Scheduled Curtailments Cancellations. Should be received at least one business day prior to start date of curtailment Resource Availability should not reflect the curtailment Day Ahead offers can be entered. Scheduled Curtailments Modifications. Modification 1: - PowerPoint PPT Presentation
Popular Tags:
4
Scheduled Curtailments Cancellations Should be received at least one business day prior to start date of curtailment Resource Availability should not reflect the curtailment Day Ahead offers can be entered 1
Transcript
Page 1: Scheduled Curtailments Cancellations

Scheduled CurtailmentsCancellations

• Should be received at least one business day prior to start date of curtailment

• Resource Availability should not reflect the curtailment

• Day Ahead offers can be entered

1

Page 2: Scheduled Curtailments Cancellations

2

Scheduled CurtailmentsModifications

• Modification 1:– Delayed start date, same end date – Notice must be received at least 7 calendar days prior to changed start

date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)

Original Curtailment

Start Date End Date

Modification 1: Later Start Date

Start Date

Page 3: Scheduled Curtailments Cancellations

3

Scheduled CurtailmentsModifications

• Modification 2:– Same start date, earlier end date– Notice must be received at least 7 calendar days prior to changed end

date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)

– Same requirements if curtailment extended past original end date (notice 7 / 15 calendar days prior to original end date)

Original Curtailment

Start Date End Date

Modification 2: Earlier End Date

End Date

Page 4: Scheduled Curtailments Cancellations

4

Scheduled CurtailmentsCurtailment Schedule Change

• Change in Schedule:– Change to both start and end dates– Original curtailment will be cancelled, new curtailment entered– Notice must be received at least 7 calendar days prior to curtailment

start date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)

Original Curtailment

Start Date End Date

Change: Different Start and End Dates

End DateStart Date


Recommended