Sequencing Batch Reactor Design Report
AIT Waste Water Treatment System
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
i
Document History
Version
Number
Description Date Author Checked
1 Original 27/03/13 TS LM
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
ii
Table of Contents Document History ............................................................................................................................... i
1.0 Introduction .......................................................................................................................... 1
2.0 Characteristics of the treatment process .............................................................................. 1
2.1 Treatment Process ................................................................................................................. 1
2.1.1 Fill ............................................................................................................................... 2
2.1.2 React ........................................................................................................................... 2
2.1.3 Settle .......................................................................................................................... 3
2.1.4 Decant ........................................................................................................................ 3
2.1.5 Idle .............................................................................................................................. 3
3.0 Treatment system design ...................................................................................................... 3
3.1 Preliminary Treatment .......................................................................................................... 4
3.1.1 Screening Influent Wastewater .................................................................................. 4
3.1.2 Influent-Flow Equalisation ......................................................................................... 4
3.2 SBR Design ............................................................................................................................. 5
3.2.1 Reactor basin .............................................................................................................. 5
3.2.2 Flow-Paced Batch Operation ...................................................................................... 5
3.2.3 Aeration ...................................................................................................................... 5
3.2.4 Decanting ................................................................................................................... 6
3.2.5 Bottom Slope .............................................................................................................. 6
3.3 Post-Basin Effluent Equalisation ........................................................................................... 6
3.4 Parameters to Be Monitored by the SCADA System ............................................................. 6
3.5 Sludge wasting and storage .................................................................................................. 7
4.0 Structural design of the treatment tank ............................................................................... 7
4.1 Equilibrium ............................................................................................................................ 7
4.2 Walls ...................................................................................................................................... 8
4.3 Base design ............................................................................................................................ 8
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
iii
List of Figures
Figure 1 β SBR treatment cycle ........................................................................................................... 2
Figure 2 - Treatment system P&IDβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦4
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
1
1.0 Introduction
SBRβs are used all over the world and have been around since the 1920s. With their growing
popularity in Europe and China as well as the United States, they are being used successfully to treat
both municipal and industrial wastewaters, particularly in areas characterised by low or varying flow
patterns.
This type of plant is particularly suited for use on the AIT campus for a number of reasons, including:
As there is limited space to locate the system, treatment can take place in a single basin,
allowing for a smaller footprint. Low total-suspended-solid values of less than 10 milligrams
per litre (mg/L) can be achieved consistently through the use of effective decanting that
eliminates the need for a separate clarifier.
The treatment cycle can be adjusted to undergo aerobic, anaerobic, and anoxic conditions in
order to achieve biological nutrient removal, including nitrification, denitrification, and some
phosphorus removal. Biochemical oxygen demand (BOD) levels of less than 5 mg/L can be
achieved consistently. Total nitrogen limits of less than 5 mg/L can also be achieved by
aerobic conversion of ammonia to nitrates (nitrification) and anoxic conversion of nitrates to
nitrogen gas (denitrification) within the same tank. Low phosphorus limits of less than 2
mg/L can be attained by using a combination of biological treatment (anaerobic phosphorus
absorbing organisms) and chemical agents (aluminium or iron salts) within the vessel and
treatment cycle.
As wastewater discharge permits to the municipal sewer are becoming more stringent, an
SBR offers a cost-effective way to achieve lower effluent limits.
2.0 Characteristics of the treatment process
SBRs are a variation of the activated-sludge process. They differ from activated-sludge plants
because they combine all of the treatment steps and processes into a single tank, whereas
conventional facilities rely on multiple basins. According to a 1999 U.S. EPA report, an SBR is no
more than an activated-sludge plant that operates in time rather than space.
2.1 Treatment Process
The operation of the SBR has been based on a fill-and-draw principle, which consists of five steps;
fill, react, settle, decant, and idle, as shown in figure 1. These characteristics of each step can be
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
2
altered for differing operational applications which may occur due to AITβs academic cycle;
particularly the significant reduction in discharge during the summer period.
Figure 1 β SBR treatment cycle
2.1.1 Fill
During the fill phase, the basin will receive influent wastewater from the equalisation tank which is
discussed in more detail in section 3.1.2. The influent provides food for the microbes in the activated
sludge, creating an environment for biochemical reactions to take place. Aeration can be varied
during the fill phase to different scenarios, for the AIT SBR an aerated fill system has been selected.
