+ All Categories
Home > Documents > SCTE Solar Story

SCTE Solar Story

Date post: 19-Jan-2017
Category:
Upload: scte
View: 219 times
Download: 0 times
Share this document with a friend
100
December 2009 - SCTE proposes solar solution in support of our Smart Energy Management Initiative – SEMI(Conceptual artwork from Alpha Technologies)
Transcript
Page 1: SCTE Solar Story

December 2009 - SCTE proposes solar solution in support of our Smart Energy Management Initiative – SEMI(Conceptual artwork from Alpha Technologies)

Page 2: SCTE Solar Story

December 2009 - Online mapping reference check to see how much unobstructed southern facing rooftop SCTE has on our building (space for a total of 18 kW)– SCTE receives bids for the project

Page 3: SCTE Solar Story

December 2009 – Output of sun chart for 140 Philips Rd, Exton PA 19341

Page 4: SCTE Solar Story

February 2010 - SCTE selects Alpha Energy as the solar project solution provider

Page 5: SCTE Solar Story

April 2010 - After submitting permit requests SCTE and Alpha needed to appear before the township board to get approval of proposed installation – safety and aesthetics were taken into consideration

Page 6: SCTE Solar Story

July 2010 - An interconnect application needed to be filed with the local electricity grid provider, giving SCTE and Alpha permission to connect the new solar system to their system

Page 7: SCTE Solar Story

March 2010 - Site inspection illustrating panel height (5’ 9”) for township approval

Page 8: SCTE Solar Story

May 2010 - Power purchase agreement (PPA) and contract negotiations completed between Alpha and SCTE to insure fair system options for both companies

Power Purchase Agreement

Page 9: SCTE Solar Story

Monthly Production Dollars

Page 10: SCTE Solar Story

11.28 kW Electricity Production

Page 11: SCTE Solar Story

May 2010 – Alpha drafts engineering documents and hardware is ordered

Page 12: SCTE Solar Story

June 2010 - SMA inverters, Sharp panels and Shletter aluminum mounting system

Page 13: SCTE Solar Story

July 2010 - Lift used to move materials onto the roof deck

Page 14: SCTE Solar Story

July 2010 - First load of materials unloaded onto the roof

Page 15: SCTE Solar Story

July 2010 - Cutting the “spaghetti matting” to shape

Page 16: SCTE Solar Story

July 2010 - Placing the pans precisely over the building’s support joists

Page 17: SCTE Solar Story

July 2010 - Lifting the pavers that will weigh the pans down

Page 18: SCTE Solar Story

July 2010 - Getting ready to finish up placing the pans

Page 19: SCTE Solar Story

July 2010 - Placing the support frames into position over the center of the pans

Page 20: SCTE Solar Story

July 2010 - Placing the support frames into position over the center of the pans

Page 21: SCTE Solar Story

July 2010 - Placing the support frames into position over the center of the pans

Page 22: SCTE Solar Story

July 2010 - Assembling the rails and frame support

Page 23: SCTE Solar Story

July 2010 - Assembling the rails and frame support

Page 24: SCTE Solar Story

July 2010 - Checking the second section rack placement and preparing that build

Page 25: SCTE Solar Story

July 2010 - Making progress on the racking assembly

Page 26: SCTE Solar Story

July 2010 - First section of racking assembled

Page 27: SCTE Solar Story

July 2010 - Making progress on the rack installation

Page 28: SCTE Solar Story

July 2010 - Racking assembly completed

Page 29: SCTE Solar Story

July 2010 - Racking assembly completed

Page 30: SCTE Solar Story

July 2010 - Racking assembly completed

Page 31: SCTE Solar Story

July 2010 - Average July full sun roof top temperature (164 degrees Fahrenheit)

Page 32: SCTE Solar Story

July 2010 - Beginning work of hanging the panels

Page 33: SCTE Solar Story

July 2010 - Hanging the first panel – ensure that the placement is square

Page 34: SCTE Solar Story

July 2010 - Checking the square reference point

Page 35: SCTE Solar Story

July 2010 - Tying the square reference string into place

Page 36: SCTE Solar Story

July 2010 - Squaring off the second row of panels

Page 37: SCTE Solar Story

July 2010 - Beginning the install of second row of panels

Page 38: SCTE Solar Story

July 2010 - Placing the upper row of panels

Page 39: SCTE Solar Story

July 2010 - Placing the upper row of panels

Page 40: SCTE Solar Story

July 2010 - Hanging the upper row of panels

Page 41: SCTE Solar Story

July 2010 - Progress hanging the second row of panels

Page 42: SCTE Solar Story

July 2010 - Temperature of the back of panels (full sun - 136 degrees Fahrenheit)

Page 43: SCTE Solar Story

July 2010 - Installing the conduit mounting brackets to the frame

Page 44: SCTE Solar Story

July 2010 - Installing the conduit mounting brackets to the frame

Page 45: SCTE Solar Story

July 2010 - Getting the combiner box ready on the rooftop

Page 46: SCTE Solar Story

July 2010 - Combiner box ready for conduit and cabling

Page 47: SCTE Solar Story

July 2010 - Preparing to mount the conduit

Page 48: SCTE Solar Story

July 2010 - All panels racked and ready for wiring procedures

Page 49: SCTE Solar Story

July 2010 - Look down the back of the array after panel wire clean up is completed

