Smart City Mission Details of the Scheme: The Smart City Mission is an ambitious programme of Hon’ble Prime Minister of India. The mission will cover 100 cities and its duration will be five years (FY2015- 16 to FY2019- 20). The objective is to promote cities that provide core infrastructure and give a decent quality of life to its citizens, a clean and sustainable environment and application of ‘Smart’ Solutions. The focus is on sustainable and inclusive development and the idea is to look at compact areas, create a replicable model which will act like a light house to other aspiring cities. During the FY 2020-21, a budget provision of Rs. 100 Crore (Rs. 50 Crore as Centre Share and Rs. 50 Crore as State Share) has been made. Status of Dharamshala Smart City Limited (DSCL): Dharamshala was included under SCM during May 2016. (2016 - 2021) The Special Purpose Vehicle was formed on 24/06/2016 and Dharamshala Smart City Limited (DSCL) was registered under the companies Act, 2013 on 20 th July, 2016. The Proposal for Smart City Projects is of Rs. 2109.69 Crore with 74 Projects. o 8 Projects of Rs. 52.75 Cr. have been completed under SCM funds. o 8 Projects of Rs. 25.59 Cr. have been completed under convergence o 25 Projects of Rs. 216.82 Cr. are under execution o 9 Projects of Rs. 279.35 Cr. are to be awarded by 30.03.2021. DSCL has received Rs. 222.89 Crore (GOI funds Rs. 196 Crore and GoHP funds Rs. 26.89 Crore. Rs. 49.00 Crores have been released by GOI as Central share recently which is being released by GoHP. DSCL has utilized approx. Rs. 173.00 Crore. UC amounting to Rs. 169.11 Crore has been submitted to GoI on 31.08.2020.
Transcript

Smart City Mission

Details of the Scheme: The Smart City Mission is an ambitious programme of Hon’ble Prime

Minister of India. The mission will cover 100 cities and its duration will be five years (FY2015-

16 to FY2019- 20). The objective is to promote cities that provide core infrastructure and give a

decent quality of life to its citizens, a clean and sustainable environment and application of ‘Smart’

Solutions. The focus is on sustainable and inclusive development and the idea is to look at compact

areas, create a replicable model which will act like a light house to other aspiring cities. During

the FY 2020-21, a budget provision of Rs. 100 Crore (Rs. 50 Crore as Centre Share and Rs. 50

Crore as State Share) has been made.

Status of Dharamshala Smart City Limited (DSCL):

Dharamshala was included under SCM during May 2016. (2016 - 2021)

The Special Purpose Vehicle was formed on 24/06/2016 and Dharamshala Smart City

Limited (DSCL) was registered under the companies Act, 2013 on 20th July, 2016.

The Proposal for Smart City Projects is of Rs. 2109.69 Crore with 74 Projects.

o 8 Projects of Rs. 52.75 Cr. have been completed under SCM funds.

o 8 Projects of Rs. 25.59 Cr. have been completed under convergence

o 25 Projects of Rs. 216.82 Cr. are under execution

o 9 Projects of Rs. 279.35 Cr. are to be awarded by 30.03.2021.

DSCL has received Rs. 222.89 Crore (GOI funds Rs. 196 Crore and GoHP funds Rs. 26.89

Crore.

Rs. 49.00 Crores have been released by GOI as Central share recently which is being released

by GoHP.

DSCL has utilized approx. Rs. 173.00 Crore.

UC amounting to Rs. 169.11 Crore has been submitted to GoI on 31.08.2020.

Status of Shimla Smart City Limited (SSCL):

Shimla was got selected under SCM in June, 2017. (2017 - 2022)

The SPV has been Notified on 09/08/2017 and registered under the Companies Act, 2013

on 01.01.2018.

The Shimla Smart City proposal is of Rs. 2905.97 Crore with 53 Projects.

Out of 53 Projects, 28 most doable projects have been identified and are given to line

departments

o 2 components of Rs. 0.91 Cr. have been completed

o 40 components of Rs. 152.88 Cr. have been awarded /under implementation.

o Tender floated for 35 components Rs. 82.59 Cr.

SSCL has received Rs. 100 Crore (GOI funds Rs. 58 Crore and GoHP Rs. 42.00 Crore) and

Rs. 34 Crore have been released to SSCL in FY 2019-20.

Rs. 68.00 Crores have been released by GOI as Central share recently which is being released

by GoHP.

SSCL has utilized approx. Rs. 89.50 Crore.

