAL COST ANALYSIS - Form 3
Prefabricated steel roof trusses; metal fascia board; Unilok Clean Colorbond metal roofing sheet with double sided
aluminium foil sisalation, Roxul MPB100 rockwool insulation blanket, chicken wire mesh; clean colorbond Ecosteel Long-
line metal gutter; UPVC rain water down pipe
ELEMENT
GROSS FLOOR AREA : 1,415.86 m² TENDER DATE : 27th
JULY 2007
Reinforced concrete G30 pile cap, column stump, ground beam & ground slab
Reinforced concrete G30 column, suspended beam, roof beam & ledge
Reinforced concrete G30 suspended slab
Squatting WC pan; wall urinal bowl; wall hung basin; ball joint shower rose bath-shower mixer; semi-recessed soap
holder; toilet roll holder; stainless steel floor trap; chrome cloth hooks; polished float glass mirror
-
Electrical : 2 x 36 W surface mounted fluorescent lighting fitting c/w parabolic lourve & reflector in 40 nos; 1 x 36 W
channel type ceiling mounted fluorescent lighting fitting in 130 nos; 1 x 18 W channel type ceiling mounted fluorescent
lighting fitting in 2 nos; 60" dia. ceiling sweep fan c/w speed regulator & fixing accessories in 1 no; exhaust fan in 2 nos;
wall mounted industrial oscillating fan in 16 nos; lighting point in concealed G.I. conduit c/w 2 x 1.5 mm2 PVC cable in 172
nos; fan point in concealed G.I. conduit c/w 2 x 1.5 mm2 PVC cable in 17 nos; 13A 1 gang white flush mounting switch
socket outlet in 22 nos; 20A TPN isolator c/w cabling in 1 no; 30A TPN isolator c/w cabling in 1 no; single arm galvanised
pole of 8 m height c/w 150 W SON luminaire street lighting; 1/4C 16 mm2 PVC/SWA/PVC underground cable
9 kg ABC dry powder portable fire extinguisher in 5 nos; 4.5kg CO2 portable fire extinguisher in 2 nos; wet chemical
system for 8 m x 2.5 m kitchen hood c/w heat detector, smoke detector, wiring, indicating light & control panel
Lightning Protection : 1" x 18" copper tape c/w saddles etc; 18" height air copper termination in 9 nos; test clamp c/w
accessories in 2 nos; earth termination using 5/8" dia. copper clad steel electrodes c/w earth chamber & earth resistance
shall be less than 10 ohms in 2 nos
Wall : External plastering; glazed ceramic wall tiling; alkali resisting primer & weathershield painting
Floor : Screeding; non-slip homogeneous floor tiling
Ceiling : Skim coating; asbestos free fibre reinforced cement board; alkali resisting primer & weathershield painting
300 mm x 300 mm x 8 mm non-slip homogeneous floor tiling; 200 mm x 200 mm x 7.5 mm non-slip homogeneous floor
Cement board; alkali resisting primer & emulsion painting
APPENDICES
CALCULATION OF
TOTAL COST ELEMENT
Item Description RM RM
1 Windows 26,248.00
2 External Doors 14,775.00
Ironmongeries 3,576.75
81.2% of Doors 0.8120
41,023.00 2,904.45
Item Doors RM %
1 External 14,775.00 81.20
2 Internal 3,420.00 18.80
18,195.00 100.00
Item Description RM RM
1 Internal Doors 3,420.00
Ironmongeries 3,576.75
18.8% of Doors 0.1880
3,420.00 672.30
Item Doors RM %
1 External 14,775.00 81.20
2 Internal 3,420.00 18.80
18,195.00 100.00
Item Description
1 Internal Walls & Partitions
2 Handrailing & Balustrades
Item Description
1 Floor Finishes
2 Wall Finishes
3 Ceiling Finishes
TOTAL 43,927.45
TOTAL 174,936.00
3D External Finishes
RM
76,722.00
26,214.00
72,000.00
TOTAL
2H Internal Doors
2F Windows & External Doors
2G Internal Walls & Partitions
TOTAL 11,551.20
8,565.20
2,986.00
RM
SUB-TOTAL
TOTAL 4,092.30
TOTAL
3
2
SUB-TOTAL
Item Description RM RM
