+ All Categories
Home > Documents > Scheduling Resources and Costs

Scheduling Resources and Costs

Date post: 02-Jun-2018
Category:
Upload: rajesh-singh
View: 226 times
Download: 0 times
Share this document with a friend

of 42

Transcript
  • 8/10/2019 Scheduling Resources and Costs

    1/42

    21

  • 8/10/2019 Scheduling Resources and Costs

    2/42

    Agenda of the Lecture

    1. Overview of the Resource Scheduling Problem

    2. Types of Resource Constraints

    3. Classification of a Scheduling Problem

    4. Resource Allocation MethodsA. Assumptions

    B. Time-Constrained Projects: Smoothing Resource Demand

    C. Resource-Constrained Projects

    5. Computer Demonstration of Resource-Constrained Scheduling

    A. The Impacts of Resource-Constrained Scheduling

    6. Splitting Activities

    7. Benefits of Scheduling Resources

    8. Assigning Project Work9. Multi project Resource Schedules

    10. Using the Resource Schedule to Develop a Project Cost Baseline

    A. Why a Time-Phased Budget Baseline Is Needed

    B. Creating a Time-Phased Budget

    82

  • 8/10/2019 Scheduling Resources and Costs

    3/42

    83

    Overview of the Resource Scheduling Problem

    Resources and PrioritiesProject network times are not a schedule

    until resources have been assigned.

    The implicit assumption is that resources will be available in

    the required amounts when needed.Adding new projects requires making realistic judgments of

    resource availability and project durations.

    Cost estimates are not a budget

    until they have been time-phased.

  • 8/10/2019 Scheduling Resources and Costs

    4/42

    84

    Project Planning Process

    FIGURE 8.1

  • 8/10/2019 Scheduling Resources and Costs

    5/42

    85

    Overview of the Resource Scheduling Problem

    .

    Resource Smoothing (or Leveling)

    Involves attempting to even out varying demandson resources by using slack (delaying noncriticalactivities) to manage resource utilization whenresources are adequate over the life of the project.

  • 8/10/2019 Scheduling Resources and Costs

    6/42

    86

    Types of Project Constraints

    Technical or Logic Constraints Constraints related to the networked sequencein which project activities must occur.

    Physical ConstraintsActivities that cannot occur in parallel or are affected by

    contractual or environmental conditions.

    Resource Constraints The absence, shortage, or unique interrelationship and

    interaction characteristics of resources that require a particular

    sequencing of project activities Kinds of Resource Constraints

    People, materials, equipment

  • 8/10/2019 Scheduling Resources and Costs

    7/4287

    Constraint Examples

    FIGURE 8.2

  • 8/10/2019 Scheduling Resources and Costs

    8/4288

    Classification of A Scheduling Problem

    Classification of ProblemUsing a priority matrix will help determine if

    the project is time or resource constrained.

    1.Time-Constrained Project

    Must be completed by an imposed date. Time is fixed, resources are flexible: additional resources

    are required to ensure project meets schedule.

    2.Resource-Constrained Project

    Is one in which the level of resources availablecannot be exceeded.

    Resources are fixed, time is flexible: inadequateresourceswill delay the project.

  • 8/10/2019 Scheduling Resources and Costs

    9/4289

    Resource Allocation Methods

    Limiting AssumptionsSplitting activities is not allowedonce an

    activity is start, it is carried to completion.

    Level of resources used for an activity cannot

    be changed.

    Risk Assumptions

    Activities with the most slack pose the least risk.

    Reduction of flexibility does not increase risk.The nature of an activity (easy, complex)

    doesnt increase risk.

  • 8/10/2019 Scheduling Resources and Costs

    10/42810

    Resource Allocation Methods (contd)

    Time-Constrained ProjectsMust be completed by an imposed date.

    Require use of leveling techniques that focuson balancing or smoothing resource demands.

    Use positive slack (delaying noncritical activities)to manage resource utilization over the durationof the project.

    1. Peak resource demands are reduced.2. Resources over the life of the project are

    reduced.

    3. Fluctuation in resource demand is minimized.

  • 8/10/2019 Scheduling Resources and Costs

    11/42

  • 8/10/2019 Scheduling Resources and Costs

    12/42

    812

    Resource Allocation Methods (contd)

    Resource Demand Leveling Techniquesfor Time-Constrained Projects

    Advantages

    Peak resource demands are reduced.

    Resources over the life of the project are reduced.

    Fluctuation in resource demand is minimized.

    Disadvantages

    Loss of flexibility that occurs from reducing slack.

    Increases in the criticality of all activities.

  • 8/10/2019 Scheduling Resources and Costs

    13/42

    813

    Resource Allocation Methods (contd)

    Resource-Constrained Projects Resources are limited in quantity or availability.

    Activities are scheduled using heuristics(rules-of-thumb) that focus on:

    1. Minimum slack

    2. Smallest (least) duration

    3. Lowest activity identification number

    The parallel method is used to apply heuristics

    An iterative process starting at the first time periodof the project and scheduling period-by-period the startof any activities using the three priority rules.