UC amounting to Rs. 89.07 Crore has been submitted to GoI on 31.08.2020.

SSCL Projects under Active Implementation:

Sr.No.

(Name of Project/ component) Tentative Cost

(Rs. In Crore)

Implementing Deptt.

1 Installation of solar panels including net metering 12.95 (Rs. 5,82,97,500/- SSCL share)

HIMURJA

Eco-Tourism development & parks Component: Face lifting of existing parks at: 2 (i) Rani-Jhansi Park

(Ward no. 15) 0.50

MC Shimla 3 (v) Gol Pahadi (Ward no. 3) 1.10

Road Widening/improvement of junctions/ Grade separators, basic work of bus stop, footpath, etc. Component (A)(i) Improvement of existing pedestrian path on Circular road:

4. Reconstruction and improvement of pedestrian path on KSC road

0.92

HPPWD 5. Reconstruction and improvement of pedestrian path on

Talland to Khalini road 0.50

6. Reconstruction of pedestrian path between Kali Dhank location

1.21

7. Construction of footpath at Navbhar, St. Bedes College 0.47 Component (B)

(i) Widening of circular road at feasible locations 8. C/I on circular road in Shimla town- 75 Rmt 1.14

HPPWD

9. C/I on circular road in Shimla town- 101 Rmt 1.01 10. C/I on Mehli Kasumpti Road IAS Colony 0.12 11. C/I on circular road in Shimla town (Below Forest Office) 0.69 12. Component (C)

Improvement of junctions at Dhalli Chowk 1.34 HPPWD

13. Boileauganj Chowk (Phase II) 1.39 14. Construction of covered footpath along Sanjauli-IGMC

road 24.83 HPPWD

15. Installation of E-toilets at important public places (15 nos.)

2.22 MC Shimla

16. Provision of vending area (i) Khalini and (ii) Vikas Nagar

0.52 RTDC

17. Development of new parkings Component (A)- Development of a parking complex near the new block of IGMC on circular road including road from IGMC to Circular road (capacity about 700 vehicles)

32.02 HPPWD

18 Implementation of city branding- Component (i): Development of Book Café at Chaura Maidan

0.78

19 Eco Tourism Development: (iii) natural spring opposite Hotel Marina

0.96 SJPNL

20 Implementation of City branding-

Component (iii):Refurbication of fountain/ site development near Takka Bench, smart display board highlighting historic importance of Ridge.

21 Development of storage tanks, channelization of nallahs and fire fighting system - Component (A)Channelization of nallah Channelization of nallah at: (i) Combermere (ii) Krishna Nagar.

10.00 SJPNL

22 Development of Pvt. Sector Subzi Mandi (pocket-1- 65 shops and 13 stores)

2.07+0.57

23 C/I on circular road in Shim la town (97 Rmt) 1.10 HPPWD 24 Reconstruction and improvement of pedestrian path and W.

metal beam crash barrier railings on MRR via Chotta Shimla

1.98 HPPWD

25 Widening of junction point at MLA Crossing and Boileauganj Chowk on MLA crossing to Tawi more.

0.93 HPPWD

26 Boileauganj Chowk (Phase I) 0.37 HPPWD 27 Construction of footpath, covered drain, paver block and

safety railings on KSC/ MRR road 2.12 HPPWD

Construction of lifts/ Escalators- 28 Installation of escalators at Jakhu temple 7.94 29 Installation of lift at MC Old Bakery Building 2.17 RTDC 30 Installation of lift at Metropole parking 1.07 RTDC 31 Component (i): Development of Book Café at Chotta

Shimla 0.33 RTDC

Development of Pvt. Sector: Unsafe structures of M.C

Shimla to be retrofitted/dismantled and provided with prefab structures:

32 Subzi Mandi (Pocket-2 28 shops and 3 stores) 0.69 HIMUDA 33 Lower Bazar (39 No. shops and 15 No. basements) 1.87 HIMUDA Procurement of garbage compactors: Procurement of

34 garbage vehicles, 4 garbage compactors and 2 road sweeping-cum-snow cutter machines

34 Road sweeping machine- 3.3 cum capacity. 2.55 HPPWD (Mech.wing) 35 Road sweeping machine- 6.2 cum capacity. 3.35

TOTAL 123.78

Projects on which initial work taken up:- Sr.No.

(Name of Project/ component)

Tent. Cost

(Rs. In Cr.)

Implementing Deptt.