Page 50: SCTE Solar Story

July 2010 - Cleaning up positive and negative panel connection cables with wire ties

Page 51: SCTE Solar Story

July 2010 - Cleaning up the positive and negative panel cables with panel clips

Page 52: SCTE Solar Story

July 2010 - First row of wind shield deflector braces installed

Page 53: SCTE Solar Story

July 2010 - First row of wind shield deflector braces installed

Page 54: SCTE Solar Story

July 2010 - Grounding clip installed on every panel and rack piece

Page 55: SCTE Solar Story

July 2010 - Fishing the DC and ground wire through the conduit under the array

Page 56: SCTE Solar Story

July 2010 - Installing the first disconnect box

Page 57: SCTE Solar Story

July 2010 - Working on the disconnect boxes

Page 58: SCTE Solar Story

July 2010 - Lightning arrestor attached to the roof top disconnect boxes

Page 59: SCTE Solar Story

July 2010 - Conduit taking the DC power from the disconnect boxes to the combiner box

Page 60: SCTE Solar Story

July 2010 - Combiner box taking the power down the side of the building

Page 61: SCTE Solar Story

July 2010 - Disconnect box on the roof

Page 62: SCTE Solar Story

July 2010 - Disconnect boxes on the roof

Page 63: SCTE Solar Story

July 2010 - Two disconnect switches on the roof

Page 64: SCTE Solar Story

July 2010 - Sensor control box mounted adjacent to the array

Page 65: SCTE Solar Story

July 2010 - Anemometer and ambient air temperature devices

Page 66: SCTE Solar Story

July 2010 - Back of panel temperature sensor

Page 67: SCTE Solar Story

July 2010 - Look down the back of the array at the wind shields

Page 68: SCTE Solar Story

July 2010 - Completed arrays

Page 69: SCTE Solar Story

July 2010 - Completed arrays

Page 70: SCTE Solar Story

July 2010 - Completed arrays

Page 71: SCTE Solar Story

July 2010 - Completed arrays

Page 72: SCTE Solar Story

July 2010 - Completed arrays

Page 73: SCTE Solar Story

July 2010 - Completed arrays

Page 74: SCTE Solar Story

July 2010 - View from ground level at the side of SCTE’s building

Page 75: SCTE Solar Story

July 2010 - View of the panels from ground level behind SCTE’s building

Page 76: SCTE Solar Story

July 2010 - Drilling a hole in the cement block to feed the cable into the building

Page 77: SCTE Solar Story

July 2010 - Examining the internal workings of the inverter

Page 78: SCTE Solar Story

July 2010 - Getting ready to mount the new meter

Page 79: SCTE Solar Story

July 2010 – Mounting the new inverters and system boxes

Page 80: SCTE Solar Story

July 2010 - Mounting the inverters and new breaker boxes

Page 81: SCTE Solar Story

July 2010 - Getting ready to pull cable

Page 82: SCTE Solar Story

July 2010 - Preparing to pull the rooftop wires into the building

Page 83: SCTE Solar Story

July 2010 - Preparing to pull the rooftop wires into the building

Page 84: SCTE Solar Story

July 2010 - Preparing to pull the rooftop wires into the building

Page 85: SCTE Solar Story

July 2010 - Completing the AC/DC wiring requirements

Page 86: SCTE Solar Story

July 2010 - Completing the AC/DC wiring requirements

Page 87: SCTE Solar Story

July 2010 - Preparing for the DC to AC wiring project

Page 88: SCTE Solar Story

July 2010 - Installation of new system meter and circuit breakers

Page 89: SCTE Solar Story

July 2010 - Brining the DC cable feed into the combiner box inside the building

Page 90: SCTE Solar Story

July 2010 - Inverter statistics

Page 91: SCTE Solar Story

July 2010 - Inverter output LCD board

Page 92: SCTE Solar Story

July 2010 - Inner workings of the inverter shut off switch

Page 93: SCTE Solar Story

August 2010 - Overview of the inner workings of the inverter

Page 94: SCTE Solar Story

August 2010 - Initial look of the inverter receiving DC power from the panels

Page 95: SCTE Solar Story

August 2010 - Initial reading of output coming off the panels

Page 96: SCTE Solar Story

August 2010 - Alpha and SCTE team assembling on the roof for the launch ceremonies

Page 97: SCTE Solar Story

August 2010 - Launch of the power purchase agreement and solar system

Page 98: SCTE Solar Story

August 2010 - Alpha and SCTE team on the roof for opening day

Page 99: SCTE Solar Story

Today - SCTE front lobby display

Page 100: SCTE Solar Story

System Specifications• 11.28 kW DC• 10 kW AC• Phase: 3phase • Voltage: 208 • Frequency: 60Hz• 48 Sharp 235 mono-crystalline modules• Schletter ballasted racking system• 2 SMA Sunnyboy 5000US inverters• Data Monitoring – website, data logging, weather

and auto-alerts


Recommended