  • 8/10/2019 Scheduling Resources and Costs

    14/42

    814

    Resource-Constrained Schedule through Period 23

    FIGURE 8.4

  • 8/10/2019 Scheduling Resources and Costs

    15/42

    815

    Resource-Constrained Schedule through Period 23

    FIGURE 8.4 (contd)

  • 8/10/2019 Scheduling Resources and Costs

    16/42

    816

    Resource-Constrained Schedule through Period 23

    FIGURE 8.4 (contd)

  • 8/10/2019 Scheduling Resources and Costs

    17/42

    817

    Resource-Constrained Schedule through Period 56

    FIGURE 8.5

  • 8/10/2019 Scheduling Resources and Costs

    18/42

    818

    Resource-Constrained Schedule through Period 56

    FIGURE 8.5 (contd)

  • 8/10/2019 Scheduling Resources and Costs

    19/42

    819

    Resource-Constrained Schedule through Period 56

    FIGURE 8.5 (contd)

  • 8/10/2019 Scheduling Resources and Costs

    20/42

    820

    Computer Demonstration of Resource-Constrained Scheduling

    EMR Project

    The development of a handheld Electronic MedicalReference guide to be used by emergency medical

    technicians and paramedics. Problem

    There are only eight design engineers who can beassigned to the project due to a shortage of design

    engineers and commitments to other projects.

  • 8/10/2019 Scheduling Resources and Costs

    21/42

    821

    EMR Project:

    Network ViewSchedule before

    Resources Leveled

    FIGURE 8.6

  • 8/10/2019 Scheduling Resources and Costs

    22/42

    822

    EMR Project before Resources Added

    FIGURE 8.7

  • 8/10/2019 Scheduling Resources and Costs

    23/42

    823

    EMR ProjectTime Constrained Resource Usage View,January 1523

    FIGURE 8.8A

  • 8/10/2019 Scheduling Resources and Costs

    24/42

    Resources Calculations

    Project requires 21 design engineers on Jan 18thand 19th (168 hrs/8 hrs per engineer = 21

    engineers)

    824

    FIGURE 8.8A

  • 8/10/2019 Scheduling Resources and Costs

    25/42

    825

    Resource Loading Chart for EMR Project, January 1523

    FIGURE 8.8B

  • 8/10/2019 Scheduling Resources and Costs

    26/42

    826

    EMR ProjectNetwork View

    Schedule

    after ResourcesLeveled

    FIGURE 8.9

  • 8/10/2019 Scheduling Resources and Costs

    27/42

    827

    EMR Project Resources Leveled

    FIGURE 8.10

  • 8/10/2019 Scheduling Resources and Costs

    28/42

    828

    The Impacts of Resource-ConstrainedScheduling

    Reduces delay but reduces flexibility.

    Increases criticality of events.

    Increases scheduling complexity. May make the traditional critical path

    no longer meaningful.

    Can break sequence of events.

    May cause parallel activities to becomesequential and critical activities with slackto become noncritical.

  • 8/10/2019 Scheduling Resources and Costs

    29/42

    829

    Splitting

    Splitting A scheduling technique use to get a better project

    schedule and/or increase resource utilization.

    Involves interrupting work on an activity to

    employ the resource on another activity, thenreturning the resource to finish the interruptedwork.

    Is feasible when startup and shutdown costs are

    low.

    Is considered the major reason why projects failto meet schedule.

  • 8/10/2019 Scheduling Resources and Costs

    30/42

    830

    Splitting Activities

    FIGURE 8.11

  • 8/10/2019 Scheduling Resources and Costs

    31/42

    831

    Benefits of Scheduling Resources

    Leaves time for considerationof reasonable alternatives:

    Cost-time tradeoffs

    Changes in priorities

    Provides information for time-phasedwork package budgets to assess:

    Impact of unforeseen events

    Amount of flexibility in available resources

  • 8/10/2019 Scheduling Resources and Costs

    32/42

    832

    Multiproject Resource Schedules

    Multiproject Scheduling Problems1. Overall project slippage

    Delay on one project create delays for other projects

    2. Inefficient resource application

    The peaks and valleys of resource demands createscheduling problems and delays for projects.

    3. Resource bottlenecks

    Shortages of critical resources required for multipleprojects cause delays and schedule extensions.

  • 8/10/2019 Scheduling Resources and Costs

    33/42

    833

    Multiproject Resource Schedules (contd)

    Managing Multiproject Scheduling:Create project offices or departments to oversee

    the scheduling of resources across projects.

    Use a project priority queuing system: first come,

    first served for resources.

    Centralize project management: treat all projectsas a part of a megaproject.

    Outsource projects to reduce the numberof projects handled internally.

  • 8/10/2019 Scheduling Resources and Costs

    34/42

    834

    Direct Labor BudgetRollup ($000)

    FIGURE 8.12

  • 8/10/2019 Scheduling Resources and Costs

    35/42

    835

    Time-Phased Work Package Budget (Labor Cost Only)

    FIGURE 8.13

  • 8/10/2019 Scheduling Resources and Costs

    36/42

    836

    Two Time-Phased Work Packages (Labor Cost Only)

    FIGURE 8.14

  • 8/10/2019 Scheduling Resources and Costs

    37/42

    837

    Patient Entry Project Network

    FIGURE 8.15

  • 8/10/2019 Scheduling Resources and Costs

    38/42

    838

    Patient Entry Time-Phased Work Packages Assigned

    FIGURE 8.16

  • 8/10/2019 Scheduling Resources and Costs

    39/42

    839

    CEBOO Project Monthly Cash Flow Statement

    FIGURE 8.17

  • 8/10/2019 Scheduling Resources and Costs

    40/42

    840

    CEBOO Project Weekly Resource Usage Schedule

    FIGURE 8.18

  • 8/10/2019 Scheduling Resources and Costs

    41/42

    841

    Key Terms

    Heuristic

    Planned value (PV)

    Resource-constrained projects

    Smoothing

    Splitting

    Time-constrained projects

    Time-phased budget baseline

  • 8/10/2019 Scheduling Resources and Costs

    42/42

    The End

    Thanks a lot for Your Attention!

    Any Comment !!!

    Any Question?????


Recommended