Remarks

Road Widening/improvement of junctions/ Grade separators, basic work of bus stop, footpath, etc Component (C) Improvement of junctions at

1 Chotta Shimla Chowk 2.23 HPPWD Repair of vacated garage taken up to shift existing shopkeepers therein.

2 Eco-Tourism development & parks Component: Face lifting of existing parks Below Ashiana Regency

0.23 MC Shimla Initial site development in progress.

3 Commercial space development Component (A) Unsafe/dilapidated building of M.C Shimla at following locations to be demolished and reconstructed: (ii) Ghora Hospital, Cart road, Shimla (Dismantling to be undertaken by MC Shimla)

2.00 HIMUDA Dismantling of dilapidated building commenced by MC Shimla.

4 Component (B) multi-storey parking complex at Vikas Nagar

13.27 MC Shimla Site Development Undertaken.

- Widening of circular road near Subzi Mandi

0.50 HPPWD Unauthorized structure demolished. Widening component to be taken up.

- Commercial space development Component (A) Unsafe/dilapidated building of M.C Shimla near Tibetan School, Chotta Shimla to be demolished and reconstructed.

1.00 RTDC Dismantling of dilapidated building taken up.

- Construction of additional parking near Jiwanoo Colony, Panthaghati

2.00 MCS Construction Work underway in AMRUT. To be clubbed with Smart City Project.

5 Installation of lifts & escalators from Lakkar

11.37 RTDC Financial bids opened. In the final stage of award.

(A) Projects for which tenders floated

bazaar bus stand to Ridge including Foot over Bridge on circular road

TOTAL 29.1

Sr. No.

Name of Project/ component Tentative Cost to be incurred

by SSCL (Rs. In Crore)

Implementing Deptt.

Development of Pvt. Sector: Unsafe structures of M.C Shimla to be retrofitted/dismantled and provided with prefab structures:

1 Ram Bazar (40 shops) 2.02 HIMUDA 2 4 Residential Blocks (36 flats) at Ghora Line

Krishna Nagar

5.18

Procurement of garbage compactors: Procurement of34 garbage vehicles, 4 garbage compactors and 2 road sweeping-cum-snow cutter machines

3 Covered Garbage vehicles (5 cum capacity) 5.45 HPPWD (Mech. Wing) 4 Refuse Garbage compactors (14 cum capacity) 1.61

Construction of lifts/ Escalators- 5 Police Chowki Lakkar Bazar to Auckland area,

etc. 5.33

Commercial space development 6 Component (B)

Unsafe/dilapidated building of M.C Shimla near Patwar Khana, Kasumpti to be demolished and reconstructed

1.68 RTDC

7 Bike sharing scheme on 3 stretches (i) Chaura Maidan to CTO, (ii) Sanjauli Chowk to Lakkar Bazar (Police Chowki), and (iii) Chotta Shimla near Secretariat to Ridge

0.50 HPIDB

Development of Smart Bus Stops with all facilities 8 Smart bus stop at Talland- valley side (Type-B) 1.61 HPPWD 9 Smart bus stop at different locations- (Nigam

Vihar, Talland-Hill side, Bemloie, near 103 tunnel, near CMP check post)

2.34 HPPWD

10 Construction of composting plant near IGMC, Circular road

1.50 MC Shimla

11 Initiatives for Govt. High School Krishna Nagar

4.50 HPSEDC

Road Widening/improvement of junctions/ Grade separators, basic work of bus stop, footpath, etc Component (A)

Pedestrian Path including (i) Improvement of existing pedestrian path on Circular road

12 C/O addl. Pedestrian path, P/F W. beam metal crash barriers railings on KSC/MRR via Chotta Shimla

2.07

HPPWD

13 Reconstruction of W. beam railings 1.32 14 Improvement of existing pedestrian path on

Circular road - Addl. Locations On various locations on Sanjauli to Lakkar Bazar road, viz., near RKMV, Snowview (Keleston) etc.

3.83

Component (A): Pedestrian Path :(ii) Providing drain etc. from Dhalli tunnel to Mashobra junction.