Under an aerated-fill scenario, the aeration unit is activated. The contents of the basin will be
aerated to convert the anoxic or anaerobic zone over to an aerobic zone. No adjustments to the
aerated-fill cycle are needed to reduce organics and achieve nitrification. However, to achieve
denitrification, it is necessary to switch the oxygen off to promote anoxic conditions for
denitrification. By switching the oxygen on and off during this phase with the diffusers, oxic and
anoxic conditions are created, allowing for nitrification and denitrification. Dissolved oxygen (DO)
should be monitored during this phase so it does not go over 0.2 mg/L. This ensures that an anoxic
condition will occur during the idle phase.
2.1.2 React
This phase will allow for further reduction or "polishing" of wastewater parameters. During this
phase, no wastewater shall enter the basin and the aeration unit is on. Because there are no
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
3
additional volume and organic loadings, the rate of organic removal will increase dramatically. Most
of the carbonaceous BOD removal will occur in the react phase. Further nitrification will also occur
by allowing the aeration to continue. The majority of denitrification will take place in the mixed-fill
phase. The phosphorus released during mixed fill, plus some additional phosphorus, will be taken up
during the react phase.
2.1.3 Settle
During this phase, activated sludge will be allowed to settle under quiescent conditions; no flow
enters the basin and no aeration takes place. The activated sludge tends to settle as a flocculent
mass, forming a distinctive interface with the clear supernatant. The sludge mass is known as the
sludge blanket. This phase is a critical part of the cycle, as if the solids do not settle rapidly, some
sludge may be drawn off during the subsequent decant phase and thereby degrade effluent quality.
2.1.4 Decant
During this phase, a submersible pump will be used to remove the clear supernatant effluent. Once
the settle phase is complete, a signal will be sent to initiate the opening of an effluent-discharge
valve. The submersible pump will offer the operator flexibility to vary fill and draw volumes. This
operation will be optimised by ensuring that the decanted volume is the same as the volume that
enters the basin during the fill phase. It is also important that no surface foam or scum is decanted.
The vertical distance from the decanter to the bottom of the tank has been maximised to avoid
disturbing the settled biomass.
2.1.5 Idle
This step occurs between the decant phase and the fill phase. The time will vary, based on the
influent flow rate and the operating strategy. During this phase, a small amount of activated sludge
(75 l/cycle), at the bottom of the SBR basin will be pumped out, a process called sludge wasting.
3.0 SBR system design
The SBR treatment system consists of several individual components. The design of the SBR
treatment system was completed by TNLS in conjunction with EPS Water, as outlined in the
following sections. All pumps, valves, pipe work etc. are to be provided by EPS. A P&ID for the
treatment system is shown in figure 2.
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
4
Figure 2 - Treatment system P&ID
3.1 Preliminary Treatment
Preliminary treatment includes screening, equalisation and flow monitoring.
3.1.1 Screening Influent Wastewater
Mechanical screens have been incorporated into the design of the SBR to effectively remove debris
prior to entering the treatment process. Removing debris from the wastewater stream before it
reaches the basins is beneficial to both the treatment process and the settling phase; excess debris is
not present to interfere with the solids that need to settle, resulting in a high-quality sludge blanket.
Screens also provide protection for the pumps. A mechanical screening system for the plant will be
provided by EPS.
3.1.2 Influent-Flow Equalisation
Flow equalisation is critical as there will be significant variations in flow rates and organic mass
loadings. As the flow from the AITβs Engineering Building will be inherently variable, both on a daily
and seasonal basis, an equalisation tank were incorporated in the design. The equalisation tank was
sized to provide 60m3 of storage, which represents twice the maximum daily flow rate. This will allow
sufficient storage of influent in the case of the majority of breakdowns or maintenance issues. The
tank was designed with an inclined βVβ shaped base and sump containing a submersible pump for
ease of cleaning and the removal of settled solids. Submersible pumps for sludge wasting and for the
pumping of influent for further treatment will be provided by EPS.
Influent-flow equalisation benefits the SBR process in the following ways:
Allows for a smaller SBR-basin size because it allows for storage until the process cycle is
complete.
Allows for storage if the reactor basin must be taken off line for maintenance, or as a result
of a breakdown.
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
5
Allows for an equal flow volume into the reactor basin, keeping the food to microorganism
ratio (F/M) reasonably stable.
3.2 SBR Design
3.2.1 Reactor basin
SBR designs should have a minimum of two basins to allow for redundancy, maintenance, high flows,
and seasonal variations. Two basins also allow for redundancy throughout the plant. Due to the
relatively low flow rate entering the plant it was found to be unsuitable to provide two dedicated
reactors. In order to provide a backup treatment unit, the post basin equalisation tank has been
designed similarly to the reactor basin. If the primary reactor is off line, the plant is still able to treat
influent wastewater, by bypassing the primary reactor and utilising the post basin equalisation tank
as a backup reactor.