1 Dewan Makan 37,782.00
2 Testing & Commissioning 6,000.00
3 Maintenance inclusive of parts within the Defect Liability Period 3,000.00
4 Shop drawing 2,000.00
5 As built drawing & operation / maintenance manual 2,000.00
37,782.00 13,000.00
0.0518
37,782.00 673.40
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 257,412.00 35.32
2 CANTEEN 20,530.00 2.82
3 DINING HALL 37,782.00 5.18
4 CLASS "D" QUARTERS
5 CLASS "C" QUARTER
6 CLASS "F" QUARTERS 117,240.00 16.09
7 MALE DORMITORY 128,185.00 17.59
8 FEMALE DORMITORY 110,490.00 15.16
9 MULTI PURPOSE HALL 29,160.00 4.00
10 RUBBISH BIN CENTRE 2,900.00 0.40
728,729.00 100.00
5B / 1
COLD WATER SUPPLY SERVICES
TOTAL
5B Plumbing Installation
3.44
COLD WATER SUPPLY SERVICES
SUB-TOTAL
TOTAL 38,455.40
SUB-TOTAL
5.18% of Main Building
25,030.00
Item Description RM RM
1 Dewan Makan 58,450.00
2 Testing & Commissioning 5,000.00
3 Maintenance inclusive of parts within the Defect Liability Period 5,000.00
4 Shop drawing 5,000.00
5 As built drawing & operation / maintenance manual 1,500.00
58,450.00 16,500.00
0.0697
58,450.00 1,150.05
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 329,375.00 39.28
2 CANTEEN 28,975.00 3.45
3 DINING HALL 58,450.00 6.97
4 CLASS "D" QUARTERS
5 CLASS "C" QUARTER
6 CLASS "F" QUARTERS 104,800.00 12.50
7 MALE DORMITORY 144,984.00 17.29
8 FEMALE DORMITORY 115,259.00 13.74
9 MULTI PURPOSE HALL 26,275.00 3.13
10 RUBBISH BIN CENTRE 5,266.00 0.63
838,609.00 100.00
5B / 2
TOTAL 59,600.05
5B Plumbing Installation
SANITARY PLUMBING SERVICES
5B Plumbing Installation
TOTAL 98,055.45
SANITARY PLUMBING SERVICES
25,225.00 3.01
SUB-TOTAL
6.97% of Main Building
SUB-TOTAL
TOTAL
COLD WATER SUPPLY SERVICES
SANITARY PLUMBING SERVICES 59,600.05
38,455.40
Item Description RM RM
1 Dewan Makan 83,920.00
2 Testing & Commissioning 3,000.00
3 Maintenance inclusive of parts within the Defect Liability Period 3,000.00
4 Shop drawing 1,000.00
5 As built drawing & operation / maintenance manual 1,000.00
83,920.00 8,000.00
0.0519
83,920.00 415.20
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 418,590.00 78.98
2 CANTEEN 83,920.00 15.83
3 DINING HALL 27,480.00 5.19
529,990.00 100.00TOTAL
5D Air-conditioning & Ventilation System
SUB-TOTAL
5.19% of Main Building
SUB-TOTAL
TOTAL 84,335.20
Item Description RM RM
1 Main Switchboard, type form 2B, floor mounted 147,451.75
2 Distribution Panel, ground mounted outdoor type sealed to IP56 18,329.40
3 Sub Switchboard, wall mounted
SSB/DM 10,510.00
4 Distribution Board
DB/DM1 3,560.00
DB/DM2 4,510.00
5 Underground Submains Cabling c/w necessary accessories
From MSB to :
SSB/DM 249,550.00
From SSB/DM 5,627.60
6 Lighting Fittings, Fans, Lighting & Power Final Sub-Circuit 54,033.80
7 Lightning Protection System
1" x 18" copper tape c/w saddles etc 7,280.00
18" height air copper termination 540.00
Test clamp c/w accessories 100.00
Earth termination using 5/8" dia. copper clad steel
electrodes c/w earth chamber & earth resistance shall be
less than 10 ohms
8 External Lighting 211,747.60
9 Testing & Commissioning 5,000.00
10 Maintenance inclusive of parts within the Defect Liability Period 5,000.00
11 Shop drawing 1,500.00
12 As built drawing & operation / maintenance manual 1,500.00
336,511.40 390,528.75
0.0838
336,511.40 32,726.31
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 1,494,001.13 37.20
2 CANTEEN 51,070.10 1.27
3 DINING HALL 336,511.40 8.38
4 CLASS "D" QUARTERS 33,561.80 0.84
5 CLASS "C" QUARTER 17,311.72 0.43