15 Providing drain etc. from Dhalli tunnel to Mashobra junction- RD 153/180 to 153/765

2.04

HPPWD- (NH Circle)

16 Providing drain etc. from Dhalli tunnel to Mashobra junction-153/180 to 155/00

2.13

17 Providing drain etc. from Dhalli tunnel to Mashobra junction- 153/765 to 154/500

2.25

18 Providing drain etc. from Dhalli tunnel to Mashobra junction- 154/500 to 154/760

1.17

19 Providing drain etc. from Dhalli tunnel to Mashobra junction-154/760 to 155/045

1.58

20 Providing drain etc. from Dhalli tunnel to Mashobra junction- 153/725 to 153/785 and 154/310 to 154/361

2.09

Component (B) (i) Widening of circular road at feasible locations

21 C/I on circular road in Shim la town (110 Rmt) 0.97

HPPWD

22 C/I on circular road in Shim la town (90 Rmt) 1.74 23 C/I on circular road in Shimla town (near Ranjan

Hotel) 1.32

24 C/I on circular road in Shimla town (near Cecil garrage)

0.94

25 C/I on circular road in Shimla town (near Timber House)

2.18

26 M/T in various locations 1.35 27 Component (B)

(ii) Improvement/widening in the area of Old Barrier near existing shops (Phase I)

2.88 HPPWD - (NH Circle)

28 Improvement of Y-junction at Dhalli Tunnel- C/O retaining wall & U shape covered drain.

2.21

HPPWD- (NH Circle) 29 Improvement of Y-junction at Dhalli Tunnel- M/T

on extended portion on Hill/ Valley side 0.63

Development of new parkings 30 Component (C) Development of a parking

complex at Totu (capacity about 150 vehicles)

4.00 HPPWD

31 Component (D) Development of smart parking's in wards as per availability of land

6.52 MC Shimla

Construction of smart foot-over bridges:

SSCL PROJECTS/ COMPONENTS WHOSE DPRs HAVE BEEN PREPARED:

32 Vikas Nagar 2.10 RTDC 33 near DDU Hosp. 0.65 RTDC 34 near Lift 4.50 RTDC Implementation of City branding 35 Component (i): Development of Book Café at

Sanjauli. 0.40 RTDC

TOTAL 82.59

Sr. No.

Name of Project/ component Tentative Cost

(Rs. In Crore)

Implemen-ting Deptt.

Remarks

1 Ducting of electrical cables/pipelines from CTO Complex upto Shimla Club (1.5 km length)- Only for SJPNL Component.

5.00 SJPNL

2 Master System Integrator for setting up Central Command & Control Centre

60.00 DIT

3 Installation of stack parking: near SDA Complex, Kasumpti for augmenting the capacity of existing park spaces (capacity about 150 vehicles)

3.00 RTDC --

4 Booth for traffic police & LED traffic lights, high mast lights and signages at different locations (i) Installation of High Mast Lights (ii) Installation of solar/ street lights at prominent locations

3.00 MC/ HPSEBL

--

Eco-Tourism development & parks: 5 Component: Face lifting of existing parks near Lift 0.21 MC

Shimla --

Commercial space development Component: Unsafe/dilapidated building of M.C

Shimla at following locations to be demolished and reconstructed

6 (ii) Near Tibetan School, Chotta Shimla 1.00 RTDC -- 7 Component: Place making Space to be developed on

Ridge near Padam Dev Complex as per decision of the Hon’ble High Court including stabilization of whole rock mass/ strata Phase 1:From Gaiety Theatre to Padam Dev Complex.

18.00 Possibility to converge

with Disaster Mitigation

measures to be explored

Development of storage tanks, channelization of nallahs and fire fighting system:

8 Component: Repair of drains , surface drainage including storm water, grey water, sewerage etc. and footpaths etc in ward No. 14 &15.

10.00 SJPNL --

9 Commercial Space Development: Component: Place making Space to be developed on Ridge near Padam Dev Complex as per decision of the Hon’ble High Court including stabilization of whole rock mass/ strata. Phase 2: FromPadam Dev Complex to DAV School.

22.00 Possibility to converge

with Disaster Mitigation

measures to be explored.