The biomass from the primary basin will be used to stock the secondary basin. For this to happen, a
means of transferring sludge between the two basins must be provided, this will be achieved by
means of the wasting pump which can be redirected to the post basin equalisation tank.
The reactor was designed to take account of flow rates, influent characteristics, hydraulic retention
time, effluent requirements etc.. The design process was completed in accordance with the design
process outlined by (Tchobanoglous, et al., 2003). From this process the reactor was sized to be
3.0m x 1.5m x 3.0m with a 0.4m free board. The completed design is provided in appendix A.
3.2.2 Flow-Paced Batch Operation
Flow-paced batch operation has been chosen for the system, this is generally preferable to time-
paced batch or continuous flow systems. Under a flow-paced batch system, the reactor receives the
same volumetric loading and approximately the same organic loading during every cycle. The SBR
basin already has stabilised supernatant in it, which dilutes the batch of incoming influent.
3.2.3 Aeration
Generally the finer the air bubbles used to aerate the waste water the more effective and
economical the treatment process. As such fine bubble membrane diffusers have been chosen over
coarse-air bubble aeration. Fine-bubble diffusers transfer more oxygen to the water due to
increased surface area in contact with water. The same amount of air introduced in a big bubble has
less surface area in contact with water than an equal amount of air divided into smaller bubbles. The
amount of surface area in contact with water is proportional to the amount of oxygen transferred
into water. Depth of aerators also plays a part in oxygen transfer, due to contact time. The deeper
the aerator, the longer it takes for the bubble to come to the surface. The fine bubble membrane
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
6
diffusers will be supplied by EPS, they will also supply blowers to supply air to the diffusers. As
previously mentioned the post basin equalisation tank will act as a standby reactor, as such it will
also be supplied with an aeration unit.
3.2.4 Decanting
During the decant phase, operating under a flow-paced batch operation, 60% of the volume
contained in the basin (i.e., the tank contents) will be decanted each time in order to prevent
disturbance of the sludge blanket. The decant phase should not interfere with the settled sludge,
and submersible pumps should avoid vortexing and taking in floatables. For the plant to run
optimally, it is important that the decant volume is the same as the volume added during the fill
phase.
3.2.5 Bottom Slope
As with the equalisation tank a sloped bottom with a sump has been provided for the purpose of
sludge wasting and for routine tank maintenance and ease of cleaning.
3.3 Post-Basin Effluent Equalisation
Post-basin effluent equalisation soothes out flow variations prior to downstream processes. By
providing storage and a controllable flow, a more economical downstream sewer system could be
deigned. This was possible as the flow from the basin is metered out and does not hydraulically
surge the downstream processes. The equalisation tank was provided which will receive effluent
from the reactor. Effluent equalisation also ensures that there are not large variations in operating
ranges. The tank was sized to hold one decantable volume of the reactor. The tank was also
designed similar to the primary reactor with an aeration system, sloped bottom with a sump and
submersible pump for sludge removal.
3.4 Parameters to Be Monitored by the SCADA System
SCADA is a computer-monitored alarm, response, control, and data acquisition system used by
operators to monitor and adjust treatment processes and facilities.
Oxidation reduction potential (ORP), dissolved oxygen (DO), pH, and alkalinity are parameters that
should be monitored by the Supervisory Control and Data Acquisition (SCADA) system.
Manufacturers determine what parameters can be monitored and controlled by the SCADA system.
Alkalinity monitoring and addition ensures that a pH of less than 7.0 does not occur. Nitrification
consumes alkalinity, and with a drop in alkalinity, pH also drops. If the plant has adequate alkalinity,
pH does not change, so it does not need to be raised. Monitoring of certain parameters is important,
and the ability to adjust these parameters from a remote location is ideal. The operator needs to be
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
7
able to add chemicals to raise the alkalinity and subsequently the pH. The set point should be an
alkalinity value rather than pH based. The operator should have the ability to fully control (i.e.,
modify) the plant-operating parameters, such as (but not limited to) cycle times, volumes, and set
points. The SCADA system will be installed and commissioned by EPS.
3.5 Sludge wasting and storage
Sludge wasting will occur during the idle cycle to provide the highest concentration of mixed liquor
suspended solids (MLSS). The plant will operate on kg of MLSS and not concentration. Sludge from
the SBR basin will be wasted to a pre-cast storage tank, with storage for over 28 days (9m3). The
sludge-holding-tank capacity was based on approximate sludge characteristics, see appendix A. A
high-level alarm and interlock will be provided to prevent sludge-waste pumps from operating
during high-level conditions in the holding tanks. Controls will also be provided to prevent overflow
of sludge from the holding tank. The sludge holding tank will consist of a steel fibre reinforced pre-
cast concrete unit with an approximate footprint of 2.6m x 2.6m, supplied by Shay Murtagh Precast.