6 CLASS "F" QUARTERS 339,118.00 8.45
7 MALE DORMITORY 737,843.15 18.37
8 FEMALE DORMITORY 861,732.55 21.46
9 MULTI PURPOSE HALL 98,402.90 2.45
10 GUARD HOUSE 46,285.50 1.15
4,015,838.25 100.00
5E Electrical Installation - LV Electrical Works
800.00
SUB-TOTAL
TOTAL 369,237.71
8.38% of Main Building
SUB-TOTAL
TOTAL
Item Description RM RM
1 Dewan Makan 26,604.00
2 Testing & Commissioning 7,500.00
3 Maintenance inclusive of parts within the Defect Liability Period 4,000.00
4 Shop drawing 1,000.00
5 As built drawing & operation / maintenance manual 1,000.00
26,604.00 13,500.00
0.0488
26,604.00 658.80
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 144,607.00 26.50
2 CANTEEN 16,858.00 3.09
3 DINING HALL 26,604.00 4.88
4 CLASS "F" QUARTERS 6,400.00 1.17
5 MALE DORMITORY 50,472.00 9.25
6 FEMALE DORMITORY 50,472.00 9.25
7 MULTI PURPOSE HALL 12,284.00 2.25
8 GUARD HOUSE 237,975.00 43.61
545,672.00 100.00TOTAL
4.88% of Main Building
SUB-TOTAL
5F Fire Protection Installation
SUB-TOTAL
TOTAL 27,262.80
Item Description RM RM
1 External telephone manhole & duct link
JC9C manhole 4,800.00
JC9 manhole 13,500.00
900 x 900 x 1000 mm (D) non-standard manhole 1,600.00
750 x 750 x 850 mm (D) non-standard manhole c/w medium 36,000.00
duty cast iron cover
2 ways 100 mm G.I. duct link 54,400.00
2 ways 100 mm PVC duct link 23,730.00
100 pairs telephone distribution cabinet 500.00
G.I. duct link c/w long bend up to DP 500.00
1 way 100 mm dia. G.I. duct link 17,765.00
1 way 100 mm dia. PVC duct link 33,900.00
100 pairs PEUTTE tel. cable from MDF to distribution cabinet 17,000.00
2 Dewan Makan
10 lbs PEUTTE tel. cable run in duct link 2,060.00
10 pairs direct line tel. DP 200.00
10 pairs extension line tel. DP 200.00
Tel. point c/w socket outlet 900.00
3 Keyphone System 14,975.00
4 Testing & Commissioning 2,000.00
5 Maintenance inclusive of parts within the Defect Liability Period 1,000.00
6 As built drawing & operation / maintenance manual 500.00
3,360.00 222,170.00
0.0539
3,360.00 11,974.96
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 18,360.00 29.45
2 CANTEEN 4,260.00 6.83
3 DINING HALL 3,360.00 5.39
4 CLASS "D" QUARTERS 5,320.00 8.53
5 CLASS "C" QUARTER 4,020.00 6.45
6 CLASS "F" QUARTERS 12,180.00 19.54
7 MALE DORMITORY 5,560.00 8.92
8 FEMALE DORMITORY 5,560.00 8.92
9 MULTI PURPOSE HALL 3,720.00 5.97
62,340.00 100.00
5H / 1
TOTAL
5H Communication Installation
SUB-TOTAL
TOTAL 15,334.96
TELECOMMUNICATION WORKS
5.39% of Main Building
SUB-TOTAL
TELECOMMUNICATION WORKS
Item Description
1 PA SOUND SYSTEM
2 MATV SYSTEM
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 11,450,912.86 42.71
2 CANTEEN 616,008.75 2.30
3 DINING HALL 1,324,531.15 4.94
4 QUARTERS "D" 579,008.10 2.16
5 QUARTERS "C" 360,446.20 1.34
6 QUARTERS "F" 4,000,505.80 14.92
7 MALE DORMITORY 4,249,382.70 15.85
8 FEMALE DORMITORY 4,207,893.40 15.70
9 GUARD HOUSE 20,295.70 0.08
26,808,984.66 100.00
Item Description
1 BELL SYSTEM
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 11,450,912.86 52.41
2 CANTEEN 616,008.75 2.82
3 DINING HALL 1,324,531.15 6.06
4 MALE DORMITORY 4,249,382.70 19.45
5 FEMALE DORMITORY 4,207,893.40 19.26
21,848,728.86 100.00
5H / 2
TOTAL 3,030.00
TOTAL
RM
50,000.00
SUB-TOTAL 50,000.00
6.06% of Main Building 0.0606
5H Communication Installation
TOTAL
SUB-TOTAL
4.94% of Main Building
TOTAL
210,000.00
110,000.00
320,000.00
0.0494
15,808.00
RM
TOTAL 31,142.96
5H Communication Installation
TELECOMMUNICATION WORKS 15,334.96