PROJECTS/ COMPONENTS WHOSE DPRs ARE UNDER PREPARATION :

10 Procurement of two Modern Ambulances & one Hearse Van for emergency services in DDU Hospital

0.80 Health Deptt.

--

Road Widening/improvement of junctions/Grade separators, basic work of bus stop, footpath, etc

11 Component: Smart pedestrian paths in different wards

10.00 MC Shimla

First mile/ last mile

connectivity 12 Construction of lifts/ Escalators:

Provision of Elevator near Bantony Castle from Cart Road to Mall Road

4.78 --

TOTAL 137.79

Commercial space development Component: Unsafe/dilapidated building of M.C

Shimla at following locations to be demolished and reconstructed

- (i) Near Ghora Hospital (Additional cost) 1.00 HIMUDA Additional cost 1 Land Acquisition as per requirement -- -- As per

requirement Construction of foot over bridges 2 Component: Elevated smart walkway from Chotta

Shimla to Ayurvedic Hospital on Chotta Shimla - Kasumpti road

8.00 RTDC --

3 Development of Pvt. Sector: Balance unsafe structures of M.C Shimla in Gunj Bazar/ Lower Bazar,SubziMandi, Lakkar Bazar etc. (about 467 shops) and the dilapidated M.C buildings in Krishna Nagar etc. (26 blocks) to be retrofitted/dismantled and provided with prefab structures at: Ganj Bazar Remaining shops- 215 No. Residential Blocks in Krishna Nagar Residential Blocks (Suji, near HPMC, Lalpani) Difference due to A/A & E/S already accorded

20.00 HIMUDA

--

4 Provision of vending area: Provision of balance prefab structures at identified locations for accommodating the existing vendors at any of the following locations: i) Near Dhalli Bye-pass ii) Near Old Bus stand circular road iii) In existing Tibetan market iv) At IGMC near Manchanda Clinic v) Near DDU Hospital towards Ram Bazar area vi) At any feasible location in Ram Bazar, Lakkar

Bazar, near KNH and near Lift. vii) Additional vending area in Old Bakery Buildibng

4.00 RTDC --

Road Widening/improvement of junctions/Grade separators, basic work of bus stop, footpath, etc:

--

5 Component : Improvement of junctions/fly-over at balance locations: Proposal of widening/ fly over SanjauliChowk(Rs. 2.00 Cr.), TawiChowk (Rs. 1.00 Cr.), junction near High Court (Rs. 1.00 Cr.) and junction near Auckland tunnel (Rs. 1.00 Cr.)

5.00 HPPWD --

Road Widening/improvement of junctions/Grade separators, basic work of bus stop, footpath, etc

6 Component: Improvement of junctions/fly-over at balance locations: Widening/ fly over fromWinterfieldupto Victory Tunnel/ Vidhan Sabha junction/ Railway Station, BCS junction.

15.00 HPPWD --

Road Widening/improvement of junctions/ Grade separators, basic work of bus stop, footpath, etc

7 Component: Improvement/ widening in the area of Old Barrier near existing shops.

10.00 HPPWD (NH)

--

8 Facade improvement on Mall road 4.00 MC Shimla

--

9 Construction of tunnel parallel to Dhalli tunnel 48.00 HPRIDC --

10 Development of ice-skating rink 7.00 Tourism Dept.

--

Construction of foot over bridges 11 Component: Construction of smart foot-over bridges:

Near Tara Hall and Auckland School 2.00 RTDC --

12 Development of safe shelters across the city - Disaster Mgmt.

--

Development of new parkings 13 Component: Development of smart parking near

Old Bus Stand (capacity about 450 vehicles)

3.48 HPPWD --

14 Development of Pvt. Sector: Balance unsafe structures of M.C Shimla in Gunj Bazar/ Lower Bazar,SubziMandi, Lakkar Bazar etc. (about 467 shops) and the dilapidated M.C buildings in Krishna Nagar etc. (26 blocks) to be retrofitted/dismantled and provided with prefab structures.

20.00 HIMUDA

Balance from Phase 1

15 Component: Development of museum/ exhibition centre at Mall Road/Ridge

1.00 MC Shimla --

TOTAL 148.48

NEW PROJECTS:

Sr. No.

Name of Project/ component Tentative Cost to be

incurred by SSCL

(Rs. In Crore)

Implemen-ting Deptt.

Remarks

1 Eco-Tourism development & parks: Component: Development of parks and open spaces in

different wards.

2.00 MC Shimla PAN CITY

Commercial space development 2 Component: Refurbishment of State Library at Ridge

and Reading room at Ridge. 1.00 HPPWD --

3 Component: Refurbishment of Sadar Police Station at SubziMandi

1.00 HIMUDA

--

4 Component: Refurbishment of Padam Dev Complex 1.00 HPPWD -- 5 Component: Refurbishment of Lakkar Bazar Bus Stand 1.00 RTDC -- 6 Component: Refurbishment of Market at Lakkar Bazar 1.00 RTDC -- 7 Component: Refurbishment of old buildings in Rani

Jhansi Park 0.50 MCS --

8 Component: Construction of Book Café in Sector III, New Shimla

0.50 RTDC --

9 Installation of E-toilets at important public places. Component: Refurbishment of toilets at Ridge and near Rotary Club.