4.0 Structural design of the treatment tank
The SBR was designed to be housed within a single reinforced concrete tank with interior dividing
walls to create individual tanks. The SBR system was also designed to be located entirely below
ground level. This layout was select for several reasons, firstly due to restrictions regarding available
space. By incorporating all treatment processes within a single unit the area requirements of the
system were greatly reduced. Also due to the nature of the institute minimal aesthetical impacts
were desirable as such by locating the system below ground level the visual impact was also greatly
reduced.
4.1 Equilibrium
In order to ensure the stability of the completed works the tank design was checked to ensure that
uplift would not occur. Due to the paucity of geotechnical information for the SBR location it was
assumed that the water table can rise to the surface. Uplift checks were completed in accordance
with EC-7 and the base of the tank was sized accordingly to ensure uplift was not possible. In order
to eliminate the possibility of uplift for the worst case scenario a base thickness 0.6m was found to
be necessary. See Appendix B for complete uplift calculations.
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
8
4.2 Walls
The exterior walls of the tank were analysed as retaining walls, as maximum stress will occur when
the tank empty and acting as an earth retaining structure. The design was completed in accordance
with EC-2. As stresses placed upon interior walls, including the worst case scenario, will be of a
lesser magnitude than that of the exterior wall similar reinforcing will be applied in those elements.
The completed structural design is supplied in Appendix C, and the associated bar schedule is
supplied in appendix D.
4.3 Base design
Similarly to the design of the walls of the tank the base was designed in accordance with EC-2
assuming the worst case scenario. The base was analysed as a one way spanning slab supported by
the side walls of the tank and loading was in the form of upward earth pressure. Upon completion of
the analysis it was found that minimum reinforcement governed. The base section was also analysed
for shear and was found not to require shear reinforcement. The section was also checked for crack
control, given the exposure class of the concrete and resulting minimum reinforcement the design
was found to be adequate. The section was also found to be adequate in relation deflection. The
completed structural design is supplied in Appendix C, and the associated bar schedule is supplied in
appendix D.
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
9
Sponsor Acceptance
Approved by the Project Sponsor:
____________________________________________ Date: _____________________
Project Sponsor: AIT
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
10
Appendix A: SBR Design
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
11
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR Design Calculation Sheet No.
1 of 7
Drawing Ref:
009
Calculations By:
TS
Checked By:
NMcH
Date
19/03/13
Reference Calculations Output
Primary data
Occupant No. 500
Flow (liters/day/person) 60
BOD5 (grams/person/day) 20
BOD5 (mg/l) 333
HYDRAULICS
Influent flow rate:
Q = No. occupants x Flow
= 500 x 60
= 30000 l/day
= 30 m3/day
Peak flow:
Daily flow Q through system assumed to occur between 9am and 6pm.
Time (T) = 9 hours
Peak flow factor =3.
Ts = 9 x 3600
= 32400 seconds
q = π π₯ 1000
ππ Γ 3
= 30 π₯ 1000
32400 π₯ 3
= 2.78 l/s
Q = 30m3/day
Q = 2.78 l/s
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
12
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR Design Calculation Sheet No.
2 of 7
Drawing Ref:
009
Calculations By:
TS
Checked By:
NMcH
Date
19/03/13
Reference Calculations Output
Dimensions:
7.0 x 3.0 x 3.0
SYSTEM SIZING
Hydraulic Retention Time (HRT) = 6 hours
Reactor Decant Rate (R) = 60%
Inner tank dimensions: Width (W) = 3.0 m
Depth (D)= 3.0 m
Free board (FB) = 0.4 m
Equalisation tank to provide minimum 24 hours storage.
Equalisation tank Ve = Q x 2
= 30 x 2
= 60 m3
Equalisation tank length = ππ
π π₯ π·
= 60
3.0 π₯ 3.0
= 6.667 m
1 No. Primary aeration basin to be provided. Post basin equalisation tank to
be designed to act as a standby reaction basin.
Batch Volume = π
24/π
=30
24/6
=7.5 m3
Aeriation Basin Vr = π
24Γ·π»π πΓ·
π
100
= 30
24Γ·6Γ·
60
100
= 12.5 m3
Ve = 60m3
Vr = 12.5m3
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
13
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR Design Calculation Sheet No.