PA SOUND SYSTEM, MATV SYSTEM 15,808.00
BELL SYSTEM 3,030.00
Item Description
1 Site Works
2 Roads & Carparks
3 Fencing & Gate
4 Footpath, External Staircase & Covered Walkway
5 Turfing
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 11,450,912.86 40.85
2 CANTEEN 616,008.75 2.20
3 DINING HALL 1,324,531.15 4.73
4 QUARTERS "D" 579,008.10 2.06
5 QUARTERS "C" 360,446.20 1.29
6 QUARTERS "F" 4,000,505.80 14.27
7 MALE DORMITORY 4,249,382.70 15.16
8 FEMALE DORMITORY 4,207,893.40 15.01
9 MULTI PURPOSE HALL 1,067,782.50 3.81
10 PUMP HOUSE 34,860.40 0.12
11 GUARD HOUSE 20,295.70 0.07
12 RUBBISH BIN CENTRE 59,206.55 0.21
13 RUANG CUCI KAKI 31,041.40 0.11
14 BUS SHED 30,689.60 0.11
28,032,565.11 100.00TOTAL
RM
7,046,000.00
1,459,391.00
751,142.89
352,559.90
347,760.00
10,120,853.79
0.0473
6A Site Works
SUB-TOTAL
4.73% of Main Building
TOTAL 478,716.38
Item Description
1 Surface Water Drainage
2 Sewage & Associated Works
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 11,450,912.86 40.85
2 CANTEEN 616,008.75 2.20
3 DINING HALL 1,324,531.15 4.73
4 QUARTERS "D" 579,008.10 2.06
5 QUARTERS "C" 360,446.20 1.29
6 QUARTERS "F" 4,000,505.80 14.27
7 MALE DORMITORY 4,249,382.70 15.16
8 FEMALE DORMITORY 4,207,893.40 15.01
9 MULTI PURPOSE HALL 1,067,782.50 3.81
10 PUMP HOUSE 34,860.40 0.12
11 GUARD HOUSE 20,295.70 0.07
12 RUBBISH BIN CENTRE 59,206.55 0.21
13 RUANG CUCI KAKI 31,041.40 0.11
14 BUS SHED 30,689.60 0.11
28,032,565.11 100.00TOTAL
SUB-TOTAL 3,606,652.55
4.73% of Main Building 0.0473
6B Drainage
RM
1,984,541.50
1,622,111.05
TOTAL 170,594.67
Item Description
1 External Water Reticulation
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 11,450,912.86 40.85
2 CANTEEN 616,008.75 2.20
3 DINING HALL 1,324,531.15 4.73
4 QUARTERS "D" 579,008.10 2.06
5 QUARTERS "C" 360,446.20 1.29
6 QUARTERS "F" 4,000,505.80 14.27
7 MALE DORMITORY 4,249,382.70 15.16
8 FEMALE DORMITORY 4,207,893.40 15.01
9 MULTI PURPOSE HALL 1,067,782.50 3.81
10 PUMP HOUSE 34,860.40 0.12
11 GUARD HOUSE 20,295.70 0.07
12 RUBBISH BIN CENTRE 59,206.55 0.21
13 RUANG CUCI KAKI 31,041.40 0.11
14 BUS SHED 30,689.60 0.11
28,032,565.11 100.00TOTAL
SUB-TOTAL 1,107,256.15
4.73% of Main Building 0.0473
6C External Services
RM
1,107,256.15
TOTAL 52,373.22
Item Description
1 Ancillary Buildings
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 11,450,912.86 41.11
2 CANTEEN 616,008.75 2.21
3 DINING HALL 1,324,531.15 4.76
4 QUARTERS "D" 579,008.10 2.08
5 QUARTERS "C" 360,446.20 1.29
6 QUARTERS "F" 4,000,505.80 14.36
7 MALE DORMITORY 4,249,382.70 15.25
8 FEMALE DORMITORY 4,207,893.40 15.11
9 MULTI PURPOSE HALL 1,067,782.50 3.83
27,856,471.46 100.00TOTAL
SUB-TOTAL 176,093.65
4.76% of Main Building 0.0476
6D Ancillary Buildings
RM
176,093.65
TOTAL 8,382.06
Item Description
1 Games Court, Football Field & Flagpost
Item Main Building RM %
1 ACADEMIC & ADMINISTRATION 11,450,912.86 40.85
2 CANTEEN 616,008.75 2.20
3 DINING HALL 1,324,531.15 4.73
4 QUARTERS "D" 579,008.10 2.06
5 QUARTERS "C" 360,446.20 1.29
6 QUARTERS "F" 4,000,505.80 14.27
7 MALE DORMITORY 4,249,382.70 15.16
8 FEMALE DORMITORY 4,207,893.40 15.01
9 MULTI PURPOSE HALL 1,067,782.50 3.81
10 PUMP HOUSE 34,860.40 0.12
11 GUARD HOUSE 20,295.70 0.07
12 RUBBISH BIN CENTRE 59,206.55 0.21
13 RUANG CUCI KAKI 31,041.40 0.11
14 BUS SHED 30,689.60 0.11
28,032,565.11 100.00TOTAL
SUB-TOTAL 638,082.45
4.73% of Main Building 0.0473
6E Recreational Facilities
RM
638,082.45
TOTAL 30,181.30