1.04 SJPNL A/A & E/S accorded

Development of storage tanks, channelization of nallahs and fire fighting system:

10 Component: Construction of RCC water storage tank at a feasible locations, viz., near Hotel Peter Hoff , Dhalli etc.

15.00 SJPNL --

11 Component: Channelization of nallah near Cancer Sarai 0.25 HPPWD -- Construction of foot over bridges 12 Component : Construction of Foot Over Bridge at

NavBaharChowk and Chalaunthi Chowk. 2.00 RTDC --

Development of new parkings 13 Component: Off street parking near SankatMochan. 5.00 HPPWD A/A&E/S

accorded 14 Component: Development of a parking –cum-

commercial complex at MC land near Govt. Sr. Secondary School, Chotta Shimla

3.00 RTDC --

15 Component: Construction of parking-cum-shopping complex on MC land at Mehli IAS Colony.

2.00 HPPWD --

16 Development of Smart Bus Stops with all facilities At various locations (viz. BCS, etc.)

1.00 HPPWD --

17 Development of Exhibition-cum-Convention Centre near Old ISBT- Component: Development of Smart City Office at MC Parking opposite Cecil Hotel, ChauraMaidan/ any other location.

0.75 RTDC --

Road Widening/improvement of junctions/Grade separators, basic work of bus stop, footpath, etc

18 Component: Improvement of junctions/fly-over at different locations: Shops at Dhalli Chowk to be dismantled and reconstructed in prefab structure. Also, the bus stop at this location may be integrated as per site conditions.

2.00 RTDC --

19 Component: Pedestrian Path: Access from existing pedestrian path upto campus/ ground of Auckland Boys School from circular road behind Auckland tunnel

0.15 RTDC --

20 Component: Relocation of Primary and Secondary School at Boileauganj to Padao/ any other convenient location.

6.00 HPPWD --

21 Component: Construction of alternate road from Rajhana to Shoghi bye pass near Sewerage Treatment plant.

3.00 HPPWD --

22 Component: Widening of road ahead of Kasumpti Bazar. 0.50 HPPWD -- 23 Component: Improvement of Shimla MandiRoad

portion Dhalli to Mashobra 4.08 HPPWD A/A & E/S

accorded 24 Component: Widening of Tutikandi junction near Old

barrier- Construction of prefab shops for shifting of existing shopkeepers.

1.00 RTDC --

25 Component: Widening of circular road near Subzi Mandi

0.50 HPPWD --

26 Component: Construction of link road from Talland to Bye Pass road

1.00 HPPWD --

27 Component: Widening of road in Dhalli Bazaar including shifting & re-construction of shops.

15.00

HPPWD (NH

Circle)

Possibility of implementing the project on PPP mode to be explored.

28 Component: Link Road from Holiday Home to Bye Pass Road

15.00

HPPWD

Feasibility to be worked

out 29 Component: Widening of road from Totu Bazar to

Power House. 2.00 HPPWD --

30 Component: Widening of road near 103 Tunnel 1.00 HPPWD -- Development of new parkings 31 Component: Construction of Parking complex opposite

IGMC Auditorium- about 400 vehicles 20.00 HPPWD Possibility of

implementing the project on PPP mode to be explored.

32 Component: Construction of parking near Bye Pass road at Fagli(CPWD land involved)

5.00 HPPWD

33 Component: Construction of additional parking near Jiwanoo Colony, Panthaghati

2.00 MCS --

34 Component: Construction of parking complex near Boileauganj.

5.00 HPPWD --

35 Development of new parking's Component: Development of parking lots near park beside Pollution Control Building, beside Block No. 28,Block No. 7,Type D- Plot No.15, Near Block No. 21

5.00 HIMUDA

--

and beside Block No. 20 in Sector 5.Sector 6- beside block No. 12 A, beside block No. 37 and beside block No. 1A

Road Widening/improvement of junctions/Grade separators, basic work of bus stop, footpath, etc

