Public Meeting Neil Schochenmaier, PE Road Design Engineering Supervisor June 7, 2018 P 0020(160)04 PCN 04FR 1 S.D. Highway 20 Structures Replacement P 0020(160)04 PCN 04FR
Transcript

Public Meeting

Neil Schochenmaier, PE

Road Design Engineering Supervisor

June 7, 2018

P 0020(160)04 PCN 04FR1

S.D. Highway 20

Structures Replacement

P 0020(160)04 PCN 04FR

West Two Bridge Locations

P 0020(160)04 PCN 04FR2

S.D. Highway 20 over the Little Missouri River and

Valley Creek

East Bridge Location

P 0020(160)04 PCN 04FR3

S.D. Highway 20 over Sioux Creek 8 mi. west of Reva

Why Are We

Here

P 0020(160)04 PCN 04FR4

Why

Are

WEHere

Purpose…

P 0020(160)04 PCN 04FR5

� Involve You, the public

Planning and Design

� Provide Project Overview

� Gather Input and Comments

Project

Background

P 0020(160)04 PCN 04FR6

We

st B

rid

ge

Tim

eli

ne

Bri

dg

es

ne

ar

Ca

mp

Cro

ok

Built

1951

Repaired

2006

Replace

2021

P 0020(160)04 PCN 04FR7

Ea

st B

rid

ge

Tim

eli

ne

Bri

dg

e W

est

of

Re

va

Built

1959

Repaired

2001

Replace

2021

P 0020(160)04 PCN 04FR8

9

0 Crashes

Bri

dg

es

ne

ar

Ca

mp

Cro

ok

*Statewide Crash Rate Rural

Minor Arterial = 1.81

Bri

dg

e W

est

of

Re

va

CRASH HISTORY 2013-2017

0 Crashes

P 0020(160)04 PCN 04FR

Bri

dg

es

ne

ar

Ca

mp

Cro

ok

10

Bri

dg

e W

est

of

Re

va

TRAFFIC

2017 ADT = 122

2042 Projected = 149

13.6% Trucks

2017 ADT = 173

2042 Projected = 212

26.6% Trucks

P 0020(160)04 PCN 04FR

What’s the

Plan

P 0020(160)04 PCN 04FR11

What’s

The

Plan

The Plan is...

P 0020(160)04 PCN 04FR12

� New Bridge over Little Missouri

River

New alignment

� New Bridge over Valley Creek

� New Box Culvert over Sioux

Creek

The Plan is...

P 0020(160)04 PCN 04FR13

� Purchase Right-of-WayNew alignment

� Utilities CoordinationMontana-Dakota Utilities Co.

Grand Electric Cooperative, Inc.

West River Cooperative Telephone Co.

Construct New Bridge

P 0020(160)04 PCN 04FR14

Right of Way

P 0020(160)04 PCN 04FR15

� Existing corridor – 150 feet

� Purchase Right-of-Way• Permanent 150 foot corridor for

new alignment

• Temporary Easements

See

Handout

See

Handout

Encroachments

P 0020(160)04 PCN 04FR16

See

Handout

See

Handout

� Social

� Economic

� Public Involvement

� Environment

National Environmental

Policy Act (1969)

P 0020(160)04 PCN 04FR17

See

Handout

� Section 4(f)

� Section 106

� Wetlands

� Threatened/Endangered

� Contaminated Material

Environment

P 0020(160)04 PCN 04FR18

See

Handout

P 0020(160)04 PCN 04FR19

Construction Traffic Control

SD Hwy 20 Remains Open

New Alignment

Diversion

Temporary Signals

What’s the

Plan

P 0020(160)04 PCN 04FR20

Remaining

Schedule

Project Schedule

P 0020(160)04 PCN 04FR21

20

18 June

Public Meeting

SummerPreliminary Design

FallLandowner Meetings

20

19

-20

20 Summer

2019ROW Acquisition

2020Final Design

20

21

Construction

Landowner

Meetings

P 0020(160)04 PCN 04FR22

� Individual

Meetings

� Impacts to

Property

See

Handout

See

Handout

Estimated Cost

P 0020(160)04 PCN 04FR23

$7.282 Million

P 0020(160)04 PCN 04FR24

Questions or Comments

June 21, 2018Neil SchochenmaierSouth Dakota Department of TransportationOffice of Road Design700 East Broadway AvenuePierre, South Dakota [email protected]