3 of 7
Drawing Ref:
009
Calculations By:
TS
Checked By:
NMcH
Date
19/03/13
Reference Calculations Output
Dimensions:
1.5 x 3.0 x 3.0
Dimensions:
1.5 x 3.0 x 3.0
Aeration Basin length = ππ
3.2 π₯ 3
= 12.5
3.0 π₯ 3.0
= 1.389 m
Post basin equalisation tank Vp = 12.5 m3
Post basin equalisation tank length = ππ
3.2 π₯ 3
= 12.5
3.0 π₯ 3.0
= 1.389 m
Vp = 12.5m3
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
14
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR Design
Calculation Sheet No.
4 of 7
Drawing Ref:
009
Calculations By:
TS
Checked By:
NMcH
Date
19/03/13
Reference Calculations Output
Reactor
MLVSS = ππππ π₯ ππ
π π₯ πΉπ
= 250 π₯ 7500
7500 π₯ 0.1
= 2500 mg/l
MLSS = (SS βVSS) ππΏπππ
0.8
= (250 β200) 2500
0.8
= 3175 mg/l
VSStotal = ππΏπππ π₯ ππ
10πΈ6
2500 π₯ 7500
10πΈ6
= 18.75 kg
Parameter Value Unit
Effluent BOD5 25 mg/l
Reactor Volume 7500 l/d
Influent suspended solids, SS 250 mg/l
Influent volatile suspended solids, VSS 200 mg/l
Wastewater temperature 10 oc
Influent BOD5 for each day 250 mg/l
Hydraulic detention time, ΞΈ 6 h
Food-to-microorganism ratio, FM 0.1 MLVSS/MLSS
Kinetic coefficients: Biomass yield, Y 0.65 kg/kg
Endogenous decay coefficient, kd 0.05 d-1
Average concentration of settled sludge, C 8000 mg/l
Settled sludge specific gravity, G 1.02
Percent of the reactor volume which will be decanted, Dr 60 %
Liquid depth of SBR 2.6 m
Sludge wasting per day As required
Percent of biodegradable in effluent 80 %
Treatment Parameters
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
15
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR Design
Calculation Sheet No.
5 of 7
Drawing Ref:
009
Calculations By:
TS
Checked By:
NMcH
Date
19/03/13
Reference Calculations Output
SStotal = ππΏππ π₯ ππ
10πΈ6
= 3175 π₯ 7500
10πΈ6
= 23.813 kg
Reactor Sludge Storage S = (SStotal x 10E6)/(C x G x 1000)
= (23.813 x 10E6)/(8000 x 1.02 x 1000)
= 2.918 m3
Sludge Depth = π
π΄πππ
= 2.918
3.0 π₯ 1.5
= 0.648 m
Liquid Depth, d = D β FB
= 3.0 β 0.4
= 2.6 m
Liquid Depth Following Decant = 2.4 β (d x Dr)
= 2.4 β (2.6 x 0.6)
= 0.84 m
Sludge Depth < Liquid Depth Following Decant
Reactor sludge
storage = 2.918m3
Reactor
adequately sized
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
16
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR Design
Calculation Sheet No.
6 of 7
Drawing Ref:
009
Calculations By:
TS
Checked By:
NMcH
Date
19/03/13
Reference Calculations Output
SLUDGE PRODUCTION
Following calculations per 7.5m3 batch
Volitile Solids Px = (Y x (SS β VSS) x Vr) β (πΎπ π₯ ππΏπππ)
10πΈ6
= (0.65 x (250 β 200) x 7500) β (0.5 π₯ 2500
10πΈ6
= 0.244 kg
Inert Solids SSi = (SS β VSS) x Vr
= (250 β 200) x 7500
= 0.350 kg
Total solids produced SSt = SSi + Px
= 0.350 + 0.244
= 0.594 kg
Sludge Produced S = πππ‘ π₯ 10πΈ6
πΆ π₯ πΊ
= 0.594 π₯ 10πΈ6
8000 π₯ 1.02
= 73 l
Sludge produced
per batch = 73l
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
17
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR Design
Calculation Sheet No.
7 of 7
Drawing Ref:
009
Calculations By:
TS
Checked By:
NMcH
Date
19/03/13
Reference Calculations Output
Monthly Sludge
Storage = 9000m3
Monthly Sludge Storage = π π₯ 4 π₯ 7 π₯ 4.33
1000
= 73 π₯ 4 π₯ 7 π₯ 4.33
1000
= 8.832 m3
Provide 9000m3 sludge holding tank
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
18
Appendix B: Uplift Check
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
19
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR uplift check
Calculation Sheet No.
1 of 3
Drawing Ref: Calculations By:
TS
Checked By:
NMH
Date
21/03/13
Reference Calculations Output
Tank Data
Tank length, B = 11.2 m
Tank depth, H = 3.0 m
Tank width, W = 3.6 m
Wall thickness, t = 0.3m
2 No. internal walls
Concrete Lid to cover tank 0.2 m thick
Assume base depth, D = 0.6m
Soil Parameters
C,k = 0
β βk = 30
Ξ³ = 22 Kn/m3
ULS DESIGN
πππ π‘,π β€ πΊπ π‘π,π + π π
DESTABILISING VERTICLE ACTION
πππ π‘,π β€ πΊππ π‘,π
= πΎπΊ,ππ π‘ πΎπ€ (π» + π·) π΅
= 1.0 x 9.81 x (3.0 + 0.6) 11.2
= 384.6 Kn/m
EC β 7 Eq. 2.8
EC β 7 Table A.15
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
20
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR uplift check
Calculation Sheet No.
2 of 3
Drawing Ref: Calculations By:
TS
Checked By:
NMH
Date
21/03/13
Reference Calculations Output
STABILISING VERTICAL ACTION
πΊπ π‘π,π = πΎπΊ,π π‘π (πΎπ,π (4 π‘ π» + π΅ π· + π΅ π‘π + 2 π₯ (π΅(π» + π·)π₯π‘)
π) )
= 0.9 (24(4 x 0.3 x 3.0 + 11.2 x 0.5 + 11.2 x 0.2 + 2(11.2(3.0+0.5)0.3
3.2))
= 405.9 Kn/m
Additional resistance between soil and tank side walls must be calculated
π π = 2 (π» + π·)πΎ ππ£β² tan πΏ
ππ£β² = 0.5 (π» + π·)(πΎ β πΎπ€)
= 0.5 (3.0 + 0.5)(22 β 9.81)
= 21.3 Kn/m2
πΏβ² =2
3(β πΎ
β² )
= 2
3(30)
= 20o
K = 0.29
π π = 2 (3.0 + 0.5)0.29 π₯ 21.3 π₯ tan 20
= 15.7 Kn/m
EC β 7 Table C.1.1
EC β 7 Table A.15
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
21
Project
AIT Wastewater Treatment System
Revision
Part of Structure
SBR uplift check
Calculation Sheet No.
3 of 3
Drawing Ref: Calculations By:
TS
Checked By:
NMH
Date
21/03/13
Reference Calculations Output
π π = 2 (π» + π·)πΎπ ππ£β² tan πΏπ
β²
β πβ² = π‘ππβ1 (
tan β πβ²
πΎπ)
= π‘ππβ1 (tan 30
1.25)
= 24.8o
πΏπβ² =
2
3(β π
β² )
= 2
3(24.8)
= 16.5o
Kd = 0.5
π π = 2 (3.0 + 0.5)0.5 π₯21.3 π₯ tan 16.5
= 22.1 Kn/m
π π =π π
πΎπ
= 15.7
1.25
= 12.6 Kn/m
πππ π‘,π β€ πΊπ π‘π,π + π π
384.6 β€ 405.9 + 12.6
384.6 β€ 418.5
EC β 7 Table C.1.1
Adequate to resist
uplift
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
22
Appendix C: Structural Design
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
23
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank
Calculation Sheet No.
1 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
21/03/13
Reference Calculations Output
BS-8005
Tank Data Tank length, B = 11.2 m Tank depth, H = 3.0 m Tank width, W = 3.6 m Base depth, D = 0.6m Wall thickness, t = 0.3m 2 No. internal walls Concrete Lid to cover tank 0.2 m thick Soil Parameters C,k = 0 β βk = 30 Ξ³ = 22 Kn/m3
Ka = 0.5 ABP = 300 kN/m2
Materrial Properties fck = 50 N/mm2 fct,eff = -4 N/mm2
fyk = 500 N/mm2 Ep = 200 kN/mm2 Ecm = 37.3 kN/mm2
National Annex Based Factors
G,sup SW = 1.35, Partial factor for unfavourable self-weight β ULS
G,inf SW = 1.0 Partial factor for favourable self-weight β ULS
Q,sup live = 1.5 Partial factor for unfavourable live loads β ULS
cc = 0.85 Compressive strength factor
c = 1.5 Partial factor for concrete (for ULS)
s = 1.15 Partial factor for rebar (for ULS)
EXPOSURE CLASS AND DURABILITY REQUIREMENTS
Exposure class = XD3
Minimum concrete cover to rebar = 45 mm
Allowable crack width = 0.30 mm
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
24
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank Stability Check
Calculation Sheet No.
2 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
23/03/13
Reference Calculations Output
HORIZONTAL FORCE
pa = KaΟgh
= 0.26 x 2200 x 10-3 x 9.81 x 3.6
= 20.2 Kn/m2
Allowing for the minimum required surcharge of 10 kN/m2, and additional
horizontal pressure of:
ps = 0.26 x 10
= 2.6 kN/m2
Hk(earth) = 0.5 pah
= 0.5 x 20.2 x 3.6
= 36.40 kN
Hk(sur) = psh
= 3.3 x 3.6
= 11.88 kN
VERTICAL LOADS
Permanent Loads:
Wall = 0.3 x 3.0 x 24 = 21.6 kN/m
Base = 0.6 x 1.8 x 24 = 25.9 kN/m
Lid = 0.2 x 1.8 x 24 = 8.6 kN/m
Total = 56.1 kN/m
Variable Loads
Effluent = 1.5 x 2.6 x 9.81 = 45.9 kN/m
Hk(earth) = 36.40
kN
Hk(Sur) = 11.88 kN
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
25
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank Wall Design
Calculation Sheet No.
3 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
23/03/13
Reference Calculations Output
BEARING PRESSURES AT THE ULTIMATE LIMIT STATE
Consider load combination 1 as the critical combination
p = N/D +/- 6M/D2
M = Ξ³f (Hk(earth) x arm) + Ξ³f (Hk(surcharge) x arm) + Ξ³f (wall x arm)
+ Ξ³f (Effluent x arm)
= 1.35 (36.4 x 3.6/3) + 1.5 (16.2 x 3.6/2) + 1.35 (21.6 x 0.75)
+ 1.5 (45.9 x 0.15)
= 59.0 + 43.7 + 21.9 + 10.3
= 134.9 kN m
Therefore bearing pressure at centre of tank:
P = (1.35 x (21.6 + 25.9 + 8.6) )/1.8 +/- (6 x 134.9)/1.82
= 42.1 +/- 249.8
= 291.9, -207.7 kN/m2
291.9 < 300 kN/m2 therefore passes bearing check
P = 291.9,
-207.7 kN/m2
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
26
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank Wall Design
Calculation Sheet No.
4 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
23/03/13
Reference Calculations Output
BENDING REINFORCEMENT
Wall:
Horizontal force = Ξ³f 0.5 KaΟgh2 + Ξ³f psh
= 1.35 x 0.5 x 0.26 x 2200 x 10-3 x 9.81 x 3.02 + 1.50 x 2.6 x 3.0
= 34.1 + 11.7
= 45.8 Kn
Considering the effective span, the maximum moment is:
MEd = 34.1 x (0.3 + 3.0/3) + 11.7 x (0.3 + 3.0/2)
= 65.4 kNm
MEd/bd2fck = 65.4 π₯106
1000 π₯ 2452 π₯ 50
= .022
Therefore la = 0.95
As = 65.4 π₯106
0.95 π₯ 245 π₯ .87 π₯ 500
= 646 mm2/m
Provide H16 bars at 225 mm centres (As(Prov) = 894 mm2/m)
The minimum area for inner and transverse wall reinforcement is given by:
As = 0.15btd/100
= 0.0015 x 1000 x 245
= 368 mm2
Provide H12 bars at 225 mm centres (As = 393 mm2/m),
bottom and distribution steel
As(Prov) = 894 mm2/m
As(Prov) = 393 mm2/m
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
27
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank Base Design
Calculation Sheet No.
5 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
23/03/13
Reference Calculations Output
BASE Vertical Loads:
Permanent Loads:
Base = 0.6 x 3.6 x 24 = 51.8 kN
Variable Loads
Effluent = 3.0 x 2.6 x 9.81 = 76.5 kN
Ground Water = 9.81 x 3.6 x 3.6 = -127.1 kN MEd = (1.0(51.8) + 1.0 (76.5)) 3.6 / 4 = 115.5 kN m MEd = (1.0(51.8) - 1.5 (127.1)) 3.6 / 4 = -125.0 kN m
MEd/bd2fck = 125.0 π₯106
1000 π₯ 5452 π₯ 50
= 0.008 Therefore la = 0.95
As,req = 125.0π₯106
0.95 π₯ 545 π₯ .87 π₯ 500
= 555 mm2/m The minimum area for steel and longitudinal distribution steel which is required in base is given by:
As = 0.15btd/100 = 0.0015 x 1000 x 545 = 818 mm2
Provide H16 bars at 225 mm centres (As = 894 mm2/m), all
directions
As(Prov) = 894 mm2/m
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
28
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank Base Design
Calculation Sheet No.