36 Component: Widening of MC roads. 5.00 MC Shimla

--

37 Component: Widening of road at critical sections leading from circular road at Navbahar Chowk upto Chelsea School.

2.00 HPPWD --

38 Component: Construction of alternate road from Sector 3 Govt. Primary School to Tutikandi Zoo.

24.00 HPPWD --

39 Component: Construction of alternate road from Sector 4, New Shimla to Rajhana to Baragaon.

3.40 HPPWD --

40 Component: Construction of pedestrian path from Ram Chandra Chowk to Machi Waali Kothi.

1.00 HPPWD --

41 Component: Strengthening and grade improvement of cart road with smart features, viz., centerline with cat-eyes, etc.

12.00 HPPWD --

42 Component: Link road from Vikas Nagar to Phase III New Shimla and Sector 5, New Shimla.

3.00 HIMUDA

--

43 Component: Construction of alternate road from Kangnadhar Phase III to DAV School.

3.00 HIMUDA

--

Development of storage tanks, channelization of nallahs and fire fighting system:

44 Component: Repair of drains, etc. in different wards. 10.00 MC Shimla

--

45 Component: Improvement of sewerage system in Dhalli and Mashobra

22.00 SJPNL --

46 Component: System Improvement, automation of pumping systems at LWSS Giri&Gumma

75.00 SJPNL --

Development of new parkings 47 Component: Development of parking –cum-commercial

complex near Bangala Colony, Totu on MC land 5.00 HPPWD --

48 Component:Construction of parking complex near Ram Nagar Bridge.

5.00 HPPWD --

49 Component: Development of smart parkings in wards as per availability of land.

5.00 MC Shimla

--

Development of Exhibition-cum-Convention Centre near Old ISBT-

50 Component: Development of MC Office/Commercial complex near SubziMandi subject to approval from Hon’ble NGT/ Supervisory Committee/ any other location

7.00 HPPWD --

51 Commercial Space Development: Component: Construction of shopping complex-cum-open space development on MC land near SD school, Engine Ghar, Sanjauli.

4.00 --

52 SCADA- Software installation 5.00 -- 53 SCADA- System improvement 50.00 SJPNL -- 54 Refurbishment of Evening College/ Library 2.00 HPPWD -- 55 Procurement of garbage compactors etc.

Component: Procurement of 2 No. electric mini buses for MC Shimla.

1.5

HPPWD (Mech. Wing)

--

DSCL Projects Execution Details

Sr. No.

Project Expenses Project Cost (₹

Cr.) Expenditure

(₹ Cr.)

Balance (₹ Cr)

Status

A PROJECTS /TENDERS EXECUTED BY DSCL

1 GIS WEB PORTAL 1.29

1.29

- Completed

2 E- NAGERPALIKA 1.17

1.10

0.07 Completed

3 DSCL WEB SITE 0.36

0.36

- In progress

4 PROPERTY TAX MAPPING 0.24

0.06

0.18 In progress

5 SMART CLASSROOMS 3.55

1.49

2.06 Completed

6 UNDERGROUND DUSTBINS 6.07

5.16

0.91 Completed

7 SOLAR POWER PLANT (Phase 1 Completed)

2.09

1.23

0.86 In progress

8 BUS SHELTERS 9.00

-

9.00 In progress

9 IMPROVING EXISTING WALKWAYS & STAIRS

23.64

-

23.64 In progress

10 PARKING AT DALAI LAMA TEMPLE 4.86

-

4.86 In progress

11 UPGRADATION OF MOUNTAINEERING INSTITUTE

3.84

-

3.84 In progress

12 SMART ROAD FROM BUS STAND TO EDUCATION BOARD

18.03

-

18.03

Award stage

Total 74.15

10.69

63.45

56 Initiatives for Smart School- Component: Development of smart school at Lalpani.

3.00

HPSEDC --

57 Implementation of City branding Component: Murals, signages etc. including publishing of coffee table booklet.

1.00 MC Shimla

--

58 Booth for traffic police & LED traffic lights, high mast lights and signages at different locations Component: Signanges at different locations

