Scheduled CurtailmentsCancellations
• Should be received at least one business day prior to start date of curtailment
• Resource Availability should not reflect the curtailment
• Day Ahead offers can be entered
1
2
Scheduled CurtailmentsModifications
• Modification 1:– Delayed start date, same end date – Notice must be received at least 7 calendar days prior to changed start
date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)
Original Curtailment
Start Date End Date
Modification 1: Later Start Date
Start Date
3
Scheduled CurtailmentsModifications
• Modification 2:– Same start date, earlier end date– Notice must be received at least 7 calendar days prior to changed end
date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)
– Same requirements if curtailment extended past original end date (notice 7 / 15 calendar days prior to original end date)
Original Curtailment
Start Date End Date
Modification 2: Earlier End Date
End Date
4
Scheduled CurtailmentsCurtailment Schedule Change
• Change in Schedule:– Change to both start and end dates– Original curtailment will be cancelled, new curtailment entered– Notice must be received at least 7 calendar days prior to curtailment
start date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)
Original Curtailment
Start Date End Date
Change: Different Start and End Dates
End DateStart Date