6 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
23/03/13
Reference Calculations Output
Base Shear
VEd = 37.7 kN
VRd,c = [CRd,ck(100Οlfck)1/3+k1Οcp]bwd
K = 1 + β200
πβ€ 2.0
= 1 + β200
600
= 1 + 0.58
= 1.58
Οl = π΄π π
ππ€π β€ 0.02
= 818
1000 π₯ 600
= .0014
Οcp = ππΈπ
π΄π β€ 0.2 fcd
= 138.9πΈ3
1000 π₯ 600 β€ 0.2 x 50
= .232 β€ 10
CRd,c = 0.18
πΎπ
= 0.18
1.5
= 0.12
Kl = 0.15
VRd,c = [0.12 x 1.58(100 x 0.0014 x 50)1/3+ 0.15 x 0.232]1000 x 600
= 238β495 N
= 238 kN
VEd < VRd,c
No shear reinforcement required VEd < VRd,c
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
29
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank Base Design
Calculation Sheet No.
7 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
23/03/13
Reference Calculations Output
BS EN
1992-1-1
7.3.2 (2)
BS EN
1992-1-1
T 7.1N
BS EN
1992-1-1
7.4.2 (2)
Base Cracking
For exposure class XD3 wmax = 0.3 mm
As,minΟs = kc k fct,eff Act
For pure bending kc = 0.4
K = 0.79
fct,eff = fctm
= 0.3fck2/3
= 0.3 x 502/3
= 4.1 N/mm2
Act =
πβ
2
= 1000 π₯ 600
2
= 300β000 mm2
Οs= fyk = 500 N/mm2
As,min,c = 0.4 x 0.79 x 4.1 x 300β000/500
= 777 mm2/m
As,prov > As,min,c
Therefore no additional steel required for crack control
Deflection
π0
π =
ππβπππ
π΄π ,πππ x 10-3
= 1000 π₯ 600β50
738 x 10-3
= 5.7
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
30
Project
AIT Wastewater Treatment System
Revision
Part of Structure
Concrete Tank Base Design
Calculation Sheet No.
8 of 8
Drawing Ref:
010
Calculations By:
TS
Checked By:
NMH
Date
23/03/13
Reference Calculations Output
The 'uncorrected' value of the limiting span/effective depth ratio, for
values of Ο0/Ο > 1.0 is given by
(l/d)0 = πΎ[11 + 1.5βππππ0
π+ 3.2 βπππ(
π0
πβ 1)3/2]
= 1.3 x [11 + 1.5 β50 x 5.7 + 3.2 β50 x (5.7 - 1)3/2 ]
= 393
This value should be multiplied by 310/Οs where the reinforcement stress under the characteristic load is given approximately by:
310/Οs =500
ππ¦π π΄π ,πππ
π΄π ,ππππ£
= 500
500 π₯ 738
818
= 1.11
(l/d)lim = 393 x 1.1
= 432
(l/d)act = 3600
600
= 6
Therefore section is adequate to meet deflection requirements
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
31
Appendix D: Bar Schedule
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
32
TNLS Consulting Engineers Drawing ref : 010 Rev: B
Site ref : AIT
Date prepared : 24-Mar-13
Job : Waste Water Treatment System
Prepared by : TS
Checked by : NMH
Member Bar
Mark
Type and size
No. of
mbrs
No. of bars
in each
Total no.
Length of each bar β mm
Shape code
A * B * C * D * E/R * Rev letter
mm mm mm mm mm
Wall 01 H 16 1 50 50 10825 41 210 3510 3510 3510 210 A
02 H 12 1 132 132 3750 23 210 3010 560 A
03 H 16 1 32 32 9050 12 3510 5555 A
04 H 16 1 14 14 10425 23 420 7045 3015 210 A
05 H 16 1 14 14 7950 41 210 3015 1625 3015 210 A
06 H 16 1 14 14 4725 23 210 3015 1545 A
07 H 16 1 50 50 4300 21 420 3510 420 A
08 H 10 1 32 32 12000 21 475 11080 475 A
09 H 10 1 32 32 4300 21 420 3480 420 A
10 H 10 1 28 28 10625 21 1770 7115 1770 A
11 H 10 1 56 56 5125 21 1770 1615 1770 A
12 H 16 1 14 14 850 00 840 B
This schedule conforms to BS 8666:2005
* Specified in multiples of 5mm. β Specified in multiples of 25mm.
type size
AIT Waste Water Treatment Facility: Sequencing Batch Reactor Design Report
33