1.00 MC Shimla

--

TOTAL 376.17

PROJECTS ENTRUSTED TO LINE DEPARTMENTS

B DHARAMSHALA MUNICIPAL CORPORATION

1 INCLUSIVE STREETS - DMC 15.89

15.65

0.24 In progress

2 MOKSHDHAM - DMC 0.37

0.36

0.01 In progress

3 PARKS & PLAYGROUNDS 0.26

0.26

- In progress

4 ELECTRIC CREMATORIUM 10.00

10.00

- DPR Stage

5 SANITARY LANDFILL AT DUMPING SITE

3.00

3.00

- DPR Stage

6 PARKING (Near Bus Stand Dharamshala) 5.00

5.00

- DPR Stage

7 PUBLIC E-TOILETS 5.00

5.00

- DPR Stage

8 IN-SITU HOUSING (IHSDP Scheme) 5.00

5.00

- In progress

44.51

44.27

0.24

C HPPWD

1 INCLUSIVE STREETS - PWD 6.82

6.20

0.62 In progress

Total 6.82

6.20

0.62

D HIMUDA

1 INCLUSIVE STREETS 7.55

7.38

0.17 Completed

2 OFFICE BUILDING 24.44

22.50

1.94 In progress

Total 31.99

29.88

2.11

E JAL SHAKTI VIBHAG (I&PH)

1 I&PH - ROOT ZONE TREATMENT(4 Location)

3.51

3.51

- Completed

2 I&PH - POTABLE TAPPED WATER SUPPLY

7.32

6.46

0.86 In progress

3 I&PH - SEWERAGE TREATMENT 7.19

6.80

0.39 In progress

4 I&PH - FAECAL MANAGEMENT SYSTEM 10.60

10.00

0.60 DPR Stage

5 ROOTZONE TREATMENT - NADDI 2.78

2.00

0.78 Tendering

6 UTILITY SHIFTING - SMART ROAD 0.98

0.78

0.20 Tendering

Total 32.37

29.55

2.82

F FOREST DEPARTMENT

1 FOREST - ECO TOURISM 1.38

0.90

0.48 Tendering

Total 1.38

0.90

0.48

G HPSEBL

1 RELOCATION OF BARE CONDUCTOR WITH AB CABLE

1.72

1.37

0.34 Tendering

2 SMART METERING 13.25

13.00

0.25

Award stage

3 UNDERGROUND CABLING - SMART ROAD

13.50

13.00

0.50 Tendering

4 UTILITY SHIFTING - SMART ROAD 0.85

0.68

0.17 Tendering

Total 29.32

28.05

1.26

H BSNL

1 UTILITY SHIFTING - SMART ROAD 1.68

1.35

0.34 Tendering

Total 1.68

1.35

0.34

I PROJECTS UNDER TENDRING STAGE

1 E-BUSES 20.00

-

20.00 DPR Stage

2 LED STREET LIGHTS 25.00

-

25.00 DPR Stage

3 INCLUSIVE STREETS BALANCE 10.00

-

10.00 DPR Stage

4 PARKS PHASE 1 3.77

-

3.77 Tendering

5 PLAYGROUNDS IN BOY SCHOOL 2.00

-

2.00 DPR Stage

6 5T WASTE TO ENERGY PLANT 10.00

-

10.00 DPR Stage

Total 70.77

-

70.77

Summary of Dharamshala Smart City Works

S.No. Source of Funds Amount (₹ Cr.) Expenditure

(₹ Cr.)

Balance (₹ Cr) Remarks

1 Project Received from Govt. of India 196.00

2 Project Grant Received from Govt. of HP 26.89

3 Interest + Tender Fees 53.06

Total Funds Received Till 17 Sept 2020 275.95

Utilization of Funds

4 PROJECTS /TENDERS EXECUTED BY DSCL

74.15

10.69

63.45 A

PROJECTS ENTRUSTED TO LINE DEPARTMENTS

5 DHARAMSHALA MUNICIPAL CORPORATION

44.51

44.27

0.24 B

6 HPPWD 6.82

6.20

0.62 C

7 HIMUDA 31.99

29.88

2.11 D

8 JAL SHAKTI VIBHAG (I&PH) 32.37

29.55

2.82 E

9 FOREST DEPARTMENT 1.38

0.90

0.48 F

9 HPSEBL 29.32

28.05

1.26 G

10 BSNL 1.68

1.35

0.34 H

Line Department Total 148.08

140.20

7.88

11 PROJECTS UNDER TENDRING STAGE 70.77

-

70.77 I

Total cost for Execution of projects 292.99

150.89

142.10

Balance after Execution of projects -17.04

FUNDS REQUIRED FOR PROJECTS APPROVED AND UNDER PLANNING STAGE

1 INTEGRATED COMMAND & CONTROL CENTRE

98.00

-

98.00 DPR Stage

2 LEFT OUT ROADS IN PAN CITY 60.00

-

60.00 DPR Stage

3 TENTATIVE COST FOR PARKINGS From PPP to SCF

46.00

-

46.00 DPR Stage

Total 158.00

158.